TEMPLATE EXPLANATION
This template must be used by SP AusNet to report service performance information for the last three quarters of the 2008 calendar year.
Yellow worksheets ('Inputs - Performance' and 'Inputs - Exclusions') are for inputs, including performance and exclusion information. SP AusNet only needs to enter data on these worksheets. Purple worksheets 'S1' to 'S9' are the s-factor results based on the performance inputs from the 'Inputs - Performance' worksheet.(NB: The caps, collars and targets for s-factor worksheets 'S6' and 'S7' have been scaled as this template only applies to the last three quarters of the 2008 calendar year)
Blue worksheet 'Revenue Calculation' quantifies the appropriate revenue to be applied to the s-factor results adjusted for CPI.
Red worksheet 'Outcomes' shows the total performance, s-factor and financial incentive results based on SP AusNet's performance in 'Inputs-Performance' and 'Revenue Calculation' worksheets.
Orange worksheet 'Exclusion Definitions' are the defined exclusions for SP AusNet which should form the basis of exclusion requests under 'Inputs-Exclusions' worksheet.
SP AusNet - Service standards report - last three quarters 2008 - template (10 February 2008).xlsExplanatory notes
SP AUSNET - SERVICE STANDARDS PERFORMANCE
Performance parameter S Performance (Without exclusions)
Performance (With exclusions)
Total circuit availability S1 99.078398% 99.117382%
Peak critical availability S2 99.745438% 99.802938%
Peak non-critical availability S3 99.810606% 99.932660%
Intermediate critical availability S4 99.366936% 99.424704%
Intermediate non-critical availability S5 99.518644% 99.530316%
Loss of supply event frequency (no. of events > 0.05 system minutes per annum) S6 1 1
Loss of supply event frequency (no. of events > 0.3 system minutes per annum) S7 1 1
Average outage duration– transformers (minutes) S8 226 226
Average outage duration– transformers (minutes) S9 263 263
Date prepared: 10 February 2009Revision date:
NOTES:
Pink cells- Input performance without exclusions from performance data
Orange cells- Input performance with exclusions from performance data
Green cells- Input date that template data was entered and date of any revisions from original version.
Performance should be measured on a calendar year basis
SP AusNet - Service standards report - last three quarters 2008 - template (10 February 2008).xlsInputs - Performance
AER Report Dec-08 SP AusNet Performance Page 3 of 30
SP AUSNET - Proposed exclusions
Event proposed for exclusion
Description of the event and its impact on the network and
performanceCause of the event Start
dateStart time
End date
End time Circuits affected Reactive plant or
transformerQuantitative
impact Reasons for exclusion request Further references
Name of the eventDetail of the event. Such as: the action of any third parties, the actions of the TNSP,assets damaged or interrupted.
A description of the cause of the event
Name of circuits affected
Name of any reactive plant or transformer affected
Number of hours, mins etc interrupted
Full details of the reason/s for excluding this event. Should include a reference to the defined exclusions and explain how it meets this exclusion definition (se
Exclusion definition tab). Eg. Exclusion 1.2 Third party event.
A TNSP may provide further details of an exclusion event. TNSP to provide reference.
Out W/O No3 Trans warranty works
X432 - (RCTS) STATION REDEVELOPMENT
SPICAPX 1/04/08 00:00:00 11/04/08 17:37:00 R3 220/66/22KV TRANS AT RCTS
257.617 EXCLUDE 1.1 Unregulated transmission asset WO # X43258AM
Complete more hand rail on Trans Rack
X320 - (MTS) STATION REDEVELOPMENT
SPICAPX 1/04/08 05:38:00 1/04/08 18:55:00 B3 220/66KV TRANS AT MTS
13.283 EXCLUDE 1.2 Connection asset WO # X32058S2
Complete more hand rail on Trans Rack
X320 - (MTS) STATION REDEVELOPMENT
SPICAPX 2/04/08 05:41:00 2/04/08 17:26:00 B3 220/66KV TRANS AT MTS
11.750 EXCLUDE 1.2 Connection asset WO # X32058S2
Complete more hand rail on Trans Rack
X320 - (MTS) STATION REDEVELOPMENT
SPICAPX 3/04/08 06:12:00 3/04/08 16:28:00 B3 220/66KV TRANS AT MTS
10.267 EXCLUDE 1.2 Connection asset WO # X32058S2
Complete more hand rail on Trans Rack
X320 - (MTS) STATION REDEVELOPMENT
SPICAPX 4/04/08 06:06:00 4/04/08 14:22:00 B3 220/66KV TRANS AT MTS
8.267 EXCLUDE 1.2 Connection asset WO # X32058S2
replace Damage Cable SPIMAINT 6/04/08 07:16:00 6/04/08 18:20:00 L1 220/22KV TRANS AT RTS
11.067 EXCLUDE 1.2 Connection asset WO # 10280299
O/HAUL Transformer and Div Sw (EM)
SPIMAINT 8/04/08 07:08:00 8/04/08 15:54:00 B2 220/66KV TRANS AT TSTS
8.767 EXCLUDE 1.2 Connection asset WO # 10269251
Out W/O No1 Trans to cutover new OLTC control
X461 - (BATS) TERMINAL STATION REBUILD
SPICAPX 8/04/08 11:18:00 22/04/08 13:41:00 B1 220/66KV TRANS AT BATS
338.383 EXCLUDE 1.2 Connection asset WO # X46158Q4
Installhebal wall columns
X320 - (MTS) STATION REDEVELOPMENT
SPICAPX 9/04/08 05:33:00 9/04/08 17:08:00 B1 220/66KV TRANS AT MTS
11.583 EXCLUDE 1.2 Connection asset WO # X32058R9
Condition Monitoring Country Trans 2day North Area
SPIMAINT 9/04/08 07:05:00 11/04/08 15:50:00 B2 220/66KV TRANS AT GNTS
56.750 EXCLUDE 1.2 Connection asset WO # 10273067
O/H No.3 Trans Div. Switch @ TSTS
SPIMAINT 9/04/08 07:06:00 9/04/08 15:49:00 B3 220/66KV TRANS AT TSTS
8.717 EXCLUDE 1.2 Connection asset WO # 10269216
No1 66 Cap bank during setting change
V775 - ROUTINE PROTECTION & CONTROL DEVICE SETTING AND CONF
SPIMAINT 9/04/08 10:23:00 9/04/08 17:57:00 NO.1 66KV CAPACITOR BANK AT TBTS
7.567 EXCLUDE 1.1 Unregulated transmission asset WO # V77558A7
O/HAUL Transformer and Trafo Union Div Sw (EM)
SPIMAINT 10/04/08 07:00:00 10/04/08 15:37:00 B1 220/66KV TRANS AT TSTS
8.617 EXCLUDE 1.2 Connection asset WO # 10269248
Install ground wire Proximty only
X320 - (MTS) STATION REDEVELOPMENT
SPICAPX 11/04/08 05:38:00 11/04/08 12:19:00 B3 220/66KV TRANS AT MTS
6.683 EXCLUDE 1.2 Connection asset WO # X32058S0
No1 66 Cap bank during setting change
V775 - ROUTINE PROTECTION & CONTROL DEVICE SETTING AND CONF
SPIMAINT 11/04/08 13:21:00 11/04/08 18:03:00 NO.1 66KV CAPACITOR BANK AT TBTS
4.700 EXCLUDE 1.1 Unregulated transmission asset WO # V77558A8
replace Transformer Surge Arrestors
X708 - REPLACEMENT OF AGEING 22KV TO 500KV SURGE ARRESTERS
SPICAPX 12/04/08 05:59:00 13/04/08 17:40:00 L4 220/22KV TRANS AT RTS
35.683 EXCLUDE 1.2 Connection asset WO # X70858A9
SCAN - 2a Trans 220kv B ph LA High RF
SPIMAINT 18/04/08 07:12:00 18/04/08 18:08:00 R2 220/66/22KV TRANS GROUP AT RCTS
10.933 EXCLUDE 1.2 Connection asset WO # 10280123
Perf Calc No4 Trans, during No2 220kv Bus outage
X508 - (GTS) STATION REDEVELOPMENT
SPICAPX 19/04/08 05:36:00 19/04/08 15:23:00 B4 220/66KV TRANS AT GTS
9.783 EXCLUDE 1.2 Connection asset WO # X50858A8
Trans Rebate for Bus outage
X556 - (RWTS) REPLACE REYROLLE 66KV CBS AND ASSOCIATED CTS
SPICAPX 20/04/08 06:05:00 20/04/08 11:57:00 B3 220/66KV TRANS AT RWTS
5.867 EXCLUDE 1.2 Connection asset WO # X55658D6
rebate for bus outage SPIMAINT 20/04/08 06:55:00 20/04/08 14:24:00 NO.1 66KV CAPACITOR BANK AT TSTS
7.483 EXCLUDE 1.1 Unregulated transmission asset WO # 10282658
rebate trans for bus outage
SPIMAINT 20/04/08 06:55:00 20/04/08 14:24:00 B1 220/66KV TRANS AT TSTS
7.483 EXCLUDE 1.2 Connection asset WO # 10280227
U 2 Trans X320 - (MTS) STATION REDEVELOPMENT
SPIMAINT 23/04/08 07:04:00 23/04/08 15:30:00 U2 66/22KV TRANS AT MTS
8.433 EXCLUDE 1.2 Connection asset WO # X32058Z1
End date and time of event
CIRCUIT AVAILABILITY
Name of any circuit availabilityparameters applying to SP AusNet
Start date and time of event
Created: 02/02/2009 16:05 Printed: 8/05/2009 3:33 PM Inputs - Exclusions File: SP AusNet - Service standards report - last three quarters 2008 - template (10 February 2008).xls
AER Report Dec-08 SP AusNet Performance Page 4 of 30
Perf calc W/O B1 Trans during bus de-energ
SPIMAINT 23/04/08 10:39:00 23/04/08 11:38:00 B1 220/66KV TRANS AT TGTS
0.983 EXCLUDE 1.2 Connection asset WO # 10281990
No1 66 Cap bank during setting change
V775 - ROUTINE PROTECTION & CONTROL DEVICE SETTING AND CONF
SPIMAINT 24/04/08 13:16:00 24/04/08 18:24:00 NO.1 66KV CAPACITOR BANK AT TBTS
5.133 EXCLUDE 1.1 Unregulated transmission asset WO # V77558A9
rebate tran outage SPIMAINT 30/04/08 07:12:00 30/04/08 14:19:00 U1 66/22KV TRANS AT RWTS
7.117 EXCLUDE 1.2 Connection asset WO # 10282110
Rebate for No1 220kv Bus outage
SPIMAINT 1/05/08 07:10:00 1/05/08 14:55:00 B2 220/66KV TRANS AT TSTS
7.750 EXCLUDE 1.2 Connection asset WO # 10282181
No 2 Trans Trip FAULT 1/05/08 08:55:00 1/05/08 10:20:00 R2A/2B 220/66/22KV TRANS GROUP AT BETS
1.417 EXCLUDE 1.2 Connection asset WO # 10282478
Perf Calc No3 Trans during No1 220kv Bus outage
X508 - (GTS) STATION REDEVELOPMENT
SPICAPX 4/05/08 06:09:00 4/05/08 17:12:00 B3 220/66KV TRANS AT GTS
11.050 EXCLUDE 1.2 Connection asset WO # X50858A3
Tran rebate for Bus outage
X556 - (RWTS) REPLACE REYROLLE 66KV CBS AND ASSOCIATED CTS
SPICAPX 4/05/08 07:01:00 4/05/08 14:13:00 B4 220/66KV TRANS AT RWTS
7.200 EXCLUDE 1.2 Connection asset WO # X55658F8
O/HAUL Transformer and Div Sw (W)
SPIMAINT 4/05/08 07:09:00 4/05/08 15:04:00 L3 220/22KV TRANS AT WMTS
7.917 EXCLUDE 1.2 Connection asset WO # 10269980
VSCAP to Powercor Outage requested by DISTCO DBPROX 4/05/08 08:03:00 4/05/08 20:13:00 12.167 EXCLUDE 1.3 Third party outage WO # 10282279Condition Monitoring Metro Trans 2day West Area(W)
SPIMAINT 5/05/08 07:31:00 6/05/08 16:00:00 B4 220/66KV TRANS AT BLTS
32.483 EXCLUDE 1.2 Connection asset WO # 10273063
Install hebel wall on B3 trans
X320 - (MTS) STATION REDEVELOPMENT
SPICAPX 6/05/08 06:04:00 6/05/08 16:59:00 B3 220/66KV TRANS AT MTS
10.917 EXCLUDE 1.2 Connection asset WO # X32058S3
Install hebel wall on B3 trans
X320 - (MTS) STATION REDEVELOPMENT
SPICAPX 7/05/08 06:07:00 7/05/08 16:41:00 B3 220/66KV TRANS AT MTS
10.567 EXCLUDE 1.2 Connection asset WO # X32058S3
Conditional Monitoring Trans 1Day RTS B4
SPIMAINT 8/05/08 06:57:00 8/05/08 15:36:00 B4 220/66KV TRANS AT RTS
8.650 EXCLUDE 1.2 Connection asset WO # 10281988
No1 Trans Group oil leaks
SPIMAINT 8/05/08 07:08:00 8/05/08 18:29:00 R1 220/66/22KV TRANS GROUP AT RCTS
11.350 EXCLUDE 1.2 Connection asset WO # 10282221
Trans Rebate for Bus outage
X556 - (RWTS) REPLACE REYROLLE 66KV CBS AND ASSOCIATED CTS
SPICAPX 10/05/08 08:15:00 10/05/08 09:45:00 B3 220/66KV TRANS AT RWTS
1.500 EXCLUDE 1.2 Connection asset WO # X55658L2
Out W/O B1 Trans to connect to fut No2 S-S trans
X498 - (MBTS) REDEVELOPMENT 220KV SWITCHYARD
SPICAPX 12/05/08 07:43:00 21/05/08 12:01:00 B1 220/66KV TRANS (HOT SPARE) AT MBTS
220.300 EXCLUDE 1.2 Connection asset WO # X49858M3
SF6 Top Up at APD Outage requested by APDALCOA APDALCOA 13/05/08 14:27:00 13/05/08 15:46:00 APD NO.1 500KV LINE AT HYTS
1.317 EXCLUDE 1.3 Third party outage WO # 10282842
Out W/O A2 TRANS isolated pending test energ
Z543 - (MLTS) INTERFACE WORK FOR NEXT 500/220KV TRANSFORMER
VEN_AUG 15/05/08 19:57:00 20/05/08 11:47:00 A2 500/220KV TRANS BANK AT MLTS
111.833 EXCLUDE 1.1 Unregulated transmission asset WO # Z54358C0
APD work Outage requested by APDALCOA APDALCOA 17/05/08 09:03:00 17/05/08 12:58:00 HYTS-APD 2 500KV W
3.917 EXCLUDE 1.3 Third party outage WO # 10282960
Rebate for Bus outage SPIMAINT 18/05/08 06:45:00 18/05/08 16:02:00 B4 220/66KV TRANS AT ERTS
9.283 EXCLUDE 1.2 Connection asset WO # 10282616
VSCAP to Powercor Outage requested by DISTCO DBPROX 18/05/08 07:50:00 18/05/08 17:38:00 9.800 EXCLUDE 1.3 Third party outage WO # 10282795Perf calc W/O No3 Trans during No2 220 Bus outage
SPIMAINT 19/05/08 07:23:00 19/05/08 17:26:00 R3 220/66/22KV TRANS AT KGTS
10.050 EXCLUDE 1.2 Connection asset WO # 10282683
Perf calc W/O No3 Trans during No2 220 Bus outage
SPIMAINT 20/05/08 06:58:00 20/05/08 16:12:00 R3 220/66/22KV TRANS AT KGTS
9.233 EXCLUDE 1.2 Connection asset WO # 10282683
SCAP to PTH Outage requested by APDALCOA APDALCOA 20/05/08 07:37:00 20/05/08 15:32:00 GTS -PTH 2 220KV WY
7.917 EXCLUDE 1.3 Third party outage WO # 10281818
Out W/O A2 Trans test energ & commiss
Z543 - (MLTS) INTERFACE WORK FOR NEXT 500/220KV TRANSFORMER
VEN_AUG 20/05/08 12:55:00 20/05/08 16:49:00 A2 500/220KV TRANS BANK AT MLTS
3.900 EXCLUDE 1.1 Unregulated transmission asset WO # Z54358C1
Perf calc W/O No1 Trans during No1 220 bus outage
SPIMAINT 21/05/08 07:16:00 21/05/08 17:12:00 R1 220/66/22KV TRANS AT KGTS
9.933 EXCLUDE 1.2 Connection asset WO # 10282687
Created: 02/02/2009 16:05 Printed: 8/05/2009 3:33 PM Inputs - Exclusions File: SP AusNet - Service standards report - last three quarters 2008 - template (10 February 2008).xls
AER Report Dec-08 SP AusNet Performance Page 5 of 30
Out W/O De-energ B2 Tr- Commiss B1 Tr hot spare
X498 - (MBTS) REDEVELOPMENT 220KV SWITCHYARD
SPICAPX 21/05/08 12:24:00 21/05/08 13:26:00 B2 220/66KV TRANS AT MBTS
1.033 EXCLUDE 1.2 Connection asset WO # X49858M5
No 3 Trans at GTS FORCED 22/05/08 06:42:00 22/05/08 11:44:00 B3 220/66KV TRANS AT GTS
5.033 EXCLUDE 1.2 Connection asset WO # 10283851
Perf calc W/O No1 Trans during No1 220 bus outage
SPIMAINT 22/05/08 07:14:00 22/05/08 17:21:00 R1 220/66/22KV TRANS AT KGTS
10.117 EXCLUDE 1.2 Connection asset WO # 10282687
CT - No1 220kv Cap Bank CB CT oil samples
SPIMAINT 22/05/08 08:02:00 22/05/08 11:13:00 NO.1 220KV CAPACITOR BANK AT DDTS
3.183 EXCLUDE 1.1 Unregulated transmission asset WO # 10282226
No 3 Trans at GTS FORCED 22/05/08 11:50:00 22/05/08 14:44:00 B3 220/66KV TRANS AT GTS
2.900 EXCLUDE 1.2 Connection asset WO # 10283852
Perf calc W/O No1 Trans during No1 220 bus outage
SPIMAINT 23/05/08 06:59:00 23/05/08 13:57:00 R1 220/66/22KV TRANS AT KGTS
6.967 EXCLUDE 1.2 Connection asset WO # 10282687
Out W/O A2 Trans for 22kV isol int'lock mods
Z543 - (MLTS) INTERFACE WORK FOR NEXT 500/220KV TRANSFORMER
VEN_AUG 23/05/08 07:06:00 23/05/08 14:14:00 A2 500/220KV TRANS BANK AT MLTS
7.133 EXCLUDE 1.1 Unregulated transmission asset WO # Z54358C3
Rebate Tran for Bus outage
X556 - (RWTS) REPLACE REYROLLE 66KV CBS AND ASSOCIATED CTS
SPICAPX 25/05/08 08:20:00 25/05/08 08:45:00 B4 220/66KV TRANS AT RWTS
0.417 EXCLUDE 1.2 Connection asset WO # X55658M2
Trans Rebate for Bus outage
X556 - (RWTS) REPLACE REYROLLE 66KV CBS AND ASSOCIATED CTS
SPICAPX 25/05/08 09:01:00 25/05/08 11:48:00 B3 220/66KV TRANS AT RWTS
2.783 EXCLUDE 1.2 Connection asset WO # X55658M5
APD No2 Line de-energised for Alcoa.
