STANDARD SPECIFICATION
FOR
SOIL IMPROVEMENT AND
LAND DEVELOPMENT FOR RAILWAY
SIDING FROM BRIDGE NO 1 TO BRIDGE NO 3
Hindustan Petroleum Corporation Ltd
Visakha Dispatch Station VR-ATP
Area, Naval Base Post
Visakhapatnam - 530 014 Andhra
Pradesh
Mott MacDonald
Mott MacDonald Consultants (India) Pvt. Ltd.
Kothari House, CTS No. 185 Off Andheri -
Kurla Road Andheri (East) Mumbai 400 059
STANDARD SPECIFICATION
FOR
SOIL IMPROVEMENT AND
LAND DEVELOPMENT FOR RAILWAY
SIDING
FROM BRIDGE NO 1 TO BRIDGE NO 3
Client HINDUSTAN PETROLEUM CORPORATION LTD.
MMCI Project No. 254624
Issue and Revision Record:
Rev Date Originator Checked Approv ed Description
A 12/9/2011 PSS VV VV Issued For Tender
B
C
Group Disclaimer
"This document has been prepared for the titled project or named part thereof and should not be relied upon or used for any other project without an independent check being carried out as to its suitability and prior written authority of Mott MacDonald being obtained. Mott MacDonald accepts no responsibility or liability for the consequences of this document being used for a purpose other than the purposes for which it was commissioned. Any person using or relying on the document for such other purpose agrees, and will by such use
or reliance be taken to confirm his agreement, to indemnify Mott MacDonald for all loss or damage resulting there from. Mott MacDonald accepts no responsibility or liability for this document to any party other than the person by whom it was commissioned.
CONTENTS OF TECHNICAL SPECIFICATIONS
No DESCRIPTION PAGES
1 SOIL STABILIZATION 5 - 15
2 EARTH WORK 16 - 23
1 Purpose
The purpose of this standard is to define specifications to be followed for Site Development including
Soil Improvement Works for Railway siding for the stretch from Bridge No.1 to Bridge No.3 using
Vacuum Consolidation (or Vacuum Pre-Loading ) method.
2 Scope
This specification covers the material and constructional requirements of Site Development including
Soil Improvement Works for Railway siding for the stretch from Bridge No.1 to Bridge No.3 using
Prefabricated Vertical Drains (PVD) with vacuum consolidation system.The extent of work shall be as
shown on drawings and as described herein. Supplementary requirements or modifications to this
specification shall be defined in the drawings or as per instructions of the HPCL/MMCI Engineer-in-
charge. The work shall be carried out as per design in a phased manner as directed by the HPCL/MMCI
Engineer-in-charge.
3 Applicable Codes (shown at relevant Sections)
4 Technical Requirements (shown at relevant Sections)
5 Use of Prefabricated Vertical Drains (PVD) with Vacuum
Consolidation/Pre- loading :
The basic design principle for the use of PVD is consolidation. In absence of PVD , the soil pore water
follows the flow path only in vertical direction i.e one-dimensional consolidation. However ,with the
use of PVD ,pore water in the clay sub-stratum flows horizontally (radially) as well as vertically i.e
three-dimensional consolidation. The consolidation process starts on application of Pre-load (the
expected load applied in advance) after the installation of band drains. Conventionally the preload is
applied by way of the temporary/permanent embankment over the treatment area . However , due to
the lack of the available time, a new method of pre-loading using vacuum loading is proposed.
The vacuum loading is the application of the external negative pressure to the soil surface, in the form
of vacuum. A higher effective stress is achieved by the negative pore pressure. Each PVD will be
connected to the vacuum channel using the tubing systems and drain connectors. The height of the
pre-load embankment used as surcharge shall not exceed the designed preload height. Piezometers
and Settlement Markers shall be installed to check the efficacy of the proposed system as per
requirements.
1 General
The work consists of ground improvement using prefabricated vertical drains (PVD) or band drains of
specified quality in conjunction with vacuum consolidation upto depths required to stabilize the
railway embankment from Bridge No.1 to Bridge No.3 which requires to be constructed over very soft
compressible clay. The work is to be carried out in marshy conditions some parts of which may be
water-logged. The clay subsoil is very weak and highly compressible and requires to be improved to
increase its shear strength as well as to minimize or eliminate post-construction settlement. The
CONTRACTOR is well advised to visit the site before making the offer.
The CONTRACTOR is required to include in his offer detailed proposal for such soil stabilization
including methodology, design and expected results to achieve satisfactory construction and
performance of the embankment in the long term. All necessary precautions necessary to avoid any
instability of the proposed embankment & also the existing works during the construction is essential
and should be included in the proposal to ensure safety at all times during construction.
