state of tennessee. presented by bob oglesby, aia, leed ap state architect office of the state...

89
State of Tennessee State of Tennessee

Upload: augusta-townsend

Post on 24-Dec-2015

223 views

Category:

Documents


4 download

TRANSCRIPT

Page 1: State of Tennessee. presented by Bob Oglesby, AIA, LEED AP State Architect Office of the State Architect (OSA)  State of

State of TennesseeState of Tennessee

Page 2: State of Tennessee. presented by Bob Oglesby, AIA, LEED AP State Architect Office of the State Architect (OSA)  State of

presented by

Bob Oglesby, AIA, LEED APState Architect

Office of the State Architect (OSA)http://www.tn.gov/finance/OSA/

State of TennesseeOffice of the State Architect’s

Building Information Modeling (BIM)Requirements (BIMr)

April 30, 2013

Office of the State Architect

Page 3: State of Tennessee. presented by Bob Oglesby, AIA, LEED AP State Architect Office of the State Architect (OSA)  State of

Office of the State Architect

Role of the State Architect

•Provide operational and technical staff support to the State Building Commission (SBC) which approves funding for all projects associated with improvements to real property

•Responsible for recommending, then developing and implementing SBC supported initiatives, programs and policies like Building Information Modeling (BIM)

•Facilitated through the three State Procurement Agencies (SPAs) – DGS’s STREAM, TBR and UT

Page 4: State of Tennessee. presented by Bob Oglesby, AIA, LEED AP State Architect Office of the State Architect (OSA)  State of

The SBC is interested in: •Considering any items which may achieve a higher and better use of taxpayer dollars spent on improvements to real property

•Items which create Greater Owner Value

• And

•Will lower the State’s Total Cost of Ownership through

• more efficient and effective design, construction and operational processes

• the realization of higher performing buildings throughout their entire life cycle

•BIM will help the State achieve this!

• And

•Improve the productivity of those providing services and products in the Design and Construction industry as well as Operations and Maintenance

Office of the State Architect

Page 5: State of Tennessee. presented by Bob Oglesby, AIA, LEED AP State Architect Office of the State Architect (OSA)  State of

Office of the State Architect

Widely Acknowledged Problems

• 30% of projects do not make schedule or budget

- Construction Management Association of America (CMAA) Industry Report 2007

• Building owners, particularly those represented by CURT, regularly experience project schedule and cost overruns.

- Construction Users Round Table (CURT) WP 1202 2004

• 37% of materials used in the construction industry become waste

- Movement for Innovation Industry Reports - Economist Magazine 2002

Page 6: State of Tennessee. presented by Bob Oglesby, AIA, LEED AP State Architect Office of the State Architect (OSA)  State of

Office of the State Architect

Creating Greater Owner Value

• The majority of cost and schedule overruns are due to lack of building systems coordination

• BIM, properly applied, can address these issues:

• Need accurate 3D model of structure and architecture

• MEP subcontractors must develop detailed 3D models

• Subcontractors must fabricate and install from those models

Page 7: State of Tennessee. presented by Bob Oglesby, AIA, LEED AP State Architect Office of the State Architect (OSA)  State of

Office of the State Architect

Utilizing Building Information Modeling during Design, Construction and Operations

2009 McGraw Hill Construction’s report “The Business Value of BIM”

The State of TN, like many Owners, say BIM projects have greater value due to:

•Improved collective understanding of design intent

•Improved coordination of drawings / documents

•Improved overall project quality

•Better cost control / predictability of project scope

•Reduced number of RFIs (Requests for Information) and Change Orders

•Reduced conflicts during construction

•Avoiding construction rework / changes

•Faster project delivery

•Providing data useful post construction for Operations and Maintenance

Page 8: State of Tennessee. presented by Bob Oglesby, AIA, LEED AP State Architect Office of the State Architect (OSA)  State of

Office of the State Architect

BIM / VDC Related Opportunities for Increasing Productivity:

by The Construction Industry Institute (CII)

The linking of BIM / VDC models to intelligent databases and through use of collaboration software helps improve communications, reduces errors and omissions, and reduces project team and construction costs

• The typical building project involves thousands of documents – contracts, budgets, schedules, codes, plans, specifications, cut sheets, shop drawings, fabrication details, warranty information, maintenance data, asset management information, operations procedures, etc.