Outage requested by APDALCOA APDALCOA 26/05/08 14:36:00 26/05/08 15:29:00 APD NO.2 500KV LINE AT HYTS
0.883 EXCLUDE 1.3 Third party outage WO # 10283375
Tran rebate for Bus outage
X320 - (MTS) STATION REDEVELOPMENT
SPIMAINT 27/05/08 06:10:00 27/05/08 16:43:00 U1 66/22KV TRANS AT MTS
10.550 EXCLUDE 1.2 Connection asset WO # X32058Z4
Tran rebate for Bus outage
X320 - (MTS) STATION REDEVELOPMENT
SPIMAINT 27/05/08 06:10:00 27/05/08 16:43:00 B3 220/66KV TRANS AT MTS
10.550 EXCLUDE 1.2 Connection asset WO # X32058Z3
OVERHAUL TRANSFORMER
SPIMAINT 27/05/08 07:10:00 27/05/08 15:38:00 B3 220/66KV TRANS AT RTS
8.467 EXCLUDE 1.2 Connection asset WO # 10282344
Tran rebate for Bus outage
X320 - (MTS) STATION REDEVELOPMENT
SPIMAINT 28/05/08 06:10:00 28/05/08 15:28:00 U1 66/22KV TRANS AT MTS
9.300 EXCLUDE 1.2 Connection asset WO # X32058Z4
Tran rebate for Bus outage
X320 - (MTS) STATION REDEVELOPMENT
SPIMAINT 28/05/08 06:10:00 28/05/08 15:28:00 B3 220/66KV TRANS AT MTS
9.300 EXCLUDE 1.2 Connection asset WO # X32058Z3
O/HAUL Transformer and Div Sw (EM)
SPIMAINT 28/05/08 07:20:00 28/05/08 15:21:00 B4 220/66KV TRANS AT RTS
8.017 EXCLUDE 1.2 Connection asset WO # 10269289
REPAIR TRANS COOLING
SPIMAINT 29/05/08 07:16:00 29/05/08 16:04:00 B1 220/66KV TRANS AT RTS
8.800 EXCLUDE 1.2 Connection asset WO # 10282764
Out W/O No2 66kV Cap bank prot setting change
V775 - ROUTINE PROTECTION & CONTROL DEVICE SETTING AND CONF
SPIMAINT 29/05/08 07:47:00 29/05/08 17:36:00 NO.2 220KV CAPACITOR BANK AT ATS
9.817 EXCLUDE 1.1 Unregulated transmission asset WO # V77558B3
Install Column wall B1 Trans & No2 66kv Bus
X320 - (MTS) STATION REDEVELOPMENT
SPIMAINT 30/05/08 06:01:00 30/05/08 15:36:00 B1 220/66KV TRANS AT MTS
9.583 EXCLUDE 1.2 Connection asset WO # X32058Z5
Perf Calc B4 Trans during No2 220kv Bus Outage
X508 - (GTS) STATION REDEVELOPMENT
SPICAPX 31/05/08 06:00:00 31/05/08 17:50:00 B4 220/66KV TRANS AT GTS
11.833 EXCLUDE 1.2 Connection asset WO # X50858B7
LYA 1 Gen Trans isolation
Outage requested by GENCO GENCO 31/05/08 07:31:00 31/05/08 23:59:59 NO.1 GEN 500/21KV TRANS AT LYPA
16.483 EXCLUDE 1.3 Third party outage WO # 10283549
LYA 1 Gen Trans isolation
Outage requested by GENCO GENCO 1/06/08 00:00:00 1/06/08 13:47:00 NO.1 GEN 500/21KV TRANS AT LYPA
13.783 EXCLUDE 1.3 Third party outage WO # 10283549
rebate Tran for bus outage
SPIMAINT 1/06/08 06:42:00 1/06/08 14:36:00 B1 220/66KV TRANS AT RTS
7.900 EXCLUDE 1.2 Connection asset WO # 10282646
Replace CT on B2 Trans 220kv CB
X670 - CT REPLACEMENT PROGRAM - STAGE 2
SPICAPX 2/06/08 07:07:00 6/06/08 12:53:00 B2 220/66KV TRANS AT TBTS
101.767 EXCLUDE 1.2 Connection asset WO # X67058A7
Out W/O Perf Calc No2 Transformer
SPIMAINT 3/06/08 07:46:00 3/06/08 17:18:00 R2 220/66/22KV TRANS AT KGTS
9.533 EXCLUDE 1.2 Connection asset WO # 10283458
REMOVE BIRD NEST SPIMAINT 3/06/08 10:37:00 3/06/08 12:18:00 L2 220/22KV TRANS BANK AT RWTS
1.683 EXCLUDE 1.2 Connection asset WO # 10282965
Out W/O Perf Calc No2 Transformer
SPIMAINT 4/06/08 07:03:00 4/06/08 17:13:00 R2 220/66/22KV TRANS AT KGTS
10.167 EXCLUDE 1.2 Connection asset WO # 10283458
Created: 02/02/2009 16:05 Printed: 8/05/2009 3:33 PM Inputs - Exclusions File: SP AusNet - Service standards report - last three quarters 2008 - template (10 February 2008).xls
AER Report Dec-08 SP AusNet Performance Page 6 of 30
Basslink Remote Trip for CB fault at BLLY
Outage requested by GENCO GENCO 8/06/08 00:31:00 8/06/08 02:36:00 BLLY 500KV LINE AT LYPS
2.083 EXCLUDE 1.3 Third party outage WO # 10284017
SCAP to JLGS Outage requested by GENCO GENCO 10/06/08 15:31:00 30/06/08 23:59:59 NO.2 UNIT 220/10.5KV TRANS AT JLGA
488.483 EXCLUDE 1.3 Third party outage WO # 10283935
Condition Monitoring Metro Trans 2day Valley Area
SPIMAINT 12/06/08 07:17:00 13/06/08 14:22:00 B1 220/66KV TRANS AT MWTS
31.083 EXCLUDE 1.2 Connection asset WO # 10273039
Install Rack Structure Handrails and Lighting
X508 - (GTS) STATION REDEVELOPMENT
SPICAPX 14/06/08 05:51:00 14/06/08 15:50:00 B4 220/66KV TRANS AT GTS
9.983 EXCLUDE 1.2 Connection asset WO # X50858C9
Out W/O No1 220kV Cap bank prot setting changes
V775 - ROUTINE PROTECTION & CONTROL DEVICE SETTING AND CONF
SPIMAINT 14/06/08 08:09:00 14/06/08 14:30:00 NO.1 220KV CAPACITOR BANK AT DDTS
6.350 EXCLUDE 1.1 Unregulated transmission asset WO # V77558B4
Replace CT on B1 Trans 220kv CB
X670 - CT REPLACEMENT PROGRAM - STAGE 2
SPICAPX 16/06/08 07:05:00 19/06/08 11:46:00 B1 220/66KV TRANS AT TBTS
76.683 EXCLUDE 1.2 Connection asset WO # X67058A8
OVERHAUL OF A TRANSFORMER BANK/GROUP
SPIMAINT 16/06/08 10:15:00 17/06/08 15:48:00 B5 220/66KV TRANS GROUP AT BLTS
29.550 EXCLUDE 1.2 Connection asset WO # 10267836
Repaire Oil leaks SPIMAINT 21/06/08 06:16:00 22/06/08 15:27:00 A1 500/220KV TRANS BANK AT CBTS
33.183 EXCLUDE 1.1 Unregulated transmission asset WO # 10283555
Rebate Trans for Bus outage
V786 - (CBTS) URGENT REPLACEMENT OF ROTS 4L 500KV CVT
SPIMAINT 21/06/08 07:05:00 21/06/08 16:31:00 B1 220/66KV TRANS AT CBTS
9.433 EXCLUDE 1.2 Connection asset WO # V78658A2
Request by City Power Outage requested by DISTCO DBPROX 21/06/08 11:08:00 22/06/08 07:04:00 ROTS NO.1 220KV LINE AT RTS
19.933 EXCLUDE 1.3 Third party outage WO # 10284035
Rebate Tran for Bus outage
X556 - (RWTS) REPLACE REYROLLE 66KV CBS AND ASSOCIATED CTS
SPICAPX 22/06/08 07:38:00 22/06/08 12:12:00 B2 220/66KV TRANS AT RWTS
4.567 EXCLUDE 1.2 Connection asset WO # X55658O8
tran rebate for bus outage
SPIMAINT 24/06/08 07:09:00 24/06/08 15:46:00 B2 220/66KV TRANS AT SVTS
8.617 EXCLUDE 1.2 Connection asset WO # 10282644
SMTS - DDTS No 1 Line Series Cap Bank Bypassed
FAULT 24/06/08 10:51:00 24/06/08 11:08:00 0.283 EXCLUDE 1.1 Unregulated transmission asset WO # 10284608
Work at APD No2 Reactor Gas Relay
Outage requested by APDALCOA APDALCOA 25/06/08 07:37:00 25/06/08 17:17:00 APD NO.2 500KV LINE AT HYTS
9.667 EXCLUDE 1.3 Third party outage WO # 10284594
De-energisation of No 1 220 kV Bus for AGL Hydro
Outage requested by STHHYDRO GENCO 27/06/08 07:17:00 27/06/08 07:20:00 0.050 EXCLUDE 1.3 Third party outage WO # 10284697
B1 Trans OUT W/O - Replace Insulators at the Rack
X508 - (GTS) STATION REDEVELOPMENT
SPICAPX 28/06/08 05:34:00 28/06/08 17:57:00 B1 220/66KV TRANS AT GTS
12.383 EXCLUDE 1.2 Connection asset WO # X50858D7
O/HAUL Transformer without Div Sw (W)
SPIMAINT 28/06/08 07:05:00 28/06/08 17:40:00 B5 220/66KV TRANS AT TTS
10.583 EXCLUDE 1.2 Connection asset WO # 10249897
Trans Rebate for Bus Outage
X556 - (RWTS) REPLACE REYROLLE 66KV CBS AND ASSOCIATED CTS
SPICAPX 28/06/08 09:37:00 28/06/08 11:07:00 B2 220/66KV TRANS AT RWTS
1.500 EXCLUDE 1.2 Connection asset WO # X55658O2
O/HAUL Transformer without Div Sw (W)
SPIMAINT 29/06/08 06:58:00 29/06/08 15:25:00 B5 220/66KV TRANS AT TTS
8.450 EXCLUDE 1.2 Connection asset WO # 10249897
Rebate Trans for Bus outage
V786 - (CBTS) URGENT REPLACEMENT OF ROTS 4L 500KV CVT
SPIMAINT 29/06/08 07:09:00 29/06/08 14:41:00 B2 220/66KV TRANS AT CBTS
7.533 EXCLUDE 1.2 Connection asset WO # V78658A4
Overhaul Transformer at YPS
SPIMAINT 30/06/08 08:04:00 30/06/08 23:59:59 AUX 'D' 220/22KV TRANS AT YPS
15.933 EXCLUDE 1.2 Connection asset WO # 10272883
B2 Trans wiring modifications
FAULT 30/06/08 12:10:00 30/06/08 16:29:00 B2 220/66KV TRANS AT RWTS
4.317 EXCLUDE 1.2 Connection asset WO # 10284818
APD work Outage requested by APDALCOA APDALCOA 30/06/08 13:07:00 30/06/08 17:01:00 HYTS-APD 2 500KV W
3.900 EXCLUDE 1.3 Third party outage WO # 10284672
O/HAUL Transformer Div Mechanism (N)
SPIMAINT 30/06/08 13:48:00 30/06/08 16:35:00 B2 220/66KV TRANS AT HOTS
2.783 EXCLUDE 1.2 Connection asset WO # 10273485
SCAP to JLGS Outage requested by GENCO GENCO 1/07/08 00:00:00 16/07/08 14:52:00 NO.2 UNIT 220/10.5KV TRANS AT JLGA
374.867 EXCLUDE 1.3 Third party outage WO # 10283935
