stakeholder engagement plan - sppmb.npt.evn.vn
TRANSCRIPT
VIETNAM ELECTRICITY
NATIONAL POWER TRANSMISSION CORPORATION
_____________________________
RENEWABLE ENERGY ACCELERATING CHANGE (REACH)
STAKEHOLDER ENGAGEMENT PLAN (SEP) (DRAFT DOCUMENT)
APRIL 2021
STAKEHOLDER ENGAGEMENT PLAN (SEP)
Renewable Energy Accelerating Change (REACH) P a g e | i
PREFACE
This document is called the Stakeholder Engagement Plan (SEP) for the “Renewable Energy
Accelerating Change (REACH)”. It is developed in compliance with World Bank’s
Environmental and Social Framework (ESF), specified in the Environmental and Social Standard
10 (ESS10) - Stakeholder Engagement and Information Disclosure. This SEP defines a process
and approach to stakeholder consultations and disclosure for 6 provinces under REACH,
including: Dak Lak, Dak Nong, Binh Phuoc, Tay Ninh, Ba Ria – Vung Tau and Dong Nai
Provinces.
STAKEHOLDER ENGAGEMENT PLAN (SEP)
Renewable Energy Accelerating Change (REACH) P a g e | ii
TABLE OF CONTENTS
I. INTRODUCTION ......................................................................................................... 1
1.1. Project Overview ...................................................................................................... 1
1.2. Objectives of the REACH ........................................................................................ 1
1.3. Project Components ................................................................................................. 1
1.4. Project Environmental and Social Risks and Impacts ................................................ 3
1.5. Objectives of SEP .................................................................................................... 3
II. LEGAL FRAMEWORK .............................................................................................. 4
2.1. National Regulations ................................................................................................ 4
2.2. World Bank’s Requirements for Stakeholder Engagement ........................................ 5
III. BRIEF SUMMARY OF PREVIOUS STAKEHOLDER ENGAGEMENT
ACTIVITIES ................................................................................................................. 5
IV. STAKEHOLDER IDENTIFICATION AND ANALYSIS .......................................... 6
4.1. Project Affected Parties ............................................................................................ 6
4.2. Other Interested Parties .......................................................................................... 11
4.3. Disadvantaged/Vulnerable Individual and Groups .................................................. 13
4.4. Summary the Needs of Project’s Stakeholders ........................................................ 15
V. STAKEHOLDER ENGAGEMENT PROGRAM ..................................................... 19
5.1. Purpose and Timing of Stakeholder Engagement Program...................................... 19
5.2. Proposed Strategy for Consultation ........................................................................ 22
5.3. Proposed Strategy to Incorporate the Views of Vulnerable Groups ......................... 30
5.4. Implementation of Free, Prior and Informed Consent (FPIC) .................................. 30
VI. GRIEVANCE REDRESS MECHANISM (GRM)..................................................... 32
6.1. Objectives of GRM ................................................................................................ 32
6.2. Project Grievance Redress Mechanism ................................................................... 33
VII. MONITORING AND REPORTING ......................................................................... 36
7.1. Involvement of Stakeholder in Monitoring Activities ............................................. 37
7.2. Reporting back to Stakeholder ................................................................................ 37
VIII. RESOURCES AND RESPONSIBILITIES FOR IMPLEMENTING
STAKEHOLDER ENGAGEMENT ACTIVITIES ................................................... 38
8.1. Resources ............................................................................................................... 38
8.2. Management Functions and Responsibilities .......................................................... 39
8.3. Budget for the SEP Preparation and Implementation .............................................. 39
LEGAL DOCUMENTS AND MINUTES OF CONSULTATION MEETING ......................... 51
STAKEHOLDER ENGAGEMENT PLAN (SEP)
Renewable Energy Accelerating Change (REACH) P a g e | iii
LIST OF TABLES
Table 1 - List of Project-Affected Parties ....................................................................................8
Table 2 - List of Other Interested parties ................................................................................... 11
Table 3 - List of disadvantaged/vulnerable groups .................................................................... 14
Table 4 - Summary of Stakeholder Needs ................................................................................. 16
Table 5 - Stakeholder Engagement and Disclosure Methods ..................................................... 20
Table 6 - Strategy for Consultation Activities ........................................................................... 25
Table 7 - Potential FPIC Steps .................................................................................................. 30
STAKEHOLDER ENGAGEMENT PLAN (SEP)
Renewable Energy Accelerating Change (REACH) P a g e | iv
ABBREVIATIONS
CPC : Commune People’s Committee
CSC : Construction Supervision Consultant
DARD : Provincial Department of Agriculture and Rural Development
DOC : Provincial Department of Construction
DOCST : Provincial Department of Culture, Sport and Tourism
DOIT : Provincial Department of Industry and Trade
DONRE : Provincial Department of Natural Resources and Environment
DOT : Provincial Department of Transport
DPC : District People’s Committee
EMDP : Ethnic Minority Development Plan
EMPF : Ethnic Minority Policy Framework
ESCP : Environmental and Social Commitment Plan
ESF : Environemental and Social Framework
ESIA : Environmental and Social Impact Assessment
ESMP : Environmental and Social Management Plan
ESS : Environmental and Social Standards
ESS10 : Stakeholder Engagement and Information Disclosure
EVN : Vietnam Electricity
E&S : Environmental and Social
GBV : Grievances related to Gender Based Violence
GHG : Green house gas
GOV : Government of Vietnam
GRM : Grievance Redress Mechanism
LEP : Law on Environmental Protection
LFDC : District Land Fund Development Centre
LMP : Labour Management Procedures
MARD : Ministry of Agriculture and Rural Development
MOC : Ministry of Construction
MPI : Ministry of Planning and Investment
MOIT : Ministry of Industry and Trade
MONRE : Ministry of Natural Resources and Environment
MOT : Ministry of Transport
NLDC : National Load Dispatch Centre
NPT : National Power Transmission Corporation
PAP : Project Affected Person
STAKEHOLDER ENGAGEMENT PLAN (SEP)
Renewable Energy Accelerating Change (REACH) P a g e | v
PAPs : Project Affected Parties
PC : People’s Committee
PECC : Power Engineering Consulting JS. Company
PPC : Provincial People’s Committee
PMB : Project Management Board
PSDP : Power Sector Development Plan
PTC : Power Transmission Company
ROW : Right of way
RP : Resettlement Plan
RPF : Resettlement Policy Framework
SEP : Stakeholder Engagement Plan
SPMB : Southern Power Project Management Board
SS : Substation
REACH : Renewable Energy Accelerating Change
TOR : Term of Reference
T/L : Transmission line
VRE : Variable renewable energy
WB : World Bank
STAKEHOLDER ENGAGEMENT PLAN (SEP)
Renewable Energy Accelerating Change (REACH) P a g e | 1
I. INTRODUCTION
1.1. Project Overview
1. Over the past decades, energy sector has been a fundamental enabler of inclusive economic
development. Energy sector's institutional and administrative arrangements were able to
successfully manage growth. EVN has been able to transform into one of the best performing
power utilities in the region. However, as Vietnam plans its next phase of growth, energy sector
stands at an inflection point. Given the rapidly evolving nature of Vietnam's economy, the coming
decades would require a strong focus by the energy sector on the 'quality', and not just the 'quantity'
of growth. The key challenges confronting the sector include: (i) managing the transition to clean-
energy based power system, (ii) ensuring energy security under the new growth factors, and (iii)
bringing in modern efficiencies and new technologies which keep pace with the changing nature
of the energy industry. Adapting to these new challenges would once again require bold vision of
the authorities as well as a strong reform agenda capable of reshaping the sector and its
institutional landscape. government’s climate impact mitigation strategy.
2. The Government of Vietnam has requested the World Bank (WB) to finance the
Renewable Energy Accelerating Change Project (REACH). This project is in line with the Seventh
Power Sector Development Plan (PSDP7/8). The proposed project will contribute to the improved
capacity of the electricity grid for enhanced variable renewable energy (VRE) integration of
private sector-led renewable energy generation and reduced greenhouse gas (GHG) emissions,
reduced electricity costs, reduction in dependence on fossil fuels, and reduction in air and water
pollution. The total cost of project is $350 million USD. The proposed Project will be implemented
from 2022 - 2026. The Project comprises of two components, (1) Grid Strengthening for VRE
Integration and (2) Dispatch Management.
3. EVN will be the project owner and responsible for coordinating with all relevant
Government agencies as well as its subsidiary companies responsible for following respective
components. The National Power Transmission Corporation (NPT) will implement Component 1,
while the National Load Dispatch Centre (NLDC) will implement Component 2. The project will
be implemented in Dak Lak, Dak Nong, Binh Phuoc, Tay Ninh, Ba Ria – Vung Tau and Dong
Nai provinces.
4. The Project will apply the World Bank Environmental and Social Framework (ESF) and
comply with applicable Vietnamese legislations. The REACH’s environmental and social risk has
been rated at Substantial. Nine out of the ten Environmental and Social Standards (ESSs) in the
ESF are relevant to the Project, including: i) ESS1 - Assessment and Management of
Environmental and Social Risks and Impacts; ii) ESS2 - Labor and Working Conditions; iii) ESS3
- Resource Efficiency and Pollution Prevention and Management; iv) ESS4 - Community Health
and Safety; v) ESS5 - Land Acquisition, Restrictions on Land Use and Involuntary Resettlement
; vi) ESS6 - Biodiversity Conservation and Sustainable Management of Living Natural Resources;
vii) ESS7 - Indigenous Peoples/Sub-Saharan African Historically Underserved Traditional Local
Communities; viii) ESS8 - Cultural Heritage; and ix) ESS10 - Stakeholder Engagement and
Information Disclosure.
1.2. Objectives of the REACH
5. The Project Development Objective (PDO) is to improve the capacity of the electricity
grid to integrate private sector led renewable energy generation projects.
6. The proposed project is comprised of the following two components: (i) Grid
Strengthening for VRE Integration Component; and (ii) The Dispatch Management Component.
1.3. Project Components
7. The Project includes the following components:
STAKEHOLDER ENGAGEMENT PLAN (SEP)
Renewable Energy Accelerating Change (REACH) P a g e | 2
Component 1: Grid Strengthening for VRE Integration (US$ 330 million of which US$182
million from WB and US$ 142 million from EVN)
8. Component 1 provides financing for power grid’s physical infrastructure (transmission lines
and substations) upgrades and development. It will also incorporate World Bank’s guidance on
investments in power grid infrastructure focusing on resilience to climate change. A brief
description of the physical infrastructure investments is included below:
a) Sub-Component 1.1: Transmission Backbone (500 kV) (US$ 318 million of which US$
174 million from WB and US$ 144 million from EVN). Sub-Component 1.1 provides
financing for construction of two new 500 kV transmission lines and substations which
are critical for evacuating power from renewable energy producing centers to the demand
centers. This investment in backbone transmission grid strengthening will enable a better
integration of around 543 MW of existing/under construction solar and wind energy
projects and unlock around 2.3 GW of new generation (see Table 2). The new unlocked
generation is expected to mobilize US$ 1.2 billion in private investments in the short-term,
and another US$ 3.7 billion in private investments in the medium-term. It is anticipated
that all these new VRE projects will directly replace new coal power plants as per the draft
PSDP 8. In addition, it will enable a reduction in transmission losses in those regions.
i. 500 kV Bac Chau Duc Transmission Line and Substation. This includes 10 km long
quad-circuit 500 kV transmission line (T/L). In addition, substation (SS) capacity of
950 MVA will be added as part of this sub-project. The location of the sub-project is in
the Ba Ria - Vung Tau Province in the Southern region of Vietnam. Total estimated
cost of this sub-project would be US$ 75 million, of which US$ 41 million would be
mobilized by the World Bank and the remainder by EVN.
ii. 500 kV Krong Buk - Tay Ninh 1 Transmission Line. This includes nearly 300 km long
double circuit 500 kV transmission line. The physical footprint of this transmission line
will traverse several provinces from the central highlights of Dak Lak to the South
Eastern province of Tay Ninh. The total estimated cost of this sub-project would be
US$ 243 million, of which US$ 133 million would be mobilized by the World Bank
and the remainder by EVN.
b) Sub-Component 1.2: Curtailment Reduction (220 kV) (US$ 12 million of which US$ 8
million from WB and US$ 4 million from EVN). Sub-Component 1.2 provides financing
for rehabilitation of 220 kV network of the existing grid infrastructure targeting
curtailment reduction of VRE projects. These could include:
i. 220 kV Phuoc Dong Substation which includes an upgrade of 250 MVA of substation
capacity and associated equipment. The location of the sub-project is in the Tay Ninh
province in the South East of Vietnam. Total estimated cost of this sub-project would
be US$ 12 million, of which US$ 8 million would be mobilized by the World Bank and
the remainder by EVN.
Component 2: Dispatch Management (US$ 20 million of which US$ 12 million from WB and
US$ 8 million from EVN).
9. Component 2 finances system management infrastructure (sensors, hardware, and software)
for the power grid operator to digitize and automate the tasks for VRE integration. As the volume
of VRE increases in the generation mix, the number of power plants is expected to be dramatically
increase (for instance, the number of solar power plants has increased from about a dozen a few
years ago to over 150 plants today). This created difficulties for the National Load Dispatch Center
(NLDC) to visualize, monitor, and control the network. In addition, the variability of the solar and
wind energy also requires additional sensitivity in management of operations with regards to
efficient forecasting of the supply and demand, as well as faster response to voltage and frequency
STAKEHOLDER ENGAGEMENT PLAN (SEP)
Renewable Energy Accelerating Change (REACH) P a g e | 3
changes. The investment supported under this component will be part of the new state-of-the-art
NLDC Control Center, which is being setup by EVN with the anticipated enhancements required
for grid management needs.
i. Control Center Automation. A SCADA with Automatic Generation Control (AGC)
for frequency and Automatic Voltage Control (AVC) for voltage management will be
financed to improve the reliability of the grid and the integration of VRE. This financing
will be used to acquire specialized set of latest Energy Management System (EMS)
applications and information technology systems whose role is to gather and analyze
real time data as well as to apply the AGC and AVC to ensure system stability. This
component will provide cutting-edge digital and disruptive technologies, and will
support ongoing modernization efforts of the power grid for monitoring, control, and
dispatch towards greater usage of VRE. Total estimated cost of this sub-project would
be US$ 20 million, of which $18 would be mobilized by the World Bank and the
remainder by EVN.
