steel insight 3

Upload: cbler

Post on 03-Apr-2018

217 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/29/2019 Steel Insight 3

    1/9

    -

    STEEL INSIGHT #03

  • 7/29/2019 Steel Insight 3

    2/9

    h | Ap 2012

    The third o the Steel nsight series looks at structural solutions or ofce buildings, and

    how steel can rovide advantages in terms o cost, rogramme time and sustainability

    steel insightmulti-storey offices

    02 | Building 1 ypical business park ofce building

    01 | ntroduction and

    overview o te study

    n ovember 2011 te BCA and

    ata teel commissioned ardiner

    & eobald (&), Peter Brett

    Associates (PBA) and Mace roup

    to undertake an impartial study o

    current construction practice or

    multi-storey ofces to provide cost

    and programme guidance or quantity

    surveyors and design teams.

    e study builds on previous

    comparisons to reect developments

    in construction tecniques and

    canges in prevalence o dierent

    structural rame solutions.

    As decisions on rame material

    and confguration will be based on a

    number o actors, not simply cost, te

    study also considered te programme

    and buildability implications or eac

    option and embodied carbon impacts

    or Building 2.

    PBA identifed and designed

    representative raming solutions

    or two typical ofce buildings a

    business park ofce (Building 1) and

    a city centre ofce (Building 2). &

    provided cost inormation or eac

    rame option and Mace considered

    buildability, logistics and programme.

    PBA also carried out te cradle to

    grave embodied carbon assessment

    on Building 2.

    e objective o te study is to

    provide a compreensive comparison

    o two typical ofce buildings acrossa number o aspects or dierent

    structural solutions. e confguration

    and design o te ofce buildings

    is based on te design teams

    experience o current practice to

    provide an impartial comparison

    tat could be used by oters wen

    considering te options available

    during te design and selection o a

    structural rame.

    Building 1 is a tyical seculative three-storey

    business ark ofce building with a gross

    internal area o around 3,200m2.

    t is tyical o a low rise building in an

    out o town location and is rectangular with

    a oor late width o 18m to give an oen

    lan sace.

    The clear oor-to-ceiling height has been

    set at 2.8m and the building contains one

    central core, 2nr lits and an external metal

    escae stair. The external enveloe has been

    assumed to be brick outer skin construction

    suorted by a steel angle o the slab

    edge with an inner lea o cold rolled metal

    studwork built directly o the slab, with an

    allowance or windows at 35% o the

    acade area.

    The building has been assumed to have

    mixed mode ventilation and the oor-to-

    oor heights include or a 150mm ceiling and

    lighting zone and a 150mm raised oor zone.

    An architects imression, roduced by

    Make Architects, is shown above.

    pBA established the structural grid at 7.5m

  • 7/29/2019 Steel Insight 3

    3/9

    POOReD FeAURe | April 2012

    03 | Buildin 1 Cost comparison

    gardinr & hobald providd th costs

    or th study, basd on markt tstin and

    rcntly tndrd projcts. Costs ar all at

    Q1 2012 prics, xclud s, VA, projct

    continncy and urnitur, fxturs and

    quipmnt/AV allowancs tc and ar

    basd on construction in th City o ondon

    to nabl dirct comparison with Buildin

    2; howvr thy can b adjustd or dirnt

    locations usin BC location actors

    (Fiur 7).

    h study rconiss th importanc o

    considrin all lmnts o th total buildin

    cost, not simply th cost o th structur

    as som lmnts ar actd mor by th

    choic o structural ram than othrs. As

    such, th study considrd whol buildin

    cost rathr than just structural ram cost.

    h substructur, roo and xtrnal claddin

    costs wr assssd or ach option rathr

    than includin constants across all options.

    h ky costs or Buildin 1 xprssd as a

    cost pr m2 ross intrnal oor ara (gFA)

    ar shown blow (Fiur 1).

    h impact o construction proramm

    or ach option has bn considrd in th

    total buildin costs, with th stl options

    bnfttin rom lowr prliminaris

    costs du to thir shortr construction

    proramms (as rviwd in dtail ovrla).

    h stl composit bam and slab option

    has both th lowst ram and uppr oors

    cost and lowst total buildin cost. his

    option has th lowst substructur costs o

    all ram options du to th lihtr ram

    wiht and th lowst roo cost du to thlihtwiht stl roo dck. h structural

    zon and oor-to-oor hiht, whil not th

    lowst o all th options, dos not rsult in

    lvatd claddin costs as only th concr

    post tnsiond at slab option has a notab

    lowr oor-to-oor hiht and thror

    rducd ara o claddin.

    Convrsly, th rinorcd concrt at

    slab option has both th hihst ram

    and uppr oors cost and hihst ovrall

    buildin cost. h ram and oors cost is

    ovr 10% hihr than th stl composit

    and th total buildin cost is about

    6% hihr. his option has th hihst

    substructur costs du to th havir ram

    wiht, th hihst roo and prliminaris

    costs du to th lonst proramm.