Created: 02/02/2009 16:05 Printed: 8/05/2009 3:33 PM Inputs - Exclusions File: SP AusNet - Service standards report - last three quarters 2008 - template (10 February 2008).xls
AER Report Dec-08 SP AusNet Performance Page 7 of 30
Overhaul Transformer at YPS
SPIMAINT 1/07/08 00:00:00 1/07/08 13:50:00 AUX 'D' 220/22KV TRANS AT YPS
13.833 EXCLUDE 1.2 Connection asset WO # 10272883
Rebate for Cap Bank SPIMAINT 2/07/08 07:04:00 2/07/08 17:24:00 NO.1 220KV CAPACITOR BANK AT ROTS
10.333 EXCLUDE 1.1 Unregulated transmission asset WO # 10285015
Overhaul Transformer at YPS
SPIMAINT 2/07/08 07:55:00 3/07/08 13:48:00 AUX 'E' 220/22KV TRANS AT YPS
29.883 EXCLUDE 1.2 Connection asset WO # 10272885
O/HAUL Transformer Div Mechanism (N)
SPIMAINT 4/07/08 07:51:00 4/07/08 13:20:00 B3 220/66KV TRANS AT HOTS
5.483 EXCLUDE 1.2 Connection asset WO # 10273483
O/HAUL Transformer Div Mechanism - bucs
SPIMAINT 4/07/08 08:45:00 4/07/08 15:10:00 B1 220/66KV TRANS AT WMTS
6.417 EXCLUDE 1.2 Connection asset WO # 10269978
Tran Rebate for Bus Outage
V769 - (CBTS) PRIMARY EQUIPMENT DEFECTS REPAIR
SPICAPX 6/07/08 07:51:00 6/07/08 15:01:00 B1 220/66KV TRANS AT CBTS
7.167 EXCLUDE 1.2 Connection asset WO # V76958B5
PTH Work Outage requested by APDALCOA APDALCOA 7/07/08 08:00:00 7/07/08 15:13:00 GTS -PTH 2 220KV WY
7.217 EXCLUDE 1.3 Third party outage WO # 10284989
SCAN Repaire hot joint
SPIMAINT 8/07/08 07:10:00 8/07/08 14:38:00 B3 220/66KV TRANS AT HTS
7.467 EXCLUDE 1.2 Connection asset WO # 10283623
O/HAUL Transformer and Div Sw (W)
SPIMAINT 8/07/08 07:15:00 9/07/08 15:25:00 B4 220/66KV TRANS AT BLTS
32.167 EXCLUDE 1.2 Connection asset WO # 10270222
Condition Monitoring Country Trans 2day North
SPIMAINT 9/07/08 06:54:00 11/07/08 12:56:00 R4 220/66/22KV TRANS AT BETS
54.033 EXCLUDE 1.2 Connection asset WO # 10273029
Investigate incorrect B2 Tran Gas Relay operation
SPIMAINT 10/07/08 09:02:00 10/07/08 14:56:00 B2 220/66KV TRANS AT HOTS
5.900 EXCLUDE 1.2 Connection asset WO # 10285021
Trans Rebate for Bus outage
X556 - (RWTS) REPLACE REYROLLE 66KV CBS AND ASSOCIATED CTS
SPICAPX 12/07/08 06:35:00 12/07/08 12:46:00 B3 220/66KV TRANS AT RWTS
6.183 EXCLUDE 1.2 Connection asset WO # X55658P5
Perf calc W/O No2 Trans GRP 22kV only
X497 - (BETS) STATION REDEVELOPMENT
SPICAPX 12/07/08 09:30:00 12/07/08 18:20:00 R2A/2B 220/66/22KV TRANS GROUP AT BETS
8.833 EXCLUDE 1.2 Connection asset WO # X49758M1
Tran rebate for Bus outage
X556 - (RWTS) REPLACE REYROLLE 66KV CBS AND ASSOCIATED CTS
SPICAPX 12/07/08 13:12:00 12/07/08 18:33:00 B4 220/66KV TRANS AT RWTS
5.350 EXCLUDE 1.2 Connection asset WO # X55658P9
Rebate Tran for Bus outage
X556 - (RWTS) REPLACE REYROLLE 66KV CBS AND ASSOCIATED CTS
SPICAPX 13/07/08 06:41:00 13/07/08 12:42:00 B1 220/66KV TRANS AT RWTS
6.017 EXCLUDE 1.1 Unregulated transmission asset WO # X55658S2
Rebate Tran for Bus outage
X556 - (RWTS) REPLACE REYROLLE 66KV CBS AND ASSOCIATED CTS
SPICAPX 13/07/08 06:41:00 13/07/08 12:42:00 U1 66/22KV TRANS AT RWTS
6.017 EXCLUDE 1.2 Connection asset WO # X55658S1
Perf calc W/O No4 Trans 22kV only
X497 - (BETS) STATION REDEVELOPMENT
SPICAPX 13/07/08 07:04:00 13/07/08 12:00:00 R4 220/66/22KV TRANS AT BETS
4.933 EXCLUDE 1.2 Connection asset WO # X49758M2
Tran Rebate for Bus outage
X556 - (RWTS) REPLACE REYROLLE 66KV CBS AND ASSOCIATED CTS
SPICAPX 13/07/08 12:59:00 13/07/08 18:32:00 B2 220/66KV TRANS AT RWTS
5.550 EXCLUDE 1.2 Connection asset WO # X55658S4
O/H Trans SPIMAINT 14/07/08 07:04:00 14/07/08 15:34:00 B3 220/66KV TRANS AT WMTS
8.500 EXCLUDE 1.2 Connection asset WO # 10249107
LNGS 2 SCAP Outage requested by GENCO GENCO 14/07/08 07:50:00 17/07/08 14:39:00 LNGS NO.2 GEN TRANS 220KV LINE AT ATS
78.817 EXCLUDE 1.1 Unregulated transmission asset WO # 10285069
SF6 Alarm to moved from RTU to SCIMS
X556 - (RWTS) REPLACE REYROLLE 66KV CBS AND ASSOCIATED CTS
SPICAPX 17/07/08 07:07:00 17/07/08 15:25:00 U1 66/22KV TRANS AT RWTS
8.300 EXCLUDE 1.2 Connection asset WO # X55658T4
Repair No 1 Trans oil leaks
SPIMAINT 18/07/08 08:03:00 18/07/08 14:08:00 NO.1 330/66/22KV TRANS AT WOTS
6.083 EXCLUDE 1.2 Connection asset WO # 10275340
Sealing of A2 Trans Enclosure Wall seams
Z546 - (MLTS) 500/220KV TRANSFORMER CONTESTABLE
VEN_AUG 19/07/08 08:02:00 19/07/08 17:07:00 A2 500/220KV TRANS BANK AT MLTS
9.083 EXCLUDE 1.1 Unregulated transmission asset WO # Z54658A7
Tran Rebate for Bus Outage
V769 - (CBTS) PRIMARY EQUIPMENT DEFECTS REPAIR
SPICAPX 20/07/08 07:10:00 20/07/08 14:44:00 B2 220/66KV TRANS AT CBTS
7.567 EXCLUDE 1.2 Connection asset WO # V76958B0
Created: 02/02/2009 16:05 Printed: 8/05/2009 3:33 PM Inputs - Exclusions File: SP AusNet - Service standards report - last three quarters 2008 - template (10 February 2008).xls
AER Report Dec-08 SP AusNet Performance Page 8 of 30
Adjust ROTS No3 Line / B1 Trans CB Trans Side ROI
X320 - (MTS) STATION REDEVELOPMENT
SPIMAINT 21/07/08 06:26:00 21/07/08 15:16:00 B1 220/66KV TRANS AT MTS
8.833 EXCLUDE 1.2 Connection asset WO # X32058AE
REPAIR/REPLACE FAULTY FAN
SPIMAINT 22/07/08 07:34:00 22/07/08 12:13:00 B2 220/66KV TRANS AT TBTS
4.650 EXCLUDE 1.2 Connection asset WO # 10285085
Fault No3 220/66KV Transformer.
FAULT 23/07/08 05:46:00 23/07/08 20:39:00 B3 220/66KV TRANS AT GTS
14.883 EXCLUDE 1.2 Connection asset WO # 10285380
Earth the metallic ducting in enclosure
X320 - (MTS) STATION REDEVELOPMENT
SPIMAINT 24/07/08 06:59:00 24/07/08 13:41:00 U1 66/22KV TRANS AT MTS
6.700 EXCLUDE 1.2 Connection asset WO # X32058AF
Repair B1 trans fans SPIMAINT 25/07/08 06:58:00 25/07/08 15:05:00 B1 220/66KV TRANS AT HTS
8.117 EXCLUDE 1.2 Connection asset WO # 10285209
B4 Trans - Install cable tray and conduits
X508 - (GTS) STATION REDEVELOPMENT
SPICAPX 26/07/08 06:02:00 26/07/08 14:58:00 B4 220/66KV TRANS AT GTS
8.933 EXCLUDE 1.2 Connection asset WO # X50858E5
Tran Rebate for Bus Outage
V769 - (CBTS) PRIMARY EQUIPMENT DEFECTS REPAIR
SPICAPX 27/07/08 07:08:00 27/07/08 14:55:00 B2 220/66KV TRANS AT CBTS
7.783 EXCLUDE 1.2 Connection asset WO # V76958B3
REPAIR FANS,PUMPS & BUSHING OIL LEVELS
SPIMAINT 28/07/08 07:15:00 28/07/08 15:12:00 B3 220/66KV TRANS AT RWTS
7.950 EXCLUDE 1.2 Connection asset WO # 10285265
Scap to PTH Outage requested by APDALCOA APDALCOA 29/07/08 07:22:00 29/07/08 14:33:00 GTS -PTH 1 220KV WY
7.183 EXCLUDE 1.3 Third party outage WO # 10285168
REPAIR FANS, PUMPS AND BUSHING OIL LEVELS
SPIMAINT 29/07/08 07:35:00 29/07/08 15:10:00 B4 220/66KV TRANS AT RWTS
7.583 EXCLUDE 1.2 Connection asset WO # 10285267
Scap to PTH Outage requested by APDALCOA APDALCOA 30/07/08 07:18:00 30/07/08 15:10:00 GTS -PTH 2 220KV WY
7.867 EXCLUDE 1.3 Third party outage WO # 10285171
Scap to PTH Outage requested by APDALCOA APDALCOA 31/07/08 07:28:00 31/07/08 14:55:00 GTS -PTH 1 220KV WY
7.450 EXCLUDE 1.3 Third party outage WO # 10285170
REPAIR OIL PUMP & FAN MOTORS
SPIMAINT 1/08/08 07:06:00 1/08/08 14:25:00 B3 220/66KV TRANS AT SVTS
7.317 EXCLUDE 1.2 Connection asset WO # 10285375
Scap to PTH Outage requested by APDALCOA APDALCOA 1/08/08 07:15:00 1/08/08 13:34:00 GTS -PTH 2 220KV WY
6.317 EXCLUDE 1.3 Third party outage WO # 10285172
Avail plant due to bus outage fix 1-4 BT CB isol
FORCED 1/08/08 13:29:00 1/08/08 15:34:00 B1 220/66KV TRANS AT MWTS
2.083 EXCLUDE 1.2 Connection asset WO # 10286928
APD Work Outage requested by APDALCOA APDALCOA 6/08/08 07:05:00 6/08/08 17:40:00 HYTS-APD 2 500KV W
10.583 EXCLUDE 1.3 Third party outage WO # 10285412
Check Bucholtz X556 - (RWTS) REPLACE REYROLLE 66KV CBS AND ASSOCIATED CTS
SPICAPX 6/08/08 07:10:00 6/08/08 17:23:00 B1 220/66KV TRANS AT RWTS
10.217 EXCLUDE 1.1 Unregulated transmission asset WO # X55658U8
APD Work Outage requested by APDALCOA APDALCOA 7/08/08 07:18:00 7/08/08 18:45:00 HYTS-APD 2 500KV W
11.450 EXCLUDE 1.3 Third party outage WO # 10285412
B2 Transformer tripped on low oil.
