spa_ work at height.boiler
DESCRIPTION
SAFE PLAN OF ACTIONTRANSCRIPT
Safe Plan of Action
Contractor
PSM/BHEL
Date: 27.04.2015
Doc no:03
Activity/ Task
Work at height
Work area/ location
BOILER III UNIT /DISMANDLING
Rev 01
Job description: Chimney Dismantling Work
PPE Required
Helmet
Safety shoes
Safety goggles
Full body double lanyard safety harness
Hand gloves
Nose mask
Ear plug
Hard hat with welding Shield
Grinding visors/ face shield
Others________________
Safety Devices
Caution tape/ Barricading pipes
Sign/Display boards
Fluorescent jackets
Lifeline/Fall Arrestor
Flash back Arrestor
Fire extinguisher
Fire blanket
Warning lights
Steps of Activity/Task
Hazard/Reaction to Change
Safe Plan
Resources
Working at height
1) Fall from ladder which is not secured
1A) Only inspected ladder shall be used
Ladder
1B) Ladders to be secured at bottom and top
1C) Ladder to be extended one meter above the platform
1D) Face the ladder while climbing up or down
1E) Always carry tools in toolbelt hoister or raise and lower them with hand line.
1F) Maintain 3 points of contact while climbing (Such as) a. 1 hand 2 feet or b. 2 hand and 1 feet
2) Fall from height
2A) Only medically fit persons shall be allowed for working at height
Medical Certificates
2B) All personnel working above 1.8 meter to be worn and secured double lanyard safety harness with shock absorbers
Double lanyard safety harness with shock absorbers
2C) All personnel (crew) must undergo tool box talk before commencement of work and maintain records
tool box talk record
2D) Secured working platform shall be provided
Working platform
2D) Safety harness shall be anchored to safe anchoring point
Safety Harness
2E) Adequate supervision shall be maintained at all time
Supervision
3) Fall of materials from height
3A) Ensure all unsecured material shall be removed from elevated platform or properly tied if it is required
Unsecured materials
3B) Housekeeping to be done on regular basis at site
Housekeeping
3C) Unwanted material shall be removed from site
Description
Prepared By
Approved by
Reviewed by
Name
Signature
Company
M/S. PSM/BHEL
Date
The signature of the supervisor confirms the completion of the hazard assessment and Safe Plan of Action by the crew.
Supervisors Signature: Date
Instructions: 1. Write name of job or task in space provided. 2. Conduct walk-through survey of work area. 3. Write the steps of the task in a safe sequence. 4. List all possible hazards involved in each step and reaction to change. 5. In the Safe Plan column, state actions that will be taken to prevent the hazards or injury from reaction to change. 6. In Resources column, list equipment, tools, etc. needed to do the job. 8. Ask each team member, who helped develop and will use this SPA, to sign in spaces provided. 9. Review the SPA at the end of the task for improvements.
Work shall stop when conditions change, the job changes, or a deficiency in the plan is discovered, and the current SPA will be modified or a new SPA created.
Safe Plan of Action
Contractor
PSM/BHEL
Date: 27.04.2015
Doc no:03
Activity/ Task
Scaffolding Erection and dismantling work
Work area/ location
BOILER III UNIT /DISMANDLING WORK
Rev 02
Job description:
PPE Required
Helmet
Safety shoes/ Gumboot
Safety goggles
Full body double lanyard safety harness
Hand gloves
Nose mask
Ear plug
Hard hat with welding Shield
Grinding visors/ face shield
Others________________
Safety Devices
Caution tape/ Barricading pipes
Sign/Display boards
Fluorescent jackets
Lifeline/Fall Arrestor
Safety net
Flash back Arrestor
Fire extinguisher
Fire blanket
Warning lights
Others________________
Steps of Activity/Task
Hazard/Reaction to Change
Safe Plan
Resources
Erection / Dismantling of scaffold
Scaffold may collapse
Obtain valid work permits
Height work permit
Ensure hard stand and leveled floor surface shall be available to construct the scaffold
Hard stand floor
Scaffold shall be made as per scaffolding procedure
Scaffolding procedure
Bracings shall be provided with the scaffold
Bracings
Ensure scaffold plumbed and leveled by spirit level
Spirit level
Scaffold shall be tied with the structure wherever possible
Earthing shall not be provided with the scaffolding structure
Person may fall from height
Fitness certificate for workers engaged for work at height
Fitness certificate
Experienced and trained scaffolders shall be allowed to erection and dismantling of scaffold
Training material
Use double lanyard full body harness with energy absorber while working at height.
