TRANSCRIPT
![Page 1: South Downtown I-405 Access Study · 2021. 2. 2. · South Downtown I-405 Access Study. Panelists. Shuming Yan Project manager, Bellevue Transportation Department Barrett Hanson Study](https://reader036.vdocuments.net/reader036/viewer/2022071412/61085c9c0fadb272c7213da0/html5/thumbnails/1.jpg)
Stakeholder Forum #4
February 4, 2021
South Downtown I-405 Access Study
![Page 2: South Downtown I-405 Access Study · 2021. 2. 2. · South Downtown I-405 Access Study. Panelists. Shuming Yan Project manager, Bellevue Transportation Department Barrett Hanson Study](https://reader036.vdocuments.net/reader036/viewer/2022071412/61085c9c0fadb272c7213da0/html5/thumbnails/2.jpg)
Panelists
Shuming YanProject manager,Bellevue Transportation Department
Barrett HansonStudy work group,WSDOT
Karl WestbyStudy work group,WSDOT
2
Emil KingStudy work group,Bellevue Community Development Department
![Page 3: South Downtown I-405 Access Study · 2021. 2. 2. · South Downtown I-405 Access Study. Panelists. Shuming Yan Project manager, Bellevue Transportation Department Barrett Hanson Study](https://reader036.vdocuments.net/reader036/viewer/2022071412/61085c9c0fadb272c7213da0/html5/thumbnails/3.jpg)
Facilitation and support
Laura LaBissoniere Miller, Community engagement –forum facilitator, PRR
Nancy Thai, Community engagement –forum support, PRR
3
Marie JensenPublic involvement manager,Bellevue Transportation Department
![Page 5: South Downtown I-405 Access Study · 2021. 2. 2. · South Downtown I-405 Access Study. Panelists. Shuming Yan Project manager, Bellevue Transportation Department Barrett Hanson Study](https://reader036.vdocuments.net/reader036/viewer/2022071412/61085c9c0fadb272c7213da0/html5/thumbnails/5.jpg)
Agenda
1. Welcome and review meeting objectives
2. Recap stakeholder engagement process
3. Review stakeholder feedback from forum #3
4. Share findings from Tier 2 evaluation analysis
5. Discussion and Q&A
6. Next steps
5
![Page 6: South Downtown I-405 Access Study · 2021. 2. 2. · South Downtown I-405 Access Study. Panelists. Shuming Yan Project manager, Bellevue Transportation Department Barrett Hanson Study](https://reader036.vdocuments.net/reader036/viewer/2022071412/61085c9c0fadb272c7213da0/html5/thumbnails/6.jpg)
Tonight’s objectives
• Share Tier 2 evaluation findings, including qualitative and quantitative analysis
• Discuss plan and policy considerations identified at previous stakeholder meetings
• Gather input to inform study team’s recommendation to City Council
6
![Page 7: South Downtown I-405 Access Study · 2021. 2. 2. · South Downtown I-405 Access Study. Panelists. Shuming Yan Project manager, Bellevue Transportation Department Barrett Hanson Study](https://reader036.vdocuments.net/reader036/viewer/2022071412/61085c9c0fadb272c7213da0/html5/thumbnails/7.jpg)
Stakeholder engagement recapForum #1:
• Overview of study goals, guiding principles, process and timeline
• Shared project purpose and need
Forum #2:
• Introduced alternatives
• Shared Tier 1 fatal flaw screening results
Forum #3:
• Shared more fatal flaw screening results
• Shared staff recommendation of five alternatives for the Council's consideration
Thank you for your input during and after each forum!
