Page 1: SR522 / NE 145th and I-405 Bus Rapid Transit Projects

StrideSR522 / NE 145th and I-405

Bus Rapid Transit Projects

06/20/19

Citizen Oversight Panel

Page 2: SR522 / NE 145th and I-405 Bus Rapid Transit Projects

2

Today’s Presentation

Topics:

New line of service: Stride Overview of projects Project refinements Progress of key project elements Phase 2 consultant contracts Next steps

Page 3: SR522 / NE 145th and I-405 Bus Rapid Transit Projects

3

A New Line of Business Opens in 2024 Two Corridors (I-405 and SR 522/ NE 145th)

BRT Systems Elements of Success Transit speed, reliability and access

improvements BRT stations (signage, shelter, amenities) Parking facilities New BRT bus fleet Bus operations and maintenance facility Branding Rider information system

Page 4: SR522 / NE 145th and I-405 Bus Rapid Transit Projects

4

SubmarkGraphic Element

“BRT Wave”

Station Design Concept Color Palette

Sound Transit welcomes Bus Rapid Transit service

Stride

Golden Ticket Soft Teal Light Gray

Wave Blue White

Primary Colors

Secondary Colors

BRT – New Line of Service

Page 5: SR522 / NE 145th and I-405 Bus Rapid Transit Projects

5

Schedule

2018-2020

Project refinement (2018)

• Q1 2019 – Board advances refined project

Conceptual Engineering & Environmental Review (2019)

Preliminary engineering (2020)

PUBLIC INVOLVEMENT

2020-2023

• Final design of roadway improvements

• Final station designs and public art

• Obtain land use and construction permits

PUBLIC INVOLVEMENT

Begins 2023

• Groundbreaking

• Construction updates and mitigation

• Construction of roadway improvements, parking and stations.

PUBLIC INVOLVEMENT

*Construction for most of the BRT projects are expected to begin by 2023 and be completed by 2024. Construction of some elements may begin before 2023 and others may occur after service starts in 2024.

Page 6: SR522 / NE 145th and I-405 Bus Rapid Transit Projects

6

SR 522 / NE 145th BRT Project Overview 8,000-9,000 daily riders 8 miles, 6 cities Transit speed and reliability improvements:

• Business Access and Transit (BAT) lanes along SR 522

• Intersection improvements/queue jumps 12 Stations:

• 10 new station locations• Station at 145th LRT Station • Shared station at NE 195th with I-405 BRT

3 new parking facilities/access improvements

Page 7: SR522 / NE 145th and I-405 Bus Rapid Transit Projects

7

Project Refinements

Stations 12 station locations 3 provisional station

locations

Roadway & Access Improvements NE 145th: Bus queue bypass lanes and intersection improvements Lake Forest Park, SR 522: continuous BAT Lanes Bothell, SR 522: BAT lanes & intersection improvements Woodinville service: further study with King County Metro Sidewalks improved where roadway widened Every SR 522/145th BRT bus connects with I-405 BRT

Parking Garages Lake Forest Park Town Center Kenmore Park and Ride Pop Keeney Stadium (Bothell)

Page 8: SR522 / NE 145th and I-405 Bus Rapid Transit Projects

8

SR 522 Bothell BAT Lanes ConstructionGround breaking April 15, 2019

Photo by Kailan Manadic,Sound Publishing

Page 9: SR522 / NE 145th and I-405 Bus Rapid Transit Projects

9

Bothell BAT Lanes

Key features: Funding construction of

Business Access and Transit Lanes

SR 522 / NE 145th BRT component funded in ST3

Complete: Q4 2020

Start of BRT service: 2024

Page 10: SR522 / NE 145th and I-405 Bus Rapid Transit Projects

10

SR 522 / NE 145th BRT Phase 2David Evans & Associates scope of work: Conceptual Design

• Fieldwork, data collection and technical studies • Stakeholder involvement • Roadway, station area, and parking facilities designed to 10 percent

Environmental Review with SEPA Checklist• Expanded checklist process• Stakeholder involvement and sufficiency for cities’ SEPA needs

Page 11: SR522 / NE 145th and I-405 Bus Rapid Transit Projects

1111

• Using consistent methodology: 2018$; construction, real estate, etc.

• Based on limited design (1-2%): 2018$; updated construction figures, updated real estate, etc.

