stb update · pdf fileright car right train ... last week’s operations focused on clean...
TRANSCRIPT
2
Network healthy, performed well heading into holiday week
Dwell, velocity, originations and arrivals improved; nearly all measures outperforming 2016
Right Car Right Train increased
Crew and power resource levels remain well matched to demand
Hump yard performance steady
Western terminals performing well
Car fulfillment settled higher, averaging 93% since improved order fulfillment process began
Local pull and place performance stable
Customer problem logs remained at lower levels
Interchange volumes current and gateways fluid
Last week’s operations focused on clean execution and clearing the network in advance of the holiday, during which many customers planned to shut down for the long weekend
3
Velocity fully recovered, continues to outperform 2016
10
12
14
16
18
20
1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 33 35 37 39 41 43 45 47 49 51
Velo
city
Week
2016 2017
PSR Implementation Height of Service
Disruption
STB Listening Session
Velocity (mph)
Fav (Unfav) % Change vs. 2016
2016 Full Year Average 14.9PSR Implementation 13.8 (7%)Height of Service Disruption 13.0 (13%)STB Listening Session 15.4 3%Current Week 17.7 19%
Note: Velocity displayed according to CSX methodology; explanation of CSX methodology can be found in appendix. Week 37 & 38 velocity excludes specific trains held through Hurricane Irma.
Velocity (mph)ImprovementDegradation
4
Dwell at or below 2016 full year levels for 15th consecutive week
Gross Dwell
8
10
12
14
16
1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 33 35 37 39 41 43 45 47 49 51
Dw
ell
Week
2016 2017
Dwell (hours)
Fav (Unfav) % Change vs. 2016
2016 Full Year Average 11.2PSR Implementation 11.6 4%Height of Service Disruption 13.1 (17%)STB Listening Session 11.0 2%Current Week 10.3 8%
Dwell (hours)
Note: Dwell displayed according to CSX methodology; explanation of CSX methodology can be found in appendix. Week 37 & 38 dwell excludes terminals that held cars through Hurricane Irma-impacted period.
PSR Implementation
Height of Service Disruption
STB Listening Session
DegradationImprovement
17.4
17.4
17.7
18.0
18.1
17.8
17.8
9.5 10
.2 11.4
11.1
10.1
9.8 10.0
Measures improved versus prior week, nearly all better than 2016
5Note: Dwell and velocity displayed according to CSX methodology; explanation of CSX methodology can be found in appendix. Q3 dwell and velocity exclude the Hurricane Irma-impacted period for terminals that held cars and specific trains held through storm, respectively.
Velocity (mph)
63%
66% 70% 74% 79
%71
% 75%
72% 75% 81
%
84% 87
%
86%
88%
14.914.2
16.2
14.0
15.7 15.414.9 14.9 14.9
16.0 16.4 16.3
17.7 17.717.1
10.0
12.0
14.0
16.0
18.0
20.0
2016 Q1 Q2 Q3 40 41 42 43 44 45 46 47 48 49 50
On Time Originations (%)
Dwell (hours)
68%64%
81%
60%
70%64%63%63%67%67%65%64%
76%72%
66%
20%
40%
60%
80%
100%
2016Q1 Q2 Q3 40 41 42 43 44 45 46 47 48 49 50
On Time Arrivals (%)
On-Time
+2 hrs
On-Time
+2 hrs
11.2 11.610.8
12.1
10.7 11.010.5 10.4 10.5 10.6 10.6 10.7 10.6
9.810.4
6.0
8.0
10.0
12.0
14.0
16.0
2016 Q1 Q2 Q3 40 41 42 43 44 45 46 47 48 49 50
84% 81%88%
74% 74%73% 74% 73%77% 77% 74% 71%
85% 83%78%
20%
40%
60%
80%
100%
2016 Q1 Q2 Q3 40 41 42 43 44 45 46 47 48 49 50
Weekly Average
Dec. 16 – Dec. 22 Dec. 16 – Dec. 22
Dec. 16 – Dec. 22 Dec. 16 – Dec. 22
Weeks
Weeks Weeks
Weeks2017
2017 2017
2017
86% 86%
82%
73%75%76%76%
77%
74%73%72%
74%
78%76%
73%
50%
55%
60%
65%
70%
75%
80%
85%
90%
2016Q1 Q2 Q3 40 41 42 43 44 45 46 47 48 49 50
Weeks
71%
70% 72
%
78%