7
![Page 8: South Downtown I-405 Access Study · 2021. 2. 2. · South Downtown I-405 Access Study. Panelists. Shuming Yan Project manager, Bellevue Transportation Department Barrett Hanson Study](https://reader036.vdocuments.net/reader036/viewer/2022071412/61085c9c0fadb272c7213da0/html5/thumbnails/8.jpg)
8
Stakeholder forum #3 feedback
![Page 9: South Downtown I-405 Access Study · 2021. 2. 2. · South Downtown I-405 Access Study. Panelists. Shuming Yan Project manager, Bellevue Transportation Department Barrett Hanson Study](https://reader036.vdocuments.net/reader036/viewer/2022071412/61085c9c0fadb272c7213da0/html5/thumbnails/9.jpg)
9
![Page 10: South Downtown I-405 Access Study · 2021. 2. 2. · South Downtown I-405 Access Study. Panelists. Shuming Yan Project manager, Bellevue Transportation Department Barrett Hanson Study](https://reader036.vdocuments.net/reader036/viewer/2022071412/61085c9c0fadb272c7213da0/html5/thumbnails/10.jpg)
10
![Page 11: South Downtown I-405 Access Study · 2021. 2. 2. · South Downtown I-405 Access Study. Panelists. Shuming Yan Project manager, Bellevue Transportation Department Barrett Hanson Study](https://reader036.vdocuments.net/reader036/viewer/2022071412/61085c9c0fadb272c7213da0/html5/thumbnails/11.jpg)
11
![Page 12: South Downtown I-405 Access Study · 2021. 2. 2. · South Downtown I-405 Access Study. Panelists. Shuming Yan Project manager, Bellevue Transportation Department Barrett Hanson Study](https://reader036.vdocuments.net/reader036/viewer/2022071412/61085c9c0fadb272c7213da0/html5/thumbnails/12.jpg)
12
![Page 13: South Downtown I-405 Access Study · 2021. 2. 2. · South Downtown I-405 Access Study. Panelists. Shuming Yan Project manager, Bellevue Transportation Department Barrett Hanson Study](https://reader036.vdocuments.net/reader036/viewer/2022071412/61085c9c0fadb272c7213da0/html5/thumbnails/13.jpg)
13
![Page 14: South Downtown I-405 Access Study · 2021. 2. 2. · South Downtown I-405 Access Study. Panelists. Shuming Yan Project manager, Bellevue Transportation Department Barrett Hanson Study](https://reader036.vdocuments.net/reader036/viewer/2022071412/61085c9c0fadb272c7213da0/html5/thumbnails/14.jpg)
Additional feedback• Concern about advancing Northeast Second Street extension
• Interest in combining Northeast Second Street extension and Lake Hills Connector southbound on-ramp options
• Interest in traffic modeling results
• Question about why Northeast Fourth Street westbound left turn to southbound on-ramp is restricted on Lake Hills Connector southbound on-ramp alternative
• Support for study team’s transparent approach
14
![Page 15: South Downtown I-405 Access Study · 2021. 2. 2. · South Downtown I-405 Access Study. Panelists. Shuming Yan Project manager, Bellevue Transportation Department Barrett Hanson Study](https://reader036.vdocuments.net/reader036/viewer/2022071412/61085c9c0fadb272c7213da0/html5/thumbnails/15.jpg)
Tier 2 evaluation findings
15
![Page 16: South Downtown I-405 Access Study · 2021. 2. 2. · South Downtown I-405 Access Study. Panelists. Shuming Yan Project manager, Bellevue Transportation Department Barrett Hanson Study](https://reader036.vdocuments.net/reader036/viewer/2022071412/61085c9c0fadb272c7213da0/html5/thumbnails/16.jpg)
Alternatives evaluated in Tier 2Lake Hills Connector southbound on-ramp
Southeast Sixth Street extension and southbound on-ramp
Southeast Sixth Street extension inside access
Northeast Second Street extension No build (baseline)
