specifications document for realisation of ps2/gs2
TRANSCRIPT
SPECIFICATIONS DOCUMENT FOR REALISATION
OF PS2/GS2 INTEGRATION TOWER
EARTH STORABLE STAGES
ASSEMBLY & INTEGRATION DIVISION [ESAID]
ISRO PROPULSION COMPLEX,
MAHENDRAGIRI - 627133, TIRUNELVELI DISTRICT,
TAMILNADU www.iprc.gov.in
TWO PART TENDER
Specification Document for PS2/GS2 Stages integration tower
CONTENTSCONTENTSCONTENTSCONTENTS
Chapter Chapter Chapter Chapter
No.No.No.No. DescriptionDescriptionDescriptionDescription Page No.Page No.Page No.Page No.
1 Introduction 1
2 Scope of work 3
3 Technical specification 6
4 General quality plan 16
5 General conditions 19
6 Financial terms & conditions 33
7 Instruction for bidding 36
8 Schedule of activities 39
9 Documentation requirements 40
10 List of references 42
11 List of drawings 43
AnnexureAnnexureAnnexureAnnexure
(A) Preferred marking system 44
(B) Form 1 : BIDDER’S PROFILE FORM 45
(C) Preferred Suppliers list 49
(D) Form 2 : FORMAT FOR PRICE QUOTATION 50
Specification Document for PS2/GS2 Stages integration tower
LIST OF TABLESLIST OF TABLESLIST OF TABLESLIST OF TABLES
Table Table Table Table
No.No.No.No. DescriptionDescriptionDescriptionDescription Page No.Page No.Page No.Page No.
1 Materials to be procured (Tentative list) 9
2 Colour of different regions of the structure 14
3 Quantity variations 31
4 Method of Payment 35
5 Schedule of activities 39
6 Preferred suppliers List 49
FORMATSFORMATSFORMATSFORMATS
FormatFormatFormatFormat
No.No.No.No. DescriptionDescriptionDescriptionDescription Page No.Page No.Page No.Page No.
1 Form 1 : BIDDER’S PROFILE FORM 45
2 Form 2 : FORMAT FOR PRICE QUOTATION 50
Specification Document for PS2/GS2 Stages integration tower
1 | P a g e
1.0 Introduction
1.11.11.11.1 PS2-GS2 stages integration tower inside the new PS2/GS2 integration building
consists of four numbers of vertical integration towers with stage support pedestal.
The integration tower will consist of the following subsystems:-
1. Structural Systems.
2. Electro-Mechanical Systems for foldable working platform
The structural systems comprises the following:-
1. Stage Support pedestal structure.
2. Stage access/working platforms
a. Fixed
b. Foldable
3. Engine level working platform.
4. Staircase structures
a. Central staircase
b. Side staircase
5. Other miscellaneous structures.
The stage support pedestal is the main load bearing member, it serves the
purpose of transferring the stage mass to the foundation. The stage access platforms
are built around the pedestal and it includes all platforms and sub structures required
for accessing the engine level and accessing four elevation levels. The other
miscellaneous structures include handrails, toe-stoppers, stiffeners, gusset plates to
the structures.
The electro-mechanical system comprises the motor-rope-drum with gear box
mechanism to fold/retract the foldable platforms. Detailed design, motor and gear box
selection and realisation of parts required, lies with the scope of the contractor.
This document summarizes the technical specifications and other terms &
conditions for realization of PS2/GS2 stages integration tower.
This tender is processed on public tender mode inviting two part bids for
techno-commercial bid and price bid separately.
1.2 Keywords and Abbreviations:
In the clauses and conditions followed in this document,
1.2.1 “Department”“Department”“Department”“Department” shall mean and include the President of India acting through the
Director, IPRC and any representative(s) of the Department duly authorised on his
behalf.
1.2.2 “Contract”“Contract”“Contract”“Contract” shall mean the formal agreement to be executed between the President of
Specification Document for PS2/GS2 Stages integration tower
2 | P a g e
India and the bidder, whom the Department may choose, based on the documents
forming this tender enquiry and acceptance thereof by the bidder and together with
the documents as referred to therein including the specifications, designs, drawings
and instructions issued from time to time by the Department.
1.2.3 “Contractor”“Contractor”“Contractor”“Contractor” shall mean the individual or firm or company whether incorporated or
not, chosen by the Department among the bidders to this tender enquiry, under-
taking the works and shall include the legal personal representatives of such
individuals or the persons composing such firm or company, or the successors of such
firm or company and the permitted assignee of such individual or firm(s) or company.
1.2.5 “Site”“Site”“Site”“Site” shall mean the land and or other places at IPRC, Mahendragiri on which work
is to be executed under the contract, which may be allotted by the Department for
the purpose of carrying out the work.
1.1.1.1.3333 AbbreviationsAbbreviationsAbbreviationsAbbreviations::::
ISRO Indian Space Research Organisation
IPRC ISRO Propulsion Complex
TNEB TamilNadu Electricity Board
SWL Safe Working Load
WPS Welding Procedure Specification
1.4 Location and Layout:
1.4.1 Geographic location of IPRC:
IPRC is situated in Tirunelveli district of Tamilnadu in India. The nearest major
towns are Nagercoil which is 25 km southward and Tirunelveli which is 60 km
northward. The nearest railway station is in Valliyoor and nearest airports are
Trivandrum, Kerala & Tuticorin, Tamilnadu.
1.4.2 Layout of PS2/GS2 integration building:
PS2/GS2 stage integration building is located at around 2 km from the main gate of
IPRC. The civil structure is already built. The floor is paved with concrete provided
with pockets for foundation bolts of columns spaced as per the tower dimensions.
Fabrication & erection of foundation bolts and filling of pockets with non shrinking
grout comes under the scope of the contractor. Foundation bolt size will be informed
by the department.
Specification Document for PS2/GS2 Stages integration tower
3 | P a g e
2.0 SCOPE OF WORK
2.1 System Description:
2.1.1 The structural systems encompass all the structural steelwork (Stage support pedestal,
support structure, platforms, columns, staircase etc.,)
2.1.2 Stage support pedestal is the main stage load transferring structure. All platforms
around the stage are to provide access all around the stage at different heights.
2.1.3 Working platforms are provided at various (4 nos.) elevations and 3 sets of staircases
are there for accessing those platforms viz., Main staircase at centre and each one at
either ends.
2.1.4 The roof is located at a height of 22 m from the finished floor level and the tower
covers an area of approximately 40m x 8 m.
2.1.5 Platforms are located at elevation of 4.75 m, 7.75 m, 11.35 m and 16 m for carrying
out stage assembly activities. These platform levels matches with the building cat walk
levels also.
2.1.6 Refer drawings Nos. ESAID/PS2-GS2/99 Sh. 1 of 2 and 2 of 2 for isometric view of
tower and foundation bolts layout.
2.2 Scope of work-Contractor:
This chapter briefly summarizes the nature of work to be carried out in different
Work Phases (WP) as follows,
2.2.1 WP 1: Study & preparation of fabrication drawings, reports:
a. Study and preparation of detailed fabrication and erection drawings based on the
input drawings provided by the Department.
b. Submission of detailed fabrication drawings, bill of materials and erection plan to the
department for review and approval.
c. Carrying out the design of connections of structural members and submission of
report.
d. Carrying out the design of electro-mechanical system for the foldable platform and
submission of report.
e. Preparation of detailed bill of materials and erection plan document.
f. Preparation of General Quality Plan as per the guidelines given in this document and
its submission to department for review and approval.
g. (Note: The fabrication shall be started only after approval of these documents by the
Department)
Specification Document for PS2/GS2 Stages integration tower
4 | P a g e
2.2.2 WP 2: Procurement of Materials:
a. All the raw materials and consumables required for the fabrication and erection of the
structure shall be procured by the Contractor.
b. The different raw materials and approximate weight estimate (for finished structure)
is given in Table 1
c. Submission of all records and test and/or inspection reports on the materials procured
to the department for approval.
2.2.3 WP 3: Fabrication of the structure / sub structures:
a. Establish fabrication process (process sheet) based on approved design and fabrication
drawing.
b. Pre-Fabricate the different elements of the structure viz., stage support structure,
staircase, platform support structures etc.,
c. Inspect and /or test the fabricated elements as per the quality plan.
d. Obtaining provisional approval of the fabricated parts from the department for
conforming to quality plan.
2.2.4 WP 4: Packing and Transportation:
a. Packing, transportation and receipt (unloading and storing) of the fabricated
structures and/or substructures from the Contractors workshop to the Department’s
site at IPRC.
b. Packing, transportation and receipt of the raw materials/consumables required for
fabrication, welding, painting etc., from the Contractors workshop to the
Department’s site at IPRC.
c. Packing, transportation and receipt of the various tooling and equipments necessary
for onsite fabrication and erection from Contractors workshop to the Department’s
site at IPRC.
d. The responsibility to receive and unload the items safely at IPRC site is vested with
the Contractor.
e. Separate list (documentation) of equipments reqd. for commissioning (Returnable) to
be made and communicated to department.
2.2.5 WP 5: Erection and Commissioning:
a. Preparation of erection and commissioning procedure and obtaining approval of the
Department.
b. Insitu fabrication of structures (other than pre fabricated structures), erection of the
structure and load testing at the Department’s site.
c. Surface treatment /painting of the structure.
e. Inspection of the structure as per the quality plan.
f. Commissioning of the structural and electro-mechanical systems.
Specification Document for PS2/GS2 Stages integration tower
5 | P a g e
2.2.6 WP 6: Installation of Mechanical Systems:
a. Installation of the structure including the stage support pedestal, staircases, platforms
with chequered plates.
b. Installation of Moving Platform and demonstrating the smooth movement of movable
platform.
2.2.7 WP 7: Miscellaneous works:
a. In situ fabrication and welding of hand rails, toe-stoppers etc. and their painting
b. Scaffoldings as and when required are under the scope of the contractor.
2.3 Scope and Services – Department:
2.3.1 The design of all the structural systems covered in this document (except the
connection design) is done by the Department and the base line drawings are
provided by the Department.
2.3.2 The ‘Approval’ of detailed fabrication drawings and process plans shall be done by the
Department on submission of same by the Contractor.
2.3.3 The ‘approval’ for dispatch clearance and milestone clearances (Work phases) shall be
provided by the department.
2.3.4 For carrying out load tests within IPRC campus, department will provide necessary
loads at free of cost to the contractor
2.3.5 The Department will provide electrical power at a fixed point near the work site in
IPRC, on chargeable basis, at prevailing rate, to the contractor. It shall however be the
responsibility of the contractor to extend the facility to suit their requirement at their
own cost.
2.3.6 The hardware required for power distribution shall be scope of the contractor and it
shall be according to the Department norms.
2.3.7 The power is supplied by Tamilnadu Electricity Board (TNEB), and hence Department
is not responsible for any failure, interruption or insufficiency of service.
2.3.8 The Department shall provide space for construction of temporary office and
temporary rooms for the storage of the instruments and materials; however the
Contractor shall establish these infrastructures at their own cost.
