status of ptcc cases
TRANSCRIPT
S.No. State File No.
Name of
the Power
utility
Name of the Power line KVCkt
Type
PL
KM
CKT.
Km.
Date of
receipt of
proposal
in CEA
Date of
receipt of
BSNL
details
Date of
receipt of
Railway
details
Date of IV
comments
sent by
CEA
Approved
on
1Arunachal
PradeshAP-01 PGCIL
1st Ckt. Of 400kV D/C Lower Subansiri
(Gerukhamukh) - Biswanath Charali
Transmission Line
400 D/C 176.0 352.0 28-Jul-11 2-Dec-08
2Arunachal
PradeshAP-02 PGCIL
2nd Ckt. Of 400kV D/C Lower Subansiri
- Biswanath Chariali Transmission Line400 D/C 176.0 352.0 18-Jun-08 2-Dec-08
3Arunachal
PradeshAP-03 PGCIL
LILO of 400kV D/C existing Ranganadi -
Balipara Line at Biswanath Chariali S/S400 D/C 13.3 26.6 18-Jun-08 1-Oct-10
4Arunachal
PradeshAP-04 PGCIL
400kV D/C Kameng (KIMI) - Balipara
Transmission Line400 D/C 55.4 110.8 23-Jul-08 21-Oct-08
5Arunachal
PradeshAP-05 PGCIL
Biswanath Chariali to Kailajuli
(Thaigibari) Earth electrode Line
(110kV) associated with 800kV HVDC
Transmission Line
110 D/C 72.4 144.8 23-Jul-08 12-Nov-08
6Arunachal
PradeshAP-06 PGCIL
400 kV D/C from Balipara-Biswanath
Chariali Line400 D/C 131.3 262.6 6-Oct-10 19-Oct-10
7Arunachal
PradeshAP-08 PGCIL
110/132kV Earth Electrode line from
Biswanath CHARIALI-NAGSANKAR-
KAILAJULI (THAIGIBAR) associated
with 800kV HVDC
110 D/C 126.0 252.0 12-Aug-11 8-Nov-11 6-Nov-11 1-Apr-13
8Arunachal
PradeshAP-09 TCAPL
220KV DC S/S at PALAMANERU -
Propsed 220 kv S/S MAANAPALLI220 D/C 58.3 116.7 25-Jul-13
9 Assam ASM-01 PGCIL800kV HVDC Biswanath Chariali-
Tanga (Bongaigaon Section) Assam800 D/C 320.0 640.0 14-Jan-08 26-Nov-07
10 Assam ASM-06 PGCIL 400kV D/C Silchar - Meliriat (Mizoram) 400 D/C 120.0 240.0 8-Jun-11 12-Jan-12 8-Oct-12 12-Jul-13
11 Assam ASM-11 PGCIL
LILO of 400kV D/C Silchar -
Bongaigaon Tx. Line of one ckt at
Byrnihat Meghalaya
400 D/C 2.1 4.2 2-Apr-12 10-May-12 6-Aug-12
12 Assam ASM-14 JPCL
220 KV double CKT T/L from Switch
Yard of Rangit-IV HEP, SIKKIM to 220
KV Sub Station of PGCIL at New
Malli(Tokal) in South Sikkim
220 D/C 3.3 6.6 16-Nov-12
CEA LD&T DIVISION - STATUS OF PTCC PROPOSALS IN CEA as on 31.03.2014
EASTERN REGION 1 of 5
S.No. State File No.
Name of
the Power
utility
Name of the Power line KVCkt
Type
PL
KM
CKT.
Km.
Date of
receipt of
proposal
in CEA
Date of
receipt of
BSNL
details
Date of
receipt of
Railway
details
Date of IV
comments
sent by
CEA
Approved
on
CEA LD&T DIVISION - STATUS OF PTCC PROPOSALS IN CEA as on 31.03.2014
13 Assam ASM-15 AEGCIL400kV DC LILO of 400kV pallatana-
bangaigaon transmission line at Azara400 D/C 3.2 6.5 14-Jan-13 28-Mar-13
14 Assam ASM-16 PGCIL 400kV DC SILCHAR-IMPHAL T/L 400 D/C 167.0 334.0 11-Jul-13 19-Aug-13 12-Sep-13 7-Mar-14
15 Bihar BHR-110 DVC220kV D/C MTPS(Mejia) to Gola S/S
With extention upto Ramgarh S/S 220 D/C 201.0 402.0 11-Apr-08 23-Jul-08 6-Nov-12 26-Jun-13
16 Bihar BHR-121 PGCIL800 kV HVDC Saharsa-Gopalganj
Transmission Line800 D/C 182.7 365.3 15-Dec-10 31-Oct-11 8-Jun-11 14-Apr-13
17 Bihar BHR-124 ENICL400kV D/C Quad Purnea - Biharshariff
Trans Line400 D/C 233.0 465.9 31-Oct-11 11-Mar-13 10-May-13 13-May-13
18 Bihar BHR-125 PGCIL400kV D/C Quad Kisanganj - Patna
Trans Line400 D/C 342.0 1368.0 31-Oct-11 31-May-13 23-Jan-12
19 Bihar BHR-127 PGCIL
800kV HVDC Islampur - Sahara Section
at Biswanathcharali - Agra 800kV
HVDC (Pkg - A4)
800 D/C 202.7 405.4 22-Dec-11
20 Bihar BHR-129 PGCIL 400KV Sasaram-Daltouganj T/L 400 D/C 195.8 391.6 16-Aug-12 14-Jan-13 1-Aug-13
21 Bihar BHR-130 PGCILLILO of Ist 400 KV D/C Kahalgaon -
Biharsharif T/L at Lakhisarai400 D/C 15.8 31.6 20-Dec-12 25-Mar-13 17-Jan-13 11-Apr-13
22 Bihar BHR-132 PGCIL400KV D/C Quard Chandwa to Gaya
T/L400 D/C 117.0 234.0 29-Apr-13 7-Apr-13
23 Bihar BHR-133 PGCIL 400 kV D/C Barh-Gorakhpur T/C 400 D/C 348.0 696.0 14-Jun-13 30-Sep-13
24 Bihar BHR-134 PGCIL800 kV HVDC GOPALGANJ-
GORAKHPUR T/L800 D/C 187.4 374.8 22-Nov-13 22-Nov-13 22-Nov-13
25 Bihar BHR-135 PGCIL400 KV D/C BIHARSHARIF -
SASARAM EXTN. T/L400 D/C 45.1 90.2 25-Mar-14
26 Jharkhand JHR-17 DVC 400kV D/C Raghunathpur TPS - Ranchi 400 D/C 150.6 301.2 16-Feb-10 9-Sep-10 10-May-11 18-Dec-13
27 Jharkhand JHR-21 DVC220 kV D/C Kalyaneshwari(DVC)-
Pithakari(PGCIL) Line220 D/C 7.6 15.2 27-Sep-10 12-Oct-10 8-Feb-11
28 Jharkhand JHR-23 DVCRamgarh DVC D/C to JSPL, Patratu
220kV D/C Tx. Line220 D/C 38.0 76.0 12-Jul-11 26-Mar-12 8-Aug-11
29 Jharkhand JHR-24 IVRCL 220kV D/C Lahardaga - Latehar 220 D/C 56.0 111.9 24-Oct-11
30 Jharkhand JHR-25 IVRCL 220kV D/C Latehar - Daltonganj 220 D/C 64.0 127.9 24-Oct-11
31 Jharkhand JHR-26 PGCIL
LILO OF 400 KV D/C Jamshedpur-
Rourkela T/L at Chaibasa, (W)
Singhbhum Jharkhand
400 D/C 27.0 54.0 19-Sep-12 19-Aug-13 10-Jan-13
EASTERN REGION 2 of 5
S.No. State File No.
Name of
the Power
utility
Name of the Power line KVCkt
Type
PL
KM
CKT.
Km.
Date of
receipt of
proposal
in CEA
Date of
receipt of
BSNL
details
Date of
receipt of
Railway
details
Date of IV
comments
sent by
CEA
Approved
on
CEA LD&T DIVISION - STATUS OF PTCC PROPOSALS IN CEA as on 31.03.2014
32 Jharkhand JHR-27 PGCIL
400 KV D/C QUAD T/L from
765/400KV Rauelu (Bero) S/S to 400KV
Chandwa S/S
400 D/C 69.0 138.0 18-Sep-12 22-Jun-13 8-Oct-12 18-Mar-14
33 Jharkhand JHR-28 PGCIL765kV S/C T/C from Raneli (Dero) S/S
to 765/400 Dharam-Jaygarh S/S765 S/C 176.0 176.0 18-Sep-12 1-May-13 7-Jan-13
34 Jharkhand JHR-29 PGCIL400kV D/C quad from 400kV Chandwa
ss to 765/400kV Gaya ss400 D/C 117.0 234.0 1-Apr-13 7-Apr-13
35 Jharkhand JHR-31 PGCIL400kV D/C PTPS PATRATU TO
BORO (New Ranchi) T/L400 D/C 49.7 99.5 8-Aug-13 5-Feb-14
36 Jharkhand JHR-32 PGCIL400 KV D/C LATEHAR (JSEB) PTPS
T/L TO PATRATU400 D/C 110.2 220.3 24-Sep-13 3-Feb-14
37 Jharkhand JHR-33 PGCIL220KV D/C RAMCHANDRAPUR -
CHAIBASA T/L220 D/C 39.0 78.0 21-Mar-14
38 Orrisa ORS-169 GMR
Diversion of 220kV D/C Line of
Meramundali-Duburi (Loc. No. 11 to
Loc. No. 18) to provide adequate
clearance over the proposed Rly Line of
M/s GMR Kamalanga Energy Ltd Orissa
220 D/C 2.0 4.0 15-Mar-11 23-Jan-12
39 Orrisa ORS-172 ESSAR
220kV D/C Line from 220/132/33 kV
Paradeep S/S to M/S Essar Steel Ltd at
Paradeep
220 D/C 8.7 17.4 14-Jul-11 2-Mar-12 9-Aug-12 20-Mar-14
40 Orrisa ORS-173 GMR
LILO at 400kV D/C Talehar -
Meramandoli PGCIL Line at GMR
Kamalanga Energy Ltd, Dhenkanal,
Odisha
400 D/C 0.8 1.7 16-Aug-11 31-Oct-11 2-Nov-11
41 Orrisa ORS-174Sterlite
Energy Ltd
400kV D/C Line from 400kV S/S M/S
Sterlite Enrgy Ltd to Lapanga OPTCL
S/S
400 D/C 14.3 28.6 23-Aug-11 6-Aug-12 26-Dec-12 18-Apr-13
42 Orrisa ORS-175 OPTCL 400kV Ib - Meramundali 400 D/C 235.0 470.0 19-Oct-11 6-Nov-12 20-Feb-14
43 Orrisa ORS-177 OPTCLLILO of 220kV D/C Budhipadar -
Tarkera power line at Kuanrmunda S/S220 D/C 14.9 29.8 25-Oct-11 26-Dec-13 10-Jan-12
44 Orrisa ORS-181 PGCIL400kV D/C Talcher II - Rourkela Tx.
Line400 D/C 157.2 314.5 30-Apr-12 24-Jul-12
45 Orrisa ORS-182 PGCIL400kV D/C Talcher II - Berhampur Tx.
Line400 D/C 217.0 434.0 30-Apr-12
EASTERN REGION 3 of 5
S.No. State File No.
Name of
the Power
utility
Name of the Power line KVCkt
Type
PL
KM
CKT.
Km.
Date of
receipt of
proposal
in CEA
Date of
receipt of
BSNL
details
Date of
receipt of
Railway
details
Date of IV
comments
sent by
CEA
Approved
on
CEA LD&T DIVISION - STATUS OF PTCC PROPOSALS IN CEA as on 31.03.2014
46 Orrisa ORS-183 PGCIL400kV D/C Berhampur - Gajuwaka Tx.
Line400 D/C 293.7 587.4 30-Apr-12
47 Orrisa ORS-189 PGCIL
765 kv D/C Jharsuguda Pooling Station
Dharamjaygarh T/L (Odisha Portion
only) Part-B
765 D/C 44.1 88.2 6-Sep-12 6-Nov-12 1-Mar-14 4-Mar-14
48 Orrisa ORS-191 IBPIL
LILO at 400kV DC Raigarh-Rourkela
T/l at cktI at Sahojbal 2X300 Mw TPS
Jharsaguwada odissa
400 D/C 23.5 47.0 10-Jan-13 7-May-13 1-Jul-13 2-Jul-13
49 Orrisa ORS-192 PGCIL765kV S/C ANGUL P/S -
JHARSUGUDA P/S T/Line-I765 S/C 270.0 270.0 6-Feb-13 17-Jun-13
50 Orrisa ORS-193 PGCIL
765kV s/c Angul pooling station-
Jharsuguda pooling station transmission
lineII
765 S/C 270.0 270.0 6-Feb-13 17-Jun-13
51 Orrisa ORS-194 OPTCL220KV D/C transline from Lakshmipur
Grid S/S to Kansariguda220 D/C 14.9 29.8 15-May-13 19-Aug-13 30-Sep-13 13-Feb-14
52 Orrisa ORS-195 OPTCL
220 kV S/C T/C on DC tower from
220/132/33 kV grid substation at
Paradeep to M/C IOCL at Paradap
220 S/C 6.3 6.3 17-Jun-13
53 Orrisa ORS-196 OPTCL765 D/C ARGUL PS TO
SRIKAKULAM PS TL PART-I765 D/C 275.6 551.2 16-Jul-13
54 Orrisa ORS-197 OPTCL
220KV D/C T/L FROM LAXMIPUR
S/S TO Proposed S/S of M/s Utkal
alumina International Ltd.
220 D/C 31.6 63.2 25-Jul-13 25-Nov-13
55 Orrisa ORS-198 PGCIL
LILO of 400KV D/C AT
MORAMUNDLI-TALCHER CKT-II
T/L AT ANGUL POOLING STN.
400 D/C 17.4 34.8 9-Sep-13 14-Jul-13 9-Sep-13 27-Sep-13
56 Orrisa ORS-199 OPTCL
220 KV DC Line from Proposed
400/220kV GRID S/S BANAPANJARI
(KHURDA) of PGCIL to proposed
220/132kv GRID S/S
220 D/C 45.9 91.8 28-Oct-13
57 West Bengal WB-95 NHPC220kV S/C from Teesta Low Dam III to
Binaguri (NJP) West Bengal220 S/C 80.8 80.8 17-Dec-09
58 West Bengal WB-96 NHPC220kV D/C from Teesta Low Dam IV to
Binaguri (NJP) West Bengal220 D/C 93.7 187.4 17-Dec-09
EASTERN REGION 4 of 5
S.No. State File No.
Name of
the Power
utility
Name of the Power line KVCkt
Type
PL
KM
CKT.
Km.
Date of
receipt of
proposal
in CEA
Date of
receipt of
BSNL
details
Date of
receipt of
Railway
details
Date of IV
comments
sent by
CEA
Approved
on
CEA LD&T DIVISION - STATUS OF PTCC PROPOSALS IN CEA as on 31.03.2014
59 West Bengal WB-101 PGCIL800kV Barobisa - Moynaguri Islampur
(Bongaigaon - Islampur) line800 D/C 212.1 424.1 17-Oct-11 12-Jul-12
60 West Bengal WB-104 CESC
220kV O/H PGCL Subhasgram S/S to
Eastern Metropolitan S/S at Kasba
(CESC)
220 D/C 23.5 47.0 17-Jan-13 22-May-12 24-May-12
61 West Bengal WB-105 TEESTA400kV D/C Teesta-III HEP to
Karandighi S/S T/L400 D/C 228.0 456.0 15-Oct-12
62 West Bengal WB-106 DVC
220kV D/C 30, MTPS-GOLA-
RAMGARH T/L CLIENT-DVC
KOLKATTA
220 D/C 207.5 415.0 19-Oct-12 9-Apr-13
63 West Bengal WB-107 PGCILLILO of Ckt-1 of 400 kV Teesta V -
New Siliguri D/C line at Rangpo GIS S/S400 D/C 3.4 6.8 7-Mar-13
64 West Bengal WB-108 PGCIL 220 kV New Melli-Rangpo D/C line 220 D/C 26.1 52.3 7-Mar-13
65 West Bengal WB-109 PGCILLILO of Ckt-1 of 400 kV Teesta V -
New Siliguri D/C line at Rangpo GIS.400 D/C 26.1 52.3 7-Mar-13
66 West Bengal WB-110 PTCOC220 kV DOMJUR tapping point to
Foundary Park S/S of WBSEICL220 S/C 10-May-13 10-May-13
67 West Bengal WB-111 PGCIL
400KV D/C QUAD LATEHAR
(ESSAR) S/S TO 400KV
LATEHAR(JSEB) S/S
400 D/C 40.4 80.9 27-Jan-14
Note:Discrepancy if any, may please be communicated to Director(PTCC)
EASTERN REGION 5 of 5
S.N
o.State File No.
Name of the
Power
utility
Name of the Power line KVCkt
Type
PL
KM
CKT.
Km.
Date of
receipt of
proposal in
CEA
Date of
receipt of
BSNL
details
Date of
receipt of
Railway
details
Date of IV
comments
sent by
CEA
Approved
by DET on
BSNL
1 Delhi DL-7 BSES220kV S/C PPK II - Matiyala Grid
66kV220 S/C 5 5.00 8-Mar-09
2 Delhi DL-9Delhi
Transco Ltd
220 kV D/C XLPE U/G Cable between
Peragarhi-Wazirpur220 D/C 8.6 17.20 8-Nov-10 10-Nov-10 10-Nov-10
3 Delhi DL-8 &10Delhi
Transco Ltd
220 kV D/C XLPE Cable from
Shalimarbagh - Wazirpur Indl. Area220 D/C 4.5 9.00 28-Mar-11 17-Dec-13 19-Jan-14 21-Jan-14 10-Feb-14
4 DELHI DEL-11 DTRANSCO
220kV XLPE U/G Power Cable lying
between 400/220kV MUNDKA S/S &
220 Kv PEERAGARHI GIS S/S at New
Delhi
220 D/C 13 26.00 26-Nov-13 10-Feb-14 10-Mar-14
5 Haryana HRA-174 HVPNL220kV D/C LILO for Durala from
Shahbad-Pehowa220 D/C 6 12.00 1-Oct-08 2-Feb-09
6 Haryana HRA-184 HVPNL220kV D/C Line from Sampla S/S to
Mohana S/S220 D/C 34.7 69.40 11-May-10 11-May-10 8-Mar-10
7 Haryana HRA-194 PGCILLILO of 400kV D/C Patiala - Hissar
Line at Kaithal400 D/C 32.76 65.52 10-May-11
8 Haryana HRA-198 PGCIL 400kV D/C Bhiwani - Jind power line 400 D/C 82.798 165.60 22-Sep-11 23-Sep-11 31-Oct-11 25-May-12 26-May-12
9 Haryana HRA-199 PGCIL400kV Quad D/C Jharli - Kabulpur -
Dipalpur trans. Line400 D/C 102.5 205.00 9-Jan-12 5-Jan-12 9-Jan-12 18-Jan-12 2-Feb-12
10 Haryana HRA-200 PGCILLILO of 400kV D/C Abdullapur -
Bawana line at Dipalpur400 D/C 0.706 1.41 24-Jan-12 27-Jan-12 27-Jan-12 27-Jan-12 10-Feb-12
11 Haryana HRA-201 Adani Power400kV D/C Quad Mohindargarh -
Dhanonda (Haryana)400 D/C 4.47 8.94 20-Jan-12 7-Mar-12 24-Feb-12 14-Mar-12 19-Mar-12
12 Haryana HRA-202 PGCIL
LILO of both circuits of 400kV D/C
Mundka (DTL) - Bamnauli (DTL) line
at Jattikalan S/S (PGCIL)
400 D/C 12.2 12.20 6-Feb-12 24-Aug-12 23-Aug-12 24-Aug-12 27-Aug-12
13 Haryana HRA-203 PGCILMEERUT - MOGA T/L 765 KV S/C
QUAD 765 S/C 179 179.00 18-Nov-13 3-Dec-13
14 Haryana HRA-204 PGCIL400kV D/C KURUKSHETRA-
JALANDHAR LINE400 D/C 113.58 227.16 11-Dec-13
15 Haryana HRA-205 PGCIL
i) 400 KV D/C KURUKSHETRA -
JALANDHAR T/L ii) LILO OF 400KV
ABDULLAPUR-SONEPAT AT
KURUKSHETRA
400 D/C 129.73 259.45 10-Dec-13
16Himachal
PradeshHP-51 PGCIL
220kV S/C Line from Karian to PGCIL
s/s Rajera220 S/C 32 32.00 6-Jan-11 6-Jan-11 6-Jan-11 10-Sep-13
CEA LD&T DIVISION - STATUS OF PTCC PROPOSALS IN CEA as on 31.03.2014
NORTHERN REGION 1 of 14
S.N
o.State File No.
Name of the
Power
utility
Name of the Power line KVCkt
Type
PL
KM
CKT.
Km.
Date of
receipt of
proposal in
CEA
Date of
receipt of
BSNL
details
Date of
receipt of
Railway
details
Date of IV
comments
sent by
CEA
Approved
by DET on
BSNL
CEA LD&T DIVISION - STATUS OF PTCC PROPOSALS IN CEA as on 31.03.2014
17Himachal
PradeshHP-52 HPPTCL
220kV D/C Line from 220/33 kV GIS
S/S Lahal to Budhil Power House HEP
at Kharamukh, Chamba
220 D/C 2.0666 4.13 22-Jun-11 22-Jun-11 22-Jun-11 8-Aug-13
18Himachal
PradeshHP-53
SORANG
POWER
400kV LILO to Karehham Wangtoo -
Abdullapur line from 100MW Sorang
Hydroproject
400 D/C 3.2 6.40 19-Jul-11 9-Sep-11 5-Dec-11 15-Jun-12 3-Jul-12
19Himachal
PradeshHP-54 HPPTCL
220kV S/C line from 220kV Budhil GIS
S/S to Chamera-III GIS S/S220 S/C 20 20.00 24-Feb-12 27-Feb-12 27-Feb-12 27-Feb-12 27-Feb-12
20Himachal
PradeshHP-55 HPPTCL
220kV D/C T/L from Hatkoti (Shale) to
220/400 KV Gumma Pooling S/S220 D/C 39.17 78.34 24-Aug-12 24-Aug-12 24-Aug-12 26-Aug-13
21Himachal
PradeshHP-56 HPPTCL
LILO OF 400 KV D/C Jhakri -
Abdulapur (PGCIL) Line at Gumma
220/400 KV pooling S/S
400 D/C 3.198 6.40 24-Aug-12 24-Aug-12 24-Aug-12 26-Aug-13
22Himachal
PradeshHP-57 HPPTCL
220kV D/C T/L from Kunihar to Rouri
line220 D/C 25.8 51.60 28-Jan-13 30-Jan-13 30-Jan-13 20-May-13
23Himachal
PradeshHP-58 PGCIL
LILO OF 400KV D/C NATHPA -
JHAKRI -MALAGARH T/L AT
RAMPUR
400 D/C 3.556 7.11 30-Jan-13 16-Feb-14 17-Feb-14 17-Feb-14
24Himachal
PradeshHP-59 PGCIL
LILO OF 220 KV JALANDHAR -
HAMEERPUR T/L AT HAMEERPUR220 D/C 16.75 33.50 28-Jun-13 2-Jul-13 7-Aug-13
25Himachal
PradeshHP-60 HPPTCL
220 KV D/C T/L FROM 66/132/220
KV POWER STATION SUNDA TO
220 KV SUBSTATION HATKOTI
220 D/C 22.593 45.19 18-Jul-13 29-Jul-13 29-Jul-13 8-Aug-13
26Jammu &
KashmirJ&K-40 PGCIL
220 kV d/c chamera-III PGCIL rajesh-
chameraIII 400 D/C 30 60.00 24-Aug-09
27Jammu &
kashmirJ&K-42 PGCIL 400 KV D/C Kishanpur to Samba T/L 400 D/C 34.8 69.60 26-Feb-13 16-Mar-13 16-Mar-13 18-Mar-13 19-Mar-13
28Jammu &
kashmirJ&K-43 PGCIL
400KV D/C KISHENPUR-NEW
WANPOH T/L AND LILO of 400KV
D/C KISHENPUR-WAGOORA T/L
400 D/C 134 268.00 6-Mar-14 6-Mar-14 6-Mar-14 11-Mar-14 25-Mar-14
29 Punjab PNB-273 PGCIL765 kV S/C Jattikalan-Moga via
Bhiwani Transmission Line765 S/C 177.09 177.09 24-Nov-10 16-Sep-11 19-Sep-11 30-Mar-12 30-Mar-12
30 Punjab PNB-275 PSTCL
LILO of 220kV D/C Malerkotla -
Gobindgarh Power line at 220kV kolaha
S/S
220 D/C 6.65 13.30 14-Jul-11 28-Nov-11
NORTHERN REGION 2 of 14
S.N
o.State File No.