    A rviw o th stl and prcast concr

    slab and post tnsiond at slab concrt

    options also hihlihts th importanc o

    considrin total buildin cost rathr than

    just ram and oor costs whn analysin

    and slctin th structural ram matria

    durin th dsin stas. h post tnsion

    option has a marinally lowr ram and

    oor cost than th stl and prcast optio

    (150/m2 compard with 151/m2), howv

    on a total buildin basis, th stl and

    prcast slab option has a lowr cost (1,56

    m2 compard with 1,610m2), du to both

    a lowr roo cost and lowr prliminaris

    rsultin rom th shortr proramm.

    hror, on comparison o all our

    options, it is vidnt that on a lik or lik

    basis th stl composit bam and slab

    ram has th lowst ram and oor and

    ovrall buildin cost, ollowd by th

    stl and prcast concrt oor slaboption with th two concrt options

    bin hihr.

    tl Composit tl and Prcast Rinorcd Concrt Post nsiond Concrt

    Concrt labs Flat lab Flat lab

    bstrctre 52/m2 gifA 55/m2 gifA 67/m2 gifA 62/m2 gifA

    frame and upper floors 140/m2 gifA 151/m2 gifA 155/m2 gifA 150/m2 gifA

    Total Building 1,535/m2 GIFA 1,561/m2 GIFA 1,631/m2 GIFA 1,610/m2 GIFA

    FiGur 1: coSTS For BuildinG 1 BASd on GroSS inTrnAl Floor ArA (GiFA)

    x 9m base a tmm g f a tya

    bsess ak fe t tate by ste

    stats a ths was se f a fame

    tyes, whh sste f the fwg

    f ts:

    1) Stee mste beams a mste sab

    2) Stee fame a east ete sabs

    3) refe ete at sab

    4) i st ete fame wth st

    tese sab

    F a ts the fats have bee

    esge as efe mass ete

    as, the e stt s steewk

    ss bae famg wth a mem esty

    bkwk f the stee ts a

    ete shea was f the ete ts.

    F bth stee ts, the 30 mte e

    esstae s ve thgh tmeset

    atg t beams a bag membes a

    bag t ms, whe f the ete

    ts, t s assme that the tea

    ms ae astee a ate f

    aesthet ses.

    Awaes have bee mae f a ts

    f a at e a at ese f at

    aea a ft mt m. i tems f f

    stt, the tw stee fame ts

    have a ghtweght stee ek f, whe the

    ete ts te the ete sab

    stt f the we s.

    The -t- heghts f the stee

    ts e a 800mm seve ze

    bew the meta ek (300mm ea

    beeath the beams) a the etets aw f a 600mm seves ze

    beeath the sab.

  • 7/29/2019 Steel Insight 3

    4/9

    A 2012

    o inform the programmes, Mace

    undertook a logistics analysis for each

    o t e rame opt ons an t s as een

    reected in total building costs through

    the preliminaries analysis.

    For both steel options, construction

    is assumed to be phased, with the

    excavat on, oun at ons, ra nage an

    service ducts, ground oor slab anderection of the steel frame and steel or

    precast decks occurring in four phases.

    A single mobile crane (about 50 tonnes)

    s use or mater a str ut on an

    loading as full perimeter access to the

    building is available and the placing of

    concrete or structural screed to oors

    would utilise a concrete pump.

    or ot concrete opt ons,

    construction is assumed to occur

    across two zones, each consisting of

    three phases. h sequence includes

    the excavation, concrete foundations,

    drainage and service ducts, ground

    oor slab, reinforced concrete columns,

    formwork and propping for slabs,

    re n orcement o post tens one

    strands and placing of insitu concrete

    slabs using a concrete pump. Atower crane located centrally on the

    building perimeter is assumed to be

    t e most pro uct ve means o mater a

    str ut on as mater a can t en e

    distributed between both construction

    zones. he cost of the tower crane base

    has been included in the preliminaries

    costs owever t s ou e note t at

    t ere may e oversa ng ssues w t a

    saddle jib crane.

    05 | Bu ng 1 og st cs an u a ty06 | u ng 1

    The cost and programme analysis of

    all four frame options for Building 1

    has shown that the steel composite

    eam an oor op on as o

    the lowest cost and the shortest

    programme, followed by the steel and

    precast concrete oor slab option.

    The frame and oor cost for the

    s ee rame op ons are up o

    lower than for concrete and theoverall building cost is up to 6%

    lower than for concrete. ven taking

    an average of the two steel options

    an an average o e wo concre e

    options, the steel option costs are

    over 4% lower for both frame cost and

    total building cost.