The CONTRACTOR shall furnish all necessary design, labour, equipment, and materials and perform all
necessary operations for the installation of prefabricated vertical drains (PVD) or band drains in
accordance with the details shown in the drawings and with the requirements of these specifications.
The PVD or band drains as well as the accessories required for vacuum consolidation shall comply with
the minimum specifications stated herein. Contractor shall note that the design details such as spacing,
depth etc. of the band drain included herein are for reference only. The work shall be executed as per
the Contractor’s design which shall be approved in advance of execution by HPCL / MMCI.
Contractor with this offer shall submit documents of the past work of comparable magnitude executed
by him which shall include as minimum the following details such as type of band drains, depth of
installation, spacing, design settlement, achieved settlement, time period, purpose , height of
embankment and proposed vacuum consolidation system details.
2 Specification for PVD / Band Drains
2.1 General
PVD or Band Drains shall be of newly manufactured materials from an approved PVD shall be of
“TD3520F or Nylex Flodrain” grade manufactured materials from an approved manufacturer. The PVD
or band drain shall be prefabricated made up of polypropylene drainage core wrapped in a non-woven
filter fabric made of polypropylene or similar material. The core shall be fabricated with suitable
drainage channels which shall provide continuous vertical drainage and shall have the minimum
properties specified herein.
The filter jacket shall be capable of resisting all bending, puncturing and tensioning subjected to during
installation and design life of the drain. The jacket shall allow free of passage of pure water to the core
without loss of soil material or piping.
2.2 Jacket
The Jacket shall be a synthetic non woven geotextile capable of resisting all bending, punching &
tensile forces imposed during installation & shall be suitable to resist local damages such as punching
through the filter by sand / grave / partition. The material shall be sufficiently rigid to withstand lateral
earth pressure to embedment & surcharge so that verifical flow capacity through the core is not
adversely affected. The material shall be flexible to bend smoothly during installation & induced
consolidation settlement without damage. It shall also not under go cracking or peeling during
installation of the drain.
2.3 Core
The core shall be a continuous plastic material fabricated to promote drainage along the axis of vertical
the drain.
2.4 Assembled drain
The mechanical properties (strength & modulus) of the assembled PV Drain shall equal or exceed those
specified for the component of Jacket & core. The assembled drain shall be resistance against wet rot
mild der, bacterial drawing, action, insects, salts, acids, alkalis, solvers & along other significant
ingredients in the site ground water. One single type of assembled drain shall be used on the project
unless otherwise specified or approved by engineer.The contractor shall submit to HPCL/MMCI
manufacturer’s test result / certificates for the batch procured documenting that the physical &
mechanical of the drain satisfy the minimum requirements of this specification.
2.5 Qualities Requirements
The CONTRACTOR shall submit samples and specify source of the PVD material. Manufacturer’s
specification & typical test results and specifications as well as a letter of commitment from the
manufacturer for supply of the required quantity for the project in time shall accompany the offer. The
manufacturer shall have ISO 9001 certification for quality assurance in the manufacturing of the
product. The product should have proven record for good performance. The HPCL/MMCI Engineer-in-
charge shall approve the PVD material before it is allowed to be used in the project. All PVD Materials
shall be labelled and tagged for sample identification and other quality control requirement. Each roll
shall be identified by the manufacturer by lot number, individual roll number, date of manufacture,
name of manufacturer and product identification of jacket and core.
2.6 Preservation & protection of band drains during shipping & storage
During Transportation and storage:
The drain shall be wrapped in heavy paper, burlap or similar heavy duty protection covering. The drain
shall be protected from sunlight, mud, dirt, dust, debris and other detrimental substances.
All damaged materials during transportation, handling and storage and which do not meet Minimum
requirement as per specifications shall be rejected by the Engineer-in-charge and no certification for
payment shall be made for such materials.
Contractor shall submit the all manufacturers test certificates, DCs/Invoices etc for the review of
HPCL/MMCI at the time of supply of PVD rolls at site. Prior to installation and at the discretion of the
Engineer, an individual test sample of 3m length shall be cut from at least one roll selected at random to
represent each batch or every 50,000 meters whichever is less. These samples (PVD and filter jacket)
shall be subjected to tests as mentioned herein in an independent approved laboratory. The cost of
samples and tests shall be deemed to be included in rates for PVD quoted. In case of any individual
sample not satisfying the minimum specifications indicated herein, then the relevant roll shall be
rejected. As a precaution two additional samples shall be drawn from two other rolls representing
material for 50,000 m & shall be tested. If either of the two samples fails to comply with any provision of
the specification, then the entire quantity of vertical drain represented by the samples shall be rejected.
