steam blowing11

49
WELCOME TOPIC- STEAM BLOWING By- Operation Team ADANI POWER MAHARASHTRA LTD,TIRODA, 5 X 660 MW

Upload: anuj-shahi

Post on 07-Nov-2014

104 views

Category:

Documents


5 download

DESCRIPTION

zx

TRANSCRIPT

Page 1: Steam Blowing11

WELCOME

TOPIC- STEAM BLOWINGBy- Operation Team

ADANI POWER MAHARASHTRA LTD,TIRODA,5 X 660 MW

Page 2: Steam Blowing11
Page 3: Steam Blowing11

INTRODUCTIONPURPOSE :

Steam blowing of MS lines, CRH,HRH,SH,RH,HP & LP bypass pipe lines of turbine is carried out in order to remove welding slag, loose foreign materials, iron pieces, rust etc. from the system, generated during manufacturing, transportation & erection.

Page 4: Steam Blowing11

EFFECT OF BLOWING DEPENDS ON

1)     Thermal shock2)     Removal force of steam3) Cleaning force of steam

Page 5: Steam Blowing11

REMOVAL FORCE OF STEAM

Blowing Mass Flow ,Q flow= √1.25 * Qmcr √(Vmcr

/Vblow)

Qmc= mass flow at MCR

Vmc= velocity at MCR

Vblow=blowing velocity

Page 6: Steam Blowing11

CLEANING FORCE OF STEAM

The necessity to create in the system, the steam velocity greater than that is possible at MCR condition is obvious. These two velocities are expressed as a ratio “Cleaning factor” or “ Distribution factor” or “Cleaning Force Ratio” denoted by “X” or “K”.

Page 7: Steam Blowing11

CLEANING FORCE REQUIRED (CFR)OR DISTRIBUTION FACTOR

a)     K=Velocity of steam during blowing / Velocity of steam at MCR

b)   K= (Steam flow during blowing)2 *(Sp.vol of steam at blowing

(Steam flow at MCR)² * ( Sp.vol of steam at MCR)

Steam flow can be measured by the net feed water flowCFR & velocities of the steam should be verified to avoid

“Over Blowing”The recommended value K > 1.25 ( between 1.25 and 1.4)

Page 8: Steam Blowing11

PRECONDITIONS FOR STEAM LINE BLOWING1) Chemical cleaning should be completed2) SH primary and secondary de-superheater

piping and RH’s emergency de-superheater piping ready for operation

3) All permanent piping & temporary piping insulated and supports/hangers are released with cold setting

4) Silencer should be connected at temporary pipe exit

5) Soot blowing for APH should be available6) Make up for deaerator made ready7) Motor Driven BFP with all controls made

ready

Page 9: Steam Blowing11

PRECONDITIONS …

7) Hydraulic test of the following lines completed:

Feed Lines MS, HRH, CRH Lines MS to Aux. PRDS Line All other auxiliary lines identified for

steam blowing 8) Sampling system made ready

Page 10: Steam Blowing11

PRECONDITIONS …

9) Boiler auxiliaries proved serviceable and ready after pilot operation like:

- Fuel oil system- Compressors & Atomizing steam system- Start-up system ( for continuous system)- Coal Mill system (for continuous system)- CHP readiness- Economizer hopper and bottom ash hopper

and its evacuation system (for continuous system)

Page 11: Steam Blowing11

PRECONDITIONS …10) All safety valve disc installed after

removing hydro-static plug in drum(sub-critical), superheaters and reheaters

11) Adequate communication between control room, boiler and TG area ensured.

12) Flow nozzle, control valves and NRV flaps wherever applicable should be not erected before steam blowing and suitable spool pieces are erected. Strainers in the path should be removed.

13) Required number of Target Plates and holder made available

Page 12: Steam Blowing11

CHEMICAL CLEANING PROCESS

BOILER FRONT SYSTEM ALKALINE FLUSHING Mass Flushing Hot water Rinsing Alkaline Flushing Hot DM water Rinsing

MAIN BOILER SYSTEM ACID CLEANIG Super Heater Filling Mass Flushing Alkaline Flushing Hot DM water Rinsing Acid Cleaning Passivation

Page 13: Steam Blowing11

CHEMICAL CLEANING …ACID CLEANING ( BY CITRIC ACID METHOD )will be

done by circulation method for effectiveness of the cleaning process.

Acid cleaning will be followed by PASSIVATION, so that the uniform protective coating of GAMMA FERRIC OXIDE is formed on the metal surface and corrosion / oxidation damage to metal surface is prevented and continue during normal operation by dosing oxygen. The gamma ferric Oxide formed by using the chemical 1-2 % sodium Nitrite(NaNO2)

Page 14: Steam Blowing11

BASIC TECHNIQUE USED

1) PUFFING METHOD

2) PURGING METHOD / CONTINEOUS BLOW METHOD

Page 15: Steam Blowing11

PUFFING METHOD

To give a thermal shock to the contour being purged, to dislodge the scale etc.

