south sudan - technical assistance for the development · pdf fileconcept note approval june...

35
AFRICAN DEVELOPMENT BANK GROUP PROJECT: TECHNICAL ASSISTANCE FOR THE DEVELOPMENT OF THE TRANSPORT SECTOR COUNTRY: REPUBLIC OF SOUTH SUDAN PROJECT APPRAISAL REPORT OITC DEPARTMENT November 2013

Upload: ngothien

Post on 12-Mar-2018

226 views

Category:

Documents


0 download

TRANSCRIPT

AFRICAN DEVELOPMENT BANK GROUP

PROJECT: TECHNICAL ASSISTANCE FOR THE DEVELOPMENT

OF THE TRANSPORT SECTOR

COUNTRY: REPUBLIC OF SOUTH SUDAN

PROJECT APPRAISAL REPORT

OITC DEPARTMENT

November 2013

TABLE OF CONTENTS

Currency Equivalents i

Fiscal Year i

Weights and Measures i

Acronyms and Abbreviations ii

Grant Information iii

Project Summary iv

Result-Based Logical Framework v

Project Timeframe vi

I. STRATEGIC THRUST & RATIONALE 1

1.1. Project Background ....................................................................................................... 1

1.2. Project Linkages with the Country Strategy and Objectives ......................................... 3

1.3. Rationale for the Bank Involvement .............................................................................. 4

1.4. Development Partners Coordination ............................................................................. 4

II. PROJECT DESCRIPTION 5

2.1. Project Objectives .......................................................................................................... 5

2.2. Project Components ....................................................................................................... 5

2.3. Technical Solution Retained and Alternatives Explored ............................................... 7

2.4. Project Type ................................................................................................................... 8

2.5. Project Cost and Financing Arrangements .................................................................... 8

2.6. Project’s Target Area and Population ............................................................................ 9

2.7. Participatory Process for Project Design and Implementation .................................... 10

2.8. Bank Group Experience, Lessons Reflected in Project Design .................................. 10

2.9. Key Performance Indicators ........................................................................................ 11

III. PROJECT FEASIBILITY 12

3.1. Economic and Financial Performance ......................................................................... 12

3.2. Environmental and Social Impacts .............................................................................. 12

IV. IMPLEMENTATION 13

4.1. Implementation Arrangements .................................................................................... 13

4.2. Monitoring ................................................................................................................... 15

4.3. Governance .................................................................................................................. 16

4.4. Sustainability ............................................................................................................... 17

4.5. Risk Management ........................................................................................................ 17

4.6. Knowledge Building .................................................................................................... 18

V. LEGAL INSTRUMENTS AND AUTHORITY 19

5.1. Legal Instrument .......................................................................................................... 19

5.2. Compliance with Bank Policies ................................................................................... 20

VI. RECOMMENDATION 20

Appendix I. Country’s comparative socio-economic indicators

Appendix II. ADB’s Portfolio in South Sudan

Appendix III. Transport projects financed/planned to be financed by other DPs

Appendix IV. Profile of the Implementing Agency, Project Management Unit (PMT)

Appendix IV. Map of the Project Area

i

Currency Equivalents As of July 2013

Currency Unit = South Sudanese Pound (SSP)

UA 1.0 = SSP 4.93472

UA 1.0 = US$ 1.50396

US$ 1.0 = SSP 3.281151

Fiscal Year

01 July – 30 June

Weights and Measures

1metric tonne = 2,204 pounds (lbs)

1 kilogramme (kg) = 2.200 lbs

1 metre (m) = 3.28 feet (ft)

1 millimetre (mm) = 0.03937 inch (“)

1 kilometre (km) = 0.62 mile

1 hectare (ha) = 2.471 acres

ii

Acronyms and Abbreviations

ADB African Development Bank

ADF African Development Fund

DFID Department for International Development

DPs Development Partners

EU The European Union

FRSC Feeder Roads Steering Committee

FSF Fragile State Facility

GDP Gross Domestic Product

GIZ Deutsche Gesellschaft für Internationale Zusammenarbeit

GRSS The Government of the Republic of South Sudan

HRDP Human Resource Development Programme

IAP Infrastructure Action Plan

ICAO International Civil Aviation Organization

iCSP Interim Country Strategy Paper

IGAD Intergovernmental Authority on Development

INA Infrastructure Needs Assessment

IWG Infrastructure Working Group

JIA Juba International Airport

JICA Japan International Cooperation Agency

KFW Kreditanstalt für Wiederaufbau

MoAF Ministry of Agriculture

MoAFTARF Ministry of Agriculture, Forestry, Tourism, Animal Resources and Fisheries

MoEDIWR Ministry of Electricity, Dams, Irrigation, and Water Resources

MoFCEP Ministry of Finance, Commerce and Economic Planning

MoFEP Ministry of Finance and Economic Planning

MoRB Ministry of Roads and Bridges

MoTR Ministry of Transport and Roads

MoTRB Ministry of Transport, Roads and Bridges

MoT Ministry of Transport

MoWNR The Ministry of Water and Natural Resources

MTCDS Medium-Term Capacity Development Strategy

NTMP National Transport Master Plan

OITC Transport and ICT Department

PC Project Coordinator

PCR Project Completion Report

PFM Public Financial Management

PMT Project Management Team

RAP Resettlement Action Plan

RSS The Republic of South Sudan

SPMIC Strengthening Project Management & Implementation Capacity

SSAC South Sudan Audit Chamber

SSCAA South Sudan Civil Aviation Authority

SSDI South Sudan Development Initiative

SSDP South Sudan Development Plan

SSRA South Sudan Roads Authority

TNA Training Need Assessment

UA Units of Account

UNOPS United Nations Office for Project Services

USAID United States Agency for International Development

USD United States Dollar

WB World Bank

iii

Grant Information

Recipient’s information

RECIPIENT: The Republic of South Sudan

EXECUTING AGENCY: Ministry of Transport, Roads and Bridges

Financing plan

Source Amount (UA) Instrument

FSF 6.93 million Grant

TOTAL COST 6.93 million

ADB’s key financing information

Grant currency

UA

Interest type N/A

Interest rate spread N/A

Commitment fee N/A

Other fees N/A

Tenor N/A

Grace period N/A

FIRR, NPV (base case) N/A

EIRR (base case) N/A

Timeframe - Main Milestones (expected)

Concept Note approval

June 2013

Project approval November 2013

Grant Signing December 2013

Launching March 2014

Effectiveness March 2014

Project Completion Report November 2017

Last Disbursement December 2017

iv

Project Summary

Project Overview: The proposed Technical Assistance for the Development of the Transport

Sector Project is designed within the context of the South Sudan Development Plan (SSDP)

priorities and in support of the development of the Transport sector. The project comprises: (i)

human resource development; (ii) studies which include National Transport Master Plan

(NTMP) study, river transport study, road study and economic diversification study; and (iii)

strengthening project management and implementation capacity. The total cost of the project

amounts to UA 6.93 million. The project will be financed by the Bank using the Fragile Sate

Facility (FSF), Pillar I Grant. The project will contribute to building institutional and human

capacity and provide a comprehensive transport master plan, prioritized interventions to improve

the river transport, analytical knowledge to diversify the economy and prepare a pipeline road

project. The outcome of the intervention will provide the basis for the sustainable development

of the transport sector to stimulate economic growth and diversification, reduce poverty, and

improve good governance and security. The project will be implemented over a four year period.

Project direct beneficiaries: The intervention will benefit the transport sector, the people of

South Sudan and many other users of improved transport infrastructure and services in South

Sudan. The river transport study in particular will contribute to improve river transport (more

than 1300 km) which will enhance connectivity along the White Nile River corridor and links

the country with Sudan and Ethiopia. The improvement is expected to benefit about 3 million

people, which is about 27% of the total population. Moreover, the road study is a preparation for

a pipeline road project which aims at unlocking the potential agricultural land for commercial

farming and benefiting about 500,000 people in the zone of influence.

Needs Assessment: The Republic of South Sudan (RSS) is facing critical challenges of nation

building as a result of weak formal institutions, acute shortage of qualified human resources and

over dependence on oil for growth. The previous Bank support, the Infrastructure Needs

Assessment (INA) and Infrastructure Action Plan (IAP), identified critical gaps for immediate

interventions and showed directions for the development of the infrastructure sector which is an

enabler for economic growth and diversification. Among the short-term interventions proposed

by the IAP which is consistent with the SSDP, include institutional and human resource

development and studies to develop a prioritized investment plan which will inform and guide

the development of the transport sector. The proposed project is designed in response to the

request from the Government of the Republic of South Sudan (GRSS) and is in line with the IAP

to develop comprehensive framework that contributes to the development of institutional and

human capacity, and the transport sector in South Sudan.

Bank’s Added Value: The proposed project is the first Bank operation in the transport sector

which is dedicated to build institutional and human capacity and provide comprehensive

framework to guide and rollout the development of the transport sector. The intervention will

provide the basis for organizing efforts and leveraging resources from the Government, the Bank

and other Development Partners towards the sustainable development of the sector. The support

is a continuation of the Bank’s engagement to lead the development of transport infrastructure

and services in South Sudan.