FAULT 10/08/08 05:06:00 10/08/08 12:56:00 B2 220/66KV TRANS AT SVTS
7.833 EXCLUDE 1.2 Connection asset WO # 10285904
decommiss No1 S/S Trans
X508 - (GTS) STATION REDEVELOPMENT
SPICAPX 10/08/08 06:19:00 10/08/08 11:58:00 B1 220/66KV TRANS AT GTS
5.650 EXCLUDE 1.2 Connection asset WO # X50858F1
Rebate Trans outage SPIMAINT 10/08/08 07:33:00 10/08/08 11:16:00 B3 220/66KV TRANS AT ERTS
3.717 EXCLUDE 1.2 Connection asset WO # 10285625
Inspect Buchholz Relay & adjust as Required
X320 - (MTS) STATION REDEVELOPMENT
SPIMAINT 11/08/08 06:40:00 11/08/08 15:56:00 B1 220/66KV TRANS AT MTS
9.267 EXCLUDE 1.2 Connection asset WO # X32058AH
Perf calc W/O No2 Tr grp
SPIMAINT 11/08/08 07:54:00 11/08/08 15:59:00 R2 220/66/22KV TRANS GROUP AT RCTS
8.083 EXCLUDE 1.2 Connection asset WO # 10285538
Inspect Buchholz Relay & adjust as Required
X320 - (MTS) STATION REDEVELOPMENT
SPIMAINT 12/08/08 06:50:00 12/08/08 16:52:00 B3 220/66KV TRANS AT MTS
10.033 EXCLUDE 1.2 Connection asset WO # X32058AJ
Inspect Buchholz Relay & adjust as Required
X320 - (MTS) STATION REDEVELOPMENT
SPIMAINT 13/08/08 06:23:00 13/08/08 15:00:00 U1 66/22KV TRANS AT MTS
8.617 EXCLUDE 1.2 Connection asset WO # X32058AK
Inspect Buchholz Relay
X320 - (MTS) STATION REDEVELOPMENT
SPIMAINT 14/08/08 06:18:00 14/08/08 15:24:00 U2 66/22KV TRANS AT MTS
9.100 EXCLUDE 1.2 Connection asset WO # X32058AG
Total circuit availabilityS1
Created: 02/02/2009 16:05 Printed: 8/05/2009 3:33 PM Inputs - Exclusions File: SP AusNet - Service standards report - last three quarters 2008 - template (10 February 2008).xls
AER Report Dec-08 SP AusNet Performance Page 9 of 30
Trans rebate for bus outage
FAULT 14/08/08 07:13:00 14/08/08 09:05:00 B1 220/66KV TRANS AT TBTS
1.867 EXCLUDE 1.2 Connection asset WO # 10286205
Rebate outage for Cap FAULT 14/08/08 07:13:00 17/08/08 14:38:00 NO.1 66KV CAPACITOR BANK AT TBTS
79.417 EXCLUDE 1.1 Unregulated transmission asset WO # 10286231
remove 1 upper and replace 1 upper fan
SPIMAINT 14/08/08 07:32:00 14/08/08 18:15:00 B1 220/66KV TRANS AT FBTS
10.717 EXCLUDE 1.2 Connection asset WO # 10285733
replace upper faulty fan
SPIMAINT 15/08/08 07:37:00 15/08/08 16:57:00 B4 220/66KV TRANS AT FBTS
9.333 EXCLUDE 1.2 Connection asset WO # 10285735
Rebate Tran for Bus outage
SPIMAINT 17/08/08 07:08:00 17/08/08 13:24:00 B3 220/66KV TRANS AT SVTS
6.267 EXCLUDE 1.2 Connection asset WO # 10283619
SCAP to LNGS Outage requested by GENCO GENCO 18/08/08 07:49:00 21/08/08 12:00:00 LNGS NO.2 GEN TRANS 220KV LINE AT ATS
76.183 EXCLUDE 1.1 Unregulated transmission asset WO # 10286073
O/HAUL Transformer Div Mechanism (N)
SPIMAINT 19/08/08 07:12:00 19/08/08 16:52:00 R2A/2B 220/66/22KV TRANS GROUP AT BETS
9.667 EXCLUDE 1.2 Connection asset WO # 10268287
O/HAUL Transformer Div Mechanism (N)
SPIMAINT 20/08/08 07:05:00 20/08/08 18:03:00 R2A/2B 220/66/22KV TRANS GROUP AT BETS
10.967 EXCLUDE 1.2 Connection asset WO # 10268287
Repair oil leak SPIMAINT 20/08/08 07:13:00 20/08/08 14:48:00 B2 220/66KV TRANS AT SVTS
7.583 EXCLUDE 1.2 Connection asset WO # 10285919
Repair/replace two faulty fans from Trans
SPIMAINT 20/08/08 08:27:00 20/08/08 14:40:00 NO.1 330/66/22KV TRANS AT WOTS
6.217 EXCLUDE 1.2 Connection asset WO # 10285032
O/HAUL Transformer Div Mechanism (N)
SPIMAINT 21/08/08 07:03:00 21/08/08 16:17:00 R2A/2B 220/66/22KV TRANS GROUP AT BETS
9.233 EXCLUDE 1.2 Connection asset WO # 10268287
O/HAUL Transformer Div Mechanism (N)
SPIMAINT 22/08/08 07:05:00 22/08/08 16:01:00 R2A/2B 220/66/22KV TRANS GROUP AT BETS
8.933 EXCLUDE 1.2 Connection asset WO # 10268287
remove faulty upper fans & invest faulty wti
SPIMAINT 22/08/08 08:07:00 22/08/08 15:42:00 B2 220/66KV TRANS AT ATS
7.583 EXCLUDE 1.2 Connection asset WO # 10285915
Repair oil leak SPIMAINT 26/08/08 07:24:00 26/08/08 15:01:00 B2 220/66KV TRANS AT SVTS
7.617 EXCLUDE 1.2 Connection asset WO # 10285919
APD Work Outage requested by APDALCOA APDALCOA 26/08/08 07:46:00 26/08/08 16:29:00 HYTS-APD 1 500KV W
8.717 EXCLUDE 1.3 Third party outage WO # 10286343
APD Work Outage requested by APDALCOA APDALCOA 27/08/08 07:30:00 27/08/08 09:23:00 HYTS-APD 2 500KV W
1.883 EXCLUDE 1.3 Third party outage WO # 10286344
Perf calc W/O No1 Trans during its 220kV CB O-H
SPIMAINT 28/08/08 07:41:00 28/08/08 14:37:00 R1 220/66/22KV TRANS AT KGTS
6.933 EXCLUDE 1.2 Connection asset WO # 10285822
O/HAUL Transformer and Trafo Union Div Sw (EM)
SPIMAINT 29/08/08 07:05:00 29/08/08 14:55:00 B3 220/66KV TRANS AT RWTS
7.833 EXCLUDE 1.2 Connection asset WO # 10269264
Perf calc W/O No3 Trans during its 220kV CB O-H
SPIMAINT 29/08/08 07:51:00 29/08/08 16:16:00 R3 220/66/22KV TRANS AT KGTS
8.417 EXCLUDE 1.2 Connection asset WO # 10285824
Rebate for Bus outage SPIMAINT 31/08/08 06:45:00 31/08/08 14:46:00 B4 220/66KV TRANS AT RWTS
8.017 EXCLUDE 1.2 Connection asset WO # 10282645
SCAP to LNGS Outage requested by GENCO GENCO 1/09/08 07:23:00 4/09/08 15:00:00 LNGS NO.1 GEN TRANS 220KV LINE AT ATS
79.617 EXCLUDE 1.1 Unregulated transmission asset WO # 10286479
O/Haul 22KV CAPACITOR BANK
SPIMAINT 3/09/08 07:01:00 3/09/08 14:46:00 NO.1 22KV CAPACITOR BANK AT RWTS
7.750 EXCLUDE 1.2 Connection asset WO # 10272575
Created: 02/02/2009 16:05 Printed: 8/05/2009 3:33 PM Inputs - Exclusions File: SP AusNet - Service standards report - last three quarters 2008 - template (10 February 2008).xls
AER Report Dec-08 SP AusNet Performance Page 10 of 30
Work for SWN SM165a
SPIMAINT 3/09/08 09:25:00 3/09/08 16:22:00 B1 220/66KV TRANS AT RWTS
6.950 EXCLUDE 1.1 Unregulated transmission asset WO # 10286681
Rebate W/O for RWTS Bus Trip
FAULT 3/09/08 16:58:00 3/09/08 17:18:00 L3 220/22KV TRANS BANK AT RWTS
0.333 EXCLUDE 1.2 Connection asset WO # 10286811
O/Haul 22KV CAPACITOR BANK
SPIMAINT 4/09/08 07:17:00 4/09/08 15:30:00 NO.2 22KV CAPACITOR BANK AT RWTS
8.217 EXCLUDE 1.2 Connection asset WO # 10272577
REBATE TRANS for CB outage
SPIMAINT 5/09/08 06:57:00 5/09/08 15:20:00 L3 220/22KV TRANS BANK AT RWTS
8.383 EXCLUDE 1.2 Connection asset WO # 10282655
Rebate Tran for Bus outage
SPIMAINT 6/09/08 07:22:00 6/09/08 13:13:00 B1 220/66KV TRANS AT SVTS
5.850 EXCLUDE 1.2 Connection asset WO # 10283621
Perf calc W/O B2 Trans during No2 66kV Bus outage
FORCED 6/09/08 14:05:00 6/09/08 16:19:00 B2 220/66KV TRANS AT TGTS
2.233 EXCLUDE 1.2 Connection asset WO # 10286906
Rebate for Tran outage
X670 - CT REPLACEMENT PROGRAM - STAGE 2
SPICAPX 10/09/08 07:06:00 12/09/08 18:29:00 B1 220/66KV TRANS AT TBTS
59.383 EXCLUDE 1.2 Connection asset WO # X67058B7
Replace oil pump X320 - (MTS) STATION REDEVELOPMENT
SPIMAINT 11/09/08 06:25:00 11/09/08 14:42:00 B4 220/66KV TRANS AT SVTS
8.283 EXCLUDE 1.2 Connection asset WO # X32058TT
out w/o for cap bank HPL - B1GS CB TESTING BY ABB
SPIMAINT 11/09/08 07:18:00 11/09/08 15:32:00 NO.2 220KV CAPACITOR BANK AT ATS
8.233 EXCLUDE 1.1 Unregulated transmission asset WO # 10296277
Condition Monitoring Metro Trans 3day Valley Area
SPIMAINT 14/09/08 07:08:00 18/09/08 16:38:00 NO.1 11/220KV TRANS BANK AT MPS (10106) SJ=001152
105.500 EXCLUDE 1.2 Connection asset WO # 10273043
Trans Rebate for Bus Outage
SPIMAINT 14/09/08 10:00:00 14/09/08 13:37:00 B1 220/66KV TRANS AT RTS
3.617 EXCLUDE 1.2 Connection asset WO # 10286960
O/HAUL Transformer and Div Sw (N)
SPIMAINT 16/09/08 08:58:00 16/09/08 15:55:00 R3 220/66/22KV TRANS AT KGTS
6.950 EXCLUDE 1.2 Connection asset WO # 10272413
O/HAUL Transformer and Div Sw (N)
SPIMAINT 17/09/08 07:30:00 17/09/08 17:12:00 R3 220/66/22KV TRANS AT KGTS
9.700 EXCLUDE 1.2 Connection asset WO # 10272413
O/HAUL Transformer and Div Sw (N)
SPIMAINT 18/09/08 07:40:00 18/09/08 15:54:00 R3 220/66/22KV TRANS AT KGTS
8.233 EXCLUDE 1.2 Connection asset WO # 10272413
Isolations for SCAP on LYA Unit 2
Outage requested by GENCO GENCO 22/09/08 12:35:00 23/09/08 09:09:00 LYPS-HWTS 1 500KV G
20.567 EXCLUDE 1.3 Third party outage WO # 10296421
No2 Trans Grp Div Sw Service ops O/Haul
SPIMAINT 23/09/08 07:02:00 23/09/08 15:05:00 R2A/2B 220/66/22KV TRANS GROUP AT BETS
8.050 EXCLUDE 1.2 Connection asset WO # 10286001
No2 Trans Grp Div Sw Service ops O/Haul
SPIMAINT 24/09/08 07:02:00 24/09/08 16:37:00 R2A/2B 220/66/22KV TRANS GROUP AT BETS
9.583 EXCLUDE 1.2 Connection asset WO # 10286001
Electranet Outage Outage requested by ELECTRAN ELECTRAN 25/09/08 08:40:00 25/09/08 17:18:00 HYTS-SESS 1 275KV WH
8.633 EXCLUDE 1.3 Third party outage WO # 10286025
Rebate for Bus Outage SPIMAINT 28/09/08 06:27:00 28/09/08 15:15:00 B2 220/66KV TRANS AT RWTS
8.800 EXCLUDE 1.2 Connection asset WO # 10286549
Transgrid Outage Outage requested by TRANSGRD TRANSGRD 29/09/08 10:04:00 29/09/08 16:06:00 MSS -DDTS 1 330KV NW
6.033 EXCLUDE 1.3 Third party outage WO # 10296473
Out W/O No2A Cap Bank to replace CB Sf6 aux rly
SPIMAINT 30/09/08 10:33:00 30/09/08 17:07:00 NO.2A 66KV CAPACITOR BANK AT BETS
6.567 EXCLUDE 1.1 Unregulated transmission asset WO # 10296637
Switching for APD Outage requested by APDALCOA APDALCOA 1/10/08 11:09:00 1/10/08 12:36:00 APD NO.2 500KV LINE AT HYTS
1.450 EXCLUDE 1.3 Third party outage WO # 10296698
Out W/O No3 Trans to install 220kV CVD's
X432 - (RCTS) STATION REDEVELOPMENT
SPICAPX 2/10/08 06:02:00 2/10/08 16:53:00 R3 220/66/22KV TRANS AT RCTS
10.850 EXCLUDE 1.1 Unregulated transmission asset WO # X43258BA
Transgrid Outage Outage requested by TRANSGRD TRANSGRD 3/10/08 07:06:00 3/10/08 13:14:00 MSS -DDTS 2 330KV NW
6.133 EXCLUDE 1.3 Third party outage WO # 10296630
Created: 02/02/2009 16:05 Printed: 8/05/2009 3:33 PM Inputs - Exclusions File: SP AusNet - Service standards report - last three quarters 2008 - template (10 February 2008).xls
AER Report Dec-08 SP AusNet Performance Page 11 of 30
Perf calc W/O No4 trans during No4 66 Bus outage
X508 - (GTS) STATION REDEVELOPMENT
SPICAPX 4/10/08 06:01:00 4/10/08 14:47:00 B4 220/66KV TRANS AT GTS
8.767 EXCLUDE 1.2 Connection asset WO # X50858G2
EPS-MBTS No 2 220kv Line Gun shot repair
FORCMAJ 6/10/08 04:11:00 6/10/08 16:54:00 MBTS-EPS 2 220KV N
12.717 EXCLUDE 1.4 Force majeure WO # 10296796
Replace Surge Divertors
X7F8 - REPLACE AGEING 66KV - 330KV SURGE RESISTRS
SPICAPX 6/10/08 07:00:00 7/10/08 15:28:00 B1 220/66KV TRANS AT HTS
32.467 EXCLUDE 1.2 Connection asset WO # X7F858A0
Replace Surge Divertors
X7F8 - REPLACE AGEING 66KV - 330KV SURGE RESISTRS
SPICAPX 8/10/08 07:04:00 9/10/08 14:29:00 B2 220/66KV TRANS AT HTS
31.417 EXCLUDE 1.2 Connection asset WO # X7F858A1
Transgrid OPGW work Outage requested by TRANSGRD TRANSGRD 9/10/08 05:40:00 9/10/08 18:13:00 JDSS-WOTS 330KV NW
12.550 EXCLUDE 1.3 Third party outage WO # 10296605
Transgrid OPGW work Outage requested by TRANSGRD TRANSGRD 10/10/08 05:55:00 10/10/08 18:56:00 JDSS-WOTS 330KV NW
13.017 EXCLUDE 1.3 Third party outage WO # 10296605
Out W/O No4 Transformer for rebuild works
X508 - (GTS) STATION REDEVELOPMENT
SPICAPX 10/10/08 06:03:00 11/10/08 06:09:00 B4 220/66KV TRANS AT GTS
24.100 EXCLUDE 1.2 Connection asset WO # X50858F2
Transgrid OPGW work Outage requested by TRANSGRD TRANSGRD 11/10/08 05:45:00 11/10/08 18:19:00 JDSS-WOTS 330KV NW
12.567 EXCLUDE 1.3 Third party outage WO # 10296605
Perf calc W/O No4 Trans during No2 220 Bus outage
X508 - (GTS) STATION REDEVELOPMENT
