stage 2 construction soil and water management sub plan€¦ · soil and water management sub plan...
TRANSCRIPT
Soil and Water Management Sub Plan
Seahampton to Kurri Kurri Section
HEA-PL-GL-SWP-001-00-03
Rev Date Prepared by Reviewed by Approved by Remarks
0 29th
March
2010
M Frankcombe T Doczy P Chatburn
1 13th
May
2010
M Frankcombe T Doczy P Chatburn Includes RTA
comments
2 10th
June
2010
J. Wright H. Chemney P. Chatburn Includes RTA, DI&I,
NSW OoW,
Councils & EMR
review comments
3 14th
July
2010
E. Woodward H. Chemney P. Chatburn Includes DoP
Comments
Hunter Expressway Alliance
SOIL AND WATER MANAGEMENT SUB PLAN
HEA-PL-GL-SWP-001-00-03 Page 2
DOCUMENT CONTROL
Document Type: Environmental Management Sub Plan Document No/Ref:
HEA-PL-GL-SWP-001-00-02
Title: Soil and Water Management Sub Plan
General
Description:
Provides management measures and mitigation strategies to be undertaken to mitigate the
potential impacts as they relate to pre-construction, construction, post-construction and
some elements (design) of the operational phase of the project.
Management of soil & water issues during the operational phase of the project will be
undertaken by RTA
Document Path: S:\HEA\01 Environment\01_08 CEMP\Volume 2\Soil & Water\For Final Submission\HEA-
PL-GL-SWP-001-00-02.doc
Approval Name Position Signed/Approved Date
Document
Editor / Author
John Wright Soil Conservationist /
Scientist
Review Howard Chemney Environment Manager
- Design
Alliance Project
Director
Peter Chatburn Project Director
Hunter Expressway Alliance
SOIL AND WATER MANAGEMENT SUB PLAN
HEA-PL-GL-SWP-001-00-03 Page 3
TABLE OF CONTENTS
1 INTRODUCTION ...........................................................................................................................5
1.1 Purpose and Scope .......................................................................................................................5
1.2 Objectives ......................................................................................................................................7
1.3 Water treatment methodology .......................................................................................................8
1.4 Environmental Constraints.............................................................................................................8
1.4.1 Climatic Conditions ................................................................................................................8
1.5 Rainfall Records and Patterns .......................................................................................................9
1.6 Rainfall Erosivity Factor .................................................................................................................9
1.6.1 Soil Types ........................................................................................................................... 10
1.7 Acid Sulphate Soils ..................................................................................................................... 12
1.8 Endangered Ecological Communities ......................................................................................... 12
1.9 Existing Waterways and/or Drainage Lines ................................................................................ 13
2 LEGISLATIVE REQUIREMENTS AND GUIDELINES .............................................................. 14
3 LIMITATIONS, CONSTRAINTS AND OPPORTUNITIES ......................................................... 16
4 PERFORMANCE CRITERIA...................................................................................................... 18
5 POTENTIAL SOURCES OF POLLUTANTS ............................................................................. 19
6 MANAGEMENT AND MITIGATION MEASURES ..................................................................... 20
6.1 Progressive erosion and sediment control plans ........................................................................ 20
6.2 Work Procedures ........................................................................................................................ 21
6.3 Environmental Construction Method Statement ......................................................................... 21
6.4 Training ....................................................................................................................................... 22
6.5 Soil Conservationist .................................................................................................................... 23
6.6 General Management and Mitigation Measures ........................................................................ 24
6.7 Design ......................................................................................................................................... 27
6.8 Access and Site Set Up .............................................................................................................. 31
6.9 Clearing....................................................................................................................................... 32
6.10 Earthworks .................................................................................................................................. 33
6.11 Drainage and Bridgeworks ......................................................................................................... 36
6.12 Paving and Vehicle Movement ................................................................................................... 40
6.13 Rehabilitation and Landscaping ................................................................................................. 42
7 INSPECTIONS ........................................................................................................................... 44
8 MONITORING AND REPORTING ............................................................................................. 46
9 CORRECTIVE ACTION ............................................................................................................. 48
Hunter Expressway Alliance
SOIL AND WATER MANAGEMENT SUB PLAN
HEA-PL-GL-SWP-001-00-03 Page 4
LIST OF TABLES
Table 1.1: Requirements of MCoA and where these have been addressed in the Sub Plan /other
documentation ......................................................................................................................................... 5
Table 1.2: Summary of Cessnock rainfall records................................................................................... 9
Table 1.3: Monthly % and Annual Rainfall Erosivity (R-factor) values for Newcastle City .................... 10
Table 1.4: Soil Types along the HEA alignment .................................................................................... 10
Table 2.1 : Relevant Legislation ............................................................................................................ 14
Table 3.1: Site constraints and opportunities ........................................................................................ 16
Table 5.1: Summary of potential sources of water pollution ................................................................. 19
Table 6.1 Management and Mitigation Measures ................................................................................ 24
Table 7.1: Inspection Requirements ...................................................................................................... 44
Table 8.1: Monitoring and Reporting Requirements ............................................................................. 46
APPENDICES
APPENDIX A – WATER QUALITY MONITORING WORK PROCEDURE
APPENDIX B – DEWATERING PROCEDURE
APPENDIX C – PROPOSED SEDIMENT BASINS
APPENDIX D – ACID SULFATE SOIL MANAGEMENT STRATEGY
APPENDIX E – AFFLUX PRELIMINARY IMPACT ASSESSMENT
APPENDIX F – LOCATION OF DRAINAGE STRICTURES, WATERWAYS AND WATER QUALITY
MONITORING LOCATIONS
Hunter Expressway Alliance
SOIL AND WATER MANAGEMENT SUB PLAN
HEA-PL-GL-SWP-001-00-03 Page 5
1 INTRODUCTION
1.1 Purpose and Scope
This Soil and Water Management Sub Plan forms part of the Construction Environmental Management Plan (CEMP) for the Hunter Expressway Alliance project (HEA).
This Sub Plan has been developed in response to condition numbers 87, 88, 89 and 93 of the Minister of Planning’s Conditions of Approval (MCoA) for the Hunter Expressway.
MCoA 87, 88, 89 and 93 stipulate the content of the Sub Plan although other MCoA’s also detail with soil and water issues, Refer to Table 1.1 below for details on the requirements of the MCoA and where these have been addressed in the Sub Plan or other documentation.
Table 1.1: Requirements of MCoA and where these have been addressed in the Sub Plan /other documentation
Requirement Where addressed
87. A detailed Soil and Water Management Sub Plan shall be prepared
in consultation with the DLWC, NSW Fisheries, and relevant Councils.
The Sub Plan shall be prepared in accordance with the Department of
Housing’s guideline Managing Urban Stormwater - Soils and Construction
and where appropriate, DLWC’s Constructed Wetlands Manual. The Sub
Plan shall be prepared prior to construction or operation. The section of
the Sub Plan dealing with construction impacts shall be submitted to the
EPA when applying for an Environment Protection Licence for the
construction phase.
This Sub Plan
88 The Soil and Water Management Sub Plan shall contain, but not be
limited to:
i. management of stormwater from the development on the quality of
surface and groundwater;
s.5 and s.6
ii. details of short and long term measures to be employed to minimise soil
erosion and the discharge of sediment to land and/or waters including the
locations of suitably sized sedimentation basins;
s.6 and App B and App. C
iii. management of the impacts of the development on watercourse
crossings including Wallis/Surveyors Creeks, South Maitland
Railway/Swamp Creek, Bishops Creek, and Black Creek;
S. 6.
Swamp Creek, Bishops Creek and
Black Creek are not impacted by the
Hunter Expressway Alliance and are
therefore not addressed in this
SWMP. Any impacts on these creeks
will be detailed in the Design &
Construction project documentation
iv. management of the impacts of Wallis/Surveyors Creeks, South
Maitland Railway/Swamp Creek, Bishops Creek, and Black Creek on the
development;
S. 6.
Swamp Creek, Bishops Creek and
Black Creek are not impacted by the
Hunter Expressway Alliance and are
therefore not addressed in this
SWMP. Any impacts on these creeks
will be detailed in the Design &
Hunter Expressway Alliance
SOIL AND WATER MANAGEMENT SUB PLAN
HEA-PL-GL-SWP-001-00-03 Page 6
Requirement Where addressed
Construction project documentation
v. identification of all potential sources of water pollution and a detailed
description of the remedial action to be taken or management systems to
be implemented to minimise discharges of these pollutants from all
sources within the subject site;
s.5 and s.6
App B
vi. detailed description of water quality monitoring to be undertaken during
the pre-construction, construction and operation stages of the proposal
including identification of locations where monitoring would be carried out;
s.7 , S. 8 and App A
vii. contingency plans for fuel and other spills. s.5. s.6 and ‘Refuelling and Liquid
Storage Protocol’ (HEA-WP-GL-
ENV-03-00-00) located in both the
Construction Environmental
Management Plan (HEA-PL-GL-
EMP-001-00-02) and the Hazard and
Risk Management Sub Plan (HEA-
PL-GL-HRP-001-00-02)
viii. a program for reporting on the effectiveness of the sediment and
erosion control system against performance goals.
Reporting shall be undertaken via
standard reporting requirements of
six monthly Construction Compliance
Reports and monthly Environmental
Performance Reports.
89. The Soil and Water Management Sub Plan shall also incorporate
detailed erosion and sedimentation controls including a strategy to
manage the extent of exposed ground surface during construction and
progressive site rehabilitation requirements (in accordance with Conditions
of Approval Nos. 97 and 114). The Sub Plan shall be prepared to the
satisfaction of DLWC and in consultation with the EPA and NSW Fisheries
and sufficient to address the technical requirements
s.6 Landscape Management Plan
(HEA-PL-GL-LP-001-00-00) and
Flora and Fauna Plan (HEA-PL-GL-
FFP-001-00-05)
90. The DLWC, or other appropriately qualified soil conservationist,
shall be consulted on a regular basis to undertake inspections of
temporary and permanent erosion and sedimentation control devices to
ensure that the most appropriate controls are being implemented and that
they are being maintained in an efficient condition at all times and meet
the requirements of any relevant approval/licence condition(s).
Requirement included in s 6.5 –
Table 6.1 and s7.
91. All water collected during construction which is likely to be
contaminated, shall be tested, treated, handled and disposed of so that it
does not pollute waters.
Requirement included in s 6.5 –
Table 6.1 and general principle
applied throughout document
92. Sediment basin(s) must be designed (stability, location, type, and
size), constructed, operated and maintained in accordance with the
guideline Managing Urban Stormwater - Soils and Construction, 3rd
edition, 1998, or its latest edition, produced by the NSW Department of
Housing unless otherwise approved by the EPA.
Sediment basins designed in
accordance with the “Blue Book”
Volume 2d and requirement reflected
in s 6.6-Table 6.1
93. The Soil and Water Management Sub Plan shall identify mitigation
measures proposed to be taken to address any:
i. afflux impacts from the roadway or structures associated with the
App E
Hunter Expressway Alliance
SOIL AND WATER MANAGEMENT SUB PLAN
HEA-PL-GL-SWP-001-00-03 Page 7
Requirement Where addressed
proposal eg. the proposed Wallis/Surveyors Creek crossing and impacts
upstream in the Buchanan area; and
ii. adverse impacts from the proposal as a result of losses to the Hunter
River floodplain storage areas for flood events above and including the 1%
Annual Exceedence Probability Event eg. the Wentworth and Dagworth
Swamps;
94. All stormwater drainage, erosion, sedimentation and water pollution
control systems and facilities of the proposal shall be located, designed,
constructed operated and maintained to meet the requirements of the
relevant authorities including the EPA and the DLWC. All facilities
including wetland filters, grass filter strips, gross pollutant traps and
sedimentation basins shall be inspected regularly and maintained in a
functional condition for the life of the project. Construction stage water
quality structures shall be maintained for a minimum of six months after
commissioning of the proposal or until revegetation has provided
groundcover to at least 70% of the exposed surface.
Requirements included in Table 6.1
95. The Proponent shall provide appropriate detention systems for
containment of spills and materials arising from accidents that are
consistent with the Proponent’s Code of Practice for Water Management –
Road Development and Management in consultation with the EPA.
Requirements included in s6.6-Table
6.1
96. The Proponent shall identify the most appropriate measures to
safeguard and/or mitigate impacts on the groundwater, or impacts arising
from any groundwater dewatering operations, in consultation with the
DLWC, prior to the commencement of construction. Measures may
include:
i. evaluation of aquifer characteristics including conductivity and salinity;
ii. identification of suitable sites for the disposal of saline groundwater from
dewatering activities; and
iii. installation of monitoring bores.
A groundwater monitoring and
management plan is currently being
developed for the project in
consultation with NSW OoW to
address the requirements of CoA 96.
This Sub Plan provides practical measures that will be implemented to minimise any detrimental impact on the surrounding environment resulting from soil erosion, sediment transport, and chemical spills during pre-construction, construction and post-construction phases of the project. Management of soil & water issues during the operational phase of the project will be undertaken by RTA
While this Sub Plan provides overall guidance and direction for the management of soil and water related issues a number of Work Method Statements and Environmental Construction Method Statements will be prepared to be used in site specific situations.
Management of soil & water issues during the operational phase of the project will be undertaken by RTA
1.2 Objectives
The objectives of the Soil and Water Management Sub Plan are to:
Hunter Expressway Alliance
SOIL AND WATER MANAGEMENT SUB PLAN
HEA-PL-GL-SWP-001-00-03 Page 8
• Minimise the impact of erosion and sedimentation from construction activities
associated with the Hunter Expressway;
• Ensure all sediment and erosion controls are implemented on site in accordance with
best practice environmental management as outlined in Department of Environment,
Climate Change and Water NSW“ Managing Urban Stormwater - Soils and
Construction, Volume 2D Main road construction” and the RTA’s “Guidelines for the
Control of Erosion and Sedimentation in Roadworks”;
• Ensure no accidental spills into nearby watercourses;
• Ensure necessary controls are implemented in key sensitive sites, such as DECCW
estate and EEC’s;
• Provide an organised, integrated systematic approach to effectively address erosion
and sedimentation and other water pollution issues during the project; and
• Provide staff with an increased level of understanding and awareness and assign
accountability of soil and water management issues.
1.3 Water treatment methodology
The aim of water quality treatment for the Hunter Expressway is to ensure that water quality objectives are achieved with minimum clearing and disruption to the existing environment and that natural habitats can be maintained in order to allow for minimum disruption to existing ecosystems.
Operational water quality treatment measures have been incorporated into the longitudinal drainage design. The preferred approach to operational water quality includes using a combination of treatment methods in the form of a treatment train. Stormwater treatment measures may include operational basins, buffer zones, vegetated swales, natural and constructed wetlands. The combination of treatment measures used will vary dependent on the receiving environment.
The receiving environment may vary between a watercourse or outlet located in an Endangered Ecological Community (EEC), non EEC area, Kurri Kurri Sand Swamp Wetlands (KSSW) or open space areas.
Basins will be be located in order to minimise environmental impacts including the impact of clearing of EEC and non EEC areas and KSSW areas. Therefore, wherever possible basins have been located out of environmentally sensitive areas.
In locations where there are environmental or corridor constraints the use of reduced or alternative solutions will be considered in order to minimise clearing impacts on sensitive areas. All options available shall be consulted on with the relevant Authorities.
It is intended to provide some level of treatment to all stormwater runoff from the main carriageway and F3 and Buchanan interchanges.
1.4 Environmental Constraints
1.4.1 Climatic Conditions
The Hunter Expressway extends approximately west to east over the Sugarloaf range onto the old Hunter river flood plain. The quality and reliability of climatic data for this area is dependent on the position of the weather stations to the Hunter Expressway construction site and length of
Hunter Expressway Alliance
SOIL AND WATER MANAGEMENT SUB PLAN
HEA-PL-GL-SWP-001-00-03 Page 9
time that the records have been collected over time.
1.5 Rainfall Records and Patterns
The climatic data records of Cessnock (Nulkaba) have been chosen to reflect the potential climatic conditions for the project site due to its proximity to the overall site and extent of available data (43 years). A summary of rainfall records is provided in Table 1.2 below.
Table 1.2: Summary of Cessnock rainfall records
Cessnock rainfall records for past 43 years (mm)
Summer - Autumn Winter - Spring
Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Year
Mean 70.2 87.3 102.1 87.0 57.0 53.3 57.3 32.0 37.4 43.5 58.4 69.7 754.3mm
Rain days
Mean 9.5 10.4 10.4 10.7 8.8 8.7 7.3 7.7 7.6 9.5 10.9 9.5 110.4
days
Note the table has been divided into Summer/Autumn & Winter/Spring
Summer /autumn period is the dominant rainfall period and is more reliable due to the dominance of easterly trade winds at this time of the year. It should be noted that summer thunderstorms (Southerly Busters) have an important bearing on rainfall intensity in this area. Their impact will be greater on the easterly side of the Sugarloaf Range affecting the Alliance component of the project more. Numerous storms are reasonably expected to cross over the Sugarloaf range at times impacting on the Alliance component of the project.
Winter /spring rainfall generally occurs during late winter and early spring and is less reliable.
The summer- autumn period has the highest probability for erosion during the thunderstorm season, compounded when areas are left bare of vegetation for prolonged periods.
1.6 Rainfall Erosivity Factor
The Rainfall Erosivity factor is a measure of the ability of “rainfall to cause erosion and is used in determining total potential soil runoff”, (referred as “R” in the Revised Universal Soil Loss Equitation RUSLE). The Rainfall Erosivity factor is used to determine the soil loss in tonnes per hectare over one year, and is used in calculations in relations in sizing sediment basins.
The project has a Rainfall Erosivity factor of 2,500 SI, this is approximately the mid range for the state of New South Wales, as written in the Blue Book.
Newcastle City is the closest location with detailed R-factor data and is detailed below in Table 1.3 below. Newcastle City is located approximately 17.4 Km from the eastern end of the project.
Hunter Expressway Alliance
SOIL AND WATER MANAGEMENT SUB PLAN
HEA-PL-GL-SWP-001-00-03 Page 10
Table 1.3: Monthly % and Annual Rainfall Erosivity (R-factor) values for Newcastle City
Monthly % & Annual Rainfall Erosivity (R-factor) values
Dec Jan Feb Mar Apr May
Jun Jul Aug Sep Oct Nov Yearly
R-value
% 8.8 9.9 12.9 10.7 8.9 7.9 6.0 4.7 5.1 5.6 5.8 8.8 3890
R-Values 342 385 501 536 416 345 307 233 183 198 218 225 3980
Ref IECA- Best Practice Erosion & Sediment control table B6 Nov 2008
This data along with rainfall patterns reinforces that the greatest erosion risk due to storm activity is during the summer/autumn season.
