south east australia gas pty ltd - department of state...

28
South East Australia Gas Pty Ltd Annual Report South Australian Pipeline Licence (PL 13) 2011 2012 Licence Year Port Campbell to Adelaide Natural Gas Transmission Pipeline

Upload: others

Post on 22-Jun-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: South East Australia Gas Pty Ltd - Department of State ...petroleum.statedevelopment.sa.gov.au/__data/assets/... · Annual Report (PL13) – Port Campbell to Adelaide Pipeline 2011

South East Australia Gas Pty Ltd

Annual Report

South Australian Pipeline Licence (PL 13)

2011 – 2012 Licence Year

Port Campbell to Adelaide

Natural Gas Transmission Pipeline

Page 2: South East Australia Gas Pty Ltd - Department of State ...petroleum.statedevelopment.sa.gov.au/__data/assets/... · Annual Report (PL13) – Port Campbell to Adelaide Pipeline 2011

Annual Report ( PL13 ) – Port Campbell to Adelaide Pipeline (PCA)

2011 – 2012 Licence Year

Page 2 of 28

TABLE OF CONTENTS

1.0 SCOPE ............................................................................................................................... 3

2.0 SUMMARY OF REGULATED ACTIVITIES ............................................................................ 3

2.1 Training ........................................................................................................... 3

2.2 Patrol Activities ................................................................................................ 4

2.3 Operations and Maintenance Activities ............................................................... 5

2.4 Cathodic Protection Potential Survey .................................................................. 7

2.5 Pipeline Location and Referral Services ............................................................... 7

2.6 Emergency Response & Preparedness ................................................................ 7

3.0 REGULATORY COMPLIANCE ............................................................................................. 8

4.0 RECTIFICATION OF NON-COMPLYING ACTIONS .............................................................. 8

5.0 MANAGEMENT SYSTEM AUDITS ...................................................................................... 8

5.1 Occupational Health and Safety ......................................................................... 8

6.0 REPORTS AND DATA ....................................................................................................... 10

7.0 INCIDENT MANAGEMENT .............................................................................................. 10

8.0 RISK MANAGEMENT ....................................................................................................... 11

9.0 PROPOSED OPERATIONAL ACTIVITIES 2012 - 2013 LICENCE YEAR ................................ 11

10.0 VOLUME OF REGULATED SUBSTANCE TRANSPORTED .................................................. 12

11.0 STATEMENT OF ANNUAL EXPENDITURE ........................................................................ 12

APPENDIX A – ASSESSMENT OF COMPLIANCE AGAINST SEO OBJECTIVES ................................ 13

APPENDIX B – REPORTABLE INCIDENTS DURING THE LICENCE YEAR ........................................ 22

APPENDIX C – STATEMENT OF ANNUAL EXPENDITURE ............................................................. 25

APPENDIX D – EASEMENT REHABILITATION SUMMARY ........................................................... 26

APPENDIX E - Reports Generated by the Licensee during the Reporting Year .......................... 28

Page 3: South East Australia Gas Pty Ltd - Department of State ...petroleum.statedevelopment.sa.gov.au/__data/assets/... · Annual Report (PL13) – Port Campbell to Adelaide Pipeline 2011

Annual Report (PL13) – Port Campbell to Adelaide Pipeline

2011 – 2012 Licence Year

Page 3

1.0 SCOPE

South East Australia Gas Pty Ltd (SEA Gas) submits this report to the Energy Resources Division - Department for Manufacturing, Innovation, Trade, Resources and Energy (DMITRE), in accordance with sub-regulation 33 (1) of the Petroleum and Geothermal Energy Regulations (SA) 2000, in relation to its operation of the SEA Gas Port Campbell to Adelaide natural gas transmission pipeline (PCA) during the licence year (1 July 2011 to 30 June 2012, as per approval from the Minister dated 3 June 2004).

This report validates operational compliance along the South Australian portion of the SEA Gas pipeline in accordance with the SEA Gas Statement of Environmental Objectives (SEO); the conditions of Pipeline Licence No. 13 and the requirements of the Petroleum and Geothermal Energy Act (SA) 2000 and regulations under the Act.

2.0 SUMMARY OF REGULATED ACTIVITIES

During the licence year SEA Gas conducted its operations in accordance with the requirements of the Petroleum and Geothermal Energy Act (SA) 2000; conditions applicable to Pipeline Licence No. 13; and Australian Standard AS 2885. There were six non-compliances against the SEA Gas SEO (Revision 4).

In accordance with sub-regulation 33(2)(a) the following regulated activities were conducted during the licence year:

2.1 Training

SEA Gas operations personnel, third-party maintenance services providers and approved contractors completed the following training during the licence year:

SEA Gas Statement of Environmental Objectives Nominated Permit Holder and Job Hazard Analysis Defect Assessment in Pipelines Pipeline Integrity Risk Management Contractor Management Draegar® Gas Detector Familiarisation Protection and Safety of Engineering Infrastructure – Dial Before You Dig Use of Portable Fire Fighting Equipment Equipment and Vehicle Environmental Inspection & Washdown Emergency Warden Senior First Aid Cardio Pulmonary Resuscitation (CPR) refresher Occupational Health & Safety briefings Skin Cancer Awareness TapRoot® Incident Investigation & Root Cause Analysis Four-wheel drive and off-road defensive driver training The New Workplace Health and Safety Act Cert IV Electro Technology & Instrumentation Certificate II in Construction Work Safety in the Construction Industry Solar (Compressor) Technical Training Centrifugal Compressor Performance and Condition Evaluation

Page 4: South East Australia Gas Pty Ltd - Department of State ...petroleum.statedevelopment.sa.gov.au/__data/assets/... · Annual Report (PL13) – Port Campbell to Adelaide Pipeline 2011

Annual Report (PL13) – Port Campbell to Adelaide Pipeline

2011 – 2012 Licence Year

Page 4

Advanced Greenhouse Gas Compliance National Pollutant Inventory Reporting & Administration Forklift Licence Automotive Engineering and Design Microsoft 6231:Maintaining a Microsoft SQL Server 2008 Database Cashflow Analysis Managing Challenging Situations Leadership Development – Managing Others Leadership Development – Managing Self Leading with Impact ArcGIS Desktop 1:Getting started with Geographic Information Systems

2.2 Patrol Activities

Programmed aerial and ground patrols of the pipeline system were carried out during the licence year (Ref, Table 1).