Knowledge Management: The proposed project will generate and transfer knowledge in the

transport sector under fragile and post-conflict setting. The project will support the acquisition

of knowledge in the areas of institutional and human capacity and transport planning which are

critically missing and yet are key requirements to deliver the huge demand for the development

of the transport sector. The project will also generate analytical knowledge for economic

diversification. The Bank will capture and disseminate the knowledge generated through

monitoring and evaluation, midterm reviews, and project study and completion reports.

v

Result-Based Logical Framework Country and project name: The Republic of South Sudan – Technical Assistance for the Development of the Transport Sector Project

Purpose of the project : to support GRSS to build human and institutional capacity and devise a strategic framework for the development of the transport sector

RESULTS CHAIN PERFORMANCE INDICATORS MEANS OF

VERIFICATION RISKS/MITIGATION MEASURES

Indicator (including CSI) Baseline Target

IMP

AC

T

Contribute to socio-economic development and

poverty reduction through improved and

sustainable transport system

Economic growth

Level of poverty

[2012]:

Contracted

by 53%;

50.6%

[2025]:

7%

30%

National Statistical

data; National Bank;

MoFCEP Reports

OU

TC

OM

ES

Improved human and institutional capacity

Improved strategy and investment plan for the

sustainable development of the transport sector

Increased analytical knowledge on constraints,

critical sectors, options, and sequencing of

interventions for economic diversification for

policy makers

Human and institutional

capacity*

Development strategy and

investment plan for

development of the

transport sector

% of Non-oil revenue of

total government budget ,

% contribution of other

non-oil sectors to GDP

[2013]

Very weak

None

15%;

29%

[2018]:

Enhanced human

and institutional

capacity

Established

development

strategy and

investment plan to

sustainably develop

the transport sector

[2018]: 35% (both)

National annual

reports; transport

development

documents; Bank

review reports

National Statistical

data; MoFCEP

Reports

Risk: Political stability and security Mitigation measures: The negotiation between South Sudan and Sudan is on-going towards peace and normal relations. GRSS has planned peace and national reconciliation conference to resolve internal conflicts. Risks: Lack of commitment & failure to allocate enough resources; Mitigation measures: GRSS is committed to the development of the transport sector & the resumption of the flow of oil and supports from development partners alleviate resource constraints Risk: Failure to implement the outputs of the studies Mitigation measures: The commitment of GRSS to develop transport and the regular dialogue and follow-up by the Bank and other development partners mitigate the risk

OU

TP

UT

S

Component 1: Human Resource Development

Programme (HRDP)

Component 2: Studies: (i) National Transport

Master Plan Study ; (ii) River Transport Study ;

(iii) Juba-Mundri-Yambio road study; and (iv)

Economic Diversification study completed

Component 3: Strengthened Project Management

HRDP & number of staff

trained

Study reports

Provision of TA

[2013]:

None

None

[2017]

Study reports

completed;

Number of trainees

at least:

- 20 short-term &

- 3Masters

2 TAs provided

Progress reports,

disbursement and

financial reports from

the Executing Agency;

Bank supervision

reports; project

completion reports

Risk: Lack of implementation capacity including procurement, financial management and quality control for the outputs. Mitigation measures: Provision is made for Financial Management Specialist and Transport Economist. Technical assistance in the areas of transport engineering and procurements will also be provided in the course of the proposed support attached to projects financed by NEPAD-IPPF and the World Bank.

KE

Y A

CT

IVIT

IES

COMPONENTS INPUTS Component 1: Training Needs Assessment (TNA), HRDP & training

Component 2: Studies: (i) National Transport Sector Master Plan Study; (ii)

River Transport Diagnostic Study; (iii) Juba-Mundri-Yambio road study; and

Economic Diversification Study

Component 3: Strengthening Project Management & Implementation Capacity

(SPMIC): (i) Provision of Technical Assistance to the Implementing Agency, (ii)

Project Management; and (iii) Financial Audit

Costs (million UA)

HRDP 1.14

Studies 4.75

SPMIC 0.78

Base cost 6.67

Price escalation 0.26

Project cost 6.93

Sources of financing (million UA)

FSF 6.93 [100%] ----------------------------- Total 6.93 [100%]

Note: * the ability to perform and execute projects effectively and efficiently

vi

Project Timeframe

I Human Resource Development

1 Short-list/RFP

2 Evaluation/Contract Award

3 Mobilization

4 TNA/HRDP Services

5 Training

II National Transport Master Plan Study

1 Short-list/RFP

2 Evaluation/Contract Award

3 Mobilization

4 Services

III River Transport Study

1 Short-list/RFP

2 Evaluation/Contract Award

3 Mobilization

4 Services

IV Road Study

1 Short-list/RFP

2 Evaluation/Contract Award

3 Mobilization

4 Services

V Economic Diversification Study

1 Short-list/RFP

2 Evaluation/Contract Award

3 Mobilization

4 Services

VI Project Management & Implementation Capacity (Technical Assistants)

1 Short-list/RFP

2 Evaluation/Contract Award

3 Services

VIIFinancial Audit Services

1 Short-list/RFP

2 Evaluation/Contract Award

3 Mobilization

4 Services

Q4

2017

Q1 Q2 Q3 Q4 Q1 Q2Activity

2014 20162015

Q3Q4 Q1 Q2 Q3 Q4Q1 Q2 Q3

1

REPORT AND RECOMMENDATION OF THE MANAGEMENT ON A PROPOSED GRANT

TO THE REPUBLIC OF SOUTH SUDAN FOR THE TECHNICAL ASSISTANCE

FOR THE DEVELOPMENT OF THE TRANSPORT SECTOR PROJECT

Management submits the following Report and Recommendation on a proposed Grant for

UA 6.93 million to finance the Technical Assistance for the Development of the Transport

Sector Project for the Republic of South Sudan.

I. STRATEGIC THRUST & RATIONALE

1.1. Project Background

1.1.1. Transport infrastructure is a major constraint to economic growth, poverty

reduction, good governance, stability and security in South Sudan. The Republic of South

Sudan (RSS) is a fragile, post-conflict country which became independent in 2011 after being

engulfed in a bloody civil conflict for nearly 50 years1. The transport infrastructure was

destroyed or left in disrepair during the protracted civil war. The new country is landlocked

far from any deep-water body without developed and strategically diversified access to

seaports of Mombasa, Djibouti and Port Sudan, and regional connectivity to improve access

to regional and international markets, and boost regional trade. The Sudd swamp, which is

the world’s largest swamp, and the large flood plains of the White Nile and its tributaries

practically cut-off transportation of communities between villages and to markets and socio-

economic infrastructure. The population is deprived of access to services and economic

opportunities. The cost of transport in South Sudan is high in comparison with other Sub-

Saharan countries; freight tariff is about three times that of Eastern Africa and four times that

of Southern Africa.

1.1.2. The RSS has a multi-modal transport system comprising roads, railways, inland

waterways, oil pipeline and air transport networks. Road transport accounts for the majority

of passenger and freight movement within, and to and from the RSS. The condition of the

existing road network is extremely poor with almost the entire network being gravel or earth

road in a state of very poor conditions and a vast majority impassable during the rainy season.

Many road sections are contaminated with landmines. Road density2 in South Sudan is

extremely low whether measured in terms of land area or population, with 19 km per 1,000

sq-km or 1.3 km/1,000 persons. The density of paved roads is insignificant with 0.2 km per

1,000 sq-km as compared with an average 16.8 for Sub-Saharan Africa and 9.9 for low

income fragile States in Africa. About 80% of the population lives in rural areas and the

majority of them have no access to an all-weather road. There is clearly a substantial deficit

in terms of road infrastructure coverage both in quantity and quality, i.e. network length and

condition.

1 South Sudan was in a bloody civil conflict with the Sudan for nearly 50 years with few breaks, starting in 1955, a year

before independence from Egypt and the United Kingdom in 1956 and ending in 2005 with the signing of the

Comprehensive Peace Agreement (CPA) on 9 January 2005 between the Sudan People’s Liberation Movement (SPLM) and

the National Congress Party (NCP). The signing of CPA marked the end of the conflict and started a new era of peace

through a decentralized system of governance in the Sudan where a Government of National Unity (GONU) and the

Government of Southern Sudan in the South were established. Under the CPA, a referendum has been held in January 2011

culminating in the independence of South Sudan on 9 July 2011. 2 African Development Bank, South Sudan Infrastructure Action Plan (2012)

2

1.1.3. Given the lack or poor condition of roads, river transport is a practical and cost

effective transport option in South Sudan. The section of the White Nile between Juba and

Juda (border with Sudan, about 1,300 km) and the Bahr el Ghazal and Sobat rivers which are

tributaries of the White Nile are navigable. Seven of the ten states of South Sudan are served

with river transport but river conditions and lack or inadequacy of navigation aids are

significant impediments to river transport.

1.1.4. South Sudan has a railway line which is about 250 km from Wau to the border with

Sudan. It was developed as part of the railway network of Sudan to transport consumer goods

from Khartoum, but it is not currently operational. The Government of the Republic of South

Sudan (GRSS) intends to develop the railway network as part of enhancing national and

regional transport system. The oil pipelines were built with the development of the oil

industry to transport crude oil to Port Sudan. South Sudan retained the largest share of the oil

reserves with independence while Sudan maintained its authority over most of the oil export

infrastructure. The oil flow has been disrupted for roughly 18 months due to disputes over

pipeline fees with the Sudanese government until agreement was reached and oil export

resumed in June, 2013. However, the sustainability of this situation is uncertain.

1.1.5. The role of air transport to provide international and domestic transport services

although more expensive, particularly when the land transport infrastructure is in bad

conditions could be significant. However, the existing airport conditions are also very poor.

Air Transport infrastructure is composed of an international airport in Juba, a domestic

airport in each state capital of the other nine states and airstrips which were used to provide

military logistics and humanitarian relief supplies. Only Juba and three domestic airports

(Rumbek, Wau and Malakal) are manned and Juba and Malakal are the only airports with

paved runways. Juba International Airport (JIA), which is the main gateway to South Sudan,

does not comply with International Civil Aviation Organization (ICAO) standards.

1.1.6. Human and institutional capacity is the major limitation to roll out the huge

demand for the development of the transport sector. The protracted civil war has exacted a

heavy toll on South Sudan, resulting in challenges to nation building, including a lack of

government institutions and human resources. As a new nation without a history of formal

institutions, rules or administration, RSS is facing a challenge to build its institutions and

develop its human resources from scratch. The Government has put in place the Medium-

Term Capacity Development Strategy (MTCDS) that provides a strategic framework for

planning and organizing institutional and human capacity in support of the recovery and

development priorities of South Sudan. The objective of the MTCDS is to ensure that the

critical institutional capacity needs required to implement the SSDP are effectively addressed.

Despite the substantial achievements of the last seven years, the development challenges

facing the new nation remain significant. Along with weak institutions, the acute shortage of

qualified and skilled human resources in the transport sector remains critical for the

development of the transport sector.

1.1.7. The development of the transport sector in RSS should be informed and guided by a

comprehensive strategy and investment plan which provides prioritized interventions with

effective implementation tools. For the new country, which is starting from scratch, all

transport interventions are priorities, but a priority of priorities needs to be selected for

efficient and optimum utilization of scarce resources and effective implementation. The right

approach to arrive at this instrument is to undertake a NTMP study. The NTMP study is

meant to analyse the features and specifics of transport demand generated from the envisaged

3

national development including the development of natural resources, population settlements,

regional and national connectivity, good governance and security requirements, projections

related to the most likely scenarios in a time horizon of 20 years . The NTMP will, therefore,

identify transport infrastructure and service priorities based on the forecasted transport

demand and devise a pragmatic and efficient framework to build institutional and human

capacity to meet the demand. NTMP for RSS is thus a principal requirement for developing

the transport sector to address comprehensively the overreaching goal of stimulating

economic growth, poverty reduction and enhancing good governance, stability and security.