1.6.1 Soil Types
Soil types have been compiled from NSW Department of Land and Water Conservation Soil Landscape Sheets for Newcastle at a 1:100,000 scale and Singleton at a 1:250,000 scale. Soil types have been described in Table 1.4 below.
Table 1.4: Soil Types along the HEA alignment
Ch. Description Soil type Topography Soil characteristics Revegetation
implications
0 – 2600
Newcastle
interchange
to end of
viaducts
Killingworth
Undulating to
rolling hills on
sediments of
Newcastle
Coal
measures,
slopes 3 to
20%, with
steep gullies
and rocky
outcrops.
� Highly erodable podzolic
soils that are sodic and
dispersive (mainly subsoils),
especially when the shallow
topsoil is removed;
� High rates of runoff – soil
hydrologic group C/D;
� Topsoil classified as Fine
type, K-factor 0.027;
� Subsoil – bleached hard
setting sandy clay loam as a
Dispersive type, K-factor
0.036; and
� Subsoil - yellowish clay as a
Dispersive type, K-factor
0.036.
Revegetation on
these soils will
be problematic
due to their very
strong acidity,
low fertility and
hard setting
surfaces.
2600 –
3850
Blue Gum
creek through
to Skyline
Ridge
Stockrington Extremely
steep slopes
15 to 20%
slopes.
� Earthy loams (sandy to clay
sandy loams) sitting on
massive conglomerate and
coal seams;
� Medium rates of runoff –soil
hydrologic group B;
� Topsoil dark sandy loam,
classified as Fine type; K-
factor 0.015;
Revegetation on
these soils will
be problematic
due to its strong
acidity, low
fertility and hard
setting surfaces.
Hunter Expressway Alliance
SOIL AND WATER MANAGEMENT SUB PLAN
HEA-PL-GL-SWP-001-00-03 Page 11
Ch. Description Soil type Topography Soil characteristics Revegetation
implications
� Subsoil – bleached gravelly
sandy clay loam Cause/Fine
type; K-factor 0.039; and
� Subsoil – bleached gravelly
sandy clay Dispersion type;
K-factor 0.039.
3850 –
7000 Killingworth See above. � See above See above
7000 –
10000
Buchanan
interchange
Beresfield Undulating to
flat country
with slopes 3
to 15% though
in this area
mainly on the
low side.
� Soils are deep with sandy to
silty topsoil on top of highly
erodible subsoils that have
a high foundation hazard
due to shrink- swell potential
as well as areas of
dispersive sodic soils;
� Medium to high rates of
runoff- soil hydrological
group C;
� Topsoil dark loam, classified
as Dispersive type; K-factor
0.028;
� Topsoil hard setting
yellowish brown sandy loam
topsoil classified as a
Dispersive type; K-factor
0.048;
� Subsoil mottled clay
classified as Fine type; K-
factor 0.018; and
� Subsoil dull yellow orange
puggy silty clay classified as
Dispersive type; K-factor
0.048 highly erodible.
Revegetation on
these soils will
be problematic
one the topsoil is
lost due to their
very strong
acidity, low
fertility, potential
high soil salinity
and hard setting
surfaces.
10000 –
11500
Buchanan
floodplain Wallis Creek
Old hunter
river flood
plain with
slopes less
than 3%
� Soils are characterised by
deep alluvial soils made up
of either brownish to black
clay loam topsoils rich in
organic matter loose sandy
loam sitting on a clayey
sandy subsoil;
� Medium to high rates of
runoff –soil hydrologic group
B/C;
� Topsoil dark
greasy(organic) clay loam ,
classified as Fine K-factor
0.029;
Unknown
Hunter Expressway Alliance
SOIL AND WATER MANAGEMENT SUB PLAN
HEA-PL-GL-SWP-001-00-03 Page 12
Ch. Description Soil type Topography Soil characteristics Revegetation
implications
� Topsoil brown loose sandy
loam, classified as Fine; K-
factor 0.042; and
� Subsoil pale loose clayey
sand to loamy sand.
Classified as Fine; K-factor
0.032.
11500 –
13200
Averys Lane
to east of
Stanford
Road
Heddon Greta Gently sloping
land between
2 to 10%
slopes.
� Soils prone to both wind and
water erosion as they are
old shallow wind blown
sands layered over bed
rock;
� Medium to high rates of
runoff – soil hydrologic
grouping B/C;
� Topsoil dark loose loamy
sand classified as Fine, K-
factor 0.016 (high wind
erosion potential);
� Topsoil greyish loose to
clayey sand classified as
fine, K- factor 0.031;
� Subsoil yellowish mottled
sandy clay, classified as
Fine; K-factor 0.024; and
� Subsoil radish mottled clay,
classified as Dispersive; K-
factor 0.026.
Revegetation on
these soils will
be problematic
one the topsoil is
lost due to their
very strong
acidity, low
fertility, potential
high soil salinity
and hard setting
surfaces.
1.7 Acid Sulphate Soils
Investigations undertaken to date indicate a low probability of acid sulphate soils being found along the Alliance section of works with only the floodplain west of the Buchanan Interchange (specifically the Wallis Creek area) having a small potential of acid sulphate soils being present or intercepted by the works.
Acid sulphate soil risk areas will be identified on Project area sensitivity mapping and details included within the relevant Environmental Construction Method Statements.
Please refer to Appendix D for the Acid Sulfate Soil Management Strategy.
1.8 Endangered Ecological Communities
The Hunter Expressway runs through a series of Endangered Ecological Communities (EEC) including:
• Coastal Plains Smooth-barked Apple Woodlands;
• Alluvial Tall Moist Forest;
Hunter Expressway Alliance
SOIL AND WATER MANAGEMENT SUB PLAN
HEA-PL-GL-SWP-001-00-03 Page 13
• Coastal Foothill Spotted gum – Iron Bark Forest;
• Kurri Sand Swamp Woodland EEC;
• Lower Hunter Spotted Gum-Ironbark Forest EEC; and
• Hunter Lowlands Redgum Forest EEC.
The HEA allocated vegetation clearing footprint of 63ha (MCoA60) and presence of endangered ecological communities will limit available locations for erosion and sediment controls such as construction sediment basins outside the footprint of the road alignment. Alternative erosion and sediment controls will need to be implemented in some location to reduce the clearing footprint of the project.
1.9 Existing Waterways and/or Drainage Lines
Approximately 37 cross-drainage structures and 9 bridge structures (see Appendix F for details) will be constructed for the Hunter Expressway. There are five main creeks associated with the alignment:
• Minmi Creek;
• Blue Gum Creek;
• Surveyors Creek;
• Wallis Creek; and
• Fishery Creek.
There has been limited water quality monitoring to date. As to be expected due to the soil types along the alignment and existing disturbance associated with past mining activities, fire trails and motorcycle tracks, turbidity and suspended solids are elevated during periods of rainfall causing runoff.
There will be erosion and sediment controls in place at all waterways to maintain the separation of clean and dirty (site) water. All waterways will be flagged as potential sensitive areas of native flora and fauna habitat and will be appropriately managed to minimise impact on the waterways.
Hunter Expressway Alliance
SOIL AND WATER MANAGEMENT SUB PLAN
HEA-PL-GL-SWP-001-00-03 Page 14
2 LEGISLATIVE REQUIREMENTS AND GUIDELINES
Key legislation and guidelines for soil and water are listed in Table 2.1 below.
Table 2.1 : Relevant Legislation
Relevant key legislation and
guidelines Application to project
Protection of the Environment
Operations Act 1997.
This Act provides for the control of polluting activities in NSW in order to
prevent pollution of the environment. Offences exist in relation to activities
that cause water, soil and air pollution. It is administered by the Department
of Environment, Climate Change and Water (DECCW).
The POEO Act contains a core list of activities (Scheduled Activity) that
require a licence. These are listed in Schedule 1 of the Act. Road
construction is a Scheduled Activity (35 Road Construction) and an
application for an Environmental Protection Licence will be submitted to
DECCW. Soil, water and air pollution associated with generation, handling
and disposal of waste are controlled through the CEMP and this Sub Plan.
Fisheries Management Act 1994. The Act provides a comprehensive framework for the sustainable
management of living aquatic resources.
Under the Act, a permit is required for any activity associated with main
roads that involves dredging or reclamation works, or that has the potential
to:
� Block the passage of fish (e.g. road crossings); and
� Harm marine vegetation.
Managing Urban Stormwater – Soils
and Construction Landcom 1998.
Provides guidance on erosion control measures to be implemented during
land development activities.
Managing Urban Stormwater – Soil
and Construction, Volume 2D –
Main road construction. Department
of Environment, Climate Change
and Water 2008.
Provides specific guidance on erosion and sediment control strategies for
main road construction.
Managing Urban Stormwater – Soil
and Construction, Volume 2C –
Unsealed Roads. Department of
Environment, Climate Change and
Water 2008.
Provides specific guidance on erosion and sediment control for unsealed
road which will be applied for geotechnical and construction access tracks
along the alignment.
Australia and New Zealand
Environment and Conservation
Council (ANZECC) and Agriculture
and Resource Management Council
of Australia and New Zealand.
(ARMCANZ): Australian and New
Zealand Guidelines for Fresh and
Marine Water Quality, 2000.
Provide objectives and guidelines to protect and improve water resources
and water quality. The guidelines are not mandatory. Applies to any water
that may be affected by construction activities such as sediment laden run-
off and/or chemical spills.
Hunter Expressway Alliance
SOIL AND WATER MANAGEMENT SUB PLAN
HEA-PL-GL-SWP-001-00-03 Page 15
Relevant key legislation and
guidelines Application to project
RTA Code of Practice for Water
Management (Road Development
and Management), 1999.
Provides the principles of water management that the RTA is committed to
following in the planning, construction and maintenance works that are
carried out at various stages of a road’s life.
RTA Erosion and Sedimentation
Risk Assessment Procedure, 2006.
Provides a process to identify RTA projects with a high risk of erosion and
sediment control impact and ensures that appropriate expertise and design
is provided to mitigate the identified risks.
Managing Urban Stormwater – Soil
and Construction, Volume 2A –
Instillation of Services, Department
of Environment Climate Change and
Water, 2008
Provides specific guidelines on erosion & sedimentation control strategies
for the instillation of services
Hunter Expressway Alliance
SOIL AND WATER MANAGEMENT SUB PLAN
HEA-PL-GL-SWP-001-00-03 Page 16
3 LIMITATIONS, CONSTRAINTS AND OPPORTUNITIES
The presence of Endangered Regional Ecosystems that need to be protected and highly erosive soils present significant challenges in achieving effective soil and water management on site. A constraints and opportunities analysis of these aspects is provided in Table 3.1 below to identify these issues and assist in the development of mitigation measures provided in section 6.
Table 3.1: Site constraints and opportunities
Issue Sub-issue Constraints Opportunities
Clearing of native
vegetation limited
to 63ha.
Insufficient room to install
sufficient number of
construction sediment basins.
Difficulties in achieving EPL
limits and protect water
quality and creek systems
from impact in locations
where it is not
possible/feasible to install
construction basins.
Use of 2 day basins and
intensive flocculation with
faster acting flocculants .
Improve source control of
erosion and sediment to limit
reliance on basins.
Rapid and progressive
stabilisation of disturbed
areas to reduce the size of
basins including providing
benches in designs to allow
the progressive stabilisation
of benches as they come
down in cuts and as they
come up in fills.
Use of temporary basins that
may be positioned partially
within the construction
footprint for use in the initial
stages of earthworks.
Install diversion/cut-off
drains to divert clean flows
away from all cleared areas
Insufficient room to install
sufficient number of
operational spill and water
quality basins.
Operational water quality
targets for the protection of
creek systems may not be
achieved. Not all creek
catchments will be able to be
protected from spills.
Prioritise operational basin
location based on spill risk.
Insufficient area to construct
basin access tracks to treat
and maintain basins.
Inability to achieve water
quality targets and maintain
basin capacity.
Use automated flocculent
dosing using the “New
Zealand” flocculent sheds or
some other means of
automated dosing to limit
access requirements (during
construction).
Improve source control of
erosion and sediment to limit
Hunter Expressway Alliance
SOIL AND WATER MANAGEMENT SUB PLAN
HEA-PL-GL-SWP-001-00-03 Page 17
Issue Sub-issue Constraints Opportunities
reliance on basins.
Insufficient room to construct
adequate drain inlet and
outlet protection works and to
adequately protect creek
diversions from erosion.
Erosion downstream of
outlets and within creek
diversions.
Utilise bridges, arches etc to
minimise requirement for
creek diversions. Use of
natural channel design
techniques to reduce the
footprint of erosion
protection works.
Insufficient area to stockpiled
stripped site topsoil.
Topsoils stockpiles will be
higher and steeper resulting
in faster decline in the
biological viability of seeds
and soil micro fauna.
Utilise degraded fire trails for
topsoil stockpiles.
Direct place topsoil for
rehabilitation purposes.
Insufficient area to allow the
upgrade of existing fire trails
for geotechnical drilling, mine
grouting and construction
access.
Access may be limited during
periods of wet weather
resulting in construction
delays. The type of
machinery/trucks that can
use the trails may be limited
resulting in construction
delays and increased costs.
Work with NPWS to
determine fire trail upgrading
requirements/planning so
that Hunter Ex access tracks
upgrading achieves NPWS’s
needs and can be removed
from the disturbance
footprint.
Site soils. Soils are highly erosive and
dispersive.
Chemical amendment of soils
necessary to reduce erosion
risk and to allow vegetation
establishment.
Rapid and progressive
stabilisation required.
All drains with flow velocities
greater than 0.3m/s will need
to be lined.
Sediment basins and
flocculation is necessary to
achieve EPL water quality
limits.
Modification of RTA
standard specifications to
address requirements.
The use of aluminium
flocculants to improve basin
and water treatment
performance (risk
assessment of negative
effects to be clarified before
consideration) .
Dedicated trained and
experienced sediment basin
management team.
Topsoil quality and volume. Topsoil likely to be of poor
quality for revegetation
purposes particularly
following stockpiling for more
than 3 months. Topsoil likely
to require chemical and
organic amendment.
Topsoil may be amended or
replaced by compost
generated from site tub
ground mulch or imported
from local suppliers
providing improved
revegetation and erosion
outcomes.
Hunter Expressway Alliance
SOIL AND WATER MANAGEMENT SUB PLAN
HEA-PL-GL-SWP-001-00-03 Page 18
4 PERFORMANCE CRITERIA
The performance criteria for the Soil and Water Management Sub Plan are to:
• Ensure that there are no pollution incidents causing environmental harm;
• Avoid pollution incidents and/or erosion and sedimentation impacts in key sensitive sites
such as Endangered Ecological Communities;
• Maintain background water quality levels in surrounding waterways.
• Control the impact of erosion and sedimentation from earthworks and other construction
activities by implementing effective erosion and sedimentation control measures;
• Prevent pollution by containing all fuel and other chemical spills and by implementing
effective control measure;
• Ensure effective communication is maintained with statutory authorities and all statutory
requirements are carried out to control impacts on the environment and prevent
pollution.
Hunter Expressway Alliance
SOIL AND WATER MANAGEMENT SUB PLAN
HEA-PL-GL-SWP-001-00-03 Page 19
5 POTENTIAL SOURCES OF POLLUTANTS
The potential sources of water pollutants are largely standard for the majority of large scale road construction projects and these are listed in Table 5.1 below. The only non-standard water pollution source considered likely for HEA is the coal mine goaf filling works whereby various mixes of fly-ash grout are pumped into the mining voids to provide structural stability for bridge foundations. The main sources of pollution are fly-ash slurries from the batching and pumping works and mine water if dewatering of the goaf is required. Initial investigations indicate that the mining voids are dry and no dewatering will be required.
Mitigation techniques are provided in Section 6.
Table 5.1: Summary of potential sources of water pollution
Activity Potential Pollution Sources
Geotechnical investigations / drilling
Sediment
Turbidity
Hydrocarbons
Operation of construction compounds and batching plants
Sediment
Turbidity
Concrete slurries
Fly-ash slurries
Clearing
Sediment
Turbidity
Hydrocarbons
Mulching of vegetation Tannins
Hydrocarbons
Soil stripping and stockpiling
Sediment
Turbidity
Hydrocarbons
Construction earthworks Sediment
Turbidity
Hydrocarbons
Bridgeworks and paving
Concrete slurries
Fly-ash slurries
Curing compounds
Hydrocarbons
Acidic mine water
Saline mine water
Operation Hydrocarbons
Heavy metals
Chemicals
Nutrients
Rubber
Hunter Expressway Alliance
SOIL AND WATER MANAGEMENT SUB PLAN
HEA-PL-GL-SWP-001-00-03 Page 20
6 MANAGEMENT AND MITIGATION MEASURES
A range of soil and water management and mitigation measures will be implemented during all phases of the road project with a strong emphasis on the construction phase where land disturbance will be greatest.
As land disturbing activities occur, specific soil and water management measures will be planned and implemented throughout the phases of the project to:
• Divert clean water flows
• Minimise erosion;
• Retain sediment at the source;
• Treat sediment laden run-off; and
• Manage the discharge of run-off from site.
• Rehabilitate disturbed areas as soon as possible
6.1 Progressive erosion and sediment control plans
Erosion and sediment control measures will be designed prior to disturbance, or as site conditions dictate, during a change in site layout, and documented in Progressive Erosion and Sediment Control Plans (PESCP). These may be specific to a site, a sub-site, sub-catchment or individual component of the work. For example:
• Clearing, grubbing and removal of topsoil
• Earthworks
• The installation of a culvert or major drainage structure clearing adjacent to a waterway;
• Bridge sites;
• Compound;
• Environmentally sensitive areas e.g. adjacent to an endangered ecological community;
• Waterway crossings;
• In-stream platforms;
• Creek bank stability works; and
• Work occurring in areas with a high erosion hazard.
PESCPs will include but not be limited to:
• Contours and clean and dirty water drainage paths;
• Limit of disturbance;
• Location and type of control measures;
• Order of works schedule; and
• Specific construction details.
PESCP’s will be developed by construction staff trained and mentored on production of PESCP’s.