Specification Document for PS2/GS2 Stages integration tower
6 | P a g e
3.0 TECHNICAL SPECIFICATION
3.1 Design of Connections:
3.1.1 The connection design shall be done for all typical connections as per the drawings
supplied along with this specification document.
3.1.2 All the connections in the structure are welded connections unless otherwise
specified. Where bolted connections are required for practical reasons, it shall be done
using high strength fasteners preferably 10.8 class.
3.1.3 The connections detailed in the drawings are only for information, the Contractor has
freedom to configure and design connections as required.
3.1.4 The design for connections shall also be carried out as per standard practice, wherever
they are not shown anywhere in the drawings.
3.1.5 All the connections in the structure shall be configured and designed according to
IS 800:1984 Code of practice for general construction in steel. The weld elements shall
be designed for full strength of the member.
3.1.6 The members meeting at a joint shall, wherever practicable, have their centroidal axis
meeting at a point and wherever possible the center of resistance of the connection
shall be on the line of action of load so as to avoid an eccentricity moment on the
connection.
3.1.7 However when the eccentricity is inevitable, the connection shall be designed to
provide adequate resistance to induced bending moment.
3.1.8 The gussets and the bearing brackets required for the connections shall also be
designed accordingly.
3.1.9 A report shall be prepared for all connections designed and shall be submitted to the
Department for review and approval. A summary of connections with designation by
size and length shall also be included in the report. (The connection design report
shall be organized in such a way to provide a clear picture of all connections in the
structure)
3.2 Design of Electro-mechanical system:
3.2.1 The electro-mechanical system is to be designed by the contractor for smooth lifting
and lowering the foldable platforms considering its weight.
3.2.2 The system shall comprise of an AC electric winch motor, gear box, rope drum,
pulleys, limit switches and mechanical stoppers.
3.2.3 A design report shall be prepared for the electro-mechanical system including the
loads calculations, motor selection, gear box, rope drum selection etc., and shall be
Specification Document for PS2/GS2 Stages integration tower
7 | P a g e
submitted to the Department for review and approval.
(The design report shall be made in such a way to provide a clear picture of all items
involved in the system including the ‘make’)
3.3 Fabrication and Erection Drawings:
3.3.1 The fabrication and erection drawings shall be prepared for the entire structure based
on the drawings supplied by the Department and connection design made by the
Contractor.
3.3.2 All drawings hence prepared shall conform to IS 696:1972 Code of practice for general
engineering drawings.
3.3.3 The welds shall be shown in the drawings according to IS 813:1986 Scheme of
symbols for welding.
3.3.4 The fabrication drawing shall clearly indicate cuts, holes, splices and other
fabrications to be done on the raw material.
3.3.5 After preparation, one hard copy and one soft copy in pdf and Autocad 2007 dwg
format, of all the fabrication and erection drawings shall be sent to the Department for
review and approval.
3.3.6 The fabrication drawings shall have clear indications of revision and purpose marked
legibly on them.
3.3.7 All the drawings and layouts used for fabrication and erection shall be to drawn scale,
only schematics are allowed not to be drawn on scale.
3.3.8 The final approved drawings shall be printed to a standard so as to have a shelf life of
10 (ten) years. The soft copies shall be provided in a standard DVD /CD having a shelf
life of 10 (Ten) years.
3.3.9 Where a standard Bill of Material form is not an integral part of the detail drawing,
separate Bills of Material listing all main material and fittings with space for
convenient "weighing up" of the structure shall be supplied by Contractor.
3.3.10 Any change or modifications carried out shall be duly updated in the fabrication
drawings by the Contractor and approval shall be obtained from the Department.
3.4 Materials:
3.4.1 Metal Surfaces, General Condition:
For Fabrication of work, use only virginvirginvirginvirgin materials that are smooth and free of surface
blemishes including pitting, rust, scale and seam marks, roller marks, rolled trade
names and roughness. Remove such blemishes by grinding, or by welding and
grinding.
3.4.2 Structural Steel:
a. The material of construction for all structural members of the structure shall be
Specification Document for PS2/GS2 Stages integration tower
8 | P a g e
structural steel as per the grades mentioned in the drawings conforming to IS
2062:1992 Specification of steel for general structural purpose.
b. The beams, channels and angle sections used in the structure are all hot rolled and
shall be conforming to IS 808:1989 Dimensions for hot rolled steel beam, channel and
angle sections.
c. The plates used in the structure are all mild steel plates conforming to IS 2062:2006
Specification of steel for general structural purpose.
f. All mild steel sheets used in the structure shall be as per IS 1079:1994.
3.4.3 Welding Consumables:
a. Proper welding electrodes compatible with the material as per the design
requirements shall be selected.
b. The electrodes shall conform to IS 814:1991 Specification of covered electrodes for
manual metal arc welding of carbon and carbon manganese steel, if manual metal arc
welding is used, in case of usage of any other welding process relevant Indian
standards must be followed.
3.4.4 Fasteners:
c. All the bolts used in the load bearing members shall be of 10.8 Class and on other
areas 8.8 class (min.) conforming to IS 3787:1985 Specification for high strength
structural bolts, IS 4000:1992 High strength bolts in steel structures.
d. All nuts used for fastening shall conform to IS 6623:1985 Specifications for high
strength structural nuts.
3.4.5 Paint:
a. Smoke grey colour paint for structural steel shall be zinc rich epoxy paint. Two coats
of paint to be applied on structures.
b. Apply two coats of zinc rich epoxy primer before giving the paint coat.
c. The painting system shall be as per IS 2932:2003
3.4.6 Hand rails:
a. The material of pipe used for hand (guard) rails shall be structural steel tubes.
b. 1” pipes shall be used. All welds shall be smoothened.
3.4.7 List of materials to be procured:
a. The following are tentative list of materials to be procured for the erection and
commissioning of the structures. The detailed bill of materials shall be prepared by the
contractor after the preparation of fabrication drawings.
Specification Document for PS2/GS2 Stages integration tower
9 | P a g e
Table 1 Materials to be Procured Table 1 Materials to be Procured Table 1 Materials to be Procured Table 1 Materials to be Procured (tentative list)(tentative list)(tentative list)(tentative list)
Sl. No.Sl. No.Sl. No.Sl. No. Material Material Material Material Estimated Wt.Estimated Wt.Estimated Wt.Estimated Wt.
1.1.1.1. Structural SteelStructural SteelStructural SteelStructural Steel
1.11.11.11.1 SectionsSectionsSectionsSections
ISMB400
ISMB300
ISMB 250
ISMB200
ISMC 200
ISMB150
ISMC 125
ISMC100
ISMB100
ISMC75
ISA60x6
ISA60x5
ISA75x5
60ISF6
1.21.21.21.2 MS Pipes
1.31.31.31.3 Pedestal Ring (Built up section)Pedestal Ring (Built up section)Pedestal Ring (Built up section)Pedestal Ring (Built up section)
1.41.41.41.4 Foundation platesFoundation platesFoundation platesFoundation plates
1.51.51.51.5 Misc. itemsMisc. itemsMisc. itemsMisc. items
1.61.61.61.6 TTTTotalotalotalotal 1,21,21,21,20000,000,000,000,000 kkkkgggg
1.1.1.1.7777 MS MS MS MS Chequered platesChequered platesChequered platesChequered plates 55,00055,00055,00055,000 KgKgKgKg
1.81.81.81.8 Grand Total 1,1,1,1,75757575,000,000,000,000 KgKgKgKg
Note: 1. The plates for gussets, splices and connections are approximated.
2. Mass is estimated based on finished size from the drawing.
3. The quantity in the finished job may vary from the estimate within 10%
4. The detailed list shall be prepared by the contractor based on the
fabrication drawings with necessary allowance for fabrication and
procurement.
2222 Painting To be estimated by the Contractor
3333 Consumables To be estimated by the Contractor
4444 Fasteners To be estimated by the Contractor
5555 Other Miscellaneous
materials (Weld rods etc.,)
To be estimated by the Contractor.
Specification Document for PS2/GS2 Stages integration tower
10 | P a g e
3.5 Fabrication:
3.5.1 Fabrication shall be done only as per the fabrication drawings approved by the
Department. Any non-conformance to the approved fabrication drawing shall be
recorded and waiver shall be obtained from the Department, at the earliest.
3.5.2 Fabricate and assemble structural members in shop to greatest extent possible. The
extent of prefabrication can be decided by the Contractor based on practical
constraints.
3.5.3 Properly mark and match mark the material for field assembly convenience.
3.5.4 Provide finish surfaces of members exposed in final structure free of markings, burrs
and other defects.
3.5.5 Camber:
Trusses, beams and Plate girders shall be fabricated with camber as per relevant Indian
standard.
3.5.6 Holes:
a. Cut, drill, punch holes perpendicular to the metal surface. For plates greater than 16
mm thickness, use only drilling.
b. Do not flame cut holes or enlarge holes by burning.
3.5.7 Splicing in members:
b. To the maximum extent, members shall be made from single member using
commercially available maximum length.
c. For other columns and beams, splices can be used and shall be designed as per
standard engineering practice. Joints should not impair the strength of the member.
d. All splices shall be shown in the detailed fabrication drawings.
3.5.8 Boxed Members:
a. Abutting edges shall be connected and sealed with a continuous weld.
b. Stiffeners and other details that will be enclosed within the box member shall be
subject to inspection by the Department and/or TPI before the closure plates are
welded into place.
3.5.9 Flooring:
a. Mild steel chequered (skid resistant raised pattern) plates shall be used for flooring in
all the platforms (except detachable working platform at engine level where
aluminium chequered plates shall be used). The thickness shall not be less than 5 mm.
b. Flooring shall be furnished to be continuous over two spans or more where
practicable.
e. When removable floor plate is required, two (2) lifting holes shall also be provided in
each removable floor plate.
Specification Document for PS2/GS2 Stages integration tower
11 | P a g e
f. Bolts or other fixings on the surfaces of platforms, landings and walkways shall be
countersunk flush with the surfaces.
3.5.10 Surface preparations:
All surfaces to be welded shall be clean and free from paint, oil, debris, scale, oxides
and other foreign material detrimental to welding, for a distance of at least 25 mm
from joint preparation.
3.5.11 Welded Connections:
a. All connections in the fabricated members are welded connections unless otherwise
mentioned explicitly.
b. The welding process shall be conforming of IS 816:1969 Code of practice for use of
metal arc welding for general construction in steel, IS 1024:1999 Use of welding in
bridges and structures subject to dynamic loading-Code of practice.
c. All welds shall be made with the appropriate grade of electrode suitable for the type of
steel being welded. Welds shall be thoroughly chipped to remove slag and shall be the
full size specified and/or as shown on approved drawings.
d. All fillet welds shall be continuous welds, Intermittent welds are not be permitted
where members are exposed to weather or corrosive atmosphere, unless the spaces
between are continuously seal welded.
e. Unless otherwise shown, all butt welds shall be complete penetration butt welds and
where possible, shall be double V butt welds. Beams, flange plates, web plates and
cord members of long trusses may be butt welded in the shop to form any long lengths
required provided that such splices do not come within the middle third of the
member. All butt welds in tubular and boxed members shall be backed by suitable
mild steel backing rings or plates.
f. Joints to be welded shall be properly clamped or tack welded so that uniform
stresses are built up.
g. Though profile of the weld is affected by the position of the joints, it shall be uniform
throughout. In case of butt and corner welds, the profile shall be slightly convex and
in the case of fillet weld, it is usually concave.
h. For usual inspection of the welds the locations, dimension and type of weld, size of
weld and type of welding rods used shall be checked. Size of weld may be slightly
over but not under the specified size (as per connection design).