SPICAPX 11/10/08 06:09:00 11/10/08 19:01:00 B4 220/66KV TRANS AT GTS
12.867 EXCLUDE 1.2 Connection asset WO # X50858F7
Out W/O No4 Transformer unavailable O'night
X508 - (GTS) STATION REDEVELOPMENT
SPICAPX 11/10/08 19:01:00 12/10/08 06:00:00 B4 220/66KV TRANS AT GTS
10.983 EXCLUDE 1.2 Connection asset WO # X50858F8
Out W/O No4 Transformer for rebuild works
X508 - (GTS) STATION REDEVELOPMENT
SPICAPX 12/10/08 06:00:00 13/10/08 20:58:00 B4 220/66KV TRANS AT GTS
38.967 EXCLUDE 1.2 Connection asset WO # X50858F9
Trans Rebate for Bus outage
SPIMAINT 12/10/08 07:19:00 12/10/08 10:00:00 B2 220/66KV TRANS AT RTS
2.683 EXCLUDE 1.2 Connection asset WO # 10286623
Transgrid OPGW work Outage requested by TRANSGRD TRANSGRD 13/10/08 05:44:00 13/10/08 15:56:00 JDSS-WOTS 330KV NW
10.200 EXCLUDE 1.3 Third party outage WO # 10296605
Transgrid OPGW work Outage requested by TRANSGRD TRANSGRD 14/10/08 05:50:00 14/10/08 19:06:00 JDSS-WOTS 330KV NW
13.267 EXCLUDE 1.3 Third party outage WO # 10296605
Clean Bird Droppings X320 - (MTS) STATION REDEVELOPMENT
SPIMAINT 14/10/08 06:43:00 14/10/08 09:24:00 B3 220/66KV TRANS AT MTS
2.683 EXCLUDE 1.2 Connection asset WO # X32058AO
O/HAUL Transformer and Div Sw (W)
SPIMAINT 14/10/08 07:03:00 14/10/08 18:48:00 B1 220/66KV TRANS AT KTS
11.750 EXCLUDE 1.2 Connection asset WO # 10291826
Transgrid OPGW work Outage requested by TRANSGRD TRANSGRD 15/10/08 05:35:00 15/10/08 18:18:00 JDSS-WOTS 330KV NW
12.717 EXCLUDE 1.3 Third party outage WO # 10296605
INSTALL NEW COOLING FAN
SPIMAINT 15/10/08 07:04:00 15/10/08 15:18:00 B4 220/66KV TRANS AT RTS
8.233 EXCLUDE 1.2 Connection asset WO # 10296485
O/HAUL Transformer and Div Sw (W)
SPIMAINT 15/10/08 07:08:00 15/10/08 15:30:00 B2 220/66KV TRANS AT KTS
8.367 EXCLUDE 1.2 Connection asset WO # 10291829
Transgrid OPGW work Outage requested by TRANSGRD TRANSGRD 16/10/08 05:30:00 16/10/08 19:12:00 JDSS-WOTS 330KV NW
13.700 EXCLUDE 1.3 Third party outage WO # 10296605
Rebate W/O DDTS-SMTS No2 Line during ROI & Esw OH
SPIMAINT 16/10/08 07:04:00 16/10/08 16:10:00 9.100 EXCLUDE 1.1 Unregulated transmission asset WO # 10297735
Transgrid OPGW work Outage requested by TRANSGRD TRANSGRD 17/10/08 05:32:00 17/10/08 18:13:00 JDSS-WOTS 330KV NW
12.683 EXCLUDE 1.3 Third party outage WO # 10296605
Transgrid OPGW work Outage requested by TRANSGRD TRANSGRD 18/10/08 05:34:00 18/10/08 16:26:00 JDSS-WOTS 330KV NW
10.867 EXCLUDE 1.3 Third party outage WO # 10296605
Rebate W/O No3 TR during No1 220kV Bus outage
X508 - (GTS) STATION REDEVELOPMENT
SPICAPX 19/10/08 05:30:00 19/10/08 18:55:00 B3 220/66KV TRANS AT GTS
13.417 EXCLUDE 1.2 Connection asset WO # X50858H9
Transgrid OPGW work Outage requested by TRANSGRD TRANSGRD 19/10/08 05:32:00 19/10/08 20:40:00 JDSS-WOTS 330KV NW
15.133 EXCLUDE 1.3 Third party outage WO # 10296605
Transgrid OPGW work Outage requested by TRANSGRD TRANSGRD 20/10/08 05:34:00 20/10/08 18:59:00 JDSS-WOTS 330KV NW
13.417 EXCLUDE 1.3 Third party outage WO # 10296605
Outage request from Pt Henry
Outage requested by APDALCOA APDALCOA 20/10/08 08:38:00 21/10/08 16:31:00 GTS -PTH 2 220KV WY
31.883 EXCLUDE 1.3 Third party outage WO # 10297280
Repair OLTC FORCED 20/10/08 13:03:00 20/10/08 14:34:00 B1 220/66KV TRANS AT KTS
1.517 EXCLUDE 1.2 Connection asset WO # 10297294
Transgrid OPGW work Outage requested by TRANSGRD TRANSGRD 21/10/08 05:39:00 21/10/08 18:32:00 JDSS-WOTS 330KV NW
12.883 EXCLUDE 1.3 Third party outage WO # 10296605
Transgrid OPGW work Outage requested by TRANSGRD TRANSGRD 22/10/08 05:32:00 22/10/08 16:39:00 JDSS-WOTS 330KV NW
11.117 EXCLUDE 1.3 Third party outage WO # 10296605
Replace Surge Divertors
X7F8 - REPLACE AGEING 66KV - 330KV SURGE RESISTRS
SPICAPX 22/10/08 07:03:00 23/10/08 14:16:00 B3 220/66KV TRANS AT SVTS
31.217 EXCLUDE 1.2 Connection asset WO # X7F858A3
Created: 02/02/2009 16:05 Printed: 8/05/2009 3:33 PM Inputs - Exclusions File: SP AusNet - Service standards report - last three quarters 2008 - template (10 February 2008).xls
AER Report Dec-08 SP AusNet Performance Page 12 of 30
Transgrid OPGW work Outage requested by TRANSGRD TRANSGRD 23/10/08 05:40:00 23/10/08 18:04:00 JDSS-WOTS 330KV NW
12.400 EXCLUDE 1.3 Third party outage WO # 10296605
Transgrid OPGW work Outage requested by TRANSGRD TRANSGRD 24/10/08 05:38:00 24/10/08 17:21:00 JDSS-WOTS 330KV NW
11.717 EXCLUDE 1.3 Third party outage WO # 10296605
Install weather shields X320 - (MTS) STATION REDEVELOPMENT
SPIMAINT 24/10/08 06:47:00 24/10/08 07:30:00 U1 66/22KV TRANS AT MTS
0.717 EXCLUDE 1.2 Connection asset WO # X32058AS
Transgrid OPGW work Outage requested by TRANSGRD TRANSGRD 25/10/08 05:40:00 25/10/08 15:15:00 JDSS-WOTS 330KV NW
9.583 EXCLUDE 1.3 Third party outage WO # 10296605
Rebate for Bus outage X741 - (TYREE,GEC FMJL,ASEA IMBA) CT REPLACEMENT
SPICAPX 25/10/08 07:13:00 25/10/08 18:41:00 B3 220/66KV TRANS AT SVTS
11.467 EXCLUDE 1.2 Connection asset WO # 10297278
O/HAUL Transformer and Div Sw (N)
SPIMAINT 25/10/08 07:48:00 25/10/08 17:19:00 B1 220/66KV TRANS AT GTS
9.517 EXCLUDE 1.2 Connection asset WO # 10270150
O/HAUL Transformer and Div Sw (N)
SPIMAINT 26/10/08 07:01:00 26/10/08 15:26:00 B1 220/66KV TRANS AT GTS
8.417 EXCLUDE 1.2 Connection asset WO # 10270150
Transgrid OPGW work Outage requested by TRANSGRD TRANSGRD 28/10/08 05:30:00 28/10/08 17:30:00 JDSS-WOTS 330KV NW
12.000 EXCLUDE 1.3 Third party outage WO # 10296605
MODIFY TRANS SD EARTHING
SPIMAINT 28/10/08 07:12:00 28/10/08 15:49:00 B1 220/66KV TRANS AT SVTS
8.617 EXCLUDE 1.2 Connection asset WO # 10297331
Transgrid OPGW work Outage requested by TRANSGRD TRANSGRD 29/10/08 05:34:00 29/10/08 16:04:00 JDSS-WOTS 330KV NW
10.500 EXCLUDE 1.3 Third party outage WO # 10296605
Transgrid OPGW work Outage requested by TRANSGRD TRANSGRD 30/10/08 05:34:00 30/10/08 15:25:00 JDSS-WOTS 330KV NW
9.850 EXCLUDE 1.3 Third party outage WO # 10296605
O/HAUL Transformer Div Mechanism (N)
SPIMAINT 30/10/08 08:02:00 30/10/08 18:03:00 B1 220/66KV TRANS AT TGTS
10.017 EXCLUDE 1.2 Connection asset WO # 10274177
Switching for APD to top up SF6 CB at APD
Outage requested by APDALCOA APDALCOA 30/10/08 09:34:00 30/10/08 11:51:00 APD NO.2 500KV LINE AT HYTS
2.283 EXCLUDE 1.3 Third party outage WO # 10297612
HOTS-RCTS 220kV Line Hattah Busfire Outage
BUSHFIRE 30/10/08 18:21:00 31/10/08 10:06:00 HOTS-RCTS 220KV
15.750 EXCLUDE 1.4 Force majeure WO # 10297647
Transgrid OPGW work Outage requested by TRANSGRD TRANSGRD 1/11/08 05:31:00 1/11/08 19:59:00 JDSS-WOTS 330KV NW
14.467 EXCLUDE 1.3 Third party outage WO # 10296605
Replace No1 Tr 66kv neutral isolator
SPIMAINT 1/11/08 06:57:00 1/11/08 11:32:00 B1 220/66KV TRANS AT GTS
4.583 EXCLUDE 1.2 Connection asset WO # 10297515
Transgrid OPGW work Outage requested by TRANSGRD TRANSGRD 3/11/08 05:35:00 3/11/08 18:02:00 JDSS-WOTS 330KV NW
12.450 EXCLUDE 1.3 Third party outage WO # 10296605
Delta E/F Alarm FORCED 3/11/08 06:46:00 3/11/08 08:09:00 L3 220/22KV TRANS BANK AT RWTS
1.383 EXCLUDE 1.2 Connection asset WO # 10297697
Transgrid OPGW work Outage requested by TRANSGRD TRANSGRD 4/11/08 05:35:00 4/11/08 13:17:00 JDSS-WOTS 330KV NW
7.700 EXCLUDE 1.3 Third party outage WO # 10296605
Perf calc W/O No1A Trans during 22kV CB outage
SPIMAINT 4/11/08 07:26:00 4/11/08 17:29:00 NO.1A TRANS AT RCTS
10.050 EXCLUDE 1.2 Connection asset WO # 10297312
Perf calc W/O No2 Tr grp
SPIMAINT 6/11/08 09:33:00 6/11/08 19:34:00 R2 220/66/22KV TRANS GROUP AT RCTS
10.017 EXCLUDE 1.2 Connection asset WO # 10297316
Install weather shields X320 - (MTS) STATION REDEVELOPMENT
SPIMAINT 7/11/08 06:51:00 7/11/08 10:04:00 U1 66/22KV TRANS AT MTS
3.217 EXCLUDE 1.2 Connection asset WO # X32058AW
Install weather shields X320 - (MTS) STATION REDEVELOPMENT
SPIMAINT 7/11/08 10:05:00 7/11/08 12:13:00 U2 66/22KV TRANS AT MTS
2.133 EXCLUDE 1.2 Connection asset WO # X32058AT
Future B1 Trans at SMTS
VEN_AUG 7/11/08 14:55:00 30/11/08 23:59:59 FUTURE B1 220/66KV TRANS AT SMTS
561.083 EXCLUDE 1.2 Connection asset WO # 10300287
Rebate W/O No3 TR during No1 220kV Bus outage
X508 - (GTS) STATION REDEVELOPMENT
SPICAPX 8/11/08 06:00:00 8/11/08 17:52:00 B3 220/66KV TRANS AT GTS
11.867 EXCLUDE 1.2 Connection asset WO # X50858I5
Installation of access hatch
V8C4 - (CBTS) RECTIFY CONSTRUCTION DEFECTS
SPIMAINT 8/11/08 06:57:00 8/11/08 16:04:00 B1 220/66KV TRANS AT CBTS
9.117 EXCLUDE 1.2 Connection asset WO # V8C458A0
Perf calc W/O No1 trans during No2 66 Bus outage
X508 - (GTS) STATION REDEVELOPMENT
SPICAPX 9/11/08 06:00:00 9/11/08 14:41:00 B1 220/66KV TRANS AT GTS
8.683 EXCLUDE 1.2 Connection asset WO # X50858J5
O/HAUL Transformer and Trafo Union Div Sw (W)
SPIMAINT 11/11/08 06:38:00 11/11/08 15:44:00 B3 220/66KV TRANS AT FBTS
9.100 EXCLUDE 1.2 Connection asset WO # 10291416
Created: 02/02/2009 16:05 Printed: 8/05/2009 3:33 PM Inputs - Exclusions File: SP AusNet - Service standards report - last three quarters 2008 - template (10 February 2008).xls
AER Report Dec-08 SP AusNet Performance Page 13 of 30
O/HAUL Transformer and Trafo Union Div Sw (W)
SPIMAINT 12/11/08 06:54:00 12/11/08 17:00:00 B3 220/66KV TRANS AT FBTS
10.100 EXCLUDE 1.2 Connection asset WO # 10291416
Clean Bird Droppings X320 - (MTS) STATION REDEVELOPMENT
SPIMAINT 12/11/08 08:16:00 12/11/08 16:15:00 B3 220/66KV TRANS AT MTS
7.983 EXCLUDE 1.2 Connection asset WO # X32058AU
O/Haul B1 TRANS AT FBTS
SPIMAINT 13/11/08 06:22:00 13/11/08 16:15:00 B1 220/66KV TRANS AT FBTS
9.883 EXCLUDE 1.2 Connection asset WO # 10291414
NO2 Trans OLTC Mech tight during operation
SPIMAINT 13/11/08 14:19:00 13/11/08 18:01:00 R2 220/66/22KV TRANS AT KGTS
3.700 EXCLUDE 1.2 Connection asset WO # 10297912
Perf calc W/O B4 trans during No4 66 Bus outage
X508 - (GTS) STATION REDEVELOPMENT
SPICAPX 15/11/08 06:40:00 15/11/08 15:00:00 B4 220/66KV TRANS AT GTS
8.333 EXCLUDE 1.2 Connection asset WO # X50858K1
Out W/O B4 trans VT ratio change
X508 - (GTS) STATION REDEVELOPMENT
SPICAPX 15/11/08 15:00:00 15/11/08 17:18:00 B4 220/66KV TRANS AT GTS
2.300 EXCLUDE 1.2 Connection asset WO # X50858K6
Perf calc W/O B4 trans during No4 66 Bus outage
X508 - (GTS) STATION REDEVELOPMENT
SPICAPX 22/11/08 06:00:00 22/11/08 18:15:00 B4 220/66KV TRANS AT GTS
12.250 EXCLUDE 1.2 Connection asset WO # X50858K5
Treatment and Regeneration of Appro 60,000
V881 - COST EST - (RTS) B1 TRANSFORMER OIL REGENERATION
SPIMAINT 22/11/08 07:11:00 23/11/08 12:00:00 B1 220/66KV TRANS AT RTS
28.817 EXCLUDE 1.2 Connection asset WO # V88158A0
B4 Trans tripped on thru fault
FAULT 23/11/08 03:05:00 23/11/08 05:14:00 B4 220/66KV TRANS AT GTS
2.150 EXCLUDE 1.2 Connection asset WO # 10298577
Investigate No2 Transformer Out of Step
SPIMAINT 27/11/08 07:54:00 27/11/08 15:15:00 R2 220/66/22KV TRANS AT KGTS
7.350 EXCLUDE 1.2 Connection asset WO # 10298413
B1 Trans SPIMAINT 27/11/08 10:31:00 27/11/08 10:50:00 B1 220/66KV TRANS AT KTS
0.317 EXCLUDE 1.2 Connection asset WO # 10298425
Installation of access hatch
V8C4 - (CBTS) RECTIFY CONSTRUCTION DEFECTS
SPIMAINT 29/11/08 07:10:00 29/11/08 16:12:00 B2 220/66KV TRANS AT CBTS
9.033 EXCLUDE 1.2 Connection asset WO # V8C458A1
Perf calc W/O B2 Trans during #1 66 bus outage
