steam engg and energy conservation
TRANSCRIPT
-
7/31/2019 Steam Engg and Energy Conservation
1/23
Copyright Forbes Marshall, 2006-07
STEAM ENGINEERINGAND ENERGY CONSERVATION
-
7/31/2019 Steam Engg and Energy Conservation
2/23
Copyright Forbes Marshall, 2006-07
Standard Steam Circuit - Energy Balance
Boiler ProcessPlant Plant
Power PRDS
Plant Unit
Fluegases
Blow
down
HP steam PRS unit
Condensate
losse
s
losses
Fuel
100%
15%
5%
80%
3%
55% to process
20%
2%
-
7/31/2019 Steam Engg and Energy Conservation
3/23
Copyright Forbes Marshall, 2006-07
Energy Conservation in Steam Systems
52 years of Steam Engineering experience in SteamGeneration, Distribution and Utilisation
Steam as the best source of process heat
The Cost of steam- Rs.400 to 1600 per tonne
- Anything from 5% to 50% of total
discretionary production cost
-
7/31/2019 Steam Engg and Energy Conservation
4/23
Copyright Forbes Marshall, 2006-07
Why Steam remainsthe best source of Process Heat
A plentiful raw material
Non-toxic, requiring no special handling
Requires no pumping - flows over long distances
naturally Simple temperature control, by simple pressure
control
Considerably cheaper than electricity or thermic
fluid
-
7/31/2019 Steam Engg and Energy Conservation
5/23
Copyright Forbes Marshall, 2006-07
Good Steam Engineering means
Proper sizing, insulation, routing and trapping
High pressure distribution and reduction at the pointof use
Separating condensate and venting air Proper process trapping
Condensate return
Temperature control
Efficient boiler operation
-
7/31/2019 Steam Engg and Energy Conservation
6/23
Copyright Forbes Marshall, 2006-07
Boiler Efficiency is the beginning
Excess air control
Proper capacity-utilisation and boiler balancing
Automatic blowdown control
Close performance monitoring for tube cleaning and
other maintenance
-
7/31/2019 Steam Engg and Energy Conservation
7/23Copyright Forbes Marshall, 2006-07
Making Boiler Efficiency Automatic
A textile mill operates two 10 tph boilers
Automatic blowdown control will save Rs.6.5 Lakhsper year (payback < 3 months)
Flue-gas trim can increase efficiency by 2% easily(payback < 1 year)
Shutting a third boiler run just in case saves Rs.2.5
lakhs per year
A Boiler Efficiency package pays for itself in sixmonths
-
7/31/2019 Steam Engg and Energy Conservation
8/23Copyright Forbes Marshall, 2006-07
Steam Trap Selection ...
A continuous discharge Float Trap in place of anintermittent discharge TD - upto 4 x processefficiency - payback in days
A thermostatic trap in place of a TD or FT on tracing
lines - payback in six months
A TD in place of an IB on a main-line - payback fromsaving radiation losses alone in 12 months
-
7/31/2019 Steam Engg and Energy Conservation
9/23Copyright Forbes Marshall, 2006-07
... and Steam Trap Monitoring
What is the cost of a leaking Steam Trap ?
An automatic on-line trap monitoring system for 50
critical traps will cost say 6 Lakhs One 1 trap failed open will waste that much in nine
months (8 Lakhs per year)
-
7/31/2019 Steam Engg and Energy Conservation
10/23Copyright Forbes Marshall, 2006-07
Metering for Energy-conservation
How much steam is worth metering ?
- 1 tph of steam @ 7000 hrs per year will cost
Rs.35 Lakhs (For SF boilers) and Rs 100 L (ForOF boilers)
Does usage demand high turndown ?
Density compensation is critical
- An uncompensated meter sized for 10.5 bar,operating at 7 bar will have an error > 15%
-
7/31/2019 Steam Engg and Energy Conservation
11/23Copyright Forbes Marshall, 2006-07
How Much Condensate is Worth Returning ?
1 tph of condensate at 3 bar will save Rs.6 Lakhs inthe fuel bill each year
And reduce the dearating of a 2 tph boiler from 15%to 5% (so you get a 200 kg boiler for free)
And Rs.30,000 in ones water-treatment cost for DMwater
And reduce heat-pollution And save water (about 600 tankers each year !)
-
7/31/2019 Steam Engg and Energy Conservation
12/23Copyright Forbes Marshall, 2006-07
Compressed Air - the ignored utility
Compressed Air is free, right ...
- A 1 mm hole @ 6 bar leaks Rs.80 per day or
Rs.2800 per year- A 10 mm hole @ 6 bar leaks Rs.8,000 per day !