1.1.8. The Bank, at the request of and in collaboration with the Government of South Sudan,

undertook the INA in 2011 and prepared the IAP for South Sudan. The assessment identified

critical gaps for immediate interventions and showed directions for the development of the

infrastructure sector. The IAP provided a comprehensive and ambitious programme to

rehabilitate, upgrade and expand the basic infrastructure network of the country in the decade

ahead. In the transport sector, consistent with the SSDP, the IAP gave high priority to the

development of basic transport infrastructure which includes roads, inland waterways and air

transports to improve national and regional connectivity, provide access to seaports, and

regional and international markets and enhance agricultural development. The IAP further

underlined the need for undertaking studies for further investigations to determine the

transport demand and prioritized investment plan to inform and guide the development of the

transport sector in the medium to long time horizons. It also emphasised human resource and

institutional capacity development that would provide the basis for rolling out the huge

demand for the development of transport infrastructure and services. The proposed project is

thus in line with the IAP and intends to develop a comprehensive framework that contributes

to the development of human and institutional capacity as well as a strategy and investment

plan for the sustainable development of the transport sector in South Sudan.

1.2. Project Linkages with the Country Strategy and Objectives

1.2.1. The proposed project is in line with the priorities of SSDP and South Sudan

Development Initiative (SSDI) to develop human and institutional capacity and inform and

guide the development of the transport sector. GRSS has articulated its long-term strategy,

Vision 2040, which sets out the broad theme of “Realizing Freedom, Equality, Justice, Peace

and Prosperity for All”. The first phase of the implementation instrument, the South Sudan

Development Plan (SSDP 2011-2016), has four overreaching pillars: (i) Governance, (ii)

Economic Development, (iii) Social and Human Development and (iv) Conflict Prevention

and Security. The SSDI has also been developed to act as implementation framework for the

SSDP. Infrastructure falls under the Economic Development pillar of SSDP. The objective

of the Infrastructure sector, as stated in the SSDP, is “to maintain, rehabilitate, provide and

operate infrastructure to enhance poverty reduction, economic growth and service delivery in

a sustainable manner”. Transport is a major component of the infrastructure programme and

the SSDP acknowledges the role of the development of transport infrastructure and services

as a paramount factor to simulate sustainable growth and improve the lively-hood of the

people.

1.2.2. The transport sector technical assistance is consistent with the Interim Country

Strategy Paper for South Sudan (iCSP 2012-2014). The iCSP articulates the Bank Group

strategy for South Sudan around “State Building through Capacity Building and

Infrastructure Development” that is fully aligned with the country’s national development

plan (SSDP). It emphasizes the creation of conditions for promoting peace, stability, and state

4

building. Human and Institutional Capacity Building in Infrastructure Development is

identified as one of the priorities for Bank interventions. The country strategy and plans are

consistent with the Bank Group Strategy 2013-2022 and the strategic framework of the Bank

Group’s Transport Sector Policy (1993) all of which identify infrastructure development as a

priority.

1.3. Rationale for the Bank Involvement

1.3.1. The weak institutional and human capacity challenge for the transport sector has been

found critical in the Bank’s Infrastructure Needs Assessment. The Republic of South Sudan

is a post-conflict fragile new country which is facing formidable development challenges,

including the lack of institutional and human capacity and an economy heavily dependent on

oil that severely constrains the implementation of its development agenda. Public

administration at all levels lacks the basic human, financial and logistical means to deliver

services. A majority of civil servants have not had any formal training for several years due

to the prolonged civil conflict. Accordingly, the institutional and human capacity in South

Sudan is characterized by low level of productivity and service delivery. The weak

institutional and human capacity challenges cut across all sectors including the transport

sector.

1.3.2. The previous Bank support to South Sudan in undertaking the INA and the

preparation of the IAP are strategic interventions laid down for the infrastructure

development in the country. The Government of South Sudan considers the Bank as one of its

reliable development partners in playing a leading role in the development of infrastructure.

The proposed technical assistance for RSS is the first Bank operation in the transport sector

which is dedicated to build capacity and provide comprehensive and strategic framework for

the development of transport sector. The support is a continuation of the Bank’s engagement

to lead the development of transport infrastructure and services in South Sudan. The

intervention also provides the basis for future Bank support in the transport sector.

1.3.3. The NTMP shall provide a comprehensive strategic framework of prioritized

investment plan taking into account the transport demand and available resources and

implementation capacities. It will also cover the development of institutional and human

capacity as requirements for rolling out the development of the sector. The intervention will

provide the basis for organizing efforts and leveraging resources from the Government, the

Bank and other Development Partners towards the sustainable development of the sector. The

Bank’s comparative advantage to support the proposed intervention stems from its leadership

role in the preparation of IAP and co-chairing the Infrastructure Working Group as well as

the rich experiences that the Bank has in the development of transport infrastructure and

services in Africa, particularly in fragile states.

1.4. Development Partners Coordination

1.4.1. Aid coordination in South Sudan is at its rudimentary stage. Currently, Development

Partners (DPs) supporting the transport sector are organized in two groups, namely:

Infrastructure Working Group (IWG) and Feeder Roads Steering Committee (FRSC). DPs

participating in the IWG besides the Bank include the World Bank, JICA, KFW, GIZ,

USAID and UNICEF. The IWG chaired and co-chaired by the Ministry of Electricity, Dams,

Irrigation, and Water Resources (MoEDIWR) and the Bank respectively, participates in

budget dialogue and lead the preparation of aid financing narrative. The FRSC chaired and

5

co-chaired by the Ministry of Agriculture, Forestry, Tourism, Animal Resources and

Fisheries (MoAFTARF) and the Ministry of Transport, Roads and Bridges (MoTRB)

respectively, coordinates the development of feeder roads. The World Bank, EU, USAID,

DFID and UNWFP participate in the FRSC.

1.4.2. DPs interested to support the development of major roads besides the Bank include

the World Bank and China. USAID financed the Juba-Nimule (192 km) Road, but it has

shifted its interest to feeder roads. Other DPs supporting feeder roads include the World Bank,

EU and DFID. JICA is supporting urban transport projects including the construction of the

New Juba Nile Bridge, expansion of the Juba River Port and capacity building of Juba City in

road maintenance and management. The proposed Bank project is a strategic intervention

which will provide a comprehensive framework to leverage resources and supports from DPs

for the sustainable development of the transport sector.

Table 1.1: Overview of major donor assistance

Sector or subsector

Size

GDP Exports Labor Force

Transport N/A* N/A* N/A*

Players - Public Annual Expenditure (2011-2013 total)

Amount (US$ mil.) %

GRSS 374.87 79%

Donors 100.57 21%

475.44 100%

Level of Donor Coordination

Existence of Thematic Working Groups Y

Existence of SWAPs or Integrated Sector Approaches N

ADB's Involvement in donors coordination Co-chair, IWG

*N/A = information is not available

II. PROJECT DESCRIPTION

2.1. Project Objectives

2.1.1. The sector goal is to contribute to socio-economic development, poverty reduction

and enhance good governance and security through improved and sustainable transport

system that provides strategic seaport access, enhances national and regional connectivity to

link economic centers and access regional and international markets, and help communities to

access socio-economic infrastructure.

2.1.2. The objectives of the proposed project are to enhance institutional setup and capacity,

improve human resource capacity, streamline the transport infrastructure development,

provide information for policy makers with regard to economic diversification and strengthen

project management and implementation capacity. The outcome of the intervention will

provide the basis for the sustainable development of the transport sector in South Sudan.

2.2. Project Components

2.2.1. The project is designed to significantly contribute to the development of the transport

sector, through the development of institutional and human capacity, and strategic studies to

inform and guide the development of transport infrastructure and services. Table 2.1 shows

6

the specific components of the proposed technical assistance with cost estimates and brief

descriptions.

Table 2.1: Project Components

SN Component Name

Cost

Estimate

(UA M)

Component Brief Description

1 Human Resource

Development 1.18

Training needs assessment (TNA) to identify the existing/forecasted gaps

in knowledge and skill requirements at various managerial and technical

levels in the sector in the short, medium and long-term periods; and assess

existing in-country capacity for training and mentoring professionals in

the transport sector;

Develop Human Resource Development Programme (HRDP) with short,

medium and long term implementation time frame; recommend training

packages for imparting knowledge and skills to fill the identified gaps and

create a critical mass of professionals for effective implementation of the

transport sector;

Examine and identify opportunities for leveraging resources for financing

the human resource development programme within the country and from

development partners; and

Financing the training of priority training programmes in accordance with

the recommendation under the implementation of the HRDP.

2 Studies

2.1. National Transport

Master Plan Study 2.00

Review and assess the existing transport infrastructure and operations;

undertake transport demand forecast considering the development

projections of national developments including the development of natural

resources, population settlements, regional and national connections,

governance and security requirements;

Develop and analyse list of investment and operational alternatives; package

and prioritise complementary investments across the different modes of

transport; analyse funding options and develop a prioritised transport sector

investment programme;

Recommend feasible funding and packages for the short term priority

investments; prioritize projects for medium to long term investments;

identify social and environmental scoping studies for short term priority

investments; and

Develop efficient strategies, legal framework, and institutional setups for

rolling out implementation, monitoring the implementation of the identified

short term priorities and revise and update medium and long term priority

investments.

2.2. River Transport

Study 0.37

Review of existing data and information and assessment of the challenges to

identify significant constraints; undertake site survey of the current situation

of the main navigable routes of the White Nile River and its tributaries;

Identify and recommend required interventions including detailed studies,

surveys and projects; prioritize the interventions into short term and medium

to long term investments with cost estimates; and

Identify interventions for potential private sector investment and public

private partnership; and recommend appropriate and adequate environmental

and social safeguards.

2.3. Road Study 2.26

A feasibility study, Environment and Social Impact Assessment,

Resettlement Action Plan, Detailed Engineering Design and preparation of

Bidding Documents of the Juba-Mundri-Yambio road.