Name of the
Power
utility
Name of the Power line KVCkt
Type
PL
KM
CKT.
Km.
Date of
receipt of
proposal in
CEA
Date of
receipt of
BSNL
details
Date of
receipt of
Railway
details
Date of IV
comments
sent by
CEA
Approved
by DET on
BSNL
CEA LD&T DIVISION - STATUS OF PTCC PROPOSALS IN CEA as on 31.03.2014
31 Punjab PNB-276 PSTCL220kV D/C Line from Bahadurgarh to
Devigarh220 D/C 28.059 56.12 20-Jul-11 28-Nov-11
32 Punjab PNB-277 PSTCL400kV D/C Talwandi Saboo TPS -
Mukatsar400 D/C 100.3 200.60 28-Jul-11 12-Feb-14 12-Feb-14
33 Punjab PNB-278 PSTCL400kV D/C Talwandi Sabo TPS - Dhuri
S/S400 D/C 87.789 175.58 28-Jul-11 2-Jul-12 12-Feb-14 13-Feb-14
34 Punjab PNB-279 PSTCL400kV D/C Talwandi Sabo TPS -
Nakodar & One Ckt. LILO at Moga400 D/C 166.02 332.04 16-Aug-11 25-Jul-12 29-Nov-12 22-Jan-14
35 Punjab PNB-280 PSTCL220kV D/C line on DC towers from
Bottianwala- Mastewala220 D/C 11.798 23.60 16-Aug-11 16-Sep-11 16-Sep-11
36 Punjab PNB-281 PSTCL220kV D/C Bathinda - Malout line
LILO for Badal220 D/C 25.15 50.30 16-Aug-11 10-Feb-12
37 Punjab PNB-282 PSTCL400kV D/C Mukatsar - Makhu
transmission line400 D/C 95.52 191.04 24-Oct-11 10-Feb-12 13-Dec-11 13-Sep-13
38 Punjab PNB-283 PSTCL400kV D/C Makhu - Amritsar
transmission line400 D/C 64.55 129.10 31-Oct-11 18-Jun-13 20-Nov-12 13-Feb-14
39 Punjab PNB-284 PSTCL400kV D/C Nakodar - Makhu
transmission line400 D/C 52.49 104.98 14-Mar-12 2-Jul-12 11-Apr-12 29-Oct-12 3-Nov-12
40 Punjab PNB-285 PSTCL400kV D/C Rajpura - Dhuri
Transmission Line400 D/C 85.169 170.34 14-May-12 5-Mar-13 24-Jul-12 12-Apr-13
41 Punjab PNB-286 PSTCL 400kV D/C Rajpura TPS - Rajpura S/S 400 D/C 8.839 17.68 6-Jun-12 9-Oct-12 24-Jul-12 13-Mar-13
42 Punjab PNB-287 PGCILLILO OF 400 KV D/C BANOLA-
AMRITSAR line at Hamirpur400 D/C 3.36 6.72 13-Jul-12 11-Sep-12 30-Aug-12 19-Mar-14
43 Punjab PNB-288 PSTCL220 KV D/C Line from MUKTASAR -
KOTAKPURA (SANDHVAN) LINE-I220 D/C 38.18 76.36 25-Oct-12 30-Jan-13
44 Punjab PNB-289 PSTCL
220 KV D/C Line from MUKTASAR -
BAJAKHANA LILO for
KALKAPURA
220 D/C 1.52 3.04 25-Oct-12 30-Jan-13
45 Punjab PNB-290 PSTCL220KV D/C GHTP Lehra MOHABBAT
- MANSA LILO for Talwandi Sabo T/L220 D/C 29.85 59.70 3-Dec-12
46 Punjab PNB-291 PSTCL
220 KV D/C GHTP Lehra
MOHABBAT - MANSA LILO for
Dhanaula T/L
220 D/C 38.76 77.52 3-Dec-12
47 Punjab PNB-292 PSTCL
220 KV D/C T/L from 400 KV S/Stn .
MUKATSAR - 220 KV S/Stn.
GHUBAYA
220 D/C 37.913 75.83 3-Dec-12 19-Feb-13 19-Feb-13 22-Jan-14
NORTHERN REGION 3 of 14
S.N
o.State File No.
Name of the
Power
utility
Name of the Power line KVCkt
Type
PL
KM
CKT.
Km.
Date of
receipt of
proposal in
CEA
Date of
receipt of
BSNL
details
Date of
receipt of
Railway
details
Date of IV
comments
sent by
CEA
Approved
by DET on
BSNL
CEA LD&T DIVISION - STATUS OF PTCC PROPOSALS IN CEA as on 31.03.2014
48 Punjab PNB-293 PSTCL220 KV GOINDWAL SAHIB -
CHOHLA SAHIB D/C Line220 D/C 27.623 55.25 11-Dec-12 21-Aug-13
49 Punjab PNB-294 PSTCL220 KV GOINDWAL SAHIB -
SULTANPUR D/C Line220 D/C 18.995 37.99 11-Dec-12 21-Mar-13 25-Mar-14 28-Mar-14
50 Punjab PNB-295 PSTCL
LILO of one ckt of 220kV Rajila to
patran at kakrala D/C on D/C ckt tower
line
220 D/C 3.275 6.55 16-Feb-13
51 Punjab PNB-296 PSTCL220kV Dhuri to Bhalvan loop out D/C
on D/C tower 220 D/C 13.5 27.00 11-Feb-13
52 Punjab PNB-297 PSTCL220kV Dhuri to Bhalwan loop out D/C
on D/C tower 220 D/C 13.522 27.04 11-Feb-13 2-Jul-13
53 Punjab PNB-298 PSTCL 220kV Dhuri to Bhalwan loop line 220 D/C 13.7 27.40 13-Feb-13 2-Jul-13 22-Apr-13 22-Jan-14
54 Punjab PNB-299 PSTCL220kV Dhuri to Bhalwan D/C line on
D/C tower220 D/C 13.7 27.40 25-Feb-13
55 Punjab PNB-300 PSTCL220kV line from 400kV sub station
Dhuri(Bhalwan) - Banyan line220 D/C 50.343 100.69 14-Mar-13 2-Jul-13 25-Nov-13
56 Punjab PNB-301 PSTCL220kV D/C Goindwal Saheb to
Bottiyawalla trans line220 D/C 64.245 128.49 25-Mar-13 18-Jun-13 25-Mar-14 28-Mar-14
57 Punjab PNB-302 PSTCL 400kV Rajpura to Dhuri D/C trans line 400 D/C 187.9 375.81 4-Mar-13
58 Punjab PNB-303 PSTCL 220kV Goindwal Saheb to Chola Saheb 220 D/C 27.623 55.25 9-Apr-13 25-Mar-14 25-Mar-14 29-Mar-14
59 Punjab PNB-304 PSTCL220KV D/C Ferozpur-Talwandi LILO at
Sadiq220 D/C 38.764 77.53 22-Apr-13 28-Jan-14 29-May-13
60 Punjab PNB-305 PSTCL 220KV D/C Rajpura labur line 220 D/C 29.36 58.72 26-Apr-13 18-Jun-13 18-Jun-13
61 Punjab PNB-306 PSTCL220KV D/C T/L from 400KV S/S
Mukatsar to 220KV S/S Abohar 220 D/C 42.531 85.06 26-Apr-13 18-Jun-13 21-Oct-13 22-Jan-14 24-Jan-14
62 Punjab PNB-307 PSTCL400KV D/C line from 400KV S/S
Rajpura to Nakodar 400 D/C 139.53 279.06 7-May-13 29-Jul-13 11-Jul-13 7-Nov-13 21-Nov-13
63 Punjab PNB-308 PSTCL220KV D/C line from 400KV S/S from
Rajpura to Devigarh220 D/C 36.944 73.89 15-May-13
NORTHERN REGION 4 of 14
S.N
o.State File No.
Name of the
Power
utility
Name of the Power line KVCkt
Type
PL
KM
CKT.
Km.
Date of
receipt of
proposal in
CEA
Date of
receipt of
BSNL
details
Date of
receipt of
Railway
details
Date of IV
comments
sent by
CEA
Approved
by DET on
BSNL
CEA LD&T DIVISION - STATUS OF PTCC PROPOSALS IN CEA as on 31.03.2014
64 Punjab PNB-309 PSTCL
220KV S/C from D/C tower from
400KV S/S LUDHIANA to DORAHA
T/L
220 S/C 27.063 27.06 9-May-13 28-Jan-14
65 Punjab PNB-310 PSTCL
220KV D/C Line on D/C tower from
220KV S/S Bagha, Purana to Baza
Khana
220 D/C 34.47 68.94 8-Jul-13 7-Aug-13
66 Punjab PNB-311 PSTCLMAKHU-RASHINA D/C/ LINE
220KV 220 D/C 45.917 91.83 16-Sep-13 26-Nov-13
67 Punjab PNB-312 PSTCL NAKODAR-NURMEHAL LINE 220 D/C 15.18 30.36 21-Nov-13 28-Jan-14
68 Punjab PNB-313 PSTCL NAKODAR-KARTARPUR LINE 220 D/C 26.84 53.68 6-Feb-14
69 Punjab PNB-314 PSTCL
LILO OF Ist CKT of 220kV PATIALA
TO PATRAN D/C LINE AT 220KV
PASIANA S/S
220 D/C 1.24 2.48 25-Mar-14
70 Punjab PNB-315 PSTCL
LILO OF II CKT of 220kV PATIALA
TO PATRAN D/C LINE AT 220KV
RAJALA S/S
221 D/C 6.073 12.15 25-Mar-14
71 Punjab PNB-316 PSTCLLILO OFBHALWAN-BANGAN AT
CHHAJLI 220 KV S/S (LOOP-100)222 D/C 14.525 29.05 25-Mar-14
72 Rajasthan RAJ-375 RVPNL220kV D/C LILO to Mahindra SEZ
from Bassi-Heerapura220 D/C 24 48.00 23-May-08 13-Aug-08 17-Jun-08
73 Rajasthan RAJ-381 BSNL telephone line anta-singhpur 220 S/C 12 12.00 1-Sep-08
74 Rajasthan RAJ-382 BSNLtelephone line gangapur -
KHANKHALA220 S/C 6 6.00 1-Sep-08
75 Rajasthan RAJ-386 BSNL AOFC route mohanamandi- jaipur 220 S/C 3.5 3.50 5-Aug-08 5-Aug-08
76 Rajasthan RAJ-387
VEDANTA
HINDUSTA
N ZINC
LTD.
220kV s/c chittorgarh-CPP VPZL
station220 S/C 10 10.00 1-Oct-08
77 Rajasthan RAJ-410 RVPNL 400kV D/C&S/C STPS-Bikaner 400 D/C 4 8.00 16-Jun-09 1-Sep-09 1-Sep-09
78 Rajasthan RAJ-420 RVPNL220kV D/C (LILO) Ajmer - Beawer
Line220 D/C 18 36.00 26-Mar-10 5-May-11 17-Jun-10
79 Rajasthan RAJ-421 RVPNL220kV D/C (LILO) Ajmer - Kishangarh
Line220 D/C 6 12.00 26-Mar-10 5-May-11 17-Jun-10
NORTHERN REGION 5 of 14
S.N
o.State File No.
Name of the
Power
utility
Name of the Power line KVCkt
Type
PL
KM
CKT.
Km.
Date of
receipt of
proposal in
CEA
Date of
receipt of
BSNL
details
Date of
receipt of
Railway
details
Date of IV
comments
sent by
CEA
Approved
by DET on
BSNL
CEA LD&T DIVISION - STATUS OF PTCC PROPOSALS IN CEA as on 31.03.2014
80 Rajasthan RAJ-433 RVPNL220kV D/C Mandawar(Dausa)-
MIA(Alwar)Line220 D/C 56 112.00 22-Jul-10 9-Dec-10 23-Sep-10 6-Feb-12 12-Feb-13
81 Rajasthan RAJ-435 RVPNL
220kV D/C line to connect LILO of
220kV S/C Heerapura-Khetri(II Ckt) to
LILO of one ckt of 220kV D/C Kotputli-
Neemrana Line
220 D/C 50 100.00 28-Jul-10 21-Dec-10 21-Dec-10 5-Sep-13
82 Rajasthan RAJ-436 RVPNL220 kV S/C Jhunjhunu-Nawalgarh
Power Line220 S/C 30.5 30.50 3-Nov-10 28-Nov-11 24-Nov-10
83 Rajasthan RAJ-437 RVPNL220 kV D/C LILO to Sawa from
Chittorgarh-Nimbahera Line220 D/C 2 4.00 23-Dec-10 25-Jul-12 18-Jun-12 21-Aug-12 28-Aug-12
84 Rajasthan RAJ-441 RVPNL 220kV D/C Dhechu to Phulod 220 D/C 32 64.00 11-Mar-11 26-Jul-11 15-Apr-11 28-Feb-12 29-Feb-12
85 Rajasthan RAJ-442 RVPNL 400kV D/C Phagi - Heerapura 400 D/C 48 96.00 31-Mar-11 13-Dec-11 12-May-11 11-Sep-13
86 Rajasthan RAJ-443 RVPNL 400kV D/C Phagi - Ajmer 400 D/C 105 210.00 1-Apr-11 2-Apr-12 12-May-11 13-Sep-13
87 Rajasthan RAJ-446 RVPNL 220kV D/C Hindaun - Gangapur 220 D/C 50.2 100.40 5-May-11 2-Mar-12 2-Mar-12 29-Aug-13
88 Rajasthan RAJ-447 RVPNL220kV D/C Bikaner (400kV GSS) S/S -
Gajner220 D/C 59.2 118.40 24-May-11 26-Jul-11 20-Jun-11 14-Mar-13 19-Mar-13
89 Rajasthan RAJ-448 PGCIL 400kV D/C Nimrana to Sikar transline 400 D/C 176 352.00 30-May-11 19-Oct-11 30-May-11 3-Jan-12 28-Dec-11
90 Rajasthan RAJ-450 RVPNL
220kV D/C LILO at 200kV D/C KTPS
(Kota) – Beawer line (Ckt. I) to
proposed 220kV GSS Bundi
220 D/C 6 12.00 7-Jul-11 10-Feb-12 10-Feb-12 12-Nov-12 23-Nov-12
91 Rajasthan RAJ-451 RVPNL 220kV S/C Suratgarh - Padampur 220 S/C 55 55.00 18-Jul-11 28-Nov-11 29-Aug-11 14-Mar-13 19-Mar-13
92 Rajasthan RAJ-453 RVPNL 220kV S/C Dechu - Tinwari Line 220 S/C 70.84 70.84 3-Oct-11 28-Nov-11 31-Oct-11 13-Apr-12 16-Apr-12
93 Rajasthan RAJ-454 RVPNLLILO of 220kV Dausa - Hindaun Line at
Sikrai220 D/C 9 18.00 5-Oct-11 27-Aug-12 27-Oct-11 21-Jan-13
94 Rajasthan RAJ-456 RVPNLLILO of 220kV Sirohi - Kankroli line at
Bali220 D/C 2.424 4.85 5-Oct-11 10-Feb-12 12-Dec-11 11-Apr-12 16-Apr-12
95 Rajasthan RAJ-457 RVPNL220kV S/C Bhilwara - M/S Jindal Saw
Ltd. Bhilwara220 S/C 3 9.00 4-Oct-11 13-Dec-11 14-Nov-11
96 Rajasthan RAJ-458 RVPNLLILO of 220kV Metra - Nagaur line at
Kuchera220 D/C 9 18.00 4-Oct-11 23-Mar-12 31-Oct-11
97 Rajasthan RAJ-459 RVPNL220kV S/C Hanumangarh - Udyogvihar
Trans. Line220 S/C 46.25 46.25 4-Oct-11 28-Nov-11 31-Oct-11 13-Mar-13 19-Mar-13
NORTHERN REGION 6 of 14
S.N
o.State File No.
Name of the
Power
utility
Name of the Power line KVCkt
Type
PL
KM
CKT.
Km.
Date of
receipt of
proposal in
CEA
Date of
receipt of
BSNL
details
Date of
receipt of
Railway
details
Date of IV
comments
sent by
CEA
Approved
by DET on
BSNL
CEA LD&T DIVISION - STATUS OF PTCC PROPOSALS IN CEA as on 31.03.2014
98 Rajasthan RAJ-460 RVPNL220kV S/C Padampur - Udyogvihar
Trans. Line220 S/C 37.55 37.55 4-Oct-11 10-Feb-12 27-Oct-11 24-Feb-12 29-Feb-12
99 Rajasthan RAJ-461 RVPNL765kV 2XS/C Anta (Baran) - Phagi
Line Ckt - I765 S/C 210 210.00 17-Oct-11 31-Dec-12 17-Oct-11 21-Aug-13 30-Aug-13
100 Rajasthan RAJ-462 RVPNL765kV 2XS/C Anta (Baran) - Phagi
Line Ckt - II765 S/C 215 215.00 17-Oct-11 20-Aug-13 21-Oct-11 23-Aug-13 30-Aug-13
101 Rajasthan RAJ-463 BSNLArmoured OFC Nadasar - Rajlani
Telecom line220 S/C 8 8.00 19-Oct-11 1-Jul-12 1-Jul-12 23-Jul-12
102 Rajasthan RAJ-464 BSNLArmoured OFC Badanwari - Godan
Telecom line220 S/C 5 5.00 19-Oct-11 1-Jul-12 1-Jul-12 23-Jul-12
103 Rajasthan RAJ-465 BSNLArmoured OFC Jajod - Srimadhopur
Telecom line220 S/C 9 9.00 19-Oct-11 1-Jul-12 1-Jul-12 23-Jul-12
104 Rajasthan RAJ-466 RVPNLLILO of 220kV Bhilwara - Chittorgarh
line at Hamirgarh S/S220 D/C 8 16.00 28-Nov-11 30-Apr-12 14-Dec-11
105 Rajasthan RAJ-467 RVPNL 220kV S/C Sikar - Nawalgarh Tx. Line 220 S/C 24 24.00 28-Nov-11 30-Apr-12 17-Jan-12
106 Rajasthan RAJ-468 RVPNLLILO of 220kV Bharatpur - Mandawar
line at Nadbai S/S220 D/C 5 10.00 28-Nov-11 2-Jul-12 2-Jul-12 26-Nov-12 26-Nov-12
107 Rajasthan RAJ-469 RVPNL
220kV S/C XLPE Cable between
Heerapura (400kV GIS) S/S to NPH
Jaipur (proposed 220kV GIS S/S)
220 S/C 11.45 11.45 5-Dec-11 2-Apr-12 24-Feb-12 29-Aug-13
108 Rajasthan RAJ-470 PGCIL
LILO of 220kV D/C line from Sikar -
Ratangarh (RVPNL) at Sikar (400kV)
S/S
220 D/C 3 6.00 21-Dec-11 22-Nov-11 26-Nov-11 18-Jan-12 10-Feb-12
109 Rajasthan RAJ-471 RVPNL220kV D/C Kotputli - Manoharpur
power line220 S/C 30 30.00 27-Jan-12 18-Oct-12 6-Feb-12 8-Feb-13 15-Feb-13
110 Rajasthan RAJ-472 RVPNL
220kV LILO to 400kV GSS Neemrana
PGCIL S/S from 1 ckt at Neemrana -
Khushkera power line
220 D/C 4 8.00 10-Feb-12 18-Oct-12 21-Feb-12 8-Nov-12 23-Nov-12
111 Rajasthan RAJ-473 RVPNL220kV LILO to Amberi S/S from Debari-
Kankroli line220 D/C 16 32.00 10-Feb-12 25-Jul-12 24-Feb-12
112 Rajasthan RAJ-474 RVPNL220kV LILO to Bamantukda S/S from
Kankroli-Bali power line220 D/C 4 8.00 10-Feb-12 25-Jul-12 21-Feb-12 5-Sep-13
113 Rajasthan RAJ-475 RVPNL 220kV S/C Renwal - Danta power line 220 S/C 30 30.00 21-Feb-12 18-Oct-12 25-Apr-12
114 Rajasthan RAJ-476 RVPNL 220kV S/C Dhod-Danta power line 220 S/C 30 30.00 21-Feb-12 18-Oct-12 2-Mar-12 8-Feb-13 15-Feb-13
115 Rajasthan RAJ-477 RVPNL 400kV D/C Chhabra - Anta power line 400 D/C 89.788 179.58 21-Feb-12 18-Oct-12 12-Sep-12 6-Sep-13
NORTHERN REGION 7 of 14
S.N
o.State File No.
Name of the
Power
utility
Name of the Power line KVCkt
Type
PL
KM
CKT.
Km.