• Documents which include lots of redundancy and leads to unintentional sharing of inaccurate or out of date information

• Having a common set of real-time information accessible to project owners, project managers, contractors, subcontractors, designers, consultants, and others saves times, improves communication, and reduces errors caused by conflicting information in individual documents or silo applications

• Indirect benefiting contractors so they can more consistently count on construction documents with fewer errors and/or coordination problems

Page 9: State of Tennessee. presented by Bob Oglesby, AIA, LEED AP State Architect Office of the State Architect (OSA)  State of

Office of the State Architect

• Use of BIM can also assist the contractor in better managing its workforce and materials

• Real time project information at the job site can expedite and improve on-site contractor decision making and work sequencing and foster collaborative problem solving and solutions

• Virtual building models assist contractors and subcontractors to better understand the project scope and costs, and resolving conflicts, etc. before starting construction

• Assist contractors in better sequencing their labor activities to eliminate down time and coordinate different trade’s schedules and work areas so that construction is progressing efficiently and as fast as responsibly possible

• Assist trades in better pre-packaging the materials needed for each day’s work so there is less walking around and more work going on

• BIM can support improved Supply Chain Management to significantly cut waste related to time, materials and labor and more efficient procurement of materials and supplies (also potentially reducing on-site storage requirements)

• It can also assist contractors in identifying the best location for materials, supplies and equipment on an on-going basis

Page 10: State of Tennessee. presented by Bob Oglesby, AIA, LEED AP State Architect Office of the State Architect (OSA)  State of

Office of the State Architect

3D modeling supports prefabrication and modularization

•Easier access to tools and less materials waste

Which allows for

•Improved quality and precision in fabrication,

•Lower project costs,

•More efficient use of materials,

•Higher labor productivity,

•Fewer job-site environmental impacts,

•Compressed project schedules,

•Increased worker safety,

•Provision of Contractor “as-built” information (versus Designer “record” drawings) which provides more “value added” services and data for Owners

This will all result in Greater Owner Value - shorter schedules, tighter bids and lower costs

Page 11: State of Tennessee. presented by Bob Oglesby, AIA, LEED AP State Architect Office of the State Architect (OSA)  State of

Office of the State Architect

OSA BIM Consultant Work

Today:

•We will be discussing:

• Recap the steps taken to date

• Mention other upcoming OSA BIM events

• Offer an Informational Session / Webinar on the new TN BIM Requirements (BIMr)

• Introduction – Bob Oglesby, OSA

• What is included and why – OSA consultant Kristine Fallon (KFA )

• Information regarding resources available from software vendors – Kristine Fallon

• Questions and Answers period at the end of today’s session

Page 12: State of Tennessee. presented by Bob Oglesby, AIA, LEED AP State Architect Office of the State Architect (OSA)  State of

Office of the State Architect

OSA BIM Consultant Work

To date:

• I went around state last year discussing State’s interest in BIM and assessing industry’s use

• TN AEC industry representatives completed OSA survey assessing their BIM experience

• 56% using BIM on daily basis

• 89% would support a State BIM program for use by project team members

•OSA held Town Hall / Webinar – BIM Kickoff in September 2012

•What is BIM and why Owners like the State want it used on their projects?

•First step in developing a common vision of the potential uses and benefits of BIM for design, construction, and operations from the Owner’s perspective

•Intent was to demystify BIM; establish a common understanding of the technology, its potential and pitfalls; and suggest options for implementation by the State of TN

Page 13: State of Tennessee. presented by Bob Oglesby, AIA, LEED AP State Architect Office of the State Architect (OSA)  State of

Office of the State Architect

OSA BIM Consultant Work

To date (continued):

•KFA met with each SPA to gather their initial perspectives – in September 2012

•KFA developed first draft of BIMr – in November 2012

•OSA established a TN AEC industry BIM Working Group – to review and comment on BIMr – in December 2012

• Extensively surveyed the members regarding their BIM use and experience

• Incorporated their feedback into revised draft documents

•Finalized draft of BIM Requirements – in January 2013

Page 14: State of Tennessee. presented by Bob Oglesby, AIA, LEED AP State Architect Office of the State Architect (OSA)  State of

Office of the State Architect

OSA BIM Consultant Work

To date (continued):

•Reviewed and incorporated initial comments in February 2013 from

• UT, TBR, and STREAM

• AEC industry attorneys, insurance and surety reps

• Developed Owner’s O & M criteria for space and equipment management (based on COBie Guide) – in March 2013

•Reviewed and incorporated additional comments in March 2013 from

• UT, TBR, and STREAM

•Presented Report on OSA’s BIM Requirements to SBC’s ESC on April 22, 2013

•Released BIM Requirements (BIMr) version 1 on April 23, 2013 – available on OSA website

Page 15: State of Tennessee. presented by Bob Oglesby, AIA, LEED AP State Architect Office of the State Architect (OSA)  State of

Office of the State Architect

OSA BIM Consultant Work

Next steps:

• Conduct training on Design and Construction BIM Usage with State Project Managers and Facilities Managers – on August 13, 2013

• Offer pre-AIA Convention Workshop - open to AEC industry – on August 14, 2013

• 8:00 am Arrival and Registration

• 8:30 am Marlon Blackwell: Using BIM to Create Stellar Design

Since the 1970’s design innovators have looked to the computational power of computers to assist in the representation and coordination

of geometrically complex buildings. Today, BIM-based fabrication of building components is making the impossible possible. Learn from an award-

winning designer why your firm needs to embrace BIM wholeheartedly.