2.4. Economic

Diversification

Study

0.30

Prepare diversification profile, road map, a monitoring and evaluation

framework with clear milestones, indicators for the implementation and

harmonized coordination structures for economic diversification.

3 Strengthening Project Management and Implementation Capacity

3.1. Technical Assistance 0.52 Provisions for Technical Assistants in the areas of Financial Management and

Transport Economics each for two years

3.2. Project Management/

Operation 0.24

Provisions for project management and operation including allowances, travel

expenses, and other miscellaneous expenses (fuel, transportation, and office

supplies)

3.3. Financial Audit 0.06 Financial audit

7

2.3. Technical Solution Retained and Alternatives Explored

2.3.1. Different options of providing the proposed support were explored during the project

preparation. The options explored shown in Table 2.2 are in line with the iCSP (2012-2014)

and in consideration of the requests from GRSS, and the findings of INA and IAP. The

alternative selected provides an opportunity to balance and address critical needs for building

human and institutional capacity and providing a framework for the development of the

transport sector which enables GRSS to prioritize investments in accordance with the

transport demand and, financial and implementation capacity.

Table 2.2: Project alternatives considered and explored

SN Alternative Brief description Reasons for rejection/selection

1

Multi-sector

Programme of

Human and

Institutional

Capacity

Development in

Infrastructure

Intends to develop the human and

institutional capacity of infrastructure

subsectors (Transport, Power, Agricultural

Infrastructure, Water & Sanitation and ICT)

involving legal and regulatory capacity; and

restructuring and strengthening institutional

framework; capacity building; development

of pipeline projects; and provision of

technical assistance as project

implementation support to line Ministries.

The programme is large and complex to

implement, and requires the involvement of

numerous actors from line Ministries as well

as from the Bank side that require strong

coordination & project management; and

Financial requirement of the programme

exceeds by far the available ADF country

allocation.

2

Capacity

Building for the

Transport Sector

Comprises human and institutional capacity

building for the transport sector including

short to long term trainings, development of

legal framework to establish and build the

capacity of the different transport subsector

institutions, development of pipeline

projects and provision of technical

assistances.

Focusses on building human and

institutional capacity without any linkage

with the extent of the demand for transport

infrastructure and services, and determine

the capacity requirements to achieve the

demand; and

Does not address the critical issue of

enabling the Government to prioritize

investments in the transport sector.

3

Technical

Assistance for

the Development

of the Transport

Sector

Comprises human resources development,

strategic studies which provides a

framework for the development of the

transport sector including NTMP study,

river transport study, development of

pipeline road project and economic

diversification study together with

strengthening of project management and

implementation capacity.

Designed to provide a mix of interventions

to build human and institutional capacity

and undertake strategic studies to enable

the Government to prioritize investments in

the transport sector; and

The human and institutional capacity

building is linked with the capacity

requirements for the development of the

transport sector.

2.3.2. The Bank Team designed the components of the project such that they strategically

and comprehensively address the development of the transport sector with a framework of

systematically building institutional and human capacity. With respect to this, one of the

prioritized interventions in the IAP proposed programme is the requirement of a NTMP to

inform and guide the development of the transport sector which fits well in the request of the

GRSS. The NTMP will provide the foundation for the requirements of the institutional and

human resource development. This acknowledges that the institutional and human capacity

issues are derived demands for developing the transport sector. These considerations have

been thoroughly looked at by the Bank Team in close collaboration with GRSS to select the

project components listed in Table 2.1 which strategically address post-conflict critical issues

of RSS to advance the development of the transport sector.

8

2.4. Project Type

The proposed operation is a technical assistance financed by grant resources from the

Fragile State Facility (FSF), Pillar I. The project focuses on three inter-related areas that are

outlined in Table 2.1, and is a continuation of the Bank support to lead the transport sector

development and significantly assist the human and institutional capacity building in the

RSS. The project is designed to provide support in the transport sector and dovetails well

with the Bank’s on-going support to capacity building in RSS. Appendix II provides

information with respect to all Bank Group Operations.

2.5. Project Cost and Financing Arrangements

2.5.1. The estimated cost of the project, net of taxes amounts to UA 6.93 million

(US$10.42 million), of which UA 5.26 million (76%) is payable in foreign currency and UA

1.67 million (24%) is payable in local currency. A provision for price escalation of 3% and

7% for foreign and local costs respectively has been taken into account. The project cost was

estimated based on prevailing unit rates in South Sudan and the region. A summary of the

cost estimates net of taxes is presented in Table 2.3.

Table 2.3: Project cost estimates by components [net of taxes]

Component SS Pound Million UA million

Foreign

Cost

Local

Cost Total

Foreign

Currency

Local

Cost Total

A. Human Resource Development 4.493 1.123 5.616 0.910 0.228 1.138

Sub Total 4.493 1.123 5.616 0.910 0.228 1.138

B. Studies

National Transport Master Plan Study 7.619 1.905 9.524 1.544 0.386 1.930

River Transport study 1.396 0.349 1.745 0.283 0.071 0.354

Juba-Mundri-Yambio road study 8.600 2.150 10.749 1.743 0.436 2.178

Economic Diversification Study 1.134 0.284 1.418 0.230 0.057 0.287

Sub Total 18.749 4.687 23.436 3.799 0.950 4.749

C. Strengthening Project Management and Implementation Capacity

Technical Assistance 1.974 0.493 2.467 0.400 0.100 0.500

Project Operating Cost 0.000 5.155 5.155 0.000 0.220 0.220

Financial Audit 0.000 0.297 0.297 0.000 0.060 0.060

Sub Total 1.974 5.945 7.919 0.400 0.380 0.780

Base Cost 25.215 11.756 36.971 5.110 1.558 6.667

Price Escalation (3% for FC % 7% for LC) 0.756 0.823 1.579 0.153 0.109 0.262

Total 25.972 12.579 38.550 5.263 1.667 6.930

Note: Exchange rates as of July 2013, 1 UA = SSP4.93472; 1 UA = US$1.50396

2.5.2. Considering the current difficult economic situation of South Sudan, the Bank gave

a waiver for the 5% minimum counterpart funding requirement for the project. Accordingly,

the entire project cost (net of taxes), UA 6.93 million, will be financed by the Bank from the

FSF allocation. The project cost by category of expenditure and the expenditure schedule by

components are shown in Table 2.4 and 2.5 respectively.

9

Table 2.4: Project cost by category of expenditure [UA million net of taxes]

Categories of expenditure Foreign

Currency

Local

Currency

Total

Costs

%

Foreign

A. Services

Studies 3.99 0.99 4.98 80%

Training 0.72 0.19 0.91 79%

Technical Assistance 0.40 0.10 0.50 80%

Financial Audit 0.00 0.06 0.06 -

B. Project Operating Cost 0.00 0.22 0.22 -

Base Cost 5.11 1.56 6.67 77%

Price Escalation (3% for FC % 7% for LC) 0.15 0.11 0.26

Total 5.26 1.67 6.93 76%

Table 2.5: Project expenditure schedule by components [UA million net of taxes]

Component 2014 2015 2016 2017 Total

A. Human Resource Development 0.04 0.38 0.38 0.38 1.18

B. Studies

National Transport Master Plan Study 0.40 1.20 0.40 - 2.00

River Transport study 0.16 0.21 - - 0.37

Juba-Mundri-Yambio Road Study 0.45 1.36 0.45 - 2.26

Economic Diversification Study 0.13 0.17 - - 0.30

C. Strengthening Project Management and Implementation Capacity

Technical Assistance 0.07 0.15 0.15 0.15 0.52

Project Operating Cost 0.03 0.07 0.07 0.07 0.24

Financial Audit 0.01 0.01 0.02 0.02 0.06

Total 1.29 3.55 1.47 0.62 6.93

2.6. Project’s Target Area and Population

2.6.1. The proposed project deals with interventions most of which are comprehensive and

strategic in nature that provide a foundation for the transport sector development and help to

diversify the economy. These interventions will benefit the entire Government and the eleven

million South Sudanese in many ways. Firstly, the project will provide a strategic framework

for leveraging resources and significantly assist in building the weak institutional and human

capacity systematically to rollout the demand for the development of the transport

infrastructure and services. Secondly, the project will provide a transport master plan which

will inform and guide balanced development of all modes of transport with a prioritised

investment plan based on merits and benefits of projects in stimulating economic growth,

reducing poverty, and enhancing good governance and security.

2.6.2. The project component in river transport will identify interventions for improving

critical bottlenecks to develop the river transport infrastructure and services which remains

practical and cost effective transport option to reach communities along the White Nile and

its tributaries. River transport in South Sudan serves seven states out of the ten states and

connects South Sudan with Sudan and Ethiopia. The project is, thus, expected to improve

regional connectivity and benefit about 3 million people which is about 27% of the total

population of the country. Further, the Juba-Mundri-Yambio road study is a preparation for a

10

pipeline road project that connects the Central Equatoria (where Juba is located)) to Western

Equatoria state which has a high potential for commercial agricultural produce such as rice,

tea, coffee, oil palm, forestry and groundnut. In addition to unlocking the region for

commercial farming, the pipeline road project which will be prepared under the Road Study

component, if implemented, will potentially benefit about 500,000 people in the zone of

influence.

2.7. Participatory Process for Project Design and Implementation

2.7.1. Several Senior Government officials at the then MoFEP, MoT and MoRB were

consulted during the preparation and appraisal of the project in April and June 2013

respectively. The consultations centred on: (i) the reform in the then MoT to establish

authorities in the different transport subsectors under its mandate and regulate the transport

operation; (ii) institutional and human capacity development needs; (iii) transport

development strategy; (iv) the urgent need of river transport study; and (v) road study to

prepare a pipeline project. Within the former MoT and MoRB, the Bank Group held detailed

consultations with senior staff members of the following Directorates/Departments: (i)

Directorate of River Transport; (ii) Directorate of Rail Transport; (iii) Directorate of Road

Transport and Safety; (iv) South Sudan Civil Aviation Authority; (v) Directorate of Roads

and Bridges; (vi) South Sudan Roads Authority; and (vii) Project Management Team.

Consultation was also made with the College of Engineering and Architecture, University of

Juba which explored the possibility of collaborations to participate in the implementation of

the project as well as possible involvement in human resource development.