10. Institutional arrangements and capacity for implementation and sustainability. EVN
will be the overall responsibility for implementing the project and will be responsible EVN will
be the overall responsibility for implementing the project and will be responsible for: (i)
coordinating with all relevant Government agencies as well as its subsidiary companies
responsible for respective components. Component 1 will be implemented by EVN’s National
Power Transmission Company (NPT) and Component 2 will be implemented by the NDLC. NPT
and NLDC would assign specific project management boards to undertake day-to-day
management of the project related tasks. In this preparation phase, Southern Power Management
Board (SPMB) of NPT is responsible for preparing E&S documents.
1.4. Project Environmental and Social Risks and Impacts
11. During project identification, 3 subprojects of Component 1, involving the construction of
500kV and 220kV transmission lines and substations, have been screened. Most of the activities
under this component would involve civil works includes construction of the substations and T/L
tower foundations; installation of T/L and transformers; erection of power towers and wiring.
Some subprojects under this component may also include construction of small and short access
roads and clearance of right of way (ROW).
12. The project would not have impacts critical natural habitats and forests, or important
physical cultural resources. The majority of the potential adverse impacts relate to land acquisition
and clearance, construction related impacts, and health and safety risks associated with operation
of high-voltage substations and transmission lines of the subprojects under Component 1.
However, these potential impacts are expected to be moderate to high, temporary, site-specific
and mostly reversible and mitigation measures can readily be designed in most cases.
13. Component 2 of the project focuses on enhancing the system management infrastructure
(sensors, hardware, and software) for the power grid operator to digitize and automate the tasks
for VRE integration. Besides, automate the Control Center to improve the reliability of the grid
and the integration of VRE. These activities are unlikely to cause adverse E&S impacts and risks.
1.5. Objectives of SEP
14. The stakeholder engagement process serves various purposes. The objective of the SEP is
therefore to:
(1) Provide ongoing information on the project to government agencies, international
development partners, national non-government organizations, private sector partners and
indigenous communities and the general community;
STAKEHOLDER ENGAGEMENT PLAN (SEP)
Renewable Energy Accelerating Change (REACH) P a g e | 4
(2) Provide timely and appropriate information prior to and during the implementation of the
project to enable informed participation in the project and definition of appropriate
mitigation measures;
(3) Encourage equal participation of all affected groups in the consultation process;
(4) Disclose if any, environmental or social impacts of the project and proposed mitigation
measures;
(5) Obtain stakeholder input on any mitigation measures;
(6) Provide ongoing information on the implementation of the mitigation measures;
(7) Facilitate open and continuous communication and consultation between various
stakeholders and communities;
(8) Address any concerns, comments and provide feedback to concerns through a Grievance’s
Redress Mechanism (GRM) to satisfactory manage and mitigate any concerns about the
project.
15. The SEP requires a process and approach for stakeholder consultations and disclosure of
the REACH:
(i) Stakeholder engagement requirements of national policy and applicable World Bank
Standards.
(ii) Stakeholders that are likely to be affected and those that will influence the project and its
activities.
(iii) Approaches and schedule for consultation and engagement with stakeholders during
preparation of the SEP.
(iv) Processes, structures and timing for sharing project information aiming at ensuring regular,
accessible, transparent and appropriate feedback.
(v) Proposed Grievance Redress Mechanism (GRM) for REACH.
II. LEGAL FRAMEWORK
2.1. National Regulations
16. This SEP considers the existing institutional and regulatory framework within the context
of the following main Government of Vietnam (GOV) legal instruments:
The Constitution of the Socialist Republic of Viet Nam (2013), effective 1 January 2014.
The Law on Environmental Protection (No.55/2014/QH13) dated 23 June 2014, Decree
on Environmental Protection Planning, Strategic Environmental Assessment,
Environmental Impact Assessment and Environmental Protection Plans (No.18/2015/ND-
CP) dated 14 February 2015, and Decree on amending and supplementing a number of
articles of Decrees on the implementation of the Law on Environmental Protection
(No.40/2019/ND-CP) dated 13 May 2019 are key legal frameworks for environmental
management in Vietnam.
The Land Law 2013 implementing decrees (Nos.43/2014, 44/2014, 47/2014, 01/2017,
104/2014 and 148/2020) and Circular 37/2014 provides a comprehensive framework for
land acquisition and resettlement. At provincial level, the PPCs have issued decisions on
compensation, assistance and resettlement when the State acquires land, based on the Land
Law and implementing decrees.
STAKEHOLDER ENGAGEMENT PLAN (SEP)
Renewable Energy Accelerating Change (REACH) P a g e | 5
Law on Complaints, 2011. This Law and implementing Decree No.75/2012/ND-CP
identify the legal framework on grievances.
The Law on Reception of Citizens, 2013. The Law is stipulating responsibilities in
receiving citizens, and the rights and obligations of complainers and denouncers.
Ordinance No. 34/2007/PL-UBTVQH11 on exercise of democracy in communes, wards
and townships. This ordinance stipulates projects and information that have to be
disclosed, discussed, decided and monitored by the people.
2.2. World Bank’s Requirements for Stakeholder Engagement
17. The World Bank’s Environmental and Social Framework (ESF) includes Environmental
and Social Standard (ESS) - “Stakeholder Engagement and Information Disclosure” (ESS10),
which recognizes “the importance of open and transparent engagement between the Borrower
and project stakeholders as an essential element of good international practice”. ESS10
emphasizes that effective stakeholder engagement can significantly improve the environmental
and social sustainability of projects, enhance project acceptance, and make a significant
contribution to successful project design and implementation.
III. BRIEF SUMMARY OF PREVIOUS STAKEHOLDER ENGAGEMENT
ACTIVITIES
18. Since 2020, NPT/PMBs and consultants had held many meetings, documents to consult,
discuss and choose the location option of the sub-project and consultation on E&S documents
(ESMF, ESCP, SEP, LMP, EMPF and RPF). Documents and meetings are summarized in the
Annex 1.
19. Negotiations are underway with the People's Committee of Tay Ninh province to agree on
the construction site of the 220kV Phuoc Dong substation subproject.
20. For the 500kV Krong Buk - Tay Ninh 1 subproject, because the subproject is in the Pre-
Feasibility Study stage, the line direction is selected and preliminary agreed with the local
authorities. After the Pre-Feasibility Study has been approved and transitioned to the Feasibility
Study phase, the meetings and formal agreements with the local authorities at all levels (district,
province) and related agencies will be implement.
21. During this SEP preparation, the consultant has joined the meetings with NPT, PMB,
World Bank Task Team dated 22 December 2020 and conducted site visits to proposed
components in 06 provinces from 11 to 15 January 2021.
22. Five stakeholder consultations on E&S documents (ESMF, ESCP, SEP, LMP, EMPF and
RPF) with DONRE of provinces Binh Phuoc, Dak Nong, Dak Lak and Dong Nai was carried out
from January 14, 2021 to March 17, 2021.
23. Due to the current Covid-19 pandemic, consultation meetings on environment and society
(ESMF, ESCP, SEP, LMP, EMPF and RPF) in Tay Ninh and Ba Ria – Vung Tau provinces have
not been conducted. In the next time, consultation meetings at these provinces will be conducted
(scheduled for March or April 2021), and adapted to Covid-19 pandemic situation.
24. During the next stage of project preparation, various consultation activities with the local
community, district will be carried out by various modalities (focus group discussions, in-depth
interview). Group discussion is an effective means of consultations for it encourages the sharing
and discussion regards views and ideas related to the proposed project.
25. The implementing agency (SPMB/PECCs), with the support of their consultant, will carry
out additional consultations at the district level before the end of May 2021 in North Chau Duc
STAKEHOLDER ENGAGEMENT PLAN (SEP)
Renewable Energy Accelerating Change (REACH) P a g e | 6
and Krong Buck subprojects. These additional consultations will be carried out with local
stakeholders: representatives from commune and district People Committees (PCs), Women
Union, and CEMA for those areas where ethnic groups are present. The districts selected to carry
out the additional consultations at the district level will be those where the project will very likely
finance activities, even though the final technical designs have not been finalized yet. The SPMB
will document the stakeholder's feedback through consultation minutes. The Project SEP, and the
rest of the ESF instruments (if required), will be revised, updated, and redisclosed accordingly.
IV. STAKEHOLDER IDENTIFICATION AND ANALYSIS
26. Project stakeholders are people and entities who have a role in the Project, or could be
affected by the Project, or who are interested in the Project. Project stakeholders are defined as
individuals, groups or other entities who:
(i) are impacted or likely to be impacted directly or indirectly, positively or adversely, by the
Project (also known as ‘affected parties’); and
(ii) may have an interest in the Project (‘interested parties’). They include individuals or
groups whose interests may be affected by the Project and who have the potential to
influence the Project outcomes in any way.
4.1. Project Affected Parties
27. Affected parties include those directly or indirectly affected by the Project either
negatively or positively. This group includes:
1. EVN: who is responsible for coordinating with all relevant Government agencies as well
as its subsidiary companies responsible for following respective components.
2. NPT: who will implement Component 1 of the Project.
3. National Load Dispatch Centre (NLDC): who will implement Component 2 of the
Project.
4. PMBs (under the NPT): who will be responsible for preparation and construction of
subprojects.
5. Power Transmission Companies (PTCs - under the NPT): the unit will support power
cut-off of existing transmission lines for construction and connection of sub-projects
6. Local businesses affected by the construction of subprojects: this group includes:
- Businesses have land acquisition for substation and tower foundations of the transmission
line
- Businesses have structures relocated
- Businesses have trees and crops affected
- Businesses have land in ROW of the transmission line
7. Local communities and individuals affected by the construction of subprojects: this
group includes:
- Households have land acquisition for substation and tower foundations of the
transmission line
- Households have houses and structures relocated
- Households have trees and crops affected
- Households have land in ROW of the transmission line
STAKEHOLDER ENGAGEMENT PLAN (SEP)
Renewable Energy Accelerating Change (REACH) P a g e | 7
- Households nearby the subproject area
- Households along the road for transportation of construction materials and equipment
- Women (female members of the affected households)
- Other vulnerable groups (disabled, poor/near poor, landless households, ethnic minority
people).
STAKEHOLDER ENGAGEMENT PLAN (SEP)
Renewable Energy Accelerating Change (REACH) P a g e | 8
Table 1 - List of Project-Affected Parties
Project-affected
parties
Indicative
description
Identified groups of
project-affected parties Relevance to the Project Impacts Engagement methods
Project
beneficiaries
- Executing/
implementing
agencies
- EVN, NPT, PMBs
- Executive/ implementing
authorities.
- The project is expected to
bring about environmental
and social benefits in the
long term from: i) improve
infrastructure to increase
the efficiency of power
transmission; ii) Enhance
the reliability of power
system; and iii) Reduce the
power system losses;
- Positively
affected.
- Moderate
impacts.
- Should be informed
on the progress of the
project, schedule of
civil works through
meetings and
progress reports.
- Should be informed
on the progress of the
project through
public meetings and
information posted at
local levels.
People who will be
physically or
economically
displaced by the
project
- Physically or
economically
persons
displaced by the
Project.
- People who
reside or have
land and non-
land assets in the
Right of Way
(ROW) of the
proposed
investments.
- Businesses in project area.
- Residents living in and/or
around the proposed
project area.
- Ethnic Minority people.
- Women.
- Other vulnerable groups
(disabled, poor/near poor,
landless households).
- The project will cause land
acquisition and restrictions
on land use, which may
lead to physical
displacement (relocation,
loss of residential land or
loss of shelter) and
economic displacement
(loss of productive land,
assets or access to assets,
leading to loss of income
sources or other means of
livelihood).
- Negatively
affected.
- Moderate to
substantial
impacts.
- PAPs shall be
informed and
consulted during all
project
implementation to
ensure their views are
incorporated in the
RP and EMDP, and
project design
through public
consultation and
surveys.
STAKEHOLDER ENGAGEMENT PLAN (SEP)
Renewable Energy Accelerating Change (REACH) P a g e | 9
Project-affected
parties
Indicative
description
Identified groups of
project-affected parties Relevance to the Project Impacts Engagement methods
- Potential Project Affected
Persons (PAPs) shall be
consulted using the plan
outlined in this SEP. This
will be done throughout the
project cycle to ensure their
views are incorporated in
the RPF/RP, EMPF/EMDP
and project design.
- PAPs shall be
consulted about their
choices and options,
particularly on
relocation issues and
restoration of
livelihoods, through
public meetings and
focus-groups
discussions.
Affected
organization
- Organization
whose activities
are interrupted,
affected by the
project
- Power transmission
companies (PTCs)
- The project needs to cut off
power of the existing
500kV and 220kV
transmission lines to
perform construction
(cross-section) and connect
the project
- Negatively
affected.
- Low
impacts.
- This organization
need to be informed
of the construction
progress at the cross-
connecting and
connected location,
and the electrical
connection diagram
in the area
STAKEHOLDER ENGAGEMENT PLAN (SEP)
Renewable Energy Accelerating Change (REACH) P a g e | 10
Project-affected
parties
Indicative
description
Identified groups of
project-affected parties Relevance to the Project Impacts Engagement methods
Local community
residing around the
project areas
- Local
community who
are exposed to
pollution, traffic
safety risks,
gender risks,
among others.
- Residents living in and/or
around the proposed
project area;
- Workers of the contractors.
- Women;
- Other vulnerable groups
(disabled, poor, landless
households).
- The project is likely to
cause adverse
environmental and social
impacts on the local
community in the project
areas.
- Negatively
affected.
- Low to
moderate
impacts.
- Should be informed
on the progress of the
project, mitigations
measures and GRM
through public
meetings and
information posted at
local levels and
conduct the Focus
Group Discussions
(FGDs) with women
and vulnerable
groups.
STAKEHOLDER ENGAGEMENT PLAN (SEP)
Renewable Energy Accelerating Change (REACH) P a g e | 11
4.2. Other Interested Parties
28. Interested Parties are those who may have interests in this project and/or the ability to
influence its outcome, either positively or negatively. This group includes:
(i) Central government agencies: MOIT, MONRE, MPI, MARD, MOC, MOT who may
directly involve in the process of regulation updates/revision enabling/facilitating the
Project activities.