Hunter Expressway Alliance
SOIL AND WATER MANAGEMENT SUB PLAN
HEA-PL-GL-SWP-001-00-03 Page 21
Training on the preparation of PESCP’s will be undertaken by the Soil Conservationist.
PESCPs will be presented as a series of drawings (based on construction plans) and will be reviewed and approved by the Environmental Manager (or delegate) and the Alliance Soil Conservationist.
PESCP’s will be prepared prior to any land disturbing activities and will be part of the documentation included on the Ground Disturbance Permit.
6.2 Work Procedures
Work Procedures will be prepared for all activities to ensure sound construction practices are implemented and to minimise the risk of environmental and safety incidents, quality non-conformances or system failures.
The Section Managers, Construction Field Manager and the Environment Manager (or delegates) will develop Work Procedures to ensure suitability and adequacy of meeting specified contract and CEMP requirements. The following work procedure relevant to the prevention of water pollution that are likely to be developed but are not limited to:
• pipe culverts
• drainage structures
• open drains
• kerb and/or gutter
• precast concrete box culverts
• earthworks excavation
• embankment and select
• rock fill embankment
• rock fill gabions and mattresses
• placing concrete in sub base
• placing concrete in base
• excavation and backfill for bridges
• concrete works for bridges
• paving operations, application of curing and bitumen compounds to pavements, saw-
cutting, equipment washout.
• selection of stockpiles
6.3 Environmental Construction Method Statement
In addition to activity specific Work Procedures, Environmental Construction Method Statements (ECMS) shall be prepared for specific activities. These activities shall be determined in conjunction with the EMR. ECMSs shall require the certification of the EMR as being in accordance with the Conditions of Approval and all undertakings made in the EIS and Representations Report.
All ECM’s and Work Procedures will require the development of a PESCP.
Hunter Expressway Alliance
SOIL AND WATER MANAGEMENT SUB PLAN
HEA-PL-GL-SWP-001-00-03 Page 22
Activities that will be covered by ECMS’s are presented in a Matrix in Appendix H of the CEMP Volume 1.
ECMS’s for bridges and works in waterways will be developed in accordance with Alliance Specification G39. Particular issues that will be addressed in the ECMS will include:
• Quick installation of culverts to ensure that transverse drainage is in place during the
early stages of construction;
• Where possible, quick installation of wing walls will be undertaken so that waterway
erosion and sediment impacts are minimised; and
• Working platforms shall be avoided where possible. If a working platform cannot be
avoided then it shall be well designed. Any temporary work platforms constructed within
the creeks for bridge construction purposes will consist of clean rock fill, ensuring that
the potential for erosion is minimised.
6.4 Training
All employees, contractors and utility staff working on site will undergo environmental training in relation to:
• Legal requirements and due diligence;
• Alliance specific erosion and sediment control drivers;
• Erosion;
• Sedimentation;
• Chemical pollution controls;
• Pollution and water quality;
• Emergency response; and
• Spill kits and their use
Key staff will undertake more comprehensive training relevant to their position and/or responsibility including those:
• Responsible for design, installation and maintenance of erosion and sedimentation
controls;
• Involved in the preparation of PESCPs;
• Involved in the treatment and release sediment basins;
• Responsible for the maintenance of chemical and fuel storage areas; and
• Track and trail construction and maintenance.
This training may be provided as ‘toolbox’ training or at a more advanced level by the Environment Manager and/or Alliance Soil Conservationist.
Records will be kept of all personnel undertaking the site induction and training, including the contents of the training, date and name of trainer/s.
Hunter Expressway Alliance
SOIL AND WATER MANAGEMENT SUB PLAN
HEA-PL-GL-SWP-001-00-03 Page 23
6.5 Soil Conservationist
The soil conservationist engaged for the HEA project is John Wright from TREES PTY LTD.
Prior to starting up his own company John was the recognised expert within the D.L.W.C. on soil conservation issues relevant to road construction which is still his area of speciality.
Johns soil conservation advice and services are extensively used by all the main road contractors in NSW.
Johns CV can be found at the following address: http://www.treespl.com/staff_john.htm
In addition Mike Murphy (Certified Professional in Erosion & Sediment Control No. 2389) will be undertaking RTA Peer Review of all soil conservation issues on the HEA project.
This Soil & Water Management Sub Plan was initially prepared by Michael Francombe (Soil Conservationist for Parsons Brinkerhoff and now with KMH Environmental).
Amendments to the Sub Plan as a result of comments received via Agency and Council consultation have been incorporated by John Wright.
Hunter Expressway Alliance
SOIL AND WATER MANAGEMENT SUB PLAN
HEA-PL-GL-SWP-001-00-03_Soil & Water_Final Page 24
6.6 General Management and Mitigation Measures
Table 6.1 – Management and Mitigation Measures
Management and mitigation measures Responsibility Source of Requirement Timing
General
This Soil and Water Management Sub Plan shall be prepared in
consultation with the DLWC (now DECCW), NSW Fisheries (now
I&I NSW), and relevant Councils. Environmental Manager MCoA87 Prior to construction
This Soil and Water Management Sub Plan shall be certified by the
EMR and approved by the Director General of Planning. Environmental Manager MCoA 21 and MCoA 26 Prior to construction
This Soil and Water Management Sub Plan has been prepared in
accordance with Managing Urban Stormwater and Alliance
Specification G39. Environmental Manager MCoA87 N/A
A Soil Conservationist has been employed on the project to
undertake inspections and provide advice on erosion and sediment
control measures and certify Progressive Erosion and Sediment
Control Plans (PESCP).
The soil conservationist will ensure that the most appropriate
controls are being implemented and that they are being maintained
in an efficient condition at all times and meet the requirements of
any relevant approval/licence condition(s)
Environmental Manager MCoA90 Pre-construction and
construction phases
All stormwater drainage, erosion, sedimentation and water pollution
control systems and facilities will be located, designed, constructed
operated and maintained to meet the requirements of the relevant
authorities including the EPA and the NSW OoW
Design Manager / Senior Project
Engineer/Superintendent MCoA 94
Pre-construction,
construction and post-
construction phases
All water collected during construction which is likely to be
contaminated, shall be tested, treated, handled and disposed of so
that it does not pollute waters.
Senior Project Engineer/Superintendent
MCoA 91 construction phase
Hunter Expressway Alliance
SOIL AND WATER MANAGEMENT SUB PLAN
HEA-PL-GL-SWP-001-00-03 Page 25
Management and mitigation measures Responsibility Source of Requirement Timing
Weather forecasts shall be used to guide work activities undertaken
onsite.
Weather forecasts to be checked at the start of each day and prior
to undertaking a new work activity. If rain is imminent, do not
undertake works that may have environmental risk.
Where weather forecasts predict weather conditions which may
pose an environmental risk - site environmental controls will be
checked inspected and secured to reduce erosion and sediment
control impacts as necessary.
Works that may lead to erosion and sedimentation shall not be
scheduled prior to forecasted rainfall events.
Construction Manager / Superintendent
Pre-construction and
construction phases
Bulk hydrocarbons and chemicals will be stored in covered bunded
areas and/or self bunded tanks will be utilised;
Small quantities of hydrocarbons and chemicals will be stored on
bunded pallets;
Refuelling and servicing of plant and equipment will be undertaken
away from sensitive areas;
Hydrocarbon and chemical spill kits will be provided as appropriate
and relevant personnel will be trained in their use;
Maintain spill kits on-site near storage areas and equipment;
Plant and equipped will be maintained in accordance with OEM
requirements to minimise the risk of breakdown and spills; and
All hydrocarbon and chemical spills will be reported, cleaned up and
any contaminated waste will be disposed of lawfully.
Project Manager/ Environment Manager MCoA118 Pre-construction and
construction phases
Sediment basins will be treated with flocculants to facilitate the
settlement of suspended solids as required. The type of flocculent
will be dependent on the soil type, necessary treatment time,
downstream receiving environment and flocculent application
technique.
Flocculent type will also conform to EPL requirement re eco-toxicity
(upon receipt)
Construction Manager & Environment
Manager Construction Phase
Hunter Expressway Alliance
SOIL AND WATER MANAGEMENT SUB PLAN
HEA-PL-GL-SWP-001-00-03 Page 26
Management and mitigation measures Responsibility Source of Requirement Timing
Sedimentation basins will be cleaned out on a regular basis as
necessary to ensure the build up of sediment is removed.
No more than 1/3 of the basin capacity in sediment will be allowed
to accumulate before cleaning out is required.
Depth of sediment will be determined either by use of a dip stick or
the installation of a marker post denoting the sediment line
Senior Project Engineer/Superintendent Construction Phase
Rapid stabilisation and rehabilitation of all disturbed areas Senior Project Engineer/Superintendent Construction Phase
Hunter Expressway Alliance
SOIL AND WATER MANAGEMENT SUB PLAN
HEA-PL-GL-SWP-001-00-03 Page 27
6.7 Design
Management and mitigation measures Responsibility Source of Requirement Timing
Design
The design team will be briefed on the specific soil and water
management issues for the project and have been included in the risk
assessment process. Environmental Manager
Soils and Construction,
Volume 2d Design phase
Design drawings will show all permanent drainage, erosion and
sediment control measures as well as temporary and permanent water
quality basins.
Highway Lead Design Manager Soils and Construction,
Volume 2d
Design phase
The design will consider the use of bridges and arches instead of
culverts to minimise disturbance to and the diversion of natural
channel and creeks.
Highway Lead Design Manager,
Bridge Lead Design Manager MCoA88 Design phase
The design, construction and operation of construction sediment
basins will comply with the requirements of Managing Urban
Stormwater: Soils and Construction, Volume 1 4th Edition, March
2004, Managing Urban stormwater: Soils and Construction, Volume
2D, Main Road Construction and RTA Specification G38 will be Type
D basins due to the presence of dispersive soils
Design Manager MCoA 92
Blue Book, Volume 2d
RTA Spec G38
Design and construction
phases
Construction sediment basins will be Type D 85th percentile, 5 day
basins except where limited by clearing disturbance limits.
Construction basins will be Type D 80th percentile, 5 day basins when
located away from sensitive areas except where limited by clearing
disturbance limits. The use of smaller basins will be determined with
the DECCW.
Design Manager MCoA 92
Blue Book, Volume 2d
RTA Spec G38
Design and construction
phases
As far as practical, sediment basins will be located in non-vegetated
areas in order to reduce the clearing footprint.
Where possible, sediment basin design shall maximise the distance
between basin outlets and adjacent environmentally sensitive areas.
Design Manager Design and construction
phases
The construction sediment basins and associated equipment will
include: Design Manager RTA App 14 of SWTC Design and construction
phases
Hunter Expressway Alliance
SOIL AND WATER MANAGEMENT SUB PLAN
HEA-PL-GL-SWP-001-00-03 Page 28
Management and mitigation measures Responsibility Source of Requirement Timing
• flow control structures (i.e. baffles, bypass weir), at the inlet of
the construction sediment basin, that form an inlet chamber
and limit flows to a maximum velocity to 0.5m/s. The size
and location of the inlet chamber will allow desilting by
conventional earthmoving equipment such as a backhoe;
• internal baffles where the length-to-width ratio of the
construction sediment basin is less than 3:1;
• automatic basin flocculent dosing stations that comply with
the requirements of E.4.2 of Managing Urban Stormwater:
Soils and Construction Volume 1 4th Edition, March 2004 and
use liquid flocculants that comply with the requirements of
Specification G38.
• forebays to trap coarse sediments; and
• floating siphon devices that decant the construction sediment
basin by siphoning water from the top of the water column.
• An emergency outlet or spillway
• Outlet protection to reduce erosion downstream
• Compacted earth embankments or a rock filled wire basked
wall with geofabric lining;
A spill containment system to capture accidental chemical and fuel
spills during operation of the Works will be designed to minimise the
impacts of accidental spills, including those on environmentally
sensitive areas.
Those areas requiring treatment during the operation of the Works will
be identified by a Water Quality and Spills Risk Assessment.
Agreement to the Water Quality and Spills Risk Assessment will be
made with the relevant Authorities.
Design Manager
MCoA 95
RTA App 14, s.14.2.3(b)
RTA Code of Practice for
Water Management (1999)
Design phase
The Alliance will design and construct an operational water quality
system that may include swales, wet/dry basins, bioretention base
ponds and constructed wetlands to control the intensity of and remove
pollutants from stormwater runoff (including from pavements and
Design Manager / Construction
Manager
RTA App 14, s.14.2.2
Design and Construction
phase
Hunter Expressway Alliance
SOIL AND WATER MANAGEMENT SUB PLAN
HEA-PL-GL-SWP-001-00-03 Page 29
Management and mitigation measures Responsibility Source of Requirement Timing
bridges) prior to discharge.
The Alliance will design and construct operational water quality
systems in those areas identified by a Water Quality and Spills Risk
Assessment.
Agreement to the Water Quality and Spills Risk Assessment will be
made with the relevant Authorities.
Design Manager / Construction
Manager
RTA App 14, s.14.2.2
Design and Construction
phase
The Alliance will design and construct a spill containment system to
capture accidental chemical and fuel spills during operation of the
Works and minimise the impacts of accidental spills, including those
on environmentally sensitive areas.
Those areas requiring treatment during the operation of the Works will
be identified by a Water Quality and Spills Risk Assessment.
Agreement to the Water Quality and Spills Risk Assessment will be
made with the relevant Authorities.
Design Manager / Construction
Manager
RTA App 14, s.14.2.3
Design and Construction
phase
Operational spill basins shall have a minimum capacity of 20000L. Highway Lead Design Manager
MCoA 95
App 14, s.14.2.3(b)
RTA Code of Practice for
Water Management (1999)
Operational phase
The design will maximise the segregation of clean and dirty water
catchments during both the construction and operational phases of the
project.
Highway Lead Design Manager Soils and Construction,
Volume 2d
Design and construction
phases
The design of culverts will allow for the temporary stable bypass of
clean cross drainage during construction. Highway Lead Design Manager
Soils and Construction,
Volume 2d
Design and construction
phases
Lined catch drains and berm drains will be provided to protect cut
batters and to divert clean run on water through or away from
disturbed areas.
Highway Lead Design Manager Soils and Construction,
Volume 2d
Design and construction
phases
Kerbs, gutters or dykes discharging into lined batter drains will be
provided to protect fill batters. Highway Lead Design Manager
Soils and Construction,
Volume 2d
Design and construction
phases
Hunter Expressway Alliance
SOIL AND WATER MANAGEMENT SUB PLAN
HEA-PL-GL-SWP-001-00-03 Page 30
Management and mitigation measures Responsibility Source of Requirement Timing
Culvert and drainage structures will be designed and constructed to
minimise impacts on creeks and fish passage, e.g. invert of culverts
and pipes will be 200mm below the bed level of creeks;
Highway Lead Design Manager App 5, Table 4 Design, construction and
operational phases
Bridge piers, scour protection and abutments shall be located to
minimise disturbance to the bed and banks of creeks and flow lines. Bridge Lead Design Manager App 5, Table 4 Construction Phase
Hunter Expressway Alliance
SOIL AND WATER MANAGEMENT SUB PLAN
HEA-PL-GL-SWP-001-00-03 Page 31
6.8 Access and Site Set Up
Management and mitigation measures Responsibility Source of Requirement Timing
Access and Site Set Up
Develop plan showing which access tracks are to be used and which
tracks are NO Go areas Construction Manager Construction Phase
Erosion and sedimentation controls will be installed prior to any land
disturbance to ensure that all runoff from the site is managed
appropriately. Construction Manager
Soils and Construction
Volume 2d Construction Phase
Where natural surface levels allow, sediment basins will be
constructed prior to the commencement of top soil stripping and will be
operational when subsoil earthworks commence.
Construction Manager Construction Phase
Sedimentation basins will collect sediment-laden run-off from
disturbed areas of the construction site. Sediment basins will be
located to maximise the collection of turbid runoff.
Construction
Manager/Environment Manager Construction Phase
Construction water sources will include:
• project sedimentation basins;
• local non-potable supplies (e.g. farm dams, local creeks, bore
water);
• local potable supplies;
• constructed dams
A permit to extract water from local creeks will be sought from DECCW
(Office of Water) in accordance with the Water Management Act 2000
if applicable.
Environment Manager Construction Phase
Hunter Expressway Alliance
SOIL AND WATER MANAGEMENT SUB PLAN
HEA-PL-GL-SWP-001-00-03 Page 32
6.9 Clearing
Clearing - Management and mitigation measures Responsibility Source of Requirement Timing
Clearing
Wherever possible during clearing, soil surface cover will be
maintained, including use of the cut stump method to minimise soil
exposure to erosion for clearing near waterways. Construction Manager App 15 s.15.5.1 Construction phase
Develop work procedures and PESCP. Construction Manager Construction phase
PESCP’s to be approved by the Environmental Manager and Soil
Conservationist prior to commencing new works. Construction Manager
Construction phase
Where possible divert all clean water flows away or around the site
prior to clearing commences Construction Manager Construction phase
Where possible install sediment basins prior to clearing Construction Manager
Site vegetation will be either removed from site for re-use/sale, or tub
ground and either stockpiled (& managed to become compost for
revegetation purposes) or windrowed to form sediment retention
berms.
Construction Manager MCoA64 Construction phase
Clearing will not involve the removal of groundcover/grasses and
topsoil in order to retain the runoff infiltration capacity of the
groundcover for as long as possible, and to minimise topsoil runoff. Senior Project Engineer Construction phase
The topsoil will be kept in place in areas not being excavated to
prevent exposure of the subsoil during clearing operations. Senior Project Engineer Construction phase
Where applicable, temporary windrows will be used to keep runoff
from spilling over embankment batters during construction, and used
in combination with temporary batter drains to enable controlled
discharge of runoff down battered slopes without causing erosion.
Senior Project Engineer Construction phase
Hunter Expressway Alliance
SOIL AND WATER MANAGEMENT SUB PLAN
HEA-PL-GL-SWP-001-00-03 Page 33
6.10 Earthworks
Management and mitigation measures Responsibility Source of Requirement Timing
Earthworks
Develop Work Method Statements and PESCP’s for all earthworks Senior Project
Engineer/Superintendent Construction phase
PESCP’s to be approved by the Environmental Manager and Soil
Conservationist prior to commencing new works. Construction Manager
Spoil, select material, sub soils, mulch or compost stockpiles will:
• Generally be located within the road reserve, and in areas
identified for future disturbance or at sites identified for
compound and or batching plant location;
• Be located at least 20 metres from any creeks, water bodies
or a flood prone area;
• Be constructed as low, flat elongated mounds where
construction room permits;
• Have sediment fences down slope and earth banks upslope
to divert run-on water
• Stockpiles are not to be located on native vegetation;
• Soil stockpiles to be protected from wind erosion by covering
with geotextile until required.