2.7.2. The Bank Group also held detailed consultations with development partners,

including the World Bank, USAID, DFID, EU and JICA. The consultations focused on the

central role of the components of the project in providing a comprehensive framework for the

development of the transport sector and significant assistant for developing the institutional

and human capacity, and the synergy of the proposed operation with the on-going assistance

being provided by the Bank and other partners to the GRSS. Consultations with development

partners also focused on the way forward in coordinating and harmonizing efforts with

respect to supporting the huge demand for developing the transport sector with particular

attention to institutional and human capacity building challenges. The dialogue initiated with

the South Sudan Authorities and development partners was enhanced during the preparation

of the project and will continue in the implementation phase.

2.7.3. During implementation of the project, public consultations will be part of the

requirements of all the studies and will clearly be indicated as mandatory tasks of the

assignments in the Terms of References. Workshops and consultations will be made with all

stakeholders in the course of the studies. The Project Management Team (PMT) will be

responsible for facilitating all workshops and public consultations. Consultations related to

environmental and social implications of the studies will be given particular attention.

2.8. Bank Group Experience, Lessons Reflected in Project Design

2.8.1. The Bank Group has been inactive in Sudan since 1995 due to conflict and sanctions

induced by outstanding arrears to the International Finance Institutions (IFIs) and the wider

donor community until the limited re-engagement started after the signing of CPA in 2005.

The ongoing Institutional Capacity Building for Poverty Reduction and Good Governance

Project was approved in March 2007 for UA 9.62 million in the form of an ADF grant with

activities both in Sudan and South Sudan under the two tier system of governance. This was

11

followed by the Assistance to the University of Juba, approved in May 2011 for UA 0.32

million from the Bank administered Trust Fund, and Public Finance Management and Aid

Coordination, approved for UA 4.8 million from FSF Pillar 3 grant in December 2012. The

ongoing institutional support to public financial management and aid-coordination will

improve the financial management capacity of the Ministry of Finance, Commerce and

Economic Planning (MoFCEP) and Ministry of Transport, Roads and Bridges (MoTRB) for

the implementation of the proposed project. The lessons and experiences of implementing

these operations in South Sudan and lessons learnt from Bank operations in the sector

particularly in post-conflict fragile countries such as Sierra Leone and Liberia have been vital

in informing the design of the proposed project. Desk review of the Bank operations in these

countries revealed that projects suffered from implementation delays primarily due to lack of

institutional and human capacity.

2.8.2. The key lessons learned from the Bank operations in fragile and post-conflict

Regional Member Countries (RMCs) include: (i) significant delays in fulfilling conditions

prior to disbursement; (ii) weak capacity for project implementation especially regarding to

adherence to the Bank procurement/fiduciary rules and procedures; (iii) weak project

management and supervision; and (iv) coordination of development partners. In light of these

lessons, conditions precedent to the first disbursement have been streamlined to avoid start-

up delays due to late fulfillment. The proposed project will be implemented by the PMT with

provisions of Technical Assistants in the areas of Financial Management and Transport

Economics to strengthen its capacity. The PMT is better equipped and staffed, and has been

and will also be provided Technical Assistant supports attached to other projects during the

course of the proposed project.

2.8.3. The project design was discussed and agreed between the Bank Team and the GRSS

to incorporate the lessons gained from other Bank operations. The project design captured

key recommendations from previous Bank operations, particularly, in fragile countries. The

specific components of the project dealing with institutional and human resource

development including on-the-job trainings make the proposed project more focused to

address the primary cause of delay of projects in fragile countries.

2.9. Key Performance Indicators

2.9.1. At completion of the project implementation three outcomes are expected: (i)

improved human and institutional capacity; (ii) improved strategy and investment plan for the

sustainable development of the transport sector; and (iii) increased analytical knowledge for

economic diversification. The outputs of the project will be: (i) human resource development

programme and provision of priority trainings; (ii) reports of studies including (a) NTMP; (b)

prioritized interventions to improve the river transport; (c) pipeline road project; and (d)

analytical knowledge on economic diversification. The project also has provisions for

strengthening project management and implementation capacity of the Implementing Agency

which will also help to transfer knowledge and skill through on-job-training.

2.9.2. The outcomes of the project will be monitored with the use of baseline data that

will be collected as part of all studies. The Terms of References of each study will clearly

indicate the baseline data requirements. Baseline data such as traffic volume; vehicle fleet;

national statistics on economic growth, poverty and import-export; traffic accident data;

transport cost for passenger and goods movement; accessibility index; volume of passenger

and goods movement using river transport; and existing statistics on available qualified and

skilled manpower in the transport sector will be collected by the respective consultants. The

12

data collection will be undertaken by the Executing Agency periodically at various intervals

throughout the project implementation as a means of monitoring progress towards the

projected targets. The performance of the project will be monitored using progress reports,

qualitative assessments, regular monitoring and evaluation through field supervisions by

Project Task Team and Field Office Staff, mid-term review report, and financial auditing by

appropriate Bank staff and external auditing firm. These will be supplemented by

assessments that will emerge from the continuous stakeholder consultation process that is

incorporated throughout the project.

III. PROJECT FEASIBILITY

3.1. Economic and Financial Performance

3.1.1. The expected economic and financial benefits of the technical assistance by far

outweigh the cost of the operations. In the short term, effective implementation of the project

will furnish the new country with a NTMP and human resource development programme to

guide the development of the transport sector and contribute to improving the institutional

and human capacity. These, subsequently, will help to rollout the huge demand for expanding

the transport infrastructure and services. In the medium to long terms, as the human resource

development programme is realized to produce a critical mass of professionals in the sector

and institutional capacity is in place, the development of the transport sector will be

implemented in accordance with the transport master plan. The institutional and human

capacity will continue to play a leading role to sustainably develop the transport sector by

periodically updating the NTMP to capture the dynamically changing transport needs of the

country.

3.1.2. The spectrum of the benefits of the project is, therefore, wide and ranges from short to

long terms. While the costs of the project components are quantifiable, the direct and indirect

benefits in the short and medium to long time horizons cover the entire country and extend to

the region in improving people’s mobility and access to opportunities which consequently

result in improved economic and social development, poverty reduction, stability and security

in RSS.

3.2. Environmental and Social Impacts

3.2.1. The project is classified as Category III and will therefore have no adverse effect on

the environment. Category III classification implies that the project is not expected to have

any adverse environmental impact for which an environmental assessment is normally

necessary. Indeed, as the components of the project entail studies that provide the framework

for the transport sector investments, the project will provide wide opportunities to institute a

systematic way of handling environmental and social issues in the development of the

transport sector.

3.2.2. A joint assessment report3 produced by the Government and UNDP documented

striking impacts observed in South Sudan relating to climate change and environmental

degradation on water, soil, forest, biodiversity, agriculture and fisheries. The report cites a

number of opportunities that the new country has compared to most other countries in the

3 Ministry of Environment, Government of the Republic of South Sudan, and United Nations Development Programme

(January 2012). Environmental Impacts Risks and Opportunities Assessment: Natural Resources Management and Climate

Change in South Sudan.

13

region which include among others the possibility for creating effective governmental

structures and systems. Noting the dynamics and the probable effects of climate change, and

environmental and social issues in RSS, the study components of the technical assistance will

provide pertinent significant attention to inclusive green growth and gender issues in all the

studies. The NTMP study, in particular, will take stock of the opportunity to create a system

that ensures gender balance and inclusive green growth for sustainable transport

development. Furthermore, the human resource development will also provide significant

focus to build capacity in managing environmental and social issues.

3.2.3. The proposed project aims at the development of the transport sector which enhances

socio-economic opportunities and consequently stimulate economic growth and poverty

reduction which are fundamental development objectives of the RSS. The development of

transport has a multiplier effect of initiating development in other sectors such as agriculture,

tourism, mining and trade and enhancing access to socio-economic infrastructure. The project

will also contribute to good governance, stability and national security which are essential

elements for economic growth and prosperity. Besides the catalytic effects of transport for

economic diversification, the economic diversification study will provide an analytical

knowledge base to diversify the economy and move out of the oil dependency. The social

benefits of most of the project components cover the whole country while the river transport

and the road study project is limited to the influence zone of the corridors of the specific

components as described in Section 2.6.

3.2.4. In a country where the literacy rate for females is 28% compared to 55% for males,

gender inequality is a critical challenge and prevails in various ways such as access to

education, control over assets and decision-making. GRSS has a political will to empower

women by putting the right policies and laws in place to promote gender equity. As a

consequence, the ratio of girls to boys in primary, secondary and tertiary education has been

rising. Similarly, the proportion of posts held by women in the Government has increased.

However, challenges remain. The proposed project, particularly the NTMP, river transport

study and economic diversification study, will support government’s plans to enhance gender

mainstreaming into its development programmes by enhancing access to socio-economic

infrastructure notably health institution, markets and schools through the provision of

improved transport infrastructure and services.

IV. IMPLEMENTATION

4.1. Implementation Arrangements

4.1.1. The transport sector has undergone frequent changes of institutional restructuring.

After the signing of the CPA, in the transition period (January 2005-July 2011), the Ministry

of Transport and Roads (MoTR) was established to lead the transport sector. After

independence, the transport sector was reorganized under two ministries, namely: Ministry of

Transport (MoT) and Ministry of Roads and Bridges (MoRB). MoT was responsible for the

overall transport sector policy and regulation as well as administration of the air, rail and

river transports while MoRB was accountable for the development and administration of

roads and bridges. On 23 July 2013, through the Republican Order No 14/2013 for the

reduction and restructuring of the ministries of the National Government, the transport sector

is restructured again under one ministry, the Ministry of Transport, Roads and Bridges

(MoTRB). At state level, a State Ministry of Physical Infrastructure (MoPI) takes

responsibility for intrastate transport infrastructure in each of the ten states of South Sudan.

14

4.1.2. The transport components of the proposed project fall under the MoTRB while the

economic diversification study belongs to MoFCEP. The Bank Group assessment during the

appraisal mission was that the capacity of the former MoT was weak to implement the

components under its responsibility. The then MoRB was better established in relative terms

with clear direction regarding the development of a national and regional road network. The

Bill for the creation of South Sudan Roads Authority (SSRA) was enacted in January 2011,

but the authority is not fully established to assume its responsibilities. In the transition period,

a Project Management Team (PMT) which was operating under the then MoRB is relatively

well staffed and familiar with the World Bank procurement and implementation procedures.

The PMT is currently implementing the World Bank financed rural road project and

government financed operations.

