southern natural gas company, l.l.c. shipper meeting€¦ · 2016 summer overview • sng’s...

301
1 Southern Natural Gas Company, L.L.C. Shipper Meeting October 12-13, 2016 The Sheraton Hotel Birmingham, Alabama

Upload: others

Post on 26-Jul-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

1

Southern Natural Gas Company, L.L.C. Shipper Meeting

October 12-13, 2016

The Sheraton Hotel

Birmingham, Alabama

Page 2: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

2

Welcome and Opening Remarks

Norman Holmes President, South Region

SNG Shipper Meeting Birmingham, AL ▪ October 12, 2016

Page 3: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

3

Agenda

• Operations Review – Ganesh Venkateshan, Gas Control Manager

• Business Development Updates – Mike Varagona, VP of Business Development

• NAESB & DART Updates – Gene Nowak, VP of Transportation & Storage Services

• Announcements and Remaining Agenda – Janice Parker, Commercial Director

Page 4: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

4

SNG Rate Case Timing

• Per 2013 Rate Case Settlement, SNG must file new rates to be effective 9/1/18

– Base period of 12/1/16 - 11/30/17

– Test period of 12/1/17 – 8/31/18

• We will try to reach a pre-filing settlement

– Similar process to 2013

– Will begin customer settlement discussions in fall of 2017

• SNG will file a rate case on 3/1/18 if pre-settlement efforts fail

Page 5: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

5

Questions?

Thank You for Your Business!

Page 6: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

6

SNG Operations Review

Ganesh C. Venkateshan Manager, SNG Gas Control

SNG Shipper Meeting

Birmingham, AL ▪ October 12, 2016

Page 7: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

7

Agenda

• System and Transportation Overview • Operations Review

• 2016 Summer Review • 2015-2016 Winter Review • Operational Flow Orders • Maintenance Update

• Getting Ready for Winter 2016/2017

Page 8: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

8

SNG System Overview

South Main

North Main

Cypress Line

East Leg

West Leg

SESH South Georgia

1.8 bcf/d capacity

2.4 bcf/d North Louisiana

Zone 0 Zone 1 Zone 2 Zone 3

Elba Express

Ocmulgee

Gwinville

Wrens

Enterprise Elba Island

Bear Creek

Muldon

• Miles of pipe 7,000 miles

• Flow meters 550

• Total HP 560,000

• Total compressor stations 36

Approximate values

• SNG winter capacity 3.9 Bcf/d

• Winter peak day delivery 1/8/10 4.149 MMDth

• Summer peak power gen 6/13/16 1.746 MMDth

• Total storage fields 2

• Storage working capacity 65.6 Bcf

Approximate values

Page 9: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

9

2016 Transportation YTD September

• 2016 Transport Summary – Power Generation markets are up 3.5% from 2015

• New power generation record (previously set in 2012) • Increases driven by lower Henry Hub pricing which drove fuel switching in

Southeastern U.S.

– Lower gas prices • Driven primarily by higher storage inventories and available flowing supply

– Total System Deliveries averaged 2,612 MDth/d • Slightly greater than 2015

– Moved to the DART computer system and pathed nominations in April – Storage is on track to fill to average levels in November – Outages completed on a timely schedule

Page 10: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

10

CSS Storage Inventory

0

10

20

30

40

50

60

J F M A M J J A S O N D

MD

th

2006-2014 2012 2015 Capacity Average 2016

Customer CSS Inventory

Page 11: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

11

Average Daily Deliveries

943 977 953 853 962 885 827 884 959 975 926

312 417 378 559

617 684 1,004 899

887 1,067 1,105

206 196 204

199

233 243

247 237 236

240 221

478 488 543 461

432 358

355 282

311

288 360

1,938 2,078 2,078 2,072

2,243 2,170

2,433 2,302

2,393

2,570 2,612

0

500

1,000

1,500

2,000

2,500

3,000

2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016

Md

th/d

LDC Power Industrial Interconnects

YTD - SEP

Page 12: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

12

Year on Year Deliveries Sept YTD 2016 YTD

September 2015 YTD

September % Change

LDC 926 975 -5.0%

Power 1,105 1,067 +3.5%

Industrial 221 240 -8.1%

Interconnects 360 288 +25.0%

TOTAL 2,612 2,570 +1.6%

• All volumes are MDth/d

Page 13: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

13

2016 Summer Review

Page 14: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

14

2016 Summer Overview

Month

Throughput Comparison to Same Month Previous Year

No. of Type 3

OFO Days

Weather

May 2016 8.1% higher 0 Slightly warmer than avg

June 2016 9.0% higher 16 Much warmer than avg

July 2016 6.2% higher 26 Much warmer than avg

August 2016 7.1% higher 24 Much warmer than avg

September 2016 6.7% higher 0 Much warmer than avg

• Type 3 OFOs are implemented to protect primary firm service when demand for transportation exceeds pipeline capacity

• All industry segments continue to add to and use their firm capacity

Page 15: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

15

2016 Summer Overview

• SNG’s facility performance was good during the extended hot weather – Compressor stations were staffed as needed

• Record power generation

• 2015 Summer vs 2016 Summer

– 2015 – milder than this year, shorter duration, lower gas prices – 2016 – higher temperatures, longer duration, lower gas prices

• Storage levels were higher than normal but facilities performed well

• 3-month Thomaston Compressor Station outage was completed as scheduled

without limiting in-path or primary firm service. We also had other planned outages and ILI runs to manage.

Page 16: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

16

Summer Weather and Throughput

Page 17: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

17

Summer Cooling Degree Days (CDDs*) 2010-2016

*CDD = System Mean Temperature Minus 65 Degrees

220

484

597 562

426

221

418

467 470

281

0

100

200

300

400

500

600

700

May June July August September

2011 2012 2013 2014 2015 2016 10 Year Average

CD

Ds

Page 18: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

18

Impact of Summer Weather on Total Demand

0

100

200

300

400

500

600

700

0

500

1,000

1,500

2,000

2,500

3,000

3,500

11

/01

/10

01

/01

/11

03

/01

/11

05

/01

/11

07

/01

/11

09

/01

/11

11

/01

/11

01

/01

/12

03

/01

/12

05

/01

/12

07

/01

/12

09

/01

/12

11

/01

/12

01

/01

/13

03

/01

/13

05

/01

/13

07

/01

/13

09

/01

/13

11

/01

/13

01

/01

/14

03

/01

/14

05

/01

/14

07

/01

/14

09

/01

/14

11

/01

/14

01

/01

/15

03

/01

/15

05

/01

/15

07

/01

/15

09

/01

/15

11

/01

/15

01

/01

/16

03

/01

/16

05

/01

/16

07

/01

/16

09

/01

/16

CD

Ds

Md

th/d

Avg Daily Demand CDD

Page 19: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

19

Average Daily Deliveries May – September

751 756 705 635 659 683 720 670 711 738 728

470 540 499 621

764 822

1,115 917

1,036 1,154 1,264 209

195 204 205

230 244

237

237 233

246 217

563 612

592 536 481 354

369

276

306 273

382

1,993 2,103

2,000 1,997 2,134 2,103

2,441

2,100

2,286 2,411

2,591

0

500

1,000

1,500

2,000

2,500

3,000

2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016

Md

th/d

LDC Power Industrial Interconnects

MAY - SEP

Page 20: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

20

2016 Summer Throughput

• Total System Deliveries averaged 2,591 MDth/d • 180 MDth/d greater than 2015 summer

• Peak power generation days for 2016 – 06/13/16 1,746 MDth – 07/25/16 1,693 MDth – 07/08/16 1,680 MDth

• SNG set several Power Demand Records this summer – Top 5 days – 9 out of top 10 days – 15 out of top 20 days

• Power Generation increase – Driven by Henry Hub pricing which drove fuel switching in southeastern U.S. – Warmer than average summer

Page 21: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

21

May-Sep 2016 Throughput 2016

May – Sep

2015

May – Sep % Change

LDC 728 738 -1.4%

Power 1,264 1,154 +9.5%

Industrial 217 246 -12.0%

Interconnects 382 273 +39.7%

TOTAL 2,591 2,412 +7.4%

• All volumes are MDth/d

Page 22: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

22

Summer Average Daily LDC Demand

0

100

200

300

400

500

600

700

800

900

May Jun Jul Aug Sep

2012 2013 2014 2015 2016

Md

th/d

Page 23: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

23

Summer Average Daily Power Demand

0

200

400

600

800

1,000

1,200

1,400

1,600

May Jun Jul Aug Sep

2012 2013 2014 2015 2016

Md

th/d

Page 24: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

24

Summer Deliveries By Year

0

500

1,000

1,500

2,000

2,500

3,000

2012 2013 2014 2015 2016

May June July August September

Avg Dels = 2,591 CDDs = 2,289

Md

th/d

Avg Dels = 2,441 CDDs = 1,871

Avg Dels = 2,100 CDDs = 1,583

Avg Dels = 2,286 CDDs = 1,784

Avg Dels = 2,411 CDDs = 1,818

Page 25: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

25

Power Generation in the Summer Has a Strong Correlation to Weather

0

100

200

300

400

500

600

700

0

200

400

600

800

1,000

1,200

1,400

1,600

11

/01

/10

01

/01

/11

03

/01

/11

05

/01

/11

07

/01

/11

09

/01

/11

11

/01

/11

01

/01

/12

03

/01

/12

05

/01

/12

07

/01

/12

09

/01

/12

11

/01

/12

01

/01

/13

03

/01

/13

05

/01

/13

07

/01

/13

09

/01

/13

11

/01

/13

01

/01

/14

03

/01

/14

05

/01

/14

07

/01

/14

09

/01

/14

11

/01

/14

01

/01

/15

03

/01

/15

05

/01

/15

07

/01

/15

09

/01

/15

11

/01

/15

01

/01

/16

03

/01

/16

05

/01

/16

07

/01

/16

09

/01

/16

CD

D*

Md

th/d

Daily Power Demand CDD

*Cooling Degree Day (CDD) = System Mean Temperature Minus 65 Degrees

Page 26: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

26

But Power Demand is Also Impacted by Gas Prices

$0.00

$1.00

$2.00

$3.00

$4.00

$5.00

$6.00

$7.00

0

200

400

600

800

1,000

1,200

1,400

1,600

11

/01

/10

01

/01

/11

03

/01

/11

05

/01

/11

07

/01

/11

09

/01

/11

11

/01

/11

01

/01

/12

03

/01

/12

05

/01

/12

07

/01

/12

09

/01

/12

11

/01

/12

01

/01

/13

03

/01

/13

05

/01

/13

07

/01

/13

09

/01

/13

11

/01

/13

01

/01

/14

03

/01

/14

05

/01

/14

07

/01

/14

09

/01

/14

11

/01

/14

01

/01

/15

03

/01

/15

05

/01

/15

07

/01

/15

09

/01

/15

11

/01

/15

01

/01

/16

03

/01

/16

05

/01

/16

07

/01

/16

09

/01

/16

SNG

Ind

ex P

rice

Md

th/d

Daily Power Demand SNG Index Price

Page 27: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

27

Atlanta Area Summer Cooling Degree Days (CDDs)

CDD = System Mean Temperature Minus 65 Degrees

Actual Actual

CDDs % of Normal CDDs % of Normal

May 206 112% 263 143%

Jun 473 127% 446 120%

Jul 559 119% 517 110%

Aug 540 121% 470 105%

Sep 408 91% 266 100%

2186 126% 1962 113%

2016 2015

Page 28: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

28

2015-2016 Winter Review

Page 29: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

29

2015-16 Winter Overview

Month

Throughput Comparison to Same Month Previous Year

No. of Type 3

OFO Days

Weather

November 2015 7.8% lower 1 Much milder than avg

December 2015 10.9% lower 0 Much milder than avg

January 2016 0.8% lower 15 Slightly colder than avg

February 2016 12.9% lower 8 Slightly milder than avg

March 2016 7.1% lower 0 Much milder than avg

• Type 3 OFOs are implemented to protect primary firm service when demand for transportation exceeds pipeline capacity

• All industry segments continue to add to and use their firm capacity

* Unplanned maintenance during average winter weather may require a Type 3 OFO

Page 30: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

30

2015-16 Winter Overview

• SNG’s facility performance was good during the winter – Compressor stations staffed 24x7 as needed

