    Stakeholder Register/Analysis

    Stakeholder Name: Dr. Lipsett (Project Owner/client)Key Stakeholder

    (Y/N): YES

    Interests: Dr. Lipsett (the client) needs a smooth transition to the new laboratory. He needs the

    complete plan for the new laboratory to be finished by the end of the winter term. He expects no

    disruption to existing research projects.

    Stakeholder Communications Strategy:

    Communication Needs: Meeting Preferences:Communication

    Limitations:

    Updates upon completion of

    milestones and consultations

    regarding any major problems

    or difficulties

    Meetings are to be scheduled

    well in advance and should,

    preferably, take place at the

    University of Alberta

    Stakeholder has a busy

    schedule limiting availability

    for meeting.

    Avenues For Communication:

    Meeting (Y/N): YES Telephone (Y/N): YES E-mail (Y/N) : YES

    SWOT Analysis

    Strengths:Valuable knowledge regarding laboratory and researcher needs as well as

    experience dealing with the University of Alberta and its administrations.

    Weakness

    es: Has a busy schedule and requires advanced notice.

    Opportuni

    ties:

    Stands to benefit from project primarily through the reusability of the plan slated

    for development

    Threats:Missing the relocation deadline could hinder other University research programs as

    well as Dr. Lipsetts own research.

    Stakeholder Influence On Project:

    The stakeholder, being the project teams client, has the greatest influence on this project.

    Schedule, cost, objectives, requirements and virtually all other project aspects have and continueto be developed around the clients needs.

    Stakeholder Expectations Management (Key Stakeholders only):

    The stakeholder requires a relocation plan and laboratory layout plan. These requirements put

    major emphasis on scheduling. Scheduling must be completed precisely and with significant time

    Notes: DNA represents does not apply, where information is limited, beyond the required scope and or deemed

    inconsequential.

  • 8/7/2019 Stakeholder register and analysis 1

    2/19

    Stakeholder Register/Analysis

    allocated for last minute changes, unforeseen stakeholder needs, and relocation time slot

    flexibility. The project scope needs to be wide enough to accommodate a potential large amount

    of needs from Dr. Lipsetts researchers.

    Detailed Interests/Priorities Analysis (Key Stakeholders only) :

    Key Stakeholder

    Interests:Efficiency, safety, functionality, organization and schedule adherence.

    Key Stakeholder

    Priorities:

    A well devised plan that meets the needs of himself, his researches

    and colleagues.

    Principal Objective: To relocate and setup a new laboratory with the use of the teams plan

    and strategies.

    Consequences Resulting From Missed Principal Objective: Interruption to research,

    colleagues and the daily activities at the University of Alberta.

    Stakeholder Name: Shannon MacDonald (Project Manager)Key Stakeholder

    (Y/N): NO

    Interests: Project manager needs timely achievement of project goals within the approved

    budget. She expects improvement in her professional growth as well as to gain project

    management experience.

    Stakeholder Communications Strategy:

    Communication Needs: Meeting Preferences:Communication

    Limitations:

    Updates upon completion of

    tasks and advanced notice of

    difficulties and prompt

    circulation in new information.

    Team Meetings take place

    every Monday at 5:00 pm. Any

    additional meeting must

    scheduled well in advance and

    take place at the University of

    Alberta (ETLC).

    Stakeholder has a busy

    schedule limiting availability

    for meeting making efficiency

    a priority.

    Avenues For Communication:

    In Person Meeting (Y/N):

    YESTelephone (Y/N): YES E-mail (Y/N) : YES

    SWOT Analysis

    Notes: DNA represents does not apply, where information is limited, beyond the required scope and or deemed

    inconsequential.

  • 8/7/2019 Stakeholder register and analysis 1

    3/19

    (DNA

    (DNA

    Stakeholder Register/Analysis

    Strengths: Experience with project management, efficient, and has great organizational skills

    Weakness

    es:

    Has a busy schedule and requires advanced notice to address issues.

    Opportuni

    ties:

    Stands to benefit from project primarily through the gaining experience and

    expanding her references.

    Threats: Failure to accomplish goals will lead to loss or reputation and academic standing.

    Stakeholder Influence On Project:

    The stakeholder, being the project manager, has the final say on project direction as well as

    facilitates communication between the client (Dr. Lipsett) and the teams Supervisor (Dr. Sami

    Fahmy ). The stakeholder defines the teams culture and takes responsibility for the projectsdeliverables.

