spe-rgce case studies

Upload: thangarspe

Post on 30-May-2018

228 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/9/2019 SPE-RGCE Case studies

    1/19

  • 8/9/2019 SPE-RGCE Case studies

    2/19

  • 8/9/2019 SPE-RGCE Case studies

    3/19

    INTRODUCTION

    Aim of this study is to reduce the drillingcost in ultra deep water by usingmodified second and third generation

    rigs other than fourth and fifthgeneration.

    This study focuses how to reduce the

    environmental pollution in deepwaterconfigurations in case of riser failure.

  • 8/9/2019 SPE-RGCE Case studies

    4/19

    STUDY FIELD

    Block = Donggaladeepwater block,

    OffshoreMahakam straight,

    Indonesia.

    Rig type = second and

    third generation(jack up rig)

  • 8/9/2019 SPE-RGCE Case studies

    5/19

    Drilling data

    Total Depth = 13,000 ft

    Water Depth = 6,000 ft

    Well plan Conductor casing= 13 3/8 inch

    Surface casing = 11 inch

    Intermediate casing = 9 5/8 inch

    Production casing = 7 inch

  • 8/9/2019 SPE-RGCE Case studies

    6/19

    PROBLEM IN THE WELL

    Surface casing had to be set higherthan planned to avoid penetrationinto the shallow gas zone.

    Well plan need to be changed

  • 8/9/2019 SPE-RGCE Case studies

    7/19

    OPTIONS AND THEIR

    LIMITATIONS Option 1:drilling ahead and setting the 95/8-in. casing

    followed by the 7-in. casing string.

    Problems: After setting the 7-in. casing string higher than

    was called for in the well plan, had to drilldeeper using smaller casing sizes.

    The smaller hole would have to be drilled usingslim hole tools, which would have presented thedifficulty of a smaller internal diameter at TD

    Difficulty in logging and testing for formationevaluation

  • 8/9/2019 SPE-RGCE Case studies

    8/19

    Option 2:

    To plug and abandon the well andcontinue exploration in a different

    areaOption 3:

    To start with a larger conventional

    casing size to maintain adequate holesize in the target zone.

    Limitation: Require more rig size capacity

  • 8/9/2019 SPE-RGCE Case studies

    9/19

    SOLUTION :EXPANDABLE

    OPEN HOLE LINER A 1,300-ft string of 95/8113/4-in. solid

    expandable open hole liner was run to

    depth and set at 9,400 ft. Liner expansion was performed with

    hydraulic pressure up the liner.

    As each stand of drill pipe was removedfrom the hole, the pressure was bled off,and the stand was broken out andracked back in the derrick.

  • 8/9/2019 SPE-RGCE Case studies

    10/19

  • 8/9/2019 SPE-RGCE Case studies

    11/19

    The process of reconnecting the topdrive and resuming upward expansionwas repeated until the entire liner had

    been expanded and sealed

    The liner was pressure tested to 1,000psi for 30 minutes.

    The expansion cone was then pulledout of hole, and the float shoe wasdrilled out.

  • 8/9/2019 SPE-RGCE Case studies

    12/19

    RESULT:

    Installation of an expandable linerenabled to get back on the originalwell plan and

    Reached the target zone withadequate wellbore size.

  • 8/9/2019 SPE-RGCE Case studies

    13/19

    PROBLEM 2

    Fear of environmental pollution dueto riser failure in the surface stackBOP

    Loss of mud in the ocean floor.

    High cost of drilling per well

  • 8/9/2019 SPE-RGCE Case studies

    14/19

    OPTIONS & THEIR

    LIMITATIONS Option 1: Use of subsurface BOP stack to prevent

    riser failure and use of low pressure riser

    Limitation: Require fifth generation drilling rig (drill

    ship) with the typical day rate increase upto 2oo,000 $/day

    Option 2: Use of surface stack BOP and high

    pressure riser Limitation: More chance for riser failure

  • 8/9/2019 SPE-RGCE Case studies

    15/19

    SOLUTION : ENVIRONMENTALSAFEGUARD SUBSEA SHUTOFFVALVE

    Offers a practical means of

    disconnection in an emergency. Capability to shear, seal, and

    disconnect from the seabed;

    In an unplanned disconnect, therelease of mud from the riser intothe sea is reduced by nearly 60%.

  • 8/9/2019 SPE-RGCE Case studies

    16/19

  • 8/9/2019 SPE-RGCE Case studies

    17/19

    RESULT

    The implications of using thistechnology combination extendbeyond project cost; operators cannow reach ultra deepwater targetsusing a wellbore size that waspreviously possible only by use of

    subsea-BOP technology.

  • 8/9/2019 SPE-RGCE Case studies

    18/19

    ADVANTAGE

    Use of a high-pressure riser as opposed toa low-pressure riser used with fourth- andfifth-generation rigs.

    Lower mobilization costs. Significant reduction in day rates.

    Less fuel consumption.

    Reduced mud volume.

    Lower bit costs based on smaller holesize.

    Reduced casing cost as a result ofeliminating a number of strings.

  • 8/9/2019 SPE-RGCE Case studies

    19/19