State Route 94
Corridor Improvement Project
May 10, 2016
Project Overview
Widening & resurfacing SR 94 including I-76 bridge
Great Oaks Trail & Park Centre realigned
Access management improvements
2016 Construction Season
• SR 94 Mainline – May to June
– Continue utility relocation
– Drainage work south of Interstate 76
– Installing water line south of Interstate 76
– Installing new traffic signals
– Minimum of single lane in each direction will be
maintained at all times with turn lanes
2016 Construction Season
• SR 94 Mainline – June to October
– Continue installation of traffic signals
– Widen east side of SR 94
• Single lane in each direction will be maintained
• Center turn lane
2016 Construction Season
• SR 94 Mainline – June to October (Cont.)
– Widen east side of SR 94 bridge over I-76
• I-76: Shoulder closures
• I-76: Temporary lane closures in off-peak hours
• SR 94: 4 Lanes maintained on bridge
2016 Construction Season
Alley Work
2016 Construction Season
• Alley 1 – Improve existing access road to Legacy Inn
KFC
Legacy Inn
2016 Construction Season
• Alley 2 - New access road to Dunkin Donuts, BellStores,
and Casa Del Rio
BellStores
Dunkin Donuts
Casa Del Rio
2016 Construction Season
• Alley 5, 6, & 9 – New access road around Drug Mart Plaza
Drug Mart
2016 Construction Season
• Alley 7 & 8 – Improve and expand “old Kmart” access
road, provide rear access to businesses fronting SR 94
Burger King
Chipotle
Big Lots
2017 Construction Season
• Highlights
– SR 94 mainline work will include:
• Drainage work north of I-76
• Widen west side of SR 94
• Widen west side of SR 94 bridge over I-76
• One lane of traffic in each direction at all times
– Alley construction
• 3 and 4
2017 Construction Season
• Alley 3 & 4 – Improve and expand drive off of Great Oaks
Trail (to Panera/Wendy’s/McDonalds/Goodyear/etc.)
McDonald’s
Wendy’s
2018 Construction Season
• Highlights
– Bridge painting, concrete sealing
– Landscaping
– Final striping work
– Clean up
– Completion: June 2018
Communications
• Communications with Stakeholders
– Web updates for the project
– Weekly email communications as a look-ahead
to coming week
– Sign up via Nixel at City’s website
– ODOT District 3 Public Information Office
• 419-281-0513 or [email protected]
– Harry Stark, City of Wadsworth
• 330-335-2873 or [email protected]
2016 Construction Season
• Reminders during construction:
– If your business experiences an interruption in
utility service as the companies relocate their
utilities within ODOT’s right-of-way, please
contact your utility provider immediately.
– Leave the utility flags and survey laths in place
and please communicate this to any 3rd party
landscaping companies.
Taking Care of Your Business
• Remain Customer Focused:
– Ensure your front line sales staff are up to date
on the construction progress, especially when
local roads are closed to remind callers
– Include information on your website or in
marketing materials by linking to the project
website
– Communicate with neighboring businesses for
possible partnerships, such as cooperative
advertising, promotions or joint activities
Taking Care of Your Business
• Employee Focused:
– Work with employees to make sure the customer
contacts about the traffic impacts are upbeat and
focused on the final construction product
– Demonstrate a positive attitude toward
construction
– Ensure you receive email updates concerning
traffic impacts and ongoing construction work
(sign up today or on project website)
Information Resources
ODOT: Official website for the Ohio Department of Transportation
www.transportation.ohio.gov
Project Information: Visit for SR 94 basic project information
www.transportation.ohio.gov/94
Project Information & Email Sign Up:
http://www.wadsworthcity.com/the-city/home/high-street-project.html
Ohgo: Real time Ohio traffic updates
www.Ohgo.com