State Transportation Board “District” Engineers Report Presentation By: Randy Everett Date: May 15, 2020
State Transportation Board “District” Engineers Report
Presentation By: Randy Everett Date: May 15, 2020
DISTRICT INFORMATION
KEY CONSTRUCTION STAFF:
RANDY EVERETT – SENIOR ADMINISTRATOR JAMES HARTMAN – ASSISTANT DISTRICT ENGINEER DYLAN CARDIE – ASSISTANT DISTRICT ENGINEER
Current Construction Projects Preservation Projects (Pavement and Bridge) Modernize Projects (Minor Projects, Safety) Expansion Projects
Presenter
Presentation Notes
Our schedule for today
Pavement Preservation - Flush • SR87 • US60 • I-17 • Loop202 San Tan • Loop202 Red Mountain • Loop 101 Agua Fria
Modernization Projects
High T Interchange at Maricopa Road & SR347 Advertise: June 2020 Construction Cost: $1.23M
Loop 101 Pima Freeway Widening
Construction Completion: 55% Contract Time Completion: 61%
Presenter
Presentation Notes
Our schedule for today
I-17 Drainage Upgrade
Construction Completion: 6% Contract Time Completion: 25%
Presenter
Presentation Notes
Our schedule for today
I-17 &Central Ave Bridge Replacement
Construction Completion: 0% Contract Time Completion: 5%
Presenter
Presentation Notes
Our schedule for today
I-10 and Fairway TI
Construction Completion: 81% Contract Time Completion: 92%
Presenter
Presentation Notes
Our schedule for today
Loop 101 Price Freeway
Construction Completion: 82% Contract Time Completion: 65%
Presenter
Presentation Notes
Our schedule for today
I-17 Pinnacle Peak & Happy Valley TI
Construction Completion: 64% Contract Time Completion: 82%
Presenter
Presentation Notes
Our schedule for today
SR24 – Gateway Freeway
Advertise: June 2020 Construction Cost: $131M
Presenter
Presentation Notes
Our schedule for today
Lindsay Road TI
Advertise: July 2020 Construction Cost: $26.9 Million
Presenter
Presentation Notes
Our schedule for today
I-10 Gila River Bridge Replacement
Advertise: March 2021 Construction Cost: $78 Million
Presenter
Presentation Notes
Our schedule for today
Future Considerations
Presenter
Presentation Notes
The Roadmap – our strategic plan to transformation We want to take a few minutes to recognize all we’ve accomplished - Milestone Celebration Current State – a quick look at some key progress measures Reflections – spend time reflecting on what’s working and what’s getting in our way - practice using our own methodology to address obstacles – define the problem, root cause analysis, develop & test countermeasures Sustainability – using our reflections work, start thinking about and defining our move towards sustainment, even if we are not perfect
Remove Asphalt Carefully
Presenter
Presentation Notes
The Roadmap – our strategic plan to transformation We want to take a few minutes to recognize all we’ve accomplished - Milestone Celebration Current State – a quick look at some key progress measures Reflections – spend time reflecting on what’s working and what’s getting in our way - practice using our own methodology to address obstacles – define the problem, root cause analysis, develop & test countermeasures Sustainability – using our reflections work, start thinking about and defining our move towards sustainment, even if we are not perfect
Diamond Grinding
Presenter
Presentation Notes
The Roadmap – our strategic plan to transformation We want to take a few minutes to recognize all we’ve accomplished - Milestone Celebration Current State – a quick look at some key progress measures Reflections – spend time reflecting on what’s working and what’s getting in our way - practice using our own methodology to address obstacles – define the problem, root cause analysis, develop & test countermeasures Sustainability – using our reflections work, start thinking about and defining our move towards sustainment, even if we are not perfect