4.1.3. The PMT will be the Implementing Agency of the proposed project under the

Executing Agency, Ministry of Transport, Roads, and Bridges (MoTRB). The procurement of

the consultant for the economic diversification study will also be handled by the PMT with

the full participation of technical representatives from MoFCEP. After procurement, the

economic diversification study will be managed by MoFCEP in coordination with the PMT.

However, the PMT will be responsible for reporting to the Bank. SSRA will take over the

responsibility of implementing the project when it is fully established and have adequate

capacity.

4.1.4. The project has provisions for Technical Assistants in the areas of Financial

Management and Transport Economics to strengthen the project management and

implementation capacity of the PMT. The World Bank has been supporting the PMT and will

also provide shortly Technical Assistance support in procurement. In the course of the

proposed project, a Technical Assistant in the area of Transport Engineering will be provided

to PMT attached to a Bank project which is being processed in parallel for NEPAD IPPF

financing with the request from the Intergovernmental Authority on Development (IGAD).

4.1.5. Considering the current economic situation of the country, the project has also

made provision for project management/operation to cover project related costs such as

allowances, travel expenses, and other miscellaneous operating expenses (fuel, electricity,

transportation, and office supplies). The Implementing Agency will prepare a detailed manual

specifying the type of activities to be covered and expenditure procedures for the use of the

provision which requires prior review and approval by the Bank.

Procurement

4.1.6. All procurements financed by the Bank will be in accordance with the Bank's Rules

and Procedures for the Use of Consultants, May 2008, revised July 2012 edition and the

provisions stipulated in the Financing Agreement, using the relevant Bank Request for

Proposal Documents. PMT will be responsible for handling procurements. The resources,

capacity, expertise and experience of the PMT together with the provisions of technical

assistances was assessed and found acceptable to carry out procurement. Details of the

procurement arrangements under the project are summarized in the Technical Annexes,

Section C.

Financial Management

4.1.7. The Public Financial Management (PFM) systems are weak. Fiduciary risks are

substantial due to weaknesses in the overall Public Financial Management (PFM) systems

15

largely attributable to infancy of the country. However, there is some positive trajectory

indicating that the PFM systems are being implemented to address the deficiencies. Fiduciary

diagnostics undertaken in South Sudan in the last two years include: (i) Public Expenditure

and Financial Accountability (PEFA) assessment in 2011 and (ii) South Sudan Integrated

Fiduciary Assessment (SSIFA) in 2012. The PEFA assessment undertaken in 2011 was the

first one for the country and as a result there are no comparative PEFA scores for prior years.

In this regard, the Government prepared a Public Finance Management (PFM) Reform

Action Plan with a view to addressing the identified weaknesses. The Public Financial

Management and Accountability Bill and also Taxation Act had been enacted. The MoFCEP

is taking steps to address inefficiencies. Moreover, the recently Bank Financed PFM capacity

building project will have important interventions to strengthen the PFM System.

4.1.8. The PMT has an experienced Project Accountant and the project has a provision of

a Financial Management Technical Assistant to strengthen its capacity. The TA will work

closely with the PMT to provide budgeting, accounting, internal controls and financial

reporting for the project as well as provide on-the-job training to MoTRB financial

management staff. The Bank also plans to provide tailor-made training before the Bank

funded project commences. The Internal Audit Department of the MoTRB and MoFCEP will

include the project in their annual work plans. MoTRB with the support of the appointed FM

Specialist will be responsible for coordinating and preparing quarterly interim financial

reporting (IFRs) and the IFRs will be due for submission to the Bank no later than 45 days

after the end of each quarter. To the extent possible, this quarterly reporting will be

harmonized with the World Bank (WB) funded project both in terms of format and timing.

4.1.9. At the end of each financial year (July-June) and at the end of the project, MoTRB

will be required to produce annual financial statements in a format to be agreed with the Bank

and harmonized with WB. The financial statements will be audited by a qualified auditor

acceptable to the Audit Chamber (AC) as well as to the Bank. The same auditor will audit the

Bank funded project as well as the WB funded project using agreed audit TORs. The audit

report, complete with a Management Letter will be submitted to the Bank no later than 6

months at the end of the Financial Year and at the end of the project.

4.1.10. Most disbursements under the project will be via direct payments method.

However, for the capacity building components, the Executing Agency will open a Special

Account at a bank acceptable to the Fund. The Fund will transfer six months estimated

expenditures into the Special Account to cover eligible project expenditures. Details of

Disbursements will be provided in the Disbursement Letter and Disbursement Handbook

which will be provided when the Project is approved.

4.2. Monitoring

4.2.1. The implementation of the transport components of the project will be overseen by

a Transport Technical Committee (TTC) that will facilitate, coordinate, monitor and assist as

necessary the technical aspects of the project. The TTC members will consist of

representatives from the South Sudan Roads Authority; South Sudan Civil Aviation

Authority; Juba University; Engineering Council of South Sudan; Directorate of River

Transport; Directorate of Road Transport and Safety; Directorate of Railway Transport, with

the Project Management Team as the Secretariat of the TTC. The nominated TTC members

shall have a capacity to provide the required technical inputs. The TTC may also co-opt other

officials to provide technical inputs in their fields of expertise. TTC shall have no contractual

obligations under any of the consultancy contracts. The Committee shall meet quarterly or by

16

notice. MoTRB will appoint a Project Coordinator (PC) within the PMT who will be a civil

engineer with a minimum of 5 years’ experience in project management. S/he will be the

Bank’s contact person regarding the project. The PC will liaise with the consultants and

prepare and forward quarterly reports to the Bank. S/he will process and forward to the Bank

disbursement requests.

4.2.2. Similarly, the economic diversification study will be overseen by a Technical

Committee (TCE) to advise the technical aspects of the study. TCE will be composed of a

representative from the Ministry of Transport, Roads and Bridges; Ministry of Agriculture,

Forestry, Tourism, Animal Resources and Fisheries; Chamber of Commerce; Ministry of

Interior and Wild Life Conservation; Ministry of Labour, Public Services, and Human

Resource Development; Ministry of Electricity, Dams Irrigation and Water Resources;

Ministry of Petroleum, Mining and Industry; and Ministry of Environment. The MoFCEP has

designated the Director General (DG) for Macroeconomic and Planning as the coordinator of

the economic diversification study. The DG will be responsible for the day to day

management of the diversification study in coordination with the PMT.

4.2.3. Bank’s field supervision missions will be undertaken twice a year to monitor the

progress of the project and if necessary a mid-term review in the second year of execution

will be considered. The South Sudan Field Office (SSFO) will follow-up on the day to day project

operations to ensure smooth progression of the project. At 85% completion of the project

components or 95% disbursement of the grant, the Bank and the Implementing Agency will

prepare a joint Project Completion Report.

4.3. Governance

4.3.1. After independence in July 2011, the Republic of South Sudan faces a myriad of

governance and poverty challenges, as well as continued hostilities with Sudan. At the

domestic level, the country is struggling with structural obstacles such as a lack of basic

infrastructure, the weak development of government institutions and the lasting level of

insecurity. Corruption is present in all sectors of the economy and at all levels of the new

state apparatus. It is manifested in various forms, including financial and political corruption,

patronage, pervasive tribalism and misuse of power. There is still very little quantitative data

available on the extent of corruption in the country. A report on corruption in South Sudan4

indicates that the country performs extremely poorly in its first ranking on the 2011 World

Bank’s Worldwide Governance Indicators, scoring well below 20 (on a scale of 0 to 100) in

all areas of governance assessed. The report further cited the 2011 Global Corruption

Barometer that 67% of all citizens surveyed believe that corruption in the country has

increased during the three years preceding the survey.

4.3.2. Since the CPA in 2005, there have been efforts to step up the fight against corruption,

but South Sudan’s anticorruption framework is still embryonic. The country has not yet

signed or ratified any international conventions against corruption. The institution with the

constitutional mandate to investigate and prosecute corruption cases is the South Sudan Anti-

Corruption Commission (SSACC). But the capacity of the SSACC, resources and political

will often hamper effective implementation.

4 Magali Mores and Njoya Tikum (March 2013); Overview of corruption and anti-corruption in South Sudan. U4:Anti-

Corruption Resource Centre (www.U4.no); Transparency International (www.tranparency.org) and CMI Crr. Michelsen

Institute (www.cmi.no)

17

4.3.3. For this project, procurement and financial management will be in accordance with

the Bank rules and therefore the risk of fraud and corruption has been minimized. Adequate

provisions have also been made for auditing of the project on annual basis.

4.4. Sustainability

4.4.1. The proposed project significantly contributes to the sustainability of the transport

sector. The potential contributions of the project towards the sustainability of the sector are

two-fold. Firstly, the development of the human and institutional capacity is the prime

contributor for the sustainability of the transport sector development. South Sudan is a post-

conflict fragile country where the institutional and human capacity is very weak. The project

primarily aims at reforming and strengthening of the sector institutions with necessary

regulatory framework to enable them efficiently manage and administer the development of

the transport sector. The human resource development programme which will be prepared

and the priority trainings implemented under the project will also contribute considerably to

the development of the critical mass of professionals in the sector which is vital to ensure

sustainability.

4.4.2. Secondly, the strategic studies which will be undertaken will contribute to the

preparation of comprehensive strategic NTMP with prioritized investment plan to inform and

guide the development of the transport sector. This will help to expand, upgrade and

rehabilitate transport infrastructure and provide transport services in a manner that all modes

of transport are complementarily developed and the scarce resources are effectively utilized

to meet the travel demand. It will also ensure the development of the transport infrastructure

in an orderly manner to improve national and regional connectivity in accordance with the

development and security demands of the country.

4.4.3. Both the human and institutional capacity development and the transport master plan

are key requirements for developing the transport sector in a sustainable manner. Furnishing

these requirements at the early level of the development of the sector gives an opportunity for

South Sudan to get the transport development agenda right at the start. With the abundant

available natural resources in South Sudan, stainable development of the transport sector will

contribute to balanced and accelerated economic growth and poverty reduction in the

country.

4.4.4. Options of financing sources will be assessed and explored under each study to have

an outlined financing mechanism to ensure the implementation of study outputs. The

financing options can have several models and combinations of Government, Development

Partners and Private Sector financings. The findings of the financing mechanisms and options

will be discussed at stakeholders’ validation workshops which will be organized as parts of

each study.