SPIMAINT 30/11/08 18:22:00 30/11/08 18:41:00 B2 220/66KV TRANS AT HOTS
0.317 EXCLUDE 1.2 Connection asset WO # 10298148
Future B1 Trans at SMTS
VEN_AUG 1/12/08 00:00:00 31/12/08 23:59:59 FUTURE B1 220/66KV TRANS AT SMTS
744.000 EXCLUDE 1.2 Connection asset WO # 10300287
replace faulty transformer mechanism
SPIMAINT 1/12/08 07:03:00 2/12/08 14:38:00 B3 220/66KV TRANS AT WMTS
31.583 EXCLUDE 1.2 Connection asset WO # 10298353
Works for Power Station
Outage requested by GENCO GENCO 1/12/08 20:46:00 1/12/08 21:41:00 BLTS 220KV LINE AT NPSD
0.917 EXCLUDE 1.3 Third party outage WO # 10298562
Works for Power Station
Outage requested by GENCO GENCO 1/12/08 21:55:00 1/12/08 22:13:00 FBTS 220KV LINE AT NPSD
0.300 EXCLUDE 1.3 Third party outage WO # 10298563
KGTS No2 Trans OLTC Fault
FORCED 3/12/08 00:12:00 3/12/08 01:04:00 R2 220/66/22KV TRANS AT KGTS
0.867 EXCLUDE 1.2 Connection asset WO # 10298609
Out W/O A2 Trans to connect new 1B CB Cts
X565 - REPLACE 220KV TYREE CTS
SPICAPX 3/12/08 06:37:00 3/12/08 10:53:00 A2 500/220KV TRANS BANK AT MLTS
4.267 EXCLUDE 1.1 Unregulated transmission asset WO # X56558G4
APD Work Outage requested by APDALCOA APDALCOA 3/12/08 08:02:00 3/12/08 08:30:00 HYTS-APD 2 500KV W
0.467 EXCLUDE 1.3 Third party outage WO # 10298431
Repair oil leaks SPIMAINT 4/12/08 06:55:00 4/12/08 14:56:00 L3 220/22KV TRANS BANK AT RWTS
8.017 EXCLUDE 1.2 Connection asset WO # 10298311
top up 2 off 220kv trans bushings
SPIMAINT 4/12/08 07:12:00 4/12/08 14:53:00 B1 220/66KV TRANS AT WMTS
7.683 EXCLUDE 1.2 Connection asset WO # 10298631
APD Work Outage requested by APDALCOA APDALCOA 4/12/08 08:01:00 4/12/08 11:44:00 HYTS-APD 1 500KV W
3.717 EXCLUDE 1.3 Third party outage WO # 10298434
Investigate No2 Transformer Out of Step
SPIMAINT 4/12/08 08:28:00 4/12/08 13:45:00 R2 220/66/22KV TRANS AT KGTS
5.283 EXCLUDE 1.2 Connection asset WO # 10298542
Power Station requirements
Outage requested by GENCO GENCO 5/12/08 23:36:00 8/12/08 00:32:00 NO.6 GEN TRANS 220/16.5KV(CHECK PCB REGISTER) AT HWPS
48.933 EXCLUDE 1.3 Third party outage WO # 10298672
Created: 02/02/2009 16:05 Printed: 8/05/2009 3:33 PM Inputs - Exclusions File: SP AusNet - Service standards report - last three quarters 2008 - template (10 February 2008).xls
AER Report Dec-08 SP AusNet Performance Page 14 of 30
P/Station requirements - W1 Gen to 220 kV System
Outage requested by GENCO GENCO 6/12/08 04:08:00 6/12/08 04:17:00 W1A 230/20KV GEN TRANS (CHECK PCB REGISTER) AT YWPS
0.150 EXCLUDE 1.3 Third party outage WO # 10298676
Perf calc W/O No2 Trans during its 66kv CB outage
SPIMAINT 9/12/08 12:43:00 9/12/08 15:27:00 B2 220/66KV TRANS AT SHTS
2.733 EXCLUDE 1.2 Connection asset WO # 10298339
Perf calc W/O B2 Trans during #1 66 bus outage
SPIMAINT 10/12/08 21:14:00 10/12/08 21:24:00 B2 220/66KV TRANS AT HOTS
0.167 EXCLUDE 1.2 Connection asset WO # 10298320
Transformer Div. Switch Overhaul
SPIMAINT 11/12/08 07:01:00 11/12/08 14:27:00 B2 220/66KV TRANS AT HTS
7.433 EXCLUDE 1.2 Connection asset WO # 10290912
Rebate W/O 3A Cap bk during CB outage
SPIMAINT 14/12/08 06:36:00 14/12/08 18:00:00 NO.3A 66KV CAPACITOR BANK AT BETS
11.400 EXCLUDE 1.1 Unregulated transmission asset WO # 10298596
No2 Transf fault on 22kV Cable
FAULT 14/12/08 12:34:00 14/12/08 20:40:00 NO.2 330/66/22KV TRANS AT WOTS
8.100 EXCLUDE 1.2 Connection asset WO # 10298841
Perf calc W/O No2 Trans during #3 66 bus outage
SPIMAINT 14/12/08 18:36:00 14/12/08 18:57:00 R2A/2B 220/66/22KV TRANS GROUP AT BETS
0.350 EXCLUDE 1.2 Connection asset WO # 10298591
invest / repair faulty trans mechanism
SPIMAINT 15/12/08 07:31:00 16/12/08 15:04:00 B3 220/66KV TRANS AT WMTS
31.550 EXCLUDE 1.2 Connection asset WO # 10298760
APD Work Outage requested by APDALCOA APDALCOA 16/12/08 14:50:00 16/12/08 18:08:00 HYTS-APD 2 500KV W
3.300 EXCLUDE 1.3 Third party outage WO # 10298847
APD Work Outage requested by APDALCOA APDALCOA 17/12/08 07:46:00 17/12/08 16:23:00 HYTS-APD 2 500KV W
8.617 EXCLUDE 1.3 Third party outage WO # 10298847
Electranet Outage Outage requested by ELECTRAN ELECTRAN 17/12/08 08:45:00 17/12/08 16:20:00 HYTS-SESS 2 275KV WH
7.583 EXCLUDE 1.3 Third party outage WO # 10297872
HYTS-APD No2 Line De-Energised for APD
Outage requested by APDALCOA APDALCOA 18/12/08 11:01:00 18/12/08 15:53:00 HYTS-APD 2 500KV W
4.867 EXCLUDE 1.3 Third party outage WO # 10299057
Out W/O for reconnection of No2 Trans 22kV Cable
SPIMAINT 21/12/08 10:43:00 21/12/08 17:27:00 NO.2 330/66/22KV TRANS AT WOTS
6.733 EXCLUDE 1.2 Connection asset WO # 10299041
Replace Pump SPIMAINT 22/12/08 06:59:00 22/12/08 17:12:00 B4 220/66KV TRANS AT SVTS
10.217 EXCLUDE 1.2 Connection asset WO # 10298992
Repair oil leaks SPIMAINT 22/12/08 07:07:00 22/12/08 14:31:00 L3 220/22KV TRANS BANK AT RWTS
7.400 EXCLUDE 1.2 Connection asset WO # 10298311
APD work Outage requested by APDALCOA APDALCOA 22/12/08 07:45:00 22/12/08 15:17:00 HYTS-APD 2 500KV W
7.533 EXCLUDE 1.3 Third party outage WO # 10299134
APD work Outage requested by APDALCOA APDALCOA 23/12/08 08:00:00 23/12/08 11:02:00 HYTS-APD 1 500KV W
3.033 EXCLUDE 1.3 Third party outage WO # 10299222
Works for Power Station
Outage requested by GENCO GENCO 1/12/08 20:46:00 1/12/08 21:41:00 BLTS 220KV LINE AT NPSD
0.917 EXCLUDE 2.3 Third party outage WO # 10298562
Works for Power Station
Outage requested by GENCO GENCO 1/12/08 21:55:00 1/12/08 22:13:00 FBTS 220KV LINE AT NPSD
0.083 EXCLUDE 2.3 Third party outage WO # 10298563
APD Work Outage requested by APDALCOA APDALCOA 4/12/08 08:01:00 4/12/08 11:44:00 HYTS-APD 1 500KV W
0.733 EXCLUDE 2.3 Third party outage WO # 10298434
APD Work Outage requested by APDALCOA APDALCOA 16/12/08 14:50:00 16/12/08 18:08:00 HYTS-APD 2 500KV W
3.300 EXCLUDE 2.3 Third party outage WO # 10298847
APD Work Outage requested by APDALCOA APDALCOA 17/12/08 07:46:00 17/12/08 16:23:00 HYTS-APD 2 500KV W
5.383 EXCLUDE 2.3 Third party outage WO # 10298847
Electranet Outage Outage requested by ELECTRAN ELECTRAN 17/12/08 08:45:00 17/12/08 16:20:00 HYTS-SESS 2 275KV WH
5.333 EXCLUDE 2.3 Third party outage WO # 10297872
HYTS-APD No2 Line De-Energised for APD
Outage requested by APDALCOA APDALCOA 18/12/08 11:01:00 18/12/08 15:53:00 HYTS-APD 2 500KV W
4.867 EXCLUDE 2.3 Third party outage WO # 10299057
APD work Outage requested by APDALCOA APDALCOA 22/12/08 07:45:00 22/12/08 15:17:00 HYTS-APD 2 500KV W
4.283 EXCLUDE 2.3 Third party outage WO # 10299134
APD work Outage requested by APDALCOA APDALCOA 23/12/08 08:00:00 23/12/08 11:02:00 HYTS-APD 1 500KV W
0.033 EXCLUDE 2.3 Third party outage WO # 10299222
S2 Peak critical availability
Created: 02/02/2009 16:05 Printed: 8/05/2009 3:33 PM Inputs - Exclusions File: SP AusNet - Service standards report - last three quarters 2008 - template (10 February 2008).xls
AER Report Dec-08 SP AusNet Performance Page 15 of 30
Excavate adjacent to No1 66kv Reactor
X724 - (HOTS) NO.1 SHUNT REACTOR REPLACEMENT
SPICAPX 19/11/08 15:08:00 19/11/08 16:12:00 NO.1 66KV REACTOR AT HOTS
1.067 EXCLUDE 3.7 Shunt reactor WO # X72458A2
Out W/O 220kV Shunt Reactor to replace its CTs
X565 - REPLACE 220KV TYREE CTS
SPICAPX 4/12/08 07:02:00 5/12/08 12:50:00 220KV SHUNT REACTOR AT MLTS
12.833 EXCLUDE 3.7 Shunt reactor WO # X56558G5
O/Haul - 66kV reactor SPIMAINT 10/12/08 07:27:00 10/12/08 15:14:00 NO.3 66KV REACTOR AT RCTS
4.233 EXCLUDE 3.7 Shunt reactor WO # 10272601
Repair No2 66kv Reactor oil leaks
SPIMAINT 11/12/08 07:23:00 11/12/08 16:04:00 NO.2 66KV REACTOR AT RCTS
5.067 EXCLUDE 3.7 Shunt reactor WO # 10284435
Work at APD No2 Reactor Gas Relay
Outage requested by APDALCOA APDALCOA 25/06/08 07:37:00 25/06/08 17:17:00 APD NO.2 500KV LINE AT HYTS
9.667 EXCLUDE 4.3 Third party outage WO # 10284594
APD work Outage requested by APDALCOA APDALCOA 30/06/08 13:07:00 30/06/08 17:01:00 HYTS-APD 2 500KV W
3.900 EXCLUDE 4.3 Third party outage WO # 10284672
PTH Work Outage requested by APDALCOA APDALCOA 7/07/08 08:00:00 7/07/08 15:13:00 GTS -PTH 2 220KV WY
7.217 EXCLUDE 4.3 Third party outage WO # 10284989
Scap to PTH Outage requested by APDALCOA APDALCOA 29/07/08 07:22:00 29/07/08 14:33:00 GTS -PTH 1 220KV WY
7.183 EXCLUDE 4.3 Third party outage WO # 10285168
Scap to PTH Outage requested by APDALCOA APDALCOA 30/07/08 07:18:00 30/07/08 15:10:00 GTS -PTH 2 220KV WY
7.867 EXCLUDE 4.3 Third party outage WO # 10285171
Scap to PTH Outage requested by APDALCOA APDALCOA 31/07/08 07:28:00 31/07/08 14:55:00 GTS -PTH 1 220KV WY
7.450 EXCLUDE 4.3 Third party outage WO # 10285170
Scap to PTH Outage requested by APDALCOA APDALCOA 1/08/08 07:15:00 1/08/08 13:34:00 GTS -PTH 2 220KV WY
6.317 EXCLUDE 4.3 Third party outage WO # 10285172
APD Work Outage requested by APDALCOA APDALCOA 6/08/08 07:05:00 6/08/08 17:40:00 HYTS-APD 2 500KV W
10.583 EXCLUDE 4.3 Third party outage WO # 10285412
APD Work Outage requested by APDALCOA APDALCOA 7/08/08 07:18:00 7/08/08 18:45:00 HYTS-APD 2 500KV W
11.450 EXCLUDE 4.3 Third party outage WO # 10285412
APD Work Outage requested by APDALCOA APDALCOA 26/08/08 07:46:00 26/08/08 16:29:00 HYTS-APD 1 500KV W
8.717 EXCLUDE 4.3 Third party outage WO # 10286343
APD Work Outage requested by APDALCOA APDALCOA 27/08/08 07:30:00 27/08/08 09:23:00 HYTS-APD 2 500KV W
1.883 EXCLUDE 4.3 Third party outage WO # 10286344
O/Haul - 66kV reactor SPIMAINT 1/07/08 08:01:00 1/07/08 15:18:00 NO.2 66KV REACTOR AT HOTS
7.283 EXCLUDE 5.7 Shunt reactor WO # 10272603
Event proposed for exclusion
Description of the event and its impact on the network and
performanceCause of the event Start
dateStart time
End date
End time Circuits affected Maximum system
demandQuantitative
impactDemand shed
and time Reasons for exclusion request Further references
Name of the eventDetail of the event. Such as: the action of any third parties, the actions of the TNSP,assets damaged or interrupted.
A description of the cause of the event
Name of circuits or plant affected
The max system demand that occurred up until the time of the event
Number of hours, mins etc interrupted
The (MW) demand shed and the duration it was shed for.
Full details of the reason/s for excluding this event. Should include a reference to the defined exclusions and explain how it meets this exclusion definition (seExclusion definition tab). Eg. Exclusion 1.2 Third party event
A TNSP may provide further details of an exclusion event. TNSP to provide reference.
Event proposed for exclusion
Description of the event and its impact on the network and
performanceCause of the event Start
dateStart time
End date
End time
Quantitative impact
Capped impact (if applicable) Reasons for exclusion request Further references
Name of the eventDetail of the event. Such as: the action of any third parties, the actions of the TNSP,assets damaged or interrupted.
A description of the cause of the event
Number of hours, mins etc interrupted
Impact following any applicable cap
Full details of the reason for excluding this event. Should include a reference to the defined exclusions and explain how it meets this exclusion definition (seExclusion definition tab). Eg. Exclusion 1.2 Third party event
A TNSP may provide further details of an exclusion event. TNSP to provide reference.