• 2014-2015 Winter vs 2015-2016 Winter

– 2014-15 – multiple, longer duration cold fronts, lower gas prices – 2015-16 - milder temperatures, shorter-lived cold fronts, lower gas prices

• Storage facilities performed well; more inventory than average

• The amount of large planned maintenance projects in 2016 caused SNG to start its

maintenance season in late February to take advantage of milder temperatures forecasted for March

• Flowing supply was at a similar level to the previous year but the mix was slightly different

Page 31: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

31

Texas

Oklahoma Elba

Island

Muldon

Bear

Creek

Elba Express

NW Alabama 2016 153 MMcf/d 2015 174 MMcf/d 2011 237 MMcf/d 2008 262 MMcf/d

North Louisiana 2016 213 MMcf/d 2015 209 MMcf/d 2011 281 MMcf/d 2008 279 MMcf/d

All Other 2016 347 MMcf/d 2015 250 MMcf/d 2011 167 MMcf/d 2008 41 MMcf/d

West Leg 2016 587 MMcf/d 2015 632 MMcf/d 2011 640 MMcf/d 2008 562 MMcf/d

East Leg 2016 336 MMcf/d 2015 379 MMcf/d 2011 375 MMcf/d 2008 648 MMcf/d

Total Supply 2016 2,506 MMcf/d 2015 2,503 MMcf/d 2011 2,240 MMcf/d 2008 2,093 MMcf/d

EEC/SLNG 2016 134 MMcf/d 2015 130 MMcf/d 2011 132 MMcf/d 2008 301 MMcf/d

Shale Interconnects 2016 736 MMcf/d 2015 729 MMcf/d 2011 408 MMcf/d 2008 0 MMcf/d

SNG System Supplies By Major Location Average Daily Supply for 12 Months Ending March

Page 32: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

32

Winter Weather and Throughput

Page 33: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

33

Winter Heating Degree Days (HDDs*) 2011-2016

*HDD = 65 Degrees Minus System Mean Temperature

253 267

665

456

157

321

557 607

461

293

0

100

200

300

400

500

600

700

800

900

November December January February March

2011/12 2012/13 2013/14 2014/15 2015/16 30 Year Average

HD

Ds

Page 34: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

34

Impact of Winter Weather on Total Demand

0

100

200

300

400

500

600

700

800

900

0

500

1,000

1,500

2,000

2,500

3,000

3,500

11

/01

/10

01

/01

/11

03

/01

/11

05

/01

/11

07

/01

/11

09

/01

/11

11

/01

/11

01

/01

/12

03

/01

/12

05

/01

/12

07

/01

/12

09

/01

/12

11

/01

/12

01

/01

/13

03

/01

/13

05

/01

/13

07

/01

/13

09

/01

/13

11

/01

/13

01

/01

/14

03

/01

/14

05

/01

/14

07

/01

/14

09

/01

/14

11

/01

/14

01

/01

/15

03

/01

/15

05

/01

/15

07

/01

/15

09

/01

/15

11

/01

/15

01

/01

/16

03

/01

/16

HD

Ds

Md

th/d

Avg Daily Demand HDD

Page 35: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

35

Average Daily Deliveries January – March 2006-16

1,318 1,350 1,397 1,247

1,559 1,280

1,048 1,291 1,415 1,430 1,307

86 243 250 474

452

501 844

891 679

979

884

202

197 212 191

227

236 259

241 239

239

225

340

331 449 314

380

352 299

294 318

320

320

1,946

2,122

2,308 2,226

2,618

2,369 2,450

2,717 2,651

2,968

2,737

0

500

1,000

1,500

2,000

2,500

3,000

2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016

Md

th/d

LDC Power Industrial Interconnects

JAN - MAR

Page 36: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

36

2015-2016 Winter Throughput

• Peak throughput days for Winter 2015/16 – 01/11/16 3.910 MMDth

– 01/05/16 3.832 MMDth

– 02/09/16 3.736 MMDth

– January 11 was 6th highest throughput day in SNG history

– 2015-16 winter accounted for 3 of the Top 25 highest throughput days in SNG history

• Power generation daily quantities were lower than last winter but higher than average

Page 37: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

37

Nov-Mar Throughput Comparison 2015/16

Nov – Mar

2014/15

Nov – Mar % Change

LDC 1,156 1,365 -15.3%

Power 919 945 -2.7%

Industrial 229 236 -3.2%

Interconnects 309 286 +7.9%

TOTAL 2,613 2,832 -7.7%

• All volumes are MDth/d

Page 38: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

38

Winter Average Daily LDC Demand

0

200

400

600

800

1,000

1,200

1,400

1,600

1,800

Nov Dec Jan Feb Mar

2012/13 2013/14 2014/15 2015/16

Md

th/d

Page 39: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

39

Winter Average Daily Power Demand

0

200

400

600

800

1,000

1,200

Nov Dec Jan Feb Mar

2012/13 2013/14 2014/15 2015/16

Md

th/d

Page 40: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

40

Atlanta Area Winter Heating Degree Days (HDDs)

HDD = 65 Degrees Minus System Mean Temperature

Actual Actual

HDDs % of Normal HDDs % of Normal

Nov 230 68% 474 140%

Dec 252 41% 456 74%

Jan 698 104% 672 100%

Feb 457 91% 683 136%

Mar 178 52% 237 69%

1815 73% 2522 109%

2015/16 2014/15

Page 41: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

41

Operational Flow Orders (OFOs)

Page 42: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

42

Type 3 OFO Overview Winter 2015-16

• Type 3 Operational Flow Orders (OFOs) are implemented when demand is forecasted to exceed capacity

– OFOs are used to protect primary firm services

• System conditions dictate the level of interruptible reductions and OFOs needed

• Winter 2016 constraints primarily occurred on the South System through

– East of Enterprise Compressor Station (east MS)

– East of Ellerslie Compressor Station (west GA)

Page 43: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

43

Segment Restrictions & Type 3 OFO Factors • Factors SNG considers when evaluating whether to implement Segment Restrictions

and/or Type 3 OFO penalties: – Weather Forecast – system means in the mid-40’s and mid-80’s are where demand starts to approach

capacity

– Day of week – weekday demand exceeds weekend/holiday demand

– Expected duration of heavy demand

– Recent history

– Nominated deliveries

– Actual takes from the system higher than entitlements

• Factors considered in scheduling once Segment Restrictions or Type 3 OFO is implemented: – Contracted No Notice – doesn’t have to be nominated and forecasted usage needs to be reserved

– Receipts downstream of constraint increase SNG’s ability to deliver

– Actual takes from the system vs entitlements

– Expected duration of heavy demand

Page 44: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

44

Maintenance Update

Page 45: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

45

Maintenance Planning Process • Typical types of planned work

Compressors: • ESD and safety tests • Emission tests • Run-hour inspections &

maintenance to insure reliability

• Various engine/compressor repairs

Integrity Management: • Various pig runs (ILI) • Remediation of anomalies • Hydrotests • Selected wrinkle bend

replacements

3rd Party Needs: • Class location changes • Line relocations • Expansion projects Storage Field: Shut-in tests & maintenance – spring & fall

• Gas Control models impact to capacity and compares against expected flow to determine best outage windows

• Goal is to avoid impact to firm service that we forecast to be needed or coordinate with the customer(s) to manage the impact

• Plan may need to be adjusted to account for unscheduled outages, multiple outages, equipment availability, contractors, weather, and other items out of our control

Page 46: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

46

Maintenance Communication

• Annual Maintenance Posting provided by March each year

• Updated Monthly

– Via EBB posting and Customer WebEx held prior to bid week

• Maintenance Contacts

Ganesh Venkateshan – Manager (713) – 420 – 2099 (office) (832) – 980 - 8296 (cell) [email protected]

Kal Dankovich – Outage Coordinator (713) – 420 – 7522 (office) (713) – 420 – 7305 (Gas Control) [email protected]

Jimmy Reese – Lead Controller (713) – 420 – 7310 (office) (713) – 420 - 7305 (Gas Control) [email protected]

Daniel Mitchell – Lead Controller (713) – 420 - 5874 (office) (713) – 420 – 7305 (Gas Control) [email protected]

Page 47: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

47

2016 SNG Maintenance Program

Overview # of Jobs

System Total 922

Posted 67

Posted (with possible impact) 36

Posted (no impact expected but risks could develop)

31

South Main lines 30

North Main lines 33

Other lines 4

Page 48: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

48

Remaining Major Projects

• Elba Express Company (EEC) Expansion project planned tie-in work – October 17-25; multiple segment outages with a full outage some days – Scheduled during low flow period and bundled projects to minimize duration

• Storage maintenance – Muldon shut in test completed (Oct 4-11) – Bear Creek shut in test Oct 18-25

• New Item: SNG is developing a repair plan for its 20” Wrens-Savannah 2nd Loop Line and is evaluating the capacity impact on Segment 580 (see Critical Notice 700476) – Line is currently at a reduced pressure

Page 49: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

49

Getting Ready for Winter 2016-17

Page 50: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

50

Preparing for Winter 2016-17

• Readiness testing on HP will be completed before winter

• Storage fields will be ready

• Plan is to complete maintenance projects by November

• OFO philosophy will remain consistent with past years

• Expected pipeline flows:

• Continued strong power loads

• Traditional supply basins should remain consistent with 2015-16 flows

• Weather is forecasted to be cooler than normal which will increase LDC loads

• Departmental contact information is provided in your meeting packet – do not hesitate to call us

Page 51: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

51

Questions?

Thank You for Your Business!

Page 52: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

52

Business Development Project Updates

Mike Varagona Vice President, Business Development

SNG Shipper Meeting

Birmingham, AL ▪ October 12, 2016

Page 53: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

53

Forward Looking Statements This presentation contains forward-looking statements. These forward-looking statements are identified as any statement that does not relate strictly to historical or current facts. In particular, statements, express or implied, concerning future actions, conditions or events, future operating results or the ability to generate revenues, income or cash flow or to pay dividends are forward-looking statements. Forward-looking statements are not guarantees of performance. They involve risks, uncertainties and assumptions. Future actions, conditions or events and future results of operations of Kinder Morgan, Inc. may differ materially from those expressed in these forward-looking statements. Many of the factors that will determine these results are beyond Kinder Morgan's ability to control or predict. These statements are necessarily based upon various assumptions involving judgments with respect to the future, including, among others, the ability to achieve synergies and revenue growth; national, international, regional and local economic, competitive and regulatory conditions and developments; technological developments; capital and credit markets conditions; inflation rates; interest rates; the political and economic stability of oil producing nations; energy markets; weather conditions; environmental conditions; business and regulatory or legal decisions; the pace of deregulation of retail natural gas and electricity and certain agricultural products; the timing and success of business development efforts; terrorism; and other uncertainties. There is no assurance that any of the actions, events or results of the forward-looking statements will occur, or if any of them do, what impact they will have on our results of operations or financial condition. Because of these uncertainties, you are cautioned not to put undue reliance on any forward-looking statement. Please read "Risk Factors" and "Information Regarding Forward-Looking Statements" in our most recent Annual Report on Form 10-K and our subsequently filed Exchange Act reports, which are available through the SEC’s EDGAR system at www.sec.gov and on our website at www.kindermorgan.com.