    Notes: DNA represents does not apply, where information is limited, beyond the required scope and or deemed

    inconsequential.

    Stakeholder Expectations Management (Key Stakeholders only):

    Detailed Interests/Priorities Analysis (Key Stakeholders only) :

    Key Stakeholder

    Interests:

    Key Stakeholder

    Priorities:

    Principal Objective:

    Consequences Resulting From Missed Principal Objective

  • 8/7/2019 Stakeholder register and analysis 1

    4/19

    (DNA

    Stakeholder Register/Analysis

    Stakeholder Name: The University of Alberta andAdministration

    Key Stakeholder

    (Y/N): YES

    Interests: The University of Albertas interests lay in the commissioning a fully functional

    laboratory compliant to relevant technological and safety standards. It expects introduction of a

    new laboratory to provide more experimentation options to the professors, students and

    researchers. Thus, the University is interested in a well developed laboratory relocation and

    layout plan.

    Stakeholder Communications Strategy:

    Communication Needs: Meeting Preferences:Communication

    Limitations:

    No communication initiation

    from the project team isrequired. In the event the

    university is needed it can be

    contacted through its

    representatives

    Stakeholders representatives

    have a busy schedule limitingavailability for meeting

    making.

    Avenues For Communication:

    In Person Meeting (Y/N):

    YESTelephone (Y/N): YES E-mail (Y/N) : YES

    SWOT Analysis

    Strengths:

    Stakeholder represents a great deal of knowledge and experience. The stakeholder

    will also provide infrastructure, personnel, furnishings, supplies and various other

    pieces of equipment.

    Weakness

    es:Contact and consultation will be difficult.

    Opportuni

    ties:

    The University will benefit from as a result of the research yielded from students

    who have benefited for the laboratory design.

    Threats: Failure to accomplish goals could lead to loss of research time and quality.

    Stakeholder Influence On Project:

    The University of Alberta will provide many of the resources needed for the project to be

    completed and will, in some areas, control the scope of the project. The project must also meet

    and adhere to all of the Universities policies, rules, and regulations.

    Notes: DNA represents does not apply, where information is limited, beyond the required scope and or deemed

    inconsequential.

  • 8/7/2019 Stakeholder register and analysis 1

    5/19

    Stakeholder Register/Analysis

    Stakeholder Name: The Project Team Key Stakeholder(Y/N): NO

    Interests: Project team is interested in completing this project to the satisfaction of the client

    (Dr. Lipsett) and the teams supervisor (Sami Fahmy). The team is also looking to gain

    experience in the field of project management and to further develop each members skills.

    Stakeholder Communications Strategy:

    Communication Needs: Meeting Preferences:Communication

    Limitations:

    Updates upon completion of

    tasks and advanced notice of

    difficulties and prompt

    circulation in new information.

    Team Meetings take place

    every Monday at 5:00 pm. Any

    additional meeting must

    scheduled well in advance and

    take place at the University of

    Alberta (ETLC).

    Stakeholders have a busy

    schedule limiting availability

    for meeting making efficiency

    a priority.

    Notes: DNA represents does not apply, where information is limited, beyond the required scope and or deemed

    inconsequential.

    Stakeholder Expectations Management (Key Stakeholders only):

    The stateholder requires a plan that does not affect operations of its other research projects,

    departments, and personnel. The University has allocated laboratory space currently being

    occupied by Dr. Lipsetts researchers to another research team. In order for the other research

    team to move forward Dr. Lipsetts must vacate his current laboratory. University students must

    not be affected by the move ether.

    Detailed Interests/Priorities Analysis (Key Stakeholders only) :

    Key Stakeholder

    Interests:Laboratory is vacated and a new one is setup.

    Key Stakeholder

    Priorities:Safety is a priority and also scheduled deadlines are met.

    Principal Objective: The lab Space is available and new research can begin while Dr. Lipsetts

    research continues.

    Consequences Resulting From Missed Principal Objective: Loss of research time and

    potential losses in research due to experimentation alterations and or delays.

  • 8/7/2019 Stakeholder register and analysis 1

    6/19

    (DNA

    (DNA

    Stakeholder Register/Analysis

    Avenues For Communication:

    In Person Meeting (Y/N):

    YESTelephone (Y/N): YES E-mail (Y/N) : YES

    SWOT Analysis

    Strengths:Together, the teams represents a great deal of knowledge and experience and are

    proficient communicators and problems solvers

    Weakness

    es:Varying schedules make holding additional meetings difficult.