• 9:30 am Break

Page 16: State of Tennessee. presented by Bob Oglesby, AIA, LEED AP State Architect Office of the State Architect (OSA)  State of

Office of the State Architect

OSA BIM Consultant Work

• 9:45 am TN OSA BIM Requirements and Your Business

An industry panel of TN designers and contractors will discuss their experience to date with BIM and how TN OSA requirements will change how they use BIM on state projects. Bob Oglesby, AIA, State Architect, will chair the panel and explain how he expects these BIM Requirements to deliver value to the citizens of Tennessee.

• 10:45 am Break

• 11:00 am Getting Your Firm in the Best Position to Meet the State’s New BIM Requirements

There are many resources to assist design and construction firms in making the most of BIM and meeting TN OSA’s requirements.

This panel includes our workshop sponsors, who will discuss available tools and training specific to the TN OSA BIM Requirements.

• Noon Adjourn

Page 17: State of Tennessee. presented by Bob Oglesby, AIA, LEED AP State Architect Office of the State Architect (OSA)  State of

Office of the State Architect

OSA BIMr

Mission of BIM Requirements

•To create building projects with greater long term owner value through an enhanced design, construction and operations process.

Purpose and Application of the BIM Requirements

•For the consistent development and management of BIM on State building projects.

•They apply to all projects designated to use BIM, and their Designers and Consultants,

and/or to their Contractors and Subcontractors, as specified and selected by any of the three State Procurement Agencies (SPAs):

• State of Tennessee Real Estate Asset Management (STREAM),

• The University of Tennessee (UT), and

• The Tennessee Board of Regents (TBR).

•They may also be voluntarily used by Designers, and/or Contractors, working on State projects who choose on their own to use BIM and agree to do so according to the State’s standards.

Page 18: State of Tennessee. presented by Bob Oglesby, AIA, LEED AP State Architect Office of the State Architect (OSA)  State of

Office of the State Architect

OSA BIMr

BIM General Principles:

•These BIM Requirements do not change the contractual relationship between the parties

or

shift the risks between those parties.

•All parties to any contract relating to the Project shall contain flow down clauses requiring all other parties to those contracts to comply with these BIM Requirements

•Nothing in the BIM Requirements modify, amend, suspend or abrogate any obligation of the Designer to the Owner or the Owner to the Contractor relating to the constructability of the Project’s design.

Page 19: State of Tennessee. presented by Bob Oglesby, AIA, LEED AP State Architect Office of the State Architect (OSA)  State of

Office of the State Architect

OSA BIMr

Ownership and Rights of Data

•The Owner shall have ownership of and rights to all BIMs, electronic CAD files, and building data developed during the Project.

Risk Allocation

• Each non-Owner party shall be responsible for any contribution that it makes to a BIM or that arises from that party’s access to a BIM.

Such responsibility includes any contribution or access to a BIM by a Project Team member in contract with that party and of a lower tier than that party.

Page 20: State of Tennessee. presented by Bob Oglesby, AIA, LEED AP State Architect Office of the State Architect (OSA)  State of

Office of the State Architect

Questions and Answers

Page 21: State of Tennessee. presented by Bob Oglesby, AIA, LEED AP State Architect Office of the State Architect (OSA)  State of

Office of the State Architect

TN OSA BIM Requirements Overview

For DesignersFor Contractors

Page 22: State of Tennessee. presented by Bob Oglesby, AIA, LEED AP State Architect Office of the State Architect (OSA)  State of

Office of the State Architect

TN OSA Approach • All of a BIM project’s team members must use BIM• Open Standards

• No requirement to use a specific software product• As-Built BIMs to be delivered in IFC format• Space and Equipment Inventories to be delivered in COBie format

•At end of Design•At end of Construction

• Major drawings must be extracted from the BIM• Design• Construction

• BIMs must be the basis for: •Area and volume calculations•Energy analysis•Interference checking•Space and equipment inventories

• Design and Construction teams must use collaboration technology to share models and other project information

Page 23: State of Tennessee. presented by Bob Oglesby, AIA, LEED AP State Architect Office of the State Architect (OSA)  State of

Office of the State Architect

BIM Requirements for Designers

Page 24: State of Tennessee. presented by Bob Oglesby, AIA, LEED AP State Architect Office of the State Architect (OSA)  State of

