spectrometer solenoid design and procurement review steve virostek mike green mike zisman lawrence...
Post on 19-Dec-2015
216 views
TRANSCRIPT
Spectrometer Solenoid
Design and Procurement
Review
Steve VirostekMike Green
Mike ZismanLawrence Berkeley National Lab
MICE Collaboration Meeting October 10, 2006
Spectrometer Solenoid Design & Procurement
Page 2
S. Virostek, M. Green, M. Zisman - Lawrence Berkeley Lab
•Design review held by Wang NMR on Sept 6, 2006-Attendees: S. Virostek, M. Zisman, M. Green, D. Li-Complete design package book provided by Wang-Issues and actions items identified during review-Follow up document from Wang addresses issues
•Detailed magnet design is now complete
•Superconducting wire sent from LBNL to Wang
•Coil formers and high TC leads ordered by Wang
•First magnet scheduled to be shipped end Aug 07
Spectrometer Solenoid Update
Spectrometer Solenoid Design & Procurement
Page 3
S. Virostek, M. Green, M. Zisman - Lawrence Berkeley Lab
He Filler Neck
Lead Neck
Cold Mass Support
PMT Iron Shield
Space for Radiation Shield Support Stand
Cooler Neck
Spectrometer Solenoid Design & Procurement
Page 4
S. Virostek, M. Green, M. Zisman - Lawrence Berkeley Lab
Lead Neck
Gas Pipe
4.2 K Coolers
Condenser Tank
Liquid Pipe
Cold Mass
4K End
60K Intercept
300K End
Spectrometer Solenoid Design & Procurement
Page 5
S. Virostek, M. Green, M. Zisman - Lawrence Berkeley Lab
Magnet Coil Parameters
Parameter Match 1 Match 2 End 1 Center End 2Coil length (mm) 201.2 199.5 110.6 1314.3 110.6Coil inner radius (mm) 258 258 258 258 258Coil thickness (mm) 44.7 29.8 59.6 21.3 66.0Number of layers 42 28 56 20 62Number of turns per layer 120 119 66 784 66Coil overall current density (A mm Š2) 142.19 152.62 127.37 152.44 135.18Coil current I (A) 253.7 272.1 227.2 272.2 241.1Coil self inductance (H) 12.8 5.4 9.5* 41.4* 11.1*Coil Stored Energy at I (MJ) 0.41 0.20 0.25 1.53 0.32
Uniform Field Magnets
* The uniform field magnet coils in series have a self inductance of 77 H
Separately Powered
Coil package length = 2530 mm
-
Spectrometer Solenoid Design & Procurement
Page 6
S. Virostek, M. Green, M. Zisman - Lawrence Berkeley Lab
Magnet Coil Load Lines
10864200
100
200
300
400
500T = 3.4 KT = 4.2 KT = 5.0 KTracker M1Tracker M2Tracker E1Tracker CTracker E2
Magnet Peak B and Conductor B (T)
Mag
net
an
d C
ond
uct
or C
urr
ent
(A)
Spectrometer Solenoid Design & Procurement
Page 7
S. Virostek, M. Green, M. Zisman - Lawrence Berkeley Lab
•Indirect cooling using liquid helium condensers
•Baseline design will use two cryocoolers but will allow mounting of a third cooler, if necessary
•Cryocoolers and high TC leads will be accessible by means of removable cover plates
•60K (or less) thermal shield is conductively cooled using the first stage of the cryocoolers
•Thermal shield nitrogen reservoir will protect the high TC leads and provide extra cooling margin
Design Overview (coil cooling)
Spectrometer Solenoid Design & Procurement
Page 8
S. Virostek, M. Green, M. Zisman - Lawrence Berkeley Lab
•Single piece 6061-T6 aluminum coil former
•Each layer wet wound using Stycast 2850 FT
•2.5 mil thick fiberglass between winding layers
•Aluminum coil banding will provide hoop force support and ensure coils are tight after cooldown
•Conductor joints are to be lapped by at least 24” to minimize the I2R losses
•Passive quench protection will be provided by a system of diodes & resistors
Design Overview (coil construction)
Spectrometer Solenoid Design & Procurement
Page 9
S. Virostek, M. Green, M. Zisman - Lawrence Berkeley Lab
•Helium vessel (Al) and vacuum vessel (304SS) to be designed & tested according to PV code