![Page 17: South Downtown I-405 Access Study · 2021. 2. 2. · South Downtown I-405 Access Study. Panelists. Shuming Yan Project manager, Bellevue Transportation Department Barrett Hanson Study](https://reader036.vdocuments.net/reader036/viewer/2022071412/61085c9c0fadb272c7213da0/html5/thumbnails/17.jpg)
Tier 2 – Alternatives evaluation
Cost
Access and safety
Impact on
propertydevelopment
Alignment with adopted plans and policies
Travel time
Stakeholder Input
Community Input
17
QualitativeAnalysis and
Measures
Quantitative
Analysis and
Measures
![Page 18: South Downtown I-405 Access Study · 2021. 2. 2. · South Downtown I-405 Access Study. Panelists. Shuming Yan Project manager, Bellevue Transportation Department Barrett Hanson Study](https://reader036.vdocuments.net/reader036/viewer/2022071412/61085c9c0fadb272c7213da0/html5/thumbnails/18.jpg)
Alignment with adopted plans and policies
18
![Page 19: South Downtown I-405 Access Study · 2021. 2. 2. · South Downtown I-405 Access Study. Panelists. Shuming Yan Project manager, Bellevue Transportation Department Barrett Hanson Study](https://reader036.vdocuments.net/reader036/viewer/2022071412/61085c9c0fadb272c7213da0/html5/thumbnails/19.jpg)
Alignment with regional and local transportation plans• All alternatives, except No build, align with state and regional plans
• Lake Hills Connector southbound on-ramp
o Auto access only; no bike lanes and sidewalks, no east-west connection
• Southeast Sixth Street extension options (southbound on-ramp and inside access)
o New access to I-405, multimodal with east-west connection
• Northeast Second Street extension
o Multimodal with east-west connection
o No new freeway access
• No build
o Does not include vehicle capacity to support future growth
19
![Page 20: South Downtown I-405 Access Study · 2021. 2. 2. · South Downtown I-405 Access Study. Panelists. Shuming Yan Project manager, Bellevue Transportation Department Barrett Hanson Study](https://reader036.vdocuments.net/reader036/viewer/2022071412/61085c9c0fadb272c7213da0/html5/thumbnails/20.jpg)
Alignment with land use and urban design plans and policies• Lake Hills Connector southbound on-ramp
o No significant policy conflict
• Southeast Sixth Street extension options (southbound on-ramp and inside
access)
o East Main transit-oriented development work did not anticipate ramps at Southeast Sixth Street
• Northeast Second Street extension
o No new access to support growth
o Reduces redevelopment potential
• No build
o No new access to support growth
20
![Page 21: South Downtown I-405 Access Study · 2021. 2. 2. · South Downtown I-405 Access Study. Panelists. Shuming Yan Project manager, Bellevue Transportation Department Barrett Hanson Study](https://reader036.vdocuments.net/reader036/viewer/2022071412/61085c9c0fadb272c7213da0/html5/thumbnails/21.jpg)
Alignment with existing environmental codes and policies• Lake Hills Connector southbound on-ramp
o Permanent impacts from shade, lighting, noise and water quality
• Southeast Sixth Street extension options (southbound on-ramp and inside
access)
o Likely temporary impacts to wetlands during construction
o Permanent impacts from shade, lighting, noise and water quality
• Northeast Second Street extension
o Permanent wetland and stream impacts
o Permanent impacts from shade, lighting, noise and water quality
o No build
o Maintains existing conditions – no environmental impacts
![Page 22: South Downtown I-405 Access Study · 2021. 2. 2. · South Downtown I-405 Access Study. Panelists. Shuming Yan Project manager, Bellevue Transportation Department Barrett Hanson Study](https://reader036.vdocuments.net/reader036/viewer/2022071412/61085c9c0fadb272c7213da0/html5/thumbnails/22.jpg)