Page 54: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

54

U.S. Energy Renaissance

• Over the past 10 years, the U.S. has seen significant growth in its energy reserves, and the potential for energy self-sufficiency has greatly improved

BUT

Shale Technology Energy Renaissance

Page 55: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

55

Regulatory Environment is Hostile

• Aggressive opposition to almost all fossil fuel energy infrastructure development is now commonplace

• Regulators, politicians, courts – influenced/ all being affected by opposition tactics

• Permitting process filled with uncertainties

• Many projects already delayed/cancelled

– TransCanada's Keystone XL pipeline

– TGP’s Northeast Direct

– Spectra’s Constitution

• Industry efforts to counter the negative movement have thus far been ineffective

• Inevitably costs will rise and project timelines will lengthen

Page 56: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

56

Immediate Effects Close to Home

• The SNG/EEC expansion project was filed in March of 2014 with an expected in-service of June 2016

• The project completion is now expected to occur in December of

2016 - approximately 2.75 years after the filing – a year longer than the historical norm

• The rule of thumb that a pipeline project should take approximately

12 months to permit and 9 months to construct is simply no longer a reasonable paradigm, and the timing uncertainty associated with obtaining a permit has increased significantly

Page 57: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

57

Changing Supply and Demand

Macro View

Page 58: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

58

Shale Gas Growth

Source: ICF International Base Case, July 2016

ICF Projection

Page 59: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

59

Changing Demand

Source: ICF International Base Case, July 2016

Page 60: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

60 Source: ICF International Base Case, July 2016

MIDCON 13.3 13.2 -0.1%

Changing Supply Demographics

Page 61: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

61

Pipeline Infrastructure Response Potential Capacity Additions by Corridor

Source: Industry research

Pipeline Project ISD MMcf/d

SOUTH VIA ATLANTIC – 5.1 Bcf/d

SNG SNG/EEC Expansion 2016 409

Transco Atlantic Sunrise 2018 1,200

Transco Dalton Expansion 2017 448

Dominion Atlantic Coast 2018 1,500

EQT/NextEra Mountain Valley 2018 1,500

Pipeline Project ISD MMcf/d

EAST – 2.7 Bcf/d

AGT AIM 2016 340

Tennessee Connecticut Expansion 2017 72

AGT Atlantic Bridge 2017 153

PennEast PennEast 2018 1,000

National Fuel Northern Access 2017 497

Tennessee Invenergy 2018 180

Transco Atlantic Sunrise 2018 500

Pipeline Project ISD MMcf/d

WEST – 0.4 Bcf/d

Dominion Lebanon West Ph 2 2016 130

Tennessee Susquehanna West 2017 145

Tennessee Orion 2018 135

Pipeline Project ISD MMcf/d

MIDWEST/NORTH VIA OHIO –5.8 Bcf/d

REX Z3 Capacity Enhancement 2016 800

Spectra NEXUS 2018 1,500

Energy Transfer Rover 2017 3,500

Pipeline Project ISD MMcf/d

GULF VIA OHIO - 6.7 Bcf/d

CGT Leach Xpress 2016 1,500

TETCO Gulf Markets 2016 250

CGT Utica Access 2016 205

Texas Gas Northern Supply Access 2017 384

TETCO Gulf Markets II 2017 400

TETCO AIDAIR Southwest 2017 200

TETCO Lebanon Extension 2017 100

Tennessee Susquehanna West 2017 145

TETCO Access South 2017 320

NGPL Gulf Coast Southbound 2018 460

Tennessee Broad Run Expansion 2018 200

CGT WB Express 2018 1,300

CGT Mountaineer Express 2018 1,400

2.7 Bcf/d

0.4 Bcf/d

5.8 Bcf/d

Page 62: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

62 Source: ICF International Base Case, July 2016

3.0

Supply to Market Corridor Flow Patterns 2015 vs. 2025

Page 63: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

63

Elba Liquefaction Project (ELC+SLNG)

EEC Expansion (Liquefaction and Non-liquefaction)

SNG Zone 3 Expansion via EEC

SNG to South Georgia Expansion

Texas Eastern to SNG Interconnection

EEC Expansion

ELC/SLNG Liquefaction

SNG Expansion

SNG to So Ga Expansion

Texas Eastern Interconnection

SNG Related Projects in Progress

Page 64: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

64

Expansion Drivers

• Demand growth and supply constraints east of Ocmulgee on SNG

• Export and capacity monetization opportunities for subscriber of Elba Island

Page 65: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

65

SNG Pipeline System Neck-down East of Ocmulgee

South Main

North Main

Cypress Line

East Leg

West Leg

SESH South Georgia

1.8 bcf/d capacity

2.4 bcf/d capacity

North Louisiana

Zone 0 Zone 1 Zone 2 Zone 3

Elba Express

Ocmulgee

Gwinville

Wrens

Enterprise Elba Island

Bear Creek

Muldon

Ellerslie

Page 66: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

66 Plot Plan

Elba Liquefaction Project

66

• Install 10 Moveable Modular Liquefaction Systems • Total Liquefaction Capacity 357,350 MMBtu/d

Page 67: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

67

Liquefaction Project Update

• On June 1, 2016 ELC and SLNG received a favorable FERC order

• Sierra Club and two individuals filed timely requests for rehearing

• Awaiting FERC decision on rehearing

• Expect to commence construction 4th quarter

• Expected in-service mid 2018

Page 68: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

68

EEC Pipeline A Conduit for East End Supply to SNG

South Main

North Main

East Leg

West Leg

SESH South Georgia North Louisiana

Zone 0 Zone 1 Zone 2 Zone 3

Elba Express

Pipeline

SLNG

(Elba

Island)

Bear Creek Storage

Muldon Storage

Interconnects with Transco *

Southern Natural Gas Company *

Elba Express Pipeline (North to South from Transco) • 190 Miles of Pipeline w/ 10,000 HP compression • 225 MDth/d existing firm (Transco to Savannah) • Expansion underway resulting in approximately 400 -

500 MDth/d of Zone 3 gas supply available for SNG

GLNG

Page 69: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

69

SNG/EEC Expansion Facilities

• Expansion for 10 firm SNG customers and 6 firm EEC customers • 853,045 MMBtu/d of incremental firm • Adding over 130,000 HP at new and existing compressor stations • Adding approximately 3 miles of 36 inch loop upstream of Gallion • Adding meters, regulators, coolers and other ancillary equipment

EEC/SNG Expansions

Riceboro

Brookman

Hilliard.

Thomaston

Hartwell

Jefferson

Rincon Gallion

Page 70: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

70

EEC and SNG Zone 3 Expansions

• In conjunction with the Liquefaction Project, the anchor shipper contracted with EEC to reverse flow and transport gas from the Transco interconnects to the Elba Island facility

– EEC (Feb 17) 190,927 MMBtu/d (liquefaction) – EEC (TBD 18) 102,100 MMBtu/d (liquefaction) – EEC (TBD 18) 142,940 MMBtu/d (liquefaction) – Total 435,967 MMBtu/d

• SNG and EEC held general open seasons in August of 2013 with a follow-up open season on SNG in March 2014

– EEC (Dec16) 175,410 MMBtu/d (6 customers) – SNG (Dec16) 216,500 MMBtu/d * (10 customers) – SNG (Jun17) 25,169 MMBtu/d * (incremental volume for 1 customer) – Total 417,079 MMBtu/d * – New Incremental 853,045 MMBtu/d – Existing Capacity 224,620 MMBtu/d – Grand Total N to S 1,077,665 MMBtu/d * Volumes reflect deliveries out of EEC into SNG

Liquefaction Related

Non - Liquefaction Related

Page 71: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

71

Cumulative Net Volume Buildup

224,620 224,620 224,620 224,620 224,620

216,500 216,500 241,668 241,668

190,927

435,967

175,410

175,410 175,410

175,410

0

200,000

400,000

600,000

800,000

1,000,000

1,200,000

Now Dec-16 Feb-17 Jun-17 TBD-18

MM

Btu

/d

Other EEC

EEC to Elba

SNG Expansion

Now EEC to SNG

Potential to flow into SNG

+391,910 +245,040

224,620

832,625

1,077,665

616,530

+190,927 Total added +853,045 MMBtu/d

807,457

+25,168

190,927

Page 72: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

72

EEC and SNG Expansions – 2016/17/18

1. Net after turnback of 130,000 Dth/d is 611,377 Dth/d 2. SNG has subscribed for upstream capacity on EEC for these

customer volumes (plus fuel) in order to provide seamless SNG service from the Transco receipt points with EEC, through EEC to SNG delivery points

Pipeline Customer Year Dth/d Mcf/d Term EEC Shell 2017/18 435,967 427,000 23/24 EEC Effingham County Power 2016 86,000 84,231 15 EEC MGAG 2016 2,910 2,850 15

EEC BG (thru 3/2019) and SCE&G (remaining term) 2016 61,500 60,235 15

EEC Southern Company 2019 130,000 127,326 12

EEC BG (thru 3/2019) and Southern Co (remaining term) 2016 25,000 24,486 15

EEC SNG 2016 See Below Below Below Total EEC (w/o SNG) 741,377 726,128 /1

Net of turnback 611,377 598,802 Pipeline Customer Year Dth/d Mcf/d Term

SNG Weyerhaeuser 2016 2,144 2,100 10 SNG Atlanta Gas Light 2016 40,000 39,177 10 SNG PCS Nitrogen 2016 6,637 6,500 10 SNG MGAG 2016 3,574 3,500 10 SNG Peoples Gas 2016/17 50,000 48,972 20 SNG JEA 2016 55,000 53,869 15 SNG Rayonier 2016 12,763 12,500 10 SNG BASF 2016 14,131 13,840 10 SNG Southern Company 2016 25,000 24,486 15 SNG International Paper 2016 30,800 30,166 10

Total SNG Transport /2 240,049 235,110 Into SNG out of EEC 241,668 236,698

Page 73: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

73

Seamless Service Using EEC Capacity

• To provide new FT service to its customers, SNG has contracted with EEC for FT capacity – SNG’s 10 expansion shippers have capacity from the EEC/Transco Zone

4 or 5 receipt point(s) to the shipper’s delivery point(s)

• The SNG shippers will submit nominations to SNG and SNG will nominate on EEC on their behalf (i.e., seamless service) – Shippers’ nominations will incur pancaked fuel

• EEC’s expansion fuel is estimated at 1% but will be filed soon

• For more information: – Please attend the Contracts/Capacity Release breakout session and

the Scheduling breakout session – Call your Account Manager or Scheduling Representative

Page 74: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

74

SNG to South Georgia Expansion

Expansion • 5,096 Dth/d from TGP Rosehill to 7 Georgia municipals

– Phase 1: 3,350 Dth/d in-service 12/18/2015

– Phase 2: 1,746 Dth/d starting 12/1/2016 (target)

Scope of work • Phase I

– Cylinder mods. at Enterprise (#10)

– HP uprate at Ellerslie (#9) control work only

– 1 Regulator, pipe up-rate and mods, meter upgrade, transmitters

• Phase 2:

– Re-wheel Selma units # 1 & #2, and Auburn #3

Page 75: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

75

New Interconnect(s)

* Interconnection initiated and reimbursed by Texas Eastern

Company County/State In-Service Date Pipe R/D Capacity Mcf/d

Texas Eastern * Attala County, MS Target 1st Qtr ‘17 SNG Receipt 160,000

New Transco Interconnect #

# Subject to an open season posted 10/12/16

Page 76: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

76

Questions?

Thank You for Your Business!

Page 77: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

77

NAESB & DART Updates

Gene Nowak Vice President, Transportation & Storage Services

SNG Shipper Meeting Birmingham, AL ▪ October 12, 2016

Page 78: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

78

NAESB Update

• FERC Order 809 Rehearing 9/17/15 – NAESB 3.0 – Implemented 4/1/2016 with additional cycles and timeline adjustments – Requested NAESB to review Scheduling Processes for improvements – Final update report due to FERC next week - 10/17/16

• Multiple Gas Electric Harmonization (GEH) Forum meetings Feb-Mar 2016 – Open meetings for gas and electric participants – Education and brainstorming of ideas – results passed on to NAESB Board of Directors

• Items added by NAESB Board to Wholesale Gas Quadrant (WGQ) Annual Plan for consideration: – Confirmations – level, methods – Special Efforts nominations (optional)

• Outside of or between grid-wide timelines • Shaped flow profile • May impact all aspects of gas transactions, not just nominations

– Hourly nomination quantities – separate request but related to the Special Efforts – Communication protocols – between ISOs/LDCs/Gas Generators/Marketers

Page 79: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

79

NAESB Update

• Ongoing meetings in WGQ – Business Practices Standards (BPS) subcommittee – Met eight times since July 2016 – Slow progress – Trying to standardize activities that currently happen without discrete

transactions (nominations/scheduling/confirmations) • Examples: Non-uniform hourly flows or early flow changes before cycle time • Happens today via a Gas Control to Gas Control communication

• Report to FERC will summarize progress with meeting notes – No standards have been developed to date

• If standards do develop – could be included in the next release (Version 3.1) – NAESB may file in late 2017 to be implemented in late 2018?