3.5.12 Shop errors:
a. Fabrication errors or potential errors resulting from incorrectly detailed components
are to be reported immediately to the Department. The Department will consider the
action required for correction or modification of the work.
Specification Document for PS2/GS2 Stages integration tower
12 | P a g e
b. If corrections are necessary, written instructions will be given to the Contractors to
carry out such work.
c. If fabrication errors are found during erection, the Contractor will be advised and
repairs and/or modifications as considered necessary by the Department will be in the
scope of Contractor.
d. Fixtures required for handling and erection shall be fabricated preferably, during the
pre-fabrication at Contractor’s site.
e. In case of complicated structures templates/layout to be taken and checked first before
the structure is checked with layout.
f. All straightening and shaping to form shall be done by pressure and not by
hammering. Any bending or cutting shall be carried out in such a manner as not to
impair the strength to the metal.
3.5.13 Tolerances:
All finished fabricated members shall be within the tolerances as per IS 7215:1974
Tolerances for fabrication of steel structures.
3.6 Handling, Transporting and Storing:
3.6.1 The transportation of the pre-fabricated structures, raw materials, tools, erection
equipment and other relevant hardware from Contractor’s site to the Department’s
site falls in the scope of the Contractor.
3.6.2 Steelwork shall be handled and stored by methods and equipment that will not result
in overstress, deformation or damage to protective coatings. Members shall not be
stored directly in contact with the ground.
3.6.3 Members bent or buckled by the Contractor during handling shall be liable to
rejection. Any steelwork that is deformed as a result of handling, storing and
transporting and which prevents the proper assembling and fitting up of parts shall be
replaced or corrected by the Contractor. The method of correction shall be subject to
the agreement of the Department. Damage to paintwork during handling and erection
shall be repaired in accordance with specification.
3.6.4 Bolts, nuts and washers shall be stored in grit free containers, in weatherproof
premises. Loose pieces for connections shall be attached to their respective members
and clearly marked for identification.
3.6.5 During site handling, storage and erection, the Contractor shall take all necessary
precautions to prevent damage to the painted or other protected steelwork surfaces.
3.7 Erection:
3.7.1 The Contractor shall submit to the Department for agreement, details of the
equipment and methods proposed for use in the erection of the steelwork in an
Specification Document for PS2/GS2 Stages integration tower
13 | P a g e
erection plan. The agreement of the Department shall not relieve the Contractor of
responsibility for the adequacy and safety of the work during erection.
3.7.2 The erection of steel work shall be planned and carried out ensuring safe working
conditions and methods at all times. All erection gear and equipment shall be of
adequate strength and comply with all applicable Statutory Acts and Regulations.
3.7.3 Foundations:
The foundations for the erection of various columns of the structure are already
available at Department’s site. Foundation bolts and grouting of foundation bolt with
non-shrinking grout are under the contractor’s scope. The size of the bolts shall be
finalized in discussion with the department.
3.7.4 Field Measurements:
a. Check actual locations of foundations and other constructions to which the steel
framing must fit, by accurate field measurements before field erection. Show recorded
dimensions on the final shop drawings.
3.7.5 Alignment:
3.7.6 Each part of the structure shall be aligned and leveled within the specified erection
tolerances, as is practicable after it has been erected. Permanent connections shall not
be made between members until sufficient elements of the structure has been aligned,
leveled, plumbed and temporary connected to ensure that members will not be
displaced during subsequent erection or alignment of the remainder of the structure.
3.7.7 During erection, the work shall at all times be securely bolted, guyed or braced. The
Contractor shall ensure the stability of the structure at all stages or erection and shall
supply the necessary temporary bracing. If requested by Department the Contractor
shall submit certified engineering computations for stability, alignment of the
structure.
3.7.8 Tolerances:
a. The erection shall be executed in such a way that the tolerance after completion of
the erection conforms to IS 12843:1989 Tolerances for erection of steel structures.
3.7.9 Check for trial assembly when specified or when required to avoid problems of
matching of difficult components at site.
3.7.10 Do not use gas cutting torches in the field for the correction of the fabrication errors
in primary structural framing. Cutting will be permitted only in the secondary
members.
3.7.11 Finish the gas cut surfaces using grinding to provide a smooth appearance.
3.7.12 Establish required leveling and plumbing measurements on mean operating
temperature of the structure. Make allowance for the difference in temperature
Specification Document for PS2/GS2 Stages integration tower
14 | P a g e
during erection and the mean temperature at which the structure will be when
completed.
3.7.13 The erection process shall have strict compliance with IS 7205: Indian safety code for
structural steelwork.
3.8 Painting
3.8.1 One coat of primer shall be applied to all structural members, areas inaccessible after
erection shall be given with two coats of primer.
3.8.2 Paints, oils and varnishes of specified and approved brand, quality and colour (See
table 2) alone shall be used.
3.8.3 No admixtures are permitted, but if for any reason thinning is necessary in case of
ready mixed paint the brand of thinner recommended by manufacturer or as
instructed by the Department shall be used.
3.8.4 Approved paints, oils etc., shall be brought to Department’s site on original container
in sealed condition and stored in proper condition, in the Contractor premises at
Department’s site.
3.8.5 Painting except the priming works shall be started only after completing all the
structural erection works, load testing.
3.8.6 The surface shall be thoroughly cleaned and dusted off rust, dirt, scales, grease etc.,
before starting the painting.
3.8.7 The painted surface shall be free from paint runs, drops, waves, brush marks,
variations in colour, texture or finish.
3.8.8 Specified drying/curing time shall be observed before applying successive coats.
3.8.9 It is mandatory to apply one primer coat immediately after finishing any fabrication
or erection work. No structural member shall be left without protective coating in
susceptible environment after completion of fabrication.
3.8.10 Arrow marks pointing towards all exits shall be painted and solid line at least two
inches thick shall be painted along the exit path all along the staircases in a
fluorescent yellow colour as a visual aid in case of emergency.
3.8.11 The colours to be used for different regions of the structure is as follows,
Table 2 Colour of different regions of the structure.
Sl.No.Sl.No.Sl.No.Sl.No. ColourColourColourColour RegionRegionRegionRegion
a. Smoke grey All of frame members, beams, columns, bracings, gusset
plates etc., including stage support pedestal.
b. Yellow All handling components such as hooks, handles etc.,
c. Yellow & Black All hand rails with yellow & black intermittently
c. Black Top and bottom surfaces of all flooring plates.
Specification Document for PS2/GS2 Stages integration tower
15 | P a g e
d. Red Regions of low head clearance and potentially life
threatening hazardous areas. [Shall be decided by the
department]
e. Fluorescent Yellow Arrow marks in all exits, markings in all staircases,
border edges of platforms and toe-stoppers at all level
platforms.
3.8.13 The painting shall conform to IS 487:1985 Surface treatment using paints and IS
1477:1971 Part I and II Code of practice for painting ferrous metals in buildings pre-
treatment and painting.
3.3.3.3.9999 Installation of Installation of Installation of Installation of ElectroElectroElectroElectro----Mechanical System:Mechanical System:Mechanical System:Mechanical System:
3.9.1. Installation and commissioning of electro mechanical systems for 16 nos. of foldable
platforms are to be done after erection of structures.
3.9.2. The systems are to be demonstrated for smooth operation.
3.3.3.3.10101010 Load testing:Load testing:Load testing:Load testing:
3.10.1. Stage support pedestal is the main load transfer structure as the PS2/GS2 stage is
supported on it. Hence the pedestal shall be load tested.
3.10.2. Dye penetrant testing on load bearing column weldments shall be carried out after
load testing.
3.10.3 Load testing scheme shall be finalized in discussion with the department after
erection.
Specification Document for PS2/GS2 Stages integration tower
16 | P a g e
4.0 GENERAL QUALITY PLAN
4.1. The Contractor shall be responsible for the inspection and quality control of the
entire contracted job and related documentation.
4.2 The Contractor shall have an inspection and quality control setup with established
independent authority having adequate infrastructure in terms of manpower,
expertise and facilities (i.e., NDT and test equipment).
4.3 A quality plan shall be prepared by the Contractor for procurement, fabrication,
packing, transportation, erection and commissioning, taking into account the clauses
mentioned in this chapter and relevant standards.
4.4 QC Inspection:
4.4.1 The quality assurance for procurement and fabrication at the Contractor’s site shall be
in the scope of Contractor. The Contractor shall make all necessary arrangements to
employ personnel for doing the inspection. Also the Contractor shall make necessary
provisions so as to enable the Department to have access to the inspection details and
the reports.
4.4.2 The Department has the right for inspection at the contractor’s site. Contractor shall
provide necessary tools/equipments to carry out the inspection.
4.4.3 Employing a third party for QC inspection for pre-fabrication shall be decided by the
contractor. However no third party inspection is required for works carried out at
Department’s site. The quality assurance for fabrication, erection and commissioning
at the Department’s site shall also be scope of the contractor. Contractor shall provide
necessary tools/equipments to carry out the inspection.
4.5 Raw Materials:
All raw materials bought out by the contractor for executing this contract, shall be
tested as per applicable norms and codes and necessary test certificates (physical and
chemical properties) shall be available for verification.
4.6 Process Plan:
The process plan shall be prepared by the Contractor containing operation details,
quality control stages, starting from the raw materials to erection and commissioning
and it shall be got approved, by the Department before commencing the job. Any
amendment to this process plan shall be with the approval of the Department.
4.7 Shop Clearance System:
4.7.1 The Contractor’s quality control personnel shall be responsible for clearances of the
job at the Contractor’s site, as per mutually agreed quality control plan. However, at
certain specific stages (as recommended by the Department during process approval),
Specification Document for PS2/GS2 Stages integration tower
17 | P a g e
clearance of the Department’s quality personnel is mandatory.
4.7.2 The Contractor shall establish necessary records for all the inspections, tests and
acceptance and make them available to the Department.
4.8 Quality Control in Welding Processes:
4.8.1 Welding procedure specification (WPS) document shall be prepared for welded
joints. The Contractor shall be in a position to trace any fabricated joint to a WPS on
demand from the Department.
4.8.2 All weld joints shall be distinctly identified through a numbering system of
identification to be evolved and joint numbers shall be incorporated in all inspection
reports. The traceability of welds to the radiographs and weld inspection reports shall
be ensured.
4.8.3 All Welders shall be qualified as per IS 817:1996 Code of practice for training and
testing of manual metal arc welders and the certificates shall be submitted to the
Department for scrutiny.
4.8.4 The inspection of all the welded joints shall be carried out according to IS 822:1970
Code of practice for inspection of welds.