East Main Transit-Oriented Development Vision• 2019 Comprehensive Plan policies
• Southeast Sixth Street extension ramp alternatives require policy changes
22
![Page 23: South Downtown I-405 Access Study · 2021. 2. 2. · South Downtown I-405 Access Study. Panelists. Shuming Yan Project manager, Bellevue Transportation Department Barrett Hanson Study](https://reader036.vdocuments.net/reader036/viewer/2022071412/61085c9c0fadb272c7213da0/html5/thumbnails/23.jpg)
Travel time
23
![Page 24: South Downtown I-405 Access Study · 2021. 2. 2. · South Downtown I-405 Access Study. Panelists. Shuming Yan Project manager, Bellevue Transportation Department Barrett Hanson Study](https://reader036.vdocuments.net/reader036/viewer/2022071412/61085c9c0fadb272c7213da0/html5/thumbnails/24.jpg)
I-405 access capacity (2035)
24
• Southeast Sixth Street extension inside access provides highest capacity with both on- and off-ramps
![Page 25: South Downtown I-405 Access Study · 2021. 2. 2. · South Downtown I-405 Access Study. Panelists. Shuming Yan Project manager, Bellevue Transportation Department Barrett Hanson Study](https://reader036.vdocuments.net/reader036/viewer/2022071412/61085c9c0fadb272c7213da0/html5/thumbnails/25.jpg)
Additional intersection improvementsLake Hills Connector southbound on-ramp
Southeast Sixth Street extension and southbound on-ramp
Southeast Sixth Street extension inside accessRechannelization,
convert westbound left turn on-ramp to westbound through
Add eastbound and westbound left-turn lanes
Rechannelize to provide an exclusive left-turn lane
![Page 26: South Downtown I-405 Access Study · 2021. 2. 2. · South Downtown I-405 Access Study. Panelists. Shuming Yan Project manager, Bellevue Transportation Department Barrett Hanson Study](https://reader036.vdocuments.net/reader036/viewer/2022071412/61085c9c0fadb272c7213da0/html5/thumbnails/26.jpg)
City wide travel time savings
26
• Daily travel time for all roads in Bellevue
• Southeast Sixth Street extension inside access saves most travel time
![Page 27: South Downtown I-405 Access Study · 2021. 2. 2. · South Downtown I-405 Access Study. Panelists. Shuming Yan Project manager, Bellevue Transportation Department Barrett Hanson Study](https://reader036.vdocuments.net/reader036/viewer/2022071412/61085c9c0fadb272c7213da0/html5/thumbnails/27.jpg)
Intersection delay reductions Intersections evaluated
Existing IntersectionNew Intersection
Legend
![Page 28: South Downtown I-405 Access Study · 2021. 2. 2. · South Downtown I-405 Access Study. Panelists. Shuming Yan Project manager, Bellevue Transportation Department Barrett Hanson Study](https://reader036.vdocuments.net/reader036/viewer/2022071412/61085c9c0fadb272c7213da0/html5/thumbnails/28.jpg)
28
Access and safety
![Page 29: South Downtown I-405 Access Study · 2021. 2. 2. · South Downtown I-405 Access Study. Panelists. Shuming Yan Project manager, Bellevue Transportation Department Barrett Hanson Study](https://reader036.vdocuments.net/reader036/viewer/2022071412/61085c9c0fadb272c7213da0/html5/thumbnails/29.jpg)
Multimodal access• Separate bicycle lane and
sidewalks make it easier
for people to walk and bike
• New connection across I-
405
• Lake Hills Connector and
No Build do not add
facilities for people walking
and biking
29
New sidewalk/separate bike lane
Light rail
Trail
Study alternative
Legend
Southeast Sixth Street extension and southbound on-ramp
Southeast Sixth Street extension inside access
Northeast Second Street extension