HOTS-RCTS 220kV Line Hattah Busfire Outage
BUSHFIRE 30/10/08 18:21:00 31/10/08 10:06:00 HOTS-RCTS 220KV
15.750 EXCLUDE 6.4 Force majeure WO # 10297647, SIR # 10297642
Start date and time of event
End date and time of event
S5 Intermediate non-critical availability
LOSS OF SUPPLY EVENT FREQUENCY
Name of any loss of supply parameters applying to Powerlink
S3
S7Loss of supply event
frequency (No. of events > 0.3 system
AVERAGE OUTAGE DURATION
S6Loss of supply event
frequency (No. of events > 0.05 system
Peak non-critical availability
S4 Intermediate critical availability
Circuits affected
Name of any average outage duration parameters applying to SP AusNet
Name of circuits or plant affected
S8 Average outage duration (lines)
Start date and time of event
End date and time of event
Created: 02/02/2009 16:05 Printed: 8/05/2009 3:33 PM Inputs - Exclusions File: SP AusNet - Service standards report - last three quarters 2008 - template (10 February 2008).xls
AER Report Dec-08 SP AusNet Performance Page 16 of 30
NOTES:
This worksheet should include a list all events that are proposed for exclusion.
Each proposed exclusion should include a description of the event, a description of the impact and quantification of the impact on the network and performance. The descriptive elements should also include reasons for the exclusion request making reference to the "Exclusion Definitions" worksheet.
Each exclusion should be entered onto one row for each parameter. Where one exclusion event applies to more than one parameter, the relevant details of the event should be entered under each of the measure headings.
The TNSP must provide details for all events requested for exclusion in this template. In the event that the TNSP wishes to provide further details of an exclusion, this should be provided with the TNSP's performance report. The source of information should be referenced in this template.
Green cells - input description impact
Orange cells - input reasons for the exclusion request
S9Average outage
duration (transformers)
Created: 02/02/2009 16:05 Printed: 8/05/2009 3:33 PM Inputs - Exclusions File: SP AusNet - Service standards report - last three quarters 2008 - template (10 February 2008).xls
SP AUSNET- S1 - Total circuit availability
Performance Targets Graph start Collar Target Cap Graph endTotal circuit availability 98.10% 98.41% 98.73% 99.05% 99.30%
Weighting -0.20% -0.20% 0.00% 0.20% 0.20%
Performance Formulae Conditions S- Calc 1 S- Calc 2Performance = -0.002000 Availability < 98.41% -0.002000 -0.002000
= 0.625000 x Availability + -0.617063 98.41% ≤ Availability ≤ 98.73% 0.002177 0.002421
= 0.625000 x Availability + -0.617062 98.73% ≤ Availability ≤ 99.05% 0.002177 0.002421
= 0.002000 99.05% < Availability 0.002000 0.002000
Performance OutcomesPerformance
(Without Exclusions)
Performance (Exclusions)
Total circuit availability = 99.078398% 99.117382%
S-Factor = 0.200000% 0.200000%
Formulae
SP AUSNET SERVICE STANDARDSS1 - Total circuit availability
-0.25%
-0.20%
-0.15%
-0.10%
-0.05%
0.00%
0.05%
0.10%
0.15%
0.20%
0.25%
98.10% 98.40% 98.70% 99.00% 99.30%
Total circuit availabilityFi
nanc
ial I
ncen
tive
(Per
cent
age
of A
nnua
l Rev
enue
)
Service standardsincentive curve
Performance (Without Exclusions)
Performance (Exclusions)
NOTE: This sheet will automatically update based on data in input sheets
Blue cells show SP AusNet's performance targets and weightings
Yellow/Green cells show SP AusNet's performance formulae and related formula conditions based on performance targets and weightings
Pink cells show SP AusNet's performance outcomes without any events excluded from performance data
Orange cells show SP AusNet's performance outcomes with events excluded from performancedata
SP AusNet - Service standards report - last three quarters 2008 - template (10 February 2008).xls S1
SP AUSNET - S2 - Peak critical availability
Performance Targets Graph start Collar Target Cap Graph endPeak critical availability 98.50% 98.62% 99.39% 99.78% 100.00%
Weighting -0.20% -0.20% 0.00% 0.20% 0.20%
Performance Formulae Conditions S- Calc 1 S- Calc 2Performance = -0.002000 When: Availability < 98.62% -0.002000 -0.002000
= 0.259740 x Availability + -0.258156 98.62% ≤ Availability ≤ 99.39% 0.000923 0.001073
= 0.512821 x Availability + -0.509692 99.39% ≤ Availability ≤ 99.78% 0.001823 0.002118
= 0.002000 99.78% < Availability 0.002000 0.002000
Performance OutcomesPerformance
(Without Exclusions)
Performance (Exclusions)
Peak critical availability = 99.745438% 99.802938%
S-Factor = 0.182276% 0.200000%
Formulae
SP AUSNET SERVICE STANDARDSS2 - Peak critical availability
-0.25%
-0.20%
-0.15%
-0.10%
-0.05%
0.00%
0.05%
0.10%
0.15%
0.20%
0.25%
98.5% 98.7% 98.9% 99.1% 99.3% 99.5% 99.7% 99.9%
Peak critical availabilityFi
nanc
ial I
ncen
tive
(Per
cent
age
of A
nnua
l Rev
enue
)
Service standardsincentive curve
Performance (Without Exclusions)
Performance (Exclusions)
NOTE: This sheet will automatically update based on data in input sheets
Blue cells show SP AusNet's performance targets and weightings
Yellow/Green cells show SP AusNet's performance formulae and related formula conditions based on performance targets and weightings
Pink cells show SP AusNet's performance outcomes without any events excluded from performance data
Orange cells show SP AusNet's performance outcomes with events excluded from performancedata
SP AusNet - Service standards report - last three quarters 2008 - template (10 February 2008).xls S2
SP AUSNET S3 - Peak non-critical availability
Performance Targets Graph start Collar Target Cap Graph endPeak non-critical availability 98.70% 98.83% 99.40% 99.69% 100.00%
Weighting -0.05% -0.05% 0.00% 0.05% 0.05%
Performance Formulae Conditions S- Calc 1 S- Calc 2Performance = -0.000500 When: Availability < 98.83% -0.000500 -0.000500
= 0.087719 x Availability + -0.087193 98.83% ≤ Availability ≤ 99.40% 0.000360 0.000467
= 0.172414 x Availability + -0.171379 99.40% ≤ Availability ≤ 99.69% 0.000708 0.000918
= 0.000500 99.69% < Availability 0.000500 0.000500
Performance OutcomesPerformance
(Without Exclusions)
Performance (Exclusions)
Peak non-critical availability = 99.810606% 99.932660%
S-Factor = 0.050000% 0.050000%
Formulae
SP AUSNET SERVICE STANDARDSS3 - Peak non-critical availability
-0.075%
-0.050%
-0.025%
0.000%
0.025%
0.050%
0.075%
98.70% 98.90% 99.10% 99.30% 99.50% 99.70% 99.90%
Peak non-critical availabilityFi
nanc
ial I
ncen
tive
(Per
cent
age
of A
nnua
l Rev
enue
)
Service standardsincentive curve
Performance (Without Exclusions)
Performance (Exclusions)
NOTE: This sheet will automatically update based on data in input sheets
Blue cells show SP AusNet's performance targets and weightings
Yellow/Green cells show SP AusNet's performance formulae and related formula conditions based on performance targets and weightings
Pink cells show SP AusNet's performance outcomes without any events excluded from performance data
Orange cells show SP AusNet's performance outcomes with events excluded from performancedata
SP AusNet - Service standards report - last three quarters 2008 - template (10 February 2008).xls S3
SP AUSNET S4 - Intermediate critical availability
Performance Targets Graph start Collar Target Cap Graph endIntermediate critical availability 96.50% 97.29% 98.67% 99.36% 100.00%
Weighting -0.03% -0.0250% 0.00% 0.0250% 0.03%
Performance Formulae Conditions S- Calc 1 S- Calc 2Performance = -0.000250 When: Availability < 97.29% -0.000250 -0.000250
= 0.018116 x Availability + -0.017875 97.29% ≤ Availability ≤ 98.67% 0.000126 0.000137
= 0.036232 x Availability + -0.035750 98.67% ≤ Availability ≤ 99.36% 0.000253 0.000273
= 0.000250 99.36% < Availability 0.000250 0.000250
Performance OutcomesPerformance
(Without Exclusions)
Performance (Exclusions)
Intermediate critical availability = 99.366936% 99.424704%
S-Factor = 0.025000% 0.025000%
Formulae
SP AUSNET SERVICE STANDARDSS4 - Intermediate critical availability
-0.030%
-0.020%
-0.010%
0.000%
0.010%
0.020%
0.030%
96.50% 97.00% 97.50% 98.00% 98.50% 99.00% 99.50% 100.00%
Intermediate critical availabilityFi
nanc
ial I
ncen
tive
(Per
cent
age
of A
nnua
l Rev
enue
)
Servicestandardsincentive curve
Performance (WithoutExclusions)
Performance (Exclusions)
NOTE: This sheet will automatically update based on data in input sheets
Blue cells show SP AusNet's performance targets and weightings
Yellow/Green cells show SP AusNet's performance formulae and related formula conditions based on performance targets and weightings
Pink cells show SP AusNet's performance outcomes without any events excluded from performance data
Orange cells show SP AusNet's performance outcomes with events excluded from performancedata
SP AusNet - Service standards report - last three quarters 2008 - template (10 February 2008).xls S4
SP AUSNET S5 - Intermediate non-critical availability
Performance Targets Graph start Collar Target Cap Graph endIntermediate non-critical availability 97.00% 97.57% 98.73% 99.31% 100.00%
Weighting -0.03% -0.0250% 0.00% 0.0250% 0.03%
Performance Formulae Conditions S- Calc 1 S- Calc 2Performance = -0.000250 When: Availability < 97.57% -0.000250 -0.000250
= 0.021552 x Availability + -0.021278 97.57% ≤ Availability ≤ 98.73% 0.000170 0.000172
= 0.043103 x Availability + -0.042556 98.73% ≤ Availability ≤ 99.31% 0.000340 0.000345
= 0.000250 99.31% < Availability 0.000250 0.000250
Performance OutcomesPerformance
(Without Exclusions)
Performance (Exclusions)
Intermediate non-critical availability = 99.518644% 99.530316%
S-Factor = 0.025000% 0.025000%
Formulae
SP AUSNET SERVICE STANDARDSS5 - Intermediate non-critical availability
-0.030%
-0.020%
-0.010%
0.000%
0.010%
0.020%
0.030%
97.00% 97.50% 98.00% 98.50% 99.00% 99.50% 100.00%
Intermediate non-critical availabilityFi
nanc
ial I
ncen
tive
(per
cent
age
of A
nnua
l Rev
enue
) Servicestandardsincentive curve
Performance (WithoutExclusions)
Performance (Exclusions)
NOTE: This sheet will automatically update based on data in input sheets
Blue cells show SP AusNet's performance targets and weightings
Yellow/Green cells show SP AusNet's performance formulae and related formula conditions based on performance targets and weightings
Pink cells show SP AusNet's performance outcomes without any events excluded from performance data
Orange cells show SP AusNet's performance outcomes with events excluded from performancedata
SP AusNet - Service standards report - last three quarters 2008 - template (10 February 2008).xls S5
SP AUSNET S6 - Loss of supply event frequency (no. of events > 0.05 system minutes per annum)
Performance Targets Graph start Collar Target Cap Graph endLoss of supply (events > 0.05 system minutes) 8.00 7.00 5.00 2.00 1.00
Weighting -0.125% -0.125% 0.00% 0.125% 0.125%
Performance Formulae Conditions S- Calc 1 S- Calc 2Performance = -0.001250 7.00 < No. of events -0.001250 -0.001250
= -0.000625 x No. of events + 0.003125 5.00 ≤ No. of events ≤ 7.00 0.002500 0.002500
= -0.000417 x No. of events + 0.002083 2.00 ≤ No. of events ≤ 5.00 0.001667 0.001667
= 0.001250 No. of events < 2.00 0.001250 0.001250
Loss of supply (events > 0.05 system minutes) =
Performance (Without
Exclusions)
Performance (Exclusions)
Loss of supply (events > 0.05 system minutes) = 1 1
S-Factor 0.125000% 0.125000%
Formulae
SP AUSNET SERVICE STANDARDS S6 - Loss of supply event frequency (events > 0.05 system minutes)
-0.15%
-0.10%
-0.05%
0.00%
0.05%
0.10%
0.15%
1 2 3 4 5 6 7 8
Loss of supply event frequency (events > 0.05 system minutes)
Fina
ncia
l Inc
entiv
e(P
erce
ntag
e of
Ann
ual R
even
ue)
Service standardsincentive curve
Performance (Without Exclusions)
Performance (Exclusions)
NOTE: This sheet will automatically update based on data in input sheets
Blue cells show SP AusNet's performance targets and weightings
Yellow/Green cells show SP AusNet's performance formulae and related formula conditions based on performance targets and weightings
Pink cells show SP AusNet's performance outcomes without any events excluded from performance data
Orange cells show SP AusNet's performance outcomes with events excluded from performancedata
SP AusNet - Service standards report - last three quarters 2008 - template (10 February 2008).xls S6
SP AUSNET S7 - Loss of supply event frequency (no. of events > 0.3 system minutes per annum)
Performance Targets Graph start Collar Target Cap Graph endLoss of supply (events > 0.3 system minutes) 4.00 3.00 1.00 0.00 0.00
Weighting -0.13% -0.125% 0.00% 0.125% 0.13%
Performance Formulae Conditions S- Calc 1 S- Calc 2Performance = -0.001250 3.00 < No. of events -0.001250 -0.001250
= -0.000625 x No. of events + 0.000625 1.00 ≤ No. of events ≤ 3.00 0.000000 0.000000
= -0.001250 x No. of events + 0.001250 0.00 ≤ No. of events ≤ 1.00 0.000000 0.000000
= 0.001250 No. of events = 0.00 0.001250 0.001250
Loss of supply (events > 0.3 system minutes) =
Performance (Without
Exclusions)
Performance (Exclusions)
Loss of supply (events > 0.3 system minutes) = 1 1
S-Factor 0.000000% 0.000000%
Formulae
SP AUSNET SERVICE STANDARDS S7 - Loss of supply event frequency (events > 0.3 system minutes)
-0.15%
-0.10%
-0.05%
0.00%
0.05%
0.10%
0.15%
0.00 1.00 2.00 3.00 4.00
Loss of supply event frequency (events > 0.3 system minutes)
Fina
ncia
l Inc
entiv
e(P
erce
ntag
e of
Ann
ual R
even
ue)
Service standardsincentive curve
Performance (Without Exclusions)
Performance (Exclusions)
NOTE: This sheet will automatically update based on data in input sheets
Blue cells show SP AusNet's performance targets and weightings
Yellow/Green cells show SP AusNet's performance formulae and related formula conditions based on performance targets and weightings
Pink cells show SP AusNet's performance outcomes without any events excluded from performance data
Orange cells show SP AusNet's performance outcomes with events excluded from performancedata
SP AusNet - Service standards report - last three quarters 2008 - template (10 February 2008).xls S7
SP AUSNET S8 - Average outage duration (lines)
Performance Targets Graph start Collar Target Cap Graph endAverage outage duration – lines (mins) 700 667 382 98 0
Weighting -0.13% -0.125% 0.00% 0.125% 0.13%
Performance Formulae Conditions S- Calc 1 S- Calc 2Performance = -0.001250 667 < Duration -0.001250 -0.001250
= -0.000004 x Duration + 0.001675 382 ≤ Duration ≤ 667 0.000686 0.000686
= -0.000004 x Duration + 0.001681 98 ≤ Duration ≤ 382 0.000688 0.000688
= 0.001250 Duration < 98 0.001250 0.001250
Average outage duration – lines (mins) =Performance
(Without Exclusions)
Performance (Exclusions)
Average outage duration – lines (mins) = 225.685714 225.685714
S-Factor 0.068800% 0.068800%
Formulae
SP AUSNET SERVICE STANDARDS S8 - Average outage duration– lines
-0.15%
-0.10%
-0.05%
0.00%
0.05%
0.10%
0.15%
0 100 200 300 400 500 600 700
Average outage duration– lines (minutes)Fi
nanc
ial I
ncen
tive
(Per
cent
age
of A
nnua
l Rev
enue
)
Service standardsincentive curve
Performance (Without Exclusions)
Performance (Exclusions)
NOTE: This sheet will automatically update based on data in input sheets
Blue cells show SP AusNet's performance targets and weightings
Yellow/Green cells show SP AusNet's performance formulae and related formula conditions based on performance targets and weightings
Pink cells show SP AusNet's performance outcomes without any events excluded from performance data
Orange cells show SP AusNet's performance outcomes with events excluded from performancedata
SP AusNet - Service standards report - last three quarters 2008 - template (10 February 2008).xls S8
SP AUSNET S9 - Average outage duration (transformers)
Performance Targets Graph start Collar Target Cap Graph endAverage outage duration– transformers (mins) 700 556 412 268 100
Weighting -0.13% -0.125% 0.00% 0.125% 0.13%
Performance Formulae Conditions S- Calc 1 S- Calc 2Performance = -0.001250 556.00 < Duration -0.001250 -0.001250
= -0.000009 x Duration + 0.003576 412.00 ≤ Duration ≤ 556.00 0.001292 0.001292
= -0.000009 x Duration + 0.003576 268.00 ≤ Duration ≤ 412.00 0.001292 0.001292
= 0.001250 Duration < 268.00 0.001250 0.001250
Average outage duration– transformers (mins) =
Performance (Without
Exclusions)
Performance (Exclusions)
Average outage duration– transformers (mins) = 263.181818 263.181818
S-Factor = 0.125000% 0.125000%
Formulae
SP AUSNET SERVICE STANDARDS S9 - Average outage duration– transformers
-0.20%
-0.15%
-0.10%
-0.05%
0.00%
0.05%
0.10%
0.15%
0.20%
100 200 300 400 500 600 700
Average outage duration– transformers (minutes)Fi
nanc
ial I
ncen
tive
(per
cent
age
of A
nnua
l Rev
enue
) Service standardsincentive curve
Performance (Without Exclusions)
Performance (Exclusions)
NOTE: This sheet will automatically update based on data in input sheets
Blue cells show SP AusNet's performance targets and weightings
Yellow/Green cells show SP AusNet's performance formulae and related formula conditions based on performance targets and weightings
Pink cells show SP AusNet's performance outcomes without any events excluded from performance data
Orange cells show SP AusNet's performance outcomes with events excluded from performancedata
SP AusNet - Service standards report - last three quarters 2008 - template (10 February 2008).xls S9
SP AUSNET - Revenue Calculation
Revenue cap information
Base year allowed revenue
Base year 2008-09
X-factor
Commencement of regulatory period
Annual revenue adjusted for CPI Dec-07
CPI
Allowed Revenue
Calendar year revenue
Revenue
$454,974,504
2008
$341,230,878
$454,974,504
-1.01%
2008-09
1-Jan-03
160.1
NOTES:
This sheet will automatically update based on data on input sheets.