78%
75%
74%
Dec. 16 – Dec. 22
Right Car Right Train up slightly
6
Right Car Right Train1
1 ‘Right Car Right Train’ is defined as the percentage of cars that departed from a yard in accordance with their car scheduling trip plan
Right Car Right Train is no longer a measure that CSX uses to manage its operation― In precision scheduled railroading (PSR), if a car can
be advanced on another train to speed transit or ensure its on-time arrival, there is not one “right train”
Car priority is to move cars quickly, on next available train― Asset utilization a key tenet of PSR
Train priority is blocking integrity and departing all available, relevant cars from the yard― Blocking integrity certifies that a train is built correctly
and shipments are headed to the correct location― Managed through field supervision
Weekly Average
2017
9,771
9,223
9,690
9,445
9,278 9,264 9,247 9,225 9,204 9,189 9,081 9,049 9,028 8,986 8,953 8,926
0%
2%
4%
6%
8%
10%
12%
8,400
8,800
9,200
9,600
10,000
2016 Q1 Q2 Q3 40 41 42 43 44 45 46 47 48 49 50 51
7
Resourcing appropriately to meet business needs
Power and crew availability steady in fourth quarter at approximately 99% and 95%, respectively
Train & Engine Headcount and Re-crew Rate1Active Locomotives
3,673 3,763
3,376
3,200 3,182 3,184 3,162 3,165 3,174 3,180 3,192 3,200 3,179 3,083
3,013 3,013
2,000
2,400
2,800
3,200
3,600
4,000
2016 Q1 Q2 Q3 40 41 42 43 44 45 46 47 48 49 50 51
1 Re-crew rate is re-crew people starts as a percent of total measured people starts, and represents incidences of replacing a crew on the same train ID (generally due to hours of service)
Locomotive level coming down in concert with network velocity improvement
Recent headcount reduction driven by train staffing efficiency and adjustments to extra boards
2017 Weeks 2017 Weeks
21.6
22.1
22.2
20.4
18.5
18.6
19.2
19.9 20.6
17.2
19.8 17.7
18.8 18.7 20.6 20.8 20.1
21.5 20.1
17.1 17.7
20.8
6.0
10.0
14.0
18.0
22.0
26.0
30.0
2016 Q1 Q2 Q3 40 41 42 43 44 45 46 47 48 49 50
8
Hump yard performance steady
CSX Hump Terminal Overview
Transitioned to flat-switching operations
Hump terminals
Selkirk, NY
Cumberland, MD
Hamlet, NC
Waycross, GA
Atlanta, GABirmingham, AL
Nashville, TN
Louisville, KY
Avon, IN
Cincinnati, OH
Willard, OH
Toledo, OH
1 Dwell displayed according to CSX methodology; explanation of CSX methodology can be found in appendix. Q3 dwell excludes the Hurricane Irma-impacted period for terminals that held cars through the storm.
Absolute number of humps not “good” or “bad”; goal is best mix of hump and flat yards for processing efficiency
Dwell at Hump Terminals1
Dec. 16 – Dec. 22
Weekly Average
Weeks2017
Total hump yard volumes remain in a consistent band week-over-week, well below capacity of yards
Key hump productivity and efficiency measures performing well, four humps remaining
11.5
14.9
11.4 12
.9
11.8
10.1 12
.113.0 13.6 13.4
15.6
12.6
14.4
12.111.4
12.3 12.5 12.4 11.9 11.711.0
11.9
6.0
10.0
14.0
18.0
22.0
2016 Q1 Q2 Q3 40 41 42 43 44 45 46 47 48 49 50
Key terminal productivity and performance measures recovered in former “trouble” spots
Train plan changes at Evansville have resulted in very few cars processed, no longer a key terminal
9
Western terminals performing well
Western Corridor Key Terminals
Birmingham, AL
Nashville, TN
Avon, IN
Evansville, IN
Montgomery, AL
Mobile, AL
Key Western terminals
1 Dwell displayed according to CSX methodology; explanation of CSX methodology can be found in appendix. Q3 dwell excludes the Hurricane Irma-impacted period for terminals that held cars through the storm.
