status of muv3 construction a joint ihep protvino – mainz – pisa project muv3 proposed by italo...

11
STATUS OF MUV3 CONSTRUCTION A joint IHEP Protvino – Mainz – Pisa project d by Italo Mannelli: cintillator tiles with direct light collection by PMTs through air evolution to two PMT’s per tile to identify and reject signals from Čerenkov light produced by muons crossing T window ⇒ improved time resolution a cell with two PMTs on a PS beam in August 2010 entation by R. Wanke at the MUV Group Meeting, 8 Sept. 2010) echanical design available at the end of 2010: of commercially available light Al tubes (purchased by Pisa), ack Al septa to provide optical separation between adjacent cells, ates to provide mechanical rigidity and support to the scintillating s. All mechanical components, including PMT fixing collars, built in all PMTs available from the NA48 AKL system (tested in Mainz) y of the two half-modules at CERN during November 2011 Chernov, K. Kachnov (Protvino), A. Bianucci, C. Cerri (Pisa) L. Di Lella (Pisa), 14 Dec 2011

Upload: karin-bishop

Post on 13-Dec-2015

220 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: STATUS OF MUV3 CONSTRUCTION A joint IHEP Protvino – Mainz – Pisa project MUV3  Proposed by Italo Mannelli: Thick scintillator tiles with direct light

STATUS OF MUV3 CONSTRUCTIONA joint IHEP Protvino – Mainz – Pisa project

MUV3 Proposed by Italo Mannelli: Thick scintillator tiles with direct light collection by PMTs through air Design evolution to two PMT’s per tile to identify and reject early signals from Čerenkov light produced by muons crossing the PMT window ⇒ improved time resolution Test of a cell with two PMTs on a PS beam in August 2010 (see presentation by R. Wanke at the MUV Group Meeting, 8 Sept. 2010) Final mechanical design available at the end of 2010: frames of commercially available light Al tubes (purchased by Pisa), thin black Al septa to provide optical separation between adjacent cells, Iron plates to provide mechanical rigidity and support to the scintillating tiles and PMTs. All mechanical components, including PMT fixing collars, built in Protvino. Almost all PMTs available from the NA48 AKL system (tested in Mainz) Assembly of the two half-modules at CERN during November 2011 by E. Chernov, K. Kachnov (Protvino), A. Bianucci, C. Cerri (Pisa)

L. Di Lella (Pisa), 14 Dec 2011

Page 2: STATUS OF MUV3 CONSTRUCTION A joint IHEP Protvino – Mainz – Pisa project MUV3  Proposed by Italo Mannelli: Thick scintillator tiles with direct light

Sketch of the MUV3 detector

12 x 12 cells with 22 x 22 cm scintillator tiles except for the region nearthe beam tube where 2 x 2 cells are replaced by 8 smaller cells:in total, 148 cells (296 PMTs)

Page 3: STATUS OF MUV3 CONSTRUCTION A joint IHEP Protvino – Mainz – Pisa project MUV3  Proposed by Italo Mannelli: Thick scintillator tiles with direct light

Scintillator tile configuration near the beam axis

Half tiles → half cells become full cells when the two half modules are joined together

Page 4: STATUS OF MUV3 CONSTRUCTION A joint IHEP Protvino – Mainz – Pisa project MUV3  Proposed by Italo Mannelli: Thick scintillator tiles with direct light

Structures of light Al tubes manufactured by Bosch

(two frames connected together for each MUV3 half-module)

Page 5: STATUS OF MUV3 CONSTRUCTION A joint IHEP Protvino – Mainz – Pisa project MUV3  Proposed by Italo Mannelli: Thick scintillator tiles with direct light

Installing the scintillator tiles

Scintillator tiles are fixed to theMUV3 front plate by four special screws

Temporary bar will be removed

when the two half-modulesare joined together

Page 6: STATUS OF MUV3 CONSTRUCTION A joint IHEP Protvino – Mainz – Pisa project MUV3  Proposed by Italo Mannelli: Thick scintillator tiles with direct light

PMT supporting plates and light septabefore installation and connection

to the scintillator tile support

Page 7: STATUS OF MUV3 CONSTRUCTION A joint IHEP Protvino – Mainz – Pisa project MUV3  Proposed by Italo Mannelli: Thick scintillator tiles with direct light

The first MUV3 half – module is (almost) completed and is moved away from the assembly tables

Still missing: additional side walls for light tightness MUV3 “feet” with special sliding blocks to slide the two half – modules in their final positions

Page 8: STATUS OF MUV3 CONSTRUCTION A joint IHEP Protvino – Mainz – Pisa project MUV3  Proposed by Italo Mannelli: Thick scintillator tiles with direct light

The 2nd MUV3 half – module is completed(week of 5 December)

Page 9: STATUS OF MUV3 CONSTRUCTION A joint IHEP Protvino – Mainz – Pisa project MUV3  Proposed by Italo Mannelli: Thick scintillator tiles with direct light

A MUV3 “foot” with one sliding block mounted on it Sliding blocks and matching rails are commercially available (Bosch)

Sliding block

Positionof the 2nd sliding block

Page 10: STATUS OF MUV3 CONSTRUCTION A joint IHEP Protvino – Mainz – Pisa project MUV3  Proposed by Italo Mannelli: Thick scintillator tiles with direct light

During the week of 5 December two PMTs have been installedon one cell together with two partially overlapping scintillation counterslocated under half-module 1 to provide a cosmic ray trigger (I. Mannelli, A. Khudyakov)

See presentation by A. Khudyakov for the results from this test

Page 11: STATUS OF MUV3 CONSTRUCTION A joint IHEP Protvino – Mainz – Pisa project MUV3  Proposed by Italo Mannelli: Thick scintillator tiles with direct light

CONCLUSIONS

The construction of the two MUV3 half – modules is practically completed Still missing: PMT installation (foreseen for January 2012) We need 296 PMTs – we must buy ~20 additional PMTs and bases to complete the installation for the whole MUV3 and have a few spare PMTs available during the experiment It is planned to test all cells with cosmic rays using the final electronic chain before installation in ECN3