Page 80: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

80

DART Update

• Converted three legacy systems to DART – Passkey (TGP) - October 2013 – Xpress (CIG/WIC/Ruby, et al.) - March 2015 – Premier (SNG/EEC/SLNG) - April 2016

• Last one is Passport (EPNG/Mojave) – May 2017 • Committed to continually improving DART

– Input from Customer Working Groups • Comprised of SNG/EEC interested customers

– Other KM companies using DART hold similar quarterly meetings with their customers

• Purpose is to develop consensus and prioritization of improvements to DART or other processes through collaboration, idea sharing and feedback

• Met this morning for our fifth meeting since DART went live for SNG

– One code base with the ability to customize where needed – Requested changes are prioritized based on benefit vs level of effort

Page 81: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

81

Questions?

Thank You for Your Business!

Page 82: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

82

Scheduling During Winter

Operations

SNG Shipper Meeting Birmingham, AL

October 12-13, 2016

Page 83: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

83

Agenda

• Historical Constraints

• Helpful Reports to Monitor

• Segment Scheduling Review

• Scheduling Tips for Managing Your Business this Winter

• Seamless

Page 84: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

84

SNG Pipeline System

South Main

North Main

Cypress Line

East Leg

West Leg

SESH

South Georgia 1.8 bcf/d capacity

2.4 bcf/d capacity

North Louisiana

Zone 0 Zone 1 Zone 2 Zone 3

Elba Express

Ocmulgee

Gwinville

Wrens

Enterprise Elba Island

Bear Creek

Muldon

Thomaston

Page 85: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

85

Segment Map

Page 86: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

86

Historically Constrained Areas

• Constraints have been consistent with years past – North Louisiana - Onward (Segment 30)

– Southeast Supply Header (SESH)

– #606700 ETC Tiger/SNG SESH

– #606400 EGT/SNG SESH

– South of Franklinton (Segment 360)

– #605500 Col Gulf/SNG Shadyside

– Enterprise Compressor Station (Segment 420)

– Ellerslie Compressor Station (Segment 490)

Page 87: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

87

Restrictions & OFO Overview

• Factors SNG considers when evaluating whether to implement a Type 3 Operational Flow Orders (OFO) penalties: – Weather Forecast – system means in the 40’s and 80’s are where demand starts to

approach capacity – Day of week – weekday demand exceeds weekend/holiday demand – Expected duration of heavy demand – Recent history – Nominated deliveries – Actual takes from the system higher than entitlements

• Factors considered in scheduling – Contracted No Notice – doesn’t have to be nominated and forecasted usage needs to be

reserved – Receipts downstream of constraint increase SNG’s ability to deliver – Actual takes from the system vs entitlements – Expected duration of heavy demand

Page 88: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

88

SNG EBB Provides Useful Information

Page 89: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

89

Daily Type 3 OFO Probability Posting

Page 90: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

90

Pipeline Condition Notice

Page 91: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

91

Monitor Entitlement Reports

• Sent on a per cycle basis – Not just on OFO days

• ESA’s were auto-subscribed, others should be added – Report Subscriptions

• Flowing GasAdditional ReportsReport Subscriptions Available Reports. Right Click and “Add Schedule” or “Change Schedule”

– NSC057 Operator Agent Daily Entitlement Report – NSC027 Shipper Agent Daily Entitlement Report

Page 92: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

92

Out of Cycle Nominations

• SNG will use all reasonable efforts to accommodate reallocation of supply and/or market so long as the request is made before the gas day ends

• Must be requested and approved by all parties before 9:00AM

• Communication is key

– Must be approved by SNG Gas Control

• System conditions and available capacity to be evaluated

Page 93: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

93

SNG Retro Nom Policy

• SNG has established procedures and guidelines to ensure a non-discriminatory policy

• Reasons that are not acceptable for retro nominations: – Change of scheduled quantities that removes a potential penalty charge in an area under an

OFO – Change of supply and/or market after gas day is complete - these should be requested as out

of cycle nominations prior to end of gas day – Increase in nominations through a restricted area

• Procedure: – Email SNG Scheduling Rep within 7 days of the impacted gas day – Email should include the reason for the change and include all relevant information (Date, GID,

PIN) – The email should also include all counterparty approvals

Page 94: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

94

Page 95: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

95

Transport Scheduling

• Transport scheduling will be at: – The pipeline segment level for pipeline constraints – The point level for meter capacity constraints

• Contract rights will determine shipper’s priority of service through the segment and at the point

• Capacity Split screen provides scheduling priorities for submitted

nomination (Segment and Point level views) – Contractual rights are displayed at the Master level in the Contracts

screens

Page 96: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

96

Transportation Priorities Scheduling Queue Position Capacity Reduction

Method

Primary in Path (PIP) Prorata/Entitlement

In Path (IP) Previously Scheduled Prorata/Entitlement

In Path (IP) Prorata/Entitlement

Out of Path (OP) Previously Scheduled Prorata/Nominations

Out of Path (OP) Incremental Prorata/Nominations

Downstream Delivery Service (DDS) Previously Scheduled Prorata/Nominations

Downstream Delivery Service (DDS) Incremental Prorata/Nominations

IT & AO Previously Scheduled Prorata/Rate

IT & AO Incremental Prorata/Rate

Previously Scheduled will not be bumped on ID3

Page 97: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

97

Ranking

Receipt HPGT

Supply D

Supply C

Market 3

Receipt Trunkline

Supply B

Supply A 500

100

500

200

Upstream Ranks

Downstream Ranks

50

400

100

500

Upstream Ranks

Downstream Ranks

300

50

Contract Path

Ranks

300 DCGT

Market 2

Market 1

200

100

FGT 400 500

500

Rec Ranks

Rec Ranks

Del Ranks

Del Ranks

Page 98: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

98

Nomination Example Through Segment 420 Constraint

Routes are assigned In Path and Out of Path priorities through a pipeline segment constraint using customer’s path ranks

In Path 3,000

Out of Path 1,000

Master Firm Contract (MFT) North Capacity 1,000 Dth South Capacity 3,000 Dth

In Path PIN 2,000

Out of Path PIN 2,000

Page 99: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

99

Nomination Example Through Segment Constraint

SEGMENT 420

Rank 100

Rank 200

MFT Contract

MFT Contract

• Two Paths on MFT through Segment 420 • Path Ranked 100 would be assigned 2,000 In Path • Path Ranked 200 would be assigned 1,000 In Path • Path Ranked 200 would be assigned 1,000 Out of Path

2,000 Dths

2,000 Dths

Out of Path PIN

In Path PIN

Page 100: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

100

Nomination Example Through Segment 420 Constraint

If all Out of Path was reduced to 0, the In Path Pin would be reduced by 1,000 because the contract path to this PIN was ranked lower than the contract path to the Out of Path PIN

In Path 3,000

Out of Path 1,000

Master Firm Contract (MFT) North Capacity 1,000 Dth South Capacity 3,000 Dth

IP PIN 2,000

OP PIN 2,000

Page 101: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

101

Utilizing Flow Day Redirect

• Flow day redirect is when a shipper redirects a previously scheduled (PS) quantity through a constraint to a new PIN downstream of the constraint

• Must reduce the PS quantity at a PIN downstream of the constraint that you want to redirect gas from

• Must be on the same transportation contract that contains the PS

• Subject to new constraints that did not exist on previous cycle

• Previously scheduled quantities are not redirected by changing rank

Page 102: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

102

Sourcing Gas on Peak Days

• Utilize receipts, including displacement, downstream of South System constraints as much as possible – Elba Island

– Dominion Carolina Gas Transmission displacement

– Transco supply via Elba Express (Seamless nominations will be covered shortly)

– Petal, Destin, and TGP-Rose Hill are downstream of segment 420 constraint

• But they are not downstream of a segment 430 or 490 constraint

– FGT- Suwannee – Up to 60,000 dth/d meter capacity, but scheduled level of flow depends on location of South Georgia loads

Page 103: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

103

Page 104: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

104

Scheduling Cut Queue

• From this screen shippers can review any scheduling cuts by the pipeline or transportation service provider (TSP)

Page 105: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

105

Scheduling Cut Queue

• Enter Flow Date and Cycle, then click Retrieve

Page 106: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

106

Scheduling Cut Queue (cont’d)

• Double click on record for detail

Page 107: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

107

Scheduling Cut Queue Detail

This screen displays pipeline cuts by the TSP • Reason code and description will be displayed

Page 108: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

108

Unauthorized Overrun

• Description – A transportation contract is nominated in DART and is Exceeding

its Contract MDQ (ECM)

• Most Common Cause – A rolling nomination on a transport contract that was submitted

prior to a capacity release

• How to Detect – Scheduling Cut Queue / Sched Qty for Shipper reports

– Cut code will be ECM

Page 109: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

109

Unauthorized Overrun (cont’d)

• Scheduling Cut Queue – In the detail screen you will see the Point Scheduling location,

showing which Point the contract is at its highest quantity of ECM

• Trouble Shooting – Use the MDQ utilization screen to detect overrun – Copy the old nom, and revalidate to generate overrun nom edit

• Resolution – Capacity Recall – Nominate Explicit Authorized Overrun “AO” – Reduce nomination path through point of max overrun

Page 110: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

110

MDQ Utilization

• Overrun Column

– Capture volumes that are in a draft batch that are truly overrun but have not been explicitly nominated as Authorized Overrun

• Nominated Overrun Column

– Capture the total amount of Authorized Overrun that is explicitly nominated on transportation contract(s)

Page 111: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

111

MDQ Utilization (cont’d)

• MDQ-Nominated Difference (DTH)

– Will be visible for queries for any future cycle

• MDQ-Scheduled Difference (DTH)

– The column header changes from nominated to scheduled for queries of a completed scheduling cycle and the number(s) reflected are the final scheduled volumes for each transportation contract listed

Page 112: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

112

Navigation to Capacity Split Screen

Page 113: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

113

What is Different This Winter?

• There aren’t many differences to take into consideration this winter – There have been no significant changes in flowing gas supplies – Constraints on the South System are likely to occur at the same

locations as last winter – Constraints on the North System tend to be driven by colder

weather

• However, SNG Seamless transportation will be implemented as part of the EEC/SNG Expansion – Estimated to start in December

Page 114: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

114

Seamless Nominations

• SNG will be a shipper on Elba Express and offer seamless service to its shippers • EEC points will be set up as Zone 3 points on SNG to accommodate ease of

nominations – Firm expansion shippers will have capacity rights through the EEC segments – If the expansion shippers are not using the capacity, then existing shippers’ nominations will

be scheduled based on queue priority up to SNG’s TD on EEC

• SNG shippers may nominate these EEC points if they add an Exhibit C to their contract • Exhibit C provides that Shippers who use the EEC capacity will pay the EEC ACA charge and EEC

fuel, in addition to SNG’s commodity charges, surcharges and fuel • FERC has required that EEC establish an incremental North to South fuel rate to support this

expansion service which we estimate to be about 1% plus LAUF – Example:

» EEC expansion fuel from Transco to Port Wentworth » Applicable SNG fuel from Port Wentworth to SNG delivery

Page 115: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

115

For Questions and Assistance

Account Managers • Walter Coe 205-325-3708

[email protected]

• Lisa Guthrie 205-325-3816

[email protected]

• Jerry Nelson 205-325-7257

[email protected]

Oncall Account Manager • 1-800-315-0575

Scheduling • Gina Mabry, Manager

713-420-3685

[email protected]

• Scheduling Hotline 713-420-7213

Email: [email protected]

• Katie Cornutt 713-420-5648

• Veronica Esparza 713-420-5213

• Phyllis Miller 713-420-3738

• Tracy Minter 713-420-7030

• Greg Pollard 713-420-7149

• Jeremy Rainwater 713-420-6385

Page 116: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

116

SNG Shipper Meeting Birmingham, AL

October 12-13, 2016

Contracts/Capacity Release Features and Tips

Page 117: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

117

Agenda

• New Service Type for SNG Expansion – Different tariff rate – Exhibit C requirement

• Capacity release tips/reminders – Tips for releasing shippers – Tips for replacement shippers

