stakeholder meeting: planning study for rehabilitation or...

15
Stakeholder Meeting: Planning Study For Rehabilitation or Replacement of: Powerline FRS Vineyard Road FRS Rittenhouse FRS Bob Eichinger, P.E., CFM Kimley Horn Project Manager August 26, 2010 Felicia Terry, P.E., CFM FCD Project Manager

Upload: others

Post on 06-Aug-2020

14 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Stakeholder Meeting: Planning Study For Rehabilitation or ...apps.fcd.maricopa.gov/.../PVRWA3/StakeholderMeeting1_Presentatio… · Powerline FRS, Vineyard Road FRS, Rittenhouse FRS

Stakeholder Meeting:

Planning Study For Rehabilitation or Replacement of:

Powerline FRSVineyard Road FRSRittenhouse FRS

Bob Eichinger, P.E., CFMKimley Horn Project Manager

August 26, 2010

Felicia Terry, P.E., CFM

FCD Project Manager

Page 2: Stakeholder Meeting: Planning Study For Rehabilitation or ...apps.fcd.maricopa.gov/.../PVRWA3/StakeholderMeeting1_Presentatio… · Powerline FRS, Vineyard Road FRS, Rittenhouse FRS

Meeting Purpose

• Define Project Purpose and Need• Outline Stakeholder Involvement

Page 3: Stakeholder Meeting: Planning Study For Rehabilitation or ...apps.fcd.maricopa.gov/.../PVRWA3/StakeholderMeeting1_Presentatio… · Powerline FRS, Vineyard Road FRS, Rittenhouse FRS

District Flood Control Dams

Page 4: Stakeholder Meeting: Planning Study For Rehabilitation or ...apps.fcd.maricopa.gov/.../PVRWA3/StakeholderMeeting1_Presentatio… · Powerline FRS, Vineyard Road FRS, Rittenhouse FRS

Powerline FRS, Vineyard Road FRS, Rittenhouse FRS (PVR)

Project Background:

• Three Flood Control Dams Built by SCS (Now NRCS) from 1967 to 1969

• PVR Dams Modified with Central Filters: 1991, 1983, 1979

• District is Local Sponsor

• District Operates and Maintains Under Agreements with NRCS

• ADWR is Regulatory Agency

• Located on Arizona State Land Department (ASLD) Property within Superstition Vistas area

Page 5: Stakeholder Meeting: Planning Study For Rehabilitation or ...apps.fcd.maricopa.gov/.../PVRWA3/StakeholderMeeting1_Presentatio… · Powerline FRS, Vineyard Road FRS, Rittenhouse FRS

Modified Easement Area

Page 6: Stakeholder Meeting: Planning Study For Rehabilitation or ...apps.fcd.maricopa.gov/.../PVRWA3/StakeholderMeeting1_Presentatio… · Powerline FRS, Vineyard Road FRS, Rittenhouse FRS

Powerline FRS, Vineyard Road FRS, Rittenhouse FRS (PVR)

Project Background:

• PVR Dams Total 11.6 Miles in Length

• PVR Dams Max. Heights: 21 Ft, 16.5 Ft, 24.3 Ft

• Total Flood Storage of 12,600 Acre-Feet

• Provide 100-year Flood Protection for 169 Square Miles

• Year 2000 Census Downstream Population: 157,000

Page 7: Stakeholder Meeting: Planning Study For Rehabilitation or ...apps.fcd.maricopa.gov/.../PVRWA3/StakeholderMeeting1_Presentatio… · Powerline FRS, Vineyard Road FRS, Rittenhouse FRS

Why are we Rehabilitating or Replacing the Dams?

