stark county engineer’s office annual report
TRANSCRIPT
Stark County Engineer’s Office
Gas Tax Increase Passed
License Plate Fee $8,141,857
Permissive Fee $4,015,621
Gasoline Fee $2,939,200
Reimbursements $768,935
Misc. $358,398
Total $16,223,741
Capital Outlay $5,989,766
Supplies & Materials $2,102,229
Payroll $4,396,800
Employee Benefits $1,737,711
Contract Services $1,962,605
Total $16,189,111
Revenue Expenditures
Stark County Engineer’s Office 5165 Southway Street SW
Canton, OH 44706
Phone: 330-477-6781
Twitter @StarkCoEngineer
Office Financials for 2019
Noteworthy items completed in 2019 were:
The completion of a 300 ton Tension Fabric Mixing shed at Ridge Outpost. (Pictured below)
Melway Paving chip and sealed a potion of our main garage parking that included the main drive, front parking lot and west entrance at a cost of $23,237.
Ralph Byrd Construction upgraded our spill buckets to meet new State of Ohio UST require-ments. The cost of the project totaled $10,415.
Upgraded Airport Outpost lights for just under $3,000 using a grant from AEP.
WAB Global upgraded our main garage back yard pole lights for $1,400.
My staff repaired collapsed walls at the salt shed at Hartville Outpost.
Facility Upgrades
The cost to maintain roads keeps going up, but the reve-nue stream isn’t. That has been one of the main points used in the fight to raise the tax on fuel in Ohio. In April of this year, Governor Mike DeWine and the Ohio Gen-eral Assembly came to an agreement to raise the tax on gas from 28 cents to 38.5 cents per gallon. They also will raise the tax on other fuels, including diesel, from 28 cents to 47 cents. The increase in gas tax revenue is esti-mated to be $865 million. Under the new law, 45 percent of that will go to local governments. The Stark County Engineer’s Office is estimated to re-ceive an additional $1.5 million. With the additional funds, our estimated total gas tax revenue will be $3.97 million, a 63 percent increase. The extra funding will provide our office the opportunity to improve more county roads in various ways. “We’re going to try to do a little more of everything,” Dave Tor-rence said. “We are going to do more bridges. We will try to do more paving. We can replace more guardrail and signals. This gives us the possibility to upgrade equip-ment sooner.”
Stark County
Engineer’s Office
Annual Report
If You Build It, They Will Come It’s one of the busiest intersections in Stark
County: and it’s only getting busier.
In 2018, the north leg of Whipple Avenue
and the portion of Everhard Road east of
the railroad tracks were the main focus. In
2019, every other item on the to-do list
needed completed. Wenger Excavating put
their men to work on completing the nearly
$7,900,000 project. Additional turn lanes,
extensions of a two way left turn lane on
two sections of the project, replacement of
two bridge structures, upgrading signals,
adding curb and gutter, sidewalks and new
signage was what loomed ahead.
The removal of an old metal culvert and the
replacement of a new 3 sided concrete box
culvert required a nearly 3 month closure of
Everhard Road. Maneuvering the giant sec-
tions of the 30 feet by 9 feet structure into
place was no easy tasks. Imagine playing
the game Operation in reverse. You pick up
the spare ribs with the tweezers, gently try-
ing to guide it into the slot without touching
the sidewalls. Now imagine the tweezers
being a massive crane. The spare ribs turn
into 26 sections of the culvert each weigh-
ing thousands of pounds, and the sidewalls
embedded with gas and water lines along
with fiber optic cables. That was the
“game” Wenger’s contracted Ruhlin Compa-
ny to perform.
With the project now completed, motorists
and pedestrians should find it easier and
safer to make it to their destination, which
was always the goal from the beginning.
Above: The Everhard/ Whipple intersec-tion looking south Left: A section of the 3 sided box culvert that was placed under Everhard Road.