3 Technical Specification & codes for PVD
S.No Property Test Method Specification
A Composite Drain
1 Width 100 mm
2 Thickness ASTM D5199 4.1 mm
3 Mass per linear metre 90 g/m
4 Tensile strength 2.55 kN
5 Elongation at break 36%
6 Elongation at 0.5 kN
ASTM D4595
1.00%
7 95 x 10-6 m 3/s
8
Discharge capacity i = 1.0, 300 kPa pressure
(straight) i = 1.0, 350 kPa pressure 90 x 10-6 m3/s
9
10
Discharge capacity i = 1.0, 250 kPa pressure
(25% buckled)
ASTM D4716
85 x 10-6 m
3/s
B Core
1 Material Polyethylene /
Polypropylene
2 Configuration / structure Corrugated
3 Thickness ASTM D5199 3.5 mm
4 Tensile strength ASTM D638 1.25 kN
5 Elongation at break 20%
6 Compressive strength ASTM D1621 1200 kPa
C Filter
1 Material Polyester
2 Structure Nonwovwen
3 Mass per unit area ASTM D5261 120 g/m2
4 Tensile strength 530 N
5 Elongation at break
ASTM D4632
45%
6 Trapezoid tear strength ASTM D4533 150 N
7 Bursting strength ASTM D3786 1 N/mm2
8 Puncture strength ASTM D751 225N
9 Permeability 1.9 x 10-4 m/s
10 Permittivity
ASTM D4491
0.65 s-1
11 Apparent opening size ASTM D4751 80 µm
4 Vacuum Pumps and accessories
CeTeau Vacuum Consolidation system or equivalent recognized system such as Menard Vacuum
Consolidation system consisting of prefabricated band drains vertically installed from ground surface
into the soil mass to prescribed depth,a surface drainage system including a granular medium (sand
mat),horizontal drains and collector pipes leading to a vacuum pump system for transmission of vacuum
to the soil as well as discharging water and air out of the treated soil mass shall be proposed for
approval of HPCL/MMCI.
The proposed Vacuum Consolidation system shall create an accelerated isotropic consolidation in the
soil mass in a relatively short time, eliminating the need for long term and potentially unstable
surcharge loads. The applied vacuum pressure shall produce the same equivalent pressures as exerted
by a traditional preloading system of upto 3 to 5 m height of embankment fill.
5 Installation Equipment
The PVD shall be installed with approved modern hydraulic drain stitcher equipment, which will cause
minimum disturbance to the subsoil during the installation operation, capable of maintaining the
vertically the mandrel and stretcher should have the following properties/ facilities.
1. Capable to install depths up to 25mtr from existing ground.
2. The rig shall have the installation capacity of minimum 10,000 Rmt per day. For penetration
through stiff or difficult ground, the rigs shall have additional hydraulic cylinders.
3. The mandrel penetration rate shall be between 0.15 m to 0.6 m per sec. The mandrel shall protect
the drain material from tears, cuts and abrasions during installation and shall be withdrawn
smoothly after the drain is installed to the required depth.
4. The mandrel shall be rectangular in shape and the cross sectional area shall not exceed 80 Cm2.
The PVD shall be installed within a steel mandrel that will be advanced through the soil to the required
depth. Constant rate of advancement method is the preferred method for installation. The PVD shall
be installed continuously without jerks or stoppage until refusal is reached. Alternate raising &
lowering of the mandrel during driving shall not be permitted.
Use of impact hammers for installation is not allowed. Vibration shall not be used unless and otherwise
approved by the Engineer. The mandrel shall protect the drain material from tears, cuts and abrasions
during installation and shall be withdrawn smoothly after the drain is installed to the required depth.
The CONTRACTOR shall submit detailed method statement including the following with the offer:
a) Sequence and method of installation.
b) List & details of equipment which will be mobilized.
c) Proposed site organization, and
d) Work programme and quality plan
e) Overall schedule including committed delivery dates of PVD and geotextile at site.
Prior approval of all the above will be required before commencement of PVD installation. Approval of the
HPCL/MMCI Engineer-in-charge will not relieve the CONTRACTOR of his responsibility to install the PVD in
accordance with the specifications.For the proposed Vacuum loading, the PVD for each location shall be
prepared before the installation proceeds. The PVD shall be cut to the predetermined length considering
the subsoil stratification. The drain shall be assembled by attaching the drain collector at the top of PVD.
Prior to PVD installation within the designated area, the CONTRACTOR shall demonstrate that his
equipment, method and materials produce satisfactory installation in accordance with these specifications.
For this purpose, the CONTRACTOR will be required to install trial drains at locations designated by the
HPCL/MMCI Engineer-in-charge. There shall be no payment for unsatisfactorily installed drains. The spacing
and depth of PVD shall be as per the approved design and as instructed by the Engineer-in-charge.