•He vessel will contain two relief paths for safety
•Unidirectional S-2 fiberglass cold mass supports using race-track shaped links (safety factor of 4)
•304 SS support design derived from LBNL/Oxford
•Cold mass support design allows cold shipping
•TBD: lifting accommodations and base mounting
Design Overview (PV’s & supports)
Spectrometer Solenoid Design & Procurement
Page 10
S. Virostek, M. Green, M. Zisman - Lawrence Berkeley Lab
•Two cryocoolers are needed at Wang NMR by the end of Feb 2007 for installation into first magnet
•Two additional coolers needed one month later
•13 week lead time after placement of order
•Two coolers per magnet anticipated for operation
•Magnets designed to mount up to three coolers
•Two more coolers to be procured at a later date
•Short procurement spec to be done by M. Green
Cryocooler Procurement
Spectrometer Solenoid Design & Procurement
Page 11
S. Virostek, M. Green, M. Zisman - Lawrence Berkeley Lab
•First draft of power supply procurement spec is being reviewed by collaboration members
•Three 300 A and two 50 A supplies are needed for magnet operation and for testing @ FNAL
•One spare of each supply allows parallel testing of first (@FNAL) & second (@Wang) magnets
•Lead time to procure power supplies is 3 months
•First supply needed May 07 for testing at Wang
Power Supply Procurement
Spectrometer Solenoid Design & Procurement
Page 12
S. Virostek, M. Green, M. Zisman - Lawrence Berkeley Lab
•On-axis field profile and peak field on conductor
•Axial forces and axial magnetic pressure calcs
•Evaluation of fringe fields on leads & cryocoolers
•3-D magnet quench analyses (w/o Al bore tube)
•Heat leak calculations (thermal shield, He vessel)
•Calculation of cooldown cryogen requirements
•FEA stress analysis of coils and coil former
•ASME code calculations for He & vacuum vessels
Summary of Wang Analyses
Spectrometer Solenoid Design & Procurement
Page 13
S. Virostek, M. Green, M. Zisman - Lawrence Berkeley Lab
•Magnet Construction Quality Assurance Plan
•Fabrication/installation/inspection plans:-coil former, ground insulation, coil winding, coil banding-quench protection, conductor feed thrus, coil assembly
-He vessel, cold mass support, He recondenser, Hi-TC leads-thermal shield, vacuum vessel, support structure
•Winding instructions for each coil
•Project work breakdown structure and schedule
•Detailed component and assembly drawings
Other Project Documents
Spectrometer Solenoid Design & Procurement
Page 14
S. Virostek, M. Green, M. Zisman - Lawrence Berkeley Lab
Schedule Summary
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
Place Magnet Order with Wang NMR (LBNL)
Complete Magnet System Design
Write QC/QA Administration & Test Report
Procure & Deliver Superconductor to Wang (LBNL)
Conduct Magnet Design Review
Procure Coil Formers from Subcontractor
Write Spec and Procure High Tc Leads
Write Spec and Procure Cryocoolers (LBNL)
Write Spec and Procure Power Supplies (LBNL)
Wind Coils on Coil Formers
Assemble and Leak Check He Shell
Install Superinsulation and Cold Mass Supports
Install Hi-Tc Leads, Recondensers & Cryocoolers
Leak Checks, Cooldown & Acceptance Tests
Ship Magnets
Task Description2006 2007
Spectrometer Solenoid Design & Procurement
Page 15
S. Virostek, M. Green, M. Zisman - Lawrence Berkeley Lab
•Detailed magnet design is now complete
•Coil formers and high TC leads ordered
•Superconducting wire delivered to Wang
•Cryocooler order to be placed soon (~1 mo)
•Power supply spec is nearly complete
•First magnet to be shipped by end Aug 07
•Second magnet to follow 1 month later
Summary