![Page 30: South Downtown I-405 Access Study · 2021. 2. 2. · South Downtown I-405 Access Study. Panelists. Shuming Yan Project manager, Bellevue Transportation Department Barrett Hanson Study](https://reader036.vdocuments.net/reader036/viewer/2022071412/61085c9c0fadb272c7213da0/html5/thumbnails/30.jpg)
Safety
30
• Crash rates on local roadways are 20 percent higher than freeways. More access to freeways helps improve safety on local roadways
• Reducing congestion helps prevent rear-end crashes, which account for 30 percent of crashes in the study area
• Separate bicycle lanes and sidewalks improve safety for people walking and biking
![Page 31: South Downtown I-405 Access Study · 2021. 2. 2. · South Downtown I-405 Access Study. Panelists. Shuming Yan Project manager, Bellevue Transportation Department Barrett Hanson Study](https://reader036.vdocuments.net/reader036/viewer/2022071412/61085c9c0fadb272c7213da0/html5/thumbnails/31.jpg)
31
Impact on property
development
![Page 32: South Downtown I-405 Access Study · 2021. 2. 2. · South Downtown I-405 Access Study. Panelists. Shuming Yan Project manager, Bellevue Transportation Department Barrett Hanson Study](https://reader036.vdocuments.net/reader036/viewer/2022071412/61085c9c0fadb272c7213da0/html5/thumbnails/32.jpg)
Lake Hills Connector southbound on-ramp
32
![Page 33: South Downtown I-405 Access Study · 2021. 2. 2. · South Downtown I-405 Access Study. Panelists. Shuming Yan Project manager, Bellevue Transportation Department Barrett Hanson Study](https://reader036.vdocuments.net/reader036/viewer/2022071412/61085c9c0fadb272c7213da0/html5/thumbnails/33.jpg)
Southeast Sixth street extension and southbound on-ramp
![Page 34: South Downtown I-405 Access Study · 2021. 2. 2. · South Downtown I-405 Access Study. Panelists. Shuming Yan Project manager, Bellevue Transportation Department Barrett Hanson Study](https://reader036.vdocuments.net/reader036/viewer/2022071412/61085c9c0fadb272c7213da0/html5/thumbnails/34.jpg)
Southeast Sixth street extension and southbound on-ramp
![Page 35: South Downtown I-405 Access Study · 2021. 2. 2. · South Downtown I-405 Access Study. Panelists. Shuming Yan Project manager, Bellevue Transportation Department Barrett Hanson Study](https://reader036.vdocuments.net/reader036/viewer/2022071412/61085c9c0fadb272c7213da0/html5/thumbnails/35.jpg)
Southeast Sixth Street extension inside access
![Page 36: South Downtown I-405 Access Study · 2021. 2. 2. · South Downtown I-405 Access Study. Panelists. Shuming Yan Project manager, Bellevue Transportation Department Barrett Hanson Study](https://reader036.vdocuments.net/reader036/viewer/2022071412/61085c9c0fadb272c7213da0/html5/thumbnails/36.jpg)
Southeast Sixth Street extension access property impacts• Southeast Sixth Street connects
to 112th Avenue Southeast and Lake Hills Connector, no connection to 114th Avenue Southeast
• Provides property access road under the bridge for the elevated Southeast Sixth Street
36
![Page 37: South Downtown I-405 Access Study · 2021. 2. 2. · South Downtown I-405 Access Study. Panelists. Shuming Yan Project manager, Bellevue Transportation Department Barrett Hanson Study](https://reader036.vdocuments.net/reader036/viewer/2022071412/61085c9c0fadb272c7213da0/html5/thumbnails/37.jpg)
Northeast Second Street extension
37
![Page 38: South Downtown I-405 Access Study · 2021. 2. 2. · South Downtown I-405 Access Study. Panelists. Shuming Yan Project manager, Bellevue Transportation Department Barrett Hanson Study](https://reader036.vdocuments.net/reader036/viewer/2022071412/61085c9c0fadb272c7213da0/html5/thumbnails/38.jpg)
Northeast Second Street extension• Requires elevating roadway over