The CONTRACTOR shall submit proper PVD installation plans showing the location of each PVD to be
installed at least one week prior to commencement of works. Installation work can commence only after
approval is given for the installation plans submitted. Before physical installation, the Contractor shall
locate, number & stake out on ground the installation plan & from the benchmark provided by
HPCL/MMCI. The installed PV Drains shall not deviate more than 150mm from the position indicated in
plans. PV Drains installed beyond the tolerance & also those which are damaged or otherwise improperly
installed shall be rejected & abandoned in place. The stitcher shall be marched to the exact band drain
location and erected vertically. The base machine shall be activated and the mandrel shall be pushed into
the soil,till the top of connector is about 0.50 m below the working level,the mandrel will be pulled back
immediately leaving the band drain inside the soil.
The stitcher shall then be moved to the next location and the cycle shall be repeated. Rolls of band drain
material shall be sealed together by sliding the drain ends into each other and affixing them by stapling.
This will make the process of installation continuous
PVD shall be installed from the working platform to the required depth or where significant resistance
to penetration is encountered or as directed by the HPCL/MMCI Engineer-in-charge. The HPCL/MMCI
Engineer-in-charge may vary the spacing, depth or number of installations as required for the project.
The installation equipment shall be checked for verticality prior to PVD installation. The deviation shall
not exceed 1 in 50 from the vertical at places except installation at mid portion of TW gantry.
The details of PVD installation at each location shall be recorded in proper daily installation record
sheets and submitted to HPCL/MMCI Engineer-in-charge. The details recorded shall include depth, grid
location of installed PVD, start/end time for each shift, equipment breakdown period if any, total
numbers and depth installed in the day or shift, name of recorder and supervisor, weather condition
etc. The format of daily record sheets shall be submitted for prior approval before commencement of
PVD installation at site.
Splices or connections in the PVD material shall be carried out in approved manner to ensure structural
& hydraulic continuity of the PVD material to the satisfaction of the HPCL/MMCI Engineer-in-charge. At
the splice upper portion of the jacket shall be external to the lower portion. A maximum of one splice
per drain shall be permitted unless specific permission from the MMCI/HPCL Engineer. The jacket and
core shall be overlapped at min 500 mm at any splice & stapled in position.
There shall be at least 300mm of PVD material protruding above ground level at each PVD location.
The PVD shall be cut neatly at the upper end. If any deep sub-surface obstructions are encountered
and penetration below is not possible, the HPCL/MMCI Engineer-in-charge should be notified of the
same and where necessary a compensating PVD should be installed beside such a location as
instructed by the HPCL/MMCI Engineer-in-charge. The installation shall be performed without any
damage to the drain during advancement or retraction of mandrel. Alternate raising or loweing of the
mandrel or jerking during advancement shall not be permitted. Raising of the mandrel shall only be
permitted after completion of drain installation.
PVD not complying with the installation procedure detailed above shall be rejected. Replacement of
PVD at both sides of rejected point shall be installed by the contractor at no extra cost. The contractor
shall be responsible for penetrating any overlying materials as necessary to install the drains. The
contractor may use auguring, spudding or other approved methods to loosen the soil and other
approved materials prior to the installation of PVD with the approval of MMCI/HPCL.
CONTRACTOR shall take all necessary precautions to protect soil instrumentation already installed. Any
damage to instruments due to PVD installation shall be the CONTRACTOR’s responsibility and he shall
reinstall such instruments at own cost to the satisfaction of the HPCL/MMCI Engineer-in-charge.
Full time supervision is important and necessary to prevent problems at site. The various methods of
recording the penetration length
1. Scale on the mast.
2. Dial gauge (which needs calibration).
3. Automatic digital counter.
Contractor to mark the center line of track and establish reference points at a distance of 30 mt on both
sides of center line and 25 mts along the alignment as per the approved drawings. Those reference points
should be constructed with brick pillers at every 25 mts along the alignment and chainages shall be marked
with paint.
Toe distance for the PVD installation shall be marked with lime powder at every 25 mt chainage points. The
existing bed surface shall be recorded with auto level along with MMCI/HPCL representatives at every 5 mt
interval longitudinally and 2.5 mt cross sectionally.
Original ground level for part length of the proposed alignment is higher than the proposed formation
level. In such case existing soil shall be excavetd up to required depth to start PVD installation. This activity
shall certify related SOQ items. Ground level for the balance part of the alignment is lower than the
proposed formation level. In this case contractor may install PVDs directly on the ground level or if the
existing ground level is not feasible /approachable for movement of PVD rig, the same is to be prepared by
the contractor by filling suitable excavated earth or moorum after removal of slush if required below the
original ground level for which no separate payment will be done. Payment shall be made for moorum
material from original ground level to top level of prepared moorum surface for movement of PVD rig.