All site personnel Construction phase
Any stored topsoil stockpiles will be protected from water and wind
erosion by seeding with a sterile cover crop or by covering with geo-
textile fabric until required.
Senior Project
Engineer/Superintendent
App 15, s. 15.6.3(k) Construction phase
No plant or operations will be located within buffer zones (within 20m)
along waterways (to reduce risk of ground disturbance / potential fuel
spillage) unless those waterways are located outside works areas,
and/or all waterways are temporarily diverted during works and/or
other appropriate mitigation measures are employed, where
practicable.
Where not practical, other controls (to be determined on a case by
case basis and detailed in the relevant PESCP) would be employed
Senior Project
Engineer/Superintendent Construction phase
Hunter Expressway Alliance
SOIL AND WATER MANAGEMENT SUB PLAN
HEA-PL-GL-SWP-001-00-03 Page 34
Management and mitigation measures Responsibility Source of Requirement Timing
between the waterway and works area.
Erosion and sediment control devices to be implemented on site
during construction is likely to include:
• Soft and hard armour lined drains;
• Diversion banks and drains;
• Trafficable inclined diversion banks;
• Soil stabilisers;
• Culvert inlet and outlet protection;
• Amelioration of dispersive, acidic and low nutrient soils;
• Progressive revegetation;
• Hydro-mulching;
• Compost blankets;
• Sediment traps;
• Sediment basins;
• Mulch/compost bunds; and
• Coagulants and/or flocculants.
Project Manager/Environment
Manager/Superintendent
Construction phase
Where areas are identified as being most vulnerable to runoff from the
highway or disturbed areas or where the terrain suits installation of
basins, surface runoff from the road will undergo sufficient treatment
using a system of water quality control ponds incorporating traps to
contain spills of hazardous materials and ensure that runoff meets
relevant guidelines for discharge into wetlands or watercourses.
Construction Manager/Project
Manager App 15, s. 15.4 Construction phase
Diversion banks will be constructed at an appropriate grade to
minimise soil erosion (less than 1%). Project Manager/Environment
Manager/Superintendent
IECA(2008) Construction phase
Energy dissipaters will be installed at the end of diversion banks of any
overland flowpaths leading from the disturbed area, to slow flow
velocities to non-erodible levels.
Project Manager/Environment
Manager/Superintendent
Soils and Construction
Volume 2d
Prior to and during
construction
Hunter Expressway Alliance
SOIL AND WATER MANAGEMENT SUB PLAN
HEA-PL-GL-SWP-001-00-03 Page 35
Management and mitigation measures Responsibility Source of Requirement Timing
Designation and marking of transport routes across undisturbed
portions of the site will be undertaken to ensure minimal unnecessary
vegetation disturbance.
Project Manager/Environment
Manager/Superintendent
Prior to and during
construction
Undertake progressive revegetation of disturbed areas. Project Manager/Environment
Manager/Superintendent
Prior to and during
construction
Delineate clearing limits to confine construction activities within the
necessary construction area(s). Project Manager/Environment
Manager/Superintendent
Prior to and during
construction
Control measures will be maintained until the site is stable and 70%
soil surface cover has been achieved. Once the project site has been
stabilised, temporary sediment controls will be removed.
Project Manager/Environment
Manager/Superintendent MCoA94
Prior to and during
construction
Any permanent water-retaining structures or other erosion and water
management controls will be routinely maintained. Project Manager/Environment
Manager/Superintendent
App 15 Prior to and during
construction
Ensure wheels, tracks and body surfaces of plant and vehicles leaving
the site are free of mud or sediment to minimise the potential for mud
tracking on public roads. Superintendent MCoA115
Prior to and during
construction
Road sweepers will be utilised if conventional measures such as
rumble grids to not prevent mud tracking on public roads. Project Manager/Senior Project
Engineer
MCoA115 Prior to and during
construction
Hunter Expressway Alliance
SOIL AND WATER MANAGEMENT SUB PLAN
HEA-PL-GL-SWP-001-00-03 Page 36
6.11 Drainage and Bridgeworks
Management and mitigation measures Responsibility Source of Requirement Timing
Drainage and Bridgeworks
Develop Work Method Statements and PESCP’s for drainage and
bridge works. Senior Project
Engineer/Superintendent Construction phase
PESCP’s to be approved by the Environmental Manager and Soil
Conservationist prior to commencing new works. Construction Manager
Temporary waterway crossings will be constructed over local
waterways to facilitate access for earthworks activities and the
construction of bridges only if absolutely necessary. The following
mitigation measures and controls would apply to work within
waterways:
• Disturbance of watercourses by construction works will be
avoided wherever possible ;
• Work Procedures will be prepared for work in any natural
waterway;
• Appropriately sized rock will be used for constructing
waterway crossings;
• Personnel and sub-contractors will be made aware of their
environmental responsibilities through induction and
environmental training;
• There will be no temporary stockpiles of materials nor
machinery stored in drainage lines;
Where work in waterways is required (e.g. culvert installation), these
works will be carried out in the shortest possible timeframe and in dry
conditions; Adequate erosion protection controls shall be installed prior
to forecasted rainfall events.
Aquatic habitat in the form of snags, gravel bars, in-stream vegetation
(rushes, sedges), tree roots, logs and similar will be maintained in-situ
where possible or replaced following construction;
Senior Project
Engineer/Superintendent
MCoA68, App 4 s. 4.15.1,
App 5 Table 4
Construction phase
Hunter Expressway Alliance
SOIL AND WATER MANAGEMENT SUB PLAN
HEA-PL-GL-SWP-001-00-03 Page 37
Management and mitigation measures Responsibility Source of Requirement Timing
Adequate systems will be developed for liaison with regulatory
authorities and local councils regarding installation of all waterway
structures (e.g. Environmental Review Group Meetings); and
Construction phase
Platforms and temporary crossings will consist of rock containing nil to
minimal fines that are not capped. Some fines may be used at the
surface level for stability requirements , however these shall be capped
to reduce the erosion potential.
Waterway rehabilitation will be instigated immediately following
construction utilising appropriate stabilisation products and species
endemic to the area. Restoration may also involve the provision of in-
stream habitat features such as riffles, pools and snags.
Appropriate erosion and sedimentation control measures, such as
sediment fences, sediment curtains and/or other controls will be
constructed along creeks and where the slope of existing ground
requires to ensure that waterways are separated from active
work/exposed areas.
Construction Manager/Project
Manager
Construction phase
Erosion protection will be provided at the inlet/outlets of culverts and
under bridges where appropriate to minimise erosion. RTA, NPWS, II
NSW (Fisheries) and the Blue Book recommendations will be adopted
in the detailed design phase to ensure that erosion protection is
adequate. Erosion protection will be designed in an environmentally
sensitive manner, taking into account aquatic ecology and fish
movement as well as stream issues. Bank and bed protection will be
considered.
Construction Manager/Project
Manager MCoA68, App5 Table 4
Construction phase
Depending on the type of works, construction of an impervious bund
(e.g. cofferdam) will be considered to prevent water entering the area
of works.
Should cofferdams be required the process to install/ dewater and
remove coffer dams will be developed prior to the installation of any
coffer dams and best management practice will be implemented in
developing WMS & PESCP’s for their instillation and operation.
Where construction of temporary work platforms is necessary within
Construction Manager/Project
Manager/Superintendent
Construction phase
Hunter Expressway Alliance
SOIL AND WATER MANAGEMENT SUB PLAN
HEA-PL-GL-SWP-001-00-03 Page 38
Management and mitigation measures Responsibility Source of Requirement Timing
creeks for bridge construction purposes, the platform will be designed
to minimise the disturbance to the creek bed.
Should dewatering of coffer dams be required appropriate
methodology such as pumping out to a nearby basin or via watercart
shall be investigated. Release of coffer dam water directly to
waterways shall not be permitted.
Construction Manager/Project
Manager/Superintendent
Prior to commencement of
construction
Barriers will be constructed on crossings or around working areas of
watercourses during bridge cleaning and repainting and other works to
prevent dust and spray entering the watercourse.
Construction Manager/Project
Manager
Construction and operational
phases
The placement of concrete into forms in or close to any watercourse
will be carefully controlled. The use of quick setting mixes may be
appropriate in some cases to minimise the risk of water pollution.
Project Manager/Senior Project
Engineer Construction phase
Concrete pours will not be undertaken during rainfall where there is a
risk of water pollution occurring. Project Manager/Senior Project
Engineer
Construction phase
Steel or concrete piles for bridges will be used where possible to
minimise the potential for groundwater contamination, particularly in
alluvial aquifers.
Project Manager/Senior Project
Engineer Construction phase
Specific work procedures will be prepared for grout filling of the
underground mining voids. The work procedures will include measures
for the management of potentially saline and/or acidic mine water,
minimise the potential for contamination of coal seam groundwater
aquifers and for monitoring of impacts on coal seam groundwater
aquifers.
Project Manager/Environment
Manager
MCoA96 Prior to construction
Groundwater will not be discharged to any watercourse or drain
without treatment to ensure it meets necessary water quality discharge
criteria.
Project Manager/Environment
Manager MCoA91 Construction phase
Diversion banks/drains will be installed upstream of construction
activities where practicable to ensure run-on water is diverted around
disturbed areas.
Project Manager/Environment
Manager/Superintendent
Soils and Construction,
Volume 2d
Prior to and during
construction
Hunter Expressway Alliance
SOIL AND WATER MANAGEMENT SUB PLAN
HEA-PL-GL-SWP-001-00-03 Page 39
Management and mitigation measures Responsibility Source of Requirement Timing
Catch drains at the downstream boundary of construction activities will
also be created (wherever possible) to ensure any sediment laden
runoff is contained and directed toward treatment areas and not
permitted to flow onto downstream undisturbed areas and will be lined
where the flow velocity exceeds the erosive resistance of the soil.
Where the installation of catch drains is not possible temporary cross-
drains will be scribed in at regular intervals with temporary checks
placed in the drains to lower the velocity within the drains to prevent
erosion.
Project Manager/Environment
Manager/Superintendent
Soils and Construction,
Volume 2d
Prior to and during
construction
Hunter Expressway Alliance
SOIL AND WATER MANAGEMENT SUB PLAN
HEA-PL-GL-SWP-001-00-03 Page 40
6.12 Paving and Vehicle Movement
Management and mitigation measures Responsibility Source of Requirement Timing
Paving and Vehicle Movement
The following water quality controls will be provided for the batch
plants as required:
• Perimeter bunds to divert run-on away from the site;
• Installation of a first flush water pollution management
system;
• Immediate clean up of any spillage of chemicals, fuels or oils .
Water discharge requirements from the batch plant will be as detailed
in the EPL.
Project Manager/Environment
Manager Construction phase
Truck wash downs and cement truck washouts conducted in approved
areas only Superintendent
Construction phase
Water recycling will be encouraged (refer to s5.7 of the Waste
Management & Re-Use Sub Plan for further details) Project Manager/Environment
Manager
All excess concrete and waste materials stored in bunded areas prior
to reuse or disposal.
Details of concrete curing compounds and treatments will be outlined
in the work procedure to be prepared for concreting paving operations.
This will contain a description of the procedure used including
equipment, chemicals and primary/secondary controls to capture
curing compound run-off.
Vehicles will use defined access routes and tracks at all times (to be
detailed in the Traffic Management Plan).
All spoil will be covered during transportation on public roads.
Project Manager/Environment
Manager
Senior Project Engineer
Superintendent
MCoA115 Prior to construction
All phases
Construction phase
Road sweepers will be utilised as necessary to minimise sediment
being washed into nearby drains and watercourses. Superintendent MCoA115 Construction phase
Hunter Expressway Alliance
SOIL AND WATER MANAGEMENT SUB PLAN
HEA-PL-GL-SWP-001-00-03 Page 41
Management and mitigation measures Responsibility Source of Requirement Timing
Concrete mixers and pump trucks will be washed out at designated
wash-out locations on-site. Superintendent Construction phase
Specific concrete washout locations to be installed at batching plant for
major concrete wash outs and along the alignment for minor concrete
washouts Superintendent Construction phase
Training will be provided to personnel authorised to manage and
release the basins;
Waste water captured in storage bunds will be visually assessed for
contamination prior to being released. Hydrocarbon contamination will
be removed using appropriate absorbent materials;
Washdown areas for equipment will be located in bunded areas away
from watercourses and wetlands;
Concrete washout areas and pits will be adequately sized, located
away from drainage lines and maintained regularly; and
Waste water produced by the batch plants will be captured and reused
where possible.
Project Manager/Environment
Manager
Construction phase
Slurry from saw cutting and curing compounds will be retained close to
the source as far as possible. Project Manager/Senior Project
Engineer
Construction phase
Hunter Expressway Alliance
SOIL AND WATER MANAGEMENT SUB PLAN
HEA-PL-GL-SWP-001-00-03 Page 42
6.13 Rehabilitation and Landscaping
Management and mitigation measures Responsibility Source of Requirement Timing
Rehabilitation and Landscaping
Soil erosion will be minimised by establishing vegetation quickly on
disturbed areas. Permanent vegetation will be established on all
disturbed areas subject to erosion and where no further regarding or
activity is proposed. Works will be undertaken in accordance with
Alliance Specifications R178 and R179.
Project Manager/Environment
Manager MCoA 89
Construction phase
The following measures will be adopted to stabilise and restore
disturbed areas of the construction site:
• Revegetation works will be undertaken progressively and in
conjunction with earthworks to minimise the time that an area
is exposed;
• Topsoil will be reused in areas as close as possible to its
source location to maximise the benefits available from the
existing seed bank;
• Batters will be stabilised and revegetated as quickly as
possible to minimise erosion and sedimentation in
accordance with Alliance Specifications R178 and R179;
• Site soils will be tested for agronomic and erosion parameters
and soils will be ameliorated accordingly; and
• Revegetation will be undertaken using direct seeding, hydro-
mulching, compost blankets or direct planting.
Project Manager/Environment
Manager / Landscape Manager
MCoA 89
App 15, s. 15.6.3
Construction phase
Construction sediment basins that are retained during the operation
phase will be removed once the vegetation cover in the catchment
area has achieved 70% and water quality has stabilised. Following
removal the disturbed areas will be revegetated.
For permanent water quality basins the modification process following
completion of construction will involve allowing the natural seeding of
aquatic plant species (macrophytes) to assist with sediment settlement
and nutrient removal processes.
Senior Project
Engineer/Superintendent/Environ
ment Manager
MCoA94 Operational phase
Hunter Expressway Alliance
SOIL AND WATER MANAGEMENT SUB PLAN
HEA-PL-GL-SWP-001-00-03 Page 43
Management and mitigation measures Responsibility Source of Requirement Timing
All exposed areas to be stabilised (that is, compacted, sealed or
vegetated) as soon as practicable following completion of works. Senior Project Engineer Construction and operational
phase
At the completion of the work, all disturbed areas to be restored as
closely as practicable to their condition prior to completion of works. Senior Project Engineer Construction and operational
phase
Hunter Expressway Alliance
SOIL AND WATER MANAGEMENT SUB PLAN
HEA-PL-GL-SWP-001-00-03 Page 44
7 INSPECTIONS
Inspections will take place on a regular basis to ensure appropriate mitigation measures and controls are being provided and that they are effective. Site monitoring by an appropriately qualified environmental scientist or person with similar expertise in soil and water management will include the following:
Table 7.1: Inspection Requirements
Inspection Requirements When Who
Construction
Informal visual checks of all erosion and sedimentation devices by the Senior Project Engineer and Superintendent (or
delegate) to ensure that controls have been provided where required and/or are functioning correctly. Any deficient controls
will be noted and action will be taken to address.
Inspections by the Environment Staff and/or erosion and sediment control crew.
Rainfall depths/levels.
Daily and after a
rainfall event
Senior Project
Engineer and
Superintendent (or
delegate)
Environment Staff
and Maintenance
Crews
Inspections by the Environment Staff and completion of environmental checklists:
• Check that controls are being maintained in an efficient condition;
• Check that controls meet the requirements of any relevant approval and/or licence conditions; and inspections to
inform the update of PESCPs and to identify where new controls are required.
Weekly and after a
rainfall event
Environment Staff
(and site engineers
periodically as per
site commitment
matrix requirements).
Joint inspections with the Alliance Soil Conservationist , RTA client representatives and Project EMR during clearing and
earthworks phases.
Fortnightly
Superintendent/ Soil
Conservationists,
Project EMR,
Alliance
Environmental Staff
and RTA
Hunter Expressway Alliance
SOIL AND WATER MANAGEMENT SUB PLAN
HEA-PL-GL-SWP-001-00-03 Page 45
Inspection Requirements When Who
Joint inspections with regulatory agencies representatives, project EMR, relevant site staff, RTA client representatives and
Soil Conservationist.
Monthly
Superintendent/ Soil
Conservationists,
Project EMR,
Environmental Staff,
Agency
representatives and
RTA.
Reporting to DECCW on compliance with EPL conditions. Annually
Alliance Environment
Staff
Inspections following significant rainfall (10mm of rainfall within a 24 hour period) by the Project Engineer, Superintendent
and Environmental Officer.
Event based
Project Engineer,
Superintendent and
Alliance
environmental staff.
Inspection to assess whether there have been any discharges to receiving waters for rainfall events up to and including the
design rainfall event for control structures (i.e. basins).
Event based
Project Engineer,
Superintendent and
Alliance
environmental staff.
Post-construction
Ensure sediment and erosion controls are removed on completion of the rehabilitation works. On completion Environment
Manager/
Superintendent
Hunter Expressway Alliance
SOIL AND WATER MANAGEMENT SUB PLAN
HEA-PL-GL-SWP-001-00-03 Page 46
8 MONITORING AND REPORTING
Table 8.1: Monitoring and Reporting Requirements
Pre-construction
Monthly water quality monitoring will be undertaken where disturbance to the creek bed or near the creek line would occur
during construction activities.