Office of the State Architect

Software Requirements

• BIM authoring software:• Must export models in IFC format• Must support the IFC Coordination View• Must export space and equipment inventories to the COBie format

• Collaboration software:• May be provided by the Owner• Must be web-based• Must provide real-time access to project team• Must support versioning of BIM files• Must provide access-controlled folders for the team members• Must conform to any Owner IT or security requirements

Page 25: State of Tennessee. presented by Bob Oglesby, AIA, LEED AP State Architect Office of the State Architect (OSA)  State of

Office of the State Architect

Acceptable BIM Software for Designers

Autodesk Revit Autodesk Revit ArchitectureAutodesk Revit StructureAutodesk Revit MEPAutodesk AutoCAD ArchitectureAutodesk AutoCAD MEPAutodesk AutoCAD Civil 3D

Bentley ArchitectureBentley AECOsimBentley InroadsGraphisoft ArchiCADGraphisoft ArchiCAD MEPTekla StructuresDigital Project: DesignerNemetschek Vectorworks

Other products will be considered if requested

Page 26: State of Tennessee. presented by Bob Oglesby, AIA, LEED AP State Architect Office of the State Architect (OSA)  State of

Office of the State Architect

Required BIM Uses

• At each design submission, the BIMs shall be provided in IFC format• Conformed Bid BIMs also required in native format

• All plans, sections, and elevation drawings and CAD files at ¼” = 1’-0’ or smaller scale, as well as schedules and 3D views, shall be extracted from the BIMs

• BIMs shall be used to perform all area and volume calculations• BIMs shall be used as the basis for energy analysis• BIMs shall be used to identify and resolve spatial conflicts between building

systems• BIMs shall be used to produce space and equipment inventories

Page 27: State of Tennessee. presented by Bob Oglesby, AIA, LEED AP State Architect Office of the State Architect (OSA)  State of

Office of the State Architect

Reasons for Requirements• IFC-format BIMs can be merged, visualized and checked for interferences using

free software• Conformed Bid BIMs in native format can be updated by Contractor to reflect

As-Built conditions• Drawings and schedule extraction from the BIMs ensures:

• Drawings are coordinated• Building systems coordination effort is reflected in the drawings• Schedules are accurate

• Calculating areas and volumes from BIMs is quicker and more accurate• Using BIMs as the basis for energy analysis reduces time required to get a result

and allows for more iterations and optimization• BIM-based interference checking eliminates the majority of field problems• Space and equipment inventories from BIMs are more accurate

Page 28: State of Tennessee. presented by Bob Oglesby, AIA, LEED AP State Architect Office of the State Architect (OSA)  State of

Office of the State Architect

Other Significant Requirements

• Geo-referencing• Staffing

• BIM Manager• BIM Coordinators

• BIM Execution Plan

Page 29: State of Tennessee. presented by Bob Oglesby, AIA, LEED AP State Architect Office of the State Architect (OSA)  State of

Office of the State Architect

BIM Execution Plan - Designers

• Project Information• Project Designer’s and Designer’s Consultants’ Contact Information• BIM Goals and Objectives• Roles and Responsibilities• Collaboration Plan• All Software to be Used for Model Authoring• Planned Models• Modeling Standards• Model Analysis Plan• Project Deliverables• Sign-Off

Page 30: State of Tennessee. presented by Bob Oglesby, AIA, LEED AP State Architect Office of the State Architect (OSA)  State of

Office of the State Architect

BIM Use: Programming & Schematic Design

Page 31: State of Tennessee. presented by Bob Oglesby, AIA, LEED AP State Architect Office of the State Architect (OSA)  State of

Office of the State Architect

BIM Requirements: Programming & Schematic Design

Pre-Design/Programming

BIM is not required, but encouraged.

Schematic Design Massing BIM indicating siting and orientation.Submit space inventory in COBie format (COBie worksheets: Contact, Facility, Floor, and Space only).Drawings and 3D views shall be extracted from the BIMs.

Page 32: State of Tennessee. presented by Bob Oglesby, AIA, LEED AP State Architect Office of the State Architect (OSA)  State of

Office of the State Architect

BIM Output – Early Design

Page 33: State of Tennessee. presented by Bob Oglesby, AIA, LEED AP State Architect Office of the State Architect (OSA)  State of

Office of the State Architect

BIM Deliverable Requirements – Early Design Stage

Early Design Stage Presentation (or Early Design Review)

BIM in IFC format and if applicable, a site model in IFC or 3D .DWG format, with any custom (ARX) objects converted to native AutoCAD objects.