Paving the Way Into the H1-H5 (2019) Resurfacing Contracts plus a completion of Asphalt paving contract let in 2018: Approxi-
mately 58.5 miles of County Highway were resurfaced using hot mix, cold mix/recycling, chip seal and
microsurfacing, at a combined bid price of over $ 4,365,000. Funding for this work was provided partial-
ly by the $10 permissive License Tag Fee enacted in 2007. Funding was also obtained from the Ohio
Public Works Commission (OPWC), the Village of East Sparta, the City of Canton and the City of Alliance.
The work was performed by Melway Paving Company, Superior Paving and Materials Inc, Central Allied
Enterprises Inc., Northstar Asphalt Inc. and Strawser Inc. and included the following County Highways:
• Hot Mix Asphalt Resurfacing (H1-2019) – 3.5 miles, $671,129.71
Routes included are Shepler Church Ave., Sherman Church Ave., Dueber Ave. and Harrison Ave.
• Chip and Seal Resurfacing (H2-2019) – Approximately 29 miles, $793,591.26
Includes sections of Alabama Ave., Lynnhaven Ave., Blough Ave., Ridge Ave., Trump Ave., Indian Run
Ave., Orchard View Ave., Robertsville Ave., Reeder Ave., McCallum Ave., Waynesburg Dr., Duquette Ave.
and Marlboro Ave.
• Cold Mix Resurfacing/Recycling (H3) – 3.4 miles, $418,225.02
Mt. Eaton St. in Sugarcreek Township and Willowdale Ave. in Sandy Township
• Hot Mix Resurfacing (H4) – Approximately 12 miles, $1,697,520
Routes include Orrville St., Beech St., Sherrick Drive., Middlebranch Ave., Perry Dr., Dueber Ave., Portage
St., and Easton St.
• Countywide Microsurfacing (H5 – 2019) – 8 miles, $431,815.38
This project is a microsurfacing of various County Highways in Stark County. Routes include Shepler
Church Ave., Southway St., Georgetown St., Orchardview St., Portage St. and Whipple Ave.
• H4-2018 Hot Mix asphalt (Continuation) – Approximately 2.5 miles, $353,000
This project is a resurfacing and repair of Harmont Ave. and Columbus Rd. with hot mix asphalt.
Other 2019 Projects
Along with the paving program, another large individual paving project took place on Whipple Avenue (pictured
below, middle). This project consisted of resurfacing and repairing 4 miles of roadway from SR 172 to Belden
Village Avenue. Along with paving, the project included 6 signal upgrades, as well as replacements of various
sections of curb and gutter, and sidewalk. The total cost for this project was $2,190,548 and was performed by
Central Allied Enterprises.
2019 also involved upgrades to various bridge structures throughout the county. With 329 bridges under our
wing, our bridge inspection report helps us determine areas of concern. This year’s bridge report showed us that
90% of our bridges have a rating of 5 or better on a 1-9 scale.
The Chart below shows bridge projects completed in 2019:
Bridge No. Roadway Type Contractor Cost Outside Funding
OS-23-18 Weimer Dr. New box beam bridge Black Horse Bridge $ 600,000 $ 600,000 (Fed, OPWC)
PL-19-13 Everhard Rd. Precast Conc. Culvert Wenger Excavating $ 1,125,500 $1,125,500 (Fed, OPWC)
OS-22-26 Lotz Ave. 4-sided Conc. Box SCE $ 144,600
SU-10-27 Kings Highway 4-sided Conc. Box SCE $ 154,700
OS-14-51 Cindell St. 4-sided Conc. Box SCE $ 67,400
Miscellaneous Projects
Various Guardrail repairs & installations SCE $ 42,800
Bridge Structural Repairs SCE $ 25,200
Logjams and Vegetation Removal SCE $ 5,300
Erosion Repairs, Stream work SCE $ 17,400
Total Work completed by Stark County Bridge Crews: $ 457,400
Above: Lotz Avenue Bridge Above: Perry Drive Culvert