Date of
receipt of
proposal in
CEA
Date of
receipt of
BSNL
details
Date of
receipt of
Railway
details
Date of IV
comments
sent by
CEA
Approved
by DET on
BSNL
CEA LD&T DIVISION - STATUS OF PTCC PROPOSALS IN CEA as on 31.03.2014
116 Rajasthan RAJ-478 RVPNL 400kV D/C Kawad - Anta power line 400 D/C 50.3 100.60 21-Feb-12 18-Oct-12 12-Sep-12 21-Jun-13
117 Rajasthan RAJ-479 RVPNL 400kV D/C Kalisindhi - Anta power line 400 D/C 82.443 164.89 21-Feb-12 18-Oct-12 12-Sep-12 7-Jun-13
118 Rajasthan RAJ-480 RVPNL 220kV S/C Sirohi - Pindwara line 220 S/C 25 25.00 14-Mar-12 18-Oct-12 25-Apr-12
119 Rajasthan RAJ-481 RVPNLLILO of 220kV D/C Bhilwara - Bali line
at Bamantukda S/S220 D/C 9.5 19.00 12-Mar-12 25-Jul-12 21-Mar-12 5-Sep-13
120 Rajasthan RAJ-482 DSPPL 220kV D/C Doorsar Dechu S/S 220 D/C 31.02 62.04 21-Mar-12 30-Mar-12 30-Mar-12 30-Mar-12 30-Mar-12
121 Rajasthan RAJ-483 DSPPL 220kv D/.C Dangri to Akal T/L 220 D/C 47 94.00 10-May-12 14-May-12 14-May-12 14-May-12 14-May-12
122 Rajasthan RAJ-484 RVPNL220kV D/C Sanganer - Sitapura Jaipur
GIS S/S220 D/C 11.5 23.00 21-May-12 18-Oct-12 18-Oct-12 11-Sep-13
123 Rajasthan RAJ-485 RVPNL220kV LILO to Jethana S/S from Ras-
Merta Tx. Line220 D/C 21 42.00 21-May-12 28-Dec-12
124 Rajasthan RAJ-486 RVPNL220kV D/C LILO to Babai from Khetri -
Jaipur line220 D/C 2.5 5.00 22-May-12 24-Aug-12 24-Aug-12 19-Mar-14
125 Rajasthan RAJ-487 RVPNL 220kV S/C Sujangarh - Tahendesar Line 220 S/C 54.9 54.90 22-May-12 30-Jan-13 30-Jan-13
126 Rajasthan RAJ-488 RVPNL 400kV D/C Bhilwara - Chittorgarh Line 400 D/C 48 96.00 22-May-12 30-Jan-13 16-Jul-12
127 Rajasthan RAJ-489 RVPNL220kV LILO to Lalsot from Dausa -
Anta Line220 D/C 10 20.00 31-May-12 28-Dec-12 18-Jun-12 10-Sep-13
128 Rajasthan RAJ-490 RVPNL220kV LILO to Badhu from Fatangarh -
Bikaner power line220 D/C 21.106 42.21 31-May-12 24-Aug-12 24-Aug-12
129 Rajasthan RAJ-491 RVPNLLILO 220KV Khetri to Renges at Babai
power line220 D/C 1.1 2.20 14-Jun-12 24-Aug-12 16-Jul-12 12-Oct-12 16-Oct-12
130 Rajasthan RAJ-492 RVPNL220 kv D/C Jethana - Ajmer (400 KV
GSS) power line220 D/C 7 14.00 14-Jun-12 16-Jul-12
131 Rajasthan RAJ-493 RVPNL 220kV D/C Jodhpur - Bhopalgarh line 220 D/C 84.12 168.24 21-Jun-12 31-Dec-12 16-Jul-12 21-Jan-13
132 Rajasthan RAJ-494 RVPNL
400 KV S/C line from Tower No. 69 of
400 KV Chhabra-Hindaun Line to
Kawai SCTPS
400 S/C 16.34 16.34 2-Jul-12 18-Oct-12 12-Sep-12 23-Nov-12 27-Nov-12
133 Rajasthan RAJ-495 PGCIL
765 KV S/C line Gwalior-Jaipur ckt-I
(part-II) T/L from Piloud c.point to
Jaipur
765 S/C 130 130.00 13-Jun-12 13-Jun-12 31-May-13 19-Mar-14
NORTHERN REGION 8 of 14
S.N
o.State File No.
Name of the
Power
utility
Name of the Power line KVCkt
Type
PL
KM
CKT.
Km.
Date of
receipt of
proposal in
CEA
Date of
receipt of
BSNL
details
Date of
receipt of
Railway
details
Date of IV
comments
sent by
CEA
Approved
by DET on
BSNL
CEA LD&T DIVISION - STATUS OF PTCC PROPOSALS IN CEA as on 31.03.2014
134 Rajasthan RAJ-496 GMR 400 KV S/C Ajmer - Didwana T/L. 400 S/C 108.84 108.84 10-Jul-12 7-Nov-12 3-Aug-12 4-Jan-13 7-Jan-13
135 Rajasthan RAJ-497 RVPNLUpgradation of existing 132 KV S/C
Sanganer - Chaksu line to 220 KV D/C220 D/C 42 84.00 24-Jul-12 30-Jan-13 30-Jul-12 29-Jan-14 4-Feb-14
136 Rajasthan RAJ-498 RVPNL 220 KV D/C Ramgarh-Deehu Line 220 D/C 196.29 392.58 3-Aug-12 31-Dec-12 6-Sep-12
137 Rajasthan RAJ-499 RVPNL400 Kv S/C Bikaner to Didwana
transmission line 400 S/C 129 129.00 3-Aug-12 7-Nov-12 6-Sep-12 29-Nov-12 30-Nov-12
138 Rajasthan RAJ-500 GMR 220 KV D/C Didwana - Sujangarh T/L 220 D/C 29.687 59.37 3-Aug-12 7-Nov-12 6-Sep-12 11-Feb-13 12-Feb-13
139 Rajasthan RAJ-501 RVPNL220 KV LILO to Choukarweda from
Nadbai - Mandawar T/L220 D/C 2.5 5.00 1-Jul-13 10-Jul-13 1-Jul-13 9-Sep-13
140 Rajasthan RAJ-502 RVPNL220 KV D/C Jethana - Mangaliyawas
TSS (DFCC) Line220 D/C 7 14.00 24-Aug-12 28-Dec-12 6-Sep-12
141 Rajasthan RAJ-503 PGCIL400 KV D/C Quad Jaipur (RVPNL-
Jaipur, Bassi PGCIL)400 D/C 47.8 95.60 17-Sep-12 28-Sep-12 6-Sep-12 11-Dec-12 3-Jan-13
142 Rajasthan RAJ-504 PGCIL765 KV S/C Gwalior - Jaipur circuit-II
T/L765 S/C 143 143 5-Mar-13 29-Jul-13 31-May-13 20-Mar-14
143 Rajasthan RAJ-505 RVPNLLILO AT 220 KV S/C Alwar-Dausa T/L
for Alwar 400 KV S/S220 S/C 4 4.00 15-Oct-12 7-Aug-13 23-Oct-12
144 Rajasthan RAJ-506 GMR400 KV S/C Alwar - Hindaun
Transmission Line400 S/C 96.947 97.00 1-Jan-13 27-Dec-12 27-Dec-12 28-Jan-13 29-Jan-13
145 Rajasthan RAJ-507 RVPNL220 KV D/C NEEMRANA(PGCIL)
BEHROR LINE220 D/C 27 54.00 11-Dec-12 16-Feb-13 26-Dec-12 6-Sep-13
146 Rajasthan RAJ-508 RVPNL220 KV LILO to BANSAR (220KV
GSS) from ALWAR-KOTPUTTI line220 D/C 1.048 2.10 11-Dec-12 22-Apr-13 26-Dec-12 9-Sep-13
147 Rajasthan RAJ-509 RVPNL220 KV D/C CHITTORGARH (400KV
GSS) SAWA LINE220 D/C 25 50.00 11-Dec-12 7-Aug-13 29-Jul-13
148 Rajasthan RAJ-510 RVPNL220KV D/C BABAI - 220KV TSS of
M/s. DFCC MAONDA LINE220 D/C 9.5 19.00 11-Dec-12 30-Jan-13 26-Dec-12
149 Rajasthan RAJ-511 RVPNL
220KV D/C KISHANGARH - 220 KV
TSS of M/S OFCC KISHANGARH
Line.
220 D/C 25 50.00 11-Dec-12 29-Jul-13 26-Dec-12
150 Rajasthan RAJ-512 RVPNL
220KV LILO TO 400/220 KV GSS
PGCIL, Jaipur (south) from Duni-SEZ-I
Line
220 D/C 28 56.00 21-Dec-12 30-Jan-13 26-Dec-12
NORTHERN REGION 9 of 14
S.N
o.State File No.
Name of the
Power
utility
Name of the Power line KVCkt
Type
PL
KM
CKT.
Km.
Date of
receipt of
proposal in
CEA
Date of
receipt of
BSNL
details
Date of
receipt of
Railway
details
Date of IV
comments
sent by
CEA
Approved
by DET on
BSNL
CEA LD&T DIVISION - STATUS OF PTCC PROPOSALS IN CEA as on 31.03.2014
151 Rajasthan RAJ-513 RVPNL220kV LILO to lalsot from dausa to anta
line220 D/C 2 4.00 8-Jan-13
152 Rajasthan RAJ-514 PGCIL 765kV S/C Jaipur to Bhiwani 765 S/C 133.41 133.41 12-Feb-13 8-Aug-13 5-Mar-13
153 Rajasthan RAJ-515 PGCIL 765kV S/C Jaipur to Bhiwani 765 S/C 137.43 137.43 25-Feb-13 30-Sep-13 1-Apr-13
154 Rajasthan RAJ-516 RVPNL 220kV D/C Bapbhadla 220 D/C 60 120.00 28-Feb-13 26-Feb-12 25-Mar-13
155 Rajasthan RAJ-517 RVPNL220kV S/C Barsighsir to Fhalori LILO
at 220kV GSS 220 S/C 25 25.00 28-Mar-13 23-Sep-13 25-Mar-13
156 Rajasthan RAJ-518 RVPNL 400kV D/C Bhilwara to Ajmer 400 D/C 155 310.00 7-Mar-13 25-Mar-13
157 Rajasthan RAJ-519 RVPNL 220kV D/C Bhawad to Baithwasia 220 D/C 33.1 66.20 7-Mar-13 2-Jul-13 1-Sep-13 9-Sep-13
158 Rajasthan RAJ-520 RVPNL220KV LILO from Ratangarh-
REENGUS to Laxmangarh line220 D/C 4 8.00 10-May-13 26-Nov-13 27-May-13 26-Nov-13
159 Rajasthan RAJ-521 RVPNL220KV D/C LILO of 220KV S/C KTPS
Sanganar line at 220KV GSS vatika220 D/C 8 16.00 31-May-13 27-Jun-13
160 Rajasthan RAJ-522 RVPNL220KV D/C Jaipur to proposed GSS
vatika220 D/C 30 60.00 31-May-13 27-Jun-13 26-Nov-13 26-Nov-13
161 Rajasthan RAJ-523 RVPNL220 kV GSS Phulera to proposed 220
kV TSS PFCCIL Phulera 220 D/C 10.2 20.40 13-Jun-13 26-Nov-13 27-Jun-13 26-Nov-13
162 Rajasthan RAJ-524 RVPNL220 kV S/S line from 220 kV GSS
Jalare to 220 kV GSS Sayla220 S/C 53 53.00 5-Jun-13 13-Sep-13
163 Rajasthan RAJ-525 RVPNL
220 kV D/C line from PGCIL 400 kV
GSS Bhimal to RVPN 220 kV GSS
Sayla
220 D/C 42 84.00 6-Jun-13 27-Jun-13 13-Sep-13
164 Rajasthan RAJ-526 RVPNL
220 kV D/C LILO to 400 kV GSS
Udaipur from 220 kV S/C Deboi -
Chittorgarh line
220 D/C 2 4.00 21-Jun-13 21-Oct-13 29-Jul-13
165 Rajasthan RAJ-527 RVPNL
220 kV D/C LILO to 400 kV GSS
Udaipur from 220 kV S/C Deboi -
Kankral line
220 D/C 4 8.00 22-Jun-13 29-Jul-13 29-Jul-13
166 Rajasthan RAJ-528 RVPNL220 KV LILO TO DHEEDWANA
FROM KUCHAMAN -DHOD LINE220 D/C 45 90.00 23-Jul-13 13-Sep-13 29-Jul-13
167 Rajasthan RAJ-529 RVPNL230KV D/C PRATAPGARH-
BANSWARA T/L220 D/C 64 128.00 5-Sep-13 20-Sep-13
NORTHERN REGION 10 of 14
S.N
o.State File No.
Name of the
Power
utility
Name of the Power line KVCkt
Type
PL
KM
CKT.
Km.
Date of
receipt of
proposal in
CEA
Date of
receipt of
BSNL
details
Date of
receipt of
Railway
details
Date of IV
comments
sent by
CEA
Approved
by DET on
BSNL
CEA LD&T DIVISION - STATUS OF PTCC PROPOSALS IN CEA as on 31.03.2014
168 Rajasthan RAJ-530 RVPNL220KV D/C CHAKSU(PGCIL 400KV
GSS) TO CHAKSU(220KV GSS) LINE220 D/C 8 16.00 26-Sep-13 15-Oct-13 8-Oct-13 18-Mar-14
169 Rajasthan RAJ-531 RVPNL 400 KV S/C BIKANER-MERTA T/L 400 S/C 170 170.00 28-Oct-13 25-Mar-14 19-Nov-13
170 Rajasthan RAJ-532 RVPNL220 K/V D/CCHHONKARWARA-
HINDAUN T/L220 D/C 38.2 76.40 18-Nov-13 4-Mar-14
171 Rajasthan RAJ-533 RVPNL220KV D/C BALI-FALNA TSS FOR
M/S DFCC LINE220 D/C 15 30.00 30-Jan-14 25-Mar-14 19-Feb-14
172 Rajasthan RAJ-534 PGCIL
LILO of 400KV S/C BHIWADI BASSI
T/L AT KOTPUTLI associated with
"NRTSS"
400 S/C 8.722 8.72 3-Mar-14 26-Mar-14 7-Mar-14 27-Mar-14
173Uttar
PradeshUP-374 NTPC 400kV D/C Dadri - Loni Road Line 400 D/C 54.18 108.36 3-Feb-10 25-Nov-11 10-Nov-10 10-Apr-12 7-May-12
174Uttar
PradeshUP-376A PGCIL
765kV S/C Sasaram-Fatehpur (Part-I)
Transmission Line (Pkg-A4)765 S/C 167 334.00 29-Mar-12 9-Sep-11 23-Mar-12
175Uttar
PradeshUP-376B PGCIL
765kV S/C Sasaram-Fatehpur(Part-II)
Transmission Line (Pkg-A5)765 S/C 170 340.00 22-Sep-10 22-Sep-10 28-Nov-11 20-Mar-12 21-Mar-12
176Uttar
PradeshUP-377 PGCIL
800 HVDC Bipole T/L - Unnao Pkg-A8
(Gomti river xing to Nidhaura)800 D/C 200 400.00 8-Nov-10 24-Jan-11 18-Apr-11 15-Mar-12 17-Mar-12
177Uttar
PradeshUP-379 PGCIL
800kV HVDC Gorakhpur - Gopalganj
(Package A6)800 D/C 187.4 374.79 28-Apr-11 22-Nov-13 22-Nov-13
178Uttar
PradeshUP-380 PGCIL
800kV HVDC Bipole Gorakhpur -
Gomti River Xing (Package A7)800 D/C 190.5 381.00 10-May-11
179Uttar
PradeshUP-381 PGCIL 765kV S/C Fatehpur - Agra 765 S/C 167 167.00 1-May-12 30-Apr-12 16-May-11 23-May-12 24-May-12
180Uttar
PradeshUP-382 PGCIL
400kV D/C Balia - Lucknow Tx. Line at
Sohawal400 D/C 6 12.00 1-Aug-11 12-Oct-11 13-Apr-12 15-May-12 17-May-12
181Uttar
PradeshUP-386 PGCIL
220kV S/C Gonda S/S to Basti S/S
Trans. Line220 S/C 104.37 104.37 22-Sep-11 13-Jan-12 17-Jan-12 9-May-13
182Uttar
PradeshUP-387 PGCIL
765kV S/C Fatehpur - Agra (Upto
Auriya) Trans. Line765 S/C 166.37 166.37 26-Sep-11 11-Oct-11 11-Oct-11 2-Mar-12 2-Mar-12
183Uttar
PradeshUP-388 PGCIL
LILO of 400kV D/C Allahabad -
Mainpuri line at 765/400/220 kV
Fatehpur S/S (LI-18.96 LO-17.984)
400 D/C 36.9 36.90 26-Sep-11 12-Oct-11 6-Feb-12 14-Mar-12 14-Mar-12
184Uttar
PradeshUP-389 PGCIL
765kV S/C Meerut - Agra Trans. Line
(Part - II)765 S/C 131.28 131.28 17-Oct-11 9-Apr-13 9-Apr-13 16-Apr-13
185Uttar
PradeshUP-390 PGCIL
LILO of 400kV D/C Agra - Jaipur
power line400 D/C 37.16 74.32 2-Nov-11 28-Nov-11 4-Nov-11 29-Mar-12 2-Apr-12
NORTHERN REGION 11 of 14
S.N
o.State File No.
Name of the
Power
utility
Name of the Power line KVCkt
Type
PL
KM
CKT.
Km.
Date of
receipt of
proposal in
CEA
Date of
receipt of
BSNL
details
Date of
receipt of
Railway
details
Date of IV
comments
sent by
CEA
Approved
by DET on
BSNL
CEA LD&T DIVISION - STATUS OF PTCC PROPOSALS IN CEA as on 31.03.2014
186Uttar
PradeshUP-392 PGCIL
765kV S/C Agra - Jattikalan (Part-I)
(UP Portion)765 S/C 120.46 120.46 15-Nov-11 28-Nov-11 28-Nov-11 8-Mar-13 18-Mar-13
187Uttar
PradeshUP-393 PGCIL
765kV S/C Agra - Jattikalan (Part-II)
(Delhi & Haryana Portion)765 S/C 132 132.00 14-Nov-11 13-Mar-13 13-Mar-13 25-Mar-13 25-May-13
188Uttar
PradeshUP-394 PGCIL
400kV D/C RPSCL Sharjahapur to
Sharjahanpur PGCIL400 D/C 7.2 14.40 12-Dec-11 18-Dec-11 12-Dec-11 3-Jan-12 5-Jan-12
189Uttar
PradeshUP-395 PGCIL
765kV S/C Meerut - Bhiwani Trans.
Line765 S/C 174 174.00 29-Dec-11 5-Jan-12 31-May-12 7-Feb-13 8-Feb-13
190Uttar
PradeshUP-396 PGCIL
LILO of 400kV D/C Quad Dehradun -
Bagpat line at Saharanpur S/S400 D/C 28.54 57.08 13-Jan-12 10-Feb-12 2-Mar-12
191Uttar
PradeshUP-397 PGCIL
LILO of 400kV D/C Bareilly - Mondola
line at Meerut400 D/C 54.3 108.60 22-Feb-12 11-Aug-12 3-May-12 1-Mar-13 4-Mar-13
192Uttar
PradeshUP-398 PGCIL
LILO of 400kV S/C Panki - Muradnagar
line at Aligarh S/S400 S/C 33 33.00 6-Mar-12 30-May-12 30-May-12 5-Sep-12 6-Sep-12
193Uttar
PradeshUP-399 PGCIL 400kV D/C Aligarh - Sikandrabad line 400 D/C 95 190.00 6-Mar-12 30-May-12 30-May-12 5-Sep-12 6-Sep-12
194Uttar
PradeshUP-400 PGCIL
400kV D/C Kaithal - Meerut line (L/in=
30.142 L/out= 30.95)400 D/C 61.092 61.09 30-Apr-12
195Uttar
PradeshUP-401 PGCIL
765kV S/C fatehpur to agra (pkg-G3)
powerline765 S/C 166.68 166.68 1-Sep-12 3-May-12 16-May-11 18-Sep-12 19-Sep-12
196Uttar
PradeshUP-402 PGCIL
765kV S/C Sasaram - Fatehpur (Part-II)
line - package G2 Ckt-II (UP Portion)765 S/C 179.8 179.80 9-May-12 30-May-12 17-Oct-12 13-Dec-12 17-Dec-12
197Uttar
PradeshUP-403 PGCIL
400kV D/C Tanda - Gonda
Transmission line400 D/C 92 184.00 8-Jun-12 11-Sep-12 11-Sep-12
198Uttar
PradeshUP-404 PGCIL 400kV D/C Gonda - Shahjahanpur line 400 D/C 220 440.00 8-Jun-12 11-Sep-12 11-Sep-12
199Uttar
PradeshUP-405 SEUPPTCL
400KV D/C Mainpuri-Aligarh Power
line400 D/C 93 186.00 2-Jul-12 17-Jan-13 11-Dec-12
200Uttar
PradeshUP-406 PGCIL 765kV S/C Meerat to Agra T/L (part-I) 765 S/C 136.09 136.09 23-Aug-12 12-Sep-12 23-Aug-12 12-Sep-12 13-Sep-12
201Uttar
PradeshUP-407 PGCIL
400KV D/C QUAD Barreilly-Kashipur-
Roorkee T/L400 D/C 251 502.00 1-Oct-12 20-Nov-12 18-Oct-12 4-Mar-13 5-Mar-13
202Uttar
PradeshUP-408 PGCIL
400KV D/C QUAD Barreilly-Barreilly
T/L400 D/C 1.477 2.95 16-Oct-12 16-Oct-12 16-Oct-12 10-Dec-12
NORTHERN REGION 12 of 14
S.N
o.State File No.
Name of the
Power
utility
Name of the Power line KVCkt
Type
PL
KM
CKT.
Km.