• Estimates do not establish project budget: Project budget established during final design

Preliminary Estimate

Page 12: SR522 / NE 145th and I-405 Bus Rapid Transit Projects

12

Preliminary Estimate10

5

2018

$ in

milli

ons

4

3

2

1

6

7

8

9

Refined ProjectST3 Representative Project

Estimates based on limited conceptual design to compare project elements. Project budget established during final design.

$732 million $619 million

Page 13: SR522 / NE 145th and I-405 Bus Rapid Transit Projects

1313

Preliminary EstimateKey Drivers Property Acquisition Construction/Design, market conditions:

• Structured parking construction• Bridge structures for stream crossings• System needs (rider information, etc)• BRT station refinements (e.g., double platforms)• Streetscaping

Page 14: SR522 / NE 145th and I-405 Bus Rapid Transit Projects

14

I-405 BRT Project37-mile corridor: Lynnwood to Burien Proposed refined project:

• 11 BRT stations across 8 cities• 3 new/expanded parking facilities• 1 transit center• Connections to Link light rail in

Lynnwood, Bellevue and Tukwila• Estimated 25,800 riders daily by 2040

Start of service in 2024

UW Bothell/Cascadia College

Page 15: SR522 / NE 145th and I-405 Bus Rapid Transit Projects

Proposed Project Refinements: North Line

I-405 BRT with I-405 ETL Project

Ref

ined

Prop

osed

% C

hang

e

AM peak travel time (SB) 55 33 -40%

PM peak travel time (NB) 45 29 -36%

Daily ridership 10,000 12,200 22%

Page 16: SR522 / NE 145th and I-405 Bus Rapid Transit Projects

16

I-405/NE 85th Street Interchange

Representative Project

Page 17: SR522 / NE 145th and I-405 Bus Rapid Transit Projects

17

I-405/NE 85th Street Interchange

Project Description: Construct a three-level interchange with inline BRT station, direct access ramps to ETLs, and local roadway improvements Fully funded by Sound Transit

Page 18: SR522 / NE 145th and I-405 Bus Rapid Transit Projects

18

I-405/NE 85th Street Interchange

Page 19: SR522 / NE 145th and I-405 Bus Rapid Transit Projects

19

Proposed Project Refinements: South Line Tukwila International

Boulevard BRT Station:• Non-motorized access

and improvements to Link Lightrail station

• Reduced highway and arterial widening

• Improved travel time and ridership

Page 20: SR522 / NE 145th and I-405 Bus Rapid Transit Projects

20

I-405/NE 44th Street Interchange

• WSDOT Renton to Bellevue Express Toll Lane Project• Signed (capped) funding agreement• BRT Station Pad• Pedestrian access and amenities for Park and Ride to stations• Sound Transit portion of direct access ramps

• 200 stall Park and Ride• Sound Transit to deliver• Sound Transit Board has authorized purchase

Page 21: SR522 / NE 145th and I-405 Bus Rapid Transit Projects

21

I-405 BRT travel times

AM peak hour travel times to Bellevue

* Preliminary travel time estimates for planning purposes, subject to change. Existing travel times are average times. Year 2025 estimates assume new express toll lanes are open between Renton to Bellevue. Updated information will be provided prior to beginning service.

Page 22: SR522 / NE 145th and I-405 Bus Rapid Transit Projects

22

Bus Base North Critical Path – Complete by 2023 for

vehicle fleet Screening of 30+ sites Representative site: Canyon Park,

Bothell Possession and use

Bus Base Representative project location

Page 23: SR522 / NE 145th and I-405 Bus Rapid Transit Projects

23

I-405 BRT Phase 2WSP USA, Inc. Scope of work: Conceptual Design

• Fieldwork, data collection and technical studies • Stakeholder involvement • Advance design for stations and other work (survey, geotech,

ROW)• Evaluate potential BRT vehicle Fleet

Environmental Review: Develop NEPA/SEPA documentation

Page 24: SR522 / NE 145th and I-405 Bus Rapid Transit Projects

24

Preliminary Estimate

Refined ProjectST3 Representative Project

Estimates based on limited conceptual design to compare project elements. Project budget established during final design.

$1,003 million 10

5

2018

$ in

milli

ons

4

3

2

1

6

7

8

9

11

$1038 million

Page 25: SR522 / NE 145th and I-405 Bus Rapid Transit Projects

Thank you.