4.5. Risk Management

4.5.1. Political stability and security: Political stability and security situation in South

Sudan remains fragile due to internal and external conflicts. The heightened tension between

South Sudan and Sudan which has caused disruptions of oil export for roughly over 18

months eased as the result of the Government’s efforts to mitigate through a combination of

measures, including and partnering with the international community, the African Union

High Level Implementation Panel (AUHIP) and the United Nations in negotiating and

resolving post-–independence issues. The oil flow has resumed and the two neighboring

18

countries are supposed to implement other agreed issues. However, tension is heightening

between the two countries again due to the lack of trust and claims that each country supports

rebellion against the other. In June 2013, Sudan threatened to halt the oil flow for the

allegation that South Sudan is backing Sudanese rebels, which is said to be delayed after an

African mediation.

4.5.2. Furthermore, RSS has internal conflicts including the rebellion which is said to be

operating in the Jonglei state and rival tribal militia operating in almost all parts of the

country. The Government has planned to hold the first-ever comprehensive peace and

national reconciliation conference to resolve and heal internal conflicts and divisions between

political groups and communities. While trying to resolve tensions and conflicts, GRSS is

striving to implement the SSDP to deliver the peace dividend in the form of broad based and

inclusive growth. The proposed project will contribute significantly to implement the SSDP

through the development of the transport sector to stimulate economic growth and address

poverty and improve good governance and security.

4.5.3. Government commitment for the development of the transport sector: GRSS is

committed to the development of the transport sector to stimulate economic growth, poverty

reduction and to enhance governance and security. The resumption of the export of oil

improves the potential for strengthening the Government’s commitment to mobilize its own

resources which has a potential leveraging effect for more resources from development

partners for the development of the transport sector.

4.5.4. Implementation of the outputs of the studies: Failure to implement the outputs of the

studies is a potential risk for achieving the intended objectives of the proposed Bank

intervention. The commitment of the Government for developing the transport sector together

with regular dialogue and follow-up by the Bank and other development partners will

mitigate the risk of failure to implement the outputs of the studies.

4.5.5. Capacity of the Executing Agency: The institutional capacity in South Sudan in

general and in the MoTRB in particular is at its infancy. Procurement and financial

management capacity are critical constraints. Provision is made for Financial Management

Specialist and Transport Economist under the proposed support to strengthen the capacity of

the PMT. Further, the ongoing Bank supported Institutional Support Project and Public

Finance Management and Aid Coordination Project will help to strengthen capacity.

Technical assistance in the areas of transport engineering and procurement will also be

provided to the Implementing Agency in the course of the project attached to projects

financed by NEPAD-IPPF and the World Bank. There will also be close Bank supervision for

successful implementation.

4.6. Knowledge Building

The proposed project will help to generate and transfer knowledge in the transport

sector under fragile and post-conflict setting. The human resources development centres at

identifying knowledge and skill gaps in the sector, designing a programme by which these

gaps can be filled and implementing priority trainings. The programme further aims at

developing a critical mass of professionals in the sector. The NTMP study targets to generate

knowledge on the transport demand through the analyses of various explanatory variables,

develop a prioritized investment plan and devise tools for implementation. Similarly, the river

transport study aims at generating knowledge on how to provide efficient and safe river

transport services. These strategic studies involve tremendous knowledge generation and

19

transfer processes in the transport sector in a unique post-conflict new country which is a

useful experience for the Bank Group. Moreover, the economic diversification study provides

an extra dimension of the project out of transport to generate analytical knowledge for

diversifying the economy of RSS which is currently dependent on oil.

V. LEGAL INSTRUMENTS AND AUTHORITY

5.1. Legal Instrument

The project will be financed pursuant to a Protocol of Grant Agreement between the

Republic of the South Sudan and the ADB/ADF.

(A) Conditions Precedent to Entry into Force

(i) The Protocol Agreement shall enter into force upon signature by the Recipient

and the Fund.

(B) Conditions Precedent to First Disbursement: The Fund’s obligation to make the first

disbursement of the Grant to the Recipient shall be conditional upon the entry into force of

this Protocol Agreement as set forth in (A) above and the submission by the Recipient of

evidence, in the form and substance satisfactory to the Fund, of the fulfillment of the

following conditions:

(i) Having opened one (1) foreign currency Special Account and one (1) local

currency account in a bank acceptable to the Fund for the deposit of part of the

proceeds of the Grant to finance eligible expenses; and

(ii) Having designated a Project Coordinator whose skills and qualifications are

acceptable to the Fund.

(C) The Recipient hereby undertakes to:

(i) Submit evidence confirming the appointment of members of a Transport

Technical Committee (TTC), to oversee the implementation of the transport

component, whose Terms of Reference are acceptable to the Fund. The TTC

shall be composed of representatives from the South Sudan Roads Authority;

South Sudan Civil Aviation Authority; Juba University; Engineering Council of

South Sudan; Directorate of River Transport; Directorate of Road Transport and

Safety; Directorate of Railway Transport, with the Project Management Team as

the Secretariat of the TTC.

(ii) Submit evidence confirming the appointment of members of a Technical

Committee for Economic Diversification Study (TCE) composed of

representatives from the Ministry of Transport, Roads and Bridges; Ministry of

Agriculture, Forestry, Tourism, Animal Resources and Fisheries; Chamber of

Commerce; Ministry of Interior and Wild Life Conservation; Ministry of Labour,

Public Services, and Human Resource Development; Ministry of Electricity,

Dams Irrigation and Water Resources; Ministry of Petroleum, Mining and

Industry; and Ministry of Environment, to oversee the implementation of the

economic diversification study, whose Terms of Reference are acceptable to the

Fund; and

20

(iii) Submit audited financial statements, carried out by a qualified auditor acceptable

to the Fund, in accordance with Terms of Reference approved by the Fund. The

Recipient shall submit the audit report and the accompanying Management Letter

to the Fund, no later than six (6) months from the end of the Financial Year, and

no later than six (6) months from the completion of the Project.

5.2. Compliance with Bank Policies

This project complies with all applicable Bank policies.

VI. RECOMMENDATION

Management recommends that the Board of Directors approve the proposed Grant of

UA 6.93 million to the Republic of South Sudan from the FSF Pillar I to finance the

Technical Assistance for the Development of the Transport Sector for the purposes and

subject to the conditions stipulated in this report.

Appendix I. Country’s comparative socio-economic indicators

YearSouth

SudanAfrica

Develo-

ping

Countries

Develo-

ped

Countries

Basic Indicators

Area ( '000 Km²) 2011 ... 30,323 98,458 35,811Total Population (millions) 2012 10.4 1,070.1 5,807.6 1,244.6Urban Population (% of Total) 2012 ... 40.8 46.0 75.7Population Density (per Km²) 2008 15.8 34.5 70.0 23.4GNI per Capita (US $) 2011 ... 1 609 3 304 38 657Labor Force Participation - Total (%) 2012 ... 37.8 68.7 71.7Labor Force Participation - Female (%) 2012 ... 42.5 39.1 43.9Gender -Related Dev elopment Index Value 2007-2011 ... 0.502 0.694 0.911Human Dev elop. Index (Rank among 186 countries) ... ... ... ... ...Popul. Liv ing Below $ 1.25 a Day (% of Population)2005-2011 ... 40.0 22.4 ...

Demographic Indicators

Population Grow th Rate - Total (%) 2012 4.8 2.3 1.3 0.3Population Grow th Rate - Urban (%) 2012 ... 3.4 2.3 0.7Population < 15 y ears (%) 2012 ... 40.0 28.5 16.6Population >= 65 y ears (%) 2012 ... 3.6 6.0 16.5Dependency Ratio (%) 2012 ... 77.3 52.5 49.3Sex Ratio (per 100 female) 2012 104.6 100.0 103.4 94.7Female Population 15-49 y ears (% of total population) 2012 ... 49.8 53.2 45.5Life Ex pectancy at Birth - Total (y ears) 2012 59.8 58.1 67.3 77.9Life Ex pectancy at Birth - Female (y ears) 2012 61.3 59.1 69.2 81.2Crude Birth Rate (per 1,000) 2012 35.9 33.3 20.9 11.4Crude Death Rate (per 1,000) 2012 8.9 10.9 7.8 10.1Infant Mortality Rate (per 1,000) 2011 76.0 71.4 46.4 6.0Child Mortality Rate (per 1,000) 2011 120.5 111.3 66.7 7.8Total Fertility Rate (per w oman) 2012 4.9 4.2 2.6 1.7Maternal Mortality Rate (per 100,000) 2006-2010 2054.0 417.8 230.0 13.7Women Using Contraception (%) 2012 6.1 31.6 62.4 71.4

Health & Nutrition Indicators

Phy sicians (per 100,000 people) 2004-2010 … 49.2 112.2 276.2Nurses (per 100,000 people)* 2004-2009 … 134.7 187.6 730.7Births attended by Trained Health Personnel (%) 2009 19.0 53.7 65.4 ...Access to Safe Water (% of Population) 2010 68.7 67.3 86.4 99.5Access to Health Serv ices (% of Population) 2000 … 65.2 80.0 100.0Access to Sanitation (% of Population) 2010 7.4 39.8 56.2 99.9Percent. of Adults (aged 15-49) Liv ing w ith HIV/AIDS 2011 … 4.6 0.9 0.4Incidence of Tuberculosis (per 100,000) 2011 146.0 234.6 146.0 14.0Child Immunization Against Tuberculosis (%) 2011 57.0 81.6 83.9 95.4Child Immunization Against Measles (%) 2011 64.0 76.5 83.7 93.0Underw eight Children (% of children under 5 y ears) 2010-2011 27.6 19.8 17.4 1.7Daily Calorie Supply per Capita 2009 … 2 481 2 675 3 285Public Ex penditure on Health (as % of GDP) 2010 … 5.9 2.9 8.2

Education Indicators

Gross Enrolment Ratio (%)

Primary School - Total 2010-2012 68.8 101.9 103.1 106.6 Primary School - Female 2010-2012 54.5 98.4 105.1 102.8 Secondary School - Total 2010-2012 4.2 42.3 66.3 101.5 Secondary School - Female 2010-2012 2.6 38.5 65.0 101.4Primary School Female Teaching Staff (% of Total) 2010-2011 12.3 43.2 58.6 80.0Adult literacy Rate - Total (%) 2009 27.0 67.0 80.8 98.3Adult literacy Rate - Male (%) 2009 40.0 75.8 86.4 98.7Adult literacy Rate - Female (%) 2009 16.0 58.4 75.5 97.9Percentage of GDP Spent on Education 2008-2010 ... 5.3 3.9 5.2

Environmental Indicators

Land Use (Arable Land as % of Total Land Area) 2011 7.6 10.7 10.8Annual Rate of Deforestation (%) 2000-2009 0.6 0.4 -0.2Forest (As % of Land Area) 2011 23.0 28.7 40.4Per Capita CO2 Emissions (metric tons) 2009 1.2 3.1 11.4

Sources : AfDB Statistics Department Databases; World Bank: World Development Indicators; last update :

UNAIDS; UNSD; WHO, UNICEF, WRI, UNDP; Country Reports.