Monthly Environment
Manager
Monitoring will be carried out to measure the following parameters and indicators: pH; Electrical conductivity; Turbidity;
Aluminium (if aluminium based flocculants are proposed to be used) and Dissolved Oxygen. Monthly
Environment
Manager
Construction
Water quality monitoring will be undertaken upstream and downstream of the construction areas monthly and following
significant rainfall events greater than or equal to 10mm.
Monitoring will be carried out to measure the following parameters and indicators: pH; Electrical conductivity; Turbidity;
Aluminium (if aluminium based flocculants are used during construction), Dissolved Oxygen and Temperature
Monitoring will be undertaken twice monthly (1 sample during dry weather and 1 sample per month during rainfall events).
Generally where there is a 10% exceedance of downstream samples compared to upstream samples an investigation will be
undertaken to determine whether the elevated downstream results are as a result of construction impacts. Results will also be
compared with the ANZECC Water Guidelines 2000 or update.
An appropriately qualified person will undertake regular inspections and maintenance downstream of construction areas at
locations where water quality samples are taken. Refer to Appendix A for an example Water Quality Monitoring Work
Procedure.
Basins will be monitored for turbidity, pH and oil and grease before being discharged. pH adjustment and flocculation will be
undertaken as required.
Monthly Environment
Manager
Post -Construction
Sampling Sites - Post-construction monitoring sites should be representative of the impact site runoff will have on receiving
waters. The number of sampling sites would likely be less than in the construction phase, dependent on changes in site
hydrological conditions following the installation of the operational stormwater system.
Sampling frequency - Recommended default sampling frequency for post-construction monitoring is once per month. If a
Monthly Environment
manager
Hunter Expressway Alliance
SOIL AND WATER MANAGEMENT SUB PLAN
HEA-PL-GL-SWP-001-00-03 Page 47
number of results demonstrate that the site or parts of the site have stabilised, the sampling frequency and sampling locations
may be reviewed and reduced or discontinued.
Parameters - Post-construction monitoring parameters will be the same as those used during the construction of the project.
Individual parameters may be withdrawn from the program as the site stabilises or the parameter is demonstrated to be no
longer of concern. For example, where erosion has been controlled through re-vegetation and all operational stormwater
controls have been installed.
Interpretation of results - If the results exceed the site criteria for any sample respond in the same way as during the
Construction phase and report to relevant Government agencies as necessary.
If individual parameters or sampling sites are to be withdrawn from the program, it should be demonstrated that there is no
longer an impact over a minimum period of 2 months.
Hunter Expressway Alliance
SOIL AND WATER MANAGEMENT SUB PLAN
HEA-PL-GL-SWP-001-00-03_Soil & Water_Final Page 48
9 CORRECTIVE ACTION
Possible non-conformances may include non-compliance with the management measures and mitigation strategies outlined in Section 6. All incidents and non-conformances are to be reported and investigated and corrected in accordance with Section 4 of the CFEMP
Specific corrective action items for the soil and water management Sub Plan are outlined below:
• Sediment controls not effectively maintained and reinstatement or remedial action
required; and
• Spill or release of sediment laden water occurs, an incident report is submitted and
remedial action required.
This management plan will be reviewed during the construction period based on results from monitoring, observations, non-conformance or complaints. The review will allow adjustments to occur to the plan if they are found to be beneficial, or if measures need adjusting. All project staff will be notified of changes made to this Sub Plan.
Hunter Expressway Alliance
SOIL AND WATER MANAGEMENT SUB PLAN
HEA-PL-GL-SWP-001-00-03_Soil & Water_Final Page 49
APPENDIX A – WATER QUALITY MONITORING WORK PROCEDURE
Rev Date Prepared by Reviewed by Approved by Remarks
00 22-3-10 Erran Woodward Tracey Doczy Howard
Chemney
Hunter Expressway Alliance
SOIL AND WATER MANAGEMENT SUB PLAN
HEA-PL-GL-SWP-001-00-03_Soil & Water_Final Page 50
SCOPE
This document describes the procedures for the monitoring of water quality in streams and rivers which intersect the footprint of the Hunter Expressway Alliance Project (the Project).
The objective of the water monitoring is to identify any disturbance to waterways caused by clearing and construction of the Project. By assessing water quality both before and after (temporal replication) and upstream and downstream (spatial replication) of the construction works, changes in water quality will be recognised, causes identified and actions can be taken to immediately rectify and prevent any further environmental damage.
Guidelines for the water quality monitoring and reporting are outlined in the HEA Soil and Water management Sub Plan. These guidelines will be used as the foundations for this Monitoring Procedure. All monitoring will be undertaken in accordance to the Monitoring Job Safety and Environment Analysis (JSEA).
ASSESSMENT
Water quality parameters to be assessed include:
• pH
• Electrical Conductivity
• Turbidity
• Dissolved oxygen
• Temperature
• Salinity
• Aluminium (if aluminium flocculates are used during sediment basin treatment)
Site observations including weather, colour, frothing, odour, flow, surfactants, construction activities and aquatic organisms will be recorded during sampling.
Data will be obtained and stored using the Yeo-Kal Multi purpose water quality analyser (Model 611 or Model 615). This equipment will be regularly serviced and calibrated to manufacturer’s directions to ensure reliable results.
In the case where water samples need to be analysed for heavy metals, oils and organic pollutants, samples will be collected and sent in accordance to laboratory specifications to a NATA accredited laboratory for analysis.
SITE LOCATIONS
Water quality monitoring will occur in waterways both upstream and downstream of the construction and areas of disturbance from construction may occur. These waterways include:
Hunter Expressway Alliance
SOIL AND WATER MANAGEMENT SUB PLAN
HEA-PL-GL-SWP-001-00-03_Soil & Water_Final Page 51
Table 1
Waterway Site Name Location
Minmi Creek MC 0.510km
Blue Gum Creek BGC 2.590km
Surveyors Creek 1st Occurrence SC1OC 4.400km
Surveyors Creek 2nd Occurrence SC2OC 5.600km
Surveyors Creek 3rd Occurrence SC3OC 10.400km
Wallis Creek WC1 10.490km
Maps showing indicative sampling locations are included within the HEA Construction Environmental Management Plan.
MONITORING PROCEDURE
1. Preparing the equipment:
The operator must familiarise themselves with the Yeo-Kal user manual before attempting to undertake water quality monitoring. Monitoring shall only be undertaken by Environmental Officers with relevant training and experience. Ensure the Yeo-Kal equipment is prepared for use by removing the protective seal from the pH sensor and plugging in the probe cord to the connection labelled “Sensor”. The equipment should be regularly calibrated in the field (using standard solutions) and at least annually by the manufacturer (Yeokal) to ensure accuracy.
Calibration logs / certificates to be maintained for auditing purposes.
2. Collecting data:
After reaching the site, remove probe from container and place into the water without disturbing sediment. Readings should settle within a few seconds, but if readings remain inconsistent wait a short period of time until readings stabilise. While waiting, record site data and observations as mentioned above. Store results by pressing STORE on unit and record the number which will flash up. Return probe to case and move to next site.
3. Retrieving the data:
Data from the Yeo-Kal unit can be retrieved by plugging in the cable from the computer port to the COMM connector on the unit. Open the Yeo-Kal software and in the file drop window click ‘Read data from instrument’. Turn the instrument on and in the menu find ‘download data’ and press enter. Once data has downloaded find ‘clear stored data’ and press enter. This will clear all the stored data from the memory.
Hunter Expressway Alliance
SOIL AND WATER MANAGEMENT SUB PLAN
HEA-PL-GL-SWP-001-00-03_Soil & Water_Final Page 52
MONITORING FREQUENCY
Pre Construction:
As defined in the SWMSP, initial pre construction water quality monitoring was undertaken in 2007 and has been continuing on a regular basis since February 2009.
During Construction:
Monitoring will occur twice monthly during Dry and Wet Weather. For the purpose of this monitoring procedure, Wet Weather has been defined as precipitation exceeding 10 millimetres within 24hours. This value has been determined to allow enough precipitation to results in runoff.
Rainfall measurements will be determined by the Weather Station at each Zone’s compound (office locations yet to be determined). Each Zone will determine a wet weather event independently.
There will be three construction zones as follows:
• Zone 1: F3 (ch 0000) – Stockrington Road (ch 1400)
• Zone 2: Stockrington Road (ch 1400) – Rest Area (ch 8100)
• Zone 3: Rest Area (ch 8100) – project end (12900)
Post Construction:
Water quality monitoring will continue in the vein of preconstruction monitoring as determined within the Operational Environmental Management Plan (yet to be finalised).
Trigger Values
Trigger values during construction will be a 20% exceedance of downstream samples compared to upstream samples.
ANZECC Guidelines may not be used for trigger values but may be consulted as a reference in any investigations prompted by discrepancies greater than 20%. Due to the variability of individual creeks and catchments within the construction area, it is believed that the best reference data will be that of the pre construction water quality monitoring.
Actions Triggered
Once identified, an investigation will be undertaken by the Environmental Manager and Environmental Officer to determine the cause of the discrepancy. If the cause is due to Project impacts, the Zone Coordinator will discuss remediation and/or preventative actions with the relevant site manager. If required an Environmental Incident or Non Conformance Report may be initiated.
Hunter Expressway Alliance
SOIL AND WATER MANAGEMENT SUB PLAN
HEA-PL-GL-SWP-001-00-03_Soil & Water_Final Page 53
Reporting
Results of all monitoring, including a description of all exceedances and consequent investigations and alterations to works, will be reported monthly to the Alliance Leadership Team, DECC and the RTA.
Hunter Expressway Alliance
SOIL AND WATER MANAGEMENT SUB PLAN
HEA-PL-GL-SWP-001-00-03_Soil & Water_Final Page 54
APPENDIX B – DEWATERING PROCEDURE
Rev Date Prepared by Reviewed by Approved by Remarks
00 22-5-10 Erran Woodward Tracey Doczy Howard
Chemney
Hunter Expressway Alliance
SOIL AND WATER MANAGEMENT SUB PLAN
HEA - DEWATERING PROCEDURE
Under the Protection of the Environment Operations Act (1997), there is a legal responsibility to ensure that runoff leaving site has an acceptable water quality standard. This procedure must be tool-boxed to all site personnel involved in dewatering activities. Controlled dewatering may occur from sedimentation basins, farm dams and construction excavations. Dirty water must not be allowed to enter any waterway. Consult environment team for further information.
Controlled dewatering may occur from sedimentation basins, farm dams and construction excavations. Any movement of water must be accompanied by a Water Movement Permit (attached) which has been correctly completed by either the operator of water cart or supervisor of the de-watering, and a member of the Environment staff. A Water Movement Permit is required for all movement of water including:
• Dewatering from a farm dam, sediment basin, cuts, trenches or excavated areas, or
• taking water from any extraction point for any purpose.
GENERAL NOTES:
Where possible water should be used for dust suppression activities.
• Water shall not be discharged directly into a drain, creek, river or lake unless it has been
tested and meets our Environmental Protection Licence (EPL) water quality standards.
Consult Environment Team for EPL details.
• Floats and/or other devices must be used on the pump inlet, to ensure that the inlet does
not come into contact with sediment settled at the bottom of the basin or pond.
• When pumping to a grassed area the ground at the pump outlet must be stable and not
erosive. Rock wrapped in geofabric may be used to stabilise the outlet point.
• Visual checks of suspended solids level should be undertaken regularly to determine the
effectiveness of the controls.
• De-watering activities where pumps are in use must be attended by an appropriate site
representative at all times.
PROCEDURES:
Unless otherwise specified by Environment Manager, the only licensed discharge points are sediment basins. Water quality parameters and their exceedance levels are identified in the license (yet to be supplied).
1. In cuts/ large excavated areas:
Methods of dewatering areas in cuts or other large excavated areas include the following: Cut a drain to direct unwanted stored water to an adjacent sediment basin only when it has the capacity to take the volume of stored water with no overflow from the basin. The basin will then be flocculated as necessary and released once tested and the desired water quality standard has
Hunter Expressway Alliance
SOIL AND WATER MANAGEMENT SUB PLAN
been achieved.
If adjacent sediment basins are full or don’t have the capacity to take the majority of the stored water, the stored water will either be flocculated in situ, tested and released to an appropriate area (eg. grassed area, lined catch drain) once the desired water quality standards has been achieved or, pumped into a water cart and taken to another sediment basin/s which does have the required capacity. The water cart will pump the water into the sediment basin, the basin flocculated, tested and discharged once an acceptable water quality standard has been achieved. Another alternative is to use the water in the water cart for dust suppression purposes on another section of the project where needed. When dewatering, it is important to use a floating inlet to prevent sediment from being extracted from the basin.
2. Trenches, etc. (smaller excavations)
Methods of dewatering in these situations include the following: Water in trenches, etc will be pumped to an adjacent sediment basin if it has adequate capacity with no overflow from the basin. A tail-out drain may be cut directing water from a trench, depending upon its depth and the volume of water, into an adjacent sediment fence or sediment trap.
3. Dewatering of contaminated areas
Where unwanted water is stored in areas that are known to be contaminated or where there is potential for contamination, the water will be tested to determine the contaminant and level of contamination, which will dictate the best method of treatment and disposal. Consult Environment Staff for further information.
4. Sediment basins
All sediment basins to be inspected for capacity and water quality immediately following cessation of a rain period. If water is to be used for construction purposes (e.g. compaction, dust control) no treatment is required. However, the water should be removed to re-secure design capacity within 5 days. Before all de-watering the parameters of pH, T.S.S. and oil and grease are to be tested. Treatment should commence approximately 2 to 4 days before dewatering deadline to allow enough time for settlement of flocculants. Treatment should be undertaken as follows:
pH
• Test basin water with meter
• No action if pH reading between 6.5 and 8.5
• Lime to be added if pH below 6.5
• Hydrochloric Acid (32% Muriatic) or Sulfuric Acid to be added if pH above 8.5
• Determine volume of water in basin.
• Determine percentage of lime or acid required by taking a 10 litre sample of basin water
and adding a known amount of lime or acid (initially 0.004%). If the pH is still not
acceptable, vary the amount of lime or acid until within the limits.
• Once the required percentage has been determined, calculate the actual amount of lime or
acid to be added by multiplying the volume of water in the basin by the determined
percentage.
• Add the required amount of lime or acid to the basin
Hunter Expressway Alliance
SOIL AND WATER MANAGEMENT SUB PLAN
• Mix the water in the sediment basin well
• Treat for pH prior to T.S.S.
T.S.S
• Test basin water by comparing with water samples contained in jars with representative
readings up to 100mg/l created through laboratory testing. This will enable a relatively
accurate comparison which will be verified by laboratory testing approximately every six (6)
rainfall events.
• No action if T.S.S. reading <50mg/l.
• If basins require flocculation (e.g. T.S.S. >50mg/l), gypsum is to be immediately applied
evenly across the top of the water at the manufacturers recommended dosage initially,
then at an acceptable rate (i.e. trial and error as different for each basin) should more
flocculants be required.
• Basins should be monitored daily after flocculation until desired TSS is achieved and to
assist in determination of optimal dosage levels.
• Methods of application to include:
- broadcast by shovels on small basins (i.e. <200m3); general recommended dosage
is 30kg/100 cubic meters. Spreading powder evenly and thinly (i.e. “dusting”) is
recommended.
- mixing in a drum with water and pumping through a hose on large basins (i.e.
>200m3).
- spraying from a water tanker.
- Use liquid gypsum, recommended dosage of 40L/megalitre
• When spraying flocculants the mixture must hit the water at between 10 to 20 degrees to
increase surface areas exposure to the water column.
• When using liquid gypsum “Hydro-Gyp” the solution must be mixed before use to ensure
gypsum is evenly suspended throughout mixture. This is best achieved using an aeration
device at 3 bars of pressure for approximately 15 minutes.
Oil and Grease
• Examine surface of water for evidence (e.g. sheen, discoloration).
• No action if no visual contamination.
• Oil absorbent material to be spread if there is contamination (e.g. cell-u-sorb). Leave
basins to compensate for 24 to 48 hours.
• After retesting, and once the above field tests indicate, the water quality is acceptable, the
stop valve should be opened by two or three notches, for discharge (ie approximately 10%
to enable emptying within a 24 – 36 hour period to prevent sediment being stirred up by
fast release of water and erosion at the outlet).
• The process above and the retesting may need to be repeated if acceptable water quality
is not achieved initially.
• Once water in the basins has been released the stop valve must be closed for the next
rainfall event.
• Records to be kept of the rainfall events, inspections undertaken, field tests undertaken,
dosage rates and when basin water is released etc. (Refer to the attached checklist).
Hunter Expressway Alliance
SOIL AND WATER MANAGEMENT SUB PLAN
• The whole process of water quality management in sediment basins must be completed
within 5 days of cessation of a rain period. Notify Environment Manager if this timeframe is
not achieved.
5. Farm Dams
On occasion existing farm dams within the proposed alignment will require dewatering prior to excavation. The following precautions must be undertaken:
• Check with Environment Team prior to dewatering to ensure additional approvals/permits
are not required.
• Environment Team shall check if noxious weeds are observed. Manage noxious weeds
prior to dewatering in consultation with Environment Staff.
• Environment staff shall also check for Mosquitofish. Where Mosquitofish are observed all
water extraction intake pipes shall be fitted inside a mesh or gauze cage (1 mm
mesh/gauze diameter) to prevent the dispersal of the Mosquito Fish into other areas.
Floats and/or other devices must be used on the pump inlet, to ensure that the inlet does not come into contact with sediment settled at the bottom of the basin or pond. When pumping to a grassed area the ground at the pump outlet must be stable and not erosive. Rock wrapped in geofabric may be used to stabilise the outlet point and filter water being pumped. Visual checks of suspended solids level should be undertaken regularly to determine the effectiveness of the controls. De-watering activities are to be attended by a site representative at all times.
Picture of a Mosquitofish – generally 4cm to 7cm in size
6. Management of Sub-Contractors During the site induction, all subcontractors will be made aware of their obligations regarding relevant consent conditions, legislative requirements and any licence requirements. This will include activities such as dewatering that could lead to a breach of any of the consent conditions, license conditions and legislative requirements. Subcontractors will be made aware that there is a work method statement to ensure the appropriate protocol for dewatering is followed. In situations where sub-contractors will require areas of work to be dewatered, they must inform the appropriate Alliance supervisor (foreman, superintendent) of their work that an area of their work requires dewatering. The supervisor will then implement the appropriate dewatering method for the circumstance. Records will be kept by both the Thiess supervisor and the sub-contractor of the area being dewatered, the date, method of dewatering, discharge point, who undertook the work and any test results.