Date of
receipt of
proposal in
CEA
Date of
receipt of
BSNL
details
Date of
receipt of
Railway
details
Date of IV
comments
sent by
CEA
Approved
by DET on
BSNL
CEA LD&T DIVISION - STATUS OF PTCC PROPOSALS IN CEA as on 31.03.2014
203Uttar
PradeshUP-409 PGCIL
765KV S/C Barreilly-Lucknow T/L
(part-I)765 S/C 129.3 129.30 16-Oct-12 16-Oct-12 16-Oct-12 10-Dec-12
204Uttar
PradeshUP-410 SEUPPTCL
765KV S/C Mainpuri-Unnao T/L pakg-
1)765 S/C 185 185.00 10-Oct-12 21-Mar-13 25-Nov-13
205Uttar
PradeshUP-411 SEUPPTCL
400KV D/C Rewa Road-Meja T/L pckg-
1400 D/C 33.5 67.00 12-Oct-12 3-May-13 3-May-13 3-Feb-14
206Uttar
PradeshUP-412 SEUPPTCL 400KV D/C Bara-Meja T/L pckg-1 400 D/C 28 56.00 12-Oct-12 3-May-13 20-Jan-14 31-Jan-14
207Uttar
PradeshUP-413 SEUPPTCL
765KV S/C Barreilly-Lucknow T/L
(part-II)765 S/C 121.71 121.71 26-Oct-12 10-Dec-12 10-Dec-12 8-Jan-13 10-Jan-13
208Uttar
PradeshUP-414 SEUPPTCL
765KV S/C Mainpuri-Bara CKT-2 T/L
under UP BOOT Scheme 765 S/C 380 380.00 30-Oct-12 2-Jul-13 3-Dec-13
209Uttar
PradeshUP-415 SEUPPTCL
765KV S/C Mainpuri-Bara CKT-1 T/L
under UP BOOT Scheme 765 S/C 385 385.00 30-Oct-12 2-Jul-13 3-Dec-13
210Uttar
PradeshUP-416 PGCIL 400kV D/C Agra - Sikar T/L PART-I 400 D/C 196.62 393.24 14-Jan-13 3-May-13 20-Feb-13 5-Dec-13
211Uttar
PradeshUP-416A PGCIL 400kV D/C Agra - Sikar T/L PART-II 400 D/C 196.62 393.24 14-Jan-13 3-May-13 20-Feb-13 25-Nov-13
212Uttar
PradeshUP-417 PGCIL
765KV S/C Fatehpur to Agra T/L Part-
II(Pkg. G4) (Second line) Associated
with Sasan Ultra Mega power projects
scheme II
765 S/C 167 167.00 8-Apr-13 6-Sep-13 6-Sep-13 19-Sep-13
213Uttar
PradeshUP-418 SEUPPTCL
400 kV D/C Durai -Mainpuri LILO S/S
under UP Boot Scheme(Package-1)400 D/C 43 86.00 11-Jun-13 29-Jul-13 30-Sep-13
214Uttar
PradeshUP-419 PGCIL 765 KV GAYA-VARANASI T/L 765 D/C 272.85 86.00 6-Aug-13 28-Oct-13 4-Sep-13
215Uttar
PradeshUP-420 PGCIL
Extension of 400KV D/C (QUAD)
BIHAR SHAREEF-SASARAM T/L TO
VARANASI
400 D/C 125.12 86.00 30-Aug-13 20-Oct-13 14-Oct-13
216Uttar
PradeshUP-421 PGCIL
765 KV S/C KANPUR -
JHATIKALAN (PART-i) T/L765 S/C 236.84 236.84 29-Aug-13 29-Aug-13 29-Aug-13 1-Jan-14
217Uttar
PradeshUP-422 PGCIL
765kV D/C RIHAND -
VINDHYACHAL P/S T/L765 D/C 31.154 62.31 11-Dec-13 14-Mar-14 14-Mar-14 24-Mar-14
218Uttar
PradeshUP-423 PGCIL 400 kv D/C MEJA-ALLAHABAD 400 D/C 28.191 56.38 19-Feb-14 6-Mar-14
219Uttar
PradeshUP-424 PGCIL
765 KV D/C VARANASI-KANPUR
PART-II under Transmission System.765 D/C 163.66 327.33 12-Feb-14
NORTHERN REGION 13 of 14
S.N
o.State File No.
Name of the
Power
utility
Name of the Power line KVCkt
Type
PL
KM
CKT.
Km.
Date of
receipt of
proposal in
CEA
Date of
receipt of
BSNL
details
Date of
receipt of
Railway
details
Date of IV
comments
sent by
CEA
Approved
by DET on
BSNL
CEA LD&T DIVISION - STATUS OF PTCC PROPOSALS IN CEA as on 31.03.2014
220Uttarancha
lUTR-08 PGCIL
220kV S/C Maneribhali State-II HP to
220kV S/S Rishikesh220 S/C 110 110.00 3-Feb-10
221Uttarancha
lUTR-09 PTCUL
220kV S/C Barhaini Pant Nagar Trans
Line220 S/C 35.5 35.50 15-Mar-10
222Uttarancha
lUTR-10 PGCIL
400 kV D/C (Quad) Dehradun-Bagpat
Transmission Line Package A-4400 D/C 81 162.00 7-Oct-10 22-Jun-11 6-Sep-11
223Uttarancha
lUTR-11 PGCIL
400 kV D/C (Quad) Dehradun-Bagpat
Transmission Line Package A-3,Part-I400 D/C 84 168.00 7-Oct-10 13-Apr-11 16-Apr-12 12-Jul-13
224Uttarancha
lUTR-12 UTRTCL
220 kV D/C SEPL - Mahuakheraganj
T/L220 D/C 2.512 5.02 2-Feb-12 3-Apr-12 3-Apr-12 10-Apr-12 11-Apr-12
225Uttarancha
lUTR-13 PGCIL
LILO of 400 KV D/C Kashipur to
Roorkee transmission line of PGCIL at
SEPL switch yard
400 D/C 16 32.00 11-Apr-12 4-Jun-12 4-Jun-12 25-Jul-12 6-Aug-12
226Uttarancha
lUTR-14 PGCIL
400kV D/C Quad Roorkee-Saharanpur
line 400 D/C 36.062 72.12 30-Apr-12 30-Apr-12 18-May-12
227Uttarancha
lUTR-15 PGCIL
220 kV D/C Ghuttu-Ghansali Trans.
Line220 D/C 19.38 38.76 16-Jul-12 9-Oct-12
228Uttarancha
lUTR-16 PGCIL
LILO of 400KV D/C T/L from
Moradabad-Rishikesh Line at Dhampur
for Kashipur
400 D/C 59.514 119.03 22-Oct-12
229Uttarancha
lUTR-17 PTCUL
220kV LILO of Roshnahad to Roorkee
line at 400kV D/C220 D/C 36.71 73.42 30-Mar-12 23-Mar-12
230Uttarancha
lUTR-18 PGCIL
400 kV D/C Dehradun-Abdullapur
Quad T/C400 D/C 90 180.00 13-Jun-13 14-Oct-13
Note:Discrepancy if any, may please be communicated to Director(PTCC)
NORTHERN REGION 14 of 14
S.No
.State File No.
Name of
the
Power
utility
Name of the Power line KVCkt
Type
PL
KM
CKT.
Km.
Date of
receipt of
proposal in
CEA
Date of
receipt of
BSNL
details
Date of
receipt of
Railway
details
Date of
receipt of
complete
Power line
details
Date of IV
comments
sent by CEA
Approved
on
1Andra
PradeshAND-509
APTRAN
SCO
220kV LILO line to Chillakallu from 220kV
VTS-Narketpalli main line220 D/C 1.7 3.35 7-Jan-08 5-Aug-09
2Andra
PradeshAND-523
APTRAN
SCO
220kV LILO to the Proposed 220kV S/S at
RTSS Gooty from 220kV Gooty Switching
Station
220 D/C 1.5 3.00 23-Nov-09 31-Dec-12 17-Feb-11 30-Nov-10 18-Mar-14
3Andra
PradeshAND-527
APTRAN
SCO
220kV D/C Line from 220kV S/S Podili to
Proposed 220kV S/S Parchur220 D/C 74.4 148.70 15-Mar-10 27-Dec-12 14-May-10 27-Dec-12 10-Jan-13
4Andra
PradeshAND-528
APTRAN
SCO
220kV D/C Line from Samarlakota 220kV S/S
to Proposed 220MW Barge Mounted Power
Plant at Kakinada in East Godavari
220 D/C 26.3 52.54 29-Mar-10 31-Mar-11 23-Feb-11 31-Mar-11
5Andra
PradeshAND-534
APTRAN
SCO
220 kV D/C line from Hindupur to
pulivendula.220 D/C 124.0 248.00 16-Aug-10 31-Dec-12 19-Jul-11 31-Dec-12
6Andra
PradeshAND-535 PGCIL
400 kV D/C Krishnapatnam to 400 kV
Kurnool S/S400 D/C 328.1 656.29 11-Aug-10 18-Feb-11
7Andra
PradeshAND-536 PGCIL
400 kV D/C Krishnapatnam to 400 kV Gooty
S/S.400 D/C 315.9 631.82 13-Aug-10 18-Feb-11
8Andra
PradeshAND-537 PGCIL
400 kV D/C Krishnapatnam to 400 kV Nellore
S/S400 D/C 32.0 63.90 13-Aug-10 18-Feb-11
9Andra
PradeshAND-539 PGCIL
400kV D/C Line from 400kV Nannuru S/S to
400kV (New) S/S at Kurnool associated to
Krishnapatnam UMPP
400 D/C 9.3 18.63 15-Nov-10 31-Dec-13 15-Mar-11 31-Dec-13 10-Jan-14
10Andra
PradeshAND-540 PGCIL
LILO of Nagarjunasagar-Gooty 400kV S/C
Line at Kurnool 400kV S/S Tx. Line associated
to Krishnapatnam UMPP
400 D/C 35.8 71.64 15-Nov-10 6-Jan-14 5-Apr-11 6-Jan-14 10-Jan-14
11Andra
PradeshAND-542
APTRAN
SCO
1) .220 kv d/c\s/c line from jurala 220 kv s/s
to gudemdodi 220/110 kv s/s
2). 220 kv d/c\s/c line from jurala 220 kv s/s
to marlavidu 220/110 kv s/s
3). 220 kv dc/sc line from gudemdodi 220/110
kv s/s to marlavidu 220 /110 kv s/s
220 D/C 28.8 57.60 1-Feb-11 13-Jun-11 5-Dec-11 2-Jan-11 9-Jan-12
CEA LD&T DIVISION - STATUS OF PTCC PROPOSALS IN CEA as on 31.03.2014
SOUTHERN REGION 1 of 10
CEA LD&T DIVISION - STATUS OF PTCC PROPOSALS IN CEA as on 31.03.2014
12Andra
PradeshAND-543
APTRAN
SCO
220kV LILO to Vemnur from Ramagundam -
Nirmal line220 D/C 0.9 1.89 8-Feb-11 4-Mar-11 8-Jul-11
13Andra
PradeshAND-544 TCAPL
400 kv d/c vijayawada TPS- malkaran 400 kv
s/s 400 D/C 261.4 522.86 6-May-11 24-Aug-12 12-Jul-11 24-Aug-12 13-Sep-12
14Andra
PradeshAND-546
APTRAN
SCO
220 kv d/c line from 400 kv mamidpally s/s to
proposed 220 kv s/s on narrow based m/c
towers
220 D/C 6.0 12.00 12-Aug-11 24-Aug-12 7-Dec-11 1-Sep-12 4-Sep-12
15Andra
PradeshAND-547
APTRAN
SCO
400 kv d/c line from yeddumailaram
(shankarapally) to gajwel s/s 400 D/C 105.0 210.00 16-Aug-12 16-Jul-12 27-Sep-11 27-Sep-11 26-Sep-12
16Andra
PradeshAND-548
APTRAN
SCO
220kV XLPE UG Cable from
Chandrayangutta 220kV SS to 220kV Imliban
GIS SS
220 D/C 9.5 18.98 24-Aug-11 5-Oct-12 2-Jul-12 5-Oct-12 9-Jan-14
17Andra
PradeshAND-549
APTRAN
SCO
220 kv XLDE UG cable from
chandrayangutta 220 kv ss to 220 kv imliban
GIS s/s
220 D/C 16.9 33.80 25-Aug-11 20-Mar-12 19-Sep-11 20-Mar-12 21-Mar-12
18Andra
PradeshAND-550
APTRAN
SCO
220kV XLPE UG Cable from LILO of one
Single circuit of 220kV Gachibowli -
Shapurnagar DC OH
220 D/C 9.4 18.80 30-Aug-11 27-Dec-12 2-Jul-12 27-Dec-12 28-Mar-13
19Andra
PradeshAND-551
APTRAN
SCO
220kV XLPE UG Cable from 220kV SS
Moulali to 220/132/33 kV SS at Osmania
University
220 S/C 9.8 9.80 30-Aug-11 8-Aug-12 2-Jul-12 8-Aug-12 28-Mar-13
20Andra
PradeshAND-552
APTRAN
SCO
400kV D/C line from Nunna - Sattenapalli
400/220 kV SS400 D/C 107.9 215.74 29-Aug-11 5-Oct-12 17-Oct-11 5-Oct-12 26-Mar-14
21Andra
PradeshAND-553
APTRAN
SCO
LILO of 400kV Srisailam - VTPS Stage IV
DC line from Lakkarajugarlapadu village to
proposed 400/220kV SS at Sattenapalli
400 D/C 6.9 13.82 14-Sep-11 22-Oct-13 17-Oct-11 22-Oct-13 7-Nov-13
22Andra
PradeshAND-554
APTRAN
SCO
400kV D/C line from LILO of 400kV
Srisailam - Hyderabad D/C Line (Ckt. I) to
proposed 400kV S/S at Shankarapally
(Yeddumailaram)
400 D/C 82.0 164.00 24-Nov-11 20-Dec-11
23Andra
PradeshAND-556
APTRAN
SCO
400 kv d/c krishnaputnam TPP-nellone
(manubolu) quad moose line 400 D/C 35.8 71.51 13-Dec-11 5-Oct-12 28-Sep-12 5-Oct-12 10-Oct-12 3-Nov-12
24Andra
PradeshAND-557 Reliance
400kV D/C Tx. line with 2400MW Samalkot
power station to Vemagiri pooling station
(Two lines)
400 D/C 26.0 52.00 11-Jan-12
25Andra
PradeshAND-558
APTRAN
SCO
220kV D/C line from 400/220kV
Yeddumailaram S/S to 220kV Sadasivpet S/S
in Medak Distt.
220 D/C 37.5 75.00 5-Mar-12 18-Sep-13 3-Sep-12 15-Oct-13
SOUTHERN REGION 2 of 10
CEA LD&T DIVISION - STATUS OF PTCC PROPOSALS IN CEA as on 31.03.2014
26Andra
PradeshAND-559
APTRAN
SCO
220kV D/C line from Ragulpadu 220kV S/S to
proposed 33/220kV pooling station at
Vajrakarur S/S
220 D/C 5.7 11.32 16-Mar-12 3-Dec-12
27Andra
PradeshAND-560
APTRAN
SCO
LILO of 220 kv tandur-gachibowli line at
400/220 kv yeddumailaram s/s 220 D/C 10.0 20.00 26-Mar-12 8-Aug-12 9-Apr-12 1-Aug-12 31-Aug-12
28Andra
PradeshAND-561 Reliance
LILO of 400kV Kalpaka - Vemagiri
(APTRANSCO line) of one ckt of Samalkot
Genrating Station
400 D/C 12.8 25.60 15-Mar-12 20-May-13
29Andra
Pradesh
AND-562
A,B,C
APTRAN
SCO
A) 220kV DC/SC line from Regumanugadda
220kV S/S to Jonnalaboguda 220kV S/S
B) 220kV DC/SC line from Regumanugadda
220kV S/S to Gudipallygattu 220kV S/S
C) 220kV DC/SC line from Jonnalaboguda
220kV S/S to Gudipallygattu 220kV S/S
220 D/C 65.4 130.80 16-Mar-12 12-Apr-12
30Andra
PradeshAND-563
APTRAN
SCO
220KV D/C Line from M/s Sri Girija Alloys
power pvt Ltd. At Valuthimmapuram to
220KV Samatkota S/S
220 D/C 3.9 7.81 29-Jun-12 15-May-13 24-Jul-12
31Andra
PradeshAND-564
APTRAN
SCO
220 kv LILO to lower jurala hydro electric
project from veltoor-jurala main line 220 D/C 4.5 8.91 3-Jul-12 5-Oct-12 24-Jul-12 5-Oct-12 27-Nov-12
32Andra
PradeshAND-565 PGCIL
400KV D/C QUAD Line from
Thermapowertech corp. of India to Nullore
pooling stn.
400 D/C 32.4 64.86 6-Jul-12 14-Jan-13 18-Feb-13 18-Feb-13 20-May-13
33Andra
PradeshAND-566 PGCIL
400KV D/C QUAD Line from Nullore to
pooling stn. To Gooty S/S400 D/C 289.1 578.26 6-Jul-12 22-Jan-13 18-Feb-13 18-Feb-13 11-Mar-13 14-Mar-13
34Andra
Pradesh
AND-
567A
APTRAN
SCO
220 kv LILO line to 400 kv yeddumailaram
from existing 220 kv shadnagar-yedduailaram220 D/C 4.0 7.92 1-Aug-12 26-Oct-12 27-Aug-12 26-Oct-12 27-Nov-12 16-Jan-13
35Andra
Pradesh
AND-
567B
APTRAN
SCO
LILO at 400 kv yeddumailaram from 220 kv
gachibowli-yeddumailaram m/c tower in
medak dist.
220 D/C 4.0 7.92 1-Aug-12 26-Oct-12 27-Aug-12 26-Oct-12 27-Nov-12 16-Jan-13
36Andra
PradeshAND-568
APTRAN
SCO
220KV D/C Line from 220/132 pendurthi S/S
to 220KV Bhimannadorapalem Switchyard,
Vizianagram
220 D/C 9.4 18.80 7-Aug-12 27-Dec-12 11-Dec-12 27-Dec-12 8-Jan-13
37Andra
PradeshAND-569
APTRAN
SCO
220KV D/C Line from Bhimannadorapalem
Switchyard to 220 KV Bobbili S/S in
vizianagaram distt.
220 D/C 81.5 163.00 7-Aug-12
38Andra
PradeshAND-570
APTRAN
SCO
220KV D/C Line from 220/132 KV Garivid
S/S to 220/132KV Bobbili S/S in Vizianagram220 D/C 37.8 75.50 8-Jul-12 29-May-13
SOUTHERN REGION 3 of 10
CEA LD&T DIVISION - STATUS OF PTCC PROPOSALS IN CEA as on 31.03.2014
39Andra
PradeshAND-571
APTRAN
SCO
220kV D/C Line from 220kV S/S
Bhimannadorapalem to M/S Sarda Metals &
Alloys, Kantakapalli
220 D/C 8.4 16.74 1-Oct-12 7-Jan-13 11-Dec-12 7-Jan-13 7-Jan-13
40Andra
PradeshAND-572
APTRAN
SCO
220KV D/C Line from existing 220 KV D/C
line from existing 220 KV Budidampadu S/S
to the proposed 1X150 MW Power Plant of
M/S Nava Bharat Energy India Ltd. At
Paloncha, Khammam Distt.
220 D/C 60.4 120.82 18-Oct-12 1-Jan-13 4-Jan-13 4-Jan-13 4-Jan-13
41Andra
PradeshAND-573 PGCIL
LILO of 400kV D/C Simhapuri to Nellore
400kV s/s transmission line at nellore pooling
station
400 D/C 7.5 14.95 21-Jan-13 18-Feb-13 11-Feb-13 18-Feb-13 11-Mar-13 14-Mar-13
42Andra
PradeshAND-574 PGCIL
400kV D/C Gooty to Madhugiri(Tumkur)
T/L(Part I & II)400 D/C 208.7 417.48 25-Feb-13 1-Apr-13
43Andra
PradeshAND-575 TCAPL
220kV LILO to the proposed 220/33kV s/s
from existing 220kV Wanaparthy to
Regumangadda D/C line
220 D/C 5.3 10.55 1-Mar-13 9-Apr-13
44Andra
PradeshAND-576 TCAPL
220kV DC line from proposed 220kV lower
Jurala HES to existing 220/132kV Jurala S/S220 D/C 10.6 21.14 28-Feb-13 9-Apr-13
45Andra
PradeshAND-577 TCAPL
220kV DC/SC line from 220kV S/S Tadipatri
to proposed 220/33kV pooling station at
Kadavakallu,Anantpur dist.
220 D/C 26.3 52.64 12-Mar-13 25-Jun-13 9-Apr-13 25-Jun-13 27-Jun-13
46Andra
PradeshAND-578 PGCIL
400kV D/C(Quard) Salem New (Dharmapuri)
station - Somanahalli S/S T/L400 D/C 121.2 242.32 12-Mar-13 29-May-13
47Andra
PradeshAND-579
APTRAN
SCO
400kV D/C line from Bhoopalapalle TPP to
400kV s/s at Gajwel400 D/C 131.2 262.42 27-May-13 15-Mar-13 27-May-13 27-May-13 4-Jun-13
48Andra
Prades
h
AND-580 TCAPL220 KV DC LINE FROM PULIVENDULA
TO MUTHYALACHERUVULU220 D/C 54.7 109.4 23-Apr-13 11-Jun-13
49Andra
Prades
h
AND-581 PGCIL765KV D/C (Hexa-Zebra) Nellore pooling
station-Kurnool T/L765 D/C 302.3 604.6 7-Apr-13 4-Jul-13
50Andra
Prades
h
AND-582 PGCIL400KV D/C Vijaywada-Nellore T/L under
SRSS-XVIII400 D/C 341.4 682.8 6-May-13 4-Jul-13
51Andra
Prades
h
AND-583 TCAPL
220KV M/C line of 220KV cable from
220/132KV S/S Ghanpur to proposed
220/33KV S/S Hayathnagar
220 D/C 25.2 50.4 29-May-13 8-Jul-13
SOUTHERN REGION 4 of 10
CEA LD&T DIVISION - STATUS OF PTCC PROPOSALS IN CEA as on 31.03.2014
52Andra
Prades
h
AND-584 TCAPL220KV line from S/S Parschur to 400KV S/S
Sathnapally220 D/C 53.3 106.6 21-Apr-12 12-Apr-13 21-May-12 8-Aug-13
53
Andra
Prades
h
AND-585 TCAPL
220 kV M/C line from 220 kV S/S Ghanapur
to common point at marripally and erection of
220 kV D/C line from commom point at
maripally to cable 2 at Nagala Bridge
220 D/C 18.0 36.0 17-Jun-13 8-Jul-13
54Andra
Prades
h
AND-586 TCAPL220 kV line from shapuram 220 kV switching
station to prposed Subbarayunipally220 D/C 9.9 19.70 17-Jun-13 2-Jul-13
55Andra
Prades
h
AND-587 TCAPL
220 KV LILO to 220 kV Wadekothapally S/S
from 220 kV Budidampady to Bhangiri 2nd
circuit line
220 S/C 6.7 6.7 17-Jun-13 2-Jul-13
56Andra
Prades
h
AND-588 TCAPL
220 KV D/C LINE FROM
SHANKARPALLY 400/220 KV SS TO
PROPOSED 220/132KV SS PARIGI
220 S/C 43.6 43.6 12-Jul-13 30-Sep-13
57Andra
Prades
h
AND-589 TCAPL
220 KV DC/SC LINE from existing 220kv SS
PALAMANERU - Proposed 220 KV SS
MADANAPALLI
220 S/C 58.3 58.3 2-Jul-13 6-Aug-13
58Andra
Prades
h
AND-590 TCAPL220/132 KV CHINDEPALLI IN CHITOOR
DISTT.220 S/C 18.0 18.0 19-Jul-13 6-Aug-13
59Andra
Prades
h
AND-591 TCAPL220KV RENIGUNTA-MANUBALA DC
LINE220 D/C 1.2 2.4 19-Jul-13 6-Aug-13
60Andra
Prades
h
AND-592APTRAN
SCO
220 KV D/C LINE FROM
NARASARAOPET TO 400KV
SATTENAPALLY S/S
220 D/C 19.8 39.6 1-Mar-12 5-Oct-12 21-May-12 5-Oct-12 8-Aug-13
61Andra
Prades
h
AND-593 TCAPL
erection of 220 kv dc line from 400 kv s/s
MONUBELU - 220KV S/S SULLPURPET in
NELLORE Distt.
