MANDATORY SPARES (STATIC EQUIPMENT) CCR REGENERATION PACKAGE GGSRP, HMEL SECTION: A-4.1 6922-502-16-46-MD-101 Page 1 of 3 Format No. EIL-1641-1924 Rev.1 Copyright EIL – All rights reserved SECTION: A-4: MANDATORY /RECOMENDED SPARES A-4.1: STATIC EQUIPMENT CCR REGENERATION PACKAGE PROJECT : GURU GOBIND SINGH REFINERY OWNER : HPCL-MITTAL ENERGY LIMITED PMC : ENGINEERS INDIA LTD. JOB NO. : 6922 A 20.05.2008 ISSUED FOR BIDS TG VB AKM Rev. No Date Purpose Prepared by Checked by Approved by

Upload: avaisharma

Post on 27-Dec-2015

15 views

Category:

Documents


2 download

DESCRIPTION

static spare

TRANSCRIPT

Page 1: Static Spares

MANDATORY SPARES(STATIC EQUIPMENT)

CCR REGENERATION PACKAGE GGSRP, HMEL

SECTION: A-4.1 6922-502-16-46-MD-101 Page 1 of 3

Format No. EIL-1641-1924 Rev.1 Copyright EIL – All rights reserved

SECTION: A-4: MANDATORY /RECOMENDED SPARES A-4.1: STATIC EQUIPMENT

CCR REGENERATION PACKAGE

PROJECT : GURU GOBIND SINGH REFINERY OWNER : HPCL-MITTAL ENERGY LIMITED PMC : ENGINEERS INDIA LTD. JOB NO. : 6922

A 20.05.2008 ISSUED FOR BIDS TG VB AKM

Rev. No Date Purpose Prepared

by Checked

by Approved

by

Page 2: Static Spares

MANDATORY SPARES(STATIC EQUIPMENT)

CCR REGENERATION PACKAGE GGSRP, HMEL

SECTION: A-4.1 6922-502-16-46-MD-101 Page 2 of 3

Format No. EIL-1641-1924 Rev.1 Copyright EIL – All rights reserved

(A) MANDATORY SPARE PARTS 1. PRESSURE VESSELS, REGENERATION TOWER, REACTOR

Sl. No

Part Description Quantity Required

1 Bolting for each nozzle with blind/ companion flange and for each pad nozzle

10% (min. 2 nos.) for each nozzle

2 Gaskets for each nozzle with blind/ companion flange and for each pad nozzle

200 %

3 Bolting for internal flanges of each nozzle

One set for each nozzle

4 Gasket for internal flanges of each nozzle

200 %

5 Sight/light glasses assembly complete with bolting and gasket

4 sets for each installed glass.

6. Bolts, nuts, clamps, spares for demister of each size/ type

One set of each size / type

2. TUBULAR EXCHANGERS

SL. NO

PART DESCRIPTION QTY

1 Gaskets for girth joints, each nozzle with blind flange and interconnected nozzles

400%

2 Bolting (stud & nuts) 20% Bolting (Min. 4 studs and 8 nuts per joint)

3 Push Rods 100% 4 Lamiflex Sealing Strips 100%

3. ELECTRIC HEATER

SL. NO

PART DESCRIPTION QTY

1 Gaskets for girth joints, each nozzle with blind flange and interconnected nozzles

400%

2 Bolting (stud & nuts) 20% Bolting (Min. 4 studs and 8 nuts per joint)

3 Heating elements 10%(minimum 1) which shall be in-built and electrically not connected.

4. FILTERS, COALESCERS

SL.NO.

PART DESCRIPTION QTY

1 Filter Elements (Cartridges, Coalescing, separating elements)

100% for non reusable type of elements.

2 Bolting (stud & nuts) One set of each size of each nozzle 3 Gaskets 200% of each installed gasket

Page 3: Static Spares

MANDATORY SPARES(STATIC EQUIPMENT)

CCR REGENERATION PACKAGE GGSRP, HMEL

SECTION: A-4.1 6922-502-16-46-MD-101 Page 3 of 3

Format No. EIL-1641-1924 Rev.1 Copyright EIL – All rights reserved

(B) COMMISSIONING SPARES : To be recommended and supplied by vendor. (C) TWO YEARS OPERATIONAL SPARES :

Any additional spares required over and above mandatory spares for 2 years operation including spares for electrical, instrumentation, control etc. and any special tools and tackles required for maintenance shall be quoted separately along with details.