114th Avenue Northeast and I-405 to connect with 116th Avenue Northeast
• Properties with access on 114th Avenue Southeast must use Southeast Sixth Street to connect to north and downtown
38
![Page 39: South Downtown I-405 Access Study · 2021. 2. 2. · South Downtown I-405 Access Study. Panelists. Shuming Yan Project manager, Bellevue Transportation Department Barrett Hanson Study](https://reader036.vdocuments.net/reader036/viewer/2022071412/61085c9c0fadb272c7213da0/html5/thumbnails/39.jpg)
Northeast Second Street extension• Requires elevating roadway over
114th Avenue Northeast and I-405 to connect with 116th Avenue Northeast
• Properties with access on 114th Avenue Southeast must use Southeast Sixth Street to connect to north and downtown
39
![Page 40: South Downtown I-405 Access Study · 2021. 2. 2. · South Downtown I-405 Access Study. Panelists. Shuming Yan Project manager, Bellevue Transportation Department Barrett Hanson Study](https://reader036.vdocuments.net/reader036/viewer/2022071412/61085c9c0fadb272c7213da0/html5/thumbnails/40.jpg)
Cost
40
![Page 41: South Downtown I-405 Access Study · 2021. 2. 2. · South Downtown I-405 Access Study. Panelists. Shuming Yan Project manager, Bellevue Transportation Department Barrett Hanson Study](https://reader036.vdocuments.net/reader036/viewer/2022071412/61085c9c0fadb272c7213da0/html5/thumbnails/41.jpg)
Planning level cost estimates
*Cost estimate based on escalation to 2030 construction. Includes engineering, right-of-way,and construction costs. Right-of-way costs assume acquisition prior to redevelopment
![Page 42: South Downtown I-405 Access Study · 2021. 2. 2. · South Downtown I-405 Access Study. Panelists. Shuming Yan Project manager, Bellevue Transportation Department Barrett Hanson Study](https://reader036.vdocuments.net/reader036/viewer/2022071412/61085c9c0fadb272c7213da0/html5/thumbnails/42.jpg)
Putting it all together
We evaluated the five alternatives based upon:
• Alignment with adopted plans and policies
• Travel time
• Access and safety
• Property and environmental impacts
• Costs
We are looking for your feedback and input
42
![Page 43: South Downtown I-405 Access Study · 2021. 2. 2. · South Downtown I-405 Access Study. Panelists. Shuming Yan Project manager, Bellevue Transportation Department Barrett Hanson Study](https://reader036.vdocuments.net/reader036/viewer/2022071412/61085c9c0fadb272c7213da0/html5/thumbnails/43.jpg)
Discussion and Q&A
43
![Page 44: South Downtown I-405 Access Study · 2021. 2. 2. · South Downtown I-405 Access Study. Panelists. Shuming Yan Project manager, Bellevue Transportation Department Barrett Hanson Study](https://reader036.vdocuments.net/reader036/viewer/2022071412/61085c9c0fadb272c7213da0/html5/thumbnails/44.jpg)
Study schedule
![Page 45: South Downtown I-405 Access Study · 2021. 2. 2. · South Downtown I-405 Access Study. Panelists. Shuming Yan Project manager, Bellevue Transportation Department Barrett Hanson Study](https://reader036.vdocuments.net/reader036/viewer/2022071412/61085c9c0fadb272c7213da0/html5/thumbnails/45.jpg)
Next steps
• Stakeholder questionnaire (due Monday, Feb. 8)
• Online open house: Feb. 8-19
• City Council meeting: April 5
• For more information, visit BellevueWA.gov/access-study
45
![Page 46: South Downtown I-405 Access Study · 2021. 2. 2. · South Downtown I-405 Access Study. Panelists. Shuming Yan Project manager, Bellevue Transportation Department Barrett Hanson Study](https://reader036.vdocuments.net/reader036/viewer/2022071412/61085c9c0fadb272c7213da0/html5/thumbnails/46.jpg)
Thank you!