(ii) Local authorities (Province, District, and Communes): who will heavily in the site
selection process, and land acquisition, compensation and resettlement activities
(especially for subprojects of Component 1).
(iii) Mass organizations: who are mobilization, mediating problems and dissemination of
information.
(iv) Renewable energy companies and investors: they benefit from the connection to the
national power transmission system
(v) Local power companies: they benefit from increased power transmission in the area
(vi) Surrounding communities: who are not directly affected by subsprojects, but have
general interest in project implementation in their locality (commune, district or province)
(consumer groups)
(vii) Research institutes: who are related to power system (National universities, Institute of
Energy)
Table 2 - List of Other Interested parties
Stakeholder Interests Indicative List
Degree of Influence
and Engagement
methods
Central
government
agencies
- Ministries and
government agencies
are key stakeholders
for the project and
needs to be informed
about project
progress.
- State ministries and
government agencies
need to ensure project
compliance with
national legislation.
- Ministry of Industry
and Trade (MOIT)
- Ministry of Natural
Resources and
Environment
(MONRE).
- Ministry of Planning
and Investment (MPI).
- Ministry of
Construction (MOC).
- Ministry of
Agriculture and Rural
Development
(MARD).
- Ministry of Transport
(MOT)
- High influence.
- Comments on the
proposals and design.
- Advise the Prime
Minister in
accordance with
functions and duties.
- Issue dispatch,
relevant decisions to
accelerate the project
process.
Provincial
People’s
Committees
- Provincial PCs are the
highest authority to
promulgate
regulations, solve
- PPC.
- Department of
Industry and Trade
(DOIT)
- High influence.
- Agreement on
location of sub-
projects.
STAKEHOLDER ENGAGEMENT PLAN (SEP)
Renewable Energy Accelerating Change (REACH) P a g e | 12
Stakeholder Interests Indicative List
Degree of Influence
and Engagement
methods
issues concerning
guidelines and
policies, and give
instructions for the
Project
implementation and
are the links between
the functional
organizations in the
Project
implementation. The
relevant Provincial
departments are also
interested in the
Project at their
sectoral
responsibility.
- Department of
Agriculture and Rural
Development
(DARD).
- Department of
Construction (DOC).
- Department of Natural
Resources and
Environment
(DONRE).
- Department of
Transport (DOT).
- Chair meetings to
implement sub-
projects in the area
- Advise on the tasks
and responsibilities of
the management unit.
- Leading role in
intensive consultation
activities.
People’s
Committees
of District
and
Commune
- Local government
institutions protect the
rights of inhabitants in
the project area and
represent the local
communities/PAPs.
- District Land Fund
Development Centres
(DLFDCs) have
responsibility for land
acquisition,
compensation and site
clearance.
- Communes within the
Project area.
- District Land Fund
Development Centres.
- Moderate influence.
- Provide information
to stakeholders in
seminars, conferences
and during public
consultation.
- Moderate influence.
- Provide information
to PAPs on
resettlement
implementation and
policy.
- Participate in
monitoring,
evaluation.
Mass
organizations
- They main role is
mobilization,
mediating problems
and dissemination of
information through
their members.
- Women’s Union.
- Farmer’s Association.
- Youth Union.
- Fatherland Front.
- Moderate influence.
- To transmit concerns
of the community to
PMB, PPCs, DPCs.
- Support women and
vulnerable HHs.
STAKEHOLDER ENGAGEMENT PLAN (SEP)
Renewable Energy Accelerating Change (REACH) P a g e | 13
Stakeholder Interests Indicative List
Degree of Influence
and Engagement
methods
- These organizations
get feedback from the
population and can
channel complaints
and concerns
regarding any impact
of the Project on the
community.
- Mobilize community
participation in the
project.
- Receive comments
from local community
and deliver to
stakeholders.
Beneficiaries
of the project
- They benefit from the
national power
transmission system
- Group of renewable
energy companies and
investors.
- Local power
companies.
- Surrounding
communities
(consumer groups).
- Low to moderate
influence.
- Receive information
about the project.
- Participate in project
monitoring.
Research
institutes
- Universities/institutes
related to power
system
- National universities
- Institute of Energy
- Low influence
- Provide technical
guidance for the
project when required.
4.3. Disadvantaged/Vulnerable Individual and Groups
29. “Disadvantaged or vulnerable” refers to those who may be more likely to be adversely
affected by the Project. Such groups may be less able to take advantage of a project’s benefits.
Such groups are also more likely to be excluded from the consultation process. Various types of
barriers may influence the capacity of such groups to articulate their concerns and priorities about
project impacts.
30. Engagement with the vulnerable groups and individuals often requires the application of
specific measures and assistance aimed at the facilitation of their participation in the project-
related decision making so that their awareness of and input to the overall process are
commensurate to those of the other stakeholders. Within the Project Area of Influence, the
vulnerable groups may include and are not limited to the following:
(i) Elderly people and/or social policy householders (invalid soldiers, martyrs, heroic
mothers);
(ii) Poor/near-poor households;
(iii) Persons with disabilities and their caretakers;
(iv) Women, particularly women-headed households or single mothers with
underage/dependent children;
(v) Manual/traditional small-scale fishers;
(vi) The unemployed persons;
(vii) Ethnic Minority Community in the project area.
STAKEHOLDER ENGAGEMENT PLAN (SEP)
Renewable Energy Accelerating Change (REACH) P a g e | 14
31. The Table 4 below indicates disadvantaged or vulnerable groups encountered under the
REACH.
Table 3 - List of disadvantaged/vulnerable groups
Disadvantaged/vulnerable
groups
Potential barriers to limit
stakeholder effective
engagement
Specific needs to address
the barrier
- Elderly people and/or social
policy householders
(invalid soldiers, martyrs,
heroic mothers);
- Poor/Near-poor
households, female-headed
household with dependents,
elderly, persons living with
severe illness, landless
HHs.
- Manual/traditionally small-
scale fishers
- The unemployed persons.
- Poverty.
- Absence of suitable family
person to participate.
- Mobility.
- Lack of time to participate.
- Lack of interest.
- Meeting at ward/commune
level.
- Individual meetings.
- Adjustment of timing of
meetings to avoid working
time.
- Provision of transport
allowance.
- Female community
members and female
workers.
- Potentially any of above
barriers.
- Focus group meetings.
- Childcare provision during
meetings.
- Adjustment of timing of
meetings that allows
women to adequately tend
to their domestic duties.
- Mediation by Women’s
Union.
- People with disabilities. - Physical disabilities
preventing mobility.
- Various disabilities such as
visual and hearing
impairment.
- Blind language, braille
information.
- Accessible consultations
venues.
32. Vulnerable groups within the communities affected by the project will be further
confirmed and consulted through dedicated means, as appropriate. Specific measures to address
the needs of the poor and women will be put in place through both stakeholder consultation and
communication, livelihood restoration and land acquisition. There will be separate consultation
meetings conducted with vulnerable group/individuals and the purpose will be to explore the
critical issues for vulnerable and what method will be considered to support vulnerable people.
33. Disadvantaged or vulnerable individuals or groups, who often do not have a voice to
express their concerns or understand the impacts of a project. In the present context, this would
include women, who for cultural reasons have low mobility and are hard to reach, disabled and
STAKEHOLDER ENGAGEMENT PLAN (SEP)
Renewable Energy Accelerating Change (REACH) P a g e | 15
any displaced (internally or externally) families among the PAPs. Special efforts will be taken to
disseminate project information to these groups and to ensure their inclusion in the stakeholder
engagement process. To involve women, particularly among the PAPs, in the stakeholder
engagement process, the Project will work through female representatives in the affected
communities, to identify suitable venues and timing for consultations. Regarding disabled groups,
all venues for consultations, workshops and meetings should be selected with a view to facilitate
physical access for disabled. Displaced PAPs will be informed about meetings and consultations
via other community members in the area, and potentially through radio and social media.
4.4. Summary the Needs of Project’s Stakeholders
34. Summary the needs of REACH’s stakeholders is presented in Table 5.
STAKEHOLDER ENGAGEMENT PLAN (SEP)
Renewable Energy Accelerating Change (REACH) P a g e | 16
Table 4 - Summary of Stakeholder Needs
Stakeholder
Groups Key characteristics
Languages
Needs Preferred notification means Specific Needs
Local affected
communities
- The project affected
households (PAPs)/relocated
households
Vietnamese - Meetings at ward/ commune
level.
- Separate consultation meetings
with relocated households and
ethnic minority households.
- Posters at commune PC office.
- Local media (radio, TV).
- Separate consultation and FGDs
with women and affected persons
with a special consideration for
vulnerable and disadvantaged
groups.
- Suitable location for
consultations with PAP (i.e.
commune or village).
- Adjustment of timing of
meetings to avoid working
time.
- Reaching absentee PAPs.
- Involve mass organization
(especially women’s union) in
consultation preparation to
ensure inclusion of women and
vulnerable and disadvantaged
groups in Stakeholder
engagement.
- Preparation of minutes of
meetings.
Local affected
businesses
- The project affected
businesses
Vietnamese - Email & mail notification and
telephone.
- Presentation and meetings.
- Discuss and comment on the
location of the sub-project.
- Release location agreement of
the sub-project.
Organization whose
activity is
interrupted and
- Power Tranmisison
Companies (PTCs)
Vietnamese - Email & mail notification and
telephone.
- Notification of construction
progress at cross and
connected location.
STAKEHOLDER ENGAGEMENT PLAN (SEP)
Renewable Energy Accelerating Change (REACH) P a g e | 17
Stakeholder
Groups Key characteristics
Languages
Needs Preferred notification means Specific Needs
affected by the
project
- Electrical connection diagram
in the area.
Implementing
agencies
- EVN, NPT, PMBs, NLDC Vietnamese - Workshops - Presentation of SEP’s
requirements.
Central government - Ministries and government
agencies
Vietnamese - Email & mail notification and
telephone.
- Presentation and meetings.
- Aide-memoire.
- General information on the
project.
Government
agencies at
provincial and
district level
- PPCs, DPCs
- Relevant department in
provinces concerned with
project investments (i.e.
DOITs, DOTs, DARDs,
DONREs, DOCs).
Vietnamese - Email & mail notification and
telephone.
- Presentation and meetings.
- General information on the
project
- Discuss and comment on the
location of the sub-project.
- Release location agreement of
the sub-project
Government
agencies at
commune level
- CPCs.
- Mass organizations
(Women’s Union, Farmer’s
Association, Youth Union,
Fatherland Front, ...).
Vietnamese - Email & mail notification and
telephone.
- Presentation and meetings.
- General information on the
project
- Scale and level of
environmental and social
impacts of the project
Beneficiaries of the
project
- Group of companies and
investors in renewable energy.
- Local power companies.
Vietnamese - Posters at commune PC office.
- Local media (radio, TV).
- Information disclosure on
websites of EVN, NPT, PMBs
- General information on the
project
STAKEHOLDER ENGAGEMENT PLAN (SEP)
Renewable Energy Accelerating Change (REACH) P a g e | 18
Stakeholder
Groups Key characteristics
Languages
Needs Preferred notification means Specific Needs
- Residential community in the
area (Surrounding
communities).
Research institutes - National universities
- Institute of Energy
Vietnamese - Email & mail notification and
telephone.
- General information on the
project
STAKEHOLDER ENGAGEMENT PLAN (SEP)
Renewable Energy Accelerating Change (REACH) P a g e | 19
V. STAKEHOLDER ENGAGEMENT PROGRAM
5.1. Purpose and Timing of Stakeholder Engagement Program
35. The main goals of stakeholder’s engagement program are to create awareness of the key
deliverables of the project, keep stakeholders updated on key activities, and provide avenues for
affected people to voice their concerns and grievances. Main consultation activities planned is as
follows:
(i) ESIA, ESMP, RPF, EMPF, SEP, LMP and ECSP will be subject to consultations prior to
appraisal;
(ii) Subproject RPs/EMDPs will be subject to consultation once detailed design will be
available;
(iii) The ESCP will be shared for general orientation on the Government’s commitments;
(iv) During the project life cycle, it is planned to conduct, during the early stages of the project,
two meetings annually to update and consult stakeholders on project activities. During the
months leading up to, and during the construction phase, quarterly meetings will be
conducted.
36. Free printed copies of the ESIA/ESMP/RPF/EMPF/SEP/RP/EMDP/LMP and ESCP in
Vietnamese will be made accessible for the general public at the following locations:
(i) Offices of NPT, PMB;
(ii) DPC’s offices;
(iii) Commune PC’s office; and
(iv) Other designated public locations to ensure public dissemination of the project materials.
37. Electronic copies of the ESIA, ESMP, RPF/RP, EMPF/EMDP, SEP, LMP, and ESCP will
be placed on web-site of NPT, PMB and PPCs’ official websites. This will allow stakeholders
with access to the website via internet to view information about the planned development and to
initiate their involvement in the public consultation process. The website will be equipped with
an on-line feedback feature that will enable readers to leave their comments in relation to the
disclosed materials.
38. NPT, PMB will employ different means of communication to disseminate information to
different categories of stakeholders, and to engage them in consultations.
(i) To reach the maximum audience, radio spots (local radio) will be transmitted;
(ii) Information will be posted at commune PCs, to transmit brief information regarding the
project activities and upcoming consultations;
(iii) Workshop with the local communities for in-depth consultations;
(iv) Brochures and leaflets which will contain information on eligibility criteria and
entitlement matrix- these brochures will be distributed to affected people in the districts;
(v) Press releases/press conferences;
(vi) Consultations in the districts for all locally based stakeholder groups;
(vii) Separate meetings will be conducted for women, ethnic minority people (by using local
language speakers or interpreters, where required) and other vulnerable and disadvantaged
groups (as needed). Suitable location(s) will be identified with easy access.
39. The Table 6 below summarizes the proposed strategy for public disclosure.
STAKEHOLDER ENGAGEMENT PLAN (SEP)
Renewable Energy Accelerating Change (REACH) P a g e | 20
Table 5 - Stakeholder Engagement and Disclosure Methods
Project
stage
Information to be
disclosed Methods proposed
Timetable:
Locations/dates
Target
stakeholders
Percentage
reached Responsibilities
Stage 1:
Project
preparation
(before
project
appraisal)
- Main features of the
project.