6 Method of Measurement
The installed length of PVD shall be measured in linear meters upto the full depth of installation of
each PVD as recorded in daily installation records and verified by the Engineer. Lengths of overlap of
one roll with another and folding length provided for anchoring purpose are not payable. Contractor
should provide 500 mm minimum overlap & stippled and minimum 150 mm folding length for
anchoring purpose at the mouth of the mandrill without any extra cost. The same is not accountable.
7 Soil Instrumentation
Platform Settlement Gauges and Open Standpipe Piezometers are required to be installed to
monitor ground settlement and dissipation of pore pressure during the ground improvement
works. They need to be installed at designated locations and depths as required by the
HPCL/MMCI Engineer-in-charge. The Piezometers shall be installed in suitable boreholes and
shall be protected with protective pipes.
The instrument data shall be recorded at required time intervals and reports shall be submitted
regularly to the HPCL/MMCI Engineer-in-charge together with suitable plots and analysis of
the data. Details of the instruments the CONTRACTOR propose to install and methodology for
installation and monitoring shall be submitted for approval by the HPCL/MMCI Engineer-in-
charge.
8 Soil Investigation
A confirmatory soil investigation including boreholes, undisturbed soil sampling, in-situ tests such as
SPT and field vane shear tests and laboratory tests on the collected soil samples will be required after
the completion of the ground improvement work to assess the improvement in soil shear strength and
bearing capacity as a result of the ground improvement works. The CONTRACTOR will be required to
submit a programme for conducting the soil investigation and submission of report for the approval of
the HPCL/MMCI Engineer-in-charge.
9 Documents to be submitted with offer
a) Detailed design, details of proposed Vacuum Consolidation methodology, proposed spacing
and depth of PVD, etc for soil consolidation and embankment construction including
programme chart for the project.
b) Details of soil instrumentation and soil investigation & testing work proposed by the CONTRACTOR.
c) Proposal for Soil Investigation & Laboratory testing Work as per clause No. 8 above with approx.
No. of bore holes and Laboratory test proposed along with unit rates. The quoted LS price for
respective work as per the item No mentioned in relevant SOQ shall be based on this quantities &
unit rates.
d) Track record, list of projects completed, certificates of completion and records to prove eligibility
criteria of the SPECIALIST CONTRACTOR.
e) Specification, test reports, ISO certification and track record of PVD manufacturer including letter
of commitment from him for PVD supply for the project.
f) List of plant and equipment the CONTRACTOR will mobilize for the project and method statement
for PVD installation.
g) List of site personnel for the project and CV of key personnel.
10 Crushed stone material for Drainage Blanket and preloading
Crushed stone material shall be used for drainage blanket of compacted layer thickness of at least
300mm laid over the installed PVD within the area of ground improvement and compacted to achieve
the relative density above 70 %. Prior to laying drainage blanket, all the clay residues deposited during
the PVD work should be removed.
Contractor shall carried out all quality tests from the identified source and submit for the test reports
to MMCI/HPCL for source approval prior to its use in the works. Sand/crushed stone material should
have the following quality requirements.
a) Permiablity - Should not be less than 10 -4
m/ sec - Test frequency is every 2000 Cum
b) Gradation - test frequency – 250 Cum
Seive No Percent passing
10 mm 80-100
4.75 mm 75-90
2 mm 15-60
0.075 mm Less than 15% for crushed stone material
The Drainage blanket shall be spread evenly over the area and quantity of crushed stone materail for
payment purpose shall be based on actual measurements at site based on spot levels before and after
laying of crushed stone material.
Contractor should submit necessary royalty slips to HPCL/MMCI in every week or along with RA Bills.
11 Geotextile Reinforcement
After laying the crushed stone drainage blanket a Woven Geotextile Reinforcement is installed over the
crushed stone material. The Geotextile acts as reinforcement as well as a separator between the sand/
crushed stone material blanket and the embankment fill above. The Geotextile shall be laid with the
warp (machine direction) perpendicular to the alignment of the embankment. The Geotextile panels
shall be placed with adequate laps or sewn together at the overlaps between panels. Laying may be
permitted with required lapping as per the guidelines of manufacturer. In such case no extra payment
shall be paid for the lapping. Contractor should fallow strictly the manufacturers guidelines regarding
exposed to sunlight. Overlaps in no case shall be less than 300 mm.
Details and specification of woven Geotextile proposed, samples and test reports shall be submitted to
the HPCL/MMCI Engineer-in-charge for approval.
12 The main contractor has to take the assistance / guidance from the specialist subcontractor who has
sufficient experience in soil improvement work using vertical band drains. The recommended soil improvement
subcontractor for the above shall be any of the following agencies:
1. Bharat Geosystems Private Limted,
8/2, Malaviya Avenue, Thrruvanmiyur,
Chennai – 600 041, India.