Note : n.a. : Not Applicable ; … : Data Not Available.

COMPARATIVE SOCIO-ECONOMIC INDICATORS

South Sudan

May 2013

0102030405060708090

100

20

04

20

05

20

06

20

07

20

08

20

09

20

10

20

11

20

12

Infant Mortality Rate( Per 1000 )

South Sudan Africa

0

200

400

600

800

1000

1200

1400

1600

1800

20

03

20

04

20

05

20

06

20

07

20

08

20

09

20

10

20

11

GNI Per Capita US $

South Sudan Africa

0.0

1.0

2.0

3.0

4.0

5.0

6.0

20

04

20

05

20

06

20

07

20

08

20

09

20

10

20

11

20

12

Population Growth Rate (%)

South Sudan Africa

1

11

21

31

41

51

61

71

20

04

20

05

20

06

20

07

20

08

20

09

20

10

20

11

20

12

Life Expectancy at Birth (years)

South Sudan

Africa

Appendix II. ADB’s Portfolio in South Sudan

Project Sector

Date

Approved

Amount

(UA Million)

Disbursed

(UA Million)

%

Disbursed

Institutional Capacity Building for

Poverty Reduction and Good

Governance.

Governance 07 Mar 2007 6.48 4.69 72.4%

Enhancing the Capacity of the

University of Juba Education May 2011 0.32 0.14 42.8%

Public Finance Management and

Aid Coordination Finance 20 Dec 2012 4.80 0.00 0.00%

GRAND TOTAL AMOUNT 14.27 4.83 34%

Appendix III. Transport projects financed/planned to be financed by other DPs

SN Financier /Agency/ Project Title Status Start Date

Estimated

Project

Cost

Total Costs

Actual Commitments

Planned

Commitments

Actual

Expenditures

1 Multi Donor Trust

Fund

Sudan Emergency Transport and

Infrastructure Development Project (SETIDP) Completed 01/08/2006 30,195,000 9,141,000 2,011,350 8,543,191

2 Japan International

Cooperation Agency

Juba Urban Transport Infrastructure and

Capacity Development Study Completed 05/08/2008 4,000,000 400,000

400,000

3 Multi Donor Trust

Fund

Southern Sudan Road Maintenance Project

(SSRMP) Completed

40,000,000 35,400,000 115,000 38,279,472

4 Government of USA Yambio - Tambura; Ezo - Tambura Roads

(USAID) Completed 01/02/2008

5,817,882 371,324 5,462,637

5 Government of

France Support to civil aviation On-Going 20/07/2012 424,647 424,647

409,657

6 Japan International

Cooperation Agency

Strengthening the Management Capacity of

the South Sudan Inland Water Transport

Project in South Sudan

On-Going 01/03/2011 5,800,259 1,083,399 5,587,980 2,738,011

7 Government of USA Yambio-Tambura (185km) & Dabio-Ezo

(75km) Road Construction On-Going

37,935,517 15,755,000

8 Government of USA Juba-Nimule (192km) Road & Bridges

Construction On-Going

113,215,000

42,947,499

9 Government of USA Capacity Building to establish Southern Sudan

Roads Authority On-Going

13,850,000 11,600,000

5,306,469

10 Government of USA Sudan Infrastructure Services Project(SISP)

Roads and Bridges On-Going 01/01/2010

10,345,000

4,963,604

11 Japan International

Cooperation Agency

Capacity Development on Sustainable Road

Maintenance and Management in Juba On-Going

5,940,500 2,497,713 3,779,612 4,418,647

12 Japan International

Cooperation Agency

Construction of Nile River Bridge Basic -

Preparatory Survey On-Going 13/10/2010 1,272,382 1,422,851

1,428,769

13 Japan International

Cooperation Agency

Improvement of Juba River Port- Preparatory

Survey and Basic Design Survey On-Going 01/03/2010 1,150,362 1,172,773

1,188,295

14 Japan International

Cooperation Agency

Preparatory Survey on the Construction of

Lologo Bypass and Bridges in Juba City On-Going 18/03/2013 1,882,520

1,923,282 1,062,451

15 Sudan Recovery

Fund Round III: State Stabilisation Programmes On-Going 01/11/2010

3,977,123 5,795,421 4,398,290

16 Government of USA Economic Growth-Core Team Project

(USAID) On-Going 14/11/2011

115,427 1,866,434

17

United Nations

Office for Project

Services

Emergency Response Unit Sudan (OFDA) On-Going

3,000,000 4,498,619 1,001,381

18

United Nations

Office for Project

Services

World Food Programme Emergency

Operation: 200338 On-Going 01/01/2012 108,483,925 56,418,014

19 World Bank South Sudan Rural Roads Project On-Going 01/08/2012 38,000,000

38,000,000 221,574

20 Government of

France Support to the civil aviation sector Pipeline

50,000

21 Japan International

Cooperation Agency

The Project for Improvement of Juba River

Port Pipeline

32,382,040

26,645,543

22 European Union South Sudan Rural Development Programme

(SORUDEV) Pipeline

- 25,192,575

23 Government of the

Netherlands Food Security Project Pipeline

8,250,000

24 Japan International

Cooperation Agency Construction of Nile River Bridge Pipeline

93,433,912

74,049,463

25 Government of USA Pagak to Mathiang Road (USAID) Pipeline

7,137,173

26 Government of USA Yei-Morobo Feeder Road (USAID) Pipeline 01/03/2012

8,118,100

27 Government of USA Pagak to Uleng Road (USAID) Pipeline

7,137,173

Appendix IV. Profile of the Implementing Agency, Project Management

Unit (PMT)

The Project Management Team (PMT) of the Ministry of Transport, Roads and Bridges

(MoTRB) was established in 2006 by the Multi Donor Trust Fund (MDTF) as one of the

implementation requirements to execute all donors and Government funded projects

under the Ministry of Transport and Roads (MoTR). A consulting firm was hired to

establish the Unit that was supposed to have all sections to form the South Sudan Road

Authority over a period of three years, 2007-2009. The firm assigned one expert in each

section supported by two government staffs so that transfer of knowledge and skill can be

enhanced. After independence, the MoTR was split into two Ministries, leaving the PMT

to operate under the MoRB since most of the projects falls under MoRB. The two

Ministries were then merged again in July 2013. Figure 1 shows the organizational

structure of the PMT as it was established, but currently planning and contract

management sections are not in operation due to lack of staff as shown in Table 1.

Figure 1: Organizational structure of PMT

From 2009 to present, the PMT is managed by local staffs with Technical Assistance

support from time to time. Table 1 shows the current staff profile of PMT.

Table 1:. Staff profile of PMT

SN Section Number of staffs Qualification

1 Coordinator BSc in Civil Eng., P.Cert. Transport Planning and Practice, Master of

Law

2 Planning There is no staff in the section and it is not operational.

3 Engineering 5 local staffs BSc in Civil Eng.

1 local staff BSc in Surveying

4 Procurement 2 local staffs BSc in Civil Eng.

5 Contract Management There is no staff in the section and it is not operational.

6 Financial Management

1 Technical Assistance (World Bank); for April 2013-December 2014

2 local staffs BA in Administration and in

Accounting

7 Environment/Social

Monitoring (ESM)

1 local staff BSc in Environment management

1 Technical Assistance (World Bank); for the period of 2013-2013

After the contract period of the consulting firm engaged to establish the PMT, the World

Bank has provided various Technical Assistance supports attached to PMT. These

include supports in Project Financial Management over the period of 2009-2012,

preparation of ESIA Guidelines, Monitoring Tools and Manuals in January-June 2012,

M&E, FMS and Environmental & Social Management TAs to establish the

Environmental and Social Monitoring Unit in the PMT, as indicated in Table 1.

The PMT has handled projects at various responsibilities. Table 2 shows completed and

on-going projects handled by PMT.

Table 2: Projects handled by PMT

SN Title of project Period of

execution

Project cost

US$ Million

Completed Projects

1 Rehabilitation of gravel roads, 455 km 2007-2009 54.6

2 Maintenance of gravel roads, 1080 km 2007-2012 44.4

3 Feasibility and design of gravel roads, 1015 km 2007-2011 6.0

4 Inventory and Feasibility study of Rural Roads,

7000 km 2007-2010 3.13

5 TA to PMT(Maintenance Project) 2009-2012 3.0

6 TA to PMT (Establishment) 2007-2010 3.13

On-going Projects

4 Rehabilitation/maintenance of feeder roads, 450 km

@ $ 34.5m Financed by SSTTF, PMT Implementing Agency

5 Rehabilitation of feeder roads, 600 km Financed by SS Recovery Fund, Project

Management by WFP, PMT Review & Monitor

6 Rehabilitation/maintenance of feeder roads, 450

km@ $ 36 m

Financed by USAID, Project Management by

UNOPS, PMT Review & Monitor

7 Palouch-Pagak (300 km) road Design + build Government financed project; at procurement

stage, PMT is the Implementing Agency

Consultancy services

8 Environment and social impact assessment of

feeder roads

PMT is the Implementing Agency

9 Repackaging Juba-Nadapal road Project for OPRC

Contract

10 Procurement of Technical Assistance

11 Road Fund Study and RSDP

12 Establishment of Planning Unit under MRB

Appendix IV: Map of the Project Area

Note: The map on this page has been prepared by the AfDB Group’s staff exclusively for the convenience of

the readers of the report to which it is attached. The dimensions used and the boundaries shown on the map do

not imply on the part of the Group and its affiliates, any judgment on the legal status of any territory or any

endorsement or acceptance of such boundaries.

Legend

Juba-Mundri-Yambio Road Study

White Nile River

Not to Scale