Weekly Average
Dwell at Western Terminals1
Dec. 16 – Dec. 22
Weeks2017
40%
50%
60%
70%
80%
90%
100%
0
1,000
2,000
3,000
4,000
5,000
6,000
7,000
2016 Q1 Q2 Q3 40 41 42 43 44 45 46 47 48 49 50 51
Weekly Orders Customer Empty Idles (> 24 hours)
Order Fill % Order Fill % ex. Customer Empty Idles
10
Car order fulfillment settled higher
Weekly Car Orders, Customer Empty Idles, and Fill Rate1
Cars Ordered/Idle
Order Fill Rates
1 2017 fill rate has been normalized through Week 44 against historical/expected order levels (Q1 2017), as order levels disconnected with demand beginning in Q2 2017; 2016 orders and fulfillment and 2017 Week 45 and beyond do not warrant normalizing
Car ordering and fulfillment process updated as of Week 45
― Car orders now remain open for 2 weeks for fulfillment; order fill will settle over a 2-week period
― Accordingly, the current week fill rate will be adjusted in the following week for orders filled
Week 51 added 315 orders filled to week 50, order fill increased to 96%
― Settled weeks 45-50 averaging 93% fulfillment
Empty car dwell remains elevated at customer locations, impacts order fill
― Empty idle cars at a given customer held >24 hours considered available to fill that customer’s orders2017 Weeks
(Prior Process)
11
Last mile performance stable
Local Service Measurement1
94% 95%90%
81% 84% 83% 85% 85% 85% 84% 85%
77%
86% 84% 84% 83%
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
2016 Q1 Q2 Q3 40 41 42 43 44 45 46 47 48 49 50 51
1 ‘Local Service Measurement’ is defined as the percentage of cars that were pulled or placed at a customer location based upon daily customer request, the local service plan and available inventory at the local serving yard
2017 Weeks
Local Service Measurement (LSM) is no longer a metric that CSX uses to manage its operation― In precision scheduled railroading (PSR), focus on end-
to-end transit and customer expectations
Accordingly, LSM as a reported metric was discontinued upon start of PSR implementation― At request of STB, last mile tracking reinstated to
monitor through implementation period
Reliable pull and place expected as part of service to customers
12
Customer problem logs remained at lower levels
201
269
416
265 278247 253 254 266
318
213258 257 245 238
Q1 Q2 Q3 40 41 42 43 44 45 46 47 48 49 50 51Weeks
Delayed Cars Bad Order Switching Issues
Customer InquiriesDaily Average Log Volume
Customer logs largely back in normal range after network challenges as fluidity has returned
Lower level of logs, improved communication allowing faster, more comprehensive resolution ― Accountability for resolution of customer issues resides
with field responsibility― Escalating and resolving critical issues with senior
leadership
2017
570 Total Logs in Week 30 at height of service challenges
Interchanges current and performing to expectations
0
200
400
600
800
2016 Q1 Q2 Q3 40 41 42 43 44 45 46 47 48 49 50 51
East St. LouisDaily Average Interchange Volume
From To
0
200
400
600
2016 Q1 Q2 Q3 40 41 42 43 44 45 46 47 48 49 50 51
New OrleansDaily Average Interchange Volume
0
400
800
1,200
1,600
2,000
2016 Q1 Q2 Q3 40 41 42 43 44 45 46 47 48 49 50 51
Chicago Daily Average Interchange Volume
0
100
200
300
2016 Q1 Q2 Q3 40 41 42 43 44 45 46 47 48 49 50 51
MemphisDaily Average Interchange Volume
13
2017 Weeks
2017 Weeks 2017 Weeks
2017 Weeks
14
Precision scheduled railroading producing service improvement
ImproveService
OperateSafely
ControlCosts
Drive AssetUtilization
DevelopPeople
Operational Focus
TerminalFluidity
BalancedTrain Plan
Service Improvements
Rolling StockUtilization
PeopleEfficiency
FuelOptimization
TrainDensity
ImprovedFrequency
BetterReliability
FasterTransit
QuickerTurnaround
Productivity Improvements&
Realigned service frequency in second quarter
Set the groundwork of a balanced train plan in early July
Terminals’ improved efficiency and traffic flow adjustments have recovered service
Improved execution on this foundation to drive long-term service and productivity improvements
16
Velocity
Former Line of road miles per hour
CurrentTotal miles traveled per hour, including intermediate dwell of the train
ChangeReason
Includes full trip of a train and ability to diagnose overall speed profile (in support of improvement in asset cycle)
Effect onMetric Reported velocity will be lower
CSX has changed methodology on some metrics reported publicly
Dwell
Former Car time at terminal, excluding cars on the same train ID
CurrentAll car time with a terminal work event, including through cars on same train ID (e.g. crew change)
ChangeReason
Includes all dwell with ability to diagnose all events impacting car movement (in support of improvement in asset cycle)
Effect on Metric Reported dwell will be lower
Restated historical data in new methodology available on csx.com/servicemetrics
Cars Online
Former All cars on CSX, as determinedby RailInc
Current
RailInc cars on CSX, excluding cars stored, under repair, sold, and private cars ex online inventory
ChangeReason
More accurate measurement of active cars on line, i.e. cars for which CSX is focused on real-time, efficient movement
Effect on Metric
Reported cars online will be lower