Table 1 – Pipeline Patrol Schedule

Activity Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun

Weekly Road Patrol

Pelican Point PRMS to Williamstown MLV

#

Road Patrols

Iona PRMS (Vic) to Williamstown (SA) MLV

Aerial Patrols

Murray Bridge to Pelican Point (Rotary Wing) PRMS

Iona PRMS to Murray Bridge (Fixed Wing)

Daily Security Patrols

Munno Para MLV and Cavan PRMS

Observations arising from patrol activities are actioned in accordance with SEA Gas Fault Action Request (FAR) procedures.

# Due to urgent unplanned maintenance this weekly patrol was not completed.

Page 5: South East Australia Gas Pty Ltd - Department of State ...petroleum.statedevelopment.sa.gov.au/__data/assets/... · Annual Report (PL13) – Port Campbell to Adelaide Pipeline 2011

Annual Report (PL13) – Port Campbell to Adelaide Pipeline

2011 – 2012 Licence Year

Page 5

2.3 Operations and Maintenance Activities

Scheduled and variable maintenance activities were conducted during the licence year (Ref. Table 2) and reviewed monthly in consultation with maintenance services providers.

Table 2 –Scheduled Maintenance Activities

Activity Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun

Odorant/Gas Sampling & Analysis

Cavan PRMS

Calibrations of Gas Chromatographs

Cavan 1 PRMS

Cavan 2 PRMS

Torrens Island PRMS

Quarantine PRMS

Pelican Point PRMS

Scraper Stations

Coomandook A Q H Q

Pelican Point Q H Q A

Main Line Valves

Yallamurray, Coomandook, Pallamana, Williamstown, Gawler, Munno Para, Bolivar, Cavan & Pelican Point

A Q Q Q

Metering Facilities

Naracoorte PRMS A Q H Q

Jervois PRMS Q H Q A

Cavan Q A Q H

Torrens Island Q A Q H

Pelican Point Q H Q A

Corrosion Protection

Potential survey

Surge protection testing

A

Coomandook Compressor Station Maintenance

Site inspection (every second week)

Scheduled maintenance A Q H Q

Q Quarterly Maintenance Site inspection; heater inspection; Ultrasonic Flow Meter validations & meter run switching; Cathodic Protection Transformer Rectifier unit checks; smoke detector checks; soil and weed management; etc.

Page 6: South East Australia Gas Pty Ltd - Department of State ...petroleum.statedevelopment.sa.gov.au/__data/assets/... · Annual Report (PL13) – Port Campbell to Adelaide Pipeline 2011

Annual Report (PL13) – Port Campbell to Adelaide Pipeline

2011 – 2012 Licence Year

Page 6

H Six Monthly Maintenance As per quarterly maintenance, including water bath heater maintenance at Cavan; Torrens Island, Pelican Point, Quarantine, Dairy Farmers and Teys Brothers.

A Annual Maintenance As per six-monthly maintenance, inclusive of heater maintenance (spark arrestor, water sample & ignition system); mechanical maintenance (Main Line Valves, Shut-off Valve’s, Scrapers, Filters, Regulators, Pressure Safety Valves, Pressure Valves, Instrument Gas Checks, Electrical Maintenance (Batteries, Residual Current Devices, Pressure & Temperature Transducers; Solenoids; Meter Run Switching; Heat Tracing & Hazardous Area Checks), etc.

The following additional maintenance activities were conducted during the course of the licence year:

Pressure vessel external inspections

pressure safety valve change out

Refurbishment of Coomandook Compressor exhaust stack and repairs to silencer and expansion bellows

Compressor station CO2 bottle replacement

Overhaul of the 1st stage fuel gas regulators at the Coomandook Compressor Station

Gas Fired water bath heater internal inspections at Pelican Point Pressure Reducing Meter Station (PRMS) (2 off) and Torrens Island PRMS (2 off)

Excavation of three defects identified by in-line inspection at Glen Devon Road, Tailem Bend and Cookes Plains Road, South Australia.

Excavation and inspection of buried blind flange vent points and coating defect inspections at the Jervois off-take site

Inspection and controller upgrade of Flow Control Valve at Torrens Island PRMS.

Ongoing corrosion mitigation (refurbishment of surface corrosion and paint coatings of above ground pipe work at Cavan 1 & 2, Torrens Island, Quarantine & Pelican Point PRMS facilities)

Continued upgrade of existing signage (‘Warning’ to ‘Danger’) along the easement between the SA/Vic border and the Coomandook Compressor Station, to reflect recent changes to AS 2885

Environmental improvements and monitoring along the pipeline easement

‘Pipeline Awareness’; ‘Planning and Development around Pipelines’ and ‘Emergency Response’ training for emergency services, utilities and other stakeholders

Inspection, servicing and maintenance of fire detection, fire suppression; emergency response equipment; first aid kits and personal protective equipment

Page 7: South East Australia Gas Pty Ltd - Department of State ...petroleum.statedevelopment.sa.gov.au/__data/assets/... · Annual Report (PL13) – Port Campbell to Adelaide Pipeline 2011

Annual Report (PL13) – Port Campbell to Adelaide Pipeline

2011 – 2012 Licence Year

Page 7

Cathodic Protection Potential Survey

An annual cathodic protection potential survey of the PCA and associated laterals occurred during August 2011. The survey was completed and results assessed in accordance with AS 2885.3:2001 Pipelines – Gas and Liquid Petroleum Part 3: Operation and Maintenance and AS2832.1:2004 Cathodic Protection of Metals Part 1: Pipes and cables.

The survey involved measuring the pipeline potentials with respect to a saturated copper/copper sulphate reference electrode at each test point and at nominally every fifth test point, recording the pipeline potential over a 20-hour period, as required for pipelines subject to the effects of telluric currents.

The results of the survey indicated that the PCA and its associated laterals was fully protected in accordance with the protection criteria defined in Section 2.2 of AS 2832.1.

The survey also indicated that all AC (Alternating Current) surge protection devices installed along the pipeline were functional and found to be operating normally.

Readings were also taken on all corrosion probes, which were found to be operating normally.

The reconnection of the sacrificial anodes originally installed to provide temporary protection during construction appears to have been successful in reducing the magnitude of voltage variations due to telluric currents however telluric current activity was reasonably quiet during the survey period.

During the course of the survey the Pelican Point corrosion probe was replaced and the Yallamurray cathodic protection rectification unit was repaired.