46
![Page 47: South Downtown I-405 Access Study · 2021. 2. 2. · South Downtown I-405 Access Study. Panelists. Shuming Yan Project manager, Bellevue Transportation Department Barrett Hanson Study](https://reader036.vdocuments.net/reader036/viewer/2022071412/61085c9c0fadb272c7213da0/html5/thumbnails/47.jpg)
AppendixAdditional traffic information
47
![Page 48: South Downtown I-405 Access Study · 2021. 2. 2. · South Downtown I-405 Access Study. Panelists. Shuming Yan Project manager, Bellevue Transportation Department Barrett Hanson Study](https://reader036.vdocuments.net/reader036/viewer/2022071412/61085c9c0fadb272c7213da0/html5/thumbnails/48.jpg)
Travel time between major destinationsRelative to 2035 No build
48
For trips going from City Hall to I-90 westbound, the two Southeast Sixth Street extension alternatives are expected to save one minute/vehicle in travel time while allowing more people to use the freeway
The data were taken at the I-
90/Island Crest Way Interchange.
![Page 49: South Downtown I-405 Access Study · 2021. 2. 2. · South Downtown I-405 Access Study. Panelists. Shuming Yan Project manager, Bellevue Transportation Department Barrett Hanson Study](https://reader036.vdocuments.net/reader036/viewer/2022071412/61085c9c0fadb272c7213da0/html5/thumbnails/49.jpg)
Travel time between major destinationsRelative to 2035 No build
49
For trips going from City Hall to I-90 eastbound, the three alternatives that provide access to I-405 are expected to save about half-a-minute/vehicle in travel time while allowing more people to use the freeway
The data were taken at the I-90
Eastgate Interchange.
![Page 50: South Downtown I-405 Access Study · 2021. 2. 2. · South Downtown I-405 Access Study. Panelists. Shuming Yan Project manager, Bellevue Transportation Department Barrett Hanson Study](https://reader036.vdocuments.net/reader036/viewer/2022071412/61085c9c0fadb272c7213da0/html5/thumbnails/50.jpg)
No build 2035 traffic forecast(PM Peak Hour)
50
![Page 51: South Downtown I-405 Access Study · 2021. 2. 2. · South Downtown I-405 Access Study. Panelists. Shuming Yan Project manager, Bellevue Transportation Department Barrett Hanson Study](https://reader036.vdocuments.net/reader036/viewer/2022071412/61085c9c0fadb272c7213da0/html5/thumbnails/51.jpg)
51
Changes of less than ten trips/hour are not shown. The changes on most local streets are small and within daily volume fluctuations.
2035 Traffic Comparison: Lake Hills Connector southbound on-ramp vs No build(PM Peak Hour)
![Page 52: South Downtown I-405 Access Study · 2021. 2. 2. · South Downtown I-405 Access Study. Panelists. Shuming Yan Project manager, Bellevue Transportation Department Barrett Hanson Study](https://reader036.vdocuments.net/reader036/viewer/2022071412/61085c9c0fadb272c7213da0/html5/thumbnails/52.jpg)
52
Changes of less than 10 trips/hour are not shown. The changes on most local streets are small and within daily volume fluctuations.
2035 Traffic Comparison: Southeast Sixth Street Extension Inside Access vs No build(PM Peak Hour)
![Page 53: South Downtown I-405 Access Study · 2021. 2. 2. · South Downtown I-405 Access Study. Panelists. Shuming Yan Project manager, Bellevue Transportation Department Barrett Hanson Study](https://reader036.vdocuments.net/reader036/viewer/2022071412/61085c9c0fadb272c7213da0/html5/thumbnails/53.jpg)
2035 Traffic Comparison: Southeast Sixth Street Extension southbound on-ramp vs No build(PM Peak Hour)
53
Changes of less than ten trips/hour are not shown. The changes on most local streets are small and within daily volume fluctuations.
![Page 54: South Downtown I-405 Access Study · 2021. 2. 2. · South Downtown I-405 Access Study. Panelists. Shuming Yan Project manager, Bellevue Transportation Department Barrett Hanson Study](https://reader036.vdocuments.net/reader036/viewer/2022071412/61085c9c0fadb272c7213da0/html5/thumbnails/54.jpg)
2035 Traffic Comparison Northeast Second Street Extension vs No build (PM peak hour)
54
Changes of less than ten trips/hour are not shown. The changes on most of local streets are small and within daily volume fluctuations.