    Opportuni

    ties:

    The team stands to benefit from this project primarily through the acquiring

    experience and expanding our references.

    Threats: Failure to accomplish goals will lead to loss or reputation and academic standing.

    Stakeholder Influence On Project:

    The stakeholders, being the project team, collectively control the quality of work that is done.

    Our experiences, thoughts, and ideas will shape every aspect of this project in an attempt to

    provide a high quality finished product. The project team members are all held accountable to

    each other and the project manager to meet the needs of the team and client.

    Notes: DNA represents does not apply, where information is limited, beyond the required scope and or deemed

    inconsequential.

    Stakeholder Expectations Management (Key Stakeholders only):

    Detailed Interests/Priorities Analysis (Key Stakeholders only) :

    Key Stakeholder

    Interests:

    Key Stakeholder

    Priorities:

    Principal Objective:

    Consequences Resulting From Missed Principal Objective

  • 8/7/2019 Stakeholder register and analysis 1

    7/19

    (DNA

    Stakeholder Register/Analysis

    Stakeholder Name: Undergraduate Mechanical

    Engineering Students

    Key Stakeholder

    (Y/N): NO

    Interests:The undergraduate mechanical engineering students interest in this project revolves

    around their productivity remaining unencumbered. The students are to be minimally affected by

    the move and in no way is their safety to be compromised. The new laboratory must not create

    any noise that may affect students learning in class room or study areas.

    Stakeholder Communications Strategy:

    Communication Needs: Meeting Preferences:Communication

    Limitations:

    None of the undergraduate

    students have expressed any

    need or desire to be informed

    of the about planning progress

    or direction

    This stakeholder group

    represents a large number of

    individuals, it is nearly

    impossible to all of them..

    Avenues For Communication:

    In Person Meeting (Y/N):

    YESTelephone (Y/N): NO E-mail (Y/N) : NO

    SWOT Analysis

    Strengths:Students represent a great deal of knowledge and can be polled for ideas,

    concerns, and constraints.

    Weakness

    es:Their numbers will make them difficult to survey.

    Opportuni

    ties:Future labs in which they can utilize for their research.

    Threats: Disruption to the students can hinder their productivity.

    Stakeholder Influence On Project:

    The stakeholder group must be affected as little as possible. The arrangement of the lab must

    ensure that the limited study and classroom space in the Mechanical Engineering building is not

    affected by laboratory noise. Students must also be able to access the laboratory in the event

    Notes: DNA represents does not apply, where information is limited, beyond the required scope and or deemed

    inconsequential.

  • 8/7/2019 Stakeholder register and analysis 1

    8/19

    (DNA

    (DNA

    Stakeholder Register/Analysis

    teachers or researchers are T.As for their respective courses.

    Stakeholder Name: Researchers and Individuals Using theLaboratory

    Key Stakeholder

    (Y/N): YES

    Interests: This stakeholder group requires a well equipped laboratory which allows them to

    experiment and conduct analysis in a comfortable atmosphere. They expect that the new

    laboratory will not be unfamiliar to them and that it is a safe place to work and study. This

    stakeholder group must also not be greatly affected by the migration. The plan must

    accommodate their schedules and experiments.

    Stakeholder Communications Strategy:

    Communication Needs: Meeting Preferences:Communication

    Limitations:

    They require no updates or

    communications on a regular

    basis. They need only to be

    This stakeholder group is

    extremely busy and do not

    require meetings.

    Stakeholders have a busy

    schedule.

    Notes: DNA represents does not apply, where information is limited, beyond the required scope and or deemed

    inconsequential.

    Stakeholder Expectations Management (Key Stakeholders only):

    Detailed Interests/Priorities Analysis (Key Stakeholders only) :

    Key Stakeholder

    Interests:

    Key Stakeholder

    Priorities:

    Principal Objective:

    Consequences Resulting From Missed Principal Objective

  • 8/7/2019 Stakeholder register and analysis 1

    9/19

    Stakeholder Register/Analysis

    given specifics.