2.4 Pipeline Location and Referral Services

During the course of the licence year, 592 (44% increase from the previous year) third party asset referral enquiries were received for the SEA Gas Pipeline System via the free call 1100, “Dial Before You Dig” asset referral service. In response to these enquiries, 334 (38% increase) were deemed to have a potential to affect the pipeline and were subject to site assessment.

2.5 Emergency Response & Preparedness

During the licence year, SEA Gas participated in the following emergency response exercises:

Exercise Broadview (7 September 2011, a combined exercise with South Australian emergency services to assess the critical incident response of a pipeline incident within an urban area);

Exercise Cape Nelson (17 April 2012, a combined exercise with SA & Vic Police, CERT Australia, ASIO, emergency services and Wannon Water (conducted in Warrnambool, Victoria) to assess the critical incident response to a cyber-threat); and

Exercise Vulcan (21 June 2012, a combined exercise with Epic Energy and regulatory representatives (DMITRE and Office of the Technical Regulator) to assess emergency response interoperability during an incident impacting the Moomba to Adelaide and Port Campbell to Adelaide pipelines simultaneously).

Recommendations arising from these exercises have been progressively actioned to enable continuous improvement and familiarisation with the SEA Gas Emergency Response and Crisis Management Plans. The progress of each action is tracked via the SEA Gas compliance action tracking system.

During the 2012 / 2013 licence year, SEA Gas intends to host:

Page 8: South East Australia Gas Pty Ltd - Department of State ...petroleum.statedevelopment.sa.gov.au/__data/assets/... · Annual Report (PL13) – Port Campbell to Adelaide Pipeline 2011

Annual Report (PL13) – Port Campbell to Adelaide Pipeline

2011 – 2012 Licence Year

Page 8

A desktop emergency response exercise for SEA Gas employees to ensure familiarity with recent changes to the SEA Gas Emergency Response Manual (TECH-MAN-011) and Crisis Management Plan (PR-PR-002) ; and

A response exercise in collaboration with the SEA Gas maintenance services provider, to assess combined emergency response processes.

3.0 REGULATORY COMPLIANCE

No ‘serious’ incidents (as defined in the Petroleum and Geothermal Energy Act 2000) occurred during the licence year. SEA Gas has complied with the legislative requirements of the Petroleum and Geothermal Energy Act 2000 and Petroleum and Geothermal Energy Regulations 2000, its Pipeline Licence (PL13) conditions and its Statement of Environmental Objectives.

4.0 RECTIFICATION OF NON-COMPLYING ACTIONS

During the course of the licence year, there were no outstanding non-complying actions which required closure.

5.0 MANAGEMENT SYSTEM AUDITS

In accordance with sub-regulation 33(2)(d) SEA Gas conducted a series of management system audits during the licence year to assess and validate its compliance with legislative requirements. Ensuing observations, recommendations and corrective actions were risk assessed and actioned.

5.1 Occupational Health and Safety

During the licence year, SEA Gas conducted a series of audits to assess and validate occupational health and safety compliance against its Safety & Operating Plan (Safety Case) and applicable legislative requirements, policies, procedures and contractual requirements. Operational activities (and sites) throughout Victoria and South Australia were audited during the licence year, the results of which indicated compliance and ongoing opportunities for continuous workplace safety improvement.

Page 9: South East Australia Gas Pty Ltd - Department of State ...petroleum.statedevelopment.sa.gov.au/__data/assets/... · Annual Report (PL13) – Port Campbell to Adelaide Pipeline 2011

Annual Report (PL13) – Port Campbell to Adelaide Pipeline

2011 – 2012 Licence Year

Page 9

Overview of Audits Conducted During the Licence Year

Audit Scope Auditor Summary of Observations & Actions

OHSE Facilities Audit

2-yearly pipeline above ground facility inspection of all sites;

SEA Gas Compliance with relevant Occupational Health & Safety OHS legislative requirements was achieved.

Observations related to housekeeping issues and suggested improvements to reduce workplace hazards were noted.

No legislative non-conformances were noted during the audits.

Contractor Audits

Compliance with Health Safety and Environmental (HSE) policies and procedures

Compliance with contractual and legislative requirements

SEA Gas Nine audits of maintenance and service providers, contractors and sub-contractors were conducted during the licence year.

Third party contractors were found to be compliant with SEA Gas HSE policies and procedures, however some housekeeping issues were identified during the audits.

Internal Audits

AS 2885.3 (Draft Code) Gap Analysis

Drawing audit of all alignment plans and P&IDs

Audit of permit issuing process

SEA Gas A gap analysis was conducted against the draft of Australian Standard AS 2885.3. The audit identified a number of low risk areas to be addressed. The results of this analysis will be incorporated into the next revision of the SEA Gas Safety and Operating Plan (TECH-PO-001).

The drawing audit identified administrative work required to address document control deficiencies.

The permit issuing audit found general compliance with the procedure with some opportunities for improvement noted.

Health, Safety and Environmental Management System (HSEMS) Self Assessment

The required frequency of the HSEMS self assessment surveys were extended to two-yearly by DMITRE and therefore the survey was not undertaken during the licence year.

SEA Gas intends to conduct the HSEMS Self Assessment surveys of its employees and contractors during the 2012/2013 licence year.

Environmental Rehabilitation

Environmental monitoring of the pipeline easement was undertaken during the licence year, which validated the success of post-construction site regeneration and easement monitoring and confirmed compliance with stated environmental objectives. A summary of easement rehabilitation is provided in Appendix D.

There is one revegetation site remaining which will require ongoing management during the 2012/2013 licence year.

Page 10: South East Australia Gas Pty Ltd - Department of State ...petroleum.statedevelopment.sa.gov.au/__data/assets/... · Annual Report (PL13) – Port Campbell to Adelaide Pipeline 2011

Annual Report (PL13) – Port Campbell to Adelaide Pipeline

2011 – 2012 Licence Year

Page 10

Observations relating to environmental audits and environmental site inspections were communicated to DMITRE during the course of quarterly meetings throughout the licence year. Progress reports, inclusive of site management actions, were presented to ensure continued compliance with site specific revegetation plans.