Phone no. 044-24523522
2. Z-Tech (India) Pvt. Ltd.
‘D’ Wing No. 446.Vashi Plaza Sector 17,
Vashi.Navi Mumbai. Phone No. 022-
27548302
4. M/s Sohams Foundation Engg. Pvt. Ltd.
E-6, Shraddhamata Society,.
Opp. IIT Main Gate. Powai, Mumbai - 400076 Phone
No. 022-27574038/27565562 Website:
www.sohams.com
In case the main contractor wishes to execute the soil improvement work using vertical band drains by
the alternate subcontractor other than any of the four agencies mentioned above, then the tenderer
shall submit the details of such proposed alternate subcontractor(s) with their PQ documents ( i.e.
their profile, experience in PVD, turnover etc) along with the tender and contractor shall get approval
of such alternate subcontractor from MMCI/HPCL before subcontracting. The specialised
subcontractor proposed by main contractor shall comply with the technical specification of soil
improvement using vertical band brain as per clause No. 2.0.
1.0 EARTHWORK
1.1 Specifications
1.1.1 The moorum should cover the entire width of the formation from shoulder to shoulder, materials on both
edges.
1.1.2 The moorum shall have following properties:
(a) The liquid limit shall not exceed 35 and Plasticity Index shall be below 15.
(b) Uniformity co-efficient d60 should be above 4 and preferably above 7.
d10
2
(c) Co-efficient of curvature d30 should be between 1 & 3.
d60 x d10
Note: d60 is sieve size through which 60% of blanket material passes and d10 is the sieve size through
which 10% of the blanket material passes and 80 so on. The enveloping curve for the Blanketing
Material recommended by RDSO is shown in the Diagram at Annexure B of Guideline no. GE-G-1
of RDSO for Earthwork in Railway Project.
1.1.3 In case of mechanically produced blanket material, RDSO Guide lines (GE: C-2) shall be followed.
1.2 Applicable codes
The following IS codes shall be followed for classification of soils, and for conducting various tests on soils
where required.
i) IS-2720 Part-II 1973 Method of tests for soil determination of water contents (II Edition)
ii) IS-2720 Part-IV 1975
Method of test for soil grain size analysis
iii) IS-2720 Part-V 1974
Determination of liquid and plastic limit.
iv) IS-2720 Part-VIII 1983 Determination of moisture contents dry density using heavy
compaction.
v) IS-2720 Part-XIV 1985 Determination of density index (relative density) of cohesion less
soil.
vi) IS-2720 Part-XVIII 1964 (reprint in Jan. 1980) Method of test for soil determination of field
moisture equivalent.
vii) IS-2720 Part-XXIX Determination of dry density of soil in place by Core cutter methods.
viii) IS-1798-1970 Classification and identification of soils for General Engineering purpose.
1.2.1 Source of soil for embankments
No borrow pits shall be allowed with in right of way. The Characteristics of soils to be used and prohibited
are:
a) Soil having following characteristics should be used:
• Soils with fine particles (i.e. particles finer than 75 microns) not more than 50%
• Soil with liquid limits less than 35% and plasticity index less than 15%
• Soils having uniformity co-efficient preferably above 7.
The earthwork in filling will be done with CONTRACTOR's own moorum as per approved profile by
borrowing the earth from outside the HPCL premises and the rate quoted will be deemed to be inclusive
of all taxes, royalty, loading, unloading, leading, handling and re-handling of earth, lifts, ascents,
descents, crossing of nallahs, streams, tracks, levelling, dressing spreading in layers as a complete work in
all respects as per specifications indicated in succeeding paras.
1.2.2 Embankment
Before taking up embankment work :
i) All vegetation shall be uprooted and taken away from the site of work.
ii) All big size of boulders and other items not related to the work should be removed.
iii) Moorum filling shall be carried out in layers, each layer (300 mm thick) sloping out 1:40 and
compacting it with vibro rollers (8 to 10 ton capacity) at optimum moisture content to the specified
percentage compaction.
iv) The width of each layer of earthwork in moorum shall be in excess by 500 mm on either side of the
designed profile to enable compaction near the edges. The excess width, thereafter, cut and
dressed, so as to achieve the required bank profile.
v) Earthwork with moorum shall be completed up to designed formation level.
1.3 The earth filling with moorum shall be compacted mechanically using heavy roller (8 to 10 ton capacity)
to 95% MDD at OMC, layer by layer as per specification. Compaction of earth filling to be paid (included)
under respective items.