• Potential for Overtopping During Large Flood Event (PMF)

• Embankment Cracking

• Foundation Deficiencies

• Outlet Pipe Deficiencies

• Earth Fissures: Powerline FRS

• Land Subsidence: Powerline FRS, Vineyard Road FRS (North Third of Dam)

Page 8: Stakeholder Meeting: Planning Study For Rehabilitation or ...apps.fcd.maricopa.gov/.../PVRWA3/StakeholderMeeting1_Presentatio… · Powerline FRS, Vineyard Road FRS, Rittenhouse FRS

Project Goals • Primary District Goal Is Long-Term Flood Protection • Minimized Project Footprint is A Secondary Goal

Project Objectives• Develop and Evaluate Alternatives for Rehab or

Replacement of The PVR Dams• Select an Implementable Alternative• Have NRCS be a Cost Share Partner• Have Construction Completed in 10 to 15 Years

Page 9: Stakeholder Meeting: Planning Study For Rehabilitation or ...apps.fcd.maricopa.gov/.../PVRWA3/StakeholderMeeting1_Presentatio… · Powerline FRS, Vineyard Road FRS, Rittenhouse FRS

Overall Project Milestones

• Planning Study -2 years, (started Sept. 09)

See Work Chart for Work Assignments

• Rehabilitation Plan/EA and Watershed Agreement

• Final Design – 1.5 years – after Planning Study

• IGA with NRCS

• Construction in Phases

Page 10: Stakeholder Meeting: Planning Study For Rehabilitation or ...apps.fcd.maricopa.gov/.../PVRWA3/StakeholderMeeting1_Presentatio… · Powerline FRS, Vineyard Road FRS, Rittenhouse FRS

Issues for Consideration:Win-Win Project

• NRCS Project Partner: NED Alternative• Environmental considerations• Public Meetings• Project Stakeholders Involvement• Future Plans by Others: Roadway crossings and

utilities• Multi-Use and Landscape Aesthetics –By others

Page 11: Stakeholder Meeting: Planning Study For Rehabilitation or ...apps.fcd.maricopa.gov/.../PVRWA3/StakeholderMeeting1_Presentatio… · Powerline FRS, Vineyard Road FRS, Rittenhouse FRS

Regional Context Summary• Land Use Apache Junction / Pinal County/ Mesa /

Queen Creek Superstition Vistas Portalis

• Transportation Scenario B Framework (Superstition Vistas)

• Street / Light Rail

ADOT Planning Corridors• AZ 802• North South Fwy

Page 12: Stakeholder Meeting: Planning Study For Rehabilitation or ...apps.fcd.maricopa.gov/.../PVRWA3/StakeholderMeeting1_Presentatio… · Powerline FRS, Vineyard Road FRS, Rittenhouse FRS

Regional Context Summary• Open Space / Parks Pinal County

• Apache Junction• Superstition Vistas• Portalis

Maricopa County• Maricopa Trail

• Wildlife Corridors• Site Analysis

Page 13: Stakeholder Meeting: Planning Study For Rehabilitation or ...apps.fcd.maricopa.gov/.../PVRWA3/StakeholderMeeting1_Presentatio… · Powerline FRS, Vineyard Road FRS, Rittenhouse FRS

Next Steps for Stakeholders• Today – Develop Goal of Project• 2nd Stakeholder Meeting Brainstorm alternatives and narrow down

to 10• 1st Public Meeting • 3RD Stakeholder Meeting Recommendation for 4 alternatives

• 2nd Public Meeting• 3rd Public Meeting

Page 14: Stakeholder Meeting: Planning Study For Rehabilitation or ...apps.fcd.maricopa.gov/.../PVRWA3/StakeholderMeeting1_Presentatio… · Powerline FRS, Vineyard Road FRS, Rittenhouse FRS

Stakeholder Involvement

• Stakeholder Issues• Define Goals• Stakeholder Expectations

Page 15: Stakeholder Meeting: Planning Study For Rehabilitation or ...apps.fcd.maricopa.gov/.../PVRWA3/StakeholderMeeting1_Presentatio… · Powerline FRS, Vineyard Road FRS, Rittenhouse FRS

Rehabilitation or Replacement of: Powerline FRS

Vineyard Road FRSRittenhouse FRS

Questions/Discussion ?