    Avenues For Communication:

    In Person Meeting (Y/N):YES

    Telephone (Y/N): NO E-mail (Y/N) : YES

    SWOT Analysis

    Strengths:

    Stakeholder group represents a great deal of knowledge and experience. The

    stakeholder will also provide details regarding their needs to help successfully plan

    the move and laboratory.

    Weakness

    es:Contact and consultation will be difficult.

    Opportuni

    ties:

    A laboratory and migration which accommodates their schedule and research

    needs.

    Threats: Failure to accomplish goals could lead to loss of research time and quality.

    Stakeholder Influence On Project:

    This stakeholder groups requirements must be met as they work for the project teams client Dr.

    Lipsett. Their needs will help to define the true project scope as well as every aspect of both the

    laboratory layout plan and migration plan.

    Notes: DNA represents does not apply, where information is limited, beyond the required scope and or deemed

    inconsequential.

    Stakeholder Expectations Management (Key Stakeholders only):

    The stakeholder group requires a plan that does not affect their research projects or education.

    Their equipment must be moved safely and securely during a research phase that allows for it to

    be moved.

  • 8/7/2019 Stakeholder register and analysis 1

    10/19

    Stakeholder Register/Analysis

    Stakeholder Name: Mechanical Engineering TechniciansKey Stakeholder

    (Y/N): NO

    Interests:The provide the team with an idea of what assistance and resources will be made

    available and can be used during both the planning and actual moving portions of this project.

    Stakeholder Communications Strategy:

    Communication Needs: Meeting Preferences:Communication

    Limitations:

    No communication is needed.

    Details regarding the schedule

    and plan will need to be

    communicated.

    In person during working hours

    at the University of Alberta.

    Stakeholder has a busy

    schedule limiting availability

    for meeting making efficiency

    a priority.

    Avenues For Communication:

    In Person Meeting (Y/N):

    YESTelephone (Y/N): NO E-mail (Y/N) : YES

    SWOT Analysis

    Strengths: Experience with similar laboratory relocation will allows for better planning.

    Notes: DNA represents does not apply, where information is limited, beyond the required scope and or deemed

    inconsequential.

    Detailed Interests/Priorities Analysis (Key Stakeholders only) :

    Key Stakeholder

    Interests:A smooth transition into the new laboratory

    Key StakeholderPriorities:

    A fictional ergonomic laboratory

    Principal Objective: Plan a functional laboratory and migration that meets the needs of the

    researchers

    Consequences Resulting From Missed Principal Objective: Loss of research time and

    potential losses in research due to experimentation alterations and or delays. Long term

    research inefficiency.

  • 8/7/2019 Stakeholder register and analysis 1

    11/19

    (DNA

    (DNA

    Stakeholder Register/Analysis

    Weakness

    es:

    Stakeholder group has a busy schedule and requires advanced notice to address

    questions/concerns.

    Opportuni

    ties:Stands to benefit from project primarily through the gaining experience.

    Threats: (DNA)

    Stakeholder Influence On Project:

    This stakeholder group will affect the scheduling of the project. They will, from a technical and

    equipment perspective, inform the project team of what can and cant be done with the

    resources available to them.

    Stakeholder Name: Dr. Glen Thomas Key Stakeholder

    Notes: DNA represents does not apply, where information is limited, beyond the required scope and or deemed

    inconsequential.

    Stakeholder Expectations Management (Key Stakeholders only):

    Detailed Interests/Priorities Analysis (Key Stakeholders only) :

    Key Stakeholder

    Interests:

    Key StakeholderPriorities:

    Principal Objective:

    Consequences Resulting From Missed Principal Objective

  • 8/7/2019 Stakeholder register and analysis 1

    12/19

    (DNA

    Stakeholder Register/Analysis

    (Y/N): NO

    Interests: Dr. Glen Thomas is interested in minimizing the impact of the laboratory and

    migration and the individuals that us the Mechanical Engineering building. He also interested in

    what is required from him so he can find time to assist the team in the planning process. Dr.

    Thomas would be interested in dealing with any discovered deficiencies with respect toinfrastructure to meet the needs of the researchers and professors.

    Stakeholder Communications Strategy:

    Communication Needs: Meeting Preferences:Communication

    Limitations:

    No communication is needed.

    Details regarding the schedule

    and plan will not to becommunicated.

    In person Thursdays during

    working hours at the

    University of Alberta.

    Stakeholder has a busy

    schedule limiting availability

    for meeting making efficiencya priority.