Page 34: State of Tennessee. presented by Bob Oglesby, AIA, LEED AP State Architect Office of the State Architect (OSA)  State of

Section Derived from BIM – Design Development

Office of the State Architect

Page 35: State of Tennessee. presented by Bob Oglesby, AIA, LEED AP State Architect Office of the State Architect (OSA)  State of

Office of the State Architect

BIM Deliverable Requirements – Design Development

Design Development BIM partitioned by discipline and floor in IFC format only. If applicable, a site model in IFC or 3D .DWG format, with any custom (ARX) objects converted to native AutoCAD objects.BIM-based energy analysis reports

Interference reportSubmit space and equipment inventories in COBie format (COBie worksheets: Contact, Facility, Floor, Space, Zone, Type, System, and Attribute).All ¼” = 1’-0” or smaller scale drawings - Plans, Sections, and Elevations – in addition to Schedules and 3D views shall be extracted from the BIMs.

Page 36: State of Tennessee. presented by Bob Oglesby, AIA, LEED AP State Architect Office of the State Architect (OSA)  State of

Office of the State Architect

MEP BIM – Construction Documents

Page 37: State of Tennessee. presented by Bob Oglesby, AIA, LEED AP State Architect Office of the State Architect (OSA)  State of

Office of the State Architect

BIM Deliverable Requirements – Construction Documents

Construction Documents

BIM partitioned by discipline and floor in IFC format only. If required, a site model in IFC or 3D .DWG format, with any custom (ARX) objects converted to native AutoCAD objects.BIM-based energy analysis reports

Interference ReportSubmit space and equipment inventories in COBie format (COBie worksheets: Contact, Facility, Floor, Space, Zone, Type, Component, System, and Attribute).All ¼” = 1’-0” or smaller scale drawings - Plans, Sections, and Elevations – in addition to Schedules and 3D views shall be extracted from the BIMs.

Page 38: State of Tennessee. presented by Bob Oglesby, AIA, LEED AP State Architect Office of the State Architect (OSA)  State of

Merged BIMs in IFC Format

Office of the State Architect

Page 39: State of Tennessee. presented by Bob Oglesby, AIA, LEED AP State Architect Office of the State Architect (OSA)  State of

Office of the State Architect

BIM Deliverable Requirements – Bid

Bid Submit separate Conformed Bid BIMs for each floor and discipline, in native and IFC file formats. If required, a site model in native and 3D .DWG formats, with any custom (ARX) objects converted to native AutoCAD objects.Extract all Conformed Construction Drawings at ¼” = 1’-0” scale or smaller from the Conformed Bid BIMs.Submit updated space and equipment inventories in COBie format to include changes from Addenda and accepted alternates.

(COBie worksheets: Contact, Facility, Floor, Space, Zone, Type, Component, System, and Attribute).

Page 40: State of Tennessee. presented by Bob Oglesby, AIA, LEED AP State Architect Office of the State Architect (OSA)  State of

Office of the State Architect

Space and Equipment Inventories

Page 41: State of Tennessee. presented by Bob Oglesby, AIA, LEED AP State Architect Office of the State Architect (OSA)  State of

Office of the State Architect

Space Information Required

Field Name DescriptionBuildingName Owner’s Building Number

FacilityIdentification Treasury Risk Management Number

RegionCode Optional: Campus or Complex

FloorIdentification Floor Level

RoomDesignator1 Per Owner’s Standard

RoomDesignator2 Optional: Room “Nickname”

FICMUseCode For UT and TBR

GSASpaceCode For STREAM

UniqueSpaceID GUID assigned by software

GrossAreaSquareFoot Gross Area in SF

NetAssignableAreaSquareFeet Net Area in SF

Page 42: State of Tennessee. presented by Bob Oglesby, AIA, LEED AP State Architect Office of the State Architect (OSA)  State of

Office of the State Architect

Page 43: State of Tennessee. presented by Bob Oglesby, AIA, LEED AP State Architect Office of the State Architect (OSA)  State of

Office of the State Architect

Page 44: State of Tennessee. presented by Bob Oglesby, AIA, LEED AP State Architect Office of the State Architect (OSA)  State of

Office of the State Architect

Equipment Requirements

• Equipment objects shall be named, classified, and assigned attributes per the OSA requirements

• The equipment inventory shall be extracted into the COBie format

Page 45: State of Tennessee. presented by Bob Oglesby, AIA, LEED AP State Architect Office of the State Architect (OSA)  State of

Office of the State Architect

Page 46: State of Tennessee. presented by Bob Oglesby, AIA, LEED AP State Architect Office of the State Architect (OSA)  State of

Office of the State Architect

Page 47: State of Tennessee. presented by Bob Oglesby, AIA, LEED AP State Architect Office of the State Architect (OSA)  State of

Office of the State Architect

Page 48: State of Tennessee. presented by Bob Oglesby, AIA, LEED AP State Architect Office of the State Architect (OSA)  State of

Office of the State Architect

BIM Deliverable Requirements – Project Closeout

Project Closeout Review the As-Built BIMs as developed by the Contractor for conformance to the original design as formally modified throughout the Construction process.