Safety harness
Area should be barricaded
Barricading tap
Ladder shall be provided for safe access and shall be properly fixed with clamps
ladder
Hand rail and mid rail shall be provided with the scaffold
Hand rail with mid rail
Proper working platform (without space or openings) shall be provided.
Proper working platform
Ensure all gratings shall be tied with binding wires
Gratings, Binding wires
Overlapping of gratings shall be avoided while making of working platform
gratings
Proper housekeeping shall be maintained
Housekeeping
Scaffold tag system shall be followed seriously
Scaffold tags
Ensure good condition scaffolding material shall be used
Scaffolding materials
Falling of objects
Provide proper toe guard
Toe guard
Tools shall be tied with the hand through rope
Rope, tools
Do not keep any unsecured/ loose material on the working platform
Unsecured or loose material
Personal protective equipments shall be used by all workers
safety helmet, Safety shoes and goggles
Area shall be barricaded by barricading tape
barricading tape
Unauthorized persons shall not be allowed to work under concerned area
Warning signboards and postures shall be displayed at site
Signboards, posters
Instruction shall be provided to the all workers through tool box talk that do not work or move under the height work
Toolbox talk
Unloading (Using Crawler crane &Hydra Crane
Fall of material
Ensure all safety devices are functioning properly before crane is put into operation.
Properly maintained
Use tested Slings for lifting
Maintain Sling angle below 60
Proper maintenance of sling (Lubricating & Store into closed compartment).
Well trained operator & Signal man shall be employed.
Trained operator to be engaged
Safe working load (Swl) Shall be painted / Displayed on crane.
Paint to be Marked
All Lifting equipment, tools must posse valid test certificate.
Certificate
Guide rope to be used to central the load.
Worker should not be allowed under suspended load.
Training given on
Secondary brake system shall be provided.
Providing inter locking system
Crane shall be operated so none of its parts can approach live electric lines closer than 3mtr.
Heave the string slowly.
Doubling the empty slings.
Dont pull the sling from the under a load which has been lowered and is resting on it.
Use Leather hand gloves, safety shoes, safety helmet and safety belt.
Make proper tool holders/ personal tool bag at work site.
Training given on
Lifting &Shifting
Failure of D Shackles &slings
Choose the slings &D Shackles according to the Load.
Slings and D Shackles shall be inspected periodically.
Do not use worn out slings &D Shackles.
Use proper packing at corners & sharp edges.
Use proper Clearance for unloading the material with slings.
Slings shall be lubricated periodically.
Brake failure of the cranes
Ensure the Breaking system, gear mechanism before starting the operation.
Lowering hoisting & slewing shall be done smoothly and slowly.(Fast and sudden movements shall be avoided)
Secondary brake system shall be provided.
Fall of material
Safe working Load(Swl) shall be painted / displayed on the crane.
All lifting equipments, tools must posse valid test certificate to be maintained.
Oven turning
Workers should not be allowed under suspended load.
Tipping of crane
Providing interlocking system.
Not using outriggers
Crane shall is operated so that none of its parts can approach live electric lines closer than 3mtr.
Abrasion and thinning of crane hooks.
Heave the slings slowly.
Doubling the empty slings.
Should not be use for pull or drag.
Should not be moved with suspended load.
Toolbox talk
Electric shock due to contact with overhead power lines.
While lifting the load the upward movement of the hook should be controlled and there should not be any jerk.
Toolbox talk
Dont pull the sling from the under a load which has been lowered and is resting on it.
Barricade the area while lifting operation is carried out.
Description
Prepared By
Approved by
Reviewed by
Name
Signature
Company
Date
The signature of the supervisor confirms the completion of the hazard assessment and Safe Plan of Action by the crew.
Supervisors Signature: Date
Instructions: 1. Write name of job or task in space provided. 2. Conduct walk-through survey of work area. 3. Write the steps of the task in a safe sequence. 4. List all possible hazards involved in each step and reaction to change. 5. In the Safe Plan column, state actions that will be taken to prevent the hazards or injury from reaction to change. 6. In Resources column, list equipment, tools, etc. needed to do the job. 8. Ask each team member, who helped develop and will use this SPA, to sign in spaces provided. 9. Review the SPA at the end of the task for improvements.
Work shall stop when conditions change, the job changes, or a deficiency in the plan is discovered, and the current SPA will be modified or a new SPA created.
Page 1 of 2