- Sub-projects
locations
- Consultation on
province and district
level
- The province
has the project.
- In the process
of negotiating
the project
location
- Local authorities
and agencies at
district and
provincial levels
- - NPT, PMB.
- Related
Consultants.
- Project key features.
- RPF, EMPF, SEP,
and LMP.
- Public consultation
(at ward/commune
level).
- Posting at districts/
commune PCs.
- Provincial PCs’
websites.
- World Bank website.
- Affected
communes.
- Before
appraisal
- All stakeholders - 100% - NPT, PMB.
- Related
Consultants.
- District Land Fund
Development
Centres.
- Technical details on
project design.
- Compliance with
national regulations
and relevant
programs.
- Individual meetings.
- Emails.
- As needed
(and continued
throughout the
project life).
- Local
government,
state ministries,
mass
organizations
and community
groups.
- - NPT, PMB.
- Related
Consultants.
- Site-specific
environmental and
social impacts and
mitigation measures
in ESIA, ESMP,
- Public consultations
(quarterly basis).
- Individual meetings
through RP
preparation process.
- Prior to start of
civil work at
ward/
communes.
- Project affected
parties (PAPs).
- Community
groups
- - NPT, PMB.
- Related
Consultants.
STAKEHOLDER ENGAGEMENT PLAN (SEP)
Renewable Energy Accelerating Change (REACH) P a g e | 21
Project
stage
Information to be
disclosed Methods proposed
Timetable:
Locations/dates
Target
stakeholders
Percentage
reached Responsibilities
Stage 2:
Preconstruc
tion and
during
construction
RPF/RPs,
EMPF/EMDPs, SEP
and LMP.
- Awareness-raising
on the GRM.
- Preconstruction site
visits.
- GRM accessibility
will be advertised on
worksites and at the
commune level (e.g.
on notice boards).
- The GRM is
maintained
throughout the
project life.
supporting
PAPs.
- District Land Fund
Development
Centres.
- Employee Grievance
Procedure.
- Staff handbook.
- Group Meetings.
- Disclose GRM at
public places,
worksites and at the
commune level to
ensure all target
audience can reach.
- Prior to start of
civil work at
project site.
- Project workers. - - NPT, PMB.
- Construction
Supervision
Consultants (CSC)
- Contractors.
- Selection criteria and
TOR for employment
opportunities for
construction work.
- Group meetings with
mass organizations to
engage women and
vulnerable groups.
- Prior to start of
civil work at
ward/
communes.
- People who may
benefit from
employment
opportunities.
- - PMB’ E&S team.
- Women’s union
- Supervision
consultant.
Stage 3:
Post
construction
- Summary of the
outcome of project
monitoring
(including GRM).
- Summary to share at
public consultation
on a quarterly basis;
- Media releases
and/or newsletters
via email.
- Following the
completion of
civil work.
- All stakeholders. - - PMB’ E&S team.
- Independent
Monitoring
Consultant.
STAKEHOLDER ENGAGEMENT PLAN (SEP)
Renewable Energy Accelerating Change (REACH) P a g e | 22
40. The above table will be revised and finalized once the Grant Agreement is approved and
its implementation is officially launched. Among others, the situation of COVID 19 outbreak in
Vietnam will be consider and taken into account. Government of Vietnam decided to gradually
resume all activities, except in some high risk areas. once the project sites are identified, detailed
consultation and engagement activities will be developed and reflected in the updated SEP. The
proposed activities are subject to the application of Government’s regulations and the Bank’s
guidance on COVID 19. Revised/Updated SEP will be re-disclosed per ESF requirements
5.2. Proposed Strategy for Consultation
41. The project implementing agencies will mostly employ interviews, focus group
discussions, open meetings, and workshops as a means of carrying out consultations. This will be
done right in the affected communes to enable easy participation of vulnerable and disadvantaged
groups of people. The strategy will also be different depending on the Project stage as presented
below.
Project preparation stage (before project appraisal)
42. While the details of some proposed investments are unknown at this stage, the consultation
will focus on a broader range of stakeholders to understand their general interests and concerns
on the project and its potential positive and negative impacts to inform the project’s environmental
and social frameworks. This is also the stage where potential vulnerable/disadvantaged groups
relevant to the project will be identified.
Pre-construction and construction stage
43. At this stage, the details of proposed investments will be determined and specific project-
affected parties (PAPs) identified. The consultation will focus on PAPs to address their concerns
through the implementation of subproject-specific environmental and social plans. The project
will ensure that the GRM will remain effective during the civil works to promptly address any
grievances from the PAPs. The PMB will pay particular attention to vulnerable groups to ensure
inclusion and non-discrimination of such groups.
Post construction/maintenance stage
44. At this stage, the consultation will focus on the feedback from PAPs on the performance
of environmental and social mitigations conducted during the construction stage. The consultation
on employment opportunities for operation and maintenance works (O&M) will be also
conducted. Areas for improvement and lessons learned should be identified for the following
subprojects. Dissemination and reporting back to general stakeholders on the outcome of the
monitoring and evaluation of the project will be also arranged.
Public consultation and stakeholder engagement activities during COVID-19
45. In the context of the outbreak and spread of COVID-19, the Government of Vietnam
(GOV) has taken various restrictive measures, imposing strict restrictions on public gatherings,
meetings and people’s movement, and others advising against public group events. People have
been advised to exercise social distancing, and specifically to avoid public gatherings to prevent
and reduce the risk of the virus transmission. These restrictions have affected Bank requirements
for public consultation and stakeholder engagement in the project. The Bank’s Technical Note on
Public Consultations and Stakeholder Engagement was issued to guide the public consultation and
stakeholder engagement activities during COVID-19 pandemic. The Note offers suggestions to
the client on managing public consultation and stakeholder engagement, with the recognition that
the situation is developing rapidly, and careful regard needs to be given to national requirements
and any updated guidance issued by the World Health Organization (WHO). It is important that
the alternative ways of managing consultation and stakeholder engagement discussed with the
STAKEHOLDER ENGAGEMENT PLAN (SEP)
Renewable Energy Accelerating Change (REACH) P a g e | 23
client are in accordance with the local applicable laws and policies, especially those related to
media and communication.
During preparatory stages
46. Where projects are under preparation and stakeholder engagement is about to commence
or is ongoing, such as in the project E&S planning process, stakeholder consultation and
engagement activities should not be deferred, but rather designed to be fit for purpose to ensure
effective and meaningful consultations to meet project and stakeholder needs. The project
implementing agencies should note some of the following:
Review the country COVID-19 spread situation in the project area, and the restrictions put
in place by the government to contain virus spread;
Review the draft Stakeholder Engagement Plan (SEP, if it exists) or other agreed
stakeholder engagement arrangements, particularly the approach, methods and forms of
engagement proposed, and assess the associated potential risks of virus transmission in
conducting various engagement activities;
Be sure that all task team and PIU members articulate and express their understandings on
social behavior and good hygiene practices, and that any stakeholder engagement events
be preceded with the procedure of articulating such hygienic practices.
Avoid public gatherings (taking into account national restrictions), including public
hearings, workshops and community meetings, and minimize direct interaction between
project agencies and beneficiaries / affected people;
If smaller meetings are permitted, conduct consultations in small-group sessions, such as
focus group meetings. If not permitted, make all reasonable efforts to conduct meetings
through online channels, including WebEx, zoom and skype meetings;
Diversify means of communication and rely more on social media and online channels.
Where possible and appropriate, create dedicated online platforms and chatgroups
appropriate for the purpose, based on the type and category of stakeholders;
During implementation stages
47. During implementation stages, the project activities are likely to have public consultation
and stakeholder engagement activities planned and committed as part of project design. These
activities may be described in different project documents and will involve a variety of
stakeholders. Commonly planned avenues of such engagement are public hearings, community
meetings, focus group discussions, field surveys and individual interviews. With growing concern
about the risk of virus spread, there is an urgent need to adjust the approach and methodology for
continuing stakeholder consultation and engagement. The project implementing agencies should
note some of the following:
Identify and review planned activities under the project requiring stakeholder engagement
and public consultations.
Assess the level of proposed direct engagement with stakeholders, including location and
size of proposed gatherings, frequency of engagement, categories of stakeholders
(international, national, local) etc.
Assess the level of risks of the virus transmission for these engagements, and how
restrictions that are in effect in the country/project area would affect these engagements.
Identify project activities for which consultation/engagement is critical and cannot be
postponed without having significant impact on project timelines. For example, selection
of resettlement options by affected people during project implementation. Reflecting the
STAKEHOLDER ENGAGEMENT PLAN (SEP)
Renewable Energy Accelerating Change (REACH) P a g e | 24
specific activity, consider viable means of achieving the necessary input from stakeholders
(see further below).
Assess the level of ICT penetration among key stakeholder groups, to identify the type of
communication channels that can be effectively used in the project context.
48. Based on the above, the project implementing agencies should consider the specific
channels of communication that should be used while conducting stakeholder consultation and
engagement activities. The following are some considerations while selecting channels of
communication, in light of the current COVID-19 situation:
Avoid public gatherings (taking into account national restrictions), including public
hearings, workshops and community meetings;
If smaller meetings are permitted, conduct consultations in small-group sessions, such as
focus group meetings. If not permitted, make all reasonable efforts to conduct meetings
through online channels, including WebEx, zoom and skype;
Diversify means of communication and rely more on social media and online channels.
Where possible and appropriate, create dedicated online platforms and chatgroups
appropriate for the purpose, based on the type and category of stakeholders;
Employ traditional channels of communications (TV, newspaper, radio, dedicated phone-
lines, and mail) when stakeholders to do not have access to online channels or do not use
them frequently. Traditional channels can also be highly effective in conveying relevant
information to stakeholders, and allow them to provide their feedback and suggestions;
Where direct engagement with project affected people or beneficiaries is necessary, such
as would be the case for Resettlement Action Plans or Indigenous Peoples Plans
preparation and implementation, identify channels for direct communication with each
affected household via a context specific combination of email messages, mail, online
platforms, dedicated phone lines with knowledgeable operators;
Each of the proposed channels of engagement should clearly specify how feedback and
suggestions can be provided by stakeholders;
An appropriate approach to conducting stakeholder engagement can be developed in most
contexts and situations. However, in situations where none of the above means of
communication are considered adequate for required consultations with stakeholders to
decide whether the project activity can be rescheduled to a later time, when meaningful
stakeholder engagement is possible.
49. The SEP will be reviewed and updated during project implementation as necessary on
adaptive stakeholder engagement arrangements, particularly the approach, methods and forms of
engagement proposed, and assess the associated potential risks of virus transmission in conducting
various engagement activities.
50. The Table 7 below summarizes the proposed strategy for consultation for all stages of
the project.
STAKEHOLDER ENGAGEMENT PLAN (SEP)
Renewable Energy Accelerating Change (REACH) P a g e | 25
Table 6 - Strategy for Consultation Activities
Project stage Target stakeholders Topic of
consultation/engagement Methods used Locations/dates Responsibilities
STAGE 1:
PROJECT
PREPARATION
(DESIGN,
SCOPING, E&S
PLANNING,
ESIA/RPF/SEP/L
MP/ESCP
DISCLOSURE)
Project Affected Parties:
- All stakeholders.
- PAPs.
- Vulnerable groups.
- Project interventions and
scope.
- Project E&S principles,
and risks/impacts and
proposed mitigation
measures
- ESIA, RPF/RPs,
EMPF/EMDPs, SEP,
ESCP, and LMP (when
available) disclosures.
- Land compensation and
acquisition process.
- Resettlement and
livelihood restoration
options.
- Grievance redress
mechanism.
- Face-to-face public
meetings.
- Disclosure of project
information
(booklets, posters,
website).
- Posters at commune
PCs.
- Separate in-depth
consultation with
PAPs.
- Focus Group
Discussions.
- Household
questionnaires.
- Affected
commune PC,
and other places
as convenience.
- Before Project
Appraisal.
- NPT, PMB.
- Related
Consultants.
- District Land
Fund
Development
Centres.
Other Interested
Parties:
- Local authorities (PPCs,
DPCs, CPCs).
- Governmental agencies
(DOIT, DONRE, DOC,
DOT, DOIC, DARD).
- LFDCs.
- Legal compliance issues.
- Project information
scope and rationale and
E&S principles.
- Coordination activities.
- Land compensation and
acquisition process.
- Face-to-face public
meetings.
- Disclosure of project
information
(booklets, posters,
website).
- PMB venues
- Before Project
Appraisal.
- NPT, PMB.
- Related
Consultants.
STAKEHOLDER ENGAGEMENT PLAN (SEP)
Renewable Energy Accelerating Change (REACH) P a g e | 26
Project stage Target stakeholders Topic of
consultation/engagement Methods used Locations/dates Responsibilities
- Donors.
- Public utilities.
- Grievance redress
mechanism.
- ESIA, RPF, SEP, ESCP,
LMP, and RP (when
available) disclosures.
- Separate in-depth
technical
discussions.
- Sharing of project
relevant documents.
Other Interested
Parties:
- Mass organizations.
- NGOs/CSOs.
- Academies.
- Project scope and E&S
principles.
- ESIA, RPF/RPs,
EMPF/EMDPs, SEP,
ESCP, and LMP (when
available) disclosures.
- Grievance redress
mechanism.
- Public meetings,
trainings/workshops
(separate meetings
specifically for
women and
vulnerable as
needed).
- Mass/social media
communication.
- Disclosure of
brochures, posters,
website.
- Project
communities’
meeting places.
- Before Project
Appraisal.
- NPT, PMB.
- Related
Consultants.
Other Interested
Parties:
- Local community.
- Others.
- Project interventions and
scope.
- Project E&S principles,
risks/impacts and
proposed mitigation
measures.
- ESIA, RPF, SEP, ESCP,
LMP, RP and EMDP
- Face-to-face public
meetings.
- Leaflets.
- Posters at commune
PCs.
- Affected
commune PC,
and other places
at convenient.
- Before Project
Appraisal.
- NPT, PMB.
- Related
Consultants.
- District Land
Fund
Development
Centres.
STAKEHOLDER ENGAGEMENT PLAN (SEP)
Renewable Energy Accelerating Change (REACH) P a g e | 27
Project stage Target stakeholders Topic of
consultation/engagement Methods used Locations/dates Responsibilities
(when available)
disclosures.