    Avenues For Communication:

    In Person Meeting (Y/N):

    YESTelephone (Y/N): YES E-mail (Y/N) : YES

    SWOT Analysis

    Strengths:Experience with similar laboratory relocation and with administration at the

    University of Alberta.

    Weakness

    es:Bust Schedule.

    Opportuni

    ties:(DNA)

    Threats: (DNA)

    Stakeholder Influence On Project:

    This stakeholder will have a minimal effect on the project provided that the rules and regulationsoutlined in the University Calendar are adhered to. He is willing to address any infrastructure

    deficiencies that the project team encounters to provide researchers with the best possible lab.

    Notes: DNA represents does not apply, where information is limited, beyond the required scope and or deemed

    inconsequential.

    Stakeholder Expectations Management (Key Stakeholders only):

  • 8/7/2019 Stakeholder register and analysis 1

    13/19

    (DNA

    Stakeholder Register/Analysis

    Stakeholder Name: Roger MarchandKey Stakeholder

    (Y/N): NO

    Interests: Roger Marchand interests include knowing well in advance specifics relating to the

    logistics and scheduling of the movement of the large mill. He expects the scheduling will not

    affect his ongoing commitments and activities.

    Stakeholder Communications Strategy:

    Communication Needs: Meeting Preferences:Communication

    Limitations:

    No communication is needed.

    Some Details regarding the

    schedule and be

    communicated.

    In person during working hours

    at the University of Alberta.

    Stakeholder has a busy

    schedule limiting availability

    for meeting making efficiency

    a priority.Avenues For Communication:

    In Person Meeting (Y/N):

    YESTelephone (Y/N): NO E-mail (Y/N) : YES

    SWOT Analysis

    Notes: DNA represents does not apply, where information is limited, beyond the required scope and or deemed

    inconsequential.

    Detailed Interests/Priorities Analysis (Key Stakeholders only) :

    Key Stakeholder

    Interests:

    Key Stakeholder

    Priorities:

    Principal Objective:

    Consequences Resulting From Missed Principal Objective

  • 8/7/2019 Stakeholder register and analysis 1

    14/19

    (DNA

    (DNA

    Stakeholder Register/Analysis

    Strengths:

    A great Deal of experience with similar laboratory relocation and with

    administration at the University of Alberta. Roger Marchand will also be able to

    provide attritional resources in the form of advice, personnel and equipment.

    Weakness

    es:Bust Schedule.

    Opportuni

    ties:(DNA)

    Threats: (DNA)

    Stakeholder Influence On Project:

    This stakeholder will not affect the scheduling of the project. The scope of the project may

    deviate somewhat based on the experience and recommendations of Roger Marchand. His

    advice will determine some specific details regarding the organization of the new laboratory.

    Notes: DNA represents does not apply, where information is limited, beyond the required scope and or deemed

    inconsequential.

    Stakeholder Expectations Management (Key Stakeholders only):

    Detailed Interests/Priorities Analysis (Key Stakeholders only) :Key Stakeholder

    Interests:

    Key Stakeholder

    Priorities:

    Principal Objective:

    Consequences Resulting From Missed Principal Objective

  • 8/7/2019 Stakeholder register and analysis 1

    15/19

    (DNA(DNA

    (DNA

    Stakeholder Register/Analysis

    Stakeholder Name: Professors Allocated Dr. Lipsetts OldLaboratory

    Key Stakeholder

    (Y/N): YES

    Interests:The professors which need Dr. Lipsetts old laboratory space are primarily concerned

    with scheduling. The space is to be provided according to the date agreed upon. The lab space is

    also to be usable; it should retain its entire infrastructure and be ready to move.

    Stakeholder Communications Strategy:

    Communication Needs: Meeting Preferences:Communication

    Limitations:

    No communication for the

    stakeholder has been

    requested.

    Avenues For Communication:Meeting (Y/N): NO Telephone (Y/N): NO E-mail (Y/N) : YES

    SWOT Analysis

    Strengths: (DNA)

    Weakness

    es:(DNA)

    Opportunities: Stands to benefit from project by being provided with a clean ready to use lab.

    Threats:Missing the relocation deadline could hinder other University research programs as

    well as the stakeholders

    Stakeholder Influence On Project:

    The stakeholder influence on the project is minimal. The only affect is the state the old

    laboratory must be left in as well as the delivery date of the old laboratory.