• Viewing Segment Capacity • Viewing Points in the Path and Alternate Point

Requests • Viewing Available Quantity for Points

Page 118: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

118

New Service Type for SNG Expansion

Page 119: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

119

New Service Type for SNG Expansion Utilizing FT Capacity on EEC

• New service type utilized for seamless expansion service – All expansion shippers have executed unique masters for the service that are numbered “xxxxxx-

MFTESNG” • Expansion packages are shown as “yyyyyy-FTESNG”

– Original estimated tariff recourse rate of $14.06/Dth/month filed with certificate application • True-up filing with actual tariff recourse rate will be filed 30-60 days prior to in-service date

– MFTE Contracts require an Exhibit C to reflect agreement to pay EEC commodity (currently ACA) and fuel/L&U charges in addition to commodity charges and fuel on SNG

• Capacity release – Shippers that wish to acquire capacity from an MFTE contract must execute an MFTE master with an

Exhibit C – Releases >1 year will be capped at the zone 3 expansion recourse rate – Releases </= 1 year can exceed the zone 3 expansion recourse rate

• If any other SNG shipper would like to have the ability to nominate from the EEC/Transco receipt points on a seamless basis utilizing an existing SNG transportation contract, the shipper must execute an Exhibit C before any nominations will be accepted – Includes firm and interruptible transportation service – Exhibit C acknowledges that the shipper will pay charges that SNG incurs on EEC

• Currently ACA and fuel for EEC in addition to commodity and fuel owed to SNG

Page 120: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

120

Page 121: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

121

Capacity Release Tips/Reminders

Page 122: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

122

Tips/Reminders for Releasing Shippers • Awarded offers you created in DART can be copied

– Capacity Release -> Offers -> Create offer • Copy existing offer is a right-click selection from the Create offer screen

– Everything will be copied over to the new offer except

for the Bidder Affiliation

– DART also gives you the option of copying the rate

– Don’t use the Copy offer feature if the Release Type will be different • Ex: the original release was a Zonal release and the new offer will be Primary-

to-Primary

• Offers converted from Premier cannot be copied

– Detailed procedures located on the portal page under Other Information -> Conversion to DART -> DART Contracts and Cap Rlse Training Matl.pdf

Page 123: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

123

Tips/Reminders for Releasing Shippers (cont’d)

• FT-NN capacity can be released as FT – Releasing shipper can change the Rate Schedule on the Offer Detail screen from MFN to MFT

– Allows the replacement shipper to acquire the capacity on its MFT contract instead of MFN

Page 124: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

124

Tips/Reminders for Releasing Shippers (cont’d)

• Troubleshooting an Invalid Offer – First thing is review the Offer Error(s)

• The Offer Errors screen is a right-click selection from the Review/Withdraw Offer screen

– Top reasons offers go Invalid • Insufficient credit line in DART for the prearranged bidder (detailed instructions on

next slide)

• Attempting to submit a release as non-biddable that’s required to go out for bid

• Bidder affiliation is blank

• Prearranged bidder fails to confirm bid prior to bid period start date/time

– Rather than delete the invalid offer and start over, try to correct the error and resubmit

Page 125: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

125

Tips/Reminders for Releasing Shippers (cont’d)

• Detailed instructions to troubleshoot an Invalid offer due to credit – First, navigate to the Offer Error(s) screen to view the error

Page 126: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

126

Tips/Reminders for Releasing Shippers (cont’d)

– 2 error messages. Both relate to the credit issue. • “Credit not established for bidder. The replacement shipper has been notified for package id

xxxxxx.”

• “Errors found in Prearranged Bid for this offer for package id xxxxxx”

Page 127: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

127

– What happens now? • DART sends an automated email to the prearranged bidder and SNG credit

manager letting them know the offer is Invalid due to credit • This email instructs the bidder to contact the SNG credit manager to resolve

(phone number and email address given in the email) • Once credit is resolved, the SNG credit manager resubmits the offer on

behalf of the releasing shipper

– What should I do? (Tips for the releasing shipper) • Follow-up in a timely manner with the prearranged bidder to make sure

they have addressed the issue • Check back in DART occasionally to make sure the offer has submitted

successfully • Don’t delete the offer and start over since the prearranged bidder and SNG

credit manager have already been notified of the offer error

Tips/Reminders for Releasing Shippers (cont’d)

Page 128: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

128

Tips/Reminders for Replacement Shippers (cont’d)

• Prearranged bidders must confirm their bid before the bid period starts (9:00 am CCT) – Bidders who have set-up the Cap Rel Bids business preference will

receive a system generated email once the offer has been submitted and is ready to be confirmed

– Bids are confirmed in DART by going to

Capacity Release -> Bids -> Confirm Bid

– Bids not confirmed in time will go Invalid

– The releasing shipper can take the invalid

offer, change the bid period, and resubmit

Page 129: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

129

• Set-up the Cap Rel Bids business preference if you haven’t done so already – Preferences -> Business Preference

– Right-click, New. Complete the contact information and Save

– Default email address for notifications regarding bidder credit, confirm bid, match bid, and recalls

Tips/Reminders for Replacement Shippers (cont’d)

Page 130: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

130

Viewing Segment Capacity

Page 131: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

131

Segment Capacity

• Contracts -> Segment Capacity

• Select an Effective Date and Retrieve

• Allows the user to view the primary forwardhaul

and backhaul capacity at the beginning and end

of each segment

• Can view/sort/filter by segment, contract, service type, or by customer (if agent)

• “Save as” option to Excel

Page 132: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

132

Viewing Segment Capacity: default display is by segment

Page 133: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

133

Viewing Segment Capacity: can also be sorted/stacked by Contract

Page 134: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

134

Viewing Segment Capacity: can also be sorted/stacked by Service Type

Page 135: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

135

Viewing Points in the Path and Alternate Point Requests

Page 136: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

136

Points in the Path

• Misc -> Points in the Path • Enter a “From Pin and “To Pin” (not contract specific) • The screen retrieves all points in the path • When applicable, the user can select the Default route or the Cypress route • Information displayed for each in-path pin:

– Pin number – Pin name – Source (Receipt), Disposition (Delivery), or Bi-directional – Zone – Segment – Line, Section, Distance

• “Save as” option to Excel

Page 137: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

137

Points in the Path - Example 1

From PIN: 604000 To PIN: 940050 Points retrieved in these Segments:

340 350 360 370 390 410 420 430 440 460 480 490 530 560 580 615 620

Page 138: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

138

Points in the Path - Example 2

From PIN: 660000 To PIN: 654700 Points retrieved in these Segments:

617 615 580 560 530 490 480 460 440 430 420 410 400 50 90

110 120 130

Page 139: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

139

Alternate Point Requests

• Customers can also view points in the path on any firm transportation package from the Contracts window by right clicking and selecting “Available Cap for Alternate Locations SNG”

• In addition, customers can view points in the path on any submitted capacity release offer from the following screens: – All Offers/Awards – Create/Submit Bids – Offer Bids

• Customers can submit an alternate point request on any awarded firm transportation replacement package from the Contracts window by right clicking and selecting “Available Cap for Alternate Locations SNG”

• Requests are on a one-time basis per replacement package and can be effective any time during the term of the release – Can amend from/to multiple R and/or D points during the one-time request

Page 140: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

140

To submit an alternate point request, select the replacement contract from the Contracts window, right click and choose Available Cap for Alternate Locations SNG

Page 141: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

141

Select the Rqst Start Date, and then highlight the pin you wish to change. Double click in the Alternate Loc ID field to view the Alternate Location Lookup screen.

Page 142: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

142

The Alternate Location Lookup allows the user to view in-path locations and unsubscribed capacity at each location. Select the desired alternate point and click Ok. Only locations with unsubscribed capacity greater than 0 are valid for the request.

Page 143: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

143

Once an alternate point is selected, enter the quantity in the Rqst Qty column, right click, then select Validate

Page 144: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

144

If the validation is successful, the request can be submitted from this screen. Upon submission, you’re consenting to the point and/or quantity changes once Pipeline approval has been granted. An email notification will be sent once the amendment has been completed.

Page 145: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

145

Viewing Available Quantity for Points

Page 146: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

146

Available Quantity for Points

• Contracts -> Available Quantity for Points

• Displays the primary receipt and delivery points

on master firm contracts as of a particular date

• Displays the Zone and Segment of each location

• Displays the contracted, acquired, released,

recalled, and available quantity at each location

• If the same point is on multiple contracts, there’s an option to group and display point totals

• “Save as” option to Excel

Page 147: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

147

Available Quantity for Points (cont’d)

Page 148: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

148

Available Quantity for Points (cont’d)

Page 149: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

149

Questions?

Thank You for Your Business!

Page 150: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

150

SNG Shipper Meeting Birmingham, AL

October 12-13, 2016

Imbalance Management & Billing

Page 151: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

151

Agenda

• Imbalance Management – Imbalance Management Tools

– Payback Areas & Nominations

– Imbalance Resolution Methods

• Billing – No-Notice Service

– Zone Matrix and Maximization

• Operational Flow Orders (OFOs)

Page 152: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

152

Imbalance Management

Page 153: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

153

Imbalance Management Tools • Contractual Imbalance Screen

– Summary or detailed view of an imbalance by GID (Shipper’s Global company ID), Location, Day or Contract

• SNG/EEC Imbalance Agent Summary Report – Developed specifically for SNG – Summary view of imbalance for those users who are Imbalance Aggregation

Agent for other entities

• SNG/EEC Shipper Daily Imbalance Report – Daily view of Scheduled and Allocated Receipts and Deliveries, Fuel and Net

Imbalance

Page 154: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

154

Geographical Areas

• Payback will be evaluated based on location of Payback using 6 geographical/operational areas of the pipe.

Page 155: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

155

Nominating Payback

• Payback at the Pool PIN – 1 Sided Transaction – Requires Pooling contract – Payback from TSP (TT 03) & Payback to TSP (TT 04)

• Payback using Transportation Contract – Payback from TSP (TT 03) will be associated with a PIN representative of

Zone 0 – Payback to TSP (TT 04) will be associated with a PIN representative of

Zone 3 – Utilizes Transport Capacity (TT 03) & subject to applicable fuel (TT 04)

Page 156: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

156

Imbalance Resolution Methods

Page 157: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

157

Five Methods to Resolve Imbalances

• Storage on SNG

• Off-System Storage

• Trades

• Park and Loan (PAL)

• Cash-Out

Page 158: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

158

Using Storage on SNG to Resolve Imbalances

• Settle to/from shipper’s CSS or ISS account or third-party’s CSS or ISS account – Navigate in IDart: Flowing Gas Imbal Trd (and Stor Trans) Elections

– Third-party offsets require confirmation from storage holder

– Final deadline is 17 business days at 5:00 p.m. CCT

– Results of election are applied to storage account based on when the election is received • Period 1 (around 9th of month) or Period 2 (day after trading

deadline)

Page 159: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

159

159

Page 160: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

160

• Storage facility must be directly connected to SNG, e.g., Petal, Leaf River, MS Hub, and agree to transfer

• Manual process outside of DART; forms available on EBB • Select “Customer Information”, then “Forms”

• Settle to/from own account or third-party account with confirmation

• Capped at the portion of Shipper’s imbalance that is < 5% Net Imbalance Percentage

• SNG and Third-Party Storage Operator will agree on transfer schedule and shipper must nominate to effectuate the inventory transfer

Off-System Storage to Resolve Imbalances

Page 161: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

161

Using Trades to Resolve Imbalances

• Imbalances may be traded with another shipper who has an imbalance – in the opposite direction, or – in the same direction

• Process – Navigate in IDart: Flowing Gas Imbal Trd (and Stor

Trans) Imbal Trd (Stor Transfer) – No longer mandatory to post imbalance for trade

Page 162: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

162

162

Page 163: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

163

163

Page 164: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

164

164

Page 165: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

165

Using PAL to Resolve Imbalances

What is PAL

– An interruptible linepack service

– A source or disposition of gas on a nomination

– Can be used at any PIN

– Most parks and loans are discounted to a mutually agreeable market rate

– See Rate Schedule PAL in SNG’s Tariff for details

Page 166: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

166

Typical Uses of PAL

Balancing Approved by Operations

Customers have agreed-upon limits within which they can nominate parks and loans on any given day