- Land compensation and
acquisition process.
- Resettlement and
livelihood restoration
options
- Grievance redress
mechanism.
STAGE 2:
PROJECT
IMPLEMENTAT
ION
Project Affected Parties:
- All stakeholders.
- PAPs.
- Vulnerable groups.
- Project status.
- Grievance redress
mechanism.
- Land compensation and
acquisition packages.
- Resettlement and
livelihood restoration
implementation.
- Health and safety impacts
(community H&S,
community concerns).
- Employment
opportunities.
- Face-to-face public
meetings.
- Separate in-depth
consultation with
PAPs.
- Separate meetings as
needed for women
and vulnerable.
- Focus Group
Discussions.
- Grievance redress
mechanism.
- Affected
commune PC,
and other places
as convenience.
- Before Project
implementation
- NPT, PMB.
- Related
Consultants.
- District Land
Fund
Development
Centres.
- Construction
supervision and
independent E&S
monitoring
consultants.
- Contractors/sub-
contractors.
STAKEHOLDER ENGAGEMENT PLAN (SEP)
Renewable Energy Accelerating Change (REACH) P a g e | 28
Project stage Target stakeholders Topic of
consultation/engagement Methods used Locations/dates Responsibilities
Other Interested
Parties:
- Local authorities (PPCs,
DPCs, CPCs).
- Governmental agencies
(DOIT, DONRE, DOC,
DOT, DOIC, DOCST).
- LFDCs.
- Donors.
- Public utilities.
- Legal compliance issues.
- Project status and E&S
principles.
- Coordination activities.
- Reviewing and approval
procedures of land
compensation and
acquisition, and
resettlement.
- Grievance mechanism
process.
- Face-to-face public
meetings.
- Sharing of project
relevant documents.
- PMB venues
- Before Project
implementation.
- NPT, PMB.
- Construction
supervision and
independent E&S
monitoring
consultants.
- Contractors/sub-
contractors.
Other Interested
Parties:
- Mass organizations
- NGOs/CSOs.
- Academies.
- Project status.
- Grievance redress
mechanism.
- Health and safety impacts
(community H&S,
community concerns).
- Environmental and social
concerns.
- Public meetings,
trainings/workshops.
- Mass/social media
communication.
- Disclosure of
brochures, posters,
website.
- Project
communities’
meeting places.
- Before Project
construction.
- NPT, PMB.
- Construction
supervision and
independent E&S
monitoring
consultants.
- Contractors/sub-
contractors.
Other Interested
Parties:
- Local community.
- Others.
- Project status.
- Grievance redress
mechanism.
- Environmental and social
concerns.
- Public meetings,
trainings/workshops.
- Mass/social media
communication.
- Disclosure of
brochures, posters,
website.
- Project
communities’
meeting places.
- Before Project
implementation.
- NPT, PMB.
- Construction
supervision and
independent E&S
monitoring
consultants.
STAKEHOLDER ENGAGEMENT PLAN (SEP)
Renewable Energy Accelerating Change (REACH) P a g e | 29
Project stage Target stakeholders Topic of
consultation/engagement Methods used Locations/dates Responsibilities
- Contractors/sub-
contractors.
STAGE 3:
PROJECT
OPERATION
Project Affected Parties:
- All stakeholders.
- PAPs.
- Vulnerable groups.
- Project status.
- Satisfaction with
engagement activities
and GRM.
- Face-to-face public
meetings.
- Separate in-depth
consultation with
PAPs.
- Separate meetings as
needed for women
and vulnerable.
- Focus Group
Discussions.
- HH questionnaires.
o Affected
commune PC,
and other places
as convenience.
- After Project
implementation
- PMB (E&S
Team).
Other Interested
Parties:
- Mass organizations
- NGOs/CSOs.
- Academies.
- Local community.
- Others.
- Project status.
- Grievance redress
mechanism.
- Health and safety impacts
(community H&S,
community concerns).
- Environmental and social
concerns.
- Public meetings,
trainings/workshops.
- Mass/social media
communication.
- Disclosure of
brochures, posters,
website.
- Project
communities’
meeting places.
- After Project
implementation.
- PMB (E&S
Team).
STAKEHOLDER ENGAGEMENT PLAN (SEP)
Renewable Energy Accelerating Change (REACH) P a g e | 30
5.3. Proposed Strategy to Incorporate the Views of Vulnerable Groups
51. All views expressed by stakeholders will be carefully noted, documented in the
consultation summary and considered, including those of disadvantaged or vulnerable groups. The
following strategy will be used for consultation with vulnerable groups:
(i) Issuance of invitations specific to the relevant groups: a) female PAPs; b) displaced PAPs;
and iii) poor and other vulnerable groups;
(ii) Conduct specific consultations with each of these groups separately in a location and venue
easily accessible to them. Women’s union, Youth Union, Fatherland Front or elderly group
will be used as mediators and will be involved reaching these groups;
(iii) Consultation with vulnerable people will be conducted throughout the project life. There
will be separate FGDs arranged with vulnerable people during project design/ preparation
stage on a quarterly basis. The key focus will be to explore problems and needs of these
groups and how to reach them. There will also be quarterly meetings conducted with these
groups during project implementation.
5.4. Implementation of Free, Prior and Informed Consent (FPIC)
52. Should the circumstances that requires FPIC as stipulated in paragraph 17 of ESS7 occur,
PMBs will engage independent specialists to assist in the identification of the project risks and
impacts. There is no universally accepted definition of FPIC, as for the purposes of this ESS, FPIC
is established as follows:
The scope of FPIC applies to project design, implementation arrangements and expected
outcomes related to risks and impacts on the affected Local Ethnic Minority Communities;
FPIC builds on and expands the process of meaningful consultation described in ESS10
and the above sections, and will be established through good-will negotiation between the
Project Implementing Agencies and affected Local Ethnic Minority Communities;
53. The Table 4 below will provide step-by-step guidance on how to arrive at the decision to
consent to the sub-project.
Table 7 - Potential FPIC Steps
FPIC Task Responsibility Timing
Identify key stakeholders at the
Provincial and affected community
level EMDP Consultant
As soon as sub-project sites are
known
Disclose information on proposed sub-project at least 2 weeks in
advance of initial meeting PMBs
As soon as sub-project sites are
known
Initial information meeting on
Subproject and its potential impacts.
If these impacts include those requirement FPIC, then, use the
meeting to (1) determine how the
communities consent will be established. (2) how good faith
negotiations will be conducted
EMDP/SA Consultant,
PMBs, Commune, District
and Provincial Authorities
Prior to finalizing sub-project
design
STAKEHOLDER ENGAGEMENT PLAN (SEP)
Renewable Energy Accelerating Change (REACH) P a g e | 31
Document stakeholder feedback on
initial sub-project proposal EMDP Consultant
Prior to finalizing sub-project
design
Follow additional steps for goodfaith
negotiations agreed during the initial
meeting, if required.
EMDP/SA Consultant,
PMBs, Commune, District
and Provincial Authorities
Revise sub-project and prepare EMDP based on good faith
negotiations EMDP/SA Consultant,
Prior to finalizing sub-project
design
Present again the subproject
proposal, along with EMDP at a
follow up meeting, and secure agreement that can be considered
consent based on good faith
negotiations
EMDP/SA Consultant, PMBs, Commune, District
and Provincial Authorities
Prior to finalizing sub-project
design
Finalize sub-project proposal, along
with EMDP, re-disclose locally, and present at event (e.g. designated
committee meeting, elder meeting,
community referendum meeting) for
securing collective support (FPIC)
EMDP/SA Consultant,
PMBs, Commune, District
and Provincial Authorities
Prior to finalizing sub-project
design
Conduct follow on (possibly)
meetings at the community level
PMBs, Commune, District
and Provincial Authorities,
and the Contractor
Prior to finalizing sub-project
design
54. The results of consultation should be provided to the affected EM communities to enable
both SA/EMDP team and EM people to validate the results of the consultation process, and fine-
tune the proposed actions, if necessary. Providing consultation feedback is particularly important
for cases where adverse impact on the EM population were identified (from the social assessment)
and were discussed with the EM peoples during the consultation process. Provision of feedback
to the affected peoples could take the form of community meetings – conducted in a manner
similar to the FPIC standard.
55. Agreements reached between the Project Implementing Agencies and affected Local
Ethnic Minority Communities will be described, and actions necessary to accomplish agreements
will be included, in the EMDP. During implementation, the Project Implementing Agencies will
ensure that necessary actions are taken, and agreed benefits or improvements to services are
delivered, so as to maintain Local Ethnic Minority Communities’ support for the project.
5.5. Information Disclosure
56. NPT, PMB will use the websites to disclose project documents in Vietnamese and English.
All information brochures/fliers need to be posted on the websites of NPT, PMB. All prepared
E&S documents will be publicly available on NPT’s website. Project disclosure package should
include the followings:
o Environmental and Social Management Framework (ESMF)
STAKEHOLDER ENGAGEMENT PLAN (SEP)
Renewable Energy Accelerating Change (REACH) P a g e | 32
o Resettlement Framework Policy (RFP)
o Stakeholder Engagement Plan (SEP)
o Labor Management Procedures (LMP)
o Environmental and Social Commitment Plan (ESCP)
57. The Vietnamese version of this SEP will be publicly disclosed in April, 2021. The English
version will be disclosed at the World Bank external websites in April, 2021.
VI. GRIEVANCE REDRESS MECHANISM (GRM)
6.1. Objectives of GRM
58. The objective of the project Grievance Redress Mechanism (GRM) is to provide project-
affected parties with accessible and inclusive means to raise issues and grievances and allow NPT,
PMB to respond to and manage grievances filed by affected people and other parties. Grievances
may emerge from directed and indirect activities related to activities of sub-projects. Grievance
may arise among affected households and communities on variety of issues regarding land
acquisition and resettlement (i.e. compensation rates, land use origin, and eligibility to
resettlement allocation) or related to construction (dust noise, vibrations, water/soil
contamination, etc.,). Workers’ related grievances mechanisms are addressed in the project’s
Labor Management Procedure (LMP) and Resettlement related grievance shall be addressed in
accordance with the Resettlement Policy Framework (RPF) and ESIA.
59. GRM is established during the project effectiveness. The main goals of GRM are ensuring
the receipt and timely redress of grievances and concerns submitted by the aggrieved project
affected persons and resolve complaints at the project level and prevent escalation to the courts or
World Bank Accountability Mechanism. The GRM will be established to allow affected persons
appealing any disagreeable decision, practice or activity arising from land or other assets
compensation or arising from project construction. PAPs will be fully informed of their rights and
of the procedures for addressing complaints whether verbally or in writing during consultation,
survey, training and time of compensation. The GRM shall not impede access to the country’s
judicial or administrative remedies. Affected persons can approach a court of law at any time and
independent of the project level grievance redress process. Along with the World Bank
requirements on development and approval of grievance redress mechanism by implementation
of investment projects, grievance redress procedures in Vietnam is also regulated by the national
legislation, in particular by the Law on Complaints (2011) and the Law on Denunciation (2018).
60. While handling grievances, the NPT, PMB shall establish GRM as part of the accessible
and inclusive means to raise issues and grievances and to and manage grievances filed by affected
people and other parties1. The NPT, PMB shall appoint a GRM focal point to collaborate with
local authorities in handling the grievances. The design of the GRM shall take into consideration
the views of affected communities expressed during the resettlement planning process. The NPT,
PMB shall be required to disclose and explain to affected persons and communities and, to
interested other stakeholders the procedure for complaints filing as early as possible and on a
regular basis throughout the project cycle. The grievance mechanism shall be available at no cost,
and it is important that it be easily accessible, with special attention paid to accessibility for
disadvantaged and vulnerable individuals or groups.
61. The NPT, PMB will ensure that the following grievance procedure is accessible,
adequately registered and tracked, and resolution is affirmed within one month of registration.
The NPT, PMB and relevant agencies will:
1 See paragraph 21 and ESS10
STAKEHOLDER ENGAGEMENT PLAN (SEP)
Renewable Energy Accelerating Change (REACH) P a g e | 33
(i) Record, categorize and prioritize the grievances;
(ii) Settle the grievances via consultation with all stakeholders (and inform those stakeholders
of the solutions) through the below process.
6.2. Project Grievance Redress Mechanism
62. Complaints relating to any subproject's problems will be solved through negotiations to
achieve the consensus. A Grievance Redress Mechanism is recommended for the REACH to
address the complaints and grievances from the Project Affected People (PAP). PAPs can only be
encouraged (not forced) to use the project level GRM and PAP can lodge a complaint in court at
any time. In case the PAP wants to use the project's GRM, a complaint will go through three stages
before it can be transferred to the court. The enforcement unit will pay all administrative and legal
fees relating to the acceptance of complaints. This cost is included in the project budget. Complaint
procedures and resolution will be performed as follows:
The first level - Commune People’s Committee (CPCs)
o An affected household is to take his/her complaint to any member of the People's
Committee of the commune, through the village/cluster head or directly to CPCs, in
written or oral form. The said member(s) of the CPCs or the village head will inform the
CPC on the complaint. The CPCs will work directly in person with the said affected
household and will decide on the settlement of the complaint within 5 working days after
receiving such complaint. The secretariat of the CPC is responsible for documenting and
recording all the complaints that it is handling. Once the CPC issues its settlement decision,
the household can make an appeal within 30 working days. In case a second decision has
been issued but the said household is still not satisfied with such decision, the household
can appeal to the District People’s Committees.
The second level - District People’s Committees (DPCs)
o Upon receiving a complaint from a household, the DPCs will have 15 working days to
resolve the case. The DPCs are responsible for filing and storing documents on all
complaints that it handles. When the DPCs have issued a decision, the household can make
an appeal within 30 working days. In case a second decision has been issued and the
household is still not satisfied with such a decision, they can appeal to the Provincial
People’s Committee (PPC).
The third level - At Province People’s Committees (PPCs)
o Upon receiving a complaint from the household, the PPC will have 30 working days to
resolve the case. The PPC is responsible for filing and storing documents for all complaints
to be submitted. After the PPC has issued a decision, the household can appeal within 45
working days. In case a second decision has been issued and the household is still not
satisfied with such decision, they can appeal to the people’s court within 45 working days.