220 D/C 67.9 135.8 30-Jun-12 26-Jul-13
62Andra
Prades
h
AND-594 TCAPL 220 KV DC MUTTALA-RAMAGIRI T/L 220 D/C 45.0 90.0 11-Sep-13 20-Oct-13 30-Sep-13 20-Oct-13 24-Oct-13
63Andra
Prades
h
AND-595 PGCIL ANGUL P/S TO SRIKAKULAM P/S 765 D/C 275.6 551.2 10-Oct-13
64Andra
Prades
h
AND-596 TCAPL
220kV DC/SC line from 400/220KV
NANOOR S/S - 220/11kV
BRAMHANAKOTKUR S/S
220 D/C 17.2 34.3 14-Oct-13 25-Nov-13
SOUTHERN REGION 5 of 10
CEA LD&T DIVISION - STATUS OF PTCC PROPOSALS IN CEA as on 31.03.2014
65Andra
Prades
h
AND-597 TCAPL400kV DC Line with AL-59 Twin Moose from
Kalpaka 400kV SS to HNPCL Switch yard400 D/C 7.3 14.6 28-Oct-13 20-Dec-13 25-Nov-13 20-Dec-13 23-Dec-13
66Andra
Prades
h
AND-598 PGCIL
765 kV d/c (Hexa-Zebra) T/l from 765 kV S/S
at KURNOOL(AP) to 765kV S/S at
TIRUVALAM(TN)
765 D/C 355.0 710.0 7-Nov-13
67
Andra
Prades
h
AND-599 TCAPL
220kV DC/SC T/L from 400KV SS
MANUBOLO - M/s. SBQ Steels Ltd at
ANKULAPATURU in SPSR NELLORE
Distt.
220 S/C 17.5 17.5 3-Dec-13 3-Feb-14 3-Feb-14 3-Feb-14 19-Mar-14
68Andra
Prades
h
AND-600APTRAN
SCO
NARKETPALLY 220 KV S/S -
UDAYASAMUDRAM (proposed 220/11kv
S/S)
220 D/C 8.8 17.5 6-Feb-14
69Andra
Prades
h
AND-601APTRAN
SCO
ERECTION OF 400 KV QUAD D/C LINE
FROM JAIPURAM TPP - GAJEWAL S/S400 D/C 162.9 325.8 17-Feb-14
70Karnatak
aKNK-774 KPTCL
Deviation Route of 220kV D/C B.Bagewadi-
Indi Power Line220 D/C 15.812 31.62 6-Jul-09 7-Sep-10
71Karnatak
aKNK-776 KPTCL
220 KV M/C line from existing 220/66 KV
Badadi S/S to Proposal 220/66 KV Ramnagar
S/S in Banglore
220 D/C 18.33 36.66 9-Mar-10 1-Oct-10 23-Dec-10 23-Dec-10 4-Jun-12
72Karnatak
aKNK-777 KPTCL
220 KV M/C LINE FROM EXISTING 220/66
KV BADADI S/S TO PROPOSED 220/66 KV
TKML S/S AT KIABD INDUSTRIAL AREA
BADADI
220 M/C 67.5 135.00 9-Mar-10 16-Jul-12 23-Dec-10 16-Jul-12 18-Jan-13
73Karnatak
aKNK-778 KPTCL
220kV D/C Line from Existing 220/66kV
Tubinakere S/S to Proposed 220/66kV
Ramanagar S/S
220 D/C 67.5 135.00 9-Mar-10 16-Jul-12 23-Dec-10 1-Jan-13 18-Jan-13 18-Jan-13
74Karnatak
aKNK-779 KPTCL
220kV D/C Line from 220/110 kV
Ghataprabha S/S to Proposed 220/110 kV
Chikkodi S/S
220 D/C 36.219 72.44 23-Apr-10 6-Mar-10 23-Dec-10 23-Dec-10 21-May-13
75Karnatak
aKNK-780 KPTCL
220 KV UGC line from existing 220 KV A
station to existing East division station
Bangalore
220 D/C 4.0 8.00 3-Jun-10 11-Oct-10 23-Dec-10 23-Dec-10 12-Dec-12
76Karnatak
aKNK-781 KPTCL
220 KV UGC line from existing east division
station to 220 KV HAL station 220 D/C 8.0 16.00 13-Jun-10 15-Apr-11 23-Dec-10 15-Apr-11 12-Dec-12
77Karnatak
aKNK-783 KPTCL
220kV S/C line from 220/110kV Allipur S/S
to Proposed 400/220kV Kudatini (BPTS)
station in Bellary Dist.
220 S/C 18.263 18.26 30-Sep-10 19-Oct-10
78Karnatak
aKNK-785 PGCIL 765kV S/C Raichur - Sholapur 765 S/C 207.37 207.37 31-Mar-11 4-Oct-11 30-Sep-13 30-Sep-13 1-Nov-13
79Karnatak
aKNK-786 PGCIL 765kV S/C Raichur - Kurnool 765 S/C 116.2 116.20 31-Mar-11 22-Dec-12 20-May-11 21-Jul-11 10-Jan-14
SOUTHERN REGION 6 of 10
CEA LD&T DIVISION - STATUS OF PTCC PROPOSALS IN CEA as on 31.03.2014
80Karnatak
aKNK-787 KPTCL
220 KV D/C line from Jurala hydro power
project to existing 220 KV S/S at Raichur 220 D/C 48.1 96.28 19-Jul-11 7-Jun-12 31-Oct-11 7-Jun-12 2-Jul-12
81Karnatak
aKNK-790 KPTCL
220kV D/C line from existing 400/220kV
HVDC station Kolar to 220/66kV Hoskote220 D/C 35.057 70.11 21-Nov-11 15-Jun-12
82Karnatak
aKNK-791 KPTCL
220kV D/C line from proposed 400/220kV
PGCIL S/S Bidadi to existing 220/66kV
Bidadi S/S
220 D/C 3.358 6.72 21-Feb-12 25-Feb-13 15-Jun-12 25-May-13 24-Sep-13
83Karnatak
aKNK-792 KPTCL
220 KV D/C Line from existing 220KV
BIDVAL S/S TO Proposed 220KV S/S AT
M/S ENERCON INDIA INFRASTRUCTURE
LTD.
220 D/C 25.865 51.73 21-Feb-12 26-Mar-12 23-Mar-12 26-Mar-12 26-Mar-12
84Karnatak
aKNK-793 PGCIL
400 KV M/C line for Neelamamgala to Hooti
S/C and Somanahalli to Hooti S/C line at
Yelahanka Banglore
400 D/C 8 16.00 19-Sep-11 9-May-12 20-Dec-11 9-May-12 13-Jun-12 28-Sep-12
85Karnatak
aKNK-794 KPTCL
220KV D/C LINE from Madhugiri S/S to
proposed 220/66 KV pavagada S/S Tumkur
Distt.
220 D/C 60.49 120.98 24-Jul-12
86Karnatak
aKNK-795 KPTCL
220KV D/C LINE from Kemar to 220 KV
Kavoor in Mangalore Distt. 220 D/C 43.3 86.60 1-Aug-12 4-Feb-13
87Karnatak
aKNK-796 KPTCL
220 KV D/C Line from Ittagi S/S to New
proposed Kudligi (Badeladoku) in Kudligi
Taluk, Bellary Distt.
220 D/C 32.636 65.27 6-Aug-12 11-Oct-12
88Karnatak
aKNK-797 KPTCL
220 KV D/C Line from Basavana Bagevadi
S/S to proposed 220/33 KV pooling station at
M/s Suzolou Putra Structures Ltd.
220 D/C 25.84 51.68 3-Sep-12
89Karnatak
aKNK-798 SPL
400 KV D/C Line from proposed 2 X 210 MW
SPLTPP Near Raichur to proposed 2 X 1599
MVA 765/400 KV Raichur PGCIL S/S
400 D/C 22.143 44.29 3-Sep-12 13-Mar-13
90Karnatak
aKNK-799 KPTCL
220KV D/C Line from 400/220KV PGCIL
G/S Bidadi S/S to proposed 220/66 KV
Magadi S/S in Bangalore Distt.
220 D/C 32.189 64.38 8-Oct-12 13-Feb-13
91Karnatak
aKNK-800 KPTCL
220KV D/C Line from HUDC Kolar S/S to
existing 220/66 KV HOSKOTE S/S at Kolar
Distt.
220 D/C 32.189 64.38 5-Oct-12
92Karnatak
aKNK-801 KPTCL
200kV D/C line from existing 220/66kV
homnali s/s to proposed 220/66 s/s at
Benkikere in Davanagere dist
220 D/C 47.439 94.88 11-Mar-13 29-May-13
93Karnatak
aKNK-802 KPTCL
220KV S/C Line on D/C TOWERS from
existing 220/66/11 KV Bidadi Station to
proposed Bidadi Railways Traction S/S
220 S/C 5.585 5.585 28-Mar-13 29-Jul-13
SOUTHERN REGION 7 of 10
CEA LD&T DIVISION - STATUS OF PTCC PROPOSALS IN CEA as on 31.03.2014
94Karnatak
aKNK-803 KPTCL
220kV MCVTP line to proposed 220
KV/66KV exora gis station in banglore220 S/C 1.0 1.0 9-Apr-13
95Karnatak
aKNK-804 KPTCL
220 KV D/C LINE FROM GM NAWARRA
WIND ENERGY PVT. LTD SAWALSANGA
VLG. BIJAPUR DISTT.
220 D/C 21.1 42.172 9-Apr-13
96Karnatak
aKNK-805 KPTCL
220/120 KV ALIPUR STATION TO
PROPOSED 400/220 KV KUDATINI S/S220 S/C 18.3 18.3 9-Jul-13
97Karnatak
aKNK-806 PGCIL
400KV D/C BANGLORE-SALAM LILO
LINE AT HOSUR S/S 400 D/C 112.3 224.554 5-Jul-13 18-Sep-13 1-Oct-13 1-Oct-13 11-Dec-13
98Karnatak
aKNK-807 KPTCL
220kV DC line from existing 220KV Gadge
s/s to exsiting 220KV BAGALKOT S/S IN
BAGALKOT DISTT.
220 D/C 95.7 191.416 5-Aug-13
99Karnatak
aKNK-808 KPTCL
220KV DC Line from Existing 220 KV
BASAVANA BEGEVADI SS TO
PROPOSED 33/220KV P/S OF M/S
FORTUNE FIVE HYDAL PRJ PVT LTD.
220 D/C 14.5 29.03 29-Jul-13
100Karnatak
aKNK-809 KPTCL
LILO of 400 kV D/C RAICHUR-GOOTY T/L
at New Raichur 765/400 S/S400 D/C 5.2 10.4 28-Jul-13 28-Nov-13 28-Nov-13 28-Nov-13 29-Nov-13
101Karnatak
aKNK-810 PGCIL
400kV QUAD MADHUGIRI (TUMKUR) -
YELAHANKA T/L400 D/C 74.9 149.806 6-Dec-13
102Tamil
naiduTN-613 TNTCL 400 KV D/C line from MTPS stage -3 to Arasur 400 KV S/S 400 D/C 109.8 219.54 20-Jan-11 25-Jul-12 12-Jul-12 23-May-11 24-Dec-12
103Tamil
NaiduTN-614 TNTCL
LILO 400kV D/C Tuticorin- Madurai power
line to 400 KV Coastal energen's power plant
S/S
400 D/C 11.0 21.96 22-Jul-11 18-Apr-12 11-Mar-12 18-Apr-12 4-May-12 15-Jun-12
104Tamil
NaiduTN-615 TNTCL
LILO of 400kV S/C Sriperumbudur –
puducherry at Sunguvarchatram 400kV S/S400 S/C 7.76 7.76 10-Aug-11 16-Mar-12
105Tamil
NaiduTN-616 TNTCL
400 KV M/C line from NCTPS stage 2 to
Alamathy 400 KV S/S 400 D/C 34 68.00 18-Aug-11 25-Jul-12 12-Sep-11 25-Jul-12 17-Sep-12 22-Oct-12
106Tamil
NaiduTN-617 TNTCL
400 KV D/C NCTPS stage 2 to Vallur JV
Project transmission line 400 D/C 3.0 6.00 18-Aug-11 25-Jul-12 12-Sep-11 25-Jul-12 1-Aug-12
107Tamil
NaiduTN-618 TNTCL
400kV M/C Line from Alamathy 400kV S/S to
Sunguvarchatram 400kV S/S400 D/C 48.5 97.00 24-May-12 20-Feb-13 6-Aug-12 20-Feb-13 3-Jun-13
108Tamil
naiduTN-619 TNTCL
220 KV D/C LINE FROM 2*80 CPP
SWITCHYARD TO 230 KV STERLITE
SWITCHING STATION
220 D/C 1.8 3.60 29-May-12 12-Oct-12 12-Oct-12 12-Oct-12 12-Oct-12
109Tamil
naiduTN-620 TNTCL
220 KV D/C LINE FROM 2*80 CPP
SWITCHYARD TO 230 KV STERLITE
SWITCHING STATION
220 D/C 0.95 1.90 29-May-12 12-Oct-12 12-Oct-12 12-Oct-12 12-Oct-12
SOUTHERN REGION 8 of 10
CEA LD&T DIVISION - STATUS OF PTCC PROPOSALS IN CEA as on 31.03.2014
110Tamil
NaiduTN-621 PGCIL
400KV D/C Quad line from Tiruvalam-Chittor
T/L400 D/C 21.772 43.54 26-Jul-12 12-Apr-13 22-Aug-12 12-Apr-13 15-May-13 21-May-13
111Tamil
NaiduTN-622 TTCL
LILO OF 230kV Myvadi-Othakkalmandapm
feeder-II at the proposed Regen Anaikadu
230KV.
230 D/C 3.005 6.01 4-Apr-12 1-Jan-13
112Tamil
NaiduTN-623 TTCL
LILO of 230kV Gummidipoondi-
Sriperumbudur line on DC/MC towers at the
proposed Swiyaada Alloys Switchyard
230 D/C 2 4.00 29-Nov-12 14-Jan-13 18-Dec-12 14-Jan-13 15-Jan-13
113Tamil
NaiduTN-624 TTCL
230KV S/C Line on DC Towers from the
proposed Valeppaneri 230KV SS by M/s.
Suzlon to the existing TRNTRANSCO
Kayathar 230KV SS
230 S/C 21.0 21.0 12-Mar-12 17-Feb-14 1-Apr-13 17-Feb-14
114Tamil
NaiduTN-625 PGCIL
765KV D/C (Hez. Zebra) Tuticorin P/S to
Salem P/S T/L765 D/C 366.8 733.61 20-Nov-12 25-Jul-13 20-Jan-13 25-Jul-13 11-Dec-13 11-Feb-14
115Tamil
NaiduTN-626 PGCIL 400kV D/C vallur to melakottiyar t/l 400 D/C 36 72.00 2-Jan-13 6-Dec-12 6-Dec-12 6-Dec-12 3-Jan-13
116Tamil
NaiduTN-627 PGCIL
765kV S/C line from New Salom - Madguri to
Tuticorin765 S/C 245 245.00 10-Jan-13 25-Sep-13
117Tamil
NaiduTN-628 PGCIL
400kV D/C quad Sehlom pooling station
Salem S/S trans line400 D/C 60.122 120.24 7-Jan-13 29-May-13 11-Feb-13 11-Feb-13 19-Feb-14
118Tamil
NaiduTN-629 RPPL
LILO OF 230kV Myvadi-Othakkalmandapm
feeder-II at the prop aged Regen Anitkhatan230 D/C 4.992 9.98 17-Jan-13 1-Mar-13 1-Mar-13 1-Mar-13 1-Mar-13 1-Mar-13
119Tamil
NaiduTN-630 PGCIL
230kV S/C line on D/C tower from 1X60 mw
thermal power plant ARS Metal ltd
Gumidipondi
230 S/C 6.8 6.80 18-Feb-13 9-Apr-13 27-Feb-13 9-Apr-13 11-Apr-13
120Tamil
NaiduTN-631 PGCIL
400 KV NEW SALEM P/S (Dharmapuri)
S/T/C Somanahalli (earlier AND-578)400 D/C 121.2 242.3 12-Mar-13 21-Jan-14 1-Sep-13 21-Jan-14 21-Feb-14
121Tamil
NaiduTN-632 PGCIL 400 kV D/C Quad Nellore-Thiruvalan T/C 400 D/C 174.5 349.0 17-Jun-13 21-Jan-14 19-Nov-13 21-Jan-14 11-Feb-14
122Tamil
NaiduTN-633 IL&FS
400KV DC Dedicated T/L from IL&FS TN
power project at CUDDALORE TO
POWERGRID P/S AT NAGAPATTINAM
400 D/C 46.2 92.4 2-Jul-13 21-Mar-14 6-Nov-13
123Tamil
naiduTN-634 PGCIL
765 KV S/C KURNOOL - RAICHUR
SHALAPUR T/L765 D/C 116.2 232.3 6-Nov-12
124Tamil
naiduTN-635 PGCIL
LILO of 400kV D/C QUAD RAICHUR-
GOOTY T/L at 765/400kV Raichur(New) S/S400 D/C 5.2 10.4 30-Nov-13 14-Oct-13
125Tamil
naiduTN-636 PGCIL
LILO of both CKT of TUTICORIN JV -
MADURAI 400 kV D/C QUAD T/L at
Tuticorin P/S
400 D/C 2.2 4.4 26-Nov-13 21-Jan-14 18-Feb-14 18-Feb-14 20-Feb-14
SOUTHERN REGION 9 of 10
CEA LD&T DIVISION - STATUS OF PTCC PROPOSALS IN CEA as on 31.03.2014
126Tamil
naiduTN-637 PGCIL
LILO of NEYVELI-TRICHY S/C LINE AT
NAGAPATTINAM P/S400 D/C 22.6 45.2 13-Jan-14 4-Mar-14 24-Mar-14 24-Mar-14 26-Mar-14
127Tamil
naiduTN-638 PGCIL
400KV DC LINE with QUADRUPLE
MOOSE ACSR from KAYATHAR (400KV
SS) TO KARAIKUDI (400KV SS)
400 D/C 192.0 384.0 30-Jan-14
128Tamil
naiduTN-639 TNTCL
230 KV S/C LINE FROM PARUTHIYUR TO
PUGALUR S/S230 S/C 64.0 64.0 6-Feb-14 13-Mar-14
129 Kerala KER-321 PGCIL220kV m/c line from 400kV S/S at PGCIL at
Manukad to 220kV S/S220 D/C 4 8.00 21-Feb-12 21-Feb-12 21-Feb-12 21-Feb-12 22-Feb-12
130 Kerala KER-322 KPTCL220kV m/c line from 400kV S/S at Pallikkra to
220kV S/S Brahamanpuram220 D/C 6.5 13.00 25-May-10 4-Feb-13 20-Jul-10 4-Feb-13 8-Mar-13
131 Kerala KER-323 KSEB220kV M/C line from Katta kada-
Balaramapuram-Vizhiriam220 D/C 22.0 44.00 21-May-13
SOUTHERN REGION 10 of 10
S.
No.State File No.
Name of the
Power
utility
Name of the Power line KVCkt
Type
PL
KM
CKT.
Km.
Date of
receipt of
proposal in
CEA
Date of
receipt of
BSNL
details
Date of
receipt of
Railway
details
Date of IV
comments
sent by
CEA
Approved
on
1 Chattisgarh CHH-20 PGCIL
LILO of 765kV S/C Sipat - Seoni Ckt - I &
Ckt - II line at pooling station 765/400kV
Bharari S/S
765 D/C 15.8 15.83 22-Sep-11 2-Feb-12 2-Jan-12 22-Feb-12
2 Chattisgarh CHH-21 Essar Power 400kV D/C (Quad) line from Mahan - Sipat 400 D/C 336.4 772.88 4-Oct-11 4-Oct-11 24-Oct-11 14-Feb-12
3 Chattisgarh CHH-22Vandana
Vidhyut Ltd.
LILO of 400kV D/C PGCIL line Korba NTPC -
Birsinghpur to M/S Vandana Vidhyut Ltd.,
Korba
400 D/C 3.4 6.74 7-Oct-11 17-Apr-12 27-Feb-12 30-Apr-12 4-May-12
4 Chattisgarh CHH-23 CSPTCL220kV DCDS line from 220/132kV Chhuri
S/S to 220/132kV S/S Mopka220 D/C 90.0 180.00 19-Dec-11
5 Chattisgarh CHH-24 CSPTCL400kV D/C Marwa TPP to Raipur (Raita S/S)
Trans. Line400 D/C 140.8 281.58 12-Jan-12
6 Chattisgarh CHH-25 CSPTCL400kV D/C (MM) Korba West - Khedamara
line to Marwa TPP 2X500MW400 D/C 57.8 115.51 13-Feb-12
7 Chattisgarh CHH-26 GMR400kV D/C Quad GMR Generating Station
Raikheda to Medesara 765/400kV S/S PGCIL400 D/C 62.5 125.07 2-Mar-12 18-Sep-12 3-Apr-12 29-Jan-13
8 Chattisgarh CHH-27 PGCIL400kV D/C Raipur (Kumhari 400/220kV S/S) -
Raipur (Dhamdha 765/400kV S/S)400 D/C 21.5 43.05 2-Apr-12 28-Dec-12 11-Feb-13 18-Mar-13
9 Chattisgarh CHH-28 PGCIL765kV s/c Champa pooling station to
Dharamjaigarh(Korba) t/l765 S/C 58.7 58.70 23-Apr-12 3-Mar-14 29-May-13 11-Mar-14
10 Chattisgarh CHH-29 PGCIL
765kV D/C Champa pooling station-Raipur
pooling station for gen Champa and Raigarh at
Chattisgarh
765 D/C 75.0 150.00 8-May-12 20-Feb-14 10-Jun-13 11-Mar-14
11 Chattisgarh CHH-30 PGCIL765kV D/C Raigarh p5 to Raipur pooling
station765 D/C 241.0 482.05 31-May-12 17-Jan-13 11-Feb-13 25-Oct-13
12 Chattisgarh CHH-31 PGCIL
400kV D/C T/L from 4X300 mw sks power
plant (Chattisgarh)-pooling station at
PGCIL,Bansia s/s
400 D/C 26.7 53.45 18-Jun-12
13 Chattisgarh CHH-32 JINDAL400kV D/C quad t/l from 4X600 mw jpl
Tamnar to PGCIL s/sBhendra,Raigarh400 D/C 23.2 46.40 24-Jul-12 28-Dec-12 21-Dec-12 16-Jan-13
14 Chattisgarh CHH-33 KWPCLLILO of cktI(II) at 400kV D/C Raigarh-Raipur
t/l to KWPCL switchyard 400 D/C 5.3 10.60 25-Jul-12 16-Oct-12 17-Oct-12 25-Oct-12
15 Chattisgarh CHH-34 PGCIL765kV D/C Raigarh(Kotra)-Raigarh(Tamnar)
t/l765 D/C 48.0 96.00 3-Aug-12 28-Dec-12 18-Sep-12 18-Apr-13
CEA LD&T DIVISION - STATUS OF PTCC PROPOSALS IN CEA as on 31.03.2014
WESTERN REGION 1 of 19
S.
