south texas commission meetingftp.dot.state.tx.us/pub/txdot-info/adm/2013/documents/... ·...
TRANSCRIPT
Pharr District Commission Meeting
SOUTH TEXAS COMMISSION MEETING September 26, 2013
Pharr District Commission Meeting
Pharr District: Overview
The Pharr District plans, designs,
builds, operates and maintains the
state transportation system within its
eight counties.
The district is a coastal district, has
11 international crossings and is a
NAFTA corridor.
2
Population 1,291,048
Area (Sq. Miles) 8,812
Lane Miles 6,287.555
Daily Vehicle Miles 18,887.511
Registered Vehicles 898,491
TxDOT Employees 294
Pharr District Commission Meeting
Pharr District: Major Projects Underway
US 83 Super 2 highway (Zapata County, cost: $18.5 M)
US 281 Expressway Relief Route (Falfurrias-Brooks County, cost: $68 M)
FM 396 (Anzalduas International Bridge to I-2, cost: $23.4 M)
BSIF at US customs Port of Entry (South of Pharr, cost: $20.1 M)
I-69E Expressway Facility (Willacy County, cost: $25.7 M)
I-69E & SH 550 Direct Connectors (Cameron County, cost: $43.9 M)
3
Pharr District Commission Meeting
Pharr District: Planned Major Projects
2nd Access to South Padre Island
FY 14 Environmental clearance, est. cost $600 M
SH 365/ SH 68/IBTC
SH 365 – FY 16 at $138 M & SH 68 at $55 M
IBTC – ENV stages, est. cost $145 M
US 83 RELIEF ROUTE AT LA JOYA/PENITAS
FY 15 at est. cost $85 M
STARR CO. SL 195
FY 16 beginning of 17-mile relief route, est. cost $168 M
4
• Improve Economic Development
• Create A Better Quality Of Life For All
• Improve Mobility
• Relieve Congestion
• Ensure Efficient Trade Corridors
6
CCRMA Project Development List September 2013
Project Name Project Limits Project
Costs
Complete/
Under Const. Status
TOLL ROADS OPEN
SH 550 Phase I Overpass at UPRR and FM 1847 $ 7 Million $ 7.0 Million Phase 1 Toll Road Open
SH 550 North Port Spur FM 3248 to SH 48/New Port Entrance $ 34 Million $ 34.0 Million Phase 2 Toll Road Open PROJECTS COMPLETED
Olmito Switchyard Phase I North Brownsville/Olmito $ 22 Million $ 17.0 Million Construction Complete
Port Access Road SH 48/SH 550 to Capt. Donald Foust Road $ 3 Million $ 3.0 Million Construction Complete
Veterans International Bridge Expansion Over Rio Grande River at I-69E $ 6 Million $ 6.0 Million Construction Complete UNDER CONSTRUCTION
West Railroad Relocation I-69E and Olmito Switchyard into Mexico *$ 80 Million $ 80.0 Million 85% Complete
Olmito Switchyard Phase II North Brownsville/Olmito $ 3.6 Million $ 3.6 Million 95% Complete
CE Spur 56 Willacy County FM 1018 to FM 3168 $ 28 Million $ 28.0 Million 70% Complete
I-69E Sarita Overpass Sarita School Area $ 12 Million $ 12.0 Million 75% Complete
SH 550 Direct Connectors I-69E to SH 48 $ 44 Million $ 44.0 Million 30% Complete ENVIRONMENTALLY CLEARED
I-69E Brownsville to Corpus Christi $ 350 Million $ 185.0 Million $165 Million to Complete / EA Cleared ENVIRONMENTAL STUDIES
SH 32 East Loop Port of Brownsville to Veterans Bridge $ 90 Million EA Clearance 2014/$37M PTT Funds
General Brant Road FM 1847 to FM 510 $ 15 Million FY 2014 Letting
South Padre Island 2nd Access Mainland over Laguna Madre to Park Road 100 $ 465 Million FEIS in Progress
West Parkway I-69E to B&M Bridge $ 160 Million On Hold
FM 803 I-69E to SH 100 $ 6 Million EA at TxDOT – Funds in Place
North Cameron County Switchyard North of Harlingen near I-69E $ 25 Million Pending CE Preparation
North Railroad Relocation North Cameron County to SH 106 $ 60 Million Preliminary Study Complete
Outer Parkway I-69E near N. County Line to FM 1847 $ 180 Million Study in Progress
FM 509 Extension Outer Parkway to Current Section of FM 509 $ 7 Million EA Process in Progress
CORRIDOR STUDIES
Port Isabel Access Road SH 48 to Port of Port Isabel $ 3 Million Project under Design
281 Connector County Line to FM 1577 to I-69E & SH 100 $ 140 Million Planning Phase
Port International Bridge Project Port of Brownsville/East Loop into Mexico $ 50 Million Planning Phase with Mexico
TOTAL: $ 1.7 Billion $ 419.6 Million
*Includes Mexico Side
CCRMA Project Needs
http://www.hcrma.net
MASTER
PLAN
11
DEVELOP THE
INFRASTRUCTURE TO
SERVE A POPULATION
OF APPROXIMATELY
800,000 RESIDENTS
AND
FIVE INTERNATIONAL
PORTS OF ENTRY
ANZALDUAS
INT’L BRIDGE
PHARR-REYNOSA
INT’L BRIDGE
ALLIANCE
(DONNA-RIO BRAVO)