1.4 The moorum has to conform to specifications as mentioned under cluse 1. HPCL/MMCI Engineer-in-
charge may ask the CONTRACTOR/s to get the moorum samples tested as per specifications. It may
please be noted that under no circumstances, the CONTRACTORs will be allowed to form the bank with
unapproved moorum. Such tests may be repeated by the HPCL/MMCI Engineer-in-charge, during the
execution of the work. If the moorum samples are found not conforming to the required specifications
the CONTRACTORs may have to bring moorum from other approved sources. The cost of all tests will
have to be borne by the CONTRACTOR/s.
1.5 The CONTRACTOR/s shall, set out and provide all stakes, ballies, bamboo, strings, pegs and labour for
setting out profiles, of embankment required for the correct execution of the work and shall also be
responsible to maintain the same in proper order. This is deemed to be included in the item rate for the
earthwork with moorum. The CONTRACTOR/s shall take necessary precautions to prevent their being
removed, altered and disturbed and shall be responsible for the consequences of such removal,
alterations and disturbance and will take action for their proper re-instatement.
1.6 Before the earth filling with moorum is started by the CONTRACTOR, the ground between the lines
where filling is to be done for embankments at site of work shall be cleared of all trees along with their
roots, shrubs, heavy grass and undergrowth of every kind. None of the items of work mentioned in this
Para will entitle the CONTRACTOR/s to any extra payment except cutting of trees (girth size 100 mm or
above at 1 mt above the ground) which shall be paid separately as per relevant item of schedule. All
trees so removed by the CONTRACTOR will be the property of HPCL. No trees falling outside the Toe of
the bank shall be allowed to be cut. All trees having girth above 30cm (measured at 1m above GL) shall
be cut of trunks and branches. Digging and removing of roots up to a depth of 1m below the ground,
filling the same cavity with good earth, transporting the tree duly cut into standard log size to store shall
be ensured by the CONTRACTOR at its own cost.
1.6.1 The CONTRACTOR/s should commence the work systematically at one or more points in consultation
with the HPCL/MMCI Engineer-in-charge and should maintain continuous and steady progress to
complete the work in continuous lengths including leveling and dressing in order to complete further job
within the time schedule.
1.6.2 Contractor shall deploy one surveyor in full time with total station and Auto level equipments. Contractor
shall arrange for the recording joint levels along with MMCI/HPCL representatives in each stage at an
intervals as specified below.
a) For initial bed level/ top level of drainage layer – At every 5 mtr interval longitudinal and 2.5 mtr cross
sectional.
b) In case of excavation from NGL, formation level after excavation shall be recorded at an intervals as
specified under (a) above.
c) For running layers during execution – At every 10 mtr interval in both longitudinal and cross sectional.
d) For Fianl Layer – At every 5 mtr interval longitudinal and 2.5 mtr cross section.
Work shall not start without taking joint recording of the initial levels of ground as detailed under (a) &
(b) above.
Joint levels shall also be witnessed in addition to the HPCL/MMCI for stretches where part of the work is
carried out by other agency earlier. HPCL/MMCI will initiate to arrange for the representative of the
earlier agency for witnessing the levels.
1.7 The payment shall be made as per designed cross section only. No extra payment shall be paid for
settlement what so ever during construction.
1.7.1 It must be clearly understood that the rates are intended to cover the full cost of the finished works. The
banks and cutting are to be correctly dressed to profile before settlement is deemed to be included in
the unit rate coated by the vendor for moorum filling item. Removal of excess earth from bed, slopes
and filling the same with balance formation up to required level after settlement period are shall be
measured as per the relevant item numbers as per SOQ.
1.7.2 The rates also include maintenance of the banks to correct profile including repairs of all rain cuts,
making good earth work with moorum due to base settlement natural or otherwise due to rains etc. until
the final measurements have been recorded and banks taken over by the HPCL/MMCI Engineer-in-
charge. The item rates of Schedule of rates and quantities will cover the full cost of finished work of
cuttings and embankments.
1.8 For the earthwork with moorum in embankment the toes of the slopes of bank (with 500mm extra width
in on either side) on both sides of the centre line and also lines parallel to and 60 cm outside the toes of
slopes of banks should be demarcated by the CONTRACTOR with a deep borrow at least 15 cm deep.
This is to be considered as a part of setting out the work and preliminary to his being allowed to break
ground. This lock spitting is to be executed, maintained and renewed by him without any payment when
necessary or/and when ordered by HPCL/MMCI Engineer-in-charge.
1.8.1 Centre line/Reference pillars in masonry shall be provided by the CONTRACTOR in banks at suitable
height the same should however, be made in stages as the work progresses. Pillars shall be provided at
every 50 to 100 m or as directed by the HPCL/MMCI Engineer-in-charge. The centre line / reference
pillars shall not be paid for separately and deemed to be included in the item rates.