Page 49: State of Tennessee. presented by Bob Oglesby, AIA, LEED AP State Architect Office of the State Architect (OSA)  State of

Office of the State Architect

BIM Requirements for Contractors

Page 50: State of Tennessee. presented by Bob Oglesby, AIA, LEED AP State Architect Office of the State Architect (OSA)  State of

Office of the State Architect

Two Ways to Start

1. Project Designed in BIM– Maintain all or portions of the Conformed Bid BIMs – Cause the trade contractors to create Construction BIMs for

building systems2. No Design BIM

– Provide the Architectural and Structural Proxy BIMs, for coordination purposes only

– Create or cause the trade contractors to create Construction BIMs for other building systems

Page 51: State of Tennessee. presented by Bob Oglesby, AIA, LEED AP State Architect Office of the State Architect (OSA)  State of

• Designers, GC or 3rd party provides base building model

• Subcontractors model own systems

AGC: Contractors’ Guide to BIM

Federated Model:

Office of the State Architect

Page 52: State of Tennessee. presented by Bob Oglesby, AIA, LEED AP State Architect Office of the State Architect (OSA)  State of

Office of the State Architect

Software Requirements

• BIM software:• Must export models in IFC format• Must support the IFC Coordination View• Must export space and equipment inventories to the COBie format

• Collaboration software:• May be provided by the Owner• Must be web-based• Must provide real-time access to project team• Must support versioning of BIM files• Must provide access-controlled folders for the team members• Must conform to any Owner IT or security requirements

Page 53: State of Tennessee. presented by Bob Oglesby, AIA, LEED AP State Architect Office of the State Architect (OSA)  State of

Office of the State Architect

Construction BIMs

• The Contractor and the Contractor’s subcontractors and suppliers shall use BIM authoring software to update the Conformed Bid BIMs or generate new Construction BIMs that include all of the geometry and clearances needed to perform trade coordination.

• Construction BIMs shall be continuously updated and maintained to reflect current as-built conditions

• Construction BIMs shall include the facility management information required by the Owner– Maintain Space inventory provided by Designer– Create equipment inventory showing “actuals”

Page 54: State of Tennessee. presented by Bob Oglesby, AIA, LEED AP State Architect Office of the State Architect (OSA)  State of

Office of the State Architect

Designer/Contractor Equipment Data Responsibilities

Page 55: State of Tennessee. presented by Bob Oglesby, AIA, LEED AP State Architect Office of the State Architect (OSA)  State of

Office of the State Architect

Page 56: State of Tennessee. presented by Bob Oglesby, AIA, LEED AP State Architect Office of the State Architect (OSA)  State of

Required BIM Uses

• Generate equipment inventories

• Identify and resolve spatial interferences between trades and building systems prior to fabrication and field installation

• Coordinated Construction BIMs shall be used: – As the basis for Shop Drawings for those trades using BIM– To generate Coordination Drawings for those trades using BIM– To fabricate building components and systems for those trades using BIM– To install building components and systems for those trades using BIM – To produce equipment inventories which shall be delivered in COBie format

• As-Built Drawings shall be extracted from the Coordinated Construction BIMs.

Office of the State Architect

Page 57: State of Tennessee. presented by Bob Oglesby, AIA, LEED AP State Architect Office of the State Architect (OSA)  State of

• 30% of projects do not make schedule or budget• - CMAA Industry Report 2007

• Building owners, particularly those represented by CURT, regularly experience project schedule and cost overruns.

- CURT WP 1202 2004

• 37% of materials used in the construction industry become waste

- Movement for Innovation Industry Reports and Economist Magazine 2002

Before BIM:

• Corrected upwards of 300 critical conflicts in model

• 25% MEP construction schedule reduction

• ZERO field coordination change orders

• No work stoppages (550 workers) due to coordination issues

• Increased off-site fabrication• Improved Quality• Improved Safety• Decreased material waste

After BIM:

Why the Emphasis on Coordinated Construction BIMs?

Office of the State Architect

Page 58: State of Tennessee. presented by Bob Oglesby, AIA, LEED AP State Architect Office of the State Architect (OSA)  State of

Office of the State Architect

Staffing Requirements

• BIM Manager: identified by the Contractor to manage BIM coordination and deliverables from all Subcontractors and Major Suppliers during construction

• BIM Coordinator: manages the BIM deliverables of the specific subcontractor or supplier. Required for each party creating a Construction BIM.