Procedure: Raise the boiler pressure to a pre-determined value (40-60 kg/cm2), shut off firing and at the same time open the quick opening valve(EOTV), thus allowing the steam to escape to atm. with high velocity carrying with it the loose debris.

Page 16: Steam Blowing11

PRECAUTIONThe Pressure drop

allowed in drum is limited to corresponding saturation temp. change of 40 OC.

Page 17: Steam Blowing11

SCHEMESteam blowing done in stagesStage-1(a)- SH, MSL, ESV, temporary lines

from ESV to EOTV, EOTV to CRH line, CRH lines upto boiler end with temporary exhaust pipe.

Tap off lines from CRH to deaerator, auxiliary PRDS, HP heater 6a & 6b, gland sealing, etc. shall be remain closed/isolated.

stage 1a end point will be concluded by observing the indents on the target plate.

Page 18: Steam Blowing11

STAGE- 1(a)

Page 19: Steam Blowing11

STAGE- 1(b)

SH,MSL, HP bypass inter connection, hand operated valve mounted in place of HP bypass valve and CRH lines upto Boiler end with temporary exhaust piping.

In this stage 6 to 8 blows will be given through HP bypass lines to ensure cleanliness of the limb.

Boiler MS stop valve will be used for stage 1b. EOTV will be kept closed. Manually Operated Isolation Valves in HP bypass lines will be kept opened fully.

Page 20: Steam Blowing11

STAGE- 1(b)

Page 21: Steam Blowing11

STAGE-2(a)

1a plus reheater, HRH lines , Interceptor Valve and temporary pipe.

CRH line along with attemperator shall be welded with reheater before start of stage 2a. LP bypass lines shall be blanked during stage 2a. Stage 2a end point will be concluded by observing the indents on target plates

Page 22: Steam Blowing11

STAGE- 2(a)

Page 23: Steam Blowing11

STAGE- 2(b)

2a upto IV + LP bypass lines with temporary exhaust pipe.

Stage 2b blowing will be parallel blow in the path 2a & 2b. LP Bypass blanks shall be removed for stage 2b. 4 blows will be given through L.P. Bypass line to ensure cleanliness of the limbs

Page 24: Steam Blowing11

STAGE- 2(b)

Page 25: Steam Blowing11

STAGE-3

Auxiliary Steam Lines covered in steam blowing are listed below.

3a) Main steam line to Aux PRDS3b) CRH to Deaerator3c) CRH to HPH-6.All auxiliary steam lines will be steam

blown by continuous blowing method

Page 26: Steam Blowing11

STAGE-4

The following Aux steam lines, connected to deaerator are steam blown using auxiliary steam from Aux PRDS header.

4a)PRDS to Deaerator.

4b)Extraction 4 to Deaerator. 4c) PRDS to Gland steam header.

Page 27: Steam Blowing11

CONTINEOUS BLOWING METHODThe initial procedure is same as puffing

method except:

- Continuous firing till the completion of steam blowing. No need to shut of the firing during blowing.

- Maintain constant pressure during the blow

Page 28: Steam Blowing11

Recommended blowing parameters

Dynamic steam pressure= 3.5 MPaMS temp = 420(not to

exceed)HRH temp = 480( not to

exceed)Steam flow = 845 TPHCorresponding Drum pr. = 40 KscFurnace load ≈ 39%

Page 29: Steam Blowing11

METHOD- Set the Temporary purging valve, by-pass

valve and drain valve and granulating device behind the temporary pipes

- Check the tightness, support and expansion of the temporary system

- Section by section rinse of condensate water piping, feed water piping and boiler through the start-up system to CW system

Page 30: Steam Blowing11

METHOD: - Circulation begins when Fe+ in the water

of main feed water pipe and separator outlet will be less than 100 ppm.

- Maintain the circulation flow or start-up flow at minimum set value

- Start oil firing and raise the temp and press. according to the cold start-up.

Temp. rise rate of water wall = less than 2OC / min

Temp. rise rate of main steam = 4 ~ 5 OC / min

Page 31: Steam Blowing11

METHOD:- Before MS press reaches 1.0 Mpa , open

the bypass valve of temporary purging valve to warm the piping with all water drain valves of the system open.