![Page 55: South Downtown I-405 Access Study · 2021. 2. 2. · South Downtown I-405 Access Study. Panelists. Shuming Yan Project manager, Bellevue Transportation Department Barrett Hanson Study](https://reader036.vdocuments.net/reader036/viewer/2022071412/61085c9c0fadb272c7213da0/html5/thumbnails/55.jpg)
Intersection Analysis 2035 (PM peak hour)
Alternatives Change
NE 2nd St. Ext 6.6%
LHC SB Ramp +improvements -6.3%
SE 6th Inside Access +improvements -6.8%
SE 6th GP Ramp +improvements -9.6%
55
![Page 56: South Downtown I-405 Access Study · 2021. 2. 2. · South Downtown I-405 Access Study. Panelists. Shuming Yan Project manager, Bellevue Transportation Department Barrett Hanson Study](https://reader036.vdocuments.net/reader036/viewer/2022071412/61085c9c0fadb272c7213da0/html5/thumbnails/56.jpg)
2035 Mode Share in the study area
• Single-occupancy vehicle (SOV) mode share for work trips is expected to decrease from 57% to 52%
• SOV mode share for all trips is expected to decrease from 38% to 36%
![Page 57: South Downtown I-405 Access Study · 2021. 2. 2. · South Downtown I-405 Access Study. Panelists. Shuming Yan Project manager, Bellevue Transportation Department Barrett Hanson Study](https://reader036.vdocuments.net/reader036/viewer/2022071412/61085c9c0fadb272c7213da0/html5/thumbnails/57.jpg)
![Page 58: South Downtown I-405 Access Study · 2021. 2. 2. · South Downtown I-405 Access Study. Panelists. Shuming Yan Project manager, Bellevue Transportation Department Barrett Hanson Study](https://reader036.vdocuments.net/reader036/viewer/2022071412/61085c9c0fadb272c7213da0/html5/thumbnails/58.jpg)
![Page 59: South Downtown I-405 Access Study · 2021. 2. 2. · South Downtown I-405 Access Study. Panelists. Shuming Yan Project manager, Bellevue Transportation Department Barrett Hanson Study](https://reader036.vdocuments.net/reader036/viewer/2022071412/61085c9c0fadb272c7213da0/html5/thumbnails/59.jpg)
![Page 60: South Downtown I-405 Access Study · 2021. 2. 2. · South Downtown I-405 Access Study. Panelists. Shuming Yan Project manager, Bellevue Transportation Department Barrett Hanson Study](https://reader036.vdocuments.net/reader036/viewer/2022071412/61085c9c0fadb272c7213da0/html5/thumbnails/60.jpg)
![Page 61: South Downtown I-405 Access Study · 2021. 2. 2. · South Downtown I-405 Access Study. Panelists. Shuming Yan Project manager, Bellevue Transportation Department Barrett Hanson Study](https://reader036.vdocuments.net/reader036/viewer/2022071412/61085c9c0fadb272c7213da0/html5/thumbnails/61.jpg)
Additional intersection improvementsImprovements added to:• Lake Hills Connector southbound on-ramp• Southeast Sixth Street extension and southbound on-ramp• Southeast Sixth Street extension inside access
![Page 62: South Downtown I-405 Access Study · 2021. 2. 2. · South Downtown I-405 Access Study. Panelists. Shuming Yan Project manager, Bellevue Transportation Department Barrett Hanson Study](https://reader036.vdocuments.net/reader036/viewer/2022071412/61085c9c0fadb272c7213da0/html5/thumbnails/62.jpg)
• Lake Hills Connector southbound on-ramp: Eliminating westbound left turn at Northeast Fourth Street/I-405 southbound ramp
Additional intersection improvements