The PPC will then have to pay the compensation into an account.
The fourth level - Court of Law Decides
o In case a complainant brings his/her case to district/provincial people’s court and the court
rules in favor of the complainant. The decision ruling the settlement of complaints will
have to be sent to complainants and concerned parties and shall be publicly posted at the
headquarters of the People's Committee of the relevant level. The complainant will receive
such ruling three days after the result of complaint resolution at the ward/commune level
has been decided upon and 07 working days at the district or provincial level.
63. Personnel: The environment and resettlement staff (safeguard staff) assigned by the NPT,
PMB will design and maintain a database of the project-related complaints from affected
households, including information such as: the nature of the complaint, the source and date of
STAKEHOLDER ENGAGEMENT PLAN (SEP)
Renewable Energy Accelerating Change (REACH) P a g e | 34
receipt of the complaint, the name and address of the complainant, action plan, and current status.
For oral complaints, the receiving/mediator board will record these requests in a complaint form
at the first meeting with the affected person. This staff will be able to contact directly with affected
people and guide them through the official channels. A deputy director of the PMB shall be
assigned to be GRM focal point. The GRM focal point will play the essential and coordination
role among respective administrative levels for handling the complaints in a timely and
satisfactorily manner.
64. Contractor and Construction Supervision Consultant (CSC): During construction, the
GRM will also be managed by the contractors under supervision of the CSC. The contractors will
inform the affected communities and communes about the GRM availability to handle complaints
and concerns about the project. This will be done via the community consultation and information
disclosure process under which the contractors will communicate with the affected communities
and interested authorities on a regular basis. Meetings will be held at least quarterly, monthly
information brochures will be published, announcements will be placed in local media, and notices
of upcoming planned activities will be posted, etc. All contractors and CSCs will also appoint
grievance focal persons to catch and solve the problem timely.
65. All complaints and corresponding actions undertaken by the contractors will be recorded
in project safeguard monitoring reports. Complaints and claims for damages could be lodged as
follows:
(i) Verbally: direct to the CSC and/ or the contractors’ safeguard staff or representatives at
the site offices.
(ii) In writing: by hand-delivering or posting a written complaint to specified addresses.
(iii) By telephone, fax, e-mails: to the CSC, the contractors’ safeguard staff or representatives
66. Upon receipt of a complaint, the CSC, the contractors’ safeguard staff or representatives
will register the complaint in a complaint file and maintain a log of events pertaining to it
thereafter, until it is resolved. Immediately after receipt, four copies of the complaint will be
prepared. The original will be kept in the file, one copy will be used by the contractor’s safeguard
staff, one copy will be forwarded to the CSC, and the fourth copy to the PMB within 24 hours
since receipt of the complaint. Information to be recorded in the complaint log will consist of:
o The date and time of the complaint;
o The name, address and contact details of the complainant;
o A short description of the complaint;
o Actions taken to address the complaint, including contact persons and findings at each step
in the complaint redress process;
o The dates and times for the purpose of contact during the redress process;
o The final resolution of the complaint;
o The date, time and manner in which the complainant was informed thereof;
o The complainant’s signature when resolution has been obtained.
67. Minor complaints will be dealt with within one week. Within two weeks (and weekly
thereafter), a written reply will be delivered to the complainant (by hand, post, fax, e-mails)
indicating the procedures taken and progress to date.
68. The main objective will be to resolve an issue as quickly as possible by the simplest means,
involving as few people as possible, and at the lowest possible level. Only when an issue cannot
be resolved at the simplest level and/ or within 15 days, will other authorities be involved. Such a
STAKEHOLDER ENGAGEMENT PLAN (SEP)
Renewable Energy Accelerating Change (REACH) P a g e | 35
situation may arise, for example, when damages are claimed, the to-be-paid amount cannot be
resolved, or damage causes are determined.
69. Grievances related to Gender Based Violence (GBV): To avoid the risk of
stigmatization, exacerbation of the mental/psychological harm and potential reprisal, the GRM
shall have a different and sensitive approach to GBV related cases. Where such a case is reported
to the GRM, it should immediately be referred to the appropriate service providers, such as
medical and psychological support, emergency accommodation, and any other necessary services.
It should also be reported to the safeguard staff of the PMB who can advise on relevant service
providers. Data on GBV cases should not be collected through the GRM unless operators have
been trained on the empathetic, non-judgmental and confidential collection of these complaints.
Only the nature of the complaint (what the complainant says in her/his own words) and additional
demographic data, such as age and gender, can be collected as usual. All grievance related to
Gender Based Violence will be filed in a separate document and will be kept secure and
confidential.
70. Publicizing the GRM. The NPT, PMB will be in charge of publicizing the GRM. PMB
should ensure that GRM is explained during public meetings. PMB should also ensure that leaflets
on GRM are distributed during public meetings and made available at ward/commune levels with
contact numbers of the focal person for the GRM. Posters will be also be posted at commune
levels.
71. Independent monitoring consultants (environmental, social and resettlement), will be
selected by NPT, PMB through bidding. Independent monitoring consultants are responsible for
checking the procedures and decisions on settling complaints. Independent monitoring consultants
may propose additional measures to address any outstanding complaints. While checking the
procedure for complaint resolution and reviewing the decision on complaint resolution, the
independent monitoring agencies are required to closely coordinate with the Vietnam Fatherland
Front, whose members are responsible for monitoring law enforcement of local complaints.
72. The following procedures shall be followed while filing and processing complaints
through the above described GRM structures:
(i) Grievance Register Book: A grievance register book shall be opened and kept in the office
of resident engineer. All grievances shall be registered when and upon the receipt of
complaints from the aggrieved. The book shall have: (i) case reference number, (ii) the
aggrieved name, (iii) the date the case is received, (iv) the date the case is resolved and,
(v) a remarks column;
(ii) Responsibility for Registering Complains: the resident focal point in the project area shall
register in the Grievance Register Book all written complaints received;
(iii) Case Receipt: Within 24 hours of receiving complaints, the monitoring consultant shall
issue a letter to the aggrieved acknowledging receipt of the case and providing a date when
the case will be reviewed as well as the venue;
(iv) Public Access to the book: The book shall be accessible to the public;
(v) GBV grievances will not be documented in the public accessible book. However, a GBV
action plan will be prepared to manage related risks. The all-level women’s unions will be
engaged for awareness raising and ensure a system that capture GBV/SEA and HIV/AIDS
related issues will be developed;
(vi) PAPs: All PAPs who have issues with their compensation and assistances are required to
submit written complaints to the appropriate level of GRM.
THE GRIEVANCE PROCESS CHART
STAKEHOLDER ENGAGEMENT PLAN (SEP)
Renewable Energy Accelerating Change (REACH) P a g e | 36
Management level
Project level
Province level
District level
Commune level
Local community level
VII. MONITORING AND REPORTING
73. During the project implementation phase, the SEP will be periodically revised and updated
as necessary in the course of off-grid solutions project implementations in order to ensure that the
information presented herein is consistent and is the most recent, and that the identified methods
of engagement remain appropriate and effective in relation to the project context and specific
phases of the development. Any major changes to the project related activities and to its schedule
will be duly reflected in the SEP.
74. Monthly summaries and internal reports on public grievances, enquiries and related
incidents, together with the status of implementation of associated corrective actions will be
collated by responsible staff and referred to the senior management of the project. The monthly
summaries will provide a mechanism for assessing both the number and the nature of complaints
and requests for information, along with the Project’s ability to address those in a timely and
satisfactorily manner.
Follow up with World Bank Office
If not resolved
Follow up with GRM monitor
Provincial People’s Committee (PPC)
District People’s Committee (C/DPC)
Local leader/ Fatherland Front/Mediation channel
Commune People’s Committee (W/CPC)
Inform
Complainant
World Bank & Independent Monitor
Maj
or
issu
es
If not resolved
If r
eso
lved
Commune PC Office
Project Management Board (PMB)
Provincial PC Office Secretariat
If not resolved
If not resolved
If r
eso
lved
If
res
olve
d
If r
esol
ved
If
res
olve
d
If not resolved
Grievance Redress Services (GRS)
Notify
District People’s Court
Provincial People’s Court
STAKEHOLDER ENGAGEMENT PLAN (SEP)
Renewable Energy Accelerating Change (REACH) P a g e | 37
7.1. Involvement of Stakeholder in Monitoring Activities
75. Monitoring Indicators. The NPT, PMB will monitor the project implementation to assess
progress on indicators to be defined in the results framework, such as roads/canal/sewage system
rehabilitated/built; beneficiary satisfaction on such as the invested items of the project;
employment creation through the civil work; and functional maintenance systems. More specific
monitoring indicators on environmental and social issues, such as noise levels, air quality, water
quality, soil erosion, traffic and other occupational or community accidents and social issues
including gender impact will be proposed in the ESMPs. The functioning of the GRM will be also
closely monitored. The NPT, PMB will also need to monitor stakeholder engagement itself. This
includes data on the number of meetings (or focus groups), how many people participated, etc.
76. Internal Monitoring. The NPT, PMB will prepare data on activities and output in regular
monthly and quarterly reports based on input from the supervision consultant and the contractor.
To the extent possible, the monitoring and evaluation process will be participatory, engaging
community members benefiting from the infrastructure investments. A baseline survey and end-
line beneficiary survey will be carried out to measure who and to what extent people benefit from
the infrastructure as well as how it affects their lives in both social and economic terms. The
Monitoring and Evaluation (M&E) system will target the documentation of case studies capturing
the impact of the project on communities, taking into account gender, impacts on vulnerable or
marginalized groups and host communities.
77. Independent E&S monitoring consultants. An independent consultant will be hired by
the NPT, PMB to monitor the implementation of E&S instruments. The overall objective of
independent monitoring is to provide a periodic independent evaluation of the results of
implementing the environmental and social risk/impact management objectives, such as the
changes in living standards and employment, income rehabilitation and the social basis of those
affected, effectiveness, impacts and sustainability of entitlements, the need for additional
measures to minimize the damage (if any). The agency will be responsible for carrying out
environmental sampling, monitoring and marking report during subproject implementation. The
implementation of the independent monitoring mission should be based on the terms of reference
approved by World Bank. The independent monitoring agency will begin its work as soon as the
project implementation begins. Monitoring report will be periodically submitted to the NPT and
the World Bank (respectively every 03 months for NPT and every 6 months for WB in
construction phase). The agency will also supply specialized assistance to NPT and E&S matters.
7.2. Reporting back to Stakeholder
78. The project performance assessed through monitoring activities will be reported back to
stakeholders during the operation and maintenance phase, such as through disclosure of
monitoring outcome and engagement local community. The lessons learned through the
monitoring will also contribute to the design of future subprojects and be shared with their
stakeholders.
79. Monitoring and evaluation of the stakeholder process is considered vital to ensure the
project will be able to respond to identified issues and alter the schedule and nature of engagement
activities to make them more effective. Adherence to the following
characteristics/commitments/activities will assist in achieving successful engagement:
(i) Sufficient resources to undertake the engagement;
(ii) Inclusivity (inclusion of key groups) of interactions with stakeholders;
(iii) Promotion of stakeholder involvement;
(iv) Sense of trust shown by all stakeholders;
(v) Clearly defined approaches; and
STAKEHOLDER ENGAGEMENT PLAN (SEP)
Renewable Energy Accelerating Change (REACH) P a g e | 38
(vi) Transparency in all activities.
80. Monitoring of the stakeholder engagement process allows the efficacy of the process to be
evaluated. Specifically, by identifying key performance indicators that reflect the objectives of the
SEP and the specific actions and timings, it is possible to both monitor and evaluate the process
undertaken. Two distinct but related monitoring activities in terms of timing will be implemented:
(i) During the engagement activities: short-term monitoring to allow for adjustments/
improvements to be made during engagement; and
(ii) Following completion of all engagement activities: review of outputs at the end of
engagement to evaluate the effectiveness of the SEP as implemented.
VIII. RESOURCES AND RESPONSIBILITIES FOR IMPLEMENTING
STAKEHOLDER ENGAGEMENT ACTIVITIES
8.1. Resources
81. The NPT, PMB is the implementing agency, and directly manages the project
implementation. The Environmental and Social Specialists within the NPT, PMB have overall
responsibility on preparation and implementation of the relevant safeguard instruments, including
the SEP, and ensuring continuous community outreach and consultation, monitoring and
evaluating program implementation and impacts, developing and managing the grievance redress
mechanism (GRM) and reporting results to various stakeholders. Other specialists and officers in
the NPT, PMB will support the Environmental and Social Specialists in stakeholder engagement
activities.
82. The NPT, PMB shall be responsible for the implementation of the Stakeholder
Engagement Activities. Its main tasks are:
a. Preparation of the SEP;
b. Preparation of quarterly reports on social and environmental activities to the World
Bank.
83. Regarding GRM implementation, the NPT, PMB will be assisted by DLFDCs and the
District Inspectorates. A focal person will be identified within the DLFDCs or the District
inspectorates to answer to questions regarding the GRM; and the contact information of the NPT,
PMB and other key persons will also be indicated in SEP.
84. The construction supervision consultant (CSC). The NPT, PMB will be supported by a
contracted engineering and supervision consultant who will be responsible for monitoring the
contractors of the civil works as well as monitoring adherence to the safeguard instruments
including the SEP.
85. Contractor. The contractor will assign an Environmental, Social, Health and Safety
(ESHS) officer, who will be responsible for the implementation of environmental and social
requirements at construction sites. The ESHS officer will also maintain regular contact with
affected communities at the site and assist in community awareness-raising and addressing their
grievances.
86. Budgetary resources for stakeholder engagement. Adequate budget for stakeholder
engagement will be allocated from the overall project cost, which will include cost for organizing
meetings, workshops and training, hiring of staff, field visits to subproject locations, translation
and printing of relevant materials and operating GRMs. The cost for environmental and social
mitigation measures at construction sites will be integrated into the construction costs and will be
borne by the contractors.