No.State File No.
Name of the
Power
utility
Name of the Power line KVCkt
Type
PL
KM
CKT.
Km.
Date of
receipt of
proposal in
CEA
Date of
receipt of
BSNL
details
Date of
receipt of
Railway
details
Date of IV
comments
sent by
CEA
Approved
on
CEA LD&T DIVISION - STATUS OF PTCC PROPOSALS IN CEA as on 31.03.2014
16 Chattisgarh CHH-35 PGCIL 765 s/c Raigarh-Champa pooling Station t/l 765 S/C 96.3 96.29 3-Aug-12 17-Jan-13 12-Mar-14 13-Mar-14
17 Chattisgarh CHH-36 PGCIL 765kV D/C Raipur-Wardha t/l-I part I 765 D/C 120.0 240.00 23-Aug-12 22-Jan-14 10-Dec-13 13-Mar-14
18 Chattisgarh CHH-37 DBPL
400kV D/C line to 2X600 mw power plant at
DBPL at Baradhara to 765kV c/s at
Bansia(Raigarh) of PGCIL
400 D/C 18.8 37.69 6-Sep-12 29-Oct-12 25-Sep-12 1-Nov-12
19 Chattisgarh CHH-38 PGCIL
400kV m/s t/l from Raigarh(Kotra) 400/220kV
PGCIL s/s to Raigarh(Bansia) 765/400kV
PGCIL s/s
400 D/C 6.3 12.58 10-Sep-12 28-Dec-12 14-Mar-12 18-Mar-13
20 Chattisgarh CHH-39 KWPCL400kV D/C line from KWPCL Switchyard to
PGCIL s/s Bansia,Raigarh400 D/C 16.6 33.18 20-Sep-12 16-Oct-12 6-Nov-12 9-Apr-13
21 Chattisgarh CHH-40 SEW
400kV D/C line from 4X300 mw sks Power
generation(Chattisgarh) to upcomming pooling
station of PGCIL at Bansia
400 D/C 26.9 53.81 14-Nov-12 6-Nov-13 6-Nov-13 18-Nov-13 19-Feb-14
22 Chattisgarh CHH-41 CSPTCL400kV D/C transmission line from Korba west
to Khedamara 400 D/C 223.5 447.00 4-Dec-12
23 Chattisgarh CHH-42 DBPL
400kV cktIII of Raigarh-Raipur line for
400kV switchyard of DBPL Badadhara
dist.janjgir Champa(CG)
400 D/C 14.9 29.84 12-Dec-12 22-Feb-13 22-Jan-13 26-Feb-13
24 Chattisgarh CHH-43 PGCIL765kV D/C Jharsuguda-Dharamjaigarh
(Chattisgarh portion only)765 D/C 70.0 140.00 30-Aug-12 17-Jan-13 12-Mar-14 13-Mar-14
25 Chattisgarh CHH-44 TRNEL400kV D/C t/l from TRN TPS to Tammar
pooling station400 D/C 14.2 28.38 1-Mar-13 24-Jul-13 24-Jul-13 26-Jul-13 5-Aug-13
26 Chattisgarh CHH-45 ATHENA 400KV D/C T/L at Janjgir, Champa Distt. 400 D/C 24.4 28.38 29-Apr-13 12-Sep-13 28-Jun-13 3-Jan-14
27 Chattisgarh CHH-46 LANCO 400 KV D/C KORBA-TAGA QUAD T/LINE 400 D/C 46.0 92.03 1-May-13
28 Chattisgarh CHH-47 MCCPL400 KV MCCPL S/S TO existing 400KV D/C
ACBIL T/L BANDAKHAR TO BILASPUR400 D/C 2.8 5.62 23-Jul-13 27-Sep-13 27-Sep-13 27-Sep-13 27-Sep-13
29 Chattisgarh CHH-48 PGCIL765 KV S/C (Delta) RANCHI -
DHARMJAYA GARH (KORBA) T/L765 S/C 164.0 164.00 27-Aug-13
30 Chattisgarh CHH-49 PGCIL765 KV S/C DHARMJAYA GARH
(KORBA) T/L - JABALPUR T/L PART-I765 D/C 153.2 306.46 23-Sep-13
31 Chattisgarh CHH-50 PGCILLILO of 765KV RANCHI SIPAT WR P/S -
DHARMJAYAGARH (Korba)765 D/C 9.0 18.08 30-Sep-13 6-Jan-14 25-Feb-14 11-Mar-14
WESTERN REGION 2 of 19
S.
No.State File No.
Name of the
Power
utility
Name of the Power line KVCkt
Type
PL
KM
CKT.
Km.
Date of
receipt of
proposal in
CEA
Date of
receipt of
BSNL
details
Date of
receipt of
Railway
details
Date of IV
comments
sent by
CEA
Approved
on
CEA LD&T DIVISION - STATUS OF PTCC PROPOSALS IN CEA as on 31.03.2014
32 Chattisgarh CHH-51 Visa Power 765kV PGCDC AT BANSIA RAIGARH 765 D/C 13.0 26.00 14-Nov-13 20-Feb-14 20-Feb-14 26-Feb-14
33 Chattisgarh CHH-52 PGCIL765kV D/C Raipur-Wardha t/l part I line-2
(ckt-1,3,4) CG Portion765 D/C 114.3 228.62 14-Nov-13 10-Mar-14
34 DNH DNH-1 PGCIL
220KV D/C KALA-KHADOLI (through D/C
& M/C) and 220KV D/C KALA-
KHARADPADA (through D/C & M/C) T/L
for feeding Power to U.T. Of DNH from
220 D/C 26.5 53.00 14-Mar-14
35 Gujrat GUJ-599 GETCO
220 kV D/C Tower Line with ACSR 'Zebra'
conductor from 220 kV Dahej S/S to M/s
ONGC
220 D/C 7.5 15.00 17-Apr-08
36 Gujrat GUJ-603 GETCO
220 kV D/C Tower Line with ACSR Zebra
conductor from 220 kV Nanikhakar S/S to
M/s Adani Power Project Ltd. At Vill-Tunda,
Tal-Mundra, Distt-Kutchchh
220 D/C 18.0 36.00 26-Aug-08 30-Apr-10 5-Jul-11 19-Jun-12
37 Gujrat GUJ-606 GETCO
220 kV D/C Tower Line with ACSR 'Zebra'
conductor from 220 kV Mangrol S/S to 220
kV Mobha S/S.
220 D/C 110.0 220.00 16-Feb-09 7-Dec-09 17-Feb-11
38 Gujrat GUJ-612 GETCO
220 kV LILO line to proposed 220 kV
Kangasiyali S/S from existing 220 kV Gondal-
Rajkot tower line
220 D/C 14.0 28.00 17-Mar-09 6-Jul-09 3-Mar-11 28-May-12
39 Gujrat GUJ-613 GETCO400kV D/C Vadinar (Essar)-Hadala (Rajkot)
S/S400 D/C 112.0 224.00 31-Mar-09 14-Jan-10 13-Aug-12
40 Gujrat GUJ-614 GETCO220 kV D/C Varsana - 220 kV Morbi line with
ACSR Zebra conductor220 D/C 107.0 214.00 1-May-09 6-Jul-09 11-Feb-11
41 GujratGUJ-
620A
Torrent
Energy
220 kV D/C Line from Dahej SEZ Tele
Generating Station to 220/33kV GETCO West
S/S at Dahej
220 D/C 7.4 14.80 18-Jun-09 1-Dec-09 17-Dec-09 1-Mar-12
42 GujratGUJ-
620B
Torrent
Energy
220 kV D/C Line from Tele Generating Station
Sly to 220/66kV GETCO S/S at Dahej220 D/C 3.4 6.80 18-Jun-09 1-Dec-09 17-Dec-09 1-Mar-12
43 GujratGUJ-
620C
Torrent
Energy
220 kV D/C Line from Tele Generating Station
S/Y Dahej to Opal at Dahej SEZ220 D/C 2.0 4.00 18-Jun-09 1-Dec-09 1-Dec-09 1-Mar-12
44 GujratGUJ-
620D
Torrent
Energy
220 kV D/C Line 220/33kV Dahej West S/S to
ONGC C2-C3 at Dahej SEZ220 D/C 1.2 2.40 18-Jun-09 1-Dec-09 17-Dec-09 1-Mar-12
45 Gujrat GUJ-615 GETCO 220kVS/C Nanikhakher-Coastal Guj Power 220 S/C 18.0 18.00 24-Jun-09 10-Jun-09 24-Jun-09 2-Jan-13
WESTERN REGION 3 of 19
S.
No.State File No.
Name of the
Power
utility
Name of the Power line KVCkt
Type
PL
KM
CKT.
Km.
Date of
receipt of
proposal in
CEA
Date of
receipt of
BSNL
details
Date of
receipt of
Railway
details
Date of IV
comments
sent by
CEA
Approved
on
CEA LD&T DIVISION - STATUS OF PTCC PROPOSALS IN CEA as on 31.03.2014
46 Gujrat GUJ-608 GETCO
220 kV D/C tower line with Zebra conductor
from 220 kV Shivlakha S/S to Wind Farm S/S
of M/s Vestas-RRB India Tech. Pvt. Ltd. At
Village-Vandhiya, Tal-Bhachau, Distt-
Kutchchh
220 D/C 44.0 88.00 10-Aug-09 17-Feb-09 24-Feb-09
47 Gujrat GUJ-627 PGCIL400 kV D/C Gandhar (Jhanor, near Bharuch)-
Navasari (Dastan, near Bardoli) T/L.400 D/C 101.5 202.94 3-Dec-09 23-Apr-10 17-Jan-12 13-Feb-12 28-Feb-12
48 Gujrat GUJ-633 GETCO220 kV D/C line from Utran gas power plant
to 400 kV Kosamba S/S.220 D/C 43.0 86.00 11-Jun-10 23-Jul-10
49 Gujrat GUJ-634 GETCO
220 kV D/C tower line with AL-59 conductor
from 400 kV Varsana S/S to 220 kV Tappar
S/S
220 D/C 4.0 8.00 11-Jun-10 26-Jul-10 12-Oct-12 19-Mar-14
50 Gujrat GUJ-635 GETCO
220 kV D/C tower line from 220 kV
Nakhatrana S/S to 400 kV Varsana (Tappar)
S/S with AL-59 conductor, Taluka-
Anjar,Distt. -Kutchchh,Gujarat.
220 D/C 106.8 213.56 29-Jun-10 3-Nov-10 12-Jul-12 14-Jan-13
51 Gujrat GUJ-636 GETCO220 kV LILO to Bhat S/S from 220 kV D/C
Salejada-Viramgam line on Zebra conductor.220 D/C 17.8 35.63 9-Jul-10 23-Jul-10
52 Gujrat GUJ-637 GETCO220 kV LILO to 220 kV Lalpar S/S from
existing 220 kV Morbi-Dhrangadhra line220 D/C 6.7 13.40 15-Jul-10 23-Sep-10 3-May-11 10-May-12
53 Gujrat GUJ-639 GETCO220kV D/C Viramgam-Chharodi(Nano)
Tower Line220 D/C 26.9 53.80 15-Sep-10 23-Sep-10 10-May-12
54 Gujrat GUJ-640 GETCO220kV D/C Morbi-Halwad Line LILO at
Bhimasar Line-1220 D/C 108.0 216.00 26-Oct-10 12-Jan-11 1-Jun-12
55 Gujrat GUJ-641 GETCO220kV D/C Morbi-Halwad Line LILO at
Bhimasar Line-2220 D/C 107.0 214.00 26-Oct-10 12-Jan-11 27-Feb-12
56 Gujrat GUJ-642 GETCO
220kV D/C Tower Line (LILO) to proposed
220kV Batad S/S from 220kV D/C Kasor-
Vartej main line
220 D/C 20.0 40.00 26-Oct-10 12-Jan-11
57 Gujrat GUJ-643 GETCO400kV D/C LILO Line from existing Ukai
TPS-Asoj Line at 400kV Kosamba S/S400 D/C 32.0 64.00 26-Oct-10 23-May-11 12-Jul-12 6-Dec-12
58 Gujrat GUJ-644 GETCO 400kV D/C Mundra-Zerda Tx. Line -2 400 D/C 330.6 661.13 9-Dec-10 31-Jan-13
59 Gujrat GUJ-630 GETCO 220 kV D/C Kheralu-Bhutiya Line 220 D/C 99.8 199.52 25-Jan-11 7-Dec-09 3-Mar-11
WESTERN REGION 4 of 19
S.
No.State File No.
Name of the
Power
utility
Name of the Power line KVCkt
Type
PL
KM
CKT.
Km.
Date of
receipt of
proposal in
CEA
Date of
receipt of
BSNL
details
Date of
receipt of
Railway
details
Date of IV
comments
sent by
CEA
Approved
on
CEA LD&T DIVISION - STATUS OF PTCC PROPOSALS IN CEA as on 31.03.2014
60 Gujrat GUJ-607 GETCO220kV D/C Vapi-Bhilad LILO at 400 kV
Ambheti (PGCIL) S/S.220 D/C 8.0 16.00 3-Mar-11 3-Mar-11 3-Mar-11 6-Dec-12
61 Gujrat GUJ-609 GETCO220 kV D/C Vav-Ukai line LILO at 220 kV
Mota (Bardoli) S/S220 D/C 4.3 8.58 3-Mar-11 3-Mar-11 17-Feb-09 20-Mar-14
62 Gujrat GUJ-645 GETCO33kV D/C Pri-pole X- Electrod line from
Adani power plant Siracha to Dhokda33 D/C 32.1 64.23 25-Jul-11
63 Gujrat GUJ-646 torrent powerLILO of one circuit of 400kV SUGEN -
PIRANA line at UNOSUGEN400 D/C 1.2 2.38 4-Nov-11 16-Feb-12 14-Feb-12 22-Feb-12
64 Gujrat GUJ-647 GETCO 220kV D/C Kosamba - Mobha power line 220 D/C 89.0 178.00 6-Feb-12 30-Apr-12 12-Jul-12
65 Gujrat GUJ-649 torrent power400kV DC & MC triple snowbird from
degenrating station Dahej to 400kV Navsari400 D/C 105.0 210.00 11-May-12 14-Sep-12 14-Sep-12 26-Sep-12
66 Gujrat GUJ-648 PGCIL 400kV DC Navsari-Boisar T/L 400 D/C 106.1 212.10 14-May-12 27-Aug-12 27-Aug-12 8-Nov-12
67 Gujrat GUJ-650 GETCO 400kV DC Wakai -Kosamba line 400 D/C 72.0 144.00 22-May-12 17-Sep-12 16-Jul-12
68 Gujrat GUJ-651 GETCO220kV LILO line from 220kV Navsari-Vav to
220kV Popda s/s220 D/C 8.2 16.42 28-May-12 29-May-13
69 Gujrat GUJ-652 GETCO220kV DC line from 400kV Kosamba S/S -
TO -220kV Jagadia220 D/C 24.0 48.00 1-Jun-12 9-Apr-13 21-Dec-12
70 Gujrat GUJ-653 GETCO 220kv DC line from GSEG to Mota 220 D/C 59.0 118.00 1-Jun-12 9-Apr-13
71 Gujrat GUJ-654 GETCO 220kV DC line from Kosamba to Mobha 220 D/C 4.5 9.00 1-Jun-12
72 Gujrat GUJ-655 GETCO220kV LILO on M/C-D/C tower from existing
220kV Haldarwa IPCL line 220 D/C 3.6 7.10 1-Jun-12 12-Oct-12
73 Gujrat GUJ-656 PGCIL 400kV DC Pirana to vadodra T/L 400 D/C 132.0 264.00 30-Jul-12 26-Feb-13 27-May-13 28-Jun-13
74 Gujrat GUJ-657 PGCIL 400kV DC quad vadodra-asoj T/L line 400 D/C 14.4 28.87 31-Dec-12 26-Feb-13 20-Jun-13 28-Jun-13
75 Gujrat GUJ-658 GETCO220kV DC transline from TEBHDA-Enercom
wind from s/s 220kV Nyara s/s 220 D/C 89.6 179.19 3-Jan-13 29-May-13
76 Gujrat GUJ-659 GETCO220kV Ukheda Suslon s/s to 400kV Varsana
tappar220 S/C 130.5 130.53 3-Jan-13 29-May-13
77 Gujrat GUJ-660 GETCO 220kV Jamanvada - Suslan to 400kV Varsna 220 S/C 179.9 179.90 3-Jan-13 29-May-13
WESTERN REGION 5 of 19
S.
No.State File No.
Name of the
Power
utility
Name of the Power line KVCkt
Type
PL
KM
CKT.
Km.
Date of
receipt of
proposal in
CEA
Date of
receipt of
BSNL
details
Date of
receipt of
Railway
details
Date of IV
comments
sent by
CEA
Approved
on
CEA LD&T DIVISION - STATUS OF PTCC PROPOSALS IN CEA as on 31.03.2014
78 Gujrat GUJ-661 GETCO200kV Kalavad to Kangasiyali line on DC
tower 200 D/C 56.0 112.00 3-Jan-13 29-May-13
79 Gujrat GUJ-662 GETCO220kV LILO at 400kV Hadalar s/s from
existing 220kv nayara-kangashiyali line 220 D/C 17.0 34.00 3-Jan-13 29-May-13 16-Aug-13
80 Gujrat GUJ-663 GETCO400kV DC Kasamba to Charanja line twin
moose conductor 400 D/C 229.2 458.40 3-Jan-13 20-Sep-13
81 Gujrat GUJ-664 GETCO220kV LILO at 220kV Sartanpar s/s from
existing 220kV DC Hardala-Halwad line 220 D/C 13.0 26.00 2-Jan-13 29-May-13 22-Aug-13
82 Gujrat GUJ-665 PGCIL765kV indore - Vadodra part of indore -
Vadodra tl part II765 S/C 315.0 315.00 21-Jan-13 7-Oct-13 19-Aug-13 24-Dec-13
83 Gujrat GUJ-666 PGCIL400 Kv M/C LILO of both ckt of NAVSARI-
BOISAR T/L at MAGARWADA GIS S/S400 D/C 15.9 31.72 21-Feb-13 27-May-13 14-Nov-13 19-Nov-13
84 Gujrat GUJ-667 GETCEL220kV OPG project Bahadareshwar.ta
Mundra dist Bhuj to 400kV Varsana tapper ss220 D/C 56.7 113.38 9-Apr-13
85 Gujrat GUJ-668 PGCIL400 KV D/C T/L from Betul(New s/s)-
Khandwa(s/s)400 D/C 168.5 336.97 30-Jun-13
86 Gujrat GUJ-669 PGCIL400kV D/C ESSAR TPS (JAMNAGAR)
BACHHAU S/S T/L.400 D/C 225.1 450.20 2-Jul-13 23-Jul-13
87 Gujrat GUJ-670 PGCILBHACHAU S/S(PGCIL) -
VARSANA(GETCO) T/L400 D/C 9.1 18.20 30-Oct-13 6-Dec-13 25-Nov-13
88 Gujrat GUJ-671 GETCO
220 KV D/C & M/C LILO FROM
SAVARKUNDLA - OTHA LINE NO. 1 at
GPPC PLANT
220 D/C 45.3 90.52 18-Feb-14
89 Gujrat GUJ-672 GETCO 220KV D/C OTHA - SAGAPARA T/L 220 D/C 48.0 96.00 20-Feb-14
90 Gujrat GUJ-673 GETCO
1) 220KV LILO from existing BHIMASAR-
LAIPAR T/LTO SARTANPAR S/S 2)132KV
LILO from 132kv LALPAR-WANKANER
LINE(ON 220KV M/C TOWER) TO
SARTANPAR
220 D/C 8.6 17.26 3-Mar-14
91 Gujrat GUJ-674 GETCO
132 KV LILO to PADAVALA S/S from
Existing 132KV PALIYAD-VIKRAM Line on
D/C tower
132 D/C 2.0 4.00 6-Mar-14
WESTERN REGION 6 of 19
S.
No.State File No.
Name of the
Power
utility
Name of the Power line KVCkt
Type
PL
KM
CKT.
Km.
Date of
receipt of
proposal in
CEA
Date of
receipt of
BSNL
details
Date of
receipt of
Railway
details
Date of IV
comments
sent by
CEA
Approved
on
CEA LD&T DIVISION - STATUS OF PTCC PROPOSALS IN CEA as on 31.03.2014
92 Gujrat GUJ-675 GETCO
220KV D/C LILO to PS-2 (OF SSNNL - at
NANI HAMIRPAR) from SHIVLAKHA-
DEODAR Line
220 D/C 27.7 55.3 6-Mar-14
93 Gujrat GUJ-676 GETCO220KV HALVAD-SADIA Line on D/C tower
Line 220 D/C 37.6 75.2 14-Mar-14
94 Gujrat GUJ-677 GETCO220KV D/C LILO TO PS-3 (OF SSNNL - at
BHACHAU) from TAPPAR-SHIVLAKHA 220 D/C 1.4 2.9 10-Mar-14
95 Gujrat GUJ-678 GETCO
220KV D/C T/L from PS-2 (of SSNNL-at
Nani Hamirpar) to PS-1 (of SSNNL-at
Manjuvas)
220 D/C 10.3 20.5 10-Mar-14
96 Gujrat GUJ-679 GETCO220KV MOKHA - VARSANA Line on D/C
& M/C Tower220 D/C 57.8 115.7 10-Mar-14
97 Gujrat GUJ-680 GETCO
220KV MOKHA (VADALA S/S) from
Existing 220 KV Nani Khakhar-Tappar Line
no. 1
220 D/C 10.4 20.8 10-Mar-14
98 Gujrat GUJ-681 GETCO
400kv MUNDRA - HADALA LILO at
proposed 400kv HALVAD S/S on D/C tower
Line
400 D/C 45.0 90.0 14-Mar-14 5-Jan-00
99 Gujrat GUJ-682 GETCO220KV D/C LILO TO SUVA FROM
KOSAMBA-MOBHA LINE220 D/C 56.0 112.0 25-Mar-14
100 Gujrat GUJ-683 GETCO220KV D/C HALWVAD-HADALA Line on
D/C Tower 220 D/C 84.7 169.3 25-Mar-14
101 Gujrat GUJ-684 GETCO220KV S/C CHORANIA - GONDAL LINE
LILO AT 220KV SADLA S/S220 D/C 29.2 58.4 31-Mar-14
WESTERN REGION 7 of 19
S.
No.State File No.
Name of the
Power
utility
Name of the Power line KVCkt
Type
PL
KM
CKT.
Km.