Price based on the flexibility and locations

Executed on Yearly, Seasonal and Monthly Terms

Term Deals Based on Market Pricing for the

date range, location and quantity

May be same day, next day, remainder of month or agreed upon future month

Determined based on system conditions

Daily Requests As operational flexibility permits on a

nondiscriminatory basis we will grant a customer’s request to park or loan at a mutually agreeable point

Can be used to resolve monthly imbalances if system conditions permit

Page 167: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

167

Process to Request a PAL Service

• Example using imbalance resolution – Shipper has short imbalance for previous month; cashout is not

desirable this month and prefers to pay back in kind next month – Shipper requests loan to clear imbalance – SNG determines it has linepack available for loan – Shipper and SNG mutually agree on payback dates and a rate – Loan contract is executed – SNG clears imbalance with loan – Shipper nominates loan payback at the mutually agreed-to time – To initiate a PAL transaction contact Mark Wilson

• AOL IM: sonatgasman

Page 168: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

168

Using Cash-Out to Resolve Imbalances

• Month lag invoicing

– Allows for completion of all previous imbalance settlement options

– Preliminary Cashout Calculation Report in the production month’s invoice packet

– Following month’s invoice packet displays verification of resolution on Transport Contract Volume Statement-Summary (Dth) report

Page 169: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

169

Viewing No-Notice Activity and Storage Information

Page 170: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

170 170

170

Page 171: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

171

171

Page 172: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

172

172

Page 173: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

173

NAESB Storage Information (WIVL2031): This screen shows the storage fuel on net NN injection (1209) and Scheduled Withdrawal (2649) Net withdrawal is 1,440 X .62% = 9 Dth Storage Fuel

173

Page 174: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

174

174

Page 175: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

175

All Contracts (WIVL5010): This screen shows the transport fuel credit of 16 (1209 X (3.16% - 1.81%)).

175

Page 176: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

176

Zone Matrix and Maximization

Page 177: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

177

Zone Matrix

• Receipts and Deliveries allocated to IT Service are matched together

• Receipts and Deliveries to all Firm Services are matched together in service type order: AO, UAO, FT and FTNN – Within each category above Company shall match:

• Intrazone - receipts matched to deliveries in same zone

• Forward Haul – based on lowest to highest tariff rate

• Backward Haul – based on lowest to highest tariff rate

Page 178: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

178

Zone Matrix (cont’d)

• Current Zone Matrix Order:

SNG - Zone Matrix Pathing

Commodity Settlement Rates Effective September 2013

Firm Services IT, AO & UAO

Zone Matrix Current Current Type Rec Zone Del Zone Rates Rec Zone Del Zone Rates

($/Dth) ($/Dth)

Intra-Zone 1 1 0.027 1 1 0.104 3 3 0.032 3 3 0.179 2 2 0.036 2 2 0.191 0 0 0.038 0 0 0.213

Forward Haul 1 2 0.027 1 2 0.215 0 1 0.042 0 1 0.239 2 3 0.044 2 3 0.294 1 3 0.047 1 3 0.318 0 2 0.054 0 2 0.350 0 3 0.061 0 3 0.452

Reverse Path 3 1 0.027 3 1 0.104 2 1 0.027 2 1 0.104 3 2 0.036 3 2 0.191 3 0 0.038 3 0 0.213 2 0 0.038 2 0 0.213 1 0 0.038 1 0 0.213

Page 179: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

179

179

Page 180: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

180

Maximization

• Maximization is the reallocation of shipper’s overrun (AO and UAO) and IT delivered quantities to their firm reservation capacity within a zone

– This process occurs after allocations at all PINs and zone matrix has been applied

• Small Shipper MFTS and MFNS are not maximized

• Volumetric Capacity Release is not maximized

Page 181: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

181

181

Page 182: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

182

The Zone Matrix Pathing Summary and the Maximization and Final Zone Matrix reports can be found under the Flowing Gas, then Additional Reports

182

Page 183: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

183

Operational Flow Orders on SNG

Page 184: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

184

184

Page 185: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

185

OFO Type 3

Page 186: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

186

OFO Type 3 Defined

• Daily Market Demand Exceeds Capacity

– Daily Entitlements Enforced due to Pipeline Conditions

– Daily Entitlements = Scheduled Deliveries + Available No-Notice (greater of after Scheduling or after Allocations)

– Specific Delivery PIN or Group of Delivery PINs

Page 187: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

187

OFO Type 3 Has 3 Levels

• Level 1 – Correction in Flow is Needed

– Tolerance = Greater of 5% or 190 Dth

– Penalty = $ 10/Dth taken over tolerance

– Notification = 24 Hours Prior to Gas Day via Email

Page 188: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

188

OFO Type 3 Has 3 Levels (cont’d)

• Level 2 – Prompt Correction in Flow is Needed

– Tolerance = Greater of 2% or 75 Dth

– Penalty = $ 15/Dth taken over tolerance

– Notification = 20 Hours Prior to Gas Day via Email

Page 189: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

189

• Level 3 – Immediate Correction in Flow is Needed

– Tolerance = Greater of 2% or 75 Dth

– Penalty = $ 15/Dth taken over tolerance

– Notification = 4 or 20 Hours Prior to Gas Day via Phone

OFO Type 3 Has 3 Levels (cont’d)

Page 190: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

190

OFO Type 3 Checks Prior to Billing

• SNG uses OFOs only to protect system integrity

• SNG performs numerous tariff-based checks within each OFO group to determine penalties – Group Check

– Operator Check

– Nomination Agent Check

– Shipper Check

– PIN Check

Page 191: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

191

OFO Type 3 Checks

• OFO Group Check – Sum Delivery Point Entitlements for all Shippers at PINs

within the OFO group

– Increase by the Applicable Tolerance based on OFO Level

– Compare to Total Quantity Measured • If Measured > Entitlement + Tolerance

– Go to System-Wide PIN Check for all Member PINs

– Go to Operator Check for all other points

• If Measured < Entitlement + Tolerance – No Penalty Assessed

– Process Complete

Page 192: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

192

• Operator Check within an OFO Group – Sum Delivery Point Entitlements for each Operator at PINs

within the OFO group • Systemwide operators are evaluated at all PINs subject to the OFO

– Increase by the Applicable Tolerance based on OFO Level

– Compare to Total Allocated per Operator • If Allocated > Entitlement + Tolerance

– Go to Nomination Agent Check

• If Allocated < Entitlement + Tolerance – No Penalty Assessed

– Process Complete

OFO Type 3 Checks (cont’d)

Page 193: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

193

• Nomination Agent Check within an OFO Group – Sum Delivery Point Entitlements for each Nom Agent at

PINs within the OFO group – Increase by the Applicable Tolerance based on OFO

Level – Compare to Total Allocated per Nom Agent

• If Allocated > Entitlement + Tolerance – Go to Shipper Check

• If Allocated < Entitlement + Tolerance – No Penalty Assessed – Process Complete

OFO Type 3 Checks (cont’d)

Page 194: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

194

• Shipper Check within an OFO Group – Sum Delivery Point Entitlements for each Shipper at

PINs within the OFO group – Increase by the Applicable Tolerance based on OFO

Level – Compare to Total Allocated per Shipper

• If Allocated > Entitlement + Tolerance – Go to Point Check

• If Allocated < Entitlement + Tolerance – No Penalty Assessed – Process Complete

OFO Type 3 Checks (cont’d)

Page 195: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

195

• PIN Check

– If Allocated < All Entitlements + Tolerance

• No Penalty Assessed

• Process Complete

– If Allocated > All Entitlements + Tolerance

• Penalty Quantity = Allocated – (Entitlement + Tolerance)

• Penalty Amount = Penalty Quantity x Applicable Penalty $ Based on OFO Level

• Prorate to each Shipper over its Entitlement plus Tolerance

OFO Type 3 Checks (cont’d)

Page 196: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

196

OFO Type 6

Page 197: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

197

OFO Type 6 Defined

• Daily Imbalance Penalty – Shipper/Imbalance Aggregation Agent Imbalances

Threaten Physical or Operational Pipeline System Integrity

– Initiated for Short Imbalances due pipe, Long Imbalances due shipper, or Both • OFO posting will state the direction(s) subject to penalty

– If Net System Imbalance Test is Met, • No Penalties Assessed

Page 198: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

198

Step 1: Calculate Net System Imbalance

• Net System Imbalance = Total Allocated Receipts to Shippers Minus Total Fuel Minus Total Allocated Deliveries to Shippers – Includes Allocated Receipts from Storage (Withdrawals) and

Allocated Deliveries to Storage (Injections)

– If Net System Imbalance is Opposite of Penalty Direction, • No Penalty Assessed

• Process Complete

– If Net System Imbalance is Same as Penalty Direction, • Proceed to Next Step

Page 199: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

199

Step 2: Calculate Daily Net Imbalance

• Daily Net Imbalance = Allocated Receipts Minus Fuel Minus Allocated Deliveries – Includes Allocated Receipts from Storage (Withdrawals) and

Allocated Deliveries to Storage (Injections) – For each Imbalance Aggregation Agent, or – For each Shipper with no Imbalance Aggregation Agent

• If the calculated Daily Net Imbalance is Opposite of Penalty Direction, – No Penalty Assessed – Process Complete – Otherwise, proceed to the penalty calculation

Page 200: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

200

Step 3: Calculate Tolerance

• Tolerance Quantity = Greater of 2% of Shipper’s/Agent’s Allocated Deliveries or 200 Dth

Page 201: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

201

Step 4: Calculate Penalty Quantity

• Penalty Quantity = Daily Net Imbalance Minus Tolerance Quantity Minus Available No Notice – If Penalty Direction = Excess Deliveries/Short

Imbalances or Both Directions and Shipper/Agent is Short, • Available No Notice = Available Daily Withdrawal Quantity –

Scheduled Withdrawals – No Notice Withdrawals

– If Penalty Direction = Excess Receipts/Long Imbalances or Both Directions and Shipper/Agent is Long, • Available No Notice = Available Daily Injections Quantity –

Scheduled Injections – No Notice Injections

Page 202: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

202

Step 5: Calculate Penalty Quantity Tiers and Charges

• Tier 1 Quantity: 0-2% of Allocated Deliveries

– If Penalty Quantity < 2% of Allocated Deliveries or

< 200 Dth,

• No Penalty Assessed

• Process Complete

– Otherwise,

• Calculate Tier 2 Quantity (See Next Slide)

Page 203: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

203

Step 5: Calculate Penalty Quantity Tiers and Charges (cont’d)

• Tier 2 Quantity: 2-5% of Allocated Deliveries

– If Penalty Quantity < 5% of Allocated Deliveries,

• Tier 2 Quantity = Penalty Quantity

• Tier 2 Penalty Amount = Tier 2 Quantity x $ 1.00

– Otherwise,

• Tier 2 Quantity = 3% (5%-2%) of Allocated Deliveries

• Tier 2 Penalty Amount = Tier 2 Quantity x $ 1.00

• Calculate Tier 3 Quantity (See Next Slide)

Page 204: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

204

• Tier 3 Quantity: 5-8% of Allocated Deliveries

– If Penalty Quantity < 8% of Allocated Deliveries,

• Tier 3 Quantity = Penalty Quantity – Tier 2 Quantity

• Tier 3 Penalty Amount = Tier 3 Quantity x $ 5.00

– Otherwise,

• Tier 3 Quantity = 3% (8%-5%) of Allocated Deliveries

• Tier 3 Penalty Amount = Tier 3 Quantity x $ 5.00

• Calculate Tier 4 Quantity (See Next Slide)

Step 5: Calculate Penalty Quantity Tiers and Charges (cont’d)

Page 205: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

205

• Tier 4 Quantity: >8% of Allocated Deliveries

– Tier 4 Quantity = Penalty Quantity - Tier 2 Quantity - Tier 3 Quantity

– Tier 4 Penalty Amount = Tier 4 Quantity x $ 15.00

Step 5: Calculate Penalty Quantity Tiers and Charges (cont’d)

Page 206: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

206

Step 6: Calculate Total Penalty Amount

• Total Penalty Amount =

Tier 2 Penalty Amount +

Tier 3 Penalty Amount +

Tier 4 Penalty Amount

Page 207: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

207

Questions?

