soo river hydro - clean energy bc · soo river hydro intake sediment management by stuart croft...

12
Soo River Hydro Intake Sediment Management by Stuart Croft Vice President G ENERATE 2014 Operators Workshop 15 October 2014 The Summit Power Group

Upload: others

Post on 06-Sep-2019

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Soo River Hydro - Clean Energy BC · Soo River Hydro Intake Sediment Management by Stuart Croft Vice President GENERATE 2014 –Operators Workshop 15 October 2014 The Summit Power

Soo River HydroIntake Sediment Management

by

Stuart CroftVice President

GENERATE 2014 – Operators Workshop

15 October 2014

The Summit Power Group

Page 2: Soo River Hydro - Clean Energy BC · Soo River Hydro Intake Sediment Management by Stuart Croft Vice President GENERATE 2014 –Operators Workshop 15 October 2014 The Summit Power

The Summit Power Group

Soo River Hydro

A brief background

Soo River Project:

14 MW run-of-river development 15 km

north of Whistler on the Soo River

Develops 103.5 m of head; design flow

of 15 m3/s

Consists of a inflatable diversion weir

and intake, 960 m long tunnel, 240 m

long 2 m DIA buried penstock, 2 x 7 MW

Francis units, powerhouse, and tailrace

Commissioned in May 1994

Page 3: Soo River Hydro - Clean Energy BC · Soo River Hydro Intake Sediment Management by Stuart Croft Vice President GENERATE 2014 –Operators Workshop 15 October 2014 The Summit Power

The Summit Power Group

Soo River Hydro

Diversion & Intake Design

Diversion situated on a low

gradient reach of a coastal

river draining 250 km2

glaciated basin

High flow period:

May thru October

Bedload predominantly silt

and sand, some pebbles

Floating and submerged

woody debris is common

Soo River Hydro – headworks, Autumn 2012

(photo: Brian Rode)

Setting …

Page 4: Soo River Hydro - Clean Energy BC · Soo River Hydro Intake Sediment Management by Stuart Croft Vice President GENERATE 2014 –Operators Workshop 15 October 2014 The Summit Power

The Summit Power Group

Soo River Hydro

Diversion & Intake Design

Page 5: Soo River Hydro - Clean Energy BC · Soo River Hydro Intake Sediment Management by Stuart Croft Vice President GENERATE 2014 –Operators Workshop 15 October 2014 The Summit Power

The Summit Power Group

Soo River Hydro

Diversion & Intake Design

Page 6: Soo River Hydro - Clean Energy BC · Soo River Hydro Intake Sediment Management by Stuart Croft Vice President GENERATE 2014 –Operators Workshop 15 October 2014 The Summit Power

The Summit Power Group

How to remove ~ 3,000 m3/yr

silt during fisheries window

with minimal disruption to

operations & environment?

Soo River Hydro

Sediment Removal Challenge

Annual build-up of silt

– sand clogging intake,

eroding runners

Fisheries Window

15 July to 15 September

High Flow (and High

Production) period

15 April to 15 October

Autumn storm events

Page 7: Soo River Hydro - Clean Energy BC · Soo River Hydro Intake Sediment Management by Stuart Croft Vice President GENERATE 2014 –Operators Workshop 15 October 2014 The Summit Power

The Summit Power Group

Soo River Hydro

Dewater & Excavate?

Process …

Complete plant shutdown

Lower headpond

Fish recovery

Excavate & haul away

Soo River Hydro – headpond excavation, 2006

Problems …

Loss of high value production

Difficult to dewater fully

Handling & disposal of

saturated materials

Operating equipment on

saturated sediments

Page 8: Soo River Hydro - Clean Energy BC · Soo River Hydro Intake Sediment Management by Stuart Croft Vice President GENERATE 2014 –Operators Workshop 15 October 2014 The Summit Power

The Summit Power Group

Soo River Hydro

Dredging?

Process …

Systematically suction silt and sand from the

intake channel

Discharge to impoundment pond,

Allow sediments to settle overnight

Water exfiltrates through base of pond, or

Clarified water is “decanted” by pumping from

surface of pond

“Over flow” is filtered, returned to River

Sand pile is allowed to dry, then loaded and

trucked from site

Considerations …

Turbidity from “excavation” is contained

Minimal site impact, footprint, equipment

requirements

Generation operations are not affectedExcerpt from

Cascade Environmental Resources Group Ltd., Environmental Monitoring Report for 2013 Soo River Intake Sediment Removal

Page 9: Soo River Hydro - Clean Energy BC · Soo River Hydro Intake Sediment Management by Stuart Croft Vice President GENERATE 2014 –Operators Workshop 15 October 2014 The Summit Power

The Summit Power Group

Soo River Hydro

Dredging Equipment & Layout

Construct settling pond / decant works

Assemble purpose-built floating dredge

platform, including

Toyo DL-20 - 20 H.P., 10” electric slurry pump

with agitator and cutter head

Pump hoisting winch

Electric capstan to move platform along cable

anchored to shore

6” discharge line

On-board electric panel

Dredge area systematically removing silt

and sand from the intake channel

Approximate dredging flow ~ 600 US gpm with

a maximum of 20% solids.

Page 10: Soo River Hydro - Clean Energy BC · Soo River Hydro Intake Sediment Management by Stuart Croft Vice President GENERATE 2014 –Operators Workshop 15 October 2014 The Summit Power

The Summit Power Group

Soo River Hydro

Dredging Equipment & Layout

4” slurry line from DT-20 discharging to settling basin

Floating “top draw” arrangement for pump to sand filter; note sediment wedge accumulated in opposite corner

Page 11: Soo River Hydro - Clean Energy BC · Soo River Hydro Intake Sediment Management by Stuart Croft Vice President GENERATE 2014 –Operators Workshop 15 October 2014 The Summit Power

The Summit Power Group

Soo River Hydro

Dredging Equipment & Layout

Sand filters treating “decant” water drawn from top of water column at settling basin (at left), with discharge back to Soo River mainstem (to right)

Dredge in action

Page 12: Soo River Hydro - Clean Energy BC · Soo River Hydro Intake Sediment Management by Stuart Croft Vice President GENERATE 2014 –Operators Workshop 15 October 2014 The Summit Power

The Summit Power Group

Soo River Hydro

Final Thoughts

Intake sediment removal has become part of

Soo River Hydro annual operations

Innovative, small-scale dredging has allowed

Soo River Hydro to address a serious

maintenance issue with relatively little impact

on vital late summer energy deliveries

Please contact

Stuart Croft – Summit Power

[email protected]

or

Nels Powell – SOR Site Operations Manager

[email protected]

FOR MORE INFO...