6.0 REPORTS AND DATA

In accordance with Regulation 33(2)(e) the following documentation was submitted to DMITRE - Petroleum and Geothermal Energy Group, in relation to regulated activities conducted by the licensee during the course of the licence year:

Pipeline Licence No. 13 - Annual Report for 2010 - 2011 licence year

Appendix C – Statement of Expenditure, in respect of the 2010 - 2011 Annual Report

Quarterly incident report (reporting period July – September 2011)

Quarterly incident report (reporting period October – December 2011)

Quarterly incident report (reporting period January – March 2012)

Quarterly incident report (reporting period April – June 2012)

Exercise Broadview Report

Exercise Vulcan Report

7.0 INCIDENT MANAGEMENT

No ‘serious’ incidents occurred during the licence year. Six reportable incidents occurred and were reported to DMITRE Energy Resources Division in quarterly reports in accordance with Regulation 33(2)(ii) (Ref, Appendix B).

The reportable incidents occurred along the South Australian section of the PCA and are summarised as follows:

Turbid water and silt was pumped from an excavation without sedimentation controls in place;

Two minor spill incidents occurred during water bath heater vessel inspections.

Three incidents of unauthorised third party activities along the pipeline easement occurred, none of which resulted in damage to pipeline infrastructure.

As a result of the reportable incidents, SEA Gas is rolling out training to all employees and contractors on the SEO to highlight compliance requirements. Procedures have also been updated to include better planning processes to manage environmental aspects.

Unauthorised third party activities along the pipeline easement continue to pose a risk to public safety and the continued supply of natural gas to South Australia. SEA Gas continues to provide pipeline safety awareness programs in conjunction with Epic Energy and APA Group, to demonstrate a unified industry approach to pipeline safety awareness. Land liaison processes have been modified to try to achieve more face to face contact with land owners and property managers and heighten pipeline safety awareness.

Page 11: South East Australia Gas Pty Ltd - Department of State ...petroleum.statedevelopment.sa.gov.au/__data/assets/... · Annual Report (PL13) – Port Campbell to Adelaide Pipeline 2011

Annual Report (PL13) – Port Campbell to Adelaide Pipeline

2011 – 2012 Licence Year

Page 11

8.0 RISK MANAGEMENT

During the course of the licence year, SEA Gas continued to investigate sites along the pipeline easement to confirm pipeline burial depth and to address actions arising from the 2008 Pipeline Safety Management Study Review.

SEA Gas continues to work with developers to ensure that proposed developments along the pipeline system are designed to ensure continued safe operation. Several safety management studies were carried out throughout the course of the year.

SEA Gas continues to implement risk management strategies to minimise the threat to public safety and the continued safe operation of the pipeline posed by unauthorised activities by third parties. Educational and awareness programs for third party activity along the pipeline easement remain a high priority. Where practicable, educational and pipeline safety awareness programs are offered in conjunction with other asset operators.

Pipeline Awareness activities included:

Aerial and ground surveillance throughout the pipeline system;

Security patrols and electronic surveillance;

Permit to Work System, Job Safety Analysis & Safety Induction Systems;

Easement Activity Authorisation processes;

Pipeline and Safety Awareness programmes;

Planning and Development around Pipelines seminars;

Safety advertisement in community publications;

Monitoring of land-ownership and land-use changes;

Responding to Development applications via DMITRE;

Emergency stakeholder consultation programme;

Participation in State and Commonwealth forums for threat management;

Participation in pipeline industry operations forums;

Subscription to the 1100 ‘Dial Before You Dig and Dig Safe (internet based) asset information and referral systems.

9.0 PROPOSED OPERATIONAL ACTIVITIES 2012 - 2013 LICENCE YEAR

In accordance with Regulation 33(2)(h), SEA Gas proposes to conduct the following operational activities during the 2012 / 2013 licence year:

Scheduled maintenance of pipeline facilities and infrastructure;

Monitoring of cathodic protection systems including testing of buried corrosion resistance coupons.

Continued upgrade of existing signage (Warning to Danger) along the easement between Williamstown and Coomandook to reflect recent changes to AS 2885.

Environmental improvements and monitoring along the pipeline system.

Field audit of all environmental rehabilitation sites along the pipeline easement in conjunction with DMITRE Petroleum and Geothermal Group representatives.

Scheduled aerial and ground patrols of the pipeline easement.

Page 12: South East Australia Gas Pty Ltd - Department of State ...petroleum.statedevelopment.sa.gov.au/__data/assets/... · Annual Report (PL13) – Port Campbell to Adelaide Pipeline 2011

Annual Report (PL13) – Port Campbell to Adelaide Pipeline

2011 – 2012 Licence Year

Page 12

Pipeline awareness seminars and emergency response training for emergency services, utilities and safety critical stakeholders.

Direct Current Voltage Gradient Survey to assess pipeline coating integrity along the entire length of the SEA Gas pipeline system.

Coomandook compressor and exhaust collector refurbishment.

Rectification of easement subsidence and erosion.

Overhaul of Flow Control Valve at Torrens Island PRMS.

Replacement of insulation gasket on the inlet to the Naracoorte PRMS.

10.0 VOLUME OF REGULATED SUBSTANCE TRANSPORTED

In accordance with Regulation 33(2)(k), the volume of regulated substance (i.e. natural gas) transported by SEA Gas during the course of the 2011/2012 licence year was approximately 54.7 PJ (exclusive of gas deliveries into the SESA pipeline system).

11.0 STATEMENT OF ANNUAL EXPENDITURE

In accordance with Regulation 33(3)(a)-(f), information relating to SEA Gas’ expenditure is provided as “Commercial In Confidence” in accordance with sub-regulation 33(5) of the Petroleum and Geothermal Energy Regulations 2000, where public disclosure is not required in accordance with sub-regulation 33(3).

A statement of expenditure is detailed at Appendix C (Restricted Distribution) and is attached under separate cover.

Page 13: South East Australia Gas Pty Ltd - Department of State ...petroleum.statedevelopment.sa.gov.au/__data/assets/... · Annual Report (PL13) – Port Campbell to Adelaide Pipeline 2011

Annual Report ( PL13 ) – Port Campbell to Adelaide Pipeline (PCA)

2011 – 2012 Licence Year

Page 13

APPENDIX A – ASSESSMENT OF COMPLIANCE AGAINST SEO OBJECTIVES

Statement of Environmental Objectives - Operational Environmental Objectives & Compliance Outcomes

Environmental Aspect

Potential Impacts SEO Objective Compliance Outcomes

Soils and Terrain Erosion and sedimentation

Soil inversion

Soil compaction

Soil contamination

Disturbance to significant geological features

Trench subsidence

11. To maintain soil stability along the easement

No un-remediated soil erosion or subsidence along the pipeline easement

No subsidence was observed during the licence year;

Soil erosion was rectified along a section of easement passing through the Cheetham Salt fields.