Thank You for Your Business!

Page 208: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

208

SNG Shipper Meeting Birmingham, AL

October 12-13, 2016

Overview of Doing Business with SNG

Page 209: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

209

Agenda

• Introduction to SNG – Pipeline Overview and System Map – Organization

• Basics on How to Do Business on SNG – Types of Services – How to request DART access – Setting up and/or changing Agents – Setting up User preferences – Subscribing to reports

• Nominations Overview • Viewing Measurement Information

Page 210: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

210

SNG Operates SNG, EEC, SLNG, GLNG

South Main

North Main

East Leg

West Leg

SESH South Georgia North Louisiana

Zone 0 Zone 1 Zone 2 Zone 3

Elba Express

Pipeline

SLNG

(Elba

Island)

Interconnects with Transco *

Southern Natural Gas • Capacity = 3.9 bcf/day

Southern Natural Gas Company *

Elba Express Pipeline (pre-expansion) • 220 MMcf/d Summer (Transco to Elba Island) • 190 Miles of Pipeline Southern LNG • 11.52 Bcf MSQ; 1.575 MMcf MDWQ

GLNG

Cypress Line

Page 211: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

211

Kinder Morgan Pipeline Management

Team for Southern Natural Gas

Mike Varagona

VP-BD

Norman Holmes

President

South Region Pipelines

Danny Ivy

VP-Gas Control

Ray Miller

VP Pipeline

Management

Tom Dender

VP-Operations

Jorge Torres

VP-Engineering

Gary Buchler

COO -Gas Pipelines

Tom Martin

President, KM Gas Pipelines

Gene Nowak

VP – Transportation &

Storage Services

Anders Johnson

VP– Gas Storage Eng.

Debbie Cone

VP – Project Mgmt

Kevin Howard

VP – Finance

Janice Parker

Commercial Director

Tom Hutchins

VP- EH&S

Birmingham office Houston office

Page 212: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

212

Transportation & Storage Services Management Team

Gene Nowak

Vice President

Diane Jhagroo

Sr Admin Asst

Devy Traylor Charlie Bass Jr.

Manager

Business Processes

Sherri Glazebrook

Director

Scheduling

Mark Gracey

Director

Business Process

Jill Hinkle

Director – Comm.

Contract Admin

Customer contact card provides further information

Page 213: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

213

Scheduling Team SNG, EEC, and LNG

Katie Cornutt

Rep Scheduler III

Gina Mabry

Scheduling Manager

Todd Davis

Rep Scheduler Sr. I

Veronica Esparza

Rep Scheduler III

Charlotte Hawkins

Rep Scheduler Sr. I

Phyllis Miller

Rep Sr. Scheduler II

Tracy Minter

Rep Scheduler III

Jeremy Rainwater

Rep Scheduler III

Greg Pollard

Rep Scheduler II

Ahsan Mohammad

Rep Scheduler III

Scott Sokira

Rep Scheduler III

Customer contact card provides further information

Page 214: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

214

Business Development Team SNG, EEC, and LNG

Mike Varagona

VP-Business

Development Lynn Smith

Exec Asst

Devy Traylor Devy Traylor Manager-Bus Dev

Paul Brown Manager-Bus Dev

John McIntosh Director-Bus Dev

David Porco Manager-Bus Dev

Ryan Leahy

Manager-Bus Dev

Norman Holmes

President, South Region Barbara Cornutt

Exec Asst

Customer contact card provides further information

Page 215: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

215

Marketing Department SNG, EEC, and LNG

Mike Rockett Tracey Nicholson

Manager

Account Svcs

Jerry Nelson

Sr Account Mgr

Darryl Outlaw

Account Director

Lisa Guthrie

Sr Account Mgr

Walter Coe

Sr Account Mgr

Alan Barksdale Jennefer

Whisenhunt Account Svcs

Sr Analyst

Renee Hyde

Manager

Account Svcs Manager

Account Svcs

Manager

Account Svcs

Norman Holmes President

South Region

Barbara Cornutt

Exec Asst

Janice Parker

Commercial

Director

Customer contact card provides further information

Page 216: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

216

How to Become a Shipper

• Obtain a Global Identification number (GID) for your company – This number is used for all KM operated pipelines

• Provide proof of creditworthiness – Three months of surety for the service types requested

• Set up access to the DART computer system • Request a service agreement • An Account Manager and Scheduling Representative

will be assigned to assist you with your business needs

Page 217: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

217

Firm Transportation Services

• Firm transportation service (FT) subscribed from SNG – Customer contracts for firm capacity rights from specific receipt PIN(s) to

specific delivery PINS(s)

• Firm no notice transportation service (FN) and Firm storage service (CSS) subscribed from SNG – Firm transportation is bundled with firm storage service

– The firm receipt point is at the SNG storage PIN with firm capacity to the specified delivery PIN(s)

– This service is a balancing tool to allow the Shipper to inject/withdraw automatically from its firm storage account without submitting a nomination

• Vast majority of firm capacity to AL, GA, SC, TN and FL is subscribed but SNG can evaluate the cost and rates to expand its system

Page 218: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

218

Acquiring Firm Service From Another Shipper

• Capacity Release of FT, FN and/or CSS – Customer can acquire firm capacity from an existing firm shipper for the

term and rate bid and awarded

– SNG bills the reservation rate awarded in the bid, as well as the commodity charges related to quantities transported

• Delivered service from another Shipper – Customer arranges for a 3rd party to use its firm transportation services on

SNG to deliver gas to the customer’s meter

Page 219: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

219

Interruptible Services

• Interruptible Transportation (IT) service – Provided to the extent capacity is available; firm service has a higher priority

• Interruptible Storage (ISS) service – Provided to the extent capacity is available; firm service has a higher priority

• Interruptible Park and Loan (PAL) service – Customers can park gas today and unpark it later when prices are higher,

or get loans of gas today and pay it back when prices are lower • This service is a gas supply tool

– PAL is sought after when gas prices are volatile

• Transportation of the gas is also required • Provided to the extent operational assets are available after scheduling higher-

priority services • Primary contact for PAL is Mark Wilson

Page 220: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

220

Pipeline Segments are Established for each Pipeline in the DART System for Contracting and Scheduling Service

Page 221: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

221

New Pipeline Map Details the Segments and Interconnects

Enter New SNG MAP

Page 222: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

222

Electronic Bulletin Board (EBB) and Preference Setup

Page 223: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

223

EBB Access and Information

• SNG’s Electronic Bulletin Board (EBB) has access to general system information

• It can be found at http://pipeline.kindermorgan.com/

• Customers can also log into the DART computer system for their proprietary information

Page 224: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

224

Setting up DART Access

• Complete two key documents – DART System License Agreement for the desired pipeline, and – External Security Administrator (ESA) Request form(s) to administer your security needs

• A customer is advised to have two ESA representatives from its company

• Submit forms – By email to [email protected], or – By fax (832)397-4923 Attn: Mr. Jesse Battle, or – By mail to DART SYSTEM SECURITY, c/o Kinder Morgan Inc, 1001 Louisiana Street, Suite 1000,

Houston, Texas 77002 Attention: Mr. Jesse Battle

• Assistance for DART access – Business hours Mon – Fri from 7:00AM to 4:00PM (CCT)

• All inquiries received outside of these hours will be returned on the next business day

– Weekend and holiday assistance will be provided by calling the Scheduling hotline – If you need your password reset, please contact your company’s ESA(s)

Page 225: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

225

Setting up / Changing Agents

• In DART, the Shipper has the ability to initiate and/or change Agents – The Agent can also initiate the process

• Agency authorities in DART are different than Premier – See your Account Manager to determine the agency

authorities that apply to your needs

• Changes in Agents must occur at the first of a month

Page 226: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

226

Setting User Preferences

• To set the default pipeline and default service requester, click the + sign to the left of Preferences and then click User Preferences

Page 227: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

227

Set User Preferences

• Select the TSP default and the Service Requester default from the drop down and click Save.

Page 228: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

228

Add Favorites

• Right mouse click on any screen that you wish to save

• Select Add to Favorites from the pop up window

Page 229: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

229

Suggested Favorites in DART

• Nominations: Not Submitted • Nominations: Submitted • Nominations: Buy/Sell Mismatches List • Confirmation • Capacity/End-Point Splits • Scheduled Quantity: Sched Qty Shipper • Scheduling Cut Queue • Contractual Imbalance

Page 230: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

230

Viewing Open DART Windows

Always Available

Available w/Tab Manager On

Page 231: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

231

Viewing Open DART Windows

To Set “Tab Manager”

View

Page 232: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

232

Report Subscription

Page 233: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

233

Report Subscription

• Customers can subscribe to certain reports that they want to receive routinely – Scheduled Quantities – Allocations – Measurement

• Supports the ability to select when you want to receive reports – Can also run reports ‘ad hoc’ as needed

• Supports reporting for Agent relationships

Page 234: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

234

Reports

Page 235: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

235

Report Subscription

1) Red-highlighted reports are currently subscribed

2) Select a new report and right click for more options

3) Select “Add Schedule” from pop up window

Page 236: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

236

Report Subscription

Step 1 of 5: Select Frequency

Step 2 of 5: Select Days of the Week

Page 237: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

237

Report Subscription

Step 3 of 5: 1) Select Svc Req and Cycle

(suggest all NAESB Cycles) 2) Press “Clear” next to Flow

Date

Step 4 of 5: Provide Contact Information

Page 238: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

238

Report Subscription

Step 5 of 5: Confirm information and

Save your update

Page 239: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

239

Buying and Selling Gas at Pool PINs

Page 240: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

240

Pool PINs are Where Gas Can be Bought & Sold

Page 241: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

241

Pool Structure Effective April 1, 2016 • Pool PINs are virtual locations on the pipeline where gas can be bought and sold • There are multiple pooling locations on SNG • One pooling contract should be sufficient to nominate gas to a Pool PIN for sale • Unlimited buys/sells at Pool PINs • Ultimately a shipper will have to nominate the gas supply for delivery from a Pool

PIN to a physical meter station • Storage also has a virtual location as a receipt or delivery PIN where gas can be

bought and sold

Page 242: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

242

Pooling Guidelines

• All receipt PINs can be nominated to the South Louisiana Zone 0 Pool PIN

• Receipt PINs can be nominated to the Pool PIN that is in the same zone and on the same system (i.e., North or South)

• Receipt PINs on the same system can also be nominated to Pool PIN(s) in all upstream zones along the same system (i.e., North or South)

• Receipt PINs in Zone 1 can be nominated to any Pool PIN in Zone 1

• The Storage PIN can be nominated to any Zone 0 and Zone 1 Pool PIN

Page 243: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

243

Nomination Basics in DART

Page 244: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

244

Basic Terms and Concepts

– PIN – Point Identification Number (i.e. meter, location or point)

– GID – Global Identification (i.e. company identifier)

– Contract format – (ex. 11234-MFTSNG)

– Pipeline Segments

– Nomination Transaction Types

– Status

– Nomination Batch

– Pathed Non-threaded Model

– Additional ranking capabilities – point and path level

– Options to input nominations in DART

Page 245: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

245

Dart Nomination Model

Receipt PIN

Delivery PIN

DART

Pathed, Non-Threaded Nomination

K = 312643-MFTSNG

Supply A

Supply C

Market B

Market D

(Path)

Page 246: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

246

Park Withdrawal

PIN

Off Sys Supply

Buy

Loan

Pooling

Storage Withdrawal

Transport

Sell

(Disposition)

Pooling

Park

Payback (From Pipe)

(Source)

Payback (To Pipe)

Loan Payback

Storage Injection

Upstream = 2,000 Dth

Downstream = 2,000 Dth

PIN must be in balance; total Upstream volume equals total Downstream volume

DART is PIN-Centric

Page 247: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

247

DART Transaction Type Reference Vol Type - Transaction Type Description TT Buy (Current Business) 01

