TIMELINE STEEL BRIDGE ABOUT THE TEAM ABOUT THE MEMBERS [email protected] » Charged with designing and constructing a steel bridge. » Competes in a regional competition each year. » Follows guidelines set by the American Institute of Steel Construction (AISC) and the American Society of Civil Engineers (ASCE). » Historically, some 20 dedicated members, mainly sophomores and juniors. » Mainly civil engineering, mechanical engineering and engineering & management students. SPRING COMPETE » Present Mead Paper, Bridge Design Presentation and Bridge Display. » Construct bridge as quickly as possible. Load bridge laterally and vertically and compare time, weight and deflection to competition. SPRING BUILD » Clean, sand, cut, mill, drill and weld every bridge component in the lab. » Perform full-load and lateral tests on the completed bridge and make adjustments as necessary. FALL DESIGN » Read rule book and prioritize design in order to reduce the cost of the bridge. » Model bridge designs in Autodesk Inventor and AutoCAD and digitally test to determine optimal design.

Upload: others

Post on 02-Mar-2021

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: STEEL BRIDGE - Clarkson University · 2020. 5. 7. · TIMELINE STEEL BRIDGE ABOUT THE TEAM ABOUT THE MEMBERS STEELBRIDGE@CLARKSON.EDU » Charged with designing and constructing a

TIMELINE

STEEL BRIDGEABOUT THE TEAM ABOUT THE MEMBERS

[email protected]

» Charged with designing and constructing a steel bridge.

» Competes in a regional competition each year.

» Follows guidelines set by the American Institute of Steel Construction (AISC) and the American Society of Civil Engineers (ASCE).

» Historically, some 20 dedicated members, mainly sophomores and juniors.

» Mainly civil engineering, mechanical engineering and engineering & management students.

SPRING COMPETE

» Present Mead Paper, Bridge Design Presentation and Bridge Display.

» Construct bridge as quickly as possible. Load bridge laterally and vertically and compare time,

weight and deflection to competition.

SPRING BUILD

» Clean, sand, cut, mill, drill and weld every bridge component in the lab.

» Perform full-load and lateral tests on the completed bridge and make adjustments as necessary.

FALL DESIGN

» Read rule book and prioritize design in order to reduce the cost of the bridge.

» Model bridge designs in Autodesk Inventor and AutoCAD and digitally test to determine optimal design.