sr 60/us 98 intersection improvements

15
SR 60/US 98 Intersection Improvements Presented to: Polk County Transportation Planning Organization Presented by: Florida Department of Transportation District 1 October 13, 2011

Upload: gabi

Post on 25-Feb-2016

33 views

Category:

Documents


2 download

DESCRIPTION

Presented to: Polk County Transportation Planning Organization Presented by: Florida Department of Transportation District 1 October 13, 2011. SR 60/US 98 Intersection Improvements. US 98 Improvement Projects. Projects 2, 4 & 5: Under Construction - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: SR 60/US 98 Intersection Improvements

SR 60/US 98 Intersection Improvements

Presented to:Polk County Transportation Planning Organization

Presented by:Florida Department of Transportation

District 1

October 13, 2011

Page 2: SR 60/US 98 Intersection Improvements

US 98 Improvement Projects• Projects 2, 4 & 5: Under Construction

• Project 3: Final Design & Right-of-Way Acquisition

• Project 1: SR 60/US 98 Intersection Improvements from SR 60 to Manor Drive & along SR 60 to US 17

Page 3: SR 60/US 98 Intersection Improvements

Project Limits• SR 60 from east of Richland Road to west of US 17• US 98 from SR 60 to south of Manor Drive

Page 4: SR 60/US 98 Intersection Improvements

Scope of Work• Intersection Improvements

• New turn lanes at three intersections

• Replace asphalt with concrete

• Bicycle Lanes

• New Sidewalks

• Improved signalization, drainage, lighting, landscaping & signage throughout project limits

Page 5: SR 60/US 98 Intersection Improvements

The existing asphalt pavement at the SR 60/US 98 intersection will be replaced with concrete in these areas:

• SR 60 (Van Fleet Drive) From West of US 98/ Broadway Avenue to east of Wilson Avenue

• US 98 just north of SR 60

Replace Asphalt with Concrete

Page 6: SR 60/US 98 Intersection Improvements

Turn Lane Improvements SR 60/US 98: • Triple left turns on SR 60 eastbound • Dual right turns on SR 60 westbound• Triple left turns on US 98 southbound• Dual left turns & new right turn on Broadway Avenue

KEY

= Existing Turn Lane= New Turn Lane

Page 7: SR 60/US 98 Intersection Improvements

Turn Lane Improvements SR 60/Wilson Avenue:• Extending right turn lanes through the intersection for both

eastbound & westbound on SR 60

KEY

= Existing Turn Lane= New Turn Lane

Page 8: SR 60/US 98 Intersection Improvements

Turn Lane Improvements SR 60/Wal-Mart Entrance: • Extending right turn lanes through the intersection for both

eastbound & westbound on SR 60

KEY

= Existing Turn Lane= New Turn Lane

Page 9: SR 60/US 98 Intersection Improvements

Sidewalks/Bicycle Lanes • New Sidewalks:

• Both sides of SR 60 (Van Fleet Drive) • East side of US 98 from SR 60 to south of Manor Drive

• Bicycle Lanes: • Along SR 60 & US 98

throughout project limits

KEY

New Sidewalk

Page 10: SR 60/US 98 Intersection Improvements

Construction Timeline

• Project Start Date • October 15, 2011

• Project Estimated Completion • Fall of 2013

Page 11: SR 60/US 98 Intersection Improvements

Lane Closures

• Permanent Lane Closures During Construction• Additional Evening & Weekend Temporary Lane

Closures

Page 12: SR 60/US 98 Intersection Improvements

Communications• RoadWatch Updates & Press Releases

• Fact Sheets & Fliers

• Website: www.idriveus98.com

• Public Meetings

• Business Visits

• Special Briefings

• Media Interviews

Photo Courtesy of the Ledger

Page 13: SR 60/US 98 Intersection Improvements

PROJECT TEAM

Florida Department of Transportation

Cone & Graham, Inc. (Contractor)

Genesis CEI Services, LLC (Project Administrator)

ICON Consultant Group, Inc. (Designer)

Project Team

Page 14: SR 60/US 98 Intersection Improvements

Public Information OfficerKen Nelson, APRPublic Information Officer

• Cell: 863-303-3209

• Office: 863-533-6800, Ext. 6

• E-Mail: [email protected]

• Website: www.idriveus98.com

Photo Courtesy of the Ledger

Page 15: SR 60/US 98 Intersection Improvements

SR 60/US 98 Intersection Improvements

Questions?