STAKEHOLDER ENGAGEMENT PLAN (SEP)
Renewable Energy Accelerating Change (REACH) P a g e | 39
8.2. Management Functions and Responsibilities
87. The Stakeholder Engagement activities will form part of the Environmental and Social
Commitment Plan (ESCP). This is a tool which will commit stakeholders to ensure that the
planned activities are implemented and will form part of project approval documents which will
be monitored by the World Bank. The monitoring and evaluation framework for the project will
also have indicators on the ESCP whose implementation progress will be tracked and reported
accordingly. ESCP implementation progress report will be periodically produced and shared with
stakeholders for review, deliberation and action.
88. Stakeholder engagement activities at community level will mostly be done by NPT, PMB
(E&S team) who will be supported by the relevant departments at city/province level. Overall
management responsibility for implementing the SEP will rest with the Director of the PMB.
8.3. Budget for the SEP Preparation and Implementation
89. Funding for preparation and implementation of the SEP will be charged based on the
specific activities proposed in each SEP. This expense is calculated on the funding of the project.
90. Fund for the SEP preparation and implementation will be allocated from NPT’s
counterpart fund. The NPT will provide adequate funding for preparation and implementation of
the SEP.
91. The NPT, PMB will review this plan every six months to determine if any changes to
stakeholder classification or engagement are required. If so, the plan will be updated, and a new
revision distributed, and the budget will be revised accordingly.
STAKEHOLDER ENGAGEMENT PLAN (SEP)
Renewable Energy Accelerating Change (REACH) P a g e | 40
ANNEX
Consultation undertaken
Date Engagement
Activity
Participants Summary of Stakeholder Engagement Activities
May 25
2020
Consultation and
FGD
Representative of Phu My town PC,
Ba Ria – Vung Tau province
Discussion contents. SPMB and consultant submit the proposal on the
construction site of the 500kV Bac Chau Duc substation and T/Ls subproject in
Ba Ria - Vung Tau province.
Feedback from Participants. The People's Committee of Phu My town agreed
on the location of the 500kV Bac Chau Duc substation and connection, including
the 500kV T/L going through Phu My town. However, before implementing the
subproject, it is recommended that the project owner contact the specialized
agencies under the People's Committee of Phu My town to carry out the
prescribed procedures.
June 23
2020
Consultation and
FGD
Representative of Chau Đuc
District PC, Ba Ria – Vung Tau
province
Discussion contents. SPMB and consultant submit the proposal on the
construction site of the 500kV Bac Chau Duc substation and T/Ls subproject in
Ba Ria - Vung Tau province
Feedback from Participants. Chau Duc District People's Committee agreed on
the contents of the agreement on the location for the 500kV Chau Duc substation
and T/Ls
July 3
2020
Consultation and
FGD
Representative of Ba Ria Rubber
Joint Stock Company
Discussion contents. SPMB and consultant submit the proposal on the
construction site of the 500kV Bac Chau Duc substation and T/Ls subproject in
Ba Ria - Vung Tau province
Feedback from Participants. Ba Ria Rubber Joint Stock Company agreed on
the construction location of the 500kV Bac Chau Duc substation and the direction
of the 500kV and 220kV T/Ls. The Ba Ria Rubber Joint Stock Company
proposed to recover the remaining land in the surrounding area.
Sep. 14
2020
Consultation and
FGD
Representative of Department of
Construction of Ba Ria - Vung Tau
province
Discussion contents. SPMB and consultant submit the proposal on the
construction site of the 500kV Bac Chau Duc substation and T/Ls subproject in
Ba Ria - Vung Tau province
Feedback from Participants. The Department of Construction approves the
location of the 500kV Bac Chau Duc substation and the direction of the 500kV -
STAKEHOLDER ENGAGEMENT PLAN (SEP)
Renewable Energy Accelerating Change (REACH) P a g e | 41
Date Engagement
Activity
Participants Summary of Stakeholder Engagement Activities
220kV T/Ls in Chau Duc district and Phu My town, Ba Ria - Vung Tau province.
Specifically:
- Location of Bac Chau Duc 500kV substation: belonging to Cu Bi rubber farm,
Cu Bi commune, Chau Duc district, with an area of about 16ha.
- 500kV transmission line: includes 02 parallel lines, 2.8km/line in length, width
of safety corridor 32m
- 220kV transmission line: includes 04 circuit line, 15.5km in length, width of
safety corridor 25m.
SPMB is responsible for contacting the relevant agencies and units to carry out
the follow-up procedures in accordance with current regulations. During the
construction process, it is necessary to contact the People's Committee of Phu My
town, the People's Committee of Chau Duc district and the units managing the
related infrastructure systems to ensure the construction does not affect other
infrastructure systems.
SPMB must ensure to return the road surface and pavement to its original
conditions after construction is completed
Sep. 23
2020
Consultation and
FGD
Representative of Ba Ria - Vung
Tau province People Committee
Discussion contents. The construction site of the 500kV Bac Chau Duc
substation and T/Ls subproject in Ba Ria - Vung Tau province
Feedback from Participants. The People's Committee of Ba Ria - Vung Tau
province approves the location of the 500kV Bac Chau Duc substation and the
direction of the 500kV - 220kV T/Ls in Chau Duc district and Phu My town, Ba
Ria - Vung Tau province. Specifically:
- Location of Bac Chau Duc 500kV substation: belonging to Cu Bi rubber farm,
Cu Bi commune, Chau Duc district, with an area of about 16ha.
- 500kV transmission line: includes 02 parallel lines, 2.8km/line in length, width
of safety corridor 32m
- 220kV transmission line: includes 04 circuit line, 15.5km in length, width of
safety corridor 25m.
SPMB is responsible for contacting the relevant agencies and units to carry out
the follow-up procedures in accordance with current regulations. During the
construction process, it is necessary to contact the People's Committee of Phu My
STAKEHOLDER ENGAGEMENT PLAN (SEP)
Renewable Energy Accelerating Change (REACH) P a g e | 42
Date Engagement
Activity
Participants Summary of Stakeholder Engagement Activities
town, the People's Committee of Chau Duc district and the units managing the
related infrastructure systems to ensure the construction does not affect other
infrastructure systems, ensure the return of road surface and pavement after the
construction is completed.
Aug. 14
2020
Consultation and
FGD
Representative of People's
Committee of Long Thanh district,
Dong Nai province
Discussion contents. SPMB and consultant submit the proposal on the
construction site of the 500kV Bac Chau Duc substation subproject and T/Ls in
Dong Nai province.
Feedback from Participants. The People's Committee of Long Thanh district
agreed on the direction of the 500kV T/L going through Dong Nai province of
the 500kV Bac Chau Duc substation sub-project and the TL. Specifically:
- The 500kV T/L in Dong Nai province is 5.9km long, passes through Phuoc
Binh, Bau Can and Tan Hiep communes, Long Thanh district, connected to the
DC (end point) of the existing 500kV Phu My - Long Thanh - Song May
transmission line.
Aug. 27
2020
Consultation and
FGD
Representative of Department of
Agriculture and Rural Development
of Dong Nai province
Discussion contents. SPMB and consultant submit the proposal on the
construction site of the 500kV Bac Chau Duc substation subproject and T/Ls in
Dong Nai province
Feedback from Participants. The Department of Agriculture and Rural
Development of Dong Nai province agreed to the direction of the 500kV
transmission line through Dong Nai province of the Bac Chau Duc 500kV
substation and T/Ls subproject.
Aug. 27
2020
Consultation and
FGD
Representative of Department of
Transport of Dong Nai province
Discussion contents. SPMB and consultant submit the proposal on the
construction site of the 500kV Bac Chau Duc substation subproject and T/Ls in
Dong Nai province.
Feedback from Participants. The Department of Transport of Dong Nai
province comment: the option of the 500kV T/L of the 500kV Bac Chau Duc
substation subproject does not affect the central road system and the provincial
road.
Aug. 28
2020
Consultation and
FGD
Representative of Department of
Natural Resources and
Environment of Dong Nai province
Discussion contents. SPMB and consultant submit the proposal on the
construction site of the 500kV Bac Chau Duc substation subproject and T/Ls in
Dong Nai province.
STAKEHOLDER ENGAGEMENT PLAN (SEP)
Renewable Energy Accelerating Change (REACH) P a g e | 43
Date Engagement
Activity
Participants Summary of Stakeholder Engagement Activities
Feedback from Participants. Department of Natural Resources and
Environment comment: the direction of the 500kV T/L in the area of Long Thanh
district goes through the zoning land of perennial crops land, land for other
annual crops, rural residential land and traffic land. Therefore, after being agreed
on the route by the Provincial People's Committee, the Project Owner is
requested to contact the People's Committee of Long Thanh District to register
the demand in the district land use plan and plan as a basis for implementation.
Sep. 04
2020
Consultation and
FGD
Representative of Department of
Construction of Dong Nai province
Discussion contents. SPMB and consultant submit the proposal on the
construction site of the 500kV Bac Chau Duc substation subproject and T/Ls in
Dong Nai province.
Feedback from Participants.
- Department of Construction agreed on the part of the 500kV T/L goes through
Dong Nai province of the Bac Chau Duc 500kV substation and T/Ls subproject
- After being agreed on the route direction by the Provincial People's Committee,
the project owner is requested to coordinate with the People's Committee of Long
Thanh district to update the new rural planning profile and other relevant plans
Sep. 14
2020
Consultation and
FGD
Representative of Department of
Industry and Trade of Dong Nai
province
Discussion contents. SPMB and consultant submit the proposal on the
construction site of the 500kV Bac Chau Duc substation subproject and T/Ls in
Dong Nai province.
Feedback from Participants. Department of Trade has the following comments:
- The 500kV Bac Chau Duc substation and T/Ls subproject is consist with the
National Electricity Development Plan for the period 2011-2020 with a vision to
2030 (revised Planning VII)
- Agree to the agreement on the direction of the 500kV T/L part goes through
Dong Nai province of the Bac Chau Duc 500kV substation and T/Ls subproject.
Specifically:
+ Start point: 500kV busbar of 500/220kV Bac Chau Duc substation
+ End point: belongs to the existing 500kV Phu My - Long Thanh - Song May
transmission line
+ Length: includes 02 parallel lines of double circuit lines, 2.8km long/line. The
line center between the two lines is 30-40m apart
STAKEHOLDER ENGAGEMENT PLAN (SEP)
Renewable Energy Accelerating Change (REACH) P a g e | 44
Date Engagement
Activity
Participants Summary of Stakeholder Engagement Activities
+ Width of safety corridor: 32m.
- After getting agreement on route direction by PPC, project owner is requested
to:
+ Inform the project implementation progress to the Department of Trade.
+ Coordinate with the People's Committee of Long Thanh district to determine
specific locations of land acquisition, prepare compensation plans, register land
use plans and plans with the locality.
+ Agree with relevant ministries on electric tower (if any).
+ When designing, it is required to ensure technical solutions and ensure the
safety corridor according to regulations.
Oct. 14
2020
Consultation and
FGD
Representative of Dong Nai
Province People's Committee
Discussion contents. SPMB and consultant submit the proposal on the
construction site of the 500kV Bac Chau Duc substation subproject and T/Ls in
Dong Nai province.
Feedback from Participants. Dong Nai People's Committee has the following
comments:
- The 500kV Bac Chau Duc substation and T/Ls subproject is consist with the
National Electricity Development Plan for the period 2011-2020 with a vision to
2030 (revised Planning VII).
- Agree to the agreement on the direction of the 500kV T/L part goes through
Dong Nai province of the Bac Chau Duc 500kV substation and TL sub-project.
Specifically:
+ Start point: 500kV busbar of 500/220kV Bac Chau Duc substation
+ End point: belongs to the existing 500kV Phu My - Long Thanh - Song May
transmission line
+ Length: includes 02 parallel lines of double circuit lines, 2.8km long / line. The
line center between the two lines is 30-40m apart
+ Width of safety corridor: 32m.
- After getting agreement on route direction by PPC, project owner is requested
to:
+ Inform the project implementation progress to the Department of Trade.
STAKEHOLDER ENGAGEMENT PLAN (SEP)
Renewable Energy Accelerating Change (REACH) P a g e | 45
Date Engagement
Activity
Participants Summary of Stakeholder Engagement Activities
+ Coordinate with the People's Committee of Long Thanh district to determine
specific locations of land acquisition, prepare compensation plans, register land
use plans and plans with the locality.
+ Agree with relevant ministries on electric tower (if any).
Aug. 10
2020
Discussion
meeting at sub-
projects locations
5 participants, inlcude:
+ Representative of VRG Saigon
Investment Joint Stock Company
+ Representative of PECC3
Discussion contents. surveyed and unified the location of the 220kV Phuoc
Dong substation
Feedback from Participants. Agree on the location for construction of the
220kV Phuoc Dong substation as follows:
- The substation is located in block CD.2 in the Industrial - Urban - Service
Complex Phuoc Dong - Boi Loi, invested by Saigon VRG Investment Joint Stock
Company, located in Don Thuan commune, Trang Bang district, Tay Ninh
province, near the east canal, the road to the station is expected to be connected to
the internal road D7 zone B with about 50m long, the station area is about 4.8ha
Aug. 14
2020
Discussion
meeting at Tay
Ninh Province
MOT
12 participants, inlcude:
+ Representative of Department of
Trade
+ Representative of UBND Go Dau
District
+ Representative of Department of
Natural Resources and
Environment
+ Representative of Tay Ninh
Power Company
+ Representative of VRG Saigon
Investment Joint Stock Company
+ Representative of SPMB
+ PECC3
Discussion contents. advise the People's Committee of Tay Ninh province to
agree on the construction location of Phuoc Dong 220kV substation
Feedback from Participants. - Tay Ninh Power Company: agreed on the construction location of the 220kV
Phuoc Dong substation in Don Thuan commune, Trang Bang town, Tay Ninh
province, the land for construction of the station in Phuoc Dong Industrial Park.
- Department of Natural Resources and Environment: agreed on the
construction location of the 220kV Phuoc Dong substation in Don Thuan
commune, Trang Bang town, Tay Ninh province, the land for construction of the
station in Phuoc Dong Industrial Park. Investor coordinates with Saigon VRG
JSC to determine the suitability of the station's construction location with the
approved plan.
- VRG Saigon Investment Joint Stock Company: agreed on the construction
location of the 220kV Phuoc Dong substation in Don Thuan commune. The
location of the station's construction has been submitted to the Provincial People's
Committee by Saigon VRG Investment Joint Stock Company to adjust the
planning.