4.8.5 The following are the general guidelines for carrying out inspection of welds, all
welds will fall on one of the two classes,
Class 1: All load transfer members’ butt weld joints.
Class 2: All the remaining joints in the structure, stage support structure.
4.8.6 All class 1 welds shall be subjected to,
a. Visual inspection
b. Dimensional inspection
c. Dye penetrant test
d. Radiography
4.8.7 All Class 2 welds shall be subjected to,
a. Visual inspection
b. Dimensional inspection
c. Dye penetrant test
4.9 Non Conformances and Waivers:
4.9.1 Any nonconformance (deviation in a process or a specification change due to special
circumstances) to the specifications or processes produced in this document shall be
reported to the Department. The Department may grant the waivers for such
nonconformance based on the established protocols and procedures.
4.9.2 Records of all such nonconformance shall be maintained and changes to specification,
if any shall be incorporated in relevant documents and drawings along with the
Specification Document for PS2/GS2 Stages integration tower
18 | P a g e
approval of the Department.
4.9.3 All the records pertaining to the testing of materials, qualification of personnel,
inspection of welds, certificates etc., shall be submitted to the Department at
appropriate time / on demand.
4.9.4 The Department reserves the right to inspect the work at any specific stage through
its own personnel, on advance notice, in such cases the Contractor shall make
available all documents and records pertaining to the inspection, to the Department.
4.10 Pre-delivery inspection:
4.10.1 All the steel work fabricated at the Contractors site shall be transported to the
Department’s site after pre delivery inspection and subsequent issue of dispatch
clearance, by the Department. This applies only to the pre-fabricated structure.
4.10.2 The completion of the pre-fabrication shall be communicated to the Department well
in advance.
4.10.3 The number of pre-delivery inspections shall be brought out clearly in quality plan.
4.10.4 Where steel work has been inspected by the Department at the Contractor’s site,
before being delivered to the Department’s site, such inspection shall not relieve the
Contractor of the responsibility for the correctness of the fabricated steel.
Specification Document for PS2/GS2 Stages integration tower
19 | P a g e
5.0 GENERAL CONDITIONS
5.1 Contract Manager:
5.1.1 The Department shall have the right to administer the contract and for this purpose,
the Department shall nominate a representative whose name will be notified in
writing to the Contractor as Contract Manager.
5.1.2 Changes to the clauses and to terms and conditions of the contract shall be offered,
authorised or accepted on behalf of the Department by, and only by, the Contract
Manager.
5.1.3 The Contractor shall, in this respect, and in accordance with any relevant security
regulations, give the Contract Manager or representatives of the Department access to
his premises and shall give all other necessary assistance in order that he may fulfill
his task.
5.2 Department’s Representative(s):
The Department shall have the right to assure itself of the performance of the
technical work of the contract by inspection and for this purpose and for the general
purpose of technical collaboration, the Department shall nominate a representative(s)
whose name(s) shall be notified in writing to the Contractor.
5.3 Site Personnel:
5.3.1 The Contractor shall identify a Resident Works Manager (RWM) and Resident Safety
Officer (RSO). They shall be personally present or employ their representatives
whose names shall have previously been communicated in writing to the Department
and approved by the Department to supervise the work under the Contract.
5.3.2 The Contractor’s RWM shall have full technical capability and complete
administrative and financial powers to expeditiously and efficiently execute the work
under the Contract. Any written orders or instructions which the Department may
give to the Contractor’s RWM or his/ her representative shall be deemed to have
been given to the Contractor.
5.3.3 The Contractor’s RWM shall maintain an office on or adjacent to the site of work and
shall at all times keep in the said office a complete set of specifications and drawings.
The Department will normally communicate directly with the Contractor’s RCM at
site.
5.4 Contractors Default Liability:
5.4.1 The Department shall reserve the right to terminate the work in the circumstances
detailed hereunder,
5.4.2 If the Contractor fails to rectify, re-construct or replace any defective system/sub-
Specification Document for PS2/GS2 Stages integration tower
20 | P a g e
system/ equipment within a period of 60 days after the Department having given a
notice to the Contractor to rectify, reconstruct or replace the said defective system/
subsystem/ equipment or the Contractor delays, suspends or is unable to complete the
system/ subsystem/ equipment by the date mutually agreed upon.
a. If the Contractor commits breach of any of the terms and conditions of the Contract.
b. If the Government of India decides to terminate the Contract in public interest.
c. When the Contractor makes themselves liable for action under the circumstances
mentioned above, the Department will have power to forfeit the bank guarantee of
Contractor and the Contractor shall have no claim for damages whatsoever on such
forfeiture.
5.4.4 The work remaining to be completed at the time of termination of the Contract shall
be got executed through any other Contractor, in which case the expenses, which
may by incurred in excess of sums, which would have been paid to the original
Contractor, had the whole work been executed by them, shall be borne by the
original Contractor and shall be recovered from them.
5.4.5 If this work happens to be terminated as provided in Section 5.4.2, the Department,
in addition to any other right provided in this article, may require the Contractor to
change the title and deliver to the Department in the manner and as directed by
Department.
a. Any completed system / sub-system / equipment.
b. Such partially completed system/ sub-system / equipment, drawings, information,
which Contractor specifically produced / acquired for the performance of the work
5.4.6 The Department will pay to the Contractor as per the quoted price in the work for
completed system/ sub-systems/ equipment delivered to and accepted by the
Department and for manufacturing materials delivered and accepted. For the partially
completed system/ sub-systems/ equipment delivered to and accepted by the
Department, payment will be made at mutually agreed prices.
5.5 Rights of the Department:
5.5.1 The various parts of the Contract are intended to be complementary to each other but
if any discrepancies appear or any misunderstanding arises, the explanation of the
Department will be final and binding.
5.5.2 Wherever in the specifications which are a part of the work or which may be
furnished to the Contractor for directing the work, the terms and descriptions of
various qualities of workmanship, materials, structures, processes or other features of
the work are described in general terms, the meaning of fulfilment of which must
depend upon individual judgements, then in all such cases, the question shall be
Specification Document for PS2/GS2 Stages integration tower
21 | P a g e
decided by the Department and said material shall be furnished, said work shall be
done and said structure or feature shall be constructed, furnished or carried out in full
and in accordance with their interpretation of the same and to their full satisfaction
and approval, provided such interpretation is not in direct conflict with the
specifications or generally accepted good practice.
5.5.3 Whenever, in the opinion of the Department, the Contractor has made marked
departure from the schedule of completion laid down in the Contract or when
untoward circumstances force departure from the said schedule, the Department in
order to assure compliance with the schedule and the provisions of the work, shall
direct the order, pace and method of doing the work, which shall be adhered to by
the Contractor.
5.5.4 If at any time the Contractor’s methods, materials or equipment appear to the
Department to be unsafe, inefficient or inadequate for securing the safety of the
workmen or the public, the quality of the work or the rate of progress required, the
Department may order the Contractor to ensure their safety and increase the
efficiency and adequacy and the Contractor shall promptly comply with such orders.
5.5.5 If at any time the Contractor’s work-force and equipment are in the opinion of the
Department, inadequate for securing the necessary progress, as herein stipulated, the
Contractor shall, if so directed, increase the work-force and equipment to such an
extent as to give reasonable assurance of compliance with the schedule of completion.
5.5.6 The absence of such demands from the Department will not relieve the Contractor of
their obligations to secure the quality, the safe conducting of the work and the rate of
progress required by the work and the Contractor alone shall be and remain liable
and responsible for the safety, efficiency and adequacy of their methods, materials,
work-force and equipment, irrespective of whether or not they make any change as a
result of any order or orders received from the Department.
5.6 Safety of Work and Working Personnel:
5.6.1 The Department will not be responsible or held liable for any damage to person or
property consequent upon the use, misuse or failure of any construction/ fabrication
tools and equipments used by the Contractor or any of their sub-contractor’s, even
though such construction tools and equipment may be furnished, rented, or loaned to
the Contractor or their sub-contractor. The acceptance and / or use of any such
construction tools and equipment by the Contractor or their sub-contractors shall be
construed to mean that Contractor accepts all responsibilities for and agree to
indemnify and save the harmless Department from any and all claims for said
damages resulting from said use, misuse or failure of such construction tools and
Specification Document for PS2/GS2 Stages integration tower
22 | P a g e
equipment
5.6.2 The Contractor and their sub-contractors shall be responsible during work for
protection of the work which has been completed by the other Contractors. The
necessary care shall be taken to see that no damage to the same is caused by their own
men during the course of execution of their work.
5.6.3 All other works completed or in progress as well as machinery and equipment that
are liable to be damaged by Contractor’s work shall be protected by the Contractor
and such protection shall remain and be maintained until its removal is directed by
the Department.
5.6.4 The Contractor shall effectively protect all the works from action of weather and
from damages or defacement and shall cover finished parts where ever required for
their thorough protection.
5.7 Working and Safety Regulations:
5.7.1 The Contractor shall observe all statutory and legal requirements enforced by Central
and State Government applicable to the work as well as any local regulations applying
to the site issued by Department or its representatives.
5.7.2 Contractor shall comply with all the security regulations of Department.
5.7.3 Smoking, use of mobile phone, camera, match-box, lighter and any other source of
ignition is strictly prohibited inside IPRC Campus.
5.7.4 Contractor shall establish a safe work procedure and strictly comply with
a. All electricity rules and regulations.
b. Standard safety procedures to be followed in scaffolding, operating hoisting
equipments, welding & gas cutting, grinding, painting, radiography.
c. Statutory requirements for inspection and test of all lifting appliances and auxiliary
lifting gear.
5.7.5 The Contractor shall bring his own standard personnel protective equipment such as
helmets, gloves, ear muffs, safety shoes, safety belts etc., in addition he shall bring
safety tools deemed necessary to carry out the job at Department site, in addition he
should ensure proper use of them in Site.
5.7.6 In case of accident, the Department shall be informed in writing forthwith. The
Contractor shall strictly follow the regulations laid down by the Factory Inspector,
Central and State Government authorities in this regard.
5.7.8 The Contractor shall notify the Department of his intention to bring on to the site
any equipment such as space heating or welding apparatus, or any container holding
liquid or gaseous fuel or other substance, which might create a hazard. The
Department will have the right to prohibit the use of such equipment or to prescribe
Specification Document for PS2/GS2 Stages integration tower
23 | P a g e
the conditions under which such equipment may be used.
5.7.9 Erection work shall conform to IS 7205:1974 Safety code for Erection of Structural
Steelwork (latest edition).
5.7.10 The Department will have the right to prohibit the use of certain equipment or to
prescribe the conditions under which such equipment may be used.
5.7.11 Heavy handling and erection jobs are prohibited after 18:00 hrs, in case of any such
requirement, the Contractor shall obtain permission from the Department and do
such jobs only in the presence of Department representatives.
5.7.12 The movement of isotope source for radiography purpose will be permitted only with
the prior approval of Atomic Energy Regulatory Board (AERB).
5.7.13 Safety and security of contract personnel shall be in the scope of contractor even at
Department’s site, Department has no liability in this regard.