Sell (Current Business) 01

Transport (Current Business) 01

Trans(Authorized Contract Overrun) 02

Payback (Imbalance Payback From TSP) 03 Payback (Imbalance Payback To TSP) 04

Injection (Storage Injection) 06 Withdrawal (Storage Withdrawal) 07 Pooling 08

Off-system Market 117 Off-system Supply 118

Park 26 Park Withdrawal 27

Loan 28 Loan Payback 29

Purchase 119 Sale 120

Page 248: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

248

Transaction Types (TT) for Supply/Market

• General rules for nominations at the PIN level – Gas coming on or off our system directly will use off

system supply or market transaction type 117 or 118 – Buy or Sell transactions between third parties will use

transaction type 01 – Buy/Sell Mismatch is a common problem–the Appendix shows how to find them

Page 249: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

249

Nomination Status in Dart

Status Meaning Action

Submitted/Nominated Successfully Submitted No further actions required

Not Submitted/Holding Not Submitted Holding for next available cycle

Not Submitted/Draft Not Submitted Draft Saved- Not Submitted

Not Submitted/Error Not Submitted Pending Error Correction

Not Submitted/Waiting for Approval Validated Requires Pipeline Approval

Page 250: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

250

Reasons that a Nomination is Waiting for Approval

• EPSQ Validation

• Retro Nominations

– Solicit all upstream/downstream approvals

– Submit changes for ID2 of the gas day in question

• Pipeline rep will review request in detail and approve if acceptable

Page 251: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

251

Page 252: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

252

View Scheduled Quantities (Shippers)

Page 253: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

253

View Scheduled Quantities (Shippers)

• The screen will default to the Timely cycle that is currently active in the system

– Select Beg Date and End Date

– Select Cycle

– Select your Svc Req K (Optional)

– Click Retrieve button

Page 254: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

254

View Scheduled Quantities (Shippers)

• The screen displays scheduled quantity information — Rec/Del Sched Stat – scheduling status e.g. Confirmed or

Nominated

— R Qty Rec/Del (Variance) – difference between nominated volume and scheduled volume, if any

Page 255: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

255

Scheduled Quantity For Shipper Matrix

• User can select two views – NAESB WGQ Basic View – displays NAESB required data elements – Expanded View - displays two additional fields; the Counter Prty Nom and RR PL Sched

• In the middle of the screen, next to Up ID and Dn ID, you will notice the GO button. If the GO button is enabled (not grayed out), shipper can click GO which will prompt the screen to show the PIN location with the upstream and downstream transactions.

Page 256: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

256

NAESB Scheduled Quantity For Shipper Matrix – Detail Line Item

• From this screen the shipper can further review details for any PIN

– Select a specific line item (line will turn blue)

– Click Detail Line Item box

Page 257: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

257

Measurement Information

Page 258: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

258

Agenda

• Daily Meter Information

• Hourly, Real Time and Gas Quality Information

• Measurement Subscription Information

Page 259: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

259

Daily Meter Information

Page 260: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

260

Measurement Navigation

Page 261: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

261

Volume Statement Summary Report

• Daily level report for selected flow month

• Provides the Daily Mcf, MMBtu, and Btu values

• Estimate/Actual Status indicator and Revision Indicator Flag for PPA’s

Page 262: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

262

NAESB Measurement Info

• NAESB window

• Daily Measurement for PIN, Area Point PIN or System Wide PIN

• Provides Daily Volume totals along with scheduled quantity and variance

• Print/Export button

Page 263: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

263

Daily Measured Quantity by Operator

• Daily meter volume information grouped by Point Operator

• Note that there is a selection of “All” for SVC Req

• Multiple locations for operator will be returned on same report

Page 264: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

264

SNG/EEC – Measurement by Meter Station Report

• Provides the measurement information for a selected gas flow date by operator

• Lists measurement information for metering locations under Area Points

Page 265: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

265

Hourly, Real Time and Gas Quality Information

Page 266: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

266

Hourly Volumes by PIN List

• Provides hourly Volume, Energy, Btu values with suspect flag and pressure base value

• Configurable summary feature for each column of data. Avg, Count, Max, Min and Sum

Page 267: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

267

Hourly Volumes by PIN List

• Graph tab

• Right clicking on chart provides copy/save and charting options

• Ability to turn available trend items on/off

Page 268: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

268

Real Time Volumes

• Single PIN view

• View current values along with yesterday totals

Page 269: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

269

Real Time Volumes

• Multiple PIN view

• Totals row is displayed at bottom of list

• Note: All PINs selection will return any non physical measurement points (Area / SW)

Page 270: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

270

Gas Analysis List

• Gas property information by gas day; averages at bottom

• Components are provided out to C10 (Decane)

• System allows for selecting more than 1 month

Page 271: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

271

Measurement Subscription Information

Page 272: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

272

Measurement Subscription Options

Page 273: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

273

Questions?

Thank You for Your Business!

Page 274: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

274

Page 275: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

275

View Buy/Sell Mismatch Activity

• Can be found in two locations

• First in the Navigation Panel under Nominations folder

Page 276: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

276

View Buy/Sell Mismatch Activity

• Can also be found on the Batch List screen

Page 277: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

277

Buy/Sell Mismatches List

• The Flow Date and Cycle will default to the current date and Timely Cycle

• The form also defaults to checking the Mismatches Only box

• To view all the Buy/Sell transactions, select Show All Svc Req and then Retrieve

Page 278: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

278

Buy/Sell Mismatches List

• Double clicking into each line item will take you to the Detail Screen which displays the Counter Prty Nom associated with the transaction

Page 279: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

279

Buy/Sell Mismatches List • In this example, our counterparty Cedar Power has not submitted their sell

to match the counter-party nom for 500 Dth

Page 280: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

280

SNG Shipper Meeting Birmingham, AL

October 12-13, 2016

Customer Working Group

Page 281: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

281

Purpose of the SNG Customer Working Group

To develop consensus and prioritization of improvements to DART or other processes

through collaboration, idea sharing and feedback

Page 282: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

282

Current Customer Working Group Members

Page 283: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

283

Agenda

• Dart Area Specific Updates and Discussion

– Scheduling and Reporting

– Invoicing

• Review of Prioritized List

• SNG Process Updates and Discussion

Page 284: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

284

DART Scheduling & Reporting Update

Gina Mabry Manager, Scheduling

Page 285: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

285

Completed Items

• Sched Qty Shipper (WNVL0003) and Sched Qty Shipper Detail (WNVL0004) added a subtotal by Svc Req when “All” is indicated – Moved to Production in June 2016

• Nomination Package ID Report-WIVL9025 – Formatting has been addressed -

• Moved to Production in May 2016

– Agent issue running the report for “All” has been addressed • – Moved to Production in June 2016

Page 286: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

286

Completed Items

• Enhanced Capacity/End-Point Split with the ability to see previously scheduled priorities and path rank – Moved to Production in June 2016

• Batch list for both Submitted and Not Submitted are now in chronological order and includes an AM/PM designation. The specific sort is by nomination Beg date, cycle, then date submitted. – Moved to Production in September 2016

Page 287: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

287

In-Progress Items: Navigation Panel Re-Organization

• Navigation Panel Re-Organization

– Currently being tested and should be released into the production environment in October

Page 288: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

288

DART Scheduling & Reporting Open Discussion

Page 289: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

289

Invoicing Janice Parker

Director, Commercial

Page 290: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

290

Recent Progress

• WIVL3015, Daily Measured Quantity by Operator – Shows Mcf and Dth at the meter station level – Available to operators and parties to whom they grant access – Customers requested this be added to the invoice packet or made available via

report subscription

• October 5 - SNG made this report available through report subscription and enhanced it to run using the “statement month” – This means that the report will auto-generate for the month to be invoiced

until invoices are final – Customers can set it up to run daily, weekly or monthly – If operators only want this report once a month after the measurement is

final, SNG suggests choosing a monthly election with a date of the 8th

Page 291: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

291

Recent Progress (cont’d)

• WIVL9000, Location Operator Allocation Report – A fix was made in Sept so that no-notice allocations are picked

up properly at market-area delivery points without manual intervention

• Open Question – This report is available in report subscription but it looks at the

production month which is the DART standard – It would require agreement of all pipelines with regression

testing to change this report to look at the “statement month” – Is it a high priority request to request this change now that

WIVL3015 is available for the statement month?

Page 292: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

292

Dart Invoice Open Discussion

Page 293: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

293

Review of Last Prioritized List

Katie Cornutt

Scheduling Representative

Customer Working Group Coordinator

Page 294: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

294

Top 10 Ranked Items as of July 2016 1 Default the nominations/submitted, “Batch List” screen so that the nominations are in chronological order by date and cycle

2 Hide other pipeline screen/reports not applicable to SNG, i.e. user login should only allow user to see screens/reports applicable to

their assigned pipeline(s).  For example if a user only has SNG access the program should filter out the references to other pipelines in

the “tree” pick list

3 Organize reports in a more user friendly manner. SNG reports in SNG folder , TGP reports in TGP folder.

4 Reports: Can the Reports be sorted by function? It seems like a lot of reports are thrown into the catch-all “Additional Reports.”

5 Reports: The Imbalance Agent Summary Report excludes all PIN transactions. Is there a report that reflects all of a GID’s activities

on DART so audits can be performed without needing 8 reports to “summarize” our activities?

6 Add totals to cut notices.

7 When copying a nom from previous day the path rank is not always copied.

8 Add contract mismatches to the cut notices even though it is a 1-sided. I believe it sill shows as a variance on my sched qty reports.

For the sake of continuity should be added to the cut notice as well.

9 Reports: Can Reports that are not SNG oriented be blocked somehow? When we log in, we have pipeline preference, why doesn’t

that block reports that are solely for NGPL, etc.?

10 With regard to nominations, customer submits a minimum of 2 cycles per day during normal operations, and 3-4 cycles per day

during OFO’s. This would add up to ~800+ nominations submitted during the year for our GIDs. When you pull the “Submitted”

screen, all submitted nom’s show up, and then you can filter by Beg Date/End Date/etc. It will not save however once the screen is

closed. Is there a way going forward to limit the amount of data that will show up on the “Submitted” screen prior to having to filter

(i.e. maybe start with current day + any future days - similar to Premier)?

Working with IT. New report needed.

Submitted to our IT group for completion.

Working with IT.

Did Item 1’s completion minimize this concern?

Attempting to recreate.

Done.

Done.

October 2016

October 2016.

See Enhancement for 3 & 4.

Page 295: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

295

SNG Process Updates

Page 296: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

296

Pipeline Condition Notice

Page 297: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

297

Monitor Entitlement Reports

• Sent on a per cycle basis – not just on OFO days

• ESA’s were auto subscribed, others can be added – Report Subscriptions

• Flowing GasAdditional ReportsReport Subscriptions Available Reports. Right Click and “Add Schedule” or “Change Schedule”

– NSC057 Operator Agent Daily Entitlement Report – NSC027 Shipper Agent Daily Entitlement Report

• If the ESA needs to be unsubscribed, please contact your Scheduling Representative for assistance

Page 298: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

298

Out of Cycle Nominations

• SNG will use all reasonable efforts to accommodate reallocation of supply and/or market so long as the request is made before the gas day ends

• Must be requested and approved by all parties before 9:00AM

• Communication is key

– Must be approved by SNG Gas Control

• System conditions and available capacity to be evaluated

Page 299: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

299

SNG Retro Nomination Policy • SNG has established procedures and guidelines to ensure a non-discriminatory

policy • Unacceptable reasons for retro nominations:

– Change of scheduled volumes cannot create/remove a potential penalty charge in an area under an OFO

– Change of supply and/or market after gas day is complete - these should be requested as out of cycle nominations

– Increase in nominations through a restricted area – Requests that would put any party or meter further out of balance with the pipeline

• Procedure: – Email SNG Scheduling Rep within 7 days of the impacted gas day – Email should include the reason for the change and include all relevant information(Date, GID,

PIN) – The email should also include all counterparty approvals

Page 300: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

300

Questions or Other Items?

Page 301: Southern Natural Gas Company, L.L.C. Shipper Meeting€¦ · 2016 Summer Overview • SNG’s facility performance was good during the extended hot weather – Compressor stations

301

Next Steps

• Next Customer Working Group WebEx Meeting

– January 19th at 1:30 pm CST

– Move to Quarterly?