Hunter Expressway Alliance
SOIL AND WATER MANAGEMENT SUB PLAN
Under no circumstance should the sub-contractor undertake dewatering activities without informing the relevant Alliance supervisor that an area requires dewatering and the supervisor instructing them on how the situation will be managed.
Hunter Expressway Alliance
SOIL AND WATER MANAGEMENT SUB PLAN
HEA - Water Movement Permit
This Water Movement Permit must be carried by the water cart operator taking water, or site supervisor dewatering from any permanent or temporary basin. Once water movement has been completed, this permit must be returned to the Environment
Team. De-watering must be undertaken in accordance to the De-watering Work Procedure.
Date: Operator/Supervisor: Expected start Date: Time:
Expected completion Date: Time:
MU
ST
BE
CO
MP
LE
TE
D F
OR
AL
L W
AT
ER
MO
VE
ME
NT
Where from Basin ID: Extraction Point Permit Number (see over): Chainage: Other (describe):
What purpose Dewatering Dust suppression Other (describe):
If water is used for dust suppression no testing is required. If basin is being de-watered water must be tested and treated according to the De-watering Work Procedure.
Where to
Discharge point ID (Adjacent basin ID): Chainage:
Environment Officer instructions:
Environment Officer sign-off: Date:
Hunter Expressway Alliance
SOIL AND WATER MANAGEMENT SUB PLAN
HEA-PL-GL-SWP-001-00-03_Soil & Water_Final Page 55
APPENDIX C – PROPOSED SEDIMENT BASINS
S:\HEA\01 Environment\01_08 CEMP\Volume 2\Soil & Water\For Final Submission\Appendix C\HEA_Sed Basin Discharges
11/06/2010
Soil and Water Management Sub Plan
Project C = 0.5 Designed
Road Name I = 747.5 Date Designed
1I24hr = 3.52 Checked
Design 85 Date Checked
Se
d B
as
in
Vo
lum
e
Ca
tch
me
nt
Are
a
So
il E
ros
ivit
y
Fa
cto
r (K
)
1 Y
ea
r A
RI
Ma
xim
um
24
Ho
ur
Dis
ch
arg
e
An
nu
al D
isc
ha
rge
Start End X (m) Y (m) m3 ha ML ML
F3 ramp 368828.82 6359953.03 N/A 0.4033 0.036 0.2 1.5 Minmi Creek
F3 ramp 368861.72 6360238.29 576 2.3113 0.036 1.1 8.6 Minmi Creek
F3 ramp 368904.07 6360238.29 487 1.2196 0.036 0.6 4.6 Minmi Creek
300 550 368797.84 6360410.91 392 1.185 0.036 0.6 4.4 Minmi Creek
550 950 368659.93 6360495.38 317 1.2637 0.036 0.6 4.7
950 1500 368318.08 6360680.71 689 1.9667 0.036 1.0 7.4
1500 2050 367312.23 6361007.56 330 1.7936 0.036 0.9 6.7
2050 2350 366954.51 6361207.26 129 1.1555 0.036 0.6 4.3
2350 3200 366723.86 6361257.31 574 2.304 0.036 1.1 8.6
3200 3600 366197.86 6361298.51 608 1.3253 0.036 0.6 5.0
3600 4200 365602.29 6362261.95 1320 2.4956 0.036 1.2 9.3
4200 4700 365555.6 6362639.57 308 0.9067 0.036 0.4 3.4
4700 5250 365226.75 6363031.95 498 1.4951 0.036 0.7 5.6 Surveyors Creek
5250 5550 364958.35 6363248 245 0.76 0.036 0.4 2.8 Surveyors Creek
5250 5550 364909.76 6363201.73 252 0.77 0.036 0.4 2.9 Surveyors Creek
5550 5650 364824 6363267.36 180 0.5885 0.039 0.3 2.2 Surveyors Creek
5650 5750 364759.07 6363324.43 239 0.333 0.039 0.2 1.2
5750 6250 364408.75 6363592.19 447 2.0142 0.039 1.0 7.5
6250 6820 364339.97 6363663.51 918 2.24 0.039 1.1 8.4
6820 7575 363744.24 6364776.34 99 0.204 0.039 0.1 0.8
7575 7750 363770.93 6364805.74 N/A 0.9796 0.039 0.5 3.7W7600
W6250
W5750
W6180
W5650
W7575
W5200
W4200
W600
W1000
W2000
W3200
W2650
W2450
Water Quality Basin
Name
W4700
W5550N
W5550S
W400
W150
W250
W300
Sedimentation Basins 30% Design
Catchment
ChainageDischarge Point
Comments
Hunter Expressway Alliance
F11 Hunter Expressway
Annual Discharge Rates
Impervious Area
Mean Annual Rainfall in mm
1 Yr ARI 24 hr Storm in mm
Percentile
10/06/2010
Receiving Water
1 of 2
S:\HEA\01 Environment\01_08 CEMP\Volume 2\Soil & Water\For Final Submission\Appendix C\HEA_Sed Basin Discharges
11/06/2010
Soil and Water Management Sub Plan
Se
d B
as
in
Vo
lum
e
Ca
tch
me
nt
Are
a
So
il E
ros
ivit
y
Fa
cto
r (K
)
1 Y
ea
r A
RI
Ma
xim
um
24
Ho
ur
Dis
ch
arg
e
An
nu
al D
isc
ha
rge
Start End X (m) Y (m) m3 ha ML ML
Water Quality Basin
Name
Catchment
ChainageDischarge Point
CommentsReceiving Water
7750 363703.49 6365052.44 N/A 0.7932 0.039 0.4 3.0
8010 363442.12 6364981.53 1359 5.1865 0.039 2.5 19.4
8010 8450 363537.57 6365206.17 N/A 1.1173 0.039 0.5 4.2
8450 8600 363413.37 6365559.21 505 1.047 0.039 0.5 3.9
8600 8950 363317.56 6365739.64 343 1.7959 0.039 0.9 6.7
8950 9470 363142.2 6365992.39 660 2.7777 0.039 1.4 10.4
9470 10250 362169.06 6366748.92 2243 8.328 0.039 4.1 31.1 Surveyors Creek
10250 10350 362110.16 6366876.63 N/A 1.04 0.039 0.5 3.9 Surveyors Creek
ramp 362149.08 6366590.7 N/A 0.36 0.039 0.2 1.3 Surveyors Creek
10600 10750 361726.14 6366888.8 N/A 1.0074 0.039 0.5 3.8
10750 11150 361285.7 6367102.9 N/A 1.4619 0.039 0.7 5.5 Averys Creek
11150 11600 361180.94 6367115.17 737 3.0822 0.039 1.5 11.5 Averys Creek
11600 12050 360766.37 6367119.51 356 1.4406 0.039 0.7 5.4
12050 12600 360485.72 6367388.66 834 2.4945 0.039 1.2 9.3
12600 12900 359973.42 6368006.88 333 1.1075 0.048 0.5 4.1
W10200
W7875
W8010
W8450
W8650
W8930
W7870
W11650
W12050
W12900
W10350
RAB W10150
W10700
W11150
W11250
2 of 2
Hunter Expressway Alliance
SOIL AND WATER MANAGEMENT SUB PLAN
HEA-PL-GL-SWP-001-00-03_Soil & Water_Final Page 56
APPENDIX D – ACID SULFATE SOIL MANAGEMENT STRATEGY
Acid Sulfate Soil Management Strategy Seahampton to Kurri Kurri Section
Rev Date Prepared by Reviewed by Approved by Remarks
0 23 March 2010
E Woodward T Doczy P Chatburn
Hunter Expressway Alliance
ACID SULFATE SOIL MANAGEMENT STRATEGY
Acid Sulfate Soil Management Strategy Page 2
TABLE OF CONTENTS
1 INTRODUCTION ............................................................................................................................... 3
1.1 Potential Acid Sulfate Soils (PASS) ................................................................................................... 3 1.2 Actual Acid Sulfate Soils (AASS) ....................................................................................................... 3
2 POTENTIAL IMPACTS ..................................................................................................................... 4
2.1 Causes ............................................................................................................................................... 4 2.2 Effects ................................................................................................................................................ 4
3 IDENTIFICATION of ACID SULPHATE SOILS ............................................................................... 5
3.1 Step One: Visual Assessment ........................................................................................................... 7 3.2 Step Two: pH Field Test .................................................................................................................... 7 3.3 Step Three: Indicator Test ................................................................................................................. 7
3.3.1 Taking the sample .............................................................................................................. 7 3.3.2 Equipment Set Up .............................................................................................................. 8 3.3.3 The Indicator Test............................................................................................................... 8 3.3.4 Finalising the results ........................................................................................................... 8
4 TREATMENT ................................................................................................................................... 11
4.1 Treatment methodology one: ........................................................................................................... 11 4.2 Treatment methodology two: ........................................................................................................... 11
5 MONITORING .................................................................................................................................. 13
6 CONTINGENCY PROCEDURES .................................................................................................... 14
7 DISPOSAL ....................................................................................................................................... 15
7.1 Disposal of potential acid sulfate soils above the water table ......................................................... 16 7.2 Treatment of actual acid sulfate soils prior to disposal .................................................................... 16
APPENDICES
Appendix A - PASS/AASS Sample Sheet ............................................................................................. 17
Hunter Expressway Alliance
ACID SULFATE SOIL MANAGEMENT STRATEGY
Acid Sulfate Soil Management Strategy Page 3
1 INTRODUCTION
This management strategy has been developed in compliance with condition 139 of the Representatives Report for the Hunter Expressway Alliance (HEA), which states:
“Detailed soil testing must be undertaken in areas where acid-sulphate soils may occur, and a management strategy for excavation in acid-sulphate soils must be prepared and issued to contractors as part of construction documentation”.
Areas along the HEA route have been identified as containing potentially acid sulphate soils (Wallis and Fishery Creek). This Management Strategy has been prepared to minimise the risk of environmental damage caused by acid leachate. The Management Strategy applies to all construction activities and has been prepared in accordance with RTA Policy (RTA Procedure DEC - P04).The management strategy addresses the following:
• Identification of Acid Sulphate Soils (RTA Procedure DEC - P01)
• Assessment of the likely impacts of acid sulphate soils (RTA Procedure DEC - P02)
• Selection of treatments for acid sulphate soils (RTA Procedure DEC - P03)
Acid Sulfate Soils are the common name given to soils which contain iron sulfides. The process of acidification of the iron sulfides gives rise to two potentially environmentally damaging soil types:
1.1 Potential Acid Sulfate Soils (PASS)
The iron sulfides are contained in a layer of waterlogged soil. This layer can be clay, loam or sand, and is usually dark grey and soft. The water prevents oxygen in the air reacting with the iron sulfides. This layer has the potential to oxidise to sulfuric acid once exposed to air.
1.2 Actual Acid Sulfate Soils (AASS)
When the iron sulfides are exposed to air and produce sulfuric acid, they are known as actual acid sulfate soils. While soil itself can neutralise some of the sulfuric acid, the remaining acid moves through the soil, acidifying soil water, groundwater and surface waters.
Drainage of water and excavation can expose PASS to the air, causing AASS. Therefore, it is important to quickly identify and control both PASS and AASS to prevent significant environmental damage. If you are working in an area of PASS please become familiar with the testing and associated mitigation measures.
.
Hunter Expressway Alliance
ACID SULFATE SOIL MANAGEMENT STRATEGY
Acid Sulfate Soil Management Strategy Page 4
2 POTENTIAL IMPACTS
2.1 Causes
The following are a list of possible causes of impacts of road construction on sediments containing PASS materials.
1. Excavation of PASS material. Oxidation of this material can result in acid leachate.
2. Discharge of sub-surface water as a result of settlement producing acid leachate where it flows through oxidised AASS.
3. Embankment settlement will depress the underlying material with respect to the water table. In some circumstances heave at the toe of the embankment by displacement may raise PASS material above the water table.
4. Oxidation of pyrite in imported fill material.
2.2 Effects
Should any of the above causes eventuate, the following impacts may result:
• toxifying nearby soil by stripping essential elements and/or dissolving heavy metals
• reducing farm productivity and altering natural vegetation communities
• damage to infrastructure
• death or stunted growth of aquatic flora and fauna
• large scale fish kills and fish disease
• impact on aquaculture
• mass mortalities of microscopic organisms
• increased light penetration due to water clarity
• loss of acid-sensitive crustaceans
• destruction of fish eggs
• loss of habitat
• persistent iron coatings
• alterations to water plant communities
• invasion by acid-tolerant water plants
• reduced spawning success due to stress
• chemical migration barriers
• reduced food resources
• dominance of acid-tolerant plankton species
• changes in food chain and web
• reduced recruitment
• higher water temperatures due to increased light penetration
• increased availability of toxic elements
• reduced availability of nutrients
Hunter Expressway Alliance
ACID SULFATE SOIL MANAGEMENT STRATEGY
Acid Sulfate Soil Management Strategy Page 5
3 IDENTIFICATION OF ACID SULPHATE SOILS
The following procedures have been developed to determine whether the soils contain pyrite (FeS2) to levels where they could be classed as acid sulfate soil, thus requiring treatment. It has been developed based on information provided in the NSW ASSMAC guidelines (1998), and the draft Identification and Investigation of Acid Sulphate Soils guideline (2006) prepared by the WA Department of Environment.
Use the following flow chart to assist in the identification process.
Please note: information provided by Maitland City Council indicates that potential disturbance to acid sulphate soils may occur within the Alliance section of works when working at Wallis and Fishery Creek.
Hunter Expressway Alliance
ACID SULFATE SOIL MANAGEMENT STRATEGY
Acid Sulfate Soil Management Strategy Page 6
Visual Assessment:
Reference Environmentally Sensitive Area Maps. Inspect for odour and colour which may indicate
Potential Acid Sulphate Soil
pH Field Test:
Use field pH kit to test pH.
pH > 5.5:
No Actual Acid Sulphate Soil.
pH <5.5:
Potential Acid Sulphate Soil. Take a sample iand keep frozen until Indicator test can be
undertaken.
Conduct Indicator Test:
Environment staff to conduct indicator test to confirm Actual Acid Sulphate Soil
No response to Indicator Test:
No Acid Sulphate Soil. No further action required
Sample responds to Indicator Test:
Send sample to lab for verification of Acid Sulphate Soil
Hunter Expressway Alliance
ACID SULFATE SOIL MANAGEMENT STRATEGY
Acid Sulfate Soil Management Strategy Page 7
3.1 Step One: Visual Assessment
Visual assessment of PASS or AASS begins using the Environmentally Sensitive Area Maps, which identify all areas of PASS. If working in an area of PASS vigilant visual monitoring should be undertaken during all stockpiling and excavation activities.
It is also important to be able to recognise indicators of actual acid sulfate soils to prevent further acidification of land and waterways. These indicators include:
• cloudy green-blue water
• excessively clear water
• iron stains
• poor pasture
• scalded soil
• yellow jarosite
• ‘rotten egg’ smell
• waterlogged soil
• corrosion of concrete and/or steel structures
• oily-looking surface iron bacterial scum
• dark grey soils (see Figure 2 )
3.2 Step Two: pH Field Test
1. Place a small amount of soil (approx. 5-15 grams) in a beaker
2. Add distilled water to make up a soil :water paste
3. Use either a soil pH test kit or pH meter to ascertain pH value.
Field pH readings of 4 or less, indicate that actual acid sulfate soils are present with sulfides having been oxidised in the past, resulting in acid soils and acidic soil pore water. Readings greater than 4 but less than 5.5 are acid and may be the result of some previous or limited oxidation of sulfides, but is not confirmatory of actual acid sulfate soils; therefore an indicator test is required.
It should be noted that substantial exchangeable/soluble aluminium and hydrogen ions usually exist at these pH values. Other factors such as excessive fertilizer use, organic acids or strong leaching can cause pH values greater than 4 but less than 5.5.
3.3 Step Three: Indicator Test
The Indicator Test measures the existing acidity of a soil/water paste, and is therefore used to help identify AASS.
3.3.1 Taking the sample
1. Visually assess the soil for colour, texture, vegetation, porosity etc. Write down the description along with the soil location, depth, date, time and sample number onto results sheet, and onto the sampling container.
Hunter Expressway Alliance
ACID SULFATE SOIL MANAGEMENT STRATEGY
Acid Sulfate Soil Management Strategy Page 8
2. If you see a yellow jarosite component aim for that in your sample, otherwise, take a representative samples either in an airtight plastic bag or soil jar.
Note; freezing the sample prevents oxidisation but it is best to use samples which have been thawed; therefore if testing is not to be undertaken immediately, freeze samples.
3.3.2 Equipment Set Up
1. Clean the probe with Methylates Spirits or if it has been left for a long time, clean initially with weak hydrochloric acid (HCl) before repeating with Methylates Spirits.
Note: the equipment used for this test may vary, please follow calibration and maintenance instructions recommended by the equipment manufacturer.
2. Calibrate the temperature probe using a standard thermometer.
3. ‘Wash’ the pH probe with pH 4 wash solution then immerse in pH 4 to calibrate.
4. To calibrate the probe; press CAL button, “not ready” should start flashing, when this stops flashing press CFM button to adjust calibration to pH 4.
5. Follow the previous 2 steps using pH 7 buffer, to calibrate to pH 7.
3.3.3 The Indicator Test
1. Place a small amount of soil (approx. 15 grams) in two heat resistant beakers (one shall be used as a control)
Note: The control and test samples should be subsets of the same sample and be as similar in constitution as possible.
2. Cover the Control sample in distilled water and the Test sample with 50% hydrogen peroxide (H2O2) and observe the reactions, make notes on reaction intensity, speed and temperature changes. To increase reaction, place test sample in the sun/near heat. Note: Please undertake this in a very well ventilated area.
3. The reaction should be observed and rated. Continue to observe the reaction until it is complete; from 20 mins to 24 hours. Greater reaction indicates that the soil sample was more likely to have a lower pH, i.e.; super foamy reaction expects a pH of about 2.
4. While the Test sample is reacting, take the pH reading for the Control sample.
5. When reaction of test sample is complete, take pH of the solution. If required add distilled water to increase volume of solution in order to cover the pH probe.