5.8 Electrical Safety Regulation:
5.8.1 The Contractor shall arrange temporary Power Distribution Panel (PDP) with
Moulded Case Circuit Breaker (MCCB), Earth Leakage Circuit Breaker and
calibrated energy meter for taking electrical power from Department’s power
termination point. Necessary power cabling from the Department’s power
termination point to the Contractor’s PDP and from the Contractor’s PDP to the
Contractor’s utility points shall be arranged by Contractor. PDP shall be grouted
properly. All temporary cabling must comply with rules & regulations and subject
to Department’s satisfaction. After making all temporary power cabling,
Contractor shall formally apply to Department for safety and work permits. After
ascertaining the compliance of the Contractor’s temporary cabling with
Department safety regulations, Department will energize the Contractor’s PDP.
The Contractor shall employ a full time electrician to maintain his temporary
installations. The Contractor shall not however have any claim against the
Department in the event of any failure, interruption/ insufficiency of these
services. If required, the Contractor may employ a portable Diesel Generator (DG)
set to get regular power supply.
5.8.2 In no circumstances Contractor shall interfere with fuses and electrical equipment
belonging to the Department or other Contractors. Before the Contractor
connects any electrical appliance to any plug or socket belonging to other
Contractor or Department, Contractor shall do the following:
5.8.3 Ensure Department that the appliances are in good working condition.
5.8.4 Inform the Department of the maximum current rating, voltage and phase of the
Specification Document for PS2/GS2 Stages integration tower
24 | P a g e
appliance.
5.8.5 Obtain permission of the Department detailing the sockets, to which the appliance
may be connected
5.8.6 There shall be a separate temporary power supply panel with MCCB & ELCB for
connecting Contractor’s electrical equipment like welding, drilling, cutting,
grinder machines. The Department will not grant permission to plug-in until the
Department is satisfied that
a. The appliance is in good condition and is fitted with suitable plug.
b. The appliance is fitted with suitable cable, having two earth conductors.
5.8.7 All panels shall be grouted properly. All power and welding cables used shall be of
double insulated cable of suitable capacity. No weight of any description shall be
imposed on any such cable and no ladder or similar equipment shall rest against or
be attached to it. The voltage for all portable equipments like drilling machines,
temporary lighting etc, shall be 240 ± 10% volts.
5.8.8 Contractor shall have separate welding return cable. Test stand
structures/pipelines shall not be used as return cable.
5.8.9 Power cables and welding cables shall be routed properly. No test stand structure
shall be used for fixing the cable.
5.8.10 No electric cable in use by the Department/Contractor will be disturbed without
prior permission.
5.9 Communications:
All communications affecting the terms and conditions of the contract and
concerning its execution shall be made or confirmed in writing.
5.10 Subcontracting:
5.10.1 Subcontracting, if any shall be done by the contractor only with the prior knowledge
and sanction of the Department.
5.10.2 The proposal for sub contract including the terms & conditions to be stipulated, shall
be submitted to the department for approval. Only after obtaining the approval of the
department, the contractor can finalise the sub-contract.
5.10.3 The contractor shall be responsible for the proper execution of any subcontract
placed by him in connection with this contract, defaults and delays in any form or
any level cannot bind the Department.
5.11 Employment of Labours:
5.11.1 The Contractor will be expected to employ, on the work, only his regular skilled
employees with experience of this particular work. No female labour shall be
Specification Document for PS2/GS2 Stages integration tower
25 | P a g e
employed after normal working hours. No person below the age of 18 years shall be
employed. The Contractor shall pay to each person, wages not less than those
specified by Minimum Wages Act. The employees / labour, for carrying out all the
site works shall be identified well in advance by the Contractor and necessary
approval shall be obtained from the Department for entry to the work site.
5.11.2 All personnel employed as manual labour must be covered under appropriate
insurance policy (ESI).
5.12 Changes and Modifications to Specifications and Qualitative Requirements:
5.12.1 The department reserves the right at any time to modify the qualitative requirements,
specifications, patterns or drawings relating to the work covered by this contract. The
contractor shall inform the Department within 15 days, of any objections he has to
the modifications required.
5.12.2 The department may also accept modifications proposed by the contractor on his own
initiative or on behalf of subcontractors.
5.12.3 The contractor shall in a reasonable time submit an estimate of any such
modifications in the cost and/or delivery schedule of the contract.
5.12.4 In the light of these estimates, the Department will decide whether and if so at what
stage, the modifications are to be introduced and shall advise the Contractor in
writing together with the Department’s new limits of liability. When a modification
or other change is so authorized, the Contractor shall proceed with action in
accordance with the Department’s direction.
5.12.5 For any such change if unit rates are not available in the contract, the changes shall
be implemented through an amendment.
5.12.6 Any amendment to the contract which may be necessary in these respects shall be
established in the form of an amendment to contract, to be signed by both the parties.
In case of any dispute regarding cost, responsibility or delivery schedule etc., it shall
be submitted to arbitration.
5.13 First Aid:
The Contractor may have access to the Department’s qualified first aid personnel and
ambulance in case of accidents, subject to the availability of the same. However, the
Contractor shall make his own medical and transport arrangements to take care of his
employees in case of accident. The Contractor shall provide a first aid kit at the work
site to meet the requirements of minor injuries.
5.14 Publicity Relating to Contract:
Advertisements, press releases or other specialised publicity documents which are
related to or reveal the existence of a contract and are intended by the Contractor for
Specification Document for PS2/GS2 Stages integration tower
26 | P a g e
public distribution and/or the press, broadcasting, or television shall be notified to the
Department. The Department may direct the Contractor to withheld such publicity
or to require modifications to be made to the publicity material. The Contractor shall
comply with such directions. If the Contractor does not receive such direction within
thirty days of the receipt by the Department of the notification by the Contractor to
engage in such publicity, the Department shall be deemed to have no objection, to
such publicity.
5.15 Secrecy:
The technical information, drawings, specification and other related documents
forming part of enquiry or Contract are the property of the Department and shall not
be used for any other purpose, except for execution of the Contract. All rights,
including the rights in the event of grant of a patent and registration of designs are
reserved. The technical information, drawings, specifications, records and other
documents shall not be copied, transcribed, traced or reproduced in any other form or
otherwise in whole and/ or duplicated, modified and/or disclosed to a third party
and/or not misused in any other form whatsoever without the Department’s consent
in writing except to the extent required for the execution of the work. This technical
information, drawings, specifications, records and other documents shall be returned
to the Department with all approved copies and duplicates, if any, immediately after
they have been used for the agreed purpose.
5.16 Force Majeure:
If at any time during the currency of the Contract, the performance in whole or in
part by either party of any obligation under the work is prevented or delayed by
reasons of any war, hostility, acts of the public enemy/terrorist, civil commotion,
sabotage, fire, flood, earth quake, epidemics, quarantine restrictions, strikes, lockouts,
or acts of God (hereinafter referred as eventualities) and if notice is given by either
party to the other within 21 days from the date of occurrence thereof, neither party
shall for such eventuality be entitled to terminate the work nor shall any party have
any claim for damages against the other in respect of such non-performance or delay
in performance. The performance under the work shall be resumed as soon as
practicable after such eventualities have come to an end and the decision of the
Department whether the situation has been resumed or not shall be final and
conclusive. Provided further that if the performance in whole or in part of any
obligation under the work is prevented or delayed by such eventuality for a period of
exceeding 60 days, the Department may at their option terminate the Contract
provided also if the work is terminated under this clause, the Department will be at
Specification Document for PS2/GS2 Stages integration tower
27 | P a g e
liberty to take over from the Contractor at a price fixed by the Department which
shall be final, all unused, un-damaged, and acceptable material, bought-out
components and stores in course of erection and commissioning in the possession of
the Contractor at the time of such termination of such portion thereof as the
Department may deem fit excepting such material, bought-out components and stores
as the Contractor may with the concurrence of the Department elect to retain.
5.17 Contractor-Other Obligations:
5.17.1 The Contractor shall provide everything necessary for proper execution of the work
according to the intent and meaning of the specifications whether the same may or
may not be particularly shown or described therein, provided that the same can
reasonably be inferred there-from and if the Contractor finds any discrepancy there-
in, they shall immediately and in writing refer the same to the Department whose
decision shall be final and binding on the Contractor.
5.17.2 If any part of the Contractor’s work depends for proper execution upon the work of
any other Contractor, the Contractor shall inspect and promptly report in writing to
the Department any defect in such work of the other Contractors that tender it un-
suitable for proper execution of the work under this Contract. Their failure to so
inspect and report shall constitute acceptance of the other Contractor’s work as fit
and proper for the reception of their work, except as to defects which may develop in
the work of the other Contractors after proper execution of the work. To ensure
proper execution of their subsequent work, the Contractor shall measure the work
already in place and shall at once report to the Department any discrepancy between
the executed work and the drawings.
5.17.3 Contractor shall not sell, assign, mortgage, hypothecate or remove equipments or
materials which have been erected or which may be necessary for the completion of
the work without the written consent of the Department.
5.17.4 In the execution of the work, no person other than the Contractor, or their duly
appointed representatives, their sub-contractors, and their workmen, shall be allowed
to work at the site except by special permission, in writing by the Department.
5.17.5 The Contractor shall proceed with the work to be performed under this Contract and
each and every part and detail thereof, in the best and most workmen-like manner by
engaging qualified, careful and efficient workers and to the several parts thereof at
such time and in such order as the Department directs and finish such work in strict
conformance with the plans, drawings and/or specifications and any changes,
modifications or amplifications thereof made by the Department.
5.17.6 The Contractor’s personnel shall not be permitted to reside inside the Department’s
Specification Document for PS2/GS2 Stages integration tower
28 | P a g e
premises after the work. The Contractor shall make their own arrangement for
transportation, accommodation, food, health care, communication, insurance etc. for
their personnel.
5.17.7 It is the responsibility of the Contractor for arranging necessary Workmen’s
Compensation Policy for their employees and labourers as per statutory
requirements. It is compulsory to produce records of insurance details to the safety
division of IPRC for obtaining “Safety Permit” to commence site work by Contractor.
5.17.8 In respect of observance of local rules, administrative orders, working hours and the
like, the Contractor and their personnel shall co-operate with the Department.
5.18 Clean up of Work site:
The Contractor shall not store or place the equipment, materials or erection
equipment on the drive ways and streets and shall take care that their work in no
way restricts or impedes traffic or passage of men and material. During erection, the
Contractor shall without any additional payment, at all times keep the working and
storage area used by him free from accumulation of loose and combustible material,
waste materials or rubbish to avoid fire hazard and hindrance to other works of the
Department. If the Contractor fails to comply with these requirements, the
Department will proceed to clear those areas and the expenses incurred by the
Department in this regard shall be payable by the Contractor. Before completion of
the work, the Contractor shall remove or dispose in satisfactory manner all
scaffolding, temporary structures, sheds, buildings, stores, waste and debris and leave
the premises in a condition satisfactory to the Department.