Date of
receipt of
proposal in
CEA
Date of
receipt of
BSNL
details
Date of
receipt of
Railway
details
Date of IV
comments
sent by
CEA
Approved
on
CEA LD&T DIVISION - STATUS OF PTCC PROPOSALS IN CEA as on 31.03.2014
102 Gujrat GUJ-685 GETCO220 KV LILO FROM 220KV JETPUR TO
SIKKA S/S JAMNAGAR LINE -I220 D/C 60.0 120.0 31-Mar-14
103Madhya
PradeshMP-339 PGCIL 400kV D/C Indore - Indore (Quad) 400 D/C 49.7 99.46 29-Mar-10 11-Feb-11 17-Jan-12 13-Feb-12 28-Feb-12
104Madhya
PradeshMP-340 PGCIL 765kV S/C Bina - Indore 765 S/C 316.0 316.00 29-Mar-10 14-Dec-11 24-Nov-10 23-Feb-12 28-Feb-12
105Madhya
PradeshMP-341 PGCIL 765kV S/C Bina - Satna Line Ckt-I 765 S/C 274.0 274.00 17-Apr-10 28-Nov-11 24-Nov-10 3-Jan-12 10-Jan-12
106Madhya
PradeshMP-343 PGCIL 765kV S/C Satna-Bina Line Ckt-II 765 S/C 276.0 276.00 11-May-10 28-Nov-11 24-Nov-10 3-Jan-12 10-Jan-12
107Madhya
PradeshMP-345 PGCIL
765kV S/C Sasan-Satna Transmission Line
Ckt-I765 S/C 246.0 246.00 16-Aug-10 25-Apr-11 5-Dec-11 8-Feb-12
108Madhya
PradeshMP-346 MPPTCL
220kV DCDS Line for LILO of one circuit of
220kV DCDS Satana-Bansagar(Tons) for
proposed 220kV S/s Kotar
220 D/C 4.3 8.58 10-Sep-10 28-Dec-12
109Madhya
PradeshMP-347 PGCIL
765kV S/C Sasan-Satna Ckt-II Transmission
Line asociated with SASAN UMPP for
Western Region
765 S/C 244.0 244.00 14-Sep-10 25-Apr-11 5-Dec-11 8-Feb-12
110Madhya
PradeshMP-348 MPPTCL
220kV DCSS Line from 220kV S/s Sidhi for
P.S. to Mohan Aluminium Project Plant of M/s
Hindalco Industries at Bargawan Distt.
Singarauli
220 D/C 80.0 160.00 23-Sep-10 20-Apr-11 23-Feb-11 25-Jun-12
111Madhya
PradeshMP-352 PGCIL
LILO of one circuit of 220kV Bina - Shivpuri
line at Bina (PGCIL) 400kV S/S220 D/C 0.8 1.66 27-Sep-11 28-Dec-12 12-Jul-12 22-Oct-13
112Madhya
PradeshMP-351 MPPTCL
220kV DCSS Line from S/S at M/S Jaiprakash
Associates Ltd, Rewa to 220kV S/S Rewa
(Silpra) at MPPTCL
220 D/C 1.0 2.02 8-Nov-11 27-Feb-12 9-Jul-12 23-Mar-14
113Madhya
PradeshMP-353 MPPTCL
220kV D/C Malwa (Singhaji) TPH -
Chhegaon 220kV DCDS line220 D/C 47.9 95.79 12-Dec-11 27-Feb-12 10-Jul-12
114Madhya
PradeshMP-354 MPPTCL
LILO of 220kV DCDS Nagda - Neemuch line
for 220kV Daloda S/S220 D/C 4.4 8.80 29-Dec-11 17-Jan-13
115Madhya
PradeshMP-355 MPPTCL
400kV DCDS line from Malwa (Singhaji) TPS
- Chhegaon 400kV S/S400 D/C 52.3 104.69 10-Jan-12 31-Jan-13 22-Oct-12
WESTERN REGION 8 of 19
S.
No.State File No.
Name of the
Power
utility
Name of the Power line KVCkt
Type
PL
KM
CKT.
Km.
Date of
receipt of
proposal in
CEA
Date of
receipt of
BSNL
details
Date of
receipt of
Railway
details
Date of IV
comments
sent by
CEA
Approved
on
CEA LD&T DIVISION - STATUS OF PTCC PROPOSALS IN CEA as on 31.03.2014
116Madhya
PradeshMP-356 MPPTCL
220kV DCDS line from 400kV S/S PGCIL
Satna to 220kV S/S Satna MPPTCL220 D/C 2.0 4.00 23-Jan-12 10-Apr-12 10-Apr-12 24-Mar-14
117Madhya
PradeshMP-357 MPPTCL
220kV DCDS line from Gwalior (400kV)
PGCIL S/S to Gwalior-II 220kV S/S220 D/C 2.4 4.73 7-Mar-12 17-Jan-13 2-Jul-12
118Madhya
PradeshMP-358 MPPTCL
220kV DCSS line from 220kV S/S Ratlam to
220kV S/S Daloda220 D/C 75.0 150.00 21-Mar-12 28-Dec-12
119Madhya
PradeshMP-359 PGCIL
400kV D/C power line from Vindhyachal
(NTPC) - Vindhyachal pooling station400 D/C 29.3 58.56 13-Mar-12 2-Feb-12 6-Jul-12 27-Aug-12
120Madhya
PradeshMP-360 MPPTCL 400kV DCDS line from Malwa -Pithampur 400 D/C 135.9 271.70 7-May-12 28-Oct-13
121Madhya
PradeshMP-361 MPPTCL
400kV DCDS Chhegaon-400kV s/s
Jhulwahiya400 D/C 112.6 225.14 7-May-12 16-Jul-12
122Madhya
PradeshMP-362 PGCIL 765kV s/c Bhopal-Indore 765 S/C 174.0 174.00 1-Jun-12 19-Jun-13 19-Jun-13 26-Jul-13
123Madhya
PradeshMP-363 Jaypee
400kV DC quad line JNSTPP Nigari-PGCIL
s/s Satna400 D/C 156.0 312.00 24-Jul-12 28-Dec-12 26-Oct-12 7-Feb-13 3-Mar-13
124Madhya
PradeshMP-364 Sterlite 765kV s/s Jabalpur to bhopal 765 S/C 260.4 260.38 27-Jul-12 8-Mar-13 27-Dec-12 24-Jul-13
125Madhya
PradeshMP-365 PGCIL 765kV s/s Satna - Gwalior cktII 765 S/C 342.0 341.96 27-Aug-12 19-Feb-13 12-Feb-13 16-Apr-13 30-Apr-13
126Madhya
PradeshMP-366 PGCIL 765kV S/c Bina-Gwalior cktIII 765 S/C 231.0 231.00 10-Sep-12 30-Oct-13 23-Oct-13 13-Jan-14
127Madhya
PradeshMP-367 MDTCL
400kV quad line from bhopal s/s(BDTCL)-
Bhopal s/s(MPPTCL) Sukhisawaniya400 D/C 7.4 14.80 18-Sep-12 31-Jan-13 26-Dec-12 5-Jun-13
128Madhya
PradeshMP-368 PGCIL 400kV DC Annuppur - Jabalpur T/L 400 D/C 240.0 480.00 19-Nov-12 19-Aug-13 23-Jul-13 11-Feb-14
129Madhya
PradeshMP-369 PGCIL 400kV dc Jabalpur pool-Jabalpur tl 400 D/C 15.5 30.90 14-Nov-12 19-Aug-13 20-Jun-13 11-Oct-13
130Madhya
PradeshMP-370 PGCIL 765kV dc Jabalpur poal - Bina tl 765 D/C 229.1 458.22 19-Nov-12 19-Aug-13 16-Jul-13 25-Oct-13
131Madhya
PradeshMP-371 PGCIL
765kV DC Dharamjaigarh-Jabalpur pooling
SS T/l 765 D/C 384.0 768.00 19-Nov-12 7-Oct-13 19-Jun-13
132Madhya
PradeshMP-372 MPPTCL
400kV DCDS from 400kV s/s Pithampur-
765/400kV s/s Indore400 D/C 63.6 127.20 26-Dec-12 4-Sep-13
WESTERN REGION 9 of 19
S.
No.State File No.
Name of the
Power
utility
Name of the Power line KVCkt
Type
PL
KM
CKT.
Km.
Date of
receipt of
proposal in
CEA
Date of
receipt of
BSNL
details
Date of
receipt of
Railway
details
Date of IV
comments
sent by
CEA
Approved
on
CEA LD&T DIVISION - STATUS OF PTCC PROPOSALS IN CEA as on 31.03.2014
133Madhya
PradeshMP-373 PGCIL 765kV s/c Satna-Gwalior cktI transline 765 S/C 300.0 300.00 26-Feb-13 19-Feb-13 12-Feb-13 16-Apr-13 30-Apr-13
134Madhya
PradeshMP-374 PGCIL
400kV D/C Barda(Seoni)-New Pooling s/s at
Jabalpur T/L400 D/C 64.6 129.28 20-Feb-13 8-Jul-13 8-Jul-13 18-Jul-13
135Madhya
PradeshMP-375 BDTCL
765kV S/C T/L from 765kV-Dhule S/S to
Aurangabad 765 S/C 192.0 384 16-Apr-13 27-Jun-13 26-Jun-13 16-Jul-13
136Madhya
PradeshMP-376 BDTCL
400kV T/L from 400kV Dhule S/S to Dhule
S/S 400 S/C 17.8 17.8 16-Apr-13 28-Mar-13 30-May-13 3-Jul-13
137Madhya
PradeshMP-377 BDTCL 765kV Dhule S/S to Vadodara S/S(Gujrat) 765 S/C 262.0 262 16-Apr-13 27-Jun-13 30-May-13 11-Jul-13
138Madhya
PradeshMP-379 PGCIL
765 kV S/C & D/C Gwalior Jaipur T/C circuit-
1765 D/C 115.8 231.54 13-Jun-13 27-Mar-14 23-Oct-13
139Madhya
PradeshMP-380 PGCIL 765 kV S/C(Quad) Gwalior-Jaipur Circuit -2 765 S/C 117.2 234.31 13-Jun-13 27-Mar-14 10-Feb-14
140Madhya
PradeshMP-378 JTCL
765kV D/C Dharamjaygah(Korba)-Jabalpur
T/L765 D/C 376.4 752.86 23-Jul-13 6-Feb-14 16-Jul-13
141Madhya
PradeshMP-381 BACL
400KV D/C T/L from KORBA (BALCO 1200
MW Power plant) TO BHARAMJAGARH
P/S (PGCIL 765/400 KV)
400 D/C 21.9 43.858 6-Aug-13
142Madhya
PradeshMP-382 PGCIL
765 KV S/C VINDHYACHAL P/S T/L
CKT-I765 S/C 247.0 247.0 26-Aug-13 3-Dec-13
143Madhya
PradeshMP-383 PGCIL
766 KV S/C VINDHYACHAL P/S T/L
CKT-II765 S/C 96.5 96.5 26-Aug-13 3-Dec-13
144Madhya
PradeshMP-384 MPPTCL
LILO of one Ckt of 220kV DCDS
BHOPAL - ASHTA line at proposed
220kV S/s Mungaliya Chhap
220 D/C 24.7 49.33 6-Jan-14
145Madhya
PradeshMP-385 MPPTCL
220 KV DCSS LINE FROM DALODA
S/S TO BHATKHEDA S/S AT DISST.
RATLAM(M/s.D.J.ENERGY PVT.
LTD.)
220 D/C 20.4 40.72 11-Feb-14
146 Maharastra MRA-907 AIRTELBharti Airtel Shriman Complex to Mangaon
Telephone Exchange220 D/C 1.3 2.50 8-Jun-09
WESTERN REGION 10 of 19
S.
No.State File No.
Name of the
Power
utility
Name of the Power line KVCkt
Type
PL
KM
CKT.
Km.
Date of
receipt of
proposal in
CEA
Date of
receipt of
BSNL
details
Date of
receipt of
Railway
details
Date of IV
comments
sent by
CEA
Approved
on
CEA LD&T DIVISION - STATUS OF PTCC PROPOSALS IN CEA as on 31.03.2014
147 Maharastra MRA-908 MSETCL220kV D/C Lamboti (Solapur) - Tuljapur
power line. 220 D/C 38.0 76.00 27-Jul-09 1-Dec-09 9-Apr-12 4-Oct-12 28-Dec-12
148 Maharastra MRA-911 MSETCL220kV D/C LILO on M/s Seerum Intitute of
India Ltd from 220kV Theur-Magarpatta 220 D/C 1.0 2.00 18-Aug-09 7-Sep-09 9-Jul-09
149 Maharastra MRA-912 MSETCL220kV D/C Tap line for M/s Blue Ridge from
220kV Phursungi-Chinchwad 220 D/C 0.5 1.00 18-Aug-09 1-Feb-10
150 Maharastra MRA-913 MSETCL220kV D/C LILO for Kudus from 220kV
Padghe - Wada 220 D/C 13.0 26.00 18-Aug-09
151 Maharastra MRA-924 PGCIL 400kV Solapur-Kolhapur 400 D/C 219 438.00 25-Sep-09 17-Oct-11 17-Nov-11 23-Apr-12 12-Jun-12
152 Maharastra MRA-916 MSETCL220kV LILO to Baramati Agro from 220kV
Baramati-Bhigavam220 D/C 8.4 16.80 4-Nov-09 5-Nov-09 10-May-10
153 Maharastra MRA-919 MSETCL 220kV Murad-Girwali 220 D/C 93.08 186.16 9-Nov-09 18-Mar-10
154 Maharastra MRA-920 MSETCL LILO of 220kV Murud-Girawali to Harangal 220 D/C 70 140.00 9-Nov-09 18-Mar-10
155 Maharastra MRA-921 MSETCL220kV D/C LILO of Padghe-Kamba to
Rajlaxmi S/C220 D/C 9.68 19.36 10-Nov-09 6-Feb-14
156 Maharastra MRA-931 PGCIL400kV D/C Vapi - KALA (orginally Navi
Mumbai)400 D/C 360 720.00 31-Dec-09 26-Jul-10 6-Feb-14
157 Maharastra MRA-932MAHATRA
NSCO220kV M/C Paras - Balapur 220 D/C 5 10.00 18-Jan-10 20-Apr-11 23-Apr-10 16-Feb-12
158 Maharastra MRA-933 PGCIL 400kV D/C Parli - Pune 400 D/C 323 646.00 21-Jan-10 10-Aug-11 17-Nov-11
159 Maharastra MRA-937 MSETCL
220kV D/C Tap (LILO) Line for Bhosri-II S/S
from Ex. 220kV TELCO S/S - Bhosri-I S/S
Line
220 D/C 0.04 0.08 26-Feb-10 15-Mar-11 13-Jan-12 2-Mar-12 19-Mar-12
160 Maharastra MRA-940MAHATRA
NSCO
Conversion of 220 kV S/C to D/C Chalisgaon-
Bhabhaleshwar Transmission line up to
Kopargaon Tap point No. 26
220 D/C 74.63 149.26 28-Jun-10 11-Feb-11 15-Mar-11 11-Jan-12 24-Jan-12
161 Maharastra MRA-945MAHATRA
NSCO
220 kV D/C line from Akola (Apatapa) to
Anjangaon.220 D/C 52 104.00 2-Jul-10 20-Apr-11 20-Nov-11 7-Mar-12
162 Maharastra MRA-949 Mahatransco 220 kV D/C Parbhani - Shelu line. 220 D/C 53.878 107.76 17-Aug-10 24-Nov-10
163 Maharastra MRA-950 Mahatransco 220 kV D/C Paranda - Barshi line 220 D/C 36.853 73.71 17-Aug-10 31-Jan-13 15-Feb-13 19-Jul-13
WESTERN REGION 11 of 19
S.
No.State File No.
Name of the
Power
utility
Name of the Power line KVCkt
Type
PL
KM
CKT.
Km.
Date of
receipt of
proposal in
CEA
Date of
receipt of
BSNL
details
Date of
receipt of
Railway
details
Date of IV
comments
sent by
CEA
Approved
on
CEA LD&T DIVISION - STATUS OF PTCC PROPOSALS IN CEA as on 31.03.2014
164 Maharastra MRA-952 Mahatransco 220 kV D/C Nanded - Bhokar line. 220 D/C 36.4 72.80 20-Aug-10 23-Feb-11 24-Nov-10 28-Mar-12
165 Maharastra MRA-954 MSETCL
220kV D/C LILO line from Kandalgaon-
Khalapur line for M/s Top Worth S/s at
Khalapur
220 D/C 0.483 0.97 13-Jan-11 22-Sep-10 2-Dec-10 19-Mar-14
166 Maharastra MRA-955 Mahatransco
220kV D/C LILO Lineon proposed 220kV
Sawangi-Bhokordon Line for 220kV Phulambi
S/S
220 D/C 10.8 21.60 1-Oct-10 12-Jul-12 6-Jan-12 4-Sep-12 27-Oct-12
167 Maharastra MRA-959 MSETCL220kV LILO line from Satara - Vankusawada
line for M/s Ajinkyatara SSK Ltd. Dist.Satara220 D/C 2.996 5.99 3-Mar-11 20-Jun-11 21-Jun-11
168 Maharastra MRA-960GMR/
EMCO
400kV D/C EMCO TPS Warora - Bhadrawati
power line400 D/C 33.3 66.60 3-Mar-11 20-Jun-11 26-Jul-12 30-Jul-12
169 Maharastra MRA-961 Mahatransco220kV D/C LILO on Kandalgaon - Kharghar
for Villebagad s/s220 D/C 6.606 13.21 15-Mar-11 10-Aug-11 15-Jan-12 7-Feb-12 9-Feb-12
170 MaharastraMRA-
962AMSETCL 220kV D/C Balapur S/S to Malegaon S/S Line 220 D/C 70 140.00 15-Apr-11 20-Mar-14 11-Jan-12
171 Maharastra MRA-964 MSETCL 220kV D/C Koradi - Khaparkheda II S/S 220 D/C 14 28.00 3-May-11 13-Aug-12 23-May-11 10-Jan-14
172 Maharastra MRA-965 MSETCL 400kV D/C Chandrapur II S/S to Wardha S/S 400 D/C 123 246.00 3-May-11 3-Oct-11 19-Mar-12 30-Apr-12 25-Jun-12
173 Maharastra MRA-966 MSETCL 220kV M/C Koradi II S/S - Butibori III S/S 220 D/C 53 106.00 3-May-11 13-Aug-12 23-May-11 14-Jan-13
174 Maharastra MRA-967 MSETCL 400kV D/C Koradi II S/S - Wardha S/S 400 D/C 119 238.00 3-May-11 13-Aug-12 3-Oct-12 22-Mar-13
175 Maharastra MRA-970 Reliance220kV D/C Line from Rinta-T Aarey to Saki
EHV S/S220 D/C 4.06 8.12 17-Jun-11 21-Feb-12 21-Feb-12 24-May-12 7-Jun-12
176 Maharastra MRA-971 PGCIL400kV D/C (Quad) Mouda (Generating
station) - Wardha400 D/C 123.95 247.90 24-Jun-11 7-Oct-11 6-Feb-12 10-Feb-12
177 Maharastra MRA-972 MEGPTCL 400kV D/C Akola-II to Akola-I Line 400 D/C 29.74 59.44 22-Jul-11 26-Jul-12 16-May-12 11-Sep-12 6-Nov-12
178 Maharastra MRA-973 MSETCL220kV D/C LILO line from existing pusad -
Nanded line fro Ghatodi S/S220 D/C 16 32.00 9-Aug-11 29-Oct-12 10-Apr-11 14-Jan-13
179 Maharastra MRA-975 MSETCL 220kV D/C Deoli S/S to Ghatodi S/S 220 D/C 161 322.00 11-Aug-11 29-Oct-12 21-Aug-13
180 Maharastra MRA-977 MSETCL400kV D/C Chandrapur II S/S to Tadali
(Dhariwal Power Plant)400 D/C 8.6 17.20 16-Aug-11 3-Oct-11 10-Jan-13 14-Feb-13
WESTERN REGION 12 of 19
S.
No.State File No.
Name of the
Power
utility
Name of the Power line KVCkt
Type
PL
KM
CKT.
Km.
Date of
receipt of
proposal in
CEA
Date of
receipt of
BSNL
details
Date of
receipt of
Railway
details
Date of IV
comments
sent by
CEA
Approved
on
CEA LD&T DIVISION - STATUS OF PTCC PROPOSALS IN CEA as on 31.03.2014
181 Maharastra MRA-978 MSETCL
220kV D/C Line from M/S Vidarbha
Industries Power Ltd (MS/VIL) at Buttibori
MIDC to 220kV Buttibori II S/S (Phase-I)
220 D/C 1.2 2.40 16-Aug-11 4-Oct-11
182 Maharastra MRA-979
MEGPTCL +
Adani +
PGCIL
765kV S/C Koradi-III to Akola-II Ckt no.I 765 S/C 223 223.00 12-Sep-11 13-Aug-12 13-Feb-13 13-Feb-13 12-Apr-13
183 Maharastra MRA-980 MSETCL220kV D/C Line from Ghatodi (Pusad) -
Hingoli S/S220 D/C 84 168.00 3-Oct-11 29-Oct-12
184 Maharastra MRA-981 MSETCLLILO of 400kV D/C line Koradi-II to Wardha
line at 2X270MW TPS (IEPL) at Village Bela400 D/C 24.36 48.72 17-Oct-11 2-May-12 10-Apr-12 9-May-12
185 Maharastra MRA-983 MEGPTCL 765 kV S/C Tiroda - Koradi-III line 765 S/C 137.5 137.50 17-Nov-11 13-Aug-12 30-Apr-12 1-Oct-12 10-Jan-13
186 Maharastra MRA-985 MSETCLLILO of 220kV D/C Mahad - Nagothane line
at 220kV POSCO S/S220 D/C 3.5 7.00 5-Dec-11 24-Feb-12 7-Nov-12 12-Dec-12
187 Maharastra MRA-986 MSETCL 220kV Butibori-I - Butibori-III line 220 D/C 2 4.00 7-Dec-11 18-Feb-12 18-Feb-12 18-Feb-12 18-Feb-12
188 Maharastra MRA-987 MSETCL
LILO of 400kV D/C Aurangabad (Waluj) -
Bhusawal line for Tapti Tanda (Aurangabad-
II) S/S on circuits-II
400 D/C 84.73 169.46 8-Dec-11 26-Jul-12 11-Jan-12 3-Dec-12
189 Maharastra MRA-988 MSETCL
LILO of 400kV D/C Aurangabad (Waluj) -
Bhusawal line for Tapti Tanda (Aurangabad-
II) S/S on circuits-I
400 D/C 76.499 153.00 8-Dec-11 26-Jul-12 11-Jan-12 9-Nov-12
190 Maharastra MRA-989 MSETCL
220kV D/C Bidri (Mudal Titta) S/S to LILO
point on 220kV D/C Kolhapur - Samantwadi
line
220 D/C 13.156 26.31 8-Dec-11 1-May-12 12-Jul-12
191 Maharastra MRA-992 MSETCL220kV D/C Phulambri S/S to Kankora
Windmill S/S trans. Line (Aurangabad)220 D/C 19.6 39.20 14-Dec-11 12-Jul-12 8-Oct-12
192 Maharastra MRA-991 MEGPTCL 765kV S/C Tiroda - Koradi III line Ckt-II 765 S/C 137.5 137.50 16-Dec-11 13-Aug-12 30-Apr-12 1-Oct-12 10-Jan-13
193 Maharastra MRA-993 MEGPTCL 765kV S/C Koradi-III to Akola-II trans. Line 765 S/C 223 223.00 26-Dec-11 13-Aug-12
194 Maharastra MRA-994 MSETCLLILO of 220kV S/C Pedambe - Karad and
Pophali - Karad II for 220kV Nerle S/S220 D/C 1.05 2.10 26-Dec-11 2-Feb-12 2-Feb-12
195 Maharastra MRA-995 SNTCL 400kV D/C Quad Nasik - Babhaleshwar T/L 400 D/C 56.27 112.54 29-Dec-11 9-Apr-12 9-Apr-12 20-Jul-12
WESTERN REGION 13 of 19
S.