Note: The handling and storage of H2O2 is an OH&S issue and must be managed in accordance with relevant regulations and the MSDS. Conduct this test is a well ventilated area
3.3.4 Finalising the results
1. Write all observations and results onto Results Sheet (included in Appendix One).
All soil samples taken MUST be recorded on the Results Sheet irrelevant of level of testing undertaken and left with the Environment Team staff for reporting purposes.
Hunter Expressway Alliance
ACID SULFATE SOIL MANAGEMENT STRATEGY
Acid Sulfate Soil Management Strategy Page 9
Potentially positive reactions include one or more of the following:
• change in colour of the soil from grey tones to brown tones;
• the release of sulphurous odours;
• a substantial depression in pH below that of “actual” acid sulfate soils (pH 4 or less); and
• pH of less than 3.
The strength of the reaction is a useful indicator. The test is most useful and reliable with clays and loams containing low levels of organic matter. It is least useful on coffee rock, sands, or gravels, particularly dredged sands with low levels of sulfidic material (<0.05 percent S). With soils containing high organic matter (e.g. surface soils, peat, mangrove/estuarine mud and marine clays), care must be taken when interpreting the reaction as high levels of organic matter and other soil constituents particularly manganese oxides can also cause a reaction.
The following table provides information for interpretation of Control pH results:
pH value Result Comments
pH Control ≤4
Actual acid sulfate soils
(AASS) indicating oxidation of sulfides
This is generally not conclusive because
highly organic soils such as peats and occasionally heavily fertilised soils may also give pHF ≤4.
pH Control ≤3.7
Expected if jarosite exists in
the sample
This is also an AASS. Jarosite needs a pH of at least 3.7 to form. Horizons containing some jarosite and some other mottling (iron, grey) may have a pH >3.7 if the sample contains a mixture of jarosite and higher pH soil. This depends on the level of oxidation and the ability of the soil to ‘hold’ the acid.
pH Control >7
Expected in waterlogged,
unoxidised, or poorly drained
soils
Marine muds commonly have a pH >7 and this reflects seawater (pH 8.2) influence. May be a
PASS after oxidation with H2O2 .
4 < pH Control ≤5.5 An acid soil Investigate further for possible ASS link, e.g.
AASS with shell presence.
A combination of the following three factors is considered in arriving at a ‘positive’ identification of AASS:
a) A reaction with hydrogen peroxide - the strength of the reaction with peroxide is a useful indicator but cannot be used alone. Organic matter, coffee rock and other soil constituents such as manganese oxides can also cause a reaction. Care should be exercised in interpreting a reaction on surface soils and high organic matter soils such as peat and coffee rock, and some mangrove/estuarine mud and marine clays. This reaction should be rated, e.g.
L = Low reaction,
M = Medium reaction,
Hunter Expressway Alliance
ACID SULFATE SOIL MANAGEMENT STRATEGY
Acid Sulfate Soil Management Strategy Page 10
H = High reaction,
V = volcanic reaction,
X = Extreme reaction (very vigorous, gas evolution and heat generation)
b) The actual value of pHFOX (i.e. Hydrogen peroxide/soil solution in the Test sample after the reaction has finalised). If pHFOX <3, and a significant reaction occurred, then it strongly indicates a PASS. The more the pHFOX drops below 3, the more positive the presence of inorganic sulfides.
c) A much lower pHFOX than Control sample pH - The lower the final pHFOX value and the greater the difference between the pHFOX compared to the Control pH, the more indicative the presence of PASS. This difference may not be as great if starting with an already very acid pH (close to 4), but if the starting pH is neutral or alkaline then a larger change in pH should be expected. Where fine shell, coral or carbonate is present the change in pH may not be as large due to buffering. The ‘fizz test’ (effervescence with 1 M HCl) should be used to test for carbonates and shell.
Of these three factors, the final pHFOX value is the most conclusive indicator, and the lower the final pHFOX, the more confident one can be that PASS may be present.
2. Send off all samples with a significant pH drop between control and test samples, a very low pH, or a very strong/fast reaction with the Hydrogen peroxide.
All soil samples must remain frozen until Indicator Test, and if required subsequent lab analysis, is performed.
3. Keep probe moist when not in use, store in its cap with a touch of HCl.
Note: follow manufacturer’s maintenance instructions for the equipment you are using.
Hunter Expressway Alliance
ACID SULFATE SOIL MANAGEMENT STRATEGY
Acid Sulfate Soil Management Strategy Page 11
4 TREATMENT
Estimate the potential amount of soil that may be disturbed and determine a treatment area large enough to contain all excavated PASS or AASS. Treatment areas shall meet the following requirements:
a) Be located at least 50m from waterways
b) Be constructed with impervious clay bunds to prevent leachate runoff.
c) Be lined with agricultural lime on the floor of the treatment area.
The treatment area will require a settlement pond or sump to collect any runoff. The pond or sump must be designed to capture the PASS treatment area runoff a 1 in 10 year (1 hour) storm event.
4.1 Treatment methodology one:
Soil shall be laid in 300mm layers and treated with lime. The soil shall be turned over/ mixed to ensure adequate mixing. Surface applications of lime shall be applied to the treatment area at a rate capable of neutralising all acid waters that might infiltrate through PASS/AASS, prior to placing PASS/AASS in the treatment areas. The minimum application rate should be equivalent to no less than 50t of fine agricultural lime/ha (or 5kg fine agricultural lime/m2, or 20kg/m3). This application may need to be increased depending on stockpile height and actual and potential acidity of the AASS.
Note: Refer to laboratory results and recommendations for final dosing rates.
4.2 Treatment methodology two:
Where the rate required is below 2kg/m3 the material will not be treated but will be stockpiled for later use as topsoil for the works.
Where the dose rates are between 2kg/m3 and 10kg/m3, agricultural lime will spread over the area at the required rate and tyned in prior to excavation and stockpiling of the material. The base of the stockpile site will be lined with lime at 0.5kg/m2 to neutralise any water that may seep into the ground water. A sump hole will be excavated near the stockpile to enable runoff to be captured and tested to confirm the water quality leaving the material. The topsoil material will then be used in topsoiling the works.
Where the dose rates are above 10kg/m3, the material to be excavated will be separated based on its acid potential and stockpiled in a bunded area on a bed of lime at 1.0 kg/m2. This material will then be tested to confirm the appropriate dose rate and treated accordingly. A sump will be provided within the bunded area to allow the runoff to be checked for conformance. This material shall remain bunded until test results available. The stockpile will then have the additional lime added if required. After treatment, this material can then be placed in mounds for landscaping purposes compacted and covered with a minimum of 500mm of non PASS material or used to backfill piles and pile caps.
Hunter Expressway Alliance
ACID SULFATE SOIL MANAGEMENT STRATEGY
Acid Sulfate Soil Management Strategy Page 12
Figure 3: Example of an AASS treatment area.
Hunter Expressway Alliance
ACID SULFATE SOIL MANAGEMENT STRATEGY
Acid Sulfate Soil Management Strategy Page 13
5 MONITORING
A programme of regular water quality monitoring will be established involving monitoring of the water within creeks and rivers adjacent to construction. Random checking of the pH of excavated materials will be carried out on site. Additional testing will be arranged if pH levels are below background values.
Where surface water and/or leachate collects within the bunded treatment area, the water shall be tested for pH, turbidity and TSS values prior to discharge or pumped directly to a sedimentation basin. Should pH results be lower than 5, further treatment may be required.
Any runoff or fines collected in the settlement pond/sump will require assessment prior to decommissioning of the stockpile area.
Regular visual monitoring of PASS/AASS areas and surrounds shall be undertaken to identify signs of ASS oxidation. This monitoring should include detecting:
• Unexplained scalding, degradation or death of surrounding vegetation;
• Unexplained death or disease in aquatic organisms
• Formation of the mineral jarosite and other acidic salts in exposed or excavated soils
• Areas of green-blue water or extremely clear water indicating high concentrations of aluminium
• Rust coloured deposits on plants and on the banks of drains, water bodies and watercourses indicating iron precipitates
• Black to very coloured waters indicating de-oxygenation
Final validation sampling of treated soils will be conducted at the completion of treatment to determine if the neutralisation process has been successful. Validation sampling will be conducted in accordance with the Acid Sulfate Soil Manual (ASSMAC, 1998).
Hunter Expressway Alliance
ACID SULFATE SOIL MANAGEMENT STRATEGY
Acid Sulfate Soil Management Strategy Page 14
6 CONTINGENCY PROCEDURES
If PASS is suspected, appropriate actions must be taken to ensure the PASS is not able to oxidise in the field. For example:
• If PASS is shown to occur in the vicinity of your work area, choose a construction method that avoids the need to disturb PASS.
• If avoidance of PASS is not possible, notify environment staff of upcoming works at least 5 days prior to commencement of activities.
Any material that does not conform to the expected or tested levels and exhibits a high PASS will be either left in place, or if already excavated will be isolated and a suitable treatment method devised. Although experience has shown that any potential pollution does take time to develop close monitoring will be carried out until suitably treated. If a serious situation does develop in the interim immediate treatment with lime will be carried out. If PASS is suspected, appropriate actions must be taken to ensure the PASS is not able to oxidise in the field.
Hunter Expressway Alliance
ACID SULFATE SOIL MANAGEMENT STRATEGY
Acid Sulfate Soil Management Strategy Page 15
7 DISPOSAL
Once treatment has occurred, onsite re-use and/or disposal of the treated soil shall be undertaken. Testing of soil Ph shall be carried out by the Environment Team prior to reuse onsite. This material can be placed in mounds, extended batters or for landscaping purposes, compacted and covered with a minimum of 500mm of non PASS material or used to backfill piles and pile caps.
If off-site disposal is required, procedures outlined within the document Waste Classification Guidelines, Part 4: Acid Sulphate Soils (DECCW 2008) shall be implemented.
This includes the following:
• Keep potential ASS wet at all times during excavation and subsequent handling, transport and storage until they can be disposed of safely.
• ASS must be received at the proposed disposal point within 16 hours of being dug up.
• Potential ASS may be disposed of in water below the permanent water table, provided:
this occurs before they have had a chance to oxidise, i.e. within 24 hours of excavation
they meet the definition of ‘virgin excavated natural material’ (VENM) under the Protection of the Environment Operations Act 1997, even though they contain sulfidicores or soils.
• Landfills shall be licensed by DECC to dispose of potential ASS below the water table.
• DECC’s Environment Line has details on facilities able to accept this waste: phone 131 555.
• Potential ASS must be disposed of within 8 hours of their receipt at a landfill and kept wet at all times until their burial at least 2 metres below the lowest historical level of the water table at the disposal site.
• Documentation must be provided to the occupier of the landfill for each truckload of potential ASS received, indicating that the soil’s excavation, transport and handling have been in accordance with the Acid Sulfate Soil Manual, thus preventing the generation of acid.
• The occupier of the disposal site must also test the pH of each load of soil received immediately prior to its placement under water using the test method(s) in the Acid Sulfate Soil Manual (Methods 21A and/or 21Af). These details, together with the pH of the soil recorded at the time of its extraction, must be retained by the occupier of the landfill site.
• The disposal site’s licence will outline what documentation needs to be kept and for how long.
• Soil that has dried out, undergone any oxidation of its sulfidic minerals, or which has a pH of less than 5.5 must be treated by neutralisation and disposed of at a landfill that can lawfully accept it (see ‘Disposal of actual acid sulfate soils’ below).
• The pH of the water at the landfill into which the potential ASS is placed must not be less than 6.0 at any time. Landfill licence conditions require the occupiers of potential ASS disposal sites to regularly monitor the pH of ground and surface waters at their premises.
Hunter Expressway Alliance
ACID SULFATE SOIL MANAGEMENT STRATEGY
Acid Sulfate Soil Management Strategy Page 16
7.1 Disposal of potential acid sulfate soils above the water table
• Where potential ASS cannot be classified as VENM or a suitable underwater disposal site at a landfill is not available, the soil must be treated in accordance with the neutralising techniques in the Acid Sulfate Soil Manual. After treatment the soil should be chemically assessed in accordance with Step 5 in Part 1 of the Waste Classification Guidelines, available at www.environment.nsw.gov.au/waste/envguidlns. This will determine whether any other contaminants are present in the material. When the classification has been established, the soil should be disposed of to a landfill that can lawfully accept that class of waste.
• Actual ASS contain highly acidic soil horizons or layers resulting from the aeration of soil materials that are rich in iron sulfides, primarily sulfide. This oxidation produces more hydrogen ions than the sediment is able to neutralise, resulting in soils with a pH of 5.5 or less when measured in dry season conditions. These soils can usually be identified by the presence of pale yellow mottles and coatings of jarosite.
7.2 Treatment of actual acid sulfate soils prior to disposal
• Actual ASS must be treated by the generator of the waste before they can be considered for disposal. Treatment should be in accordance with the neutralising techniques outlined in the Acid Sulfate Soil Manual.
• Following neutralisation, the generator of the waste must chemically assess the soil in accordance with Step 5 of the Waste Classification Guidelines: Part 1 – Classifying waste
• (available at www.environment.nsw.gov.au/waste/envguidlns). This will determine whether there are any other contaminants that may affect how the waste is classified for disposal.
• Once classified, the waste must be taken to a landfill licensed to accept that class of waste.
• Prior arrangements should be made with the occupier of the landfill to ensure that it is licensed to accept the waste. The landfill should be informed that the actual ASS has been treated in accordance with the neutralising techniques outlined in the Acid Sulfate Soil Manual and that the waste has also been classified in accordance with Part 1 of the Waste Classification Guidelines.
(Source Document: Waste Classification Guidelines, Part 4: Acid Sulphate Soils (DECCW 2008)
Hunter Expressway Alliance
ACID SULFATE SOIL MANAGEMENT STRATEGY
Acid Sulfate Soil Management Strategy Page 17
Appendix A - PASS/AASS Sample Sheet
Combined field description and ASS data
Sample ID Soil Description (e.g. clay, silt, sand, colour)
pH Control pH Test pH Control - pH Test
Reaction Rate Temp.
Sent for testing
pH units pH units pH units L,M,H,X,V 0C YES/NO
#This reaction should be rated, e.g. L = Low reaction, M = Medium reaction, H = High reaction, X = Extreme reaction, V = volcanic reaction.
Hunter Expressway Alliance
SOIL AND WATER MANAGEMENT SUB PLAN
HEA-PL-GL-SWP-001-00-03_Soil & Water_Final Page 57
APPENDIX E – AFFLUX PRELIMINARY IMPACT ASSESSMENT
Hunter Expressway Alliance
SOIL AND WATER MANAGEMENT SUB PLAN
Water Input to Soil-Sed-Erosion Plan - CoA 93oA 93 Page 1
APPENDIX D – AFFLUX PRELIMINARY IMPACT ASSESSMENT (LOCAL AND REGIONAL)
Rev Date Prepared by Reviewed by Approved by Remarks
00 11-5-10 Terry Swanson Howard Chemney
Hunter Expressway Alliance
SOIL AND WATER MANAGEMENT SUB PLAN
Water Input to Soil-Sed-Erosion Plan - CoA 93oA 93 Page 2
SCOPE
This appendix reviews the afflux impacts upstream and downstream of cross-drainage culverts and bridges that form part of the Hunter Expressway Alliance Project (the Project). The appendix also considers the impacts of the motorway embankment in a regional flooding context.
This Soil and Water Management Sub Plan forms part of the Construction Environmental Management Plan (CEMP) for the Hunter Expressway, National Highway Link. This appendix has been developed in response to Condition of Approval No. 93 which requires the following::
93 . The Soil and Water Management Sub Plan shall identify mitigation measures proposed to be taken to address any:
i. Afflux impacts from the roadway or structures associated with the proposal eg. The proposed Wallis/Surveyors Creek crossing and impacts upstream in the Buchanan area; and
ii. Adverse impacts from the proposal as a result of losses to the Hunter River floodplain storage area for flood events above and including the 1% Annual Exceedence Probability Event eg. The Wentworth and Dagworth Swamps.
AFFLUX IMPACTS - METHODOLOGY
Calculation Methods
The cross drainage design will include hydraulic calculations for watercourses that are crossed by the HEA works to determine flooding and impacts.
The flows in the watercourses crossing the motorway will be determined and verified using a mixture of hydrological methods as follows:
Existing Flood Studies
XP-RAFTS (Catchment Specific)
Flow Rating Curve (derived from XP-RAFTS)
Rational Method (Rural)
The sizing of the watercourse crossing structures for the motorway will be determined and verified using a mixture of hydraulic methods as follows:
RMA-2 Two Dimensional Flood Model
HEC-RAS One Dimensional Flood Model
Excel Spreadsheet – Waterway Design Guide Methods
Design Events
Culverts will be sized for the design events as set out in Table D1.
Table D1.
Cross Drainage Element Design Events Refer Note
Culvert Crossing the Motorway 50,100 1,2
Bridge Crossing the Motorway 100, 2000, PMF 3,4
Culvert Crossing a Local Road or Motorway Access Ramp
20,50,100 1,2
Bridge Crossing a Local Road or Motorway Access Ramp
20,50,100, 2000,PMF
1,3,4
Culvert Crossing Private Access Track 1 2
Notes:
1. Selected design event will be dependent upon the identified afflux acceptability
2. An overland flowpath review will be undertaken to assess the impacts of a blockage where culverts (pipe or box) form the cross-drainage element.
3. A structural adequacy assessment will be undertaken using the 1 in 2000 year flood event.
4. An overland flowpath review will be undertaken for the probable maximum flood (PMF) event.
In addition to the above design events a number of additional events including the 1, 5, 10 year flood events will also be assessed to demonstrate no detrimental impacts.
In order to provide a hydrological/hydraulic approach that ensures an assessment of the motorway work impacts only, the following catchment scenarios will be modelled:
Baseline – the baseline catchments will be based on the 2010 level of development as determined from the Cessnock/Maitland Council LEP’s and aerial photography.
Post – Development - the post development catchment will be based on the 2010 level of development as determined for the baseline with the addition of any motorway works. Any changes to catchment areas, connectivity or runoff potential will be reflected.
Ultimate - the ultimate development catchment will be determined on the 2115 level of development as set out in the Cessnock/Maitland Council LEP’s and include the motorway works. Any changes to catchment areas, connectivity or runoff potential will be reflected.
Therefore for purposes of assessing the impacts of the motorway a comparison of flood levels and other flood data will be undertaken using the Baseline and Post-Development scenarios.
For purposes of confirming the motorway has 100yr flood immunity during its design life an assessment of flood levels and other flood data will be undertaken using the Ultimate scenario.