Page 59: State of Tennessee. presented by Bob Oglesby, AIA, LEED AP State Architect Office of the State Architect (OSA)  State of

Office of the State Architect

BIM Execution Plan- Contractors

• Project Information• Project Construction Team Contact Information• BIM Goals and Objectives• Roles and Responsibilities• Collaboration Plan• Kickoff Meeting• BIM Coordination Process• BIM Coordination Meetings• Software for Model Authoring• Modeling Standards and Content of Models• Other Construction Phase Analyses• BIM Deliverables• Sign-Off

Page 60: State of Tennessee. presented by Bob Oglesby, AIA, LEED AP State Architect Office of the State Architect (OSA)  State of

Office of the State Architect

Milestone DeliverablesCoordination Phase Shop Drawings shall be extracted from the coordinated Construction

BIMs.

Coordination Drawings shall be extracted from the coordinated Construction BIMs.

Closeout PhaseAs-Built BIMs partitioned by discipline and floor in IFC format.Site and landscape information may be submitted in IFC or 3D .DWG file format, with all custom objects converted to native 3D AutoCAD objects.

As-Built Drawings shall be extracted from the As-Built BIMs.

Submit updated space and equipment inventories in COBie format (COBie Worksheets: Contact, Facility, Floor, Space, Zone, Type, Component, System, Document, and Attribute).

Page 61: State of Tennessee. presented by Bob Oglesby, AIA, LEED AP State Architect Office of the State Architect (OSA)  State of

Office of the State Architect

TN OSAConstruction to Operations Building

information exchange (COBie) Requirements

Page 62: State of Tennessee. presented by Bob Oglesby, AIA, LEED AP State Architect Office of the State Architect (OSA)  State of

Image source: http://www.wbdg.org/resources/cobie.php

Why Is TN OSA Requiring COBie?• Computable asset inventory :

– Direct transfer to Facility Management system

– Can be checked for completeness and compliance with software

• Delivered faster• Savings in paper handling,

shipping, reproduction and storage

• COBie is an open standard broadly supported by BIM Facility Management software

Office of the State Architect

Page 63: State of Tennessee. presented by Bob Oglesby, AIA, LEED AP State Architect Office of the State Architect (OSA)  State of

COBie Phased Delivery• Phased delivery of project documentation

• Capture the information when it is created

Source: ERDC

Office of the State Architect

Page 64: State of Tennessee. presented by Bob Oglesby, AIA, LEED AP State Architect Office of the State Architect (OSA)  State of

Consultant Model:

Equipment Specifications

Architectural Model:

Spaces and Equipment Types

Life Cycle Data

Construction Model:Product Data,

O&Ms

Facility Management System :

Space/Equipment Inventory,

Maintenance, Replacement History

+ + >

Office of the State Architect

Page 65: State of Tennessee. presented by Bob Oglesby, AIA, LEED AP State Architect Office of the State Architect (OSA)  State of

Office of the State Architect

COBie Worksheets

COBie Worksheets TN-Required COBie Worksheets

Page 66: State of Tennessee. presented by Bob Oglesby, AIA, LEED AP State Architect Office of the State Architect (OSA)  State of

Office of the State Architect

Designer’s COBie Worksheets

• Contact• Facility• Floor• Space• Zone• Type• Component• System• Attribute

Page 67: State of Tennessee. presented by Bob Oglesby, AIA, LEED AP State Architect Office of the State Architect (OSA)  State of

Office of the State Architect

Contractor’s COBie Worksheets

• Contact• Facility (from design)• Floor (from design)• Space (from design)• Zone• Type (manufacturer, model, warranty information)• Component (serial number, installation date, warranty start date)• System• Document• Attribute

Page 68: State of Tennessee. presented by Bob Oglesby, AIA, LEED AP State Architect Office of the State Architect (OSA)  State of

Office of the State Architect

Page 69: State of Tennessee. presented by Bob Oglesby, AIA, LEED AP State Architect Office of the State Architect (OSA)  State of

Office of the State Architect

COBie Worksheet Required Content

Contact One row for each discipline or organization that provides COBie information. Fields required to be completed include: Email, CreatedBy, CreatedOn, Category, Company, and Phone

Page 70: State of Tennessee. presented by Bob Oglesby, AIA, LEED AP State Architect Office of the State Architect (OSA)  State of

Office of the State Architect

COBie Worksheet Required Content

Facility One building per COBie file. Fields required to be completed include: Name, CreatedBy, CreatedOn, Category, ProjectName, SiteName, LinearUnits, AreaUnits, VolumeUnits, CurrencyUnit, AreaMeasurement, and Description

COBie Worksheet Required Content

Zone One row for each COBie.Space and COBie.Zone type. Fields required to be completed include: Name, CreatedBy, CreatedOn, Category, and SpaceNames