5.19 Purchase of materials:
5.19.1 The Contractor shall process purchase action generally with the identified sub-
vendors/ sub-contractors as approved by the Department and if necessary purchase
action shall be initiated with any additional sub-vendor/ sub-contractor after
obtaining approval from the Department.
5.19.2 The criteria for selection of particular product and the reasoning involved therein
shall be submitted to the Department for necessary approval. However Department’s
decision will be final.
5.19.3 In keeping with the terms of the Contract, the Contractor shall undertake full
responsibility for storage, handling, packaging and transportation involved to the
accepted level of any sub-systems/ equipment covered by the work in the Contract.
5.20 Works after Office Hours:
The work by the Contractor, is allowed, at the site beyond normal working hours
(08:45 to 17:15 hrs) on working days and any time on holidays (including Saturdays
Specification Document for PS2/GS2 Stages integration tower
29 | P a g e
and Sundays) with prior approval of the Department. The Department may also direct
the Contractor to operate extra shifts over and above normal day shift to ensure
completion of the work on schedule if, in the opinion of the Department, such work
is required.
5.21 Arbitration:
Except matters in respect of which the decision of the Department is final as specified
in the Contract, any dispute, disagreement or question which cannot be settled
mutually, shall within 30 days from the date that either party informs the other in
writing, that such dispute or disagreement exists, be referred to arbitration. The
Arbitrator shall be a serving Law officer of the rank of Joint Secretary to the
Government of India. The arbitration proceedings shall be in compliance with the
Arbitration and Conciliation Act 1996. The performance under this work shall
continue during the arbitration proceedings and no payment due or payable by the
Department will be withheld unless any such payment is or forms part of the subject
matter of the arbitration proceedings.
5.22 Infringement of law:
The Department shall not be responsible if the Contractor infringes the laws or
statutes currently in force in India, or of the country in which the contract is carried
out.
5.23 Infringement of third party rights:
Unless otherwise stipulated in the contract, the contractor shall indemnify the
Department from and against all claims, proceedings, damages, costs and expenses
arising from the infringement of patent rights and intellectual property rights of
third-parties with respect to the subject of the contract – excluding any infringement
resulting from the use of documents, patents drawings or goods supplied by the
Department which may be made, or brought against the Department, or to which the
Department may be put by reasons of such infringement or alleged infringement.
5.24 Disclosure and Use of Information by the Contractor:
5.24.1 If the documents supplied by the Department are marked ‘restricted use’ the
Contractor shall take all necessary steps to ensure that the requirements of the
contract or any specification, plan, drawing, pattern, sample or information supplied
by, or on behalf of, the Department in connection there with shall not be disclosed to
any person other than a person employed or engaged by the Contractor, whether
under sub-contract or otherwise, for the performance of the contract.
Specification Document for PS2/GS2 Stages integration tower
30 | P a g e
5.25 Performance Guarantee:
5.25.1 The “Defect Liability Period” shall be 12 months from the date of the final acceptance
of the system to the satisfaction of the Department. The work shall not be considered
completed until the Department has certified in writing that they have been actually
accepted and the Defect liability period shall commence from the date of such
certificate.
5.25.2 In case any defect in the work due to bad materials, and/ or bad workmanship
develop in the work before the expiry of the period, the Contractor, on notification
by the Department, shall rectify or remedy the defects at their own cost and shall
make their own arrangements to provide materials, labour, equipment and any other
appliances. All responsibilities in this regard fall in the scope of the Contractor.
5.25.3 The equipment or components repaired or replaced by the Contractor shall be
guaranteed for a period of 12 months from the date of acceptance after repairs or
replacement.
5.25.4 The Contractor shall furnish performance guarantee in the form of an unconditional
irrevocable bank guarantee from any nationalised/scheduled bank approved by RBI to
the extent of 10% of the Contract value valid during the defect liability period. If any
defect is noticed by the Department during the defect liability period and Contractor
fails to rectify or remedy the defects, the Department will have the right to get this
done by other agencies and recover the cost incurred, as determined by the
Department, which shall be final and binding, by recovery from the amounts due to
the Contractor and/ or by enforcing bank guarantee.
5.26 Cancellation of Work:
5.26.1 The Department will have the right, at any time, to cancel the Contract either wholly
or in part by giving written notice. The Contractor shall undertake to observe the
instructions of the Department as to the winding up of the contract both on his own
part and on the part of his sub-contractors.
5.26.2 In the case of cancellation of the Contract by the Department without any fault of the
Contractor, the Contractor shall forthwith take the necessary steps to implement the
Department’s instructions. The period to be allowed to implement shall be fixed by
the Department after consultation with Contractor and, in general, shall not exceed 3
months.
5.26.3 Subject to the Contractor conforming with the instructions referred to in Section
5.27.2, the Department will take over from the Contractor at a fair and reasonable
price, decided by the Department, all finished parts not yet delivered to the
Department, all unused and undamaged materials, bought-out components and
Specification Document for PS2/GS2 Stages integration tower
31 | P a g e
articles in course of fabrication in the possession of the Contractor for the
performance of the work, except such material, the Contractor shall, with the
agreement of the Department, elect to retain.
5.26.4 The ownership of all materials, part and unfinished work paid for by the Department
under the provisions of this Section shall be vested in or transferred to the
Department as soon as they have been paid for.
5.27 Execution Schedule:
5.27.1 The entire work is to be completed within 250 days from the date of award of the
contract. Any delay in the schedule shall be dealt with according to the clauses
mentioned in this document.
5.27.2 This execution period includes time for connection design, drafting, procurement,
prefabrication, erection and commissioning at IPRC site. Detailed schedule of Detailed schedule of Detailed schedule of Detailed schedule of
activactivactivactivities is provided in Chapter 8, Table 5ities is provided in Chapter 8, Table 5ities is provided in Chapter 8, Table 5ities is provided in Chapter 8, Table 5
5.27.3 The Contractor shall prepare a realisation schedule in the form of a bar chart
identifying key milestones, preferably in the form of work phases mentioned in
clause 2.2.
5.27.4 Any delay in the work due to the non-availability of the site shall be borne by the
Department and appropriate extension in the schedule will be given by the
Department. Otherwise the contractor shall strictly complete the work within the
period mentioned.
5.27.5 Liquidated damage:
Due to reasons not attributable to Department, if the Contractor fails to complete the
work or fails to meet delivery date within the time specified in the Contract or any
extension thereof, the Department will recover from the Contractor as liquidated
damages (LD) a sum of 0.5% of the total value of the contract for each calendar week
of delay or part thereof. The total value of liquidated damages shall not exceed 10% of
the contract value. The applicability of LD shall be considered for the total execution
schedule of 250 days including commissioning.
5.28 Quantity Variations:
The quantity in the finished job may vary from the estimate only within the limits
specified below,
Table 3 Quantity variationsTable 3 Quantity variationsTable 3 Quantity variationsTable 3 Quantity variations
Job Variation
a. Fabrication, Erection and commissioning of
structure steelwork.
± 10 % by weight in kg.
b. Painting ± 10 % by area in m2.
Specification Document for PS2/GS2 Stages integration tower
32 | P a g e
c. Design of connections, Documentation and
Drafting
-
d. Fabrication and installation of
Electro-Mechanical systems
-
5.29 Minimum Qualification Criteria:
The company/firm interested to participate in the tender shall qualify at the
minimum, the following criteria along with the aforesaid specifications; however
qualification of these criteria alone does not ensure the offer of purchase order.
a. Average annual financial turnover during last three years ending 31st march
2016 shall be at least INR 90 Lakhs.
b. Experience of having successfully completed similar structural works during
last seven years ending 31st March 2016.
i. The party shall have completed one similar structural work costing not
less than INR 240 Lakhs.
OR
ii. The party shall have completed two similar structural works costing
not less than INR 150 Lakhs.
OR
iii. The party shall have completed three similar structural works costing
not less than INR 120 Lakhs.
The term similar structural work for all purpose shall be taken as work of
similar size and form as the structural work. It can be an individual work or part of a
bigger project. However a group of works cannot be clubbed together and claimed as
a single work.
Specification Document for PS2/GS2 Stages integration tower
33 | P a g e
6.0 FINANCIAL TERMS AND CONDITIONS
6.1 Books of Contractor to be open to Department:
Except as may be otherwise stipulated in the contract the books of the Contractor
relating to the contract shall be open to the Department. The Department may
inspect all such books, bills, vouchers and other financial records at any time.
6.2 Right to Audit:
Except as may be otherwise stipulated in the contract, the Department reserves the
right to audit, either itself or through an authorised representative, the claim of the
contractor for costs incurred in the execution of any contract.
6.3 Government Taxes, Duties, Levies etc.,:
6.3.1 The Contractor shall take all necessary steps in order to facilitate the Department’s
exemption from certain taxes and customs duties resulting from its position as a
Research and Development Department.
6.3.2 The Contractor shall carry out all necessary formalities in order to bring about the
exemption form taxes and duties which might otherwise be levied on the expenses he
will incur, before he submits the invoice to the Department.
6.3.3 If in case any such items are paid, the Contractor shall comply with the instructions
given to him by the Department and provide in due time the information which the
Department requires to claim reimbursement.
6.3.4 Forms C or D for concessional rate of CST for interstate purchase will not be issued
by the Department.
6.3.5 The statutory deductions on account of Income tax shall be made as per the extant
provisions contained in the Indian Income Tax Act, 1961 and tax deducted-at-source
certificate will be issued to the Contractor.
6.3.6 Excise Duty Exemption Certificate will be provided by Department for indigenous
items consigned to IPRC Mahendragiri against Proforma Invoice submitted by the
Contractor.
6.4 Advance and Progress Payments:
6.4.1 Performance Security Deposit and Performance Bank Guarantee:Performance Security Deposit and Performance Bank Guarantee:Performance Security Deposit and Performance Bank Guarantee:Performance Security Deposit and Performance Bank Guarantee:
Performance Security deposit (PSD) payable to the department shall be furnished by
the Contractor, in the form of a bank guarantee (BG), issued by a scheduled bank in
the prescribed format, withiwithiwithiwithin 30 days from the date of purchase order.n 30 days from the date of purchase order.n 30 days from the date of purchase order.n 30 days from the date of purchase order. This deposit is
meant to compensate, the department, for any loss due to failure of the supplier to
complete his obligations as per the purchase order. PSD is payable by the supplier at
Specification Document for PS2/GS2 Stages integration tower
34 | P a g e
the rate of 10 % of the purchase order value. The PSD shall be kept valid for the
entire duration of the contract and shall be extended as Performance Bank Guarantee,
for a period of twelve months, after the completion of the Contract. SSI units
registered with NSIC/DGS&D are exempted from paying Performance Security
Deposit, in that case only the Performance Bank Guarantee shall be furnished from
date of completion of the work.
6.4.2 All bank guarantees except the Performance Bank Guarantee shall be valid until the
completion of the job. The job will be deemed complete only when given in writing
by the Department. It is the job of the Contractor to ensure the validity of the bank
guarantee and extend it if required.
6.4.3 Except with specific agreement of the Department, the contractor shall not divert to
uses not provided for in the contract any material or services in respect of which
advances or progress payments have been made. The Department reserves the right to
ask the contractor for a special guarantee in order to safeguard its financial interest.