INT’L BRIDGE
HIDALGO-REYNOSA INT’L BRIDGE
PROGRESO
INT’L BRIDGE
http://www.hcrma.net
SH 365
PROJECT
PROGRESS
12
MILESTONES:
EA ENV CLASSIFICATION
DRAFT EA DOC @ LOCAL DISTRICT
BID DATE: 09/2015
CONST DATE: 12/2015
OPENING DATE: 08/2018 LIMITS PH1: FM 396/ANZALDUAS HWY TO US 281/MIL HWY (15.28 MI)
LIMITS PH2: FM 1016/CONWAY AVE TO FM 396/ANZALDUAS HWY (2.65 MI)
http://www.hcrma.net http://www.hcrma.net 13
SH 365
PROJECT
DETAIL
http://www.hcrma.net
IBTC
PROJECT
PROGRESS
14
MILESTONES:
UPDATED SCHEMATIC WITH LOW-LEVEL FLIGHT: OCT. 2013
LOCAL ENVIRONMENTAL CLEARANCE: EARLY 2014
BID DATE: 12/2016
CONST DATE: 04/2017
OPENING DATE: 11/2019 LIMITS: FROM US 83 (0.63 MI E OF FM 1423/VAL VERDE RD) TO FM 3072
(DICKER RD) AND TO FM 493 (1.5 MI N OF US 281). (12.60 MI)
http://www.hcrma.net http://www.hcrma.net 15
IBTC
PROJECT
DETAIL
http://www.hcrma.net
OVERWEIGHT
CORRIDOR
16
MILESTONES (EST.):
TEXAS HB 474 MADE
IT EFFECTIVE: 09/2013
DEVELOP WEB-BASED
PERMIT SYSTEM: 11/2013
TXDOT ADMINISTRATIVE
AGREEMENT BY: 12/2013
ISSUING PERMITS: 01/2014
ANZALDUAS
INT’L BRIDGE
PHARR-REYNOSA
INT’L BRIDGE
http://www.hcrma.net
OVERWEIGHT CORRIDOR IMPLEMENTATION Goal is to allow HCRMA to issue oversize and overweight permits online via HCRMA’s website for trucks
so that they may be in compliance with weights and measures as well with safety requirements.
Agreement with TxDOT (01/2014): HCRMA needs to negotiate an agreement with TXDOT for issuance of permits for the movement of overweight/oversize cargo and to collect a fee. HCRMA has reviewed existing overweight corridor agreements and will look to the Commission’s proposed
guidelines from the 09/2013 meeting.
Implementation of Web-based Permitting System (12/2013): HCRMA working with ProMiles to design and implement online permitting system to be made available through the HCRMA website.
Weight Scales in Mexico (03/2014): Getting scales in Mexico installed and operational
- Obtaining certification from PROFECO in Mexico for the weight scales about 1 month after installation. Weight scale operators/owners in Reynosa should also obtain certification from either Texas Dept. of Agriculture or one of their certified contractors to certify and calibrate weight scale. This can be done shortly after installation.
Border Safety Inspection Facility at the Pharr POE (04/2014)
17
Pharr District Commission Meeting
State Highway (SH) 68
18
10-mile, four-lane divided rural highway from US 83
(I-2) to FM 1925
North-south mobility corridor in central Hidalgo
County
Will improve mobility and relieve congestion on
US 281/I-69C and US 83/I-2.
Total estimated cost: $85 M
– $55 M for construction
– $6.5 M for PE
– $23.5 M for ROW/Utility
Proposed funding: Category 12
Estimated Construction Start Date: Mid-2016
Pharr District Commission Meeting
US 83 – La Joya Relief Route
19
Four-lane rural divided highway
Direct connectors provide nonstop access
to and from existing US 83 at both termini
Will provide improved east-west travel and
allow for through traffic to bypass
congested urban areas.
Estimated Cost: $83.5 M
Proposed Funding:
– Engineering $2.2 M, Category 12
– Construction $57.8 M ($34.54 M, TMFB
Category 3, $23.265 M, CBI)
– ROW/Compensable Utilities $23.5
million ($23.265 million Category 12,
$0.235 million Local)
Estimated Letting: April 2015
Pharr District Commission Meeting
Starr County Relief Route (State Loop 195)
Will significantly improve mobility
between the Rio Grande Valley and
Laredo.
Four-Lane divided rural non-toll
road with future overpasses at
select locations.
Estimated Cost: $168 M
Proposed Partial Funding:
– $ 6.0 M border infrastructure
funds
Estimated Letting: June 2016
(Phase I from FM 755 to FM 3167)
20
Pharr District Commission Meeting
Expand the approaches to the interchange to two lanes.
– Two alternatives are being considered to accommodate two-lane direct connectors: (1) leave the direct connector bridges in place and re-stripe them to two lanes or (2) reconstruct the bridges to accommodate two lanes and wider shoulders.
Phase 1: Edinburg to McAllen and McAllen to Edinburg directions (west side of interchange)
Phase 2: Edinburg to Harlingen and Harlingen to Edinburg directions (east side)
Estimated Letting: Early 2016
US 83 (I-2) US 281 (I-69) Interchange
21