1.8.2 The item rate quoted by the CONTRACTOR shall include the provision of benching in the side long ground
or side slopes in the existing bank where the earthwork joins old embankments. This aspect should be
taken into consideration while quoting the rates.
1.8.3 The breaking of all clods shall be strictly insisted upon for all earthworks with moorum in embankment
and the CONTRACTORs must take special care to ensure this.
1.9 Extra bank width of 500 mm on either side shall be rolled to ensure proper compaction at the edges. The
extra soil would be cut and dressed to avoid any loose earth at the slopes.
1.9.1 The top of the formation shall be finished to a slope of 1 in 40 as per approved profile as per guide line for
“Earthwork in Railway project, “ Guide Line no. GE: G-1 July 2003”.
1.10 SPECIFICATION FOR MECHANICAL COMPACTION OF EARTHWORK
1.10.1 After site clearance all pockets and depression left in the soil, if any, shall be made good and compacted.
1.10.2 Earthwork shall be done in layers not exceeding 300 mm thick after compaction.
i. Earthwork shall be compacted with suitable vibro rollers to obtain the density specified as per IS
10379-1982 and RDSO's guidelines for “Earthwork in Railway Project GC: G-1, July 2003” with up
to date amendments.
ii. If dry density as found out from the random samples works out to less than 95% of the maximum
dry density at optimum moisture content further rolling shall have to be done by the
CONTRACTOR till such time the required density is obtained as confirmed from subsequent tests.
iii. Each layer shall be compacted to the specified density over its entire width commencing from the
two sides, before another layer is started.
iv. While compacting, it shall be ensured that there is a minimum overlap of 150 mm between each
run of the rollers.
v. Care should be taken during the compaction operation to slope the surface of the bank to
facilitate the shedding and to minimize the absorption of rain water, particular attention being
given to the prevention of ponding.
vi. The density of each layer of compacted moorum layer shall be ascertained by the HPCL/MMCI
Engineer-in-charge by conducting FDD test as per IS 2720 at frequency of 1test per every 500 Sqm.
Contractor shall provide necessary FDD testing equipments with manpower during testing.
vii. The CONTRACTOR shall be allowed to lay a further layer of soil only after the compaction of
particular layer has been found satisfactory.
viii Where the moisture content of the earth in any layer is above OMC, it shall be left for drying for a
suitable period to bring down moisture content very near to OMC before rolling is commenced. If
the soil is dry, water shall be sprinkled either in the borrow pit or even on the spread layer, as
convenient in order to obtain a moisture content near to OMC before rolling is commenced. The
CONTRACTOR shall make his own arrangement of water and nothing extra will be paid for water
used. To control moisture at which soil is compacted and to find out the dry density of the soil the
moisture content of the soil in borrow pits and in the embankment after compaction will be
determined.
ix. The optimum moisture content and the maximum dry density of the soil shall be determined by
Standard proctor compaction test as per IS-2720 (Pt. VIII) 1983 followed by field trial as per IS-
10379-1982. This test shall be conducted for the soil taken in the borrow pits at at every 100 mts
and whenever there is a change in the nature of soil met with.
x. The site tests data and results shall be maintained in a Register as per the following Proforma:
1) Serial No.
2) Location
3) Layer No.
4) Laboratory Test results.
5) a) Maximum dry density in gm / CC or relative Density (%)
b) Optimum moisture content expressed as percentage of the dry weight of the soil
6) Field Test Results:
a) Dry density in Grams, CC or Relative Density (%) Field moisture content expressed as the
percentage of the dry weight of the soil.
7) Degree of compaction expressed as percentage of the density
8) Remarks.
1.11 The payment for the quantity of earthwork will be made on cross sectional measurement. The existing
ground/bank profile will be taken and plotted by the contractor and approved by the HPCL/MMCI
Representative before commencement of the work. The profile of the bank
required to be provided will also be plotted on the same sheets. The levels and cross Sections shall be
signed by both the HPCL/MMCI Engineer-in-charge and the CONTRACTOR/s or his/their authorized
agent. The profiles of the bank as required to be provided are for the guidance of the CONTRACTOR
to establish the toe distances of each layer during execution.
1.12 The profiles of the finished and completed bank first with extra width and subsequently after dressing will
like wise be taken in the presence of the CONTRACTOR or his/their authorized agent and superimposed on
the original ground profile. The CONTRACTOR shall be allowed to dress the bank to form finished profile
only after the bank with wider width duly compact has been checked to the satisfaction of the Engineer.
The gross value of earth work in filling will be calculated from the original and finally finished profile for
the purpose of payment.
1.13. Final measurements will be taken only after the bank has been completed to the required profile
irrespective of the prolongation of period of completion and number of monsoon that may pass during
execution.