6.4.4 These are general guidelines to be adhered, changes in these terms can be
incorporated based on the mutual agreement between the Contractor and the
Department before the submission of quotation.
6.5 Validity:
The quoted price shall be valid for a period of at least 99990 days0 days0 days0 days from the date of
opening the quotation.
6.6 Limitations of Liability:
6.6.1 The limit of liability is the amount stated in the contract i.e., the purchase order,
which shall be the maximum amount to which the Department is committed and
which can only be increased by a written agreement of the Department.
6.6.2 The Department shall not be obliged to reimburse the contractor for costs incurred in
excess of the limit of liability and the contractor shall not be obliged to continue
performance under the contract or to incur costs in excess of the limit of liability,
unless and until the Department shall have notified the Contractor in writing that
such limit has been increased up to a revised amount.
6.6.3 The Contractor is obliged to submit documents/records if any, to substantiate such
revisions.
6.7 Final Settlement:
Contractor shall be allowed to claim final settlement when all his/her obligations
under the contract have been fulfilled. The obligations of the contractor are deemed
complete only after a written statement by the Department.
6.8 Method of Payment:
Specification Document for PS2/GS2 Stages integration tower
35 | P a g e
6.8.1 The payment for the finished job shall be done on the following basis,
Table 4 Method of Payment
Sl. No. Description Basis of Payment
a. Fabrication, Erection, Testing
and Commissioning of
structural steelwork.
Finished structure weight in kilogram.
b. Painting Total area painted in square meter.
c. Design of connections,
Documentation and Drafting.
Fixed amount.
d. Installation of Electro-
mechanical systems.
Fixed amount.
6.8.2 Taxes and transportation charges shall be paid extra over the aforementioned clauses.
6.8.3 No separate payment shall be made for inspection and testing, it shall be included in
Sl. No. 6.8.1 a.
6.8.4 The payment shall be made only for the finished structure weight, no separate
payment will be given for fabrication and erection losses, hence the amount shall be
quoted accordingly. (For quotation refer Chapter 7 Instruction for Bidding)
6.8.5 No separate payment shall be made for procurement of materials and hence the
incurred procurement cost shall be included in Sl. No. 6.8.1 a, b & c.
6.8.6 Estimation of finished structural weight shall be based on the fabrication drawings
and measurement of finished job where ever possible.
6.8.7 Only relevant IndianIndianIndianIndian standardsstandardsstandardsstandards shall be used for such estimations.
6.8.8 Estimation of painting area shall also be based on the fabrication drawings and
measurement of finished job where ever possible.
6.8.9 Any dispute in the method of payment shall be communicated the Department in
advance.
Specification Document for PS2/GS2 Stages integration tower
36 | P a g e
7.0 INSTRUCTION FOR BIDDING
7.1 This chapter gives the specific instructions regarding the details to be provided along
with the quotations, to be submitted by the participants of this tender.
7.2 The Contractor is allowed to visit the Department’s site to have a clear understanding
of the site conditions and job nature before submission of quotation. A pre-bid
meeting shall be arranged, in this regard, by the Department.
7.3 The validity of the offervalidity of the offervalidity of the offervalidity of the offer shall be for 99990 days0 days0 days0 days (Ninety days) minimum from date of
opening of quotation and shall be clearly mentioned in the offer, any change in the
validity of the offer will not be entertained.
7.4 Offers shall be free from corrections and erasures. Corrections if any shall be attested
with date, by appropriate authority.
7.5 The quotation against the tender shall be submitted in two parts, in two sealed
envelopes as follows,
1.1.1.1. Technical and Commercial QuotationTechnical and Commercial QuotationTechnical and Commercial QuotationTechnical and Commercial Quotation
2.2.2.2. Price QuotationPrice QuotationPrice QuotationPrice Quotation
7.6 The technical and commercial quotation shall be opened first and the parties shall be
shortlisted, then the price quotation of the short listed parties shall be opened.
Technical and Commercial Quotation:
The technical and commercial quotation shall contain the following aspects to enable
the Department to evaluate the capability of the party to execute the job. In addition
the Contractor shall also provide the ‘Bidder’s Profile’ as per the form in Annexure 1.
7.7 Bidder’s Profile:
The bidder shall elaborately bring out in their quotation their company profile,
which shall be commensurate with the level demanded for the execution of the work
specified in this document. The details shall include the following:
7.7.1 Infra-structural facilities such as factory area, machineries, equipment, material
handling systems, etc.
7.7.2 Human resource inventory under the categories such as executives, managers,
engineers, supervisors, safety officers, foremen, technicians, unskilled labourers,
clerical staff, auxiliary staff, etc. The educational qualification, expertise and
experience of the key staff shall also be submitted.
7.7.3 Financial soundness specifying the annual turn-over, annual income tax paid, name
of the banker etc. for the last 3 years.
7.7.4 Previous experience in execution of the projects of the nature and quantum on par
Specification Document for PS2/GS2 Stages integration tower
37 | P a g e
with those specified in this document in the last 5 years.
7.7.5 Clientele, specifying the clients to whom they have executed works of nature similar
to that specified in this document. The address, telephone, fax, e-mail and contact
person of the clients shall also be specified.
7.7.6 Quality management system: If the bidder is certified for ISO 9001: 2008 quality
management system, a copy of the certificate by the accreditation agency shall be
submitted.
7.7.7 A copy of BIS license or relevant supporting document for ownership of such
standards to be used in design, drafting, fabrication, erection and commissioning.
7.8 The list of sub-vendors from whom the bidder proposes to purchase the materials and
the sub-contractors with whom the bidder proposes to sub-delegate part of the work
shall be provided.
7.6 Regarding the procurement of raw materials, it is essential that the fabricator gives
alternate/contingency measures, in case any of the materials required for this
Contract becomes scares in the market. This is necessary to ensure the time schedule
given by the contractor for completion of various activities.
7.7 The contractor shall furnish his philosophy of subcontracting with particular
reference to the equipment which may be sub contracted by him for design,
fabrication and supply.
7.8 Regarding the site work, it is essential that the contractor shall furnish summary of
his proposed plan, including the details of personnel to be posted in the site.
7.9 The contractor shall provide the detailed schedule of all the works to be completed in
the form of a bar chart within 30 days from the date of award of the contract. The
overall schedule shall not exceed 250 days.
7.10 This Schedule will be scrutinized and approved by the department and shall be used
as a basic progress monitoring tool by the Contractor as well as by the Department.
7.11 The contractor shall agree to abide by the secrecy clause and the property right
clauses, which will be incorporated in the Contract. These clauses shall be applicable
to all the documents and other information related to this contract.
7.12 The contractor shall specify exclusively any support, service etc. to be provided by
the department during the site work. However, it may be noted that accommodation
and transportation will not be provided by the department.. Regarding the medical
facilities, the contractor shall make his own arrangements for the site personnel.
Department reserves the right to provide/not provide such supports.
7.13 Price Quotation:
The following guidelines along with the Clauses in Chapter 6.0 shall be taken as
Specification Document for PS2/GS2 Stages integration tower
38 | P a g e
mandatory requirements for price quotation.
7.14 The prices quoted shall be firm and fixed and applicable for the entire duration of the
contract.
7.15 As a Government of India Organisation, the Department is exempted from the
payment of octroi and similar local levies. The contractor shall ensure that necessary
exemption certificate is obtained by them from the department to avoid any payment
of such levies.
7.16 All amounts shall be indicated both in words as well as in figures. Where there is
difference between amount quoted in words and figures, amount quoted in words
shall prevail.
7.17 The quotation shall be submitted only in the Price Quotation format as in Form 2 in
annexure D.
Specification Document for PS2/GS2 Stages integration tower
39 | P a g e
Table Table Table Table 5 Schedule of activities5 Schedule of activities5 Schedule of activities5 Schedule of activities
S.No.S.No.S.No.S.No. Description of activitiesDescription of activitiesDescription of activitiesDescription of activities Estimated timeEstimated timeEstimated timeEstimated time
1 Submission of following documents to department
a. Detailed bar chart preparation
b. Design of connections
c. Preparation of fabrication drawings
d. Design of electro-mechanical systems
e. Preparation of Quality plan
f. Performance security deposit (Bank guarantee)
30 days
2 Approval of the above documents 15 days
3 Pre-fabrication
a. Procurement of materials
b. Pre-fabrication of structures at party’s site
75 days
4 Inspection, verification of test certificates & pre-dispatch
clearance by department
10 days
5 Receipt of raw materials & pre-fabricated structures at
IPRC site
15 days
AAAAtttt IPRCIPRCIPRCIPRC ::::----
6 Erection at IPRC 60 days
7 Load testing at IPRC 10 days
8 Painting 20 days
9 Commissioning & submission of execution reports 15 days
TOTALTOTALTOTALTOTAL 250 days250 days250 days250 days
8.0 Schedule of activities
8.1 The entire work is to be completed including erection & commissioning within
250 days 250 days 250 days 250 days from the date of acceptance of the purchase order and advance payment if
any.
8.2 Tentative schedule of activities shall be as follows:-
Specification Document for PS2/GS2 Stages integration tower
40 | P a g e
9.0 DOCUMENTATION REQUIREMENTS
9.1 The following are the records and documents to be prepared and/or supplied to the
Department at appropriate times for approval/information,
Note:
ETS-Expected Time of Submission of the document.
SSSSllll. No.. No.. No.. No. Document NameDocument NameDocument NameDocument Name DescriptionDescriptionDescriptionDescription
9.1.1 Bar chart
Schedule of all the activities involved in the contract.
ETS: Thirty days from the award of contract.
9.1.2 Design report-
Connections
A report on design of all the connections in the
structure.
ETS: Thirty days from the award of contract.
9.1.3 Quality plan Quality control and quality assurance plan for all
processes from procurement, pre-fabrication, erection,
testing, commissioning of the system, conforming to
relevant standards.
ETS: Thirty days from the award of contract.
9.1.4 Fabrication drawings Including electro-mechanical systems
ETS: Thirty days from the award of contract.
9.1.5 Erection plan Proposed method of erection, load testing and
commissioning at the Department’s site.
ETS: Before the start of erection process at the
department’s site.
9.1.6 Execution report Final execution report compiling all documents &reports
ETS: After commissioning.
9.1.7 RecordsRecordsRecordsRecords
a. Materials ETS: Shall be available at party’s site.
i Material specification List of all materials procured along with their
specification.
ii Mechanical test
certificates
Mechanical test certificates for relevant materials as per
the standard.
iii Mill test certificate Mill test certificate of the structural steel material.
iv Source of supply of
materials
<Self-explanatory>
b. Welding Procedure For all the welded joints as per the quality plan.
Specification Document for PS2/GS2 Stages integration tower
41 | P a g e
Specification ETS: To be submitted at the end of the job. (Subject to
verification at any time for a completed weld joint.)
c. Welder qualification
Certificate
<Self-explanatory>
ETS: Before welding at site.
d. Non conformances and
waivers
<Self-explanatory>
ETS: To be submitted at the end of the job.
e. Modifications and their
approvals.