Grey cells show calendar year revenue
Green cells are for formula
SP AusNet - Service standards report - last three quarters 2008 - template (10 February 2008).xlsRevenue Calculation
SP AUSNET- Performance outcomes
Revenue calendar year $341,230,878
Performance S-Factor Final Incentive Performance S-Factor Final Incentive
Total circuit availability S1 98.73% 99.078398% 0.200000% $682,462 99.117382% 0.200000% $682,462 0.000000%
Peak critical availability S2 99.39% 99.745438% 0.182276% $621,981 99.802938% 0.200000% $682,462 0.017724%
Peak non-critical availability S3 99.40% 99.810606% 0.050000% $170,615 99.932660% 0.050000% $170,615 0.000000%
Intermediate critical availability S4 98.67% 99.366936% 0.025000% $85,308 99.424704% 0.025000% $85,308 0.000000%
Intermediate non-critical availability S5 98.73% 99.518644% 0.025000% $85,308 99.530316% 0.025000% $85,308 0.000000%
Loss of supply event frequency ( > 0.05 min ) S6 5 1 0.125000% $426,539 1 0.125000% $426,539 0.000000%
Loss of supply event frequency ( > 0.3 min ) S7 1 1 0.000000% $0 1 0.000000% $0 0.000000%
Average outage duration– lines (mins) S8 382 226 0.068800% $234,768 226 0.068800% $234,768 0.000000%
Average outage duration– transformers (mins) S9 412 263 0.125000% $426,539 263 0.125000% $426,539 0.000000%
TOTALS 0.801076% $2,733,519 0.818800% $2,793,999 0.017724%
Aggregate outcome
S-factor 0.818800%
Financial Incentive $2,793,999
Financial year affected by financial incentive 2009-10
Impact of exclusions
Performance without exclusions Performance with exclusionsPerformance parameter S Target
NOTE:This sheet will automatically update based on data in input sheets.
Grey cell shows relevant calendar year revenue
Green cells show performance measure targets
Pink cells show performance, s-factor results and financial incentive without exclusions
Orange cells show performance, s-factor results and financial incentive with exclusions
Blue cells show the impact of exclusions on revenue
SP AusNet - Service standards report - last three quarters 2008 - template (10 February 2008).xls Outcomes
SP AUSNET - Defined exclusions
No. Measure 1- Total circuit availabilityDefined exclusions Further description of exclusion
1.1 Unregulated transmission assets1.2 Connection assets1.3 Third party outages Exclude from ‘circuit unavailability’ any outages caused by a fault or other event on a connected third party system e.g. intertrip signal, customer installation (TNSP to
provide lists); outages requested by NEMMCO except if SP AusNet 'causes' the outage through an act or omission; or outages caused by direction of fire services (eg. MFB, CFA or DSE Bushfire Incident Co-ordinator). Exclude co-incident outages for a generator or HV direct connect customer defined as: • Planned outages requested by the Generator or HV Customer on their dedicated line (eg. APD at Portland or JLA Bluescope Steel at Tyabb or Alcoa point Henry Geelong).• Outages co-ordinated with the shutdown of the Generator or HV customers equipment such that the customer does not require system normal network reliability or transfer capability through the high voltage grid and the outage does not affect the supply of any other person who is connected to the high voltage grid;
• Faults on the dedicated line caused by faults in the Generator or HV customers installation.1.4 Force majeure1.5 Switching to control voltages Outages to control voltages within required limits, both as directed by NEMMCO and where NEMMCO does not have direct oversight of the network (in both cases only
where the element is available for immediate energisation if required)1.6 Fault-level mitigation works Fault-level mitigation works, except for that associated with JLTS 220 kV Fault Limiting Reactors and Fault Level Mitigation Works at JLTS and MWTS; and WMTS 66 kV
Bus Tie Series Fault Limiting Reactor
Measure 2- Peak critical availabilityDefined exclusions Further description of exclusion
2.1 Unregulated transmission assets2.2 Connection assets2.3 Third party outages Exclude from ‘circuit unavailability’ any outages caused by a fault or other event on a connected third party system e.g. intertrip signal, customer installation (TNSP to
provide lists); outages requested by NEMMCO except if SP AusNet 'causes' the outage through an act or omission; or outages caused by direction of fire services (eg. MFB, CFA or DSE Bushfire Incident Co-ordinator). Exclude co-incident outages for a generator or HV direct connect customer defined as: • Planned outages requested by the Generator or HV Customer on their dedicated line (eg. APD at Portland or JLA Bluescope Steel at Tyabb or Alcoa point Henry Geelong).• Outages co-ordinated with the shutdown of the Generator or HV customers equipment such that the customer does not require system normal network reliability or transfer capability through the high voltage grid and the outage does not affect the supply of any other person who is connected to the high voltage grid;
• Faults on the dedicated line caused by faults in the Generator or HV customers installation.2.4 Force majeure2.5 Switching to control voltages Outages to control voltages within required limits, both as directed by NEMMCO and where NEMMCO does not have direct oversight of the network (in both cases only
where the element is available for immediate energisation if required)2.6 Fault-level mitigation works Fault-level mitigation works, except for that associated with JLTS 220 kV Fault Limiting Reactors and Fault Level Mitigation Works at JLTS and MWTS; and WMTS 66 kV
Bus Tie Series Fault Limiting Reactor2.7 Shunt reactors Exclude from ‘circuit availability (peak critical)’ and ‘circuit availability (peak non-critical)’ any outages of shunt reactors
Measure 3- Peak non-critical availabilityDefined exclusions Further description of exclusion
3.1 Unregulated transmission assets3.2 Connection assets3.3 Third party outages Exclude from ‘circuit unavailability’ any outages caused by a fault or other event on a connected third party system e.g. intertrip signal, customer installation (TNSP to
provide lists); outages requested by NEMMCO except if SP AusNet 'causes' the outage through an act or omission; or outages caused by direction of fire services (eg. MFB, CFA or DSE Bushfire Incident Co-ordinator). Exclude co-incident outages for a generator or HV direct connect customer defined as: • Planned outages requested by the Generator or HV Customer on their dedicated line (eg. APD at Portland or JLA Bluescope Steel at Tyabb or Alcoa point Henry Geelong).• Outages co-ordinated with the shutdown of the Generator or HV customers equipment such that the customer does not require system normal network reliability or transfer capability through the high voltage grid and the outage does not affect the supply of any other person who is connected to the high voltage grid;
• Faults on the dedicated line caused by faults in the Generator or HV customers installation.3.4 Force majeure3.5 Switching to control voltages Outages to control voltages within required limits, both as directed by NEMMCO and where NEMMCO does not have direct oversight of the network (in both cases only
where the element is available for immediate energisation if required)3.6 Fault-level mitigation works Fault-level mitigation works, except for that associated with JLTS 220 kV Fault Limiting Reactors and Fault Level Mitigation Works at JLTS and MWTS; and WMTS 66 kV
Bus Tie Series Fault Limiting Reactor3.7 Shunt reactors Exclude from ‘circuit availability (peak critical)’ and ‘circuit availability (peak non-critical)’ any outages of shunt reactors
SP AusNet - Service standards report - last three quarters 2008 - template (10 February 2008).xls Exclusion definitions
Measure 4- Intermediate critical availabilityDefined exclusions Further description of exclusion
4.1 Unregulated transmission assets4.2 Connection assets4.3 Third party outages Exclude from ‘circuit unavailability’ any outages caused by a fault or other event on a connected third party system e.g. intertrip signal, customer installation (TNSP to
provide lists); outages requested by NEMMCO except if SP AusNet 'causes' the outage through an act or omission; or outages caused by direction of fire services (eg. MFB, CFA or DSE Bushfire Incident Co-ordinator). Exclude co-incident outages for a generator or HV direct connect customer defined as: • Planned outages requested by the Generator or HV Customer on their dedicated line (eg. APD at Portland or JLA Bluescope Steel at Tyabb or Alcoa point Henry Geelong).• Outages co-ordinated with the shutdown of the Generator or HV customers equipment such that the customer does not require system normal network reliability or transfer capability through the high voltage grid and the outage does not affect the supply of any other person who is connected to the high voltage grid;
• Faults on the dedicated line caused by faults in the Generator or HV customers installation.4.4 Force majeure4.5 Switching to control voltages Outages to control voltages within required limits, both as directed by NEMMCO and where NEMMCO does not have direct oversight of the network (in both cases only
where the element is available for immediate energisation if required)4.6 Fault-level mitigation works Fault-level mitigation works, except for that associated with JLTS 220 kV Fault Limiting Reactors and Fault Level Mitigation Works at JLTS and MWTS; and WMTS 66 kV
Bus Tie Series Fault Limiting Reactor4.7 Shunt reactors Exclude from ‘circuit availability (peak critical)’ and ‘circuit availability (peak non-critical)’ any outages of shunt reactors.
Measure 5- Intermediate non-critical availabilityDefined exclusions Further description of exclusion
5.1 Unregulated transmission assets5.2 Connection assets5.3 Third party outages Exclude from ‘circuit unavailability’ any outages caused by a fault or other event on a connected third party system e.g. intertrip signal, customer installation (TNSP to
provide lists); outages requested by NEMMCO except if SP AusNet 'causes' the outage through an act or omission; or outages caused by direction of fire services (eg. MFB, CFA or DSE Bushfire Incident Co-ordinator). Exclude co-incident outages for a generator or HV direct connect customer defined as: • Planned outages requested by the Generator or HV Customer on their dedicated line (eg. APD at Portland or JLA Bluescope Steel at Tyabb or Alcoa point Henry Geelong).• Outages co-ordinated with the shutdown of the Generator or HV customers equipment such that the customer does not require system normal network reliability or transfer capability through the high voltage grid and the outage does not affect the supply of any other person who is connected to the high voltage grid;
• Faults on the dedicated line caused by faults in the Generator or HV customers installation.5.4 Force majeure5.5 Switching to control voltages Outages to control voltages within required limits, both as directed by NEMMCO and where NEMMCO does not have direct oversight of the network (in both cases only
where the element is available for immediate energisation if required)5.6 Fault-level mitigation works Fault-level mitigation works, except for that associated with JLTS 220 kV Fault Limiting Reactors and Fault Level Mitigation Works at JLTS and MWTS; and WMTS 66 kV
Bus Tie Series Fault Limiting Reactor5.7 Shunt reactors Exclude from ‘circuit availability (peak critical)’ and ‘circuit availability (peak non-critical)’ any outages of shunt reactors.
Measure 6- Loss of supply event frequency (>0.05min)
Defined exclusions Further description of exclusion6.1 Unregulated transmission assets6.3 Third party outages Any outages shown to be caused by a fault or other event on a connected ‘3rd party system’ e.g. intertrip signal, generator outage, or customer installation6.4 Force majeure6.5 Successful reclose events ( <1 min duration)
Measure 7- Loss of supply event frequency (>0.3min)Defined exclusions Further description of exclusion
7.1 Unregulated transmission assets7.3 Third party outages Any outages shown to be caused by a fault or other event on a connected ‘3rd party system’ e.g. intertrip signal, generator outage, or customer installation7.4 Force majeure7.5 Successful reclose events ( <1 min duration)
Measure 8- Average outage durations (lines)Defined exclusions Further description of exclusion
8.1 Unregulated transmission assets8.3 Third party outages Any outages shown to be caused by a fault or other event on a connected ‘3rd party system’ e.g. intertrip signal, generator outage, or customer installation8.4 Force majeure
SP AusNet - Service standards report - last three quarters 2008 - template (10 February 2008).xls Exclusion definitions
8.5 Momentary Interuptions ( <1 min duration)8.6 Planned outages Planned outages do not apply to this measure. Whilst they are excluded, they do not have to be listed in the AER Template.
Measure 9 - Average outage duration (transformers)Defined exclusions Further description of exclusion
9.1 Unregulated transmission assets9.3 Third party outages Any outages shown to be caused by a fault or other event on a connected ‘3rd party system’ e.g. intertrip signal, generator outage, or customer installation9.4 Force majeure9.5 Momentary Interuptions ( <1 min duration)9.6 Planned outages Planned outages do not apply to this measure. Whilst they are excluded, they do not have to be listed in the AER Template.