Status report on EMC simulation ... The plan was to: SURVEY the existing situation over the 2001 2002 runs - Validation of plots using and eeee samples STATUS: started with Library TOMLIB,DIAG used with minor effort (after 1 day of debugging thanks to T.Spadaro) emcsim.exe Scripts ready to run over a large sample. First test-plots on energy response started/checked with 1.5 pb -1 of D3P3 dsts (runnum ~ 26519-26658) MC meeting LNF 23- 1-03 S.Misce tti

Upload: aladdin-horton

Post on 30-Dec-2015

41 views

Category:

Documents


3 download

DESCRIPTION

Status report on EMC simulation. The plan was to: SURVEY the existing situation over the 2001 2002 runs - Validation of plots using  and ee ee samples STATUS: started with  Library TOMLIB,DIAG used with minor effort (after 1 day of - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Status report on EMC simulation

Status report on EMC simulation ...

The plan was to: SURVEY the existing situation over the 2001 2002 runs - Validation of plots using and eeee samples

STATUS: started with Library TOMLIB,DIAG used with minor effort (after 1 day of debugging thanks to T.Spadaro) emcsim.exe Scripts ready to run over a large sample. First test-plots on energy response started/checked with 1.5 pb-1

of D3P3 dsts (runnum ~ 26519-26658) next steps ... run over large data sets. Insert efficiencies.

start comparing with MC, fix MC!

MC meeting LNF 23-1-03 S.Miscetti

Page 2: Status report on EMC simulation

Example of problems in EMC scale (1)

Comparing the Energy scale asa function of hit position in fiber shows : no problems just a small scale for Barrel 4-5% discrepancy along Rt or Y in Ecap

DATA

DATA vs MC

Page 3: Status report on EMC simulation

Example of problems in EMC scale (2)

Page 4: Status report on EMC simulation

Example of validation plots with EMCSIM

MC meeting LNF 23-1-03 S.Miscetti

E(MeV)

E(MeV)

Pg (MeV)

Zext(cm)

Pg(MeV)

Barrel only, E-Pg (MeV) vs ..

Page 5: Status report on EMC simulation

MC meeting LNF 23-1-03 S.Miscetti

Zext(cm)

Pg(MeV)

EMCSIM: Barrel only. (E-Pg)/Pg

Page 6: Status report on EMC simulation

Endcap region (80:180 cm in RT)

MC meeting LNF 23-1-03 S.Miscetti

RT(cm) Pg(MeV)

Page 7: Status report on EMC simulation

Barrel-Endcap region (180:200 cm in RT)

MC meeting LNF 23-1-03 S.Miscetti

Pg(MeV)

Page 8: Status report on EMC simulation

MC meeting LNF 23-1-03 S.Miscetti

20 slices in Pg (20 MeV)

Gauss fit

Extract Peak, Sigma

First look to resolution on EndCap

Page 9: Status report on EMC simulation

Endcaps .. Diff lin and energy resolution

MC meeting LNF 23-1-03 S.Miscetti

Pg(eV)Pg(MeV)

Page 10: Status report on EMC simulation

Another look at holes ..

MC meeting LNF 23-1-03 S.Miscetti

(Degree)

Gamma Gamma sample

Page 11: Status report on EMC simulation

Status of SELBKG

MC meeting LNF 23-1-03 S.Miscetti

A first skeleton of the AC module SELBKG exists: INIT routine to reads the weights from files done EV routine to filter gg sample: - selection of golden clusters ok and tested. - list of accidental clusters ok - weighting routine in progress - selection of CELE hits in progress no selection for DC hits