Pipeline operations do not enhance soil erosion on the easement

Pipeline operations did not contribute to soil erosion during the licence year.

Vegetative cover is consistent with surrounding land.

Pipeline operations enhanced vegetative cover over the easement as a result of revegetation activities.

No evidence of sub-soil in surface

Sub-soil was not deposited along the easement during the licence year. Intelligent pigging excavation sites were restored, to ensure that topsoil and sub-soil were segregated and returned to their original profile during reinstatement.

No visual evidence of soil compaction

There was neither observed evidence of soil compaction, nor any related complaints during the licence year.

No evidence of likely acid sulphate soil exposure

There are no known acid sulphate soil sites along the pipeline route.

Page 14: South East Australia Gas Pty Ltd - Department of State ...petroleum.statedevelopment.sa.gov.au/__data/assets/... · Annual Report (PL13) – Port Campbell to Adelaide Pipeline 2011

Annual Report ( PL13 ) – Port Campbell to Adelaide Pipeline (PCA)

2011 – 2012 Licence Year

Page 14

Environmental Aspect

Potential Impacts SEO Objective Compliance Outcomes

Surface contours along the easement are consistent with adjoining land

There were no modifications to surface contours carried out along the pipeline easement during the licence year.

Alternation of surface contours are initiated in consultation with stakeholders

There were no modifications to surface contours carried out along the pipeline easement during the licence year.

Water Resources Contamination of groundwater

Disruption to surface drainage patterns

Disruption to third party use of surface waters

12. To minimize and manage impacts to water resources

Drainage along the easement is maintained to pre-existing conditions or better

Surface drainage profiles are restored following maintenance activities.

No reasonable complaints received from Stakeholders in relation to use of surface waters

During the course of the licence year, operational activities did not impact upon groundwater quality.

No complaints were received in relation to any environmental impacts during the licence year.

Previously completed rehabilitation along the easement, including re-vegetation of riparian zones and installation of sedimentation traps, has generally resulted in improved water quality.

Land and Water Emissions

Land and water contamination

Disruption to third party use of surface waters

13. To effectively manage spill prevention and to respond to spill events to minimize their impact

No spills or leaks in other than areas designated to contain spills

During the course of the licence year there were two minor spill incidents, during a scheduled vessel inspection.

No waste on easement, at other than designated storage areas within facilities,

Page 15: South East Australia Gas Pty Ltd - Department of State ...petroleum.statedevelopment.sa.gov.au/__data/assets/... · Annual Report (PL13) – Port Campbell to Adelaide Pipeline 2011

Annual Report ( PL13 ) – Port Campbell to Adelaide Pipeline (PCA)

2011 – 2012 Licence Year

Page 15

Environmental Aspect

Potential Impacts SEO Objective Compliance Outcomes

pending disposal

Waste is disposed of in accordance with approved protocols

Operational waste is not stored on the easement and is temporarily stored within designated areas at facilities prior to collection by licensed waste collection providers.

SEA Gas implemented recycling initiative during the licence year to reduce waste to landfill.

Wastewater meets appropriate ANZECC criteria at point of discharge and is disposed onto land, well away from any place from which it is reasonably likely to enter any waters

No evidence of impacts to soils, water and vegetation as a result of water disposal

Waste water complies with the requirements of Public and Environmental Health (Waste Control) Regulations 1995

There were no wastewater discharges during the course of the licence year.

During dewatering of an intelligent pigging excavation site turbid groundwater and silt was deposited onto the area surrounding the excavation.

Vegetation and Fauna Removal of remnant vegetation

Spread of ecological

14. To promote and maintain regrowth of vegetation along the easement, consistent with the

Species abundance and vegetative cover along the easement to be as near as practicable to adjoining areas in accordance with site specific management criteria

Page 16: South East Australia Gas Pty Ltd - Department of State ...petroleum.statedevelopment.sa.gov.au/__data/assets/... · Annual Report (PL13) – Port Campbell to Adelaide Pipeline 2011

Annual Report ( PL13 ) – Port Campbell to Adelaide Pipeline (PCA)

2011 – 2012 Licence Year

Page 16

Environmental Aspect

Potential Impacts SEO Objective Compliance Outcomes

weeds

Spread of pathogens

surrounding area, ensuring that line if sight between pipeline marker posts is maintained

Revegetation activities completed during the licence year enhanced species abundance and biodiversity along the easement.

No reasonable complaints received from landholders or third party users in relation to adverse impacts to vegetation, native fauna or livestock

No complaints were received during the licence year.

Trimming of native vegetation to be restricted to the minimum necessary to ensure line of sight between pipeline marker posts

Vegetation trimming was restricted to line of sight maintenance along the pipeline easement.

Vegetation management within the easement or on adjacent land to the easement is limited to previously disturbed areas unless regulatory approval has been obtained

Vegetation management has continued to be consistent with stated rehabilitation guidelines, which were audited by a representative from the DMITRE - Petroleum and Geothermal Energy Group during the 2010/2011 licence year.

Clearing (other than originally approved) of remnant vegetation to be avoided unless approved.

Vegetation clearing was restricted to woody weeds (Olives) along a section of the easement near the Williamstown Main Line Valve and contributed towards the establishment of native vegetation.

Native fauna, flora and livestock impacts associated with maintenance activities to be restricted to As Low As Reasonably Practicable.

There were no observed impacts during the licence year.

Page 17: South East Australia Gas Pty Ltd - Department of State ...petroleum.statedevelopment.sa.gov.au/__data/assets/... · Annual Report (PL13) – Port Campbell to Adelaide Pipeline 2011

Annual Report ( PL13 ) – Port Campbell to Adelaide Pipeline (PCA)

2011 – 2012 Licence Year

Page 17

Environmental Aspect

Potential Impacts SEO Objective Compliance Outcomes

Weeds and Pathogens Spread of noxious weeds and pathogens

15. To prevent the introduction and spread of weeds and pathogens

Presence of weeds and pathogens on the easement is consistent with or better than adjoining land

During the licence year extensive weed management strategies were implemented along the easement, inclusive of woody weed removal to ensure the maintenance of line of sight between marker posts. Rabbit control was implemented at four revegetation sites.