STAKEHOLDER ENGAGEMENT PLAN (SEP)
Renewable Energy Accelerating Change (REACH) P a g e | 46
Date Engagement
Activity
Participants Summary of Stakeholder Engagement Activities
- Department of Trade: agreed on the construction location of the 220kV Phuoc
Dong substation in Don Thuan commune, Trang Bang town, Tay Ninh province,
the land for construction of the station in Phuoc Dong Industrial Park.
Jan. 14
2021
Discussion
meeting at Binh
Phuoc Province
MONRE
16 participants, inlcude:
+ Representative of DONRE
+ Representative of WB
+ Representative of NPT
+ Representative of SPMB
+ Representative of PECC3
+ Representative of PECC2
+ Representative of PECC4
Discussion contents. Environmental status, sensitive areas, forest and
biodiversity status, ethnic minorities in the subproject area 500kV Krong Buk -
Tay Ninh 1 T/L. Discussion on environmental and natural, social issues to pay
attention when implementing the subproject in Binh Phuoc province.
Feedback from Participants.
- MONRE (Mr. Vo Van Dinh):
+ The 500kV Krong Buk - Tay Ninh 1 T/L is about 25km away from Bu Gia
Map National Park, so it is unlikely to affect this national park.
+ Issues to note in the subproject implementation area: use water from Thac Mo
lake, Phuoc Hoa, ...
+ The natural forests in Binh Phuoc province are mainly above (Bu Gia Map
National Park) and Bu Dop district bordering with Cambodia, quite far from the
transmission line, therefore no effect.
+ Historical relics: In Binh Phuoc province, there is Ta Thiet regional base zone
at Loc Ninh district, more than 27km from the line.
+ Most of the districts in the province have ethnic minorities. According to
statistics, there are about 45 ethnic groups, of which the majority are the S’tieng
and the Kho Me ethnic groups and these groups are scattered in the communes.
- Representative of WB (Mr. Son and Mr. Hung):
+ The line has a number of locations crossing the lake (Dau Tieng lake, ...),
however, the sub-project is designed while crossing the lake with no construction
of pillars in the lake bed. Therefore, it has almost no effect on local water
sources.
+ We hope to receive the support of the province and departments for the project
to implement smoothly and on schedule.
March
15,
2021
Discussion
meeting at Dak
Nong DONRE
8 participants included:
+ Representative of DONRE
Discussion content.
- Planned location and scale of the sub-project implemented in the province.
STAKEHOLDER ENGAGEMENT PLAN (SEP)
Renewable Energy Accelerating Change (REACH) P a g e | 47
Date Engagement
Activity
Participants Summary of Stakeholder Engagement Activities
+ Representative of Environmental
Protection Agency – DONRE
+ Representative of Planning
Department – DONRE
+ Representative Land Registration
Department – DONRE
+ Representative of Ethnic
Committee
+ Representative of Land
development center
+ Representative of PECC3
- Social and environmental policies of the government and the World Bank.
- Project social and environmental documents (ESMF, RPF, EMPF, ESCP, SEP,
LMP).
- Issues of environment, nature, society, and ethnic minorities need attention
when implementing the sub-project in the province.
Comments.
- DONRE (Mr. Vo Van Minh):
+ The project is planning to use World Bank loans, has a detailed process, it is
expect that the project to consider and study the project's support level for
affected people's damage to be higher or at least equal to the unit price and
support level of the province
+ Currently, the province is planning to develop wind and solar energy, the
project will assist in offloading the area.
- Planning department- DONRE (Mr. Nguyen Khac Huy):
+ Study the direction of the tranmission line to avoid sensitive areas and nature
reserves as much as possible
+ Study on adequate compensation policy according to the policies of the
Government and WB
- Land Registration Department - DONRE (Mr. Nguyen Viet The):
+ For residential land, during the implementation process, project owners are
required to consider and support special cases that may arise in accordance with
the actual situation in the locality.
March
16,
2021
Discussion
meeting at Dak
Lak DONRE
6 participants included:
+ Representative of Branch of Land
Administration – DONRE
+ Representative of Environmental
Protection Agency – DONRE
Discussion content.
- Planned location and scale of the sub-project implemented in the province.
- Social and environmental policies of the government and the World Bank.
- Project social and environmental documents (ESMF, RPF, EMPF, ESCP, SEP,
LMP).
STAKEHOLDER ENGAGEMENT PLAN (SEP)
Renewable Energy Accelerating Change (REACH) P a g e | 48
Date Engagement
Activity
Participants Summary of Stakeholder Engagement Activities
+ Representative of Ethnic
Committee
+ Representative of Land
development center
+ Representative of PECC3
- Issues of environment, nature, society, and ethnic minorities need attention
when implementing the sub-project in the province.
Comments.
- Environmental Protection Agency (Mr. Nguyen Hoang Tung):
+ Environmental and social policy frameworks and documents are established in
accordance with the law and World Bank standards, and the locality supports
these policy frameworks and documents.
+ As for the preliminary environmental assessment, such a preliminary
environmental assessment is fine in the project preparation phase.
- Branch of Land Administration (Mr. Nguyen Anh Tuan):
+ During project implementation, it is recommended that the project owner study
the differences in policy frameworks.
March
16,
2021
Discussion
meeting at Dong
Nai DONRE
5 participants included:
+ Representative of Branch of Land
Administration – DONRE
+ Representative of Environmental
Protection Agency – DONRE
+ Representative of PECC3
Discussion content.
- Planned location and scale of the sub-project implemented in the province.
- Social and environmental policies of the government and the World Bank.
- Project social and environmental documents (ESMF, RPF, EMPF, ESCP, SEP,
LMP).
- Issues of environment, nature, society, and ethnic minorities need attention
when implementing the sub-project in the province.
Comments.
- Branch of Land Administration (Mr. Nguyen Hong Que):
+ Support the policy of project implementation to ensure electricity supply for
socio-economic development for the region
+ Land acquisition, site clearance and resettlement need to harmonize policies of
Vietnam and the World Bank to ensure the implementation of compensation and
resettlement for all projects in the province.
STAKEHOLDER ENGAGEMENT PLAN (SEP)
Renewable Energy Accelerating Change (REACH) P a g e | 49
Date Engagement
Activity
Participants Summary of Stakeholder Engagement Activities
+. The project needs to report to DONRE in arcordance to the project schedule
and to update land use plan and submit to Provincial People's Council for
approval before implementation
+ The legal framework for compensation and resettlement needs to clearly state 3
contents: legal basis for implementation, compensation for land (land for tower
foundations, land) in ROW and support policies.
- Environmental Protection Agency (Ms. Luong Thị Thu Hang):
+ The 500kV Bac Chau Duc sub-project of the 500kV Bac Chau Duc substation
pasing through Dong Nai province is within 2 provinces (Dong Nai and Ba Ria -
Vung Tau), it is necessary to prepare an EIA and submit it to the Ministry of
Natural Resources and Environment for approval according to Vietnam’s laws
and regulation regulations
+ The project implementation area in Dong Nai province is mainly Kinh people,
almost no ethnic minorities.
March
17,
2021
Discussion
meeting at Binh
Phuoc DONRE
6 participants included:
+ Representative of Branch of Land
Administration – DONRE
+ Representative of Environmental
Protection Agency – DONRE
+ Representative of PECC3
Discussion content.
- Planned location and scale of the sub-project implemented in the province.
- Social and environmental policies of the government and the World Bank.
- Project social and environmental documents (ESMF, RPF, EMPF, ESCP, SEP,
LMP).
- Issues of environment, nature, society, and ethnic minorities need attention
when implementing the sub-project in the province.
Comments.
- Environmental Protection Agency (Mr. Vo Van Dinh):
+ Route of the 500kV Krong Buk - Tay Ninh 1 tranmisison shown has meet the
environmental requirements when avoiding sensitive areas in the province (Cat
Tien National Park and Bu Gia Map National Park)
+ For the specific environmental impacts are studied and carefully considered in
the following stage.
STAKEHOLDER ENGAGEMENT PLAN (SEP)
Renewable Energy Accelerating Change (REACH) P a g e | 50
Date Engagement
Activity
Participants Summary of Stakeholder Engagement Activities
- Representative of Branch of Land Administration (Mr. Nguyen Khac
Diep):
+ For those who are not eligible for compensation, the province has issued
Decision No.31/2020/QD-UBND dated 7/12/2020, which will consider the
conditions for support.
+ Local authorities recommend to use the policy and unit price issued by the
Provincial People's Committee to harmonize and ensure compensation and site
clearance for all projects in the province
- Branch of Land Administration (Mr. Vuong Van Hao):
+ The WB policy is to bring benefits to affected people. Proposing the World
Bank to study harmoniously the policies of the project.
Note: Discuss in writing is a two-way communication between PMB, the consultant and stakeholders.
STAKEHOLDER ENGAGEMENT PLAN (SEP)
Renewable Energy Accelerating Change (REACH) P a g e | 51
LEGAL DOCUMENTS AND MINUTES OF CONSULTATION MEETING
STAKEHOLDER ENGAGEMENT PLAN (SEP)
Renewable Energy Accelerating Change (REACH) P a g e | 52
STAKEHOLDER ENGAGEMENT PLAN (SEP)
Renewable Energy Accelerating Change (REACH) P a g e | 53
STAKEHOLDER ENGAGEMENT PLAN (SEP)
Renewable Energy Accelerating Change (REACH) P a g e | 54
STAKEHOLDER ENGAGEMENT PLAN (SEP)
Renewable Energy Accelerating Change (REACH) P a g e | 55
STAKEHOLDER ENGAGEMENT PLAN (SEP)
Renewable Energy Accelerating Change (REACH) P a g e | 56
STAKEHOLDER ENGAGEMENT PLAN (SEP)
Renewable Energy Accelerating Change (REACH) P a g e | 57
STAKEHOLDER ENGAGEMENT PLAN (SEP)
Renewable Energy Accelerating Change (REACH) P a g e | 58
STAKEHOLDER ENGAGEMENT PLAN (SEP)
Renewable Energy Accelerating Change (REACH) P a g e | 59
STAKEHOLDER ENGAGEMENT PLAN (SEP)
Renewable Energy Accelerating Change (REACH) P a g e | 60
STAKEHOLDER ENGAGEMENT PLAN (SEP)
Renewable Energy Accelerating Change (REACH) P a g e | 61
STAKEHOLDER ENGAGEMENT PLAN (SEP)
Renewable Energy Accelerating Change (REACH) P a g e | 62
STAKEHOLDER ENGAGEMENT PLAN (SEP)
Renewable Energy Accelerating Change (REACH) P a g e | 63
STAKEHOLDER ENGAGEMENT PLAN (SEP)
Renewable Energy Accelerating Change (REACH) P a g e | 64
STAKEHOLDER ENGAGEMENT PLAN (SEP)
Renewable Energy Accelerating Change (REACH) P a g e | 65
STAKEHOLDER ENGAGEMENT PLAN (SEP)
Renewable Energy Accelerating Change (REACH) P a g e | 66
STAKEHOLDER ENGAGEMENT PLAN (SEP)
Renewable Energy Accelerating Change (REACH) P a g e | 67
STAKEHOLDER ENGAGEMENT PLAN (SEP)
Renewable Energy Accelerating Change (REACH) P a g e | 68
STAKEHOLDER ENGAGEMENT PLAN (SEP)
Renewable Energy Accelerating Change (REACH) P a g e | 69
STAKEHOLDER ENGAGEMENT PLAN (SEP)
Renewable Energy Accelerating Change (REACH) P a g e | 70
STAKEHOLDER ENGAGEMENT PLAN (SEP)
Renewable Energy Accelerating Change (REACH) P a g e | 71
STAKEHOLDER ENGAGEMENT PLAN (SEP)
Renewable Energy Accelerating Change (REACH) P a g e | 72
STAKEHOLDER ENGAGEMENT PLAN (SEP)
Renewable Energy Accelerating Change (REACH) P a g e | 73
STAKEHOLDER ENGAGEMENT PLAN (SEP)
Renewable Energy Accelerating Change (REACH) P a g e | 74
STAKEHOLDER ENGAGEMENT PLAN (SEP)
Renewable Energy Accelerating Change (REACH) P a g e | 75
STAKEHOLDER ENGAGEMENT PLAN (SEP)
Renewable Energy Accelerating Change (REACH) P a g e | 76
STAKEHOLDER ENGAGEMENT PLAN (SEP)
Renewable Energy Accelerating Change (REACH) P a g e | 77
STAKEHOLDER ENGAGEMENT PLAN (SEP)
Renewable Energy Accelerating Change (REACH) P a g e | 78
STAKEHOLDER ENGAGEMENT PLAN (SEP)
Renewable Energy Accelerating Change (REACH) P a g e | 79
STAKEHOLDER ENGAGEMENT PLAN (SEP)
Renewable Energy Accelerating Change (REACH) P a g e | 80
STAKEHOLDER ENGAGEMENT PLAN (SEP)
Renewable Energy Accelerating Change (REACH) P a g e | 81
STAKEHOLDER ENGAGEMENT PLAN (SEP)
Renewable Energy Accelerating Change (REACH) P a g e | 82
STAKEHOLDER ENGAGEMENT PLAN (SEP)
Renewable Energy Accelerating Change (REACH) P a g e | 83
STAKEHOLDER ENGAGEMENT PLAN (SEP)
Renewable Energy Accelerating Change (REACH) P a g e | 84
STAKEHOLDER ENGAGEMENT PLAN (SEP)
Renewable Energy Accelerating Change (REACH) P a g e | 85
STAKEHOLDER ENGAGEMENT PLAN (SEP)
Renewable Energy Accelerating Change (REACH) P a g e | 86
STAKEHOLDER ENGAGEMENT PLAN (SEP)
Renewable Energy Accelerating Change (REACH) P a g e | 87
STAKEHOLDER ENGAGEMENT PLAN (SEP)
Renewable Energy Accelerating Change (REACH) P a g e | 88
STAKEHOLDER ENGAGEMENT PLAN (SEP)
Renewable Energy Accelerating Change (REACH) P a g e | 89
STAKEHOLDER ENGAGEMENT PLAN (SEP)
Renewable Energy Accelerating Change (REACH) P a g e | 90
STAKEHOLDER ENGAGEMENT PLAN (SEP)
Renewable Energy Accelerating Change (REACH) P a g e | 91