Records pertaining to any modifications that are
mutually agreed upon.
ETS: To be submitted upon request.
f. Valid BIS certificate <Self -explanatory>
g. All Communications. <Self-explanatory>
9.2 Department’s review and approval is mandatory for the documents in Sl. No. 9.1.1 to
9.1.5.
9.3 Any other record pertaining to ensure the quality and conformance to the
specification, as in this document shall be provided to the Department by the
Contractor, on demand.
Specification Document for PS2/GS2 Stages integration tower
42 | P a g e
10.0 LIST OF REFERENCES
The reference standards are given below, The Contractor shall make sure to refer
the recent revisions of these standards,
CODECODECODECODE TITLETITLETITLETITLE
IS 800:2007 Code of practice for general construction in steel.
IS 808:1989 Dimensions for hot rolled steel beam, channel and angle sections.
IS 813:1986 Scheme of symbols for welding.
IS 814:1991 Specification for covered electrodes for manual metal arc welding of
carbon and carbon manganese steel.
IS 822:1970 Code of procedure for inspection of welds.
IS 1024:1979 Code of practice for use of welding in bridges and structures subjected to
dynamic loading.
IS 1363:1992
(Part 2 & 3)
Hexagon head bolts, screws and nuts of product grade C-screw (M5 to
M64)
IS 1363:1992
(Part 4)
Hexagon head bolts, screws and nuts of product grade A and B (M1.6 to
M64)
IS 1477-1971
Part 1
Part2
Code of practice for panting of ferrous metals in buildings.
Pretreatment
Painting
IS 2062:1992 Specification for steel for general structural purpose.
IS 3757:1985 Specification for high strength structural bolts.
IS 5872:1990 Specification for cold rolled steel strips.
IS 6623:1985 Specification for high strength structural nuts.
IS 6649:1985 Specifications for hardened tempered washers for high strength structural
nuts.
IS 7205:1974 Safety code for erection of structural steelwork.
IS 7215:1974 Tolerances for fabrication of steel structures.
IS 12843:1989 Tolerances for erection of steel structures.
Specification Document for PS2/GS2 Stages integration tower
43 | P a g e
11.0 LIST OF DRAWINGS
11.1. The list of all drawings and schematics attached with this document is given below,
11.2. The design drawing will give details about configuration, members sections and
approximate lengths of members of the structures. Details of the drawings are as
follows:
Specification Document for PS2/GS2 Stages integration tower
44 | P a g e
ANNEXUREANNEXUREANNEXUREANNEXURE (A)(A)(A)(A)
PREFFERED MARKING SYSTEM
1. Fabrication and Erection marking shall precisely follow the fabrication and erection
drawings.
2. The first letter of the mark shall be the prefix letter assigned to a particular
structure and noted as such on the general arrangement drawings. There shall be a
dash between the first and second letters of the mark.
‘S’-Stage support pedestal
‘P’-Platform
‘CS’ –Central staircase; ‘SC’ – Side staircase
3. The second letters of the mark shall indicate the type of structural framing in
accordance with the following:
‘B’
‘C’
‘D’
‘F’
‘G’
‘H’
‘K’
‘L’
‘M’
‘P’
‘R’
‘S’
‘T’
‘X’
for rolled Beams and Channels
for Column, Post or Strut
For vertical Bracings
For frames shipped in one piece
For sheeting rail
For hangers
For loose gussets
For ladders safety cages or lintels
For bolsters, shims and misc. materials
For floor plates plain, chequer or grill
For handrails and rail posts
For sag rods
For trusses
For horizontal bracing
4. Beam marks shall be painted on beams at the same end as they are shown on the
plan view of the Framing Plan. The numerical portion of the beam mark shall
identify the floor on tier thus: beam 1 to 199 on first or lowest tier, beams 200 to
299 on 2nd tier, 300 to 399 on third tier, etc.
5. All unsymmetrical beams, girders or trusses shall have a direction painted on one
end, preferably West or East.
6. All members to be marked "top" where possibility of erecting the member in an
inverted position exists.
7. All columns to have the mark painted on the outside face of the flange and marked
"west" or "east". Column marks shall carry a tier suffix for spliced columns.
8. Where a member is shipped in two or more pieces each piece shall have a different
mark.
9. All marks shall be painted on the steel in legible fashion, with letters and numbers a
minimum of 40 mm high.
Specification Document for PS2/GS2 Stages integration tower
45 | P a g e
ANNEXURE (B)
Form 1 : BIDDER’S PROFILE FORM
1. Name of the Company/ Organisation/
Firm.
2. Type of company
( Govt./Public Sector/ Private Sector)
3. Ownership details, if Private sector.
4. Is your company subsidiary to a larger
parent company? If so, whom?
5. Year of establishment
6. Primary Contact
Name
Title
Address
Phone (Office)
Mobile
Fax(Office)
7.
Alternate Contact
Name
Title
Address
Specification Document for PS2/GS2 Stages integration tower
46 | P a g e
Phone (Office)
Mobile
Fax(Office)
8. Whether Indian based company or
Foreign company with office in India?
9. Location of Offices in India
10. Location of Offices Worldwide.
11. What is your Company’s Primary
business?
12. Annual turnover for the last 3 financial
years.
(Attach documentary evidence in the
form of balance sheets, IT returns etc.,)
2012012012014444----15151515 2012012012013333----14141414 2012012012012222----13131313
13. Length of time the Company has been
doing Structural Fabrication, Erection
and commissioning.
14. No. of Employees(Permanent)
Total
Technical
Non-Technical
Structural Engineers
Mechanical
Engineers
Electrical Engineers
Fitters
Welders
Riggers
Unskilled Labours
Specification Document for PS2/GS2 Stages integration tower
47 | P a g e
15.
Details of Similar Structural jobs undertaken in past 7 years.
[Attach documentary evidence in the form of purchase order copies and completion
certificates ]
YearYearYearYear Details of the ProjectDetails of the ProjectDetails of the ProjectDetails of the Project Project CostProject CostProject CostProject Cost
Public
Sector
2015
2014
2013
2012
2011
2010
2009
Private
Sector
2015
2014
2013
2012
2011
2010
2009
16. Any other job undertaken, that you
would like to highlight.
[attach separate sheet if necessary]
17. List of Certifications obtained by the
Company.
Specification Document for PS2/GS2 Stages integration tower
48 | P a g e
18. List of major clients
19. List of major subcontractors
20. Any Other Information
Undertaking:Undertaking:Undertaking:Undertaking:
I …………………………………….. hereby certify that the information provided in this
vendor profile form is true to best of my knowledge.
SignatureSignatureSignatureSignature
Specification Document for PS2/GS2 Stages integration tower
49 | P a g e
ANNEXURE (C)
Table 6 : PREFERRED SUPPLIERS LIST
Sl. No.Sl. No.Sl. No.Sl. No. Item DescriptionItem DescriptionItem DescriptionItem Description Party’s Party’s Party’s Party’s ListListListList
1. Structural Steel SAIL, TISCO, JINDAL, VIZAG
2. Electrodes ADOR (Advani Oerlikon), D&H and ESAB
3. Paint BERGER, SHALIMAR, ASIAN, JENSON &
NICHOLSON, DULEX and POLYCOAT
5 Fasteners UNBRAKO, TVS
*Approval shall be obtained from the Department for any purchase made outside the
preferred suppliers list.
Specification Document for PS2/GS2 Stages integration tower
50 | P a g e
Form 2Form 2Form 2Form 2 : FORMAT FOR PRICE QUOTATION: FORMAT FOR PRICE QUOTATION: FORMAT FOR PRICE QUOTATION: FORMAT FOR PRICE QUOTATION
Sl.Sl.Sl.Sl.
NoNoNoNo DescriptionDescriptionDescriptionDescription QuantityQuantityQuantityQuantity UnitUnitUnitUnit
Rate INR/Unit Rate INR/Unit Rate INR/Unit Rate INR/Unit
QuantityQuantityQuantityQuantity Amount INRAmount INRAmount INRAmount INR Total Amount INRTotal Amount INRTotal Amount INRTotal Amount INR
PART APART APART APART A
1111 DESIGN OF CONNECTIONS, DOCUMENTATION AND DRAFTINGDESIGN OF CONNECTIONS, DOCUMENTATION AND DRAFTINGDESIGN OF CONNECTIONS, DOCUMENTATION AND DRAFTINGDESIGN OF CONNECTIONS, DOCUMENTATION AND DRAFTING
a. Design of connections
Lot
b. Preparation of drawings
Lot
c. Preparation of documents
Lot
TOTAL COSTTOTAL COSTTOTAL COSTTOTAL COST
PART PART PART PART BBBB
2222 FABRICATION, ERECTION AND COMMISSIONING OF STRUCTURAL STEEL WORKFABRICATION, ERECTION AND COMMISSIONING OF STRUCTURAL STEEL WORKFABRICATION, ERECTION AND COMMISSIONING OF STRUCTURAL STEEL WORKFABRICATION, ERECTION AND COMMISSIONING OF STRUCTURAL STEEL WORK
a.
Procurement of structural materials (including 10% allowance on estimated)
i. Structural steel
Kg
ii. Chequered plates
(Steel & Aluminium)
Kg
iii. Fasteners
Lot
b.
Procurement of other bought outs like motor,
gear boxes, wire ropes, rope-drum, limit
switches, control panel etc.,
Lot
c. Fabrication
Lot
ANNEXURE (D)
Specification Document for PS2/GS2 Stages integration tower
51 | P a g e
Form 2Form 2Form 2Form 2 : FORMAT FOR PRICE QUOTATION: FORMAT FOR PRICE QUOTATION: FORMAT FOR PRICE QUOTATION: FORMAT FOR PRICE QUOTATION
Sl.Sl.Sl.Sl.
NoNoNoNo DescriptionDescriptionDescriptionDescription QuantityQuantityQuantityQuantity UnitUnitUnitUnit
Rate INR/Unit Rate INR/Unit Rate INR/Unit Rate INR/Unit
QuantityQuantityQuantityQuantity Amount INRAmount INRAmount INRAmount INR Total Amount INRTotal Amount INRTotal Amount INRTotal Amount INR
d. Erection, Painting, Testing & Commissioning
Lot
TOTAL COSTTOTAL COSTTOTAL COSTTOTAL COST
PPPPART ART ART ART CCCC
3 Material transportation charges
4 Miscellaneous charges if any
5 Taxes and Levies
6 GRAND GRAND GRAND GRAND TOTAL COSTTOTAL COSTTOTAL COSTTOTAL COST
Validity of quotation (in days)Validity of quotation (in days)Validity of quotation (in days)Validity of quotation (in days)
Minimum Minimum Minimum Minimum 99990 days0 days0 days0 days
Note:Note:Note:Note: Though the quotation is made for individual items listed above, the order will be awarded on the basis of Grand total cost (Sl.No.6) of
format for quotation. The costs for all other works such as installation of hand rails, toe-stoppers etc., shall be included in Sl.No.2 (Part B)
ANNEXURE (D)