No new outbreaks or spread of weeds or pathogens

No new outbreaks of weeds were observed during the licence year. Weed management during the course of site restoration has reduced the prevalence of weeds along the pipeline easement.

No reasonable complaints received from landholders in relation to outbreaks or spread of weeds or pathogens

No complaints were received during the licence year.

Maintenance records, facility inspections and audits

Internal and external audits were conducted, inclusive of a field audit of revegetation sites along the pipeline easement.

Cultural and Historic Heritage

Damage to shallow artefact scatters

Damage to significant vegetation (for example scarred trees)

Disturbance to smaller scattered items occurring

16. To adequately protect heritage and culturally sensitive sites and values during operational activities

No impact to identified sites without prior approval in accordance with applicable legislative requirements

There were no impacts to any cultural heritage sites as a result of intelligent pigging excavations or pipeline operations.

Newly identified sites are reported and managed appropriately

No new cultural heritage sites were identified during the licence year.

Page 18: South East Australia Gas Pty Ltd - Department of State ...petroleum.statedevelopment.sa.gov.au/__data/assets/... · Annual Report (PL13) – Port Campbell to Adelaide Pipeline 2011

Annual Report ( PL13 ) – Port Campbell to Adelaide Pipeline (PCA)

2011 – 2012 Licence Year

Page 18

Environmental Aspect

Potential Impacts SEO Objective Compliance Outcomes

on or immediately below the land surface as a result of earthworks

Noise Emissions Generated operations noise may disturb people, stock and wildlife in the immediate area

17. To minimise noise impacts that may arise from operational activities

Compliance with EPA noise abatement guidelines

Operational activities continued to comply with noise abatement guidelines during the licence year.

There were no operational activities that impacted upon Red-tailed Black Cockatoo breeding habitat during the licence year.

No reasonable complaints received in relation to noise abatement issues

No complaints were received during the licence year.

Atmospheric Emissions Generation of dust from the easement and access tracks

Minor reduction in air quality resulting from vehicle emissions

Release of Greenhouse Gas Emissions from Compressor Station

18. To minimise atmospheric emissions

No uncontrolled atmospheric emissions.

There were no uncontrolled atmospheric emissions in an area not specifically designed to contain a gas escape.

SEA Gas has implemented voluntary reporting of Scope 1 and Scope 2 Greenhouse Gas Emissions.

No reasonable complaints received in relation to dust management issues

No complaints were received during the licence year.

Page 19: South East Australia Gas Pty Ltd - Department of State ...petroleum.statedevelopment.sa.gov.au/__data/assets/... · Annual Report (PL13) – Port Campbell to Adelaide Pipeline 2011

Annual Report ( PL13 ) – Port Campbell to Adelaide Pipeline (PCA)

2011 – 2012 Licence Year

Page 19

Environmental Aspect

Potential Impacts SEO Objective Compliance Outcomes

Disturbance to third party infrastructure, landholders and modified land use

Adverse effects to agricultural productivity or other primary production activities in long term

Disruption to important land use periods (that is, calving, lambing, breeding, sowing, harvesting or recreation)

Spread of noxious weeds and diseases

Disruption to conservation, recreational, industrial or other third party land use activities

Disruption or damage to roads and other transport infrastructure or networks

Disruption or damage to utility services

Disruption or damage to private infrastructure

19. To minimise disturbance to third party infrastructure, landholders and land use

Where disturbance is unavoidable or accidental, infrastructure or land use is restored to as near as practicable to the satisfaction of stakeholders

There was no disturbance to any third party activities during the licence year.

No disturbance outside the easement or approved access and work areas without prior consultation.

In consultation with landholders, maintenance activities were restricted to agreed sections of the pipeline easement and within facility boundaries.

Duration of disturbance does not exceed agreed timeframes without prior consultation.

In consultation with landholders, maintenance activities did not exceed agreed timeframes.

No reasonable complaints received in relation to disturbance

No complaints were received during the licence year.

Pre-existing land use not restricted or impeded as a result of maintenance activities unless by prior arrangement

Pre-existing land use was not restricted or impeded as a result of operation and maintenance activities.

No unauthorized disturbance to third party utilities or infrastructure

Pipeline operations and maintenance activities did not result in any disturbance to third party utilities or infrastructure during the licence year.

No reasonable complaints received in relation to unauthorized disturbance of third party utilities or infrastructure

Page 20: South East Australia Gas Pty Ltd - Department of State ...petroleum.statedevelopment.sa.gov.au/__data/assets/... · Annual Report (PL13) – Port Campbell to Adelaide Pipeline 2011

Annual Report ( PL13 ) – Port Campbell to Adelaide Pipeline (PCA)

2011 – 2012 Licence Year

Page 20

Environmental Aspect

Potential Impacts SEO Objective Compliance Outcomes

No complaints were received during the licence year.

Vegetation cover along the easement to be as near as practicable to adjoining areas in consultation with stakeholders

As a result of environmental restoration activities in consultation with affected stakeholders, vegetation cover along the easement exceeds that of the adjoining areas.

Risk to public health and safety

A threat to the pipeline can be assumed to include any element which can potentially cause pipeline failure, including threats due to location (including crossing and land use segments) and general threats common to the entire system (for example, corrosion)

20. To minimise the risk to public health and safety

No injuries or incidents involving members of the public

There were no injuries or incidents involving members of the public during the course of the licence year.

No fires as a consequence of maintenance activities

Operations and maintenance activities did not result in any fires during the licence year.

No unauthorized activity on the easement that has the potential to impact on integrity

Two unauthorized incidents were observed during the course of the licence year (Ref. Appendix B).

Emergency response and crisis management tools applied to mitigate emergency management risks; and to minimise likely incident impacts

Emergency response and crisis management tools were applied operationally during the licence year during scheduled emergency response exercises (Ref. Section 2.7).

Effective management of emergency incidents

Page 21: South East Australia Gas Pty Ltd - Department of State ...petroleum.statedevelopment.sa.gov.au/__data/assets/... · Annual Report (PL13) – Port Campbell to Adelaide Pipeline 2011

Annual Report ( PL13 ) – Port Campbell to Adelaide Pipeline (PCA)

2011 – 2012 Licence Year

Page 21

Environmental Aspect

Potential Impacts SEO Objective Compliance Outcomes

There were no incidents which required activation of the SEA Gas Emergency Response Plan during the licence year.

