Page 1: South San Francisco Station Improvement Projectand+Minutes/JPB/2018/... · 2018-09-06 · South San Francisco Station Improvement Project September 2018 Board meeting . 2 Overview

South San Francisco Station Improvement

Project

September 2018 Board meeting

Page 2: South San Francisco Station Improvement Projectand+Minutes/JPB/2018/... · 2018-09-06 · South San Francisco Station Improvement Project September 2018 Board meeting . 2 Overview

2

Overview • Project Need • Project Scope and Purpose • Project Challenges • Next Steps

Page 3: South San Francisco Station Improvement Projectand+Minutes/JPB/2018/... · 2018-09-06 · South San Francisco Station Improvement Project September 2018 Board meeting . 2 Overview

Project Purpose Why does existing station need to be replaced? • Improve system operations (Remove Hold Out

Rule) • Improve station access • Connect west and east sides of South San

Francisco

3

Page 4: South San Francisco Station Improvement Projectand+Minutes/JPB/2018/... · 2018-09-06 · South San Francisco Station Improvement Project September 2018 Board meeting . 2 Overview

4

Existing Station

Page 5: South San Francisco Station Improvement Projectand+Minutes/JPB/2018/... · 2018-09-06 · South San Francisco Station Improvement Project September 2018 Board meeting . 2 Overview

Project Scope

5

Page 6: South San Francisco Station Improvement Projectand+Minutes/JPB/2018/... · 2018-09-06 · South San Francisco Station Improvement Project September 2018 Board meeting . 2 Overview

Project Scope • Construct new center platform • Remove and relocate utilities to allow for construction of new

pedestrian underpass

• Construct new Downtown Plaza at Airport Boulevard and Grand Avenue

• Construct shuttle pick-up/drop-off area on Poletti Way

6

Page 7: South San Francisco Station Improvement Projectand+Minutes/JPB/2018/... · 2018-09-06 · South San Francisco Station Improvement Project September 2018 Board meeting . 2 Overview

Original Construction Contract Schedule and Budget • Contract advertised April 2017 to maintain PCEP Schedule • Contract awarded in August 2017 • Construction Contract = $32.2 million with 10% Contingency

• $1.5 mil on behalf of Electrification (OCS Foundations) • Construction began in January 2018 • Contract completion intended for June 2019

7

Page 8: South San Francisco Station Improvement Projectand+Minutes/JPB/2018/... · 2018-09-06 · South San Francisco Station Improvement Project September 2018 Board meeting . 2 Overview

8

Utility Relocation Work

Red = Existing Utility; Same location as Underapss Green = Relocated Utility; Away from Underpass

Page 9: South San Francisco Station Improvement Projectand+Minutes/JPB/2018/... · 2018-09-06 · South San Francisco Station Improvement Project September 2018 Board meeting . 2 Overview

9

Project Challenges

• Portion of Work is adjacent to active rail yard, requiring increased coordination with both commuter and freight operators

• Utility Relocation and Station Construction cannot be done concurrently.

• Work activities need to be coordinated with Peninsula Electrification Project. Planned activities may need to be modified to allow activities to be done concurrently.

Page 10: South San Francisco Station Improvement Projectand+Minutes/JPB/2018/... · 2018-09-06 · South San Francisco Station Improvement Project September 2018 Board meeting . 2 Overview

10

Working Adjacent to Active Rail Yard

Page 11: South San Francisco Station Improvement Projectand+Minutes/JPB/2018/... · 2018-09-06 · South San Francisco Station Improvement Project September 2018 Board meeting . 2 Overview

11

Utility Relocation Work

• Three different utilities need relocation • Requires large temporary excavation support • Limits areas to stage and store materials

Page 12: South San Francisco Station Improvement Projectand+Minutes/JPB/2018/... · 2018-09-06 · South San Francisco Station Improvement Project September 2018 Board meeting . 2 Overview

12

Underpass Construction

• Precast box installation • Avoid activity during utility relocation and wet

season (Estimated Duration = 7mos)

Page 13: South San Francisco Station Improvement Projectand+Minutes/JPB/2018/... · 2018-09-06 · South San Francisco Station Improvement Project September 2018 Board meeting . 2 Overview

Renderings of Completed Station

13

Center Platform, Looking North

Page 14: South San Francisco Station Improvement Projectand+Minutes/JPB/2018/... · 2018-09-06 · South San Francisco Station Improvement Project September 2018 Board meeting . 2 Overview

14

Renderings of Completed Station

Downtown Plaza, Looking East

Page 15: South San Francisco Station Improvement Projectand+Minutes/JPB/2018/... · 2018-09-06 · South San Francisco Station Improvement Project September 2018 Board meeting . 2 Overview

15

Summary

• Request to increase Contract Authority by $3,403,000, making Total Contract Authority $38,798,555.

• Revised Contract End Date is August 2020.

• Project likely to return for more Budget Authority

• Suspension of Station Construction to allow Utility Relocation:

• Minimizes daily time related costs since Contractor will deploy resources to Tunnel 1 and 4 while Utilities are relocated.

• Retains key Contractor staff to complete Station Construction once Tunnel 1 and 4 project is complete.

• Maximizes work areas for utilities to perform relocation work.