1 mm = Corrosion leak
2 mm = Gasket leak
10 mm = Broken or cracked pipe/hose
-
7/31/2019 Steam Engg and Energy Conservation
13/23Copyright Forbes Marshall, 2006-07
Compressed Air in a Spinning Mill
5 leaks cost Rs.1 Lakh per year
Installing Reducing valves and nozzles on cleaninghoses pays for itself in days
Air separators and drain traps drastically improve
Air quality
-
7/31/2019 Steam Engg and Energy Conservation
14/23Copyright Forbes Marshall, 2006-07
Energy Conservation in a Paper Mill
The mill makes a loss of Rs.4 Crores each year
Operates at 55% of rated capacity
The problem is scaling and poor condensateremoval from the drying cylinders
An automatic dryer package (and other smallerimprovements) could save 30% of steam consumed
and almost double output A thermo-compressor can pay its way in days
-
7/31/2019 Steam Engg and Energy Conservation
15/23Copyright Forbes Marshall, 2006-07
Thermocompressors pay back quick
A 50 tpd paper machine
- A 12 Lakhs investment with documented
savings of 25 Lakhs per year
- A saving of 0.4 kg (18% minimum) per kg ofpaper
Turbine exhaust from a sugar mill to a distillery
- A 20 Lakhs investment with savings of 64
Lakhs
- Takes care of the total steam need of the
distillery
-
7/31/2019 Steam Engg and Energy Conservation
16/23
Copyright Forbes Marshall, 2006-07
The Big Things Matter
A good boiler will
- raise dry steam
- have an efficiency > 82% in normal operation
- be easy to maintain - just brushing soot out
of tubes can increase boiler output by 10%for the same fuel-input
- operate efficiently without manual
supervision
- be correctly sized for capacity (a new 2 tphboiler will pay for itself in a year if one is
using a 4 tph for future expansion) and
operated at rated pressure
-
7/31/2019 Steam Engg and Energy Conservation
17/23
Copyright Forbes Marshall, 2006-07
The Big Things Matter - 2
Thermocompressors give you steamfor free
Boiler Efficiency Analysers automates
high efficiency
-
7/31/2019 Steam Engg and Energy Conservation
18/23
Copyright Forbes Marshall, 2006-07
The Big Things Matter - 3
Metering where every last 250 kg of steam goes
Condensate return and flash steam recovery havetypical paybacks under 3 months
Trap selection, sizing and performance monitoringdirectly boosts machinery output, reduces
maintenance and downtime, and even pays for itselfin six months
Generating and distributing steam at max pressureand reducing it at the point of use
-
7/31/2019 Steam Engg and Energy Conservation
19/23
Copyright Forbes Marshall, 2006-07
The Little things mean big savings
A few Air Vents dramatically reduces cycle time byshortening start-up time in batch processes
A Separator directly increases machine output byremoving condensate and so boosting heat transfer
A Balanced-pressure trap on tracing lines harvestsome sensible heat too
A Sight glass helps one set the SLR on a trap - anddirectly increases drying machine speed
-
7/31/2019 Steam Engg and Energy Conservation
20/23
Copyright Forbes Marshall, 2006-07
The Little things mean big savings - 2
A weekly brushing of boiler tubes can save 2% ofones fuel bill
Daily monitoring of boiler efficiency and waterquality helps diagnose problems
A Deaerator Head reduces dissolved oxygen and so
reduces corrosion (=leaks!) of pipes and fittings
Automatic Blowdown Control costs < Rs 1 Lakhpays for itself in months, and improves steam quality
Fix leaks and insulation before you give us any
business !
-
7/31/2019 Steam Engg and Energy Conservation
21/23
Copyright Forbes Marshall, 2006-07
So Where Does One Start ?
Priority 1 is Housekeeping
- Leaks
- Insulation
- Air Vents- Main-line traps
- Separators to improve steam quality
Priority 2 is Trap Selection
- FTs as Process Traps - the payback is days
-
7/31/2019 Steam Engg and Energy Conservation
22/23
Copyright Forbes Marshall, 2006-07
Priorities in Energy Conservation
Third is Diagnosis
- Metering where every 1 tph and 250 kg of
steam goes
Fourth is Condensate Return and Condensate andFlash Steam Recovery
Fifth is Pressure and Temperature Control
- Are these opportunities ?
-
7/31/2019 Steam Engg and Energy Conservation
23/23
Copyright Forbes Marshall 2006 07
Priorities in Energy Conservation
And last is Capital Investment
- New Boilers and Burners- The Cogen option
- Automated plant control systems