Page 22: South East Australia Gas Pty Ltd - Department of State ...petroleum.statedevelopment.sa.gov.au/__data/assets/... · Annual Report (PL13) – Port Campbell to Adelaide Pipeline 2011

Annual Report ( PL13 ) – Port Campbell to Adelaide Pipeline (PCA)

2011 – 2012 Licence Year

Page 22

APPENDIX B – REPORTABLE INCIDENTS DURING THE LICENCE YEAR

Incident Date &

Reference No.

KP

(approx.)

DMITRE Incident Classification

Root Causes Corrective Actions Status

August

2011

#8204

501 Induction/Training Incident Description: During excavation of an intelligent pigging defect, dewatering of the trench resulted in the deposition of turbid groundwater and silt, onto the area adjacent to the excavation.

Dewatering of the excavation was not conducted in accordance with the SEA Gas, Statement of Environmental Objectives.

Approximately two kilograms of silt was collected and disposed of with excess spoil, during reinstatement of the excavation site.

SEA Gas is in the process of delivering Statement of Environmental Objective training to employees and contractors.

SEA Gas has updated its excavation procedure to include an appropriate method for capturing silt when dewatering a trench.

Closed

October

2011

#3282

#9334

387 Work Practices Incident Description: Unauthorised fencing across the pipeline easement and an unauthorised gate and post installation on another nearby section of the pipeline easement, that had resulted in removal of a pipeline marker sign.

Safe Work practices for excavation on the pipeline easement were not followed. The property owners and manager were aware of the pipeline location; however neither the property owners, nor the property manager, requested a Dial Before You Dig asset referral. SEA Gas was also not consulted prior to the excavation on the pipeline easement or the relocation of the marker post.

Written advice was provided to the three joint owners of the property, reinforcing the need to seek approval prior to commencing activities on the pipeline easement which involve excavation to a depth greater than 300mm.

SEA Gas offered to provide the property owners and property manager a pipeline awareness session.

The resident owner and property manager were re-briefed regarding activities on the pipeline easement which require approval from SEA Gas prior to commencement. The briefing also highlighted activities on the pipeline easement, which have the potential

Closed

Page 23: South East Australia Gas Pty Ltd - Department of State ...petroleum.statedevelopment.sa.gov.au/__data/assets/... · Annual Report (PL13) – Port Campbell to Adelaide Pipeline 2011

Annual Report ( PL13 ) – Port Campbell to Adelaide Pipeline (PCA)

2011 – 2012 Licence Year

Page 23

Incident Date &

Reference No.

KP

(approx.)

DMITRE Incident Classification

Root Causes Corrective Actions Status

to compromise safe operations.

A site inspection by SEA Gas representatives confirmed that the pipeline and its protective coating had not been damaged during the installation of the fencing or strainer posts.

The pipeline marker sign was re-installed in a position on the pipeline alignment.

October

2011

#3283

538 Work Practices Incident Description: Unauthorised trenching of a polyethylene water pipeline across the pipeline easement, to a depth of 500mm by a third party contractor.

When requesting a Dial Before You Dig (DBYD) asset referral, the pipeline contractor entered the incorrect location for the proposed work site. The SEA Gas pipeline was not in the identified work area.

Prior to commencing work, the pipeline contractor did not take note of the pipeline marker signage in the near vicinity of the work area, relying solely on the information received as a result of the Dial Before You Dig request.

The property owner and the contractor were briefed regarding activities on the pipeline easement which require approval from SEA Gas prior to commencement. The briefing also highlighted activities on the pipeline easement, which have the potential to compromise safe operations.

SEA Gas instructed the contractor on how to identify a work site correctly in the DBYD system.

A site inspection by SEA Gas representatives confirmed that the pipeline and its protective coating had not been damaged during the installation of the polyethylene pipeline.

Closed

June

2012

682 Risk Management Incident Description: During the removal of the process coils from the water bath heaters at the Pelican Point

SEA Gas is currently investigating the incident and is awaiting a chemical analysis to

Under Investigation

Page 24: South East Australia Gas Pty Ltd - Department of State ...petroleum.statedevelopment.sa.gov.au/__data/assets/... · Annual Report (PL13) – Port Campbell to Adelaide Pipeline 2011

Annual Report ( PL13 ) – Port Campbell to Adelaide Pipeline (PCA)

2011 – 2012 Licence Year

Page 24

Incident Date &

Reference No.

KP

(approx.)

DMITRE Incident Classification

Root Causes Corrective Actions Status

#3256 and Torrens Island PRMS facilities, the accumulated product on the exterior of the coils dried, blowing off as a black powder and falling to the ground. Some of the powder fell on sections of the ground which had not been covered and was unable to be collected.

The risk of loose product being on the process tubes at the time of removal was not anticipated.

determine the properties of the black powder, so the appropriate course of action can be determined.

June

2012

#3257

685 Work Practices Incident Description: Water bath heaters were refilled with water containing corrosion inhibitor solution following inspection and repair of the internal fire tubes. As the heater reached its operating temperature of 55°C, the water expanded and subsequently overflowed, discharging into a bunded collection drum and onto the ground beneath each heater.

There is no written procedure for re-filling ‘cold’ water bath heaters following process tube removal.

Not all water bath heater vent points enable the capture of corrosion inhibitor solution overflow.

Develop a procedure for water bath heater corrosion inhibitor solution management and train maintenance personnel in its use.

Review adequacy of overflow capture and containment.

Under Investigation

Page 25: South East Australia Gas Pty Ltd - Department of State ...petroleum.statedevelopment.sa.gov.au/__data/assets/... · Annual Report (PL13) – Port Campbell to Adelaide Pipeline 2011

Annual Report ( PL13 ) – Port Campbell to Adelaide Pipeline (PCA)

2011 – 2012 Licence Year

Page 25

APPENDIX C – STATEMENT OF ANNUAL EXPENDITURE

Distribution of the Statement of Annual Expenditure is limited to the Petroleum and Geothermal Energy Group, Primary Industries and Resources, South Australia, in accordance with Regulation 33(3)(a)-(f).

Information relating to SEA Gas expenditure is provided as “Commercial in Confidence” in accordance with sub regulation 33(5) of the Petroleum and Geothermal Energy Regulations 2000, where public disclosure is not required in accordance with sub regulation 33(3).