    Detailed Interests/Priorities Analysis (Key Stakeholders only) :

    Notes: DNA represents does not apply, where information is limited, beyond the required scope and or deemed

    inconsequential.

    Stakeholder Expectations Management (Key Stakeholders only):

  • 8/7/2019 Stakeholder register and analysis 1

    16/19

    (DNA (DNA

    Stakeholder Register/Analysis

    Key Stakeholder

    Interests:The old lab space is clean and has all preexisting infrastructure

    Key Stakeholder

    Priorities: Schedule adherence.

    Principal Objective: To relocate and setup a new laboratory according to the agreed upon

    schedule

    Consequences Resulting From Missed Principal Objective: Interruption to research, loss of

    research time, and possible experimentation damage.

    Stakeholder Name: Guests/Visitors To The MechanicalEngineering Building

    Key Stakeholder

    (Y/N): NO

    Interests:This stakeholder group represents future students and their families as well as

    potential investors and alumni. They are interested in viewing the building without being

    hindered by the move. Visitor safety is paramount and will not be comprimesed.

    Stakeholder Communications Strategy:

    Communication Needs: Meeting Preferences:Communication

    Limitations:

    No communication is needed.

    Details regarding the schedule

    and plan will not need to be

    communicated.

    Avenues For Communication:

    In Person Meeting (Y/N):

    YESTelephone (Y/N): NO E-mail (Y/N) : NO

    SWOT Analysis

    Strengths: (DNA)

    Notes: DNA represents does not apply, where information is limited, beyond the required scope and or deemed

    inconsequential.

  • 8/7/2019 Stakeholder register and analysis 1

    17/19

    (DNA

    (DNA

    Stakeholder Register/Analysis

    Weakness

    es:Stakeholder group may slowdown or interfere with migration.

    Opportuni

    ties:(DNA)

    Threats:The migration involves heavy equipment and Guests/Visitors present a liability

    when in the vicinity.

    Stakeholder Influence On Project:

    This stakeholder group will affect the scheduling of the project. I there is a major open night or

    alumni function the move will need to be conducted around those events.

    Stakeholder Name: Vendors and Suppliers Key Stakeholder

    Notes: DNA represents does not apply, where information is limited, beyond the required scope and or deemed

    inconsequential.

    Stakeholder Expectations Management (Key Stakeholders only):

    Detailed Interests/Priorities Analysis (Key Stakeholders only) :

    Key Stakeholder

    Interests:

    Key StakeholderPriorities:

    Principal Objective:

    Consequences Resulting From Missed Principal Objective

  • 8/7/2019 Stakeholder register and analysis 1

    18/19(DNA

    (DNA

    (DNA

    (DNA

    Stakeholder Register/Analysis

    (Y/N): NO

    Interests:This stakeholder group will be provide various materials and services and will need to

    be informed of the schedule well in at advance to provide them with organizational time.

    Stakeholder Communications Strategy:

    Communication Needs: Meeting Preferences:Communication

    Limitations:

    No communication is needed.

    Details regarding the schedule

    and plan will be

    communicated.

    Avenues For Communication:

    In Person Meeting (Y/N):

    NOTelephone (Y/N): YES E-mail (Y/N) : YES

    SWOT Analysis

    Strengths:They will be able to provide suggestions and estimates for certain aspects of the

    project.

    Weakness

    es:Associated cost may be outside of our working budget.

    Opportuni

    ties:To provide the mechanical engineering staff with future services

    Threats: Schedule threatens this stakeholder group, advanced notice is required by them.

    Stakeholder Influence On Project:

    This stakeholder group will affect the scheduling of the project. Some of the services and

    materials needed during the migration and lab setup may affect laboratory commissioning. The

    scope may also be affected as their services may provide many of the new labs requirements.

    Notes: DNA represents does not apply, where information is limited, beyond the required scope and or deemed

    inconsequential.

    Stakeholder Expectations Management (Key Stakeholders only):

  • 8/7/2019 Stakeholder register and analysis 1

    19/19

    Stakeholder Register/Analysis

    Notes: DNA represents does not apply, where information is limited, beyond the required scope and or deemed

    inconsequential

    Detailed Interests/Priorities Analysis (Key Stakeholders only) :

    Key Stakeholder

    Interests:

    Key StakeholderPriorities:

    Principal Objective:

    Consequences Resulting From Missed Principal Objective