Page 71: State of Tennessee. presented by Bob Oglesby, AIA, LEED AP State Architect Office of the State Architect (OSA)  State of

Office of the State Architect

COBie Worksheet Required Content

Floor One row for each vertical level to include foundations, floors, roofs, and site. Fields required to be completed include: Name, CreatedBy, CreatedOn, Category, Elevation, and Height

Page 72: State of Tennessee. presented by Bob Oglesby, AIA, LEED AP State Architect Office of the State Architect (OSA)  State of

Office of the State Architect

COBie Worksheet Required Content

Space One row per functional space, per room. Multiple spaces in a room are possible. Fields required to be completed include: Name, CreatedBy, CreatedOn, Category, FloorName, Description, GrossArea, and NetArea

Page 73: State of Tennessee. presented by Bob Oglesby, AIA, LEED AP State Architect Office of the State Architect (OSA)  State of

Office of the State Architect

COBie Worksheet Required Content

Type One row for each scheduled product type or tagged equipment type found in the BIMs. Fields required to be completed include: Name, CreatedBy, CreatedOn, Category, Description, AssetType, Manufacturer, ModelNumber, WarrantyGuarantorParts, WarrantyDurationParts, WarrantyGuarantorLabor, WarrantyDurationLabor, WarrantyDurationUnit, NominalLength, NominalWidth, and NomimnalHeight

Page 74: State of Tennessee. presented by Bob Oglesby, AIA, LEED AP State Architect Office of the State Architect (OSA)  State of

Office of the State Architect

COBie Worksheet Required Content

Component One row for each individually scheduled product or each instance of tagged equipment found in the BIMs. Fields required to be completed include: Name, CreatedBy, CreatedOn, TypeName, Space, Description, SerialNumber, InstallationDate, WarrantyStartDate, and TagNumber

Page 75: State of Tennessee. presented by Bob Oglesby, AIA, LEED AP State Architect Office of the State Architect (OSA)  State of

Office of the State Architect

COBie Worksheet Required Content

System One row for each Component identifying the related System. Fields required to be completed include: Name, CreatedBy, CreatedOn, Category, and ComponentNames

Page 76: State of Tennessee. presented by Bob Oglesby, AIA, LEED AP State Architect Office of the State Architect (OSA)  State of

Office of the State Architect

COBie Worksheet Required Content

Attribute One row for each required Space Attribute.One row for each required Type Attribute.One row for each required Component Attribute. Fields required to be completed include: Name, CreatedBy, CreatedOn, Category, SheetName, RowName, Value, and Unit

Page 77: State of Tennessee. presented by Bob Oglesby, AIA, LEED AP State Architect Office of the State Architect (OSA)  State of

Office of the State Architect

COBie Worksheet Required Content

Document One row for each associated deliverable document identifying the relevant equipment type or component. Fields required to be completed include: Name, CreatedBy, CreatedOn, Category, ApprovalBy, Stage, SheetName, RowName, Directory, and File

Page 78: State of Tennessee. presented by Bob Oglesby, AIA, LEED AP State Architect Office of the State Architect (OSA)  State of

as seen at Fort Lewis in 2009

Why Require COBie?

Office of the State Architect

Page 79: State of Tennessee. presented by Bob Oglesby, AIA, LEED AP State Architect Office of the State Architect (OSA)  State of

Office of the State Architect

Software Companies and Technology Service Providers Supporting the TN OSA Requirements

Page 80: State of Tennessee. presented by Bob Oglesby, AIA, LEED AP State Architect Office of the State Architect (OSA)  State of
Page 81: State of Tennessee. presented by Bob Oglesby, AIA, LEED AP State Architect Office of the State Architect (OSA)  State of
Page 82: State of Tennessee. presented by Bob Oglesby, AIA, LEED AP State Architect Office of the State Architect (OSA)  State of
Page 83: State of Tennessee. presented by Bob Oglesby, AIA, LEED AP State Architect Office of the State Architect (OSA)  State of
Page 84: State of Tennessee. presented by Bob Oglesby, AIA, LEED AP State Architect Office of the State Architect (OSA)  State of
Page 85: State of Tennessee. presented by Bob Oglesby, AIA, LEED AP State Architect Office of the State Architect (OSA)  State of
Page 86: State of Tennessee. presented by Bob Oglesby, AIA, LEED AP State Architect Office of the State Architect (OSA)  State of
Page 87: State of Tennessee. presented by Bob Oglesby, AIA, LEED AP State Architect Office of the State Architect (OSA)  State of
Page 88: State of Tennessee. presented by Bob Oglesby, AIA, LEED AP State Architect Office of the State Architect (OSA)  State of
Page 89: State of Tennessee. presented by Bob Oglesby, AIA, LEED AP State Architect Office of the State Architect (OSA)  State of