Page 26: South East Australia Gas Pty Ltd - Department of State ...petroleum.statedevelopment.sa.gov.au/__data/assets/... · Annual Report (PL13) – Port Campbell to Adelaide Pipeline 2011

Annual Report ( PL13 ) – Port Campbell to Adelaide Pipeline (PCA)

2011 – 2012 Licence Year

Page 26

APPENDIX D – EASEMENT REHABILITATION SUMMARY

SEA Gas continued to conduct environmental maintenance activities along the pipeline system, including:

weed and line of sight management (to ensure unobstructed view of above ground marker posts along the easement).

attrition and additional planting along the pipeline easement to minimise exposure to erosion events.

maintenance of rabbit control fencing and rabbit control measures at revegetation sites.

An overview of Sustainable Environmental Benefit (SEB) activities conducted within South Australian during the course of the licence year is detailed below:

Sustainable Environmental Benefit (SEB) Projects

In accordance with its post construction environmental obligations the following Native Vegetation Council approved, Sustainable Environmental Benefit projects continue to be managed by designated stakeholders, following financial assistance provided by SEA Gas:

Site Description Revegetation Overview Status

Yallamurray Road, Yallamurray (KP 347)

Roadside revegetation following open excavation pipeline crossing.

Completed

Cramers Road, Willalooka (KP 354) Roadside revegetation following open excavation pipeline crossing.

Additional Muntries (Kunzea pomifera) planted during 2012 following attrition.

Rowney Road, Willalooka (KP 357) Roadside revegetation following open excavation pipeline crossing.

Completed

Coonalpyn-Field Road, Coonalpyn (KP 456)

Roadside revegetation following open excavation pipeline crossing.

Completed

Butlers Road, (KP 470) Roadside revegetation following open excavation pipeline crossing.

Completed

Frost Road (KP 477) Roadside revegetation following open excavation pipeline crossing.

Completed

Yumali Road. Ki Ki (KP479) Roadside revegetation following open excavation pipeline crossing.

Completed

Ki Ki SEB Revegetation Site (Off Easement)

Off Easement Sustainable Environmental Benefit (SEB) revegatation site

Completed

Wilkin Road, Murray Bridge (KP 554) Roadside revegetation following clearing during construction.

Completed

Pallamana Main Line Valve (KP 555) Revegetation following clearance during construction.

Completed

Southern embankment of Salt Creek (KP 560)

Revegetation following natural site erosion.

Completed

Page 27: South East Australia Gas Pty Ltd - Department of State ...petroleum.statedevelopment.sa.gov.au/__data/assets/... · Annual Report (PL13) – Port Campbell to Adelaide Pipeline 2011

Annual Report ( PL13 ) – Port Campbell to Adelaide Pipeline (PCA)

2011 – 2012 Licence Year

Page 27

Site Description Revegetation Overview Status

Private property along Palmer –Cooke Hill Road (KP 586)

Revegetation following natural site erosion.

Completed

Lucas Back Road, Mount Pleasant (KP 594)

Roadside revegetation following open excavation pipeline crossing.

Completed

Fulwoods Road, Mount Pleasant (KP 597)

Roadside revegetation following open excavation pipeline crossing.

Completed

Potts Road, Gawler (KP 631 Roadside revegetation following open excavation pipeline crossing.

Completed

Torrens Island (KP 683) Roadside revegetation following open excavation pipeline crossing.

Completed

Mount Monster Conservation Park Allotment Acquisition

As a result of SEA Gas’ sponsorship, acquisition of this land parcel was concluded during August 2007.

Mosquito Creek Restoration, Naracoorte Caves Conservation Park

In response to SEA Gas’ sponsorship, this site continues to be rehabilitated by the ‘Friends of the Naracoorte Caves’, under the auspices of the park manager.

Pooginagoric Tea Trick Road Reserve Revegetation

Attrition planting and site management (i.e. removal of tree guards on mature species and weed management) was initiated at this site during the licence year by the Department for Environment and Heritage.

SEA Gas has assisted with the installation of an interpretive sign at this site and sponsored weed management at this site during the 2011/2012 licence year.

Para Woodland Rehabilitation, Gawler

Rehabilitation at this site continues under the auspices of the South Para Woodland Park Manager and the Nature Foundation.

Ki-Ki Revegetation Project

A site inspection during the licence year confirmed continued healthy growths to establish and provide an environmental link with remnant roadside vegetation, to enhance the biodiversity offered by this project.

Page 28: South East Australia Gas Pty Ltd - Department of State ...petroleum.statedevelopment.sa.gov.au/__data/assets/... · Annual Report (PL13) – Port Campbell to Adelaide Pipeline 2011

Annual Report ( PL13 ) – Port Campbell to Adelaide Pipeline (PCA)

2011 – 2012 Licence Year

Page 28

APPENDIX E - Reports Generated by the Licensee during the Reporting Year

In accordance with sub-regulation 33(2)(e) of the Petroleum and Geothermal Energy Regulations (SA) 2000, the following reports were generated by the licensee, during the license year.

These reports relate to the operation of the PCA in accordance with the Petroleum and Geothermal Energy Act (SA) 2000.

Report Title Issued By Date Issued

Annual Report (PL13) – 2010/2011 Licence Year SEA Gas August 2011

Fitness for Purpose Report SEA Gas April 2012

April – June 2011 Quarterly Report SEA Gas July 2011

July – September 2011 Quarterly Report SEA Gas October 2011

October – December 2011 Quarterly Report SEA Gas January 2012

January – March 2012 Quarterly Report SEA Gas April 2012

Exercise Broadview Report SEA Gas October 2011

Exercise Vulcan Report SEA Gas June 2012

MAOP Review SEA Gas April 2012

Almond Grove Development – Safety Management Study

SEA Gas September 2011

Gifford Hill Racecourse Development – Safety Management Study

SEA Gas October 2011

Grand Trunkway Industrial Estate - Safety Management Study

SEA Gas December 2011

AS2885.1:2007 – Location and Sub-Location Class Review, SEA Gas Pipeline

SEA Gas February 2012

SEA Gas Pipeline (Coomandook to Pelican Point) 450mm MagneScan Inspection Results

SEA Gas August 2011

Pipeline Excavations 2011 - In-Line Inspection Results Validation

SEA Gas September 2011

In-Line Inspection Dig-Up Report (Coomandook to Pelican Point)

SEA Gas January 2012

Cathodic Protection (CP) Survey APA Group (Vic) October 2011