Afflux Acceptability Criteria
The cross drainage infrastructure will be designed to prevent damage or not worsen impacts (i.e. where existing impact identified) to existing property and infrastructure.
An afflux acceptability assessment will be undertaken for each culvert and bridge location. The level of sensitivity of the design solution to afflux will be based on a localised risk assessment that considers the following as a minimum:
i. land ownership/usage/zoning
ii. proximity of sensitive property or infrastructure
iii. material and immaterial loss to private or public property and infrastructure
iv. potential for negative environmental impacts
v. impacts on motorway embankment
vi. impacts on local road embankment and road overtopping
vii. overland flowpath potential
viii. public safety
Table D2. summarises the target and absolute afflux limits to be set in the assessment of the impacts of the motorway on waterways crossed.
Table D2.
Assessed Sensitivity
Target (mm)
Absolute (mm)
Comment
High 0 +10mm To be used where any material loss to property/infrastructure potentially occurs. To be used where impacts to the environment, public safety or motorway /local road operation are highly undesirable or cannot be satisfactorily mitigated against.
Medium 0 +50mm To be used where immaterial loss property/infrastructure potentially occurs. To be used where impacts to the environment, public safety or motorway /local road operation are moderately undesirable or where
satisfactory mitigation can be provided.
Low 0 Varies but generally >50mm
To be used where no material or immaterial loss potentially occurs. To be used where impacts to the environment, public safety or motorway /local road operation are minor and where no mitigation is required.
None N/A N/A To be used where afflux impacts are wholly contained with land within the RTA’s ownership
Note:
High Sensitivity – this will generally occur where flooding of a private property (above floor flooding) or key infrastructure (ie substation) is impacted. This will also occur where sensitive environments or key amenity facilities are impacted. Flooding afflux that can result in more local road closure (or more frequent) or unacceptable exposure of the motorway embankments to water surcharge/wetting.
Medium Sensitivity – this will generally occur where flooding of a private property/field outside the habitable areas is impacted and land use or access may be impacted. Localised mitigation treatment may be provided to reduce any impacts of the flooding. Subject to potential negotiation and agreement with some affected landowners this may be reclassified to a low sensitivity.
Low Sensitivity – this will generally occur where flooding of a private property/field outside the habitable areas is impacted. Localised mitigation treatment may be provided to reduce any impacts of the flooding.
None - this will generally represent land located within the HEA boundary or fields/forest owned by the RTA or State Government. Subject to potential negotiation and agreement with some affected landowners (if any), private fields may be reclassified to this sensitivity.
AFFLUX IMPACTS - ASSESSMENT
A preliminary assessment of afflux impacts has been undertaken using the Rural Rational Method hydrology and culvert inlet and outlet control hydraulic calculations. A number of the bridge crossings have been modelled using RMA-2 or HEC-RAS. The afflux acceptability criteria has been applied to the afflux results and upstream and downstream mitigation recommended where required.
Table D3. contains this assessment.
The assessment generally confirms that afflux impacts for the majority of culverts and bridge crossings are generally limited and either restricted to land within RTA ownership or areas of grazing/woodland.
The afflux impacts around the Wallis/Surveyors Creek and nearby Buchannan area are also generally limited to land within the RTA ownership. While a minor increase in flood level of 20mm is currently predicted to an individual habitable property (Mr J R & Mrs. M E & Ms. T M Hooley) this will be reduced at least to the absolute level requirement (+10mm) as part of the detailed design. It is expected that only minor changes to the bridge openings and spill through batters would be required to achieve this.
REGIONAL FLOOD IMPACTS
A preliminary draft report of the “Hunter River: Branxton to Green Rocks Flood Study was provided to the HEA. A full review of this report was undertaken and key points to note are as follows:
Modelling has been undertaken using a 2D flow model (TUFLOW) A 36 hour duration event was used to produce peak design flows The Hunter River has a catchment area of some 15600km2 upstream of Maitland A number of significant flood events have occurred on the Hunter River including the
flood events of 1955, 1971,1977 and 2007 which were used for calibration The timing of flows from a number of tributaries including Wallis Creek can have a
significant impact on flood levels associated with low areas of these creek systems as the flood plain areas can fill in advance of the main Hunter River peak.
The HEA motorway embankment and realigned John Booth Drive and George Booth Drive road embankments will be built out into the Wallis/Surveyors Creek floodplain. The embankment footprint area of some 0.25 km² represents a negligible percentage of the Hunter River regional flood footprint. The impact of the loss of flood storage in a regional context is negligible.
Regional flood events impacting on Wallis Creek will occur as local storage (river-locking) and backwater from the Hunter River as flood flows overtop the existing flood levees. The timescale of such an event is measured in days rather than hours and therefore the flood mechanism is controlled by volumetric constraints (i.e. a big pond) rather than backwater conveyance at particular structures (unless these are particularly constrictive).
The George Booth Drive and John Renshaw Drive bridge/culvert structures are to be reconstructed with a similar waterway area to the existing structures and therefore no impacts to regional backwater conveyance is expected.
The HEA motorway bridge opening of 176m results in a minor local afflux of some 300mm for the 100yr peak local flood event and therefore is not considered to represent a meaningful constriction to flow in a regional context. Therefore no impacts to regional backwater conveyance and flood flow balancing are expected in the Buchannan area.
HW (RL)HW
Depth (m)
AFFLUX (approx)
(M)
Land ownership upstream of Culvert/Bridge Location
Property Impact Type
Environment Impact
Public Safety
Impact Sensitivity Mitigation/Comment
Land ownership downstream of Culvert
LocationDownstream Issues Mitigation/Comment
C0016SRa 46.20 3.39 2.44 RTA Woodland Low Low None No mitigation required from cross drainage RTA None No mitigation required from cross drainage
C0020SR 56.98 0.58 0.39 RTA Woodland Low Low None No mitigation required from cross drainage RTA None No mitigation required from cross drainage
C0025SR 50.60 0.28 0.17 RTA Woodland Low Low None No mitigation required from cross drainage RTA None No mitigation required from cross drainage
BW06, BW07a, BW07b,
N/A N/A 0.00 RTA Woodland, Heritage Low Low None Bridge structures have clear span over Minmi Creek RTA None No mitigation required from cross drainage
C0054 41.48 4.12 3.18 Coal & Allied Woodland Low Low Low
Increased flood level is contained in Bush Land with minimal impact. An alternative arch culvert solution is also being considered here subject to structural and cost review.
Coal & Allied None No mitigation required from cross drainage.
C0082 64.31 1.81 1.75 Coal & Allied Woodland Low Low None No mitigation required from cross drainage Coal & AlliedExisting survey detail suggests no defined channel downstream.
Flow spreader to be utilised to return culvert outlet flow to sheet flow
C0096 72.42 1.37 1.30 Coal & Allied Woodland Low Low None No mitigation required from cross drainage Coal & AlliedExisting survey detail suggests no defined channel downstream.
Flow spreader to be utilised to return culvert outlet flow to sheet flow
BW09 (TWIN) N/A N/A 0.00 RTA Woodland Low Low NoneViaduct 1 structure has clear span over local watercourse
RTA None No mitigation required from cross drainage
BW10 (TWIN) N/A N/A Minor RTA Woodland Low Low NoneViaduct 2 structure has clear span over local watercourse with minor pier encroachment for larger events
RTA None No mitigation required from cross drainage
BW11 (TWIN) N/A N/A Minor RTA Woodland, Heritage Low Low NoneViaduct 3 structure has clear span over local watercourse with minor pier encroachment for larger events. Existing Burrenjim Dam unaffected by afflux
RTA None No mitigation required from cross drainage
C0282 66.42 2.01 1.83 Coal & Allied Woodland Low Low None No mitigation required from cross drainage Coal & Allied Discharges direct to Bluegum Creek - No issues No mitigation required from cross drainage
C0287 65.98 2.29 2.02 Coal & Allied Woodland Low Low None No mitigation required from cross drainage Coal & Allied Discharges direct to Bluegum Creek - No issues No mitigation required from cross drainage
C0324 79.69 2.39 2.31 Coal & Allied Woodland Low Low None No mitigation required from cross drainage Coal & Allied None No mitigation required from cross drainage
C0340 82.57 1.88 1.60 Coal & Allied Woodland Low Low None No mitigation required from cross drainage Coal & Allied None No mitigation required from cross drainage
C0388 77.87 1.20 0.97 Coal & Allied Woodland Low Low None No mitigation required from cross drainage Coal & AlliedConcrete channel required downstream to return flow to natural channel
No mitigation required from cross drainage
C0408 61.24 1.53 1.35 Coal & Allied Woodland Low Low None No mitigation required from cross drainage Coal & Allied No mitigation required from cross drainage No mitigation required from cross drainage
C0436SR 56.45 0.56 0.14 Coal & AlliedWoodland and Landowner Access
Low Medium Medium
Culvert designed to pass 1:20 year storm. Detailed design to ensure the current level of flood immunity for the Daracon Access road is maintained. See C0446 also.
Coal & Allied None No mitigation required from cross drainage
C0446 48.74 2.24 1.10 Coal & Allied Woodland Low Low Medium
The 100 year backwater from culvert C0446 does not overtop the Daracon Access road but the backwater may affect the current capacity of the Daracon Access culverts. Detailed design to ensure the current level of flood immunity for the Daracon Access road is maintained.
Coal & Allied None No mitigation required from cross drainage
C0522 44.67 1.49 0.77 Coal & Allied Woodland Low Low None No mitigation required from cross drainage Coal & Allied Existing survey detail suggests no defined channel downstream.
Flow spreader to be utilised to return culvert outlet flow to sheet flow
BW13 N/A N/A N/A Coal & Allied Woodland Low Low None No mitigation required from cross drainage Coal & Allied Channel realignment to join to existing channel No mitigation required from cross drainage
C0573 30.24 2.53 2.35 Coal & Allied Woodland Low Low None No mitigation required from cross drainage Coal & Allied None No mitigation required from cross drainage
C0585 37.08 1.33 1.13 Coal & Allied Woodland Low Low None No mitigation required from cross drainage Coal & Allied Existing survey detail suggests no defined channel downstream.
Flow spreader to be utilised to return culvert outlet flow to sheet flow
C0624 35.91 3.41 3.03 Mindaribba LALC Woodland Low Low None No mitigation required from cross drainage Mindaribba LALC Existing survey detail suggests no defined channel downstream.
Flow spreader to be utilised to return culvert outlet flow to sheet flow
C0732 25.34 3.34 2.83 Mindaribba LALCGrazing (D/S), Woodland (U/S)
Low Low LowHW located over RTA project boundary but is located in undeveloped bushland. No mitigation required from cross drainage
Mrs. M J HolmesNo defined Channel downstream culvert concentrates flow
Flow spreader to be utilised to return culvert outlet flow to sheet flow
C0749 27.56 1.83 1.70Mindaribba LALC/County Property holdings
Grazing Low Low None No mitigation required from cross drainage Tp & Mj Holmes pty Ltd.No defined Channel downstream culvert concentrates flow
Flow spreader to be utilised to return culvert outlet flow to sheet flow
C0766 30.18 1.45 1.25 County Property holdings Grazing Low Low None No mitigation required from cross drainage Tp & Mj Holmes pty Ltd.No defined Channel downstream culvert concentrates flow
Flow spreader to be utilised to return culvert outlet flow to sheet flow
100YR ARI EVENT UPSTREAM AFFLUX ASSESSMENT 100YR ARI EVENT DOWNSTREAM AFFLUX ASSESSMENT
C0789 24.55 1.68 1.37 Tp & Mj Holmes pty Ltd. Grazing Low Low None No mitigation required from cross drainage Tp & Mj Holmes pty Ltd. None None
C0789SR 22.68 1.95 1.62 Tp & Mj Holmes pty Ltd. Grazing Low Low None No mitigation required from cross drainage Tp & Mj Holmes pty Ltd. No defined Channel downstream culvert concentrates flow
Flow spreader to be utilised to return culvert outlet flow to sheet flow
C0806 21.96 1.06 0.88 Tp & Mj Holmes pty Ltd. Grazing Low Low None No mitigation required from cross drainage Tp & Mj Holmes pty Ltd. No defined Channel downstream culvert concentrates flow
Flow spreader to be utilised to return culvert outlet flow to sheet flow
C0858 16.46 1.82 1.61 Tp & Mj Holmes pty Ltd. Grazing Low Low Low
HW located over RTA project boundary but is located semi cleared grazing land with minimal impact expected for more frequent flood events. No mitigation required from cross drainage
Tp & Mj Holmes pty Ltd.No defined Channel downstream culvert concentrates flow
Flow spreader to be utilised to return culvert outlet flow to sheet flow
C0895 20.35 2.59 2.32 Tp & Mj Holmes pty Ltd. Grazing Low Low Low
HW located over RTA project boundary but is located semi cleared grazing land with minimal impact expected for more frequent flood events. No mitigation required from cross drainage
Tp & Mj Holmes pty Ltd.
No defined Channel downstream culvert concentrates flow. Diverted catchments from U/S of the Buchannon Motorway cut to this location will increase flow.
Flow spreader to be utilised to return culvert outlet flow to sheet flow. Flows will pass through some 150m of grazing land before entering Surveyors Creek. A farm dam low lying marsh areas are located along this route. Increased flow are likely to benefit farm dam with low impact on grazing zone. No mitigation required from cross drainage.
C0978 28.63 2.68 2.38 Tp & Mj Holmes pty Ltd. Woodland Low Low None No mitigation required from cross drainage Tp & Mj Holmes pty Ltd.No defined Channel downstream culvert concentrates flow.
Additional Survey may show defined channel.
C1013SRa N/A N/A Minor Tp & Mj Holmes pty Ltd. Grazing Low Low Low
Existing culvert to be replaced with like to ensure no increase in flow downstream to property access. A minor increase in catchment area draining to this culvert will occur as a result of the road realignment. A minor HW increase may occur and extend beyond the RTA project boundary, however the impact is likely to be mimimal, affecting an existing low area used to store water for grazing. No mitigation required from cross drainage
Mrs. C I & Mr. L L Beveridge
No defined channel downstream and culvert potentially concentrates flow. Flow path currently crosses landowners access track. No existing culvert under landowners track
Confirm that landowner will formalise pipe under their final track (currently temporary). Flow spreader to be utilised to return culvert outlet flow to sheet flow
C1013SRb 15.56 0.76 0.68 RTA Woodland Low Low None No mitigation required from cross drainage RTA None No mitigation required from cross drainage
BW170.2m (Smith), 0.2- 1.0m (RTA)
RTA & Mr M L & Mrs. B M Smith
Grazing Low LowMeduim (Smith), None (RTA)
Afflux impacts on a small area of the Smith property and is considered minimum as the affected area consist of a farm dam and immediate surrounds. The detailed design and flood modelling will review the Wallis/Surveyors Creek motorway bridges and cross-drainage with view to reducing this impact. Afflux impacts contained within RTA land ownership are acceptable.
Mrs. C D ShearmanSlight impact from AFFLUX, but not measurable (<0.01m)
No mitigation required from cross drainage
BW19
0.01 -0.03 (0.02 at Hooley House)
Mrs. M M Percival, Mr C R & Mrs. L Parker, Mr J R & Mrs. M E & Ms. T M Hooley
Grazing Low LowHigh (Hooley) Low(Others)
Afflux impacts occur on these upstream properties which are already significantly flood impacted by the existing 100yr flooding. The Hooley property contains a house which is already innundated to a significant depth while the other properties are used for grazing. The detailed design and flood modelling will review the Wallis/Surveyors Creek motorway and local road bridges and cross-drainage with view to reducing this impact.
RTA & Mr M L & Mrs. B M Smith
See BW17 U/S Comment See BW17 U/S Comment
BW18 0.01 -0.03Mrs. M M Percival, Mr C R & Mrs. L Parker, Mr J R & Mrs. M E & Ms. T M Hooley
Grazing Low Low High Same as BW19RTA & Mr M L & Mrs. B M Smith
Same as BW19 Same as BW19
C1074 1.00 RTA Grazing Low Low NoneFlood relief culvert and potential linkage between farm dams. No mitigation required from cross drainage
Mrs. C D ShearmanDischarges into farm dam - no issues predicted from cross drainage catchment.
No mitigation required from cross drainage
BW20 0.70 MRS D L & Mr W J Wade Grazing Low Low Low
Increase in upstream flood extents is minimal but beyond the RTA ownership boundary, innundating an area containing several farm ponds. and impact is negligible. No mitigation required from cross drainage.
Mrs. C D Shearman None No mitigation required from cross drainage
C1132SR 7.62 4.10 0 (regional), 1.3 (local)Mrs. C D Shearman Grazing Low Medium Low
The provision of the Shearmans access track across Avery's Creek will result in increased local event flooding behind the road embankment. This access will be utilised for lower flood events while a controlled gated access direct to the motorway will be utilised for larger flood events that cut the access track off. Works are being undertaken in consultation with the landowner and no further mitigation is required from cross drainage.
Mrs. C D Shearman & Mr. Ljg Elliott
Discharges into wet pond area - no issues predicted from cross drainage catchment.
No mitigation required from cross drainage
BW23 8.98 4.40 -1.20 Mrs Dc Ferguson Grazing Low Low None None MRS D L & Mr W J Wade See BW20 U/S comment See BW20 comment
C1150SR 19.40 0.78 0.64 RTA Grazing Low Low None None RTA None No
C1163 13.53 1.44 1.35 MR J L & Mrs K A Pyne Grazing Low Low None None RTA None No
C1206 17.76 1.49 0.91 State of NSW Woodland Low Low LowHW located over RTA project boundary within semi cleared land that is state owned. Impact is minimal and no mitigation required from cross drainage
Mr G J & Mrs. P J Field, Mr J L & Mrs. K A Payne
None No mitigation required from cross drainage
C1220 22.67 1.58 1.38 State of NSW Woodland Low Low None No mitigation required from cross drainage State of NSW None No mitigation required from cross drainage
C1290 26.61 1.01 0.86 State of NSW Woodland Low Low None No mitigation required from cross drainage State of NSWCulvert creates concentrated flow at downstream end
Flow spreader on outlet to return outlet to sheet flow
NotesAfflux assessment has been based on 100 yr ARI Storm Event on all culverts crossing the Hunter Expressway. Culvert C0436SR crossing Daracon Access Road has been assessed based on a 20yr ARI event. Culverts C1013SRa and C1013SRb have been assessed based on a 10 yr ARI event