spocc to spt 3-17-14
TRANSCRIPT
SPECIAL THANKS TO DAVE LEESTMA & JOEL WALKER
02-07-14
SUSTAINABILITY PARTNERSHIP TEAM
NASA
JOHNSON SPACE CENTER
SPOCC
T E A M
MEMBERS
BASE LEGS
COVER
80/20
STEEL
HURRICANE WINDS
SHADE
SOLAR PANEL
BACK END
MIKE EWERT TERRY TRI KIM REPPA MADDY GRUSECK LINDSAY McDOWALL GEORG BASTA
LYNNE BARENDS LINDSEY FOREMAN JAMES HOLT JODY MUNIZ KATHY PACKARD
LAURIE PETERSON IVAN RAMIREZ PENNEY STANCH JO AIKEN CARSON STANCH
HENRY WYNDON RUBEN ZAVALA JUSTIN CARTIER MIKE WABAUNSEE CARLO BOCATTO
BACKGROUND
• Sustainability Partnership Team project • 21 members have contributed in addition to their
other duties • First suggested as a “Solar Trees” team project
• Conceived in fall 2012 • Evolved into an outdoor meeting space with charging
capability • To promote sustainability, collaboration and
renewable energy at JSC • Future
• May add temporary displays or new technologies • Replicate if successful
PROGRESS
• Worked early concepts & developed conceptual design • Management go-ahead 7/2/13 • Refined design: NASA cupola theme
• Solar Powered Outdoor Collaboration Cupola (SPOCC) 7/22/13
• Built a prototype at the Sandbox 9/’13 – 2/’14 • Selected location 1/‘14 • Developed cost estimate 3/’14
DESIGN
DESIGN
13.2 ft 15.25 ft
7.5 ft
DESIGN
3.17 ft
FUN IN THE SANDBOX
THANK YOU TO
JAMES BROWN,
JUSTIN CARTIER!
PARTIAL PROTOTYPE
SHEET METAL VS FABRIC
• Prototype includes ½ sheet metal & ½ fabric covering frame so that we can compare
• Sheet metal advantages: looks more like space hardware, longer lasting
• Fabric advantages: lower cost if free fabric is available, potentially easier fabrication, but requires sewing
LOCATION
4S
3
BUDGET
ITEM Option 1 Option 2
Concrete Slab/Complete Job $10,000 – 25,000
(PAE) $TBD
Solar Panels $0 $0
Wiring/Misc. Parts $500 $500
Fans/Lighting $1,000 $1,000
Table and Chairs $1,200 Incl.
Data Collector/Display $800 $800
Frame $0 (80/20) Incl.
Brackets $6,000-20,000 N.A.
Design Cost $3,750 $TBD
Cover of Frame Sheet Metal
$2,000
Fabric
$300 w/ freebies
Incl.
Batteries $0 $0
TOTAL $25,250 - $49,250
OTHER CONSIDERATIONS
• Historic preservation • Maintenance – PAE • ADA compliant • Electrical
• Off-grid solar PV with batteries • Various charging ports
• Fan • Lights
RECOMMENDATIONS
• Fund design by PAE for welded steel frame option (TBR) • SPT/SPOCC team continues to develop electrical design
and data display system • Connect to Energy Dashboard
FORWARD WORK PLAN
Submit to Historical
Committee
Finalize Design
Funding Approval
Start Construction on Pad
SPOCC Team Adds Electrical
Collaborate And Enjoy!