No.State File No.
Name of the
Power
utility
Name of the Power line KVCkt
Type
PL
KM
CKT.
Km.
Date of
receipt of
proposal in
CEA
Date of
receipt of
BSNL
details
Date of
receipt of
Railway
details
Date of IV
comments
sent by
CEA
Approved
on
CEA LD&T DIVISION - STATUS OF PTCC PROPOSALS IN CEA as on 31.03.2014
196 Maharastra MRA-996 APTCL400kV D/C Quad Amravati TPP to Akola-II
Trans. Line400 D/C 103 206.00 16-Jan-12 26-Jul-12 21-Aug-12 30-Nov-12
197 Maharastra MRA-997 MEGPTCL 765kV S/C Quad Akola-III to Aurangabad line 765 S/C 220 220.00 2-Feb-12 26-Jul-12 2-May-12 23-Oct-12 10-Dec-12
198 MaharastraMRA-
997AMEGPTCL
765kV S/C Quad Akola-III to Aurangabad line
ckt-2765 S/C 223 223.00 2-Feb-12 26-Jul-12 2-May-12 23-Oct-12 10-Dec-12
199 Maharastra MRA-998 Reliance
LILO of 220kV MSETCL Borivali - Boisar
line at R.Infra-T Ghodbunder EHV S/S (XLPE
Cable)
220 D/C 4.3 8.60 2-Feb-12 12-Jul-12 18-Jul-12 24-Jul-12 9-Jul-12
200 Maharastra MRA-999 Reliance
XLPE Cable at 220kV D/C Cable between R
Infra Chembur EHV S/S to MSETCL
Trombay EHV S/S
220 D/C 8.125 16.25 24-Feb-12 1-Jun-12 5-Jun-12 6-Jun-12 11-Jun-12
201 MaharastraMRA-
1000MSETCL
LILO of 220kV D/C Kolhapur - Ponda line at
Hydro generating station Tillarri (Konalkatta)
S/S
220 D/C 0.199 0.40 23-Feb-12 1-Mar-12 1-Mar-12 14-Mar-12 30-Mar-12
202 MaharastraMRA-
1001
MAHATRA
NSCO220kV D/C Maishal S/S to Jath S/S 220 D/C 67.98 135.96 26-Mar-12 1-May-12 25-May-12 7-Mar-13
203 MaharastraMRA-
1002MSETCL
LILO of 220kV D/C Amaravati to Badhera
line at Nandgaon S/S220 D/C 30 60.00 26-Mar-12 26-Jul-12 8-Oct-12
204 MaharastraMRA-
1003MSETCL
220kV D/C line from 300MW Phase-II TPS
M/S VIPL to Butibori-I S/S220 D/C 1.7 3.40 26-Mar-12
205 MaharastraMRA-
1004STCL
LILO of 220kV D/C Pedamba - Karad line for
M/S Ratnagiri Wind Power Project, Dasgaon
S/S
220 D/C 4.091 8.18 26-Mar-12 1-May-12 1-May-12 22-May-12
206 MaharastraMRA-
1005MEGPTCL
LILO of 220kV D/C Satar MIDC -
Vankuswada line for Ajinkyatara SSK Ltd for
Co generation of Shri Renuka Sugar Ltd
220 D/C 4.133 8.27 26-Mar-12 2-May-12 2-May-12 22-May-12
207 MaharastraMRA-
1006Reliance
220kV D/C UG 220kV MSETCL Borivali s/s
to R.infrastucture,Borivali ENU s/s220 D/C 2.5 5.00 16-Apr-12 8-Oct-12 23-Jul-12 11-Oct-12
208 MaharastraMRA-
1007MSETCL
220kV D/C UG R infrastucture 220kV EHV
s/s 220kV MSETCL Borivali s/s220 D/C 8.3 16.60 16-Apr-12 8-Oct-12 23-Jul-12 11-Oct-12
209 MaharastraMRA-
1008
INDIA
BULL
LILO of 220kV D/C Eklahera - Babhaleshwar
line at Sinner220 D/C 0.3 0.60 25-Apr-12 13-Jul-12 21-Jul-12 21-Jul-12 21-Jul-12
210 MaharastraMRA-
1009MSETCL
LILO of 220kV D/C Gangapur - Satana line at
220kV Sakari (Sivajinagar) S/S220 D/C 27.625 55.25 24-Apr-12 8-Mar-13 1-Mar-14 11-Mar-14
WESTERN REGION 14 of 19
S.
No.State File No.
Name of the
Power
utility
Name of the Power line KVCkt
Type
PL
KM
CKT.
Km.
Date of
receipt of
proposal in
CEA
Date of
receipt of
BSNL
details
Date of
receipt of
Railway
details
Date of IV
comments
sent by
CEA
Approved
on
CEA LD&T DIVISION - STATUS OF PTCC PROPOSALS IN CEA as on 31.03.2014
211 MaharastraMRA-
1010MSETCL
220kV D/C Line LILO on Vita - Pandharpur
line for Hiwarwadi S/S220 D/C 6 12.00 6-Jun-12 12-Jul-12 17-Jul-12 17-Aug-12
212 MaharastraMRA-
1011MSETCL
LILO on 220kV D/C Khaperkheda-Khanan-
Sunblag line for 25 mw power plant at M/S
Surya laxmi cotton mills,Nagardhan
220 D/C 3.455 6.91 25-Jun-12 18-Sep-12 28-Aug-12 22-Oct-12 15-Dec-12
213 MaharastraMRA-
1012MSETCL
LILO on 220kV Mulund-Borivali line for
bhandup gis s/s by ug cable 220 D/C 0.9 1.80 7-Jul-12 3-Oct-12 3-Oct-12 20-Dec-12
214 MaharastraMRA-
1013MSETCL
LILO on 220KV Volkswagon S/S to 220KV
Mahindra S/S line for M/S Bridgestone
220KV S/S at Chakan MIDC
220 D/C 6 12.00 10-Jul-12 12-Dec-12
215 MaharastraMRA-
1014MSETCL
400KV D/C Chandrapur-II to Chandrapur S/S
Line400 D/C 2.268 4.54 12-Jul-12 17-Sep-12 4-Apr-13
216 MaharastraMRA-
1015MSETCL
400KV D/C Babhleshwar S/S to Thapti Tanda
(Aurangabad-II) S/S Line400 D/C 121.58 243.16 16-Jul-12 30-May-13 8-Mar-14 11-Mar-14
217 MaharastraMRA-
1016MSETCL
220KV D/C Line from Ahmednagar-Bhose
(Belwandi)220 D/C 47.5 95.00 13-Aug-12 28-Mar-13 28-Mar-13 22-Jul-13
218 MaharastraMRA-
1017MSETCL 220KV D/C line from Eklahare-Pimpalgaon 220 D/C 43.8 87.60 16-Aug-12 28-Mar-13 21-Dec-12 12-Sep-13
219 MaharastraMRA-
1018MSETCL
220KV D/C Line, LILO on Lonand-
Kandalgaon line for M/S Birla Surya Ltd.220 D/C 10.3 20.60 6-Sep-12
220 MaharastraMRA-
1019MSETCL
220KV D/C Line, LILO on Kandalgaon-
Lonand line for Lonand MIDC S/S220 D/C 1.65 3.30 7-Sep-12
221 MaharastraMRA-
1024MSETCL
220KV D/C Line-TAP on Bhableshwar-
Chalisgaon Line for Kopargaon S/S220 D/C 10.6 21.20 1-Oct-12 30-May-13 19-Aug-13 10-Jan-14
222 MaharastraMRA-
1020MSETCL
220KV D/C T/L from Malegaon S/S to
Kalwan S/S220 D/C 47.1 94.20 8-Oct-12 28-Mar-13
223 MaharastraMRA-
1021PGCIL
400KV D/C Navasari-Boisar T/L
(Maharashtra Portion)400 D/C 49 98.00 9-Oct-12 6-Aug-13 14-Jan-13 8-Nov-12
224 MaharastraMRA-
1022
MAHATRA
NSCO
LILO OF 400KV D/C Chandrapur-Parli Line
of CKT-I & CKT-II for 400KV Chandrapur-II
S/S
400 D/C 2.03 4.06 12-Oct-12 17-Jan-13 4-Mar-13
225 MaharastraMRA-
1023Reliance
220KV XLPE Cable Line from R'-Intra
220KV Saki EHV S/S to TATA 220KV Saki
EHV S/S
220 D/C 1.45 2.90 25-Oct-12 28-Mar-13 4-Feb-13 28-May-13
226 MaharastraMRA-
1025MSETCL
220KV D/C Line from Chandrapur MIDC S/S
to Ballarsha S/S220 D/C 24 48.00 29-Nov-12 4-Mar-13
WESTERN REGION 15 of 19
S.
No.State File No.
Name of the
Power
utility
Name of the Power line KVCkt
Type
PL
KM
CKT.
Km.
Date of
receipt of
proposal in
CEA
Date of
receipt of
BSNL
details
Date of
receipt of
Railway
details
Date of IV
comments
sent by
CEA
Approved
on
CEA LD&T DIVISION - STATUS OF PTCC PROPOSALS IN CEA as on 31.03.2014
227 MaharastraMRA-
1026MSETCL
220KV D/C Line from Wardha-II(Bhugaon)
S/S TO Warodra S/S220 D/C 83 166.00 29-Nov-12
228 MaharastraMRA-
1027PGCIL
400KV M/C(TWIN) LILO of both CKT of
400 KV D/C Vapi-Navi Mumbai T/L at kala
(New 400/220KV GIS SS)
400 D/C 9.014 18.03 12-Dec-12 26-Feb-13 10-Jun-13 28-Jun-13 12-Jul-13
229 MaharastraMRA-
1028MSETCL
220kV M/C line from kopergaon Taping point
to 400KV Babhleshwar s/s.220 D/C 37.988 75.98 21-Dec-12 30-May-13 19-Aug-13
230 MaharastraMRA-
1029GOA,SEB
220KV D/C Line from Xeldem S/S to
Cuncalim S/S in South Goa.220 D/C 12.5 25.00 26-Dec-12 12-Nov-13
231 MaharastraMRA-
1030DIL
LILO at 400kv DC parli bhadrawati Tl at
2X300 mw tadali tps chandrapur400 D/C 15.2 30.40 4-Jan-13 19-Feb-13 28-Mar-13 2-Apr-13
232 MaharastraMRA-
1031MSETCL
220kv DC LILO on 220kv chalisgram to
malegaon line for sayne220 D/C 5.0 10.00 14-Jan-13 28-Mar-13 7-Jan-14 8-Jan-14
233 MaharastraMRA-
1032MSETCL
220kv DC line LILO on 220 kv flagship
(blueridge)s/s to 220 kv theur s/s line for
220kv kondhwa s/s
220 D/C 0.6 1.20 22-Jan-13 30-May-13 3-Apr-13 8-Jan-14
234 MaharastraMRA-
1033MSETCL
220kv DC line LILO on 220 kv flagship
(blueridge)s/s to 220 kv theur s/s line for
220kv nanded citys/s
220 D/C 1.2 2.40 22-Jan-13 30-May-13 3-Apr-13 8-Jan-14
235 MaharastraMRA-
1034MSETCL
220 kv DC LILO on 220 kv deep nagar s/s to
220 kv khadka s/s line for 220kv chalisgram
s/s
220 D/C 123.0 246.00 6-Feb-13 12-Nov-13 1-Apr-13
236 MaharastraMRA-
1035MSETCL
220 kv KHARGHAR - KALWA line from
D/C to M/C220 D/C 21.9 43.75 1-Feb-13
237 MaharastraMRA-
1036MSETCL
765 KV D/C (HEX Bundle) Raipur pooling
station Wardha T/L - 01765 D/C 125.2 250.42 18-Feb-13 19-Oct-13 24-Dec-13 23-Jan-14
238 MaharastraMRA-
1037MSETCL
LILO ON 220 KV WALUJ-BBLR LINE at
220KV Deagaonrangari S/S220 D/C 26.3 52.60 13-Mar-13 30-May-13 9-Apr-13 11-Jun-13
239 MaharastraMRA-
1038PGCIL 400 KV D/c line from Dhule-Dhule 400 D/C 9.5 19.00 8-Mar-13 8-Mar-13 28-Mar-13 3-Jul-13
240 MaharastraMRA-
1039PGCIL
765 KV D/C line Raipur pooling station to
Wardha T/L765 D/C 242.4 484.778 15-Apr-13 14-Oct-13 14-Oct-13 23-Jan-14
241 MaharastraMRA-
1040MSETCL
220 KV D/C line for 220 KV D/C Vita-
Ghatnandra line220 D/C 0.9 1.81 9-Apr-13 10-May-13 10-May-13 14-May-13
242 MaharastraMRA-
1041PGCIL 400 KV D/C (quad) Padghe -Padghe 400 D/C 17.0 33.92 12-Apr-13 6-Aug-13 6-Aug-13 27-Mar-14
WESTERN REGION 16 of 19
S.
No.State File No.
Name of the
Power
utility
Name of the Power line KVCkt
Type
PL
KM
CKT.
Km.
Date of
receipt of
proposal in
CEA
Date of
receipt of
BSNL
details
Date of
receipt of
Railway
details
Date of IV
comments
sent by
CEA
Approved
on
CEA LD&T DIVISION - STATUS OF PTCC PROPOSALS IN CEA as on 31.03.2014
243 MaharastraMRA-
1042Mahatransco
Upgraadation of existing 220kV Kalwa-
Borivali line from D/C to M/C220 D/C 17.0 34.00 26-Apr-13 21-Aug-13
244 MaharastraMRA-
1043Mahatransco
220kV D/C LILO on 220kV AHMED
NAGAR S/S to 220kV BABHALESHWAR
S/S line for 220kV Kandgam
220 D/C 33.6 67.18 30-Apr-13 12-Aug-13 12-Aug-13 25-Jul-13
245 MaharastraMRA-
1044Mahatransco
220kV D/C line from Waghoda(Distt. Dhule)
to Amaner Distt. Jalgaon220 D/C 34.4 68.80 3-Jun-13
246 MaharastraMRA-
1045MSETCL
400 kv D/C line lilo on 400 kv Padghe S/S to
400 Kv Tarapur S/S line for 400 kV Kardus400 D/C 3.4 6.80 17-Jun-13
247 MaharastraMRA-
1046MSETCL
220 kv D/C line from 400 kV Kudus S/S to
220 kV wada-2(Bhavegar)S/S220 D/C 15.3 30.66 17-Jun-13
248 MaharastraMRA-
1047MSETCL
400 KV D/C LINE from 400KV JEJURI S/S
TO 400KV Hingewadi s/s400 D/C 46.2 92.35 17-Jun-13 6-Feb-14
249 MaharastraMRA-
1048MSETCL 220 kV Borivalli-Baisar line from D/c to M/c 220 D/C 87.0 174.00 17-Jun-13
250 MaharastraMRA-
1049MSETCL
220 KV D/C Line from 220KV JATH S/S TO
220KV M/S SHRI MARUTI WIND PARK
Developer at SHEDYAL S/S
220 D/C 17.6 35.20 8-Jul-13 26-Jul-13 26-Jul-13 26-Jul-13
251 MaharastraMRA-
1050PTCC
220KV D/C PODGHEWADA LINE FOR
220KV BHAVAGHAR S/S220 D/C 0.5 1.08 29-Jul-13
252 MaharastraMRA-
1051
MAHATRA
NSCO
400 KV JAJURI-TO-HINJEWADI LINE
(Jaduri-Winjihar)400 D/C 51.1 102.20 19-Aug-13 6-Feb-14
253 MaharastraMRA-
1052
MAHATRA
NSCO
220kV D/C KANDALGAON-TO-DASTURI
LINE220 D/C 74.0 148.06 19-Aug-13
254 MaharastraMRA-
1053MSETCL
220KV D/C LINE From BHAGAD S/S -
MANGAON (220KV M/s. Inox Air Products
Ltd.)
220 D/C 2.3 4.62 4-Sep-13 6-Feb-14
255 MaharastraMRA-
1054MSETCL
220kv D/C line from KUDUS (400kv S/S) -
BHIVANDI IV (Rajlaxmi) (220kv proposed)220 D/C 26.2 52.45 4-Sep-13
256 MaharastraMRA-
1055MSETCL 220kv M/C UPPALWADI-PARDI T/L 220 M/C 12.2 24.40 1-Oct-13
257 MaharastraMRA-
1056MSETCL
220kv M/C MANKAPUR - UPPALWADI
T/L (PL-7.99+2.5) KM220 M/C 10.5 20.98 3-Oct-13
WESTERN REGION 17 of 19
S.
No.State File No.
Name of the
Power
utility
Name of the Power line KVCkt
Type
PL
KM
CKT.
Km.
Date of
receipt of
proposal in
CEA
Date of
receipt of
BSNL
details
Date of
receipt of
Railway
details
Date of IV
comments
sent by
CEA
Approved
on
CEA LD&T DIVISION - STATUS OF PTCC PROPOSALS IN CEA as on 31.03.2014
258 MaharastraMRA-
1057MSETCL
400kv M/C LINE AURANGABAD(PGCIL)
S/S - AURANGABAD (MSETCL) S/S400 M/C 51.7 103.38 21-Oct-13 3-Oct-13 3-Oct-13 30-Oct-13
259 MaharastraMRA-
1058MSETCL SALAPUR S/S- BALE (SALAPUR-II) 220 D/C 41.8 83.67 28-Oct-13
260 MaharastraMRA-
1059MSETCL
PANDHARPUR-VITA LINE-
PHANDERPUR-II(BHALWANI)S/S220 D/C 12.9 25.72 6-Nov-13
261 MaharastraMRA-
1060MSETCL KATEL-WARUD LINE 220kv D/C 220 D/C 49.0 98.00 6-Nov-13
262 MaharastraMRA-
1061MSETCL
PANDHARPUR-MALINAGAR For proposed
220kv Bhalarahi s/s220 D/C 19.6 39.26 6-Nov-13
263 MaharastraMRA-
1062MSETCL KALMESHWAR-KATOL LINE 220 KV D/C 220 D/C 38.0 76.00 6-Nov-13
264 MaharastraMRA-
1063MSETCL
WARORA-WARDHA-II (BHUGAON)
220kv M/C220 D/C 9.9 19.80 6-Nov-13
265 MaharastraMRA-
1064MSETCL
HINJEWADI(220KV D/C U/G) -
HINJEWADI(220KV)-II 220 D/C 3.9 7.80 7-Nov-13
266 MaharastraMRA-
1065PGCIL
1.PARLI-PUNE(12KM) 2. AURANGABAD-
PUNE(18 KM) BOTH LINES 400 KV D/C400 D/C 30.0 60.00 5-Nov-13
267 MaharastraMRA-
1066PGCIL 765kv SALAPUR-PUNE 765 S/C 270.0 270.00 5-Nov-13
268 MaharastraMRA-
1067MSETCL
220kV M/C LINE from VILE BHAGAD S/S -
PIONEER GAS POWER PRJ. 220 M/C 2.7 5.40 13-Nov-13 6-Feb-14
269 MaharastraMRA-
1068PGCIL 400KV VAPI - KALA LINE 400 D/C 22.0 44.00 22-Nov-13 24-Mar-14 24-Mar-14 26-Mar-14
270 MaharastraMRA-
1069PGCIL
765KV D/C WARDHA - AURANGABAD
LINE-I765 D/C 348.0 696.00 24-Dec-13 24-Dec-13 24-Dec-13 21-Jan-14
271 MaharastraMRA-
1070PGCIL
765KV D/C WARDHA - AURANGABAD
LINE-II765 D/C 349.0 698.00 24-Dec-13 24-Dec-13 24-Dec-13 24-Jan-14
272 MaharastraMRA-
1071PGCIL
400 KV D/C WARDHA - AURANGABAD
LINE-9 UPGRADABLE TO 1200 KV (PNR)400 D/C 27-Jan-14
273 MaharastraMRA-
1072PGCIL
220 KV D/C BHIGWAN-WALCHAND
NAGAR LINE220 D/C 32.0 64.00 19-Feb-14
274 MaharastraMRA-
1073RSTCL 765KV S/C RAICHUR TO SOLAPUR T/L 765 S/C 208.0 208.00 10-Dec-13
WESTERN REGION 18 of 19
S.
No.State File No.
Name of the
Power
utility
Name of the Power line KVCkt
Type
PL
KM
CKT.
Km.
Date of
receipt of
proposal in
CEA
Date of
receipt of
BSNL
details
Date of
receipt of
Railway
details
Date of IV
comments
sent by
CEA
Approved
on
CEA LD&T DIVISION - STATUS OF PTCC PROPOSALS IN CEA as on 31.03.2014
275 MaharastraMRA-
1074
MAHATRA
NSCO
400KV INTERCONNECTION LINE between
765 KV EKTUNI S/S & THAPTI TANDA
(A'BAD-II) S/S CKT-I & II
400 D/C 4.7 9.40 10-Mar-14
276 MaharastraMRA-
1075
MAHATRA
NSCO
Extension of 400kv D/C BABHLESHWAR-
THAPTI TANDA (Aurangabad-II) Line from
Location No. 5 (new) to 765 KV EKTUNI
(Aurangabad) S/S
400 D/C 4.7 9.40 10-Mar-14
277 MaharastraMRA-
1076
MAHATRA
NSCO220KV PHALTAN - WALCHAND NAGAR 220 D/C 58.8 117.60 14-Mar-14
278 MaharastraMRA-
1077
MAHATRA
NSCO
220KV D/C LILO on 220kv PANDHARPUR -
JEUR line for M/S Vithalrao Shinde SSK Ltd.
220 kv s/s at GANGAMAINAGAR
220 D/C 2.5 5.00 14-Mar-14
279 MaharastraMRA-
1078
MAHATRA
NSCO
220kv D/C Line from 400KV PGCIL
Talegaon s/s for 220KV HINJEWADI MIDC
phase-I S/S & 220 KV HINJEWADI MIDC
Phase-II s/s
220 D/C 37.5 75.00 13-Mar-14
280 MaharastraMRA-
1079
MAHATRA
NSCO
LILO ON 220KV D/C VITA-LAMBOTI
LINE FROM MARUTI 220KV WINDMILL
KHANAPUR S/S AT BHUD SITE, DISTT.
SANGLI
220 D/C 23.2 46.34 25-Mar-14
Note:Discrepancy if any, may please be communicated to Director(PTCC)