-The blowing system divided into two partsA) Preliminary Steam Blowing

B) Final Steam Blowing

Page 32: Steam Blowing11

PRELIMINARY CLEANING

PORPOSE-a)Primary cleaning out sundries and bulky

grain deposited in the RH and main steam system

b)To ensure fastness of supports and hangers with proper expansion

c)Know well about the operation property of oil burning system, condensate water and feed water systems

METHOD

Page 33: Steam Blowing11

PRELIMINARRY STEAM BLOWING- Start the oil firing with max. rating of 15% - Control the gas temperature at furnace

outlet below 500 OC (max.538 OC )- Raise the SH outlet press to 1.6 – 1.8 Mpa

with steam temperature around 350 OC.- Open the temporary purging valve for 15-

20 min to blow in MS system- Maintain K around 0.5.- SH & RH desuperheater water system also

cleaned

Page 34: Steam Blowing11

FINAL STEAM BLOWING- Main steam and reheated steam system

are purged in series- Start 2-3 coal mills when oil burner hits

the rated firing rate of 15%- Increase the SH outlet press. to 3.5 Mpa.- Maintain the MS temp < 420 OC.- Keep HRH steam temp around 480 OC.- When the steam line blowing parameter

reaches , open the temporary purging valve gradually and increase the fuel and feed water volume to sustain parameter stability.

Page 35: Steam Blowing11

FINAL ….- Establish the MS flow around 40% of the

MCR (max.- 50%)- Ensure CFR (K) should be 1.25 to 1.3 for MS

and 1.05 to 1.1 for reheated steam- Blow under this operating condition for 20

to 30 min- Gradually reduce coal firing and close the

purge valve at 0.5MPa . - Remove the target plate and check it- By estimation, target may satisfy the

requirements after 15 to 20 times in-series purging

Page 36: Steam Blowing11

- When the steam line temp is above the sat. temp of MS press, close all drains and Open the boiler MSSV fully.

- Maintain the press. through controlled firing

- Insert a reference target- Check the CFR- Allow to run for 30-60 min

Page 37: Steam Blowing11

TARGET PLATE     Generally Stainless steel panel     Target plate set at the first, sixth, ninth, twelfth purging, thereafter set target for each purging until purging results qualified .     Width about 8% of the steam vent tubes inner diameter(ID) and length equal to ID     Brinell hardness < 90     Steam velocity – 258 m/sec     Target plates to be introduced just before steam blowing / light up—to be removed soon after blowing is completed.

Page 38: Steam Blowing11

ONLINE TARGET PLATE CHANGE ARRANGEMENT

GLAND PACKING ARRANGEMENT

GLAND PACKING ARRANGEMENT

Page 39: Steam Blowing11

DEBRIS FILTER

Page 40: Steam Blowing11

AUX BOILER TO AUX STEAM HEADER

Page 41: Steam Blowing11

TDBFP INLETBOILER

HPSV

HPSV

TEMPORARY PURGING VALVE

HPBP

TDBFP-1 SV

CRH LINE

MS LINE

TDBFP-2 SV

TEMPORARY LINEPERMANENT LINE

Page 42: Steam Blowing11

HP,CRH,REHEATER & HRH

BOILER

HPSV2

HPSV1

HPBP

CRH LINE

IPSV1

IPSV2

HRH LINE

TEMPORARAY LINEPERMANENT LINE

Page 43: Steam Blowing11

HP BYPASS TO CRH NRV

BOILER

HPSV2

HPSV1

HPBP

CRH LINE

IPSV1

IPSV2

HRH LINE

TEMPORARAY LINEPERMANENT LINE

Page 44: Steam Blowing11

LP BYPASS VALVE INLETBOILER

HPSV2

HPSV1

HPBP

CRH LINE

IPSV1

IPSV2

HRH LINE

LPBP

TEMPORARAY LINEPERMANENT LINE

Page 45: Steam Blowing11

STEAM BLOWING COMPLETION CRITARIA

At least 2 continuous target plates should not have ORIFICE GRANULARITY on the target shall be not larger than 0.8 mm.

CFR should be 1.25 to 1.4

No. of orifice granularity shall not supass 08 nos.

Page 46: Steam Blowing11

ADVANTAGES- Required less time for completion of the total

process- Less time required to normalize the system for

final light-up to synchronisation

- This reduces the reactionary forces on the temporary pipes

- Stresses on the boiler system are lower

Page 47: Steam Blowing11

PUFFING METHOD CONTINEOUS METHOD

More time required for complete steam blowing due to stage wise blowing(8-10 days)

More time required for stage wise temporary pipe erection and shifting of blowing device

No mill required

Quality of cleanliness is better than continuous process

Less time required for completion (3-4 days)

Less time required as only valves to be opened for different systems

Minimum 02 nos. of mill required

Quality of cleanliness is slightly less than Puffing.

Comparison between Puffing & Contineous Method

Page 48: Steam Blowing11

Comparison …PUFFING METHOD CONTINEOUS METHODThermal shock is the

driving force of cleaningMore thermal stress on

tube material and sudden loading on supports

Repeated light-up and shutdown

There is a time gap between the blows to make-up DM water

System normalization time after steam blowing is more

Silencer use is optional

Steam velocity or Removal force is the driving force

Less thermal stress on tube material

Light-up only once in the beginning of the steam blowing

DM water make-up to the system during steam blowing is a challenge

System normalization time after steam blowing is less.

Silencer use is compulsory.

Page 49: Steam Blowing11