    Furthermore, both steel framed

    op ons can a so e cons ruc e n

    a shorter time frame than for the

    concrete buildings, on average over

    5% quicker.

    04 | u ng 1 Programme compar son

    ost s un ou te y a e y r ver n

    decision making when comparing

    alternative frame materials and

    congurations. wever for many

    projects, the comparative programme

    an u a ty mpacts are argua y as

    important and should also be considered

    when selecting the frame material.

    Mace undertook the programming

    analysis for each option and to ensure

    a ro ust compar son, prece ng an

    succeeding trades to the frame elements

    were included to ensure a holistic

    approach to the study.

    he programme durations for

    construction of the ground oor slab

    (two weeks four days), external facade

    (15 weeks) and internal works to a CA A

    nish (18 weeks per oor) were assumed

    to be the same in overall duration for

    eac opt on. stu y assumes t at t e

    internal t out commences on the ground

    oor and progresses up the building

    with a lag of three weeks between the

    commencement o t e next oor, g v ng

    an overall duration of 24 weeks for

    each option.

    e su structure urat on was a so

    considered in detail for each option. Both

    steel options required nine weeks due

    to the similar quantity of work, however

    onger urat ons o wee s t ree ays

    for the reinforced concrete at slab and

    10 weeks for the post tensioned option

    were required to reect the higher volume

    of groundworks.

    e programmes or t e rame an

    upper oor construction are similar for

    both steel options. he precast slab

    requires slightly larger foundations than

    the composite option, but this is largely

    o set y t e re uce num er o s tee

    members in the precast option, giving an

    overall very similar programme.

    ikewise, it is quicker to lay the steel

    decking for the steel composite option

    ue to t e a ty to oa out mu t p e

    numbers of decks at any time while the

    precast planks are limited to one per lift,

    but this time advantage is offset due to

    the time required to stud weld each of

    t e ec s, w c s a s ower process t an

    grout lling between the precast planks

    and both then require a concrete topping.

    Ultimately, the advantages and

    isadvantages of each steel option largely

    ancel each other out providing very

    similar programme periods for both the

    rame an overa construct on. stee

    omposite option however, due to the

    speed of laying and distributing the steel

    ecks provides the quickest frame and

    verall duration by one week.

    e programmes or t e rame an

    upper oor construction are also similar

    for both concrete options as the processes

    involved in constructing the structure

    re fundamentally the same. he main

    var ant s w t n t e s a construct on,

    with the post tensioned option providing

    slightly quicker duration overall due to

    the lower quantity of reinforcement to

    place. he foundations duration for the

    post tens one opt on s a so qu c er as

    the structure is lighter and therefore the

    xtent of excavation and concrete pouring

    to the foundations is less.

    a our opt ons, t e stee compos te

    frame provides the fastest method of

    frame construction and overall programme

    for Building 1.

  • 7/29/2019 Steel Insight 3

    5/9

    s sh A 2012

    Building 2 is a typical eight-storey speculative

    city centre ofce building with a gross

    internal area o around 16,500m . is

    s ape w a ou e e g recep on area,

    central core and internal secondary escape

    stair. The clear oor-to-ceiling height has

    been set at 3m.

    The external envelope is a unitised curtain

    wa sys em cons ruc e n s orey e g

    panels 1.5m wide with eature fns solarcontrol. Solid areas are lined with cold rolled

    metal studwork, insulation and plasterboard.

    The building has been assumed to have

    our p pe an co a r con on ng w ou

    natural ventilation.

    An architects impression and indicative

    cutaway, produced by Make Architects, are

    shown above and overlea.

    es a s e e s ruc ura gr a . m

    x 15m based on experience o similar city

    centre schemes, and this was used or both o

    the ollowing rame options:

    07 | uilding 2 pical city centre ofce building

    ) ellular composite beams and

    composite slab

    2) ost tensioned band beams and slab,

    n s u co umns

    Both options adopt A piles and there

    are typically three to our piles per column

    pile cap. The core construction is steel cross

    race ram ng w a me um ens y

    blockwork infll or the steel option andconcrete shear walls or the concrete option.

    t is noted that buildings o this type would

    normally include a basement; however or

    con nu y e ween e op ons, e u ngs

    are assumed structurally to start rom ground

    oor with no impact rom any basement

    construction as the basement will be the

    same construction or all options.

    e m nu e re res s ance s prov e o

    he steel ramed option through intumescent

    coating to beams and bracing members

    and boarding to columns, while the internal

    columns o the concrete option are plastere

    and painted or aesthetic reasons.

    Allowances have been made to both

    op ons or a par open an par enc ose

    roo plant area and lit motor room. The pla

    area is a abricated steelwork portal rame

    with composite metal panel cladding and th

    roo decks or both options continue the o

    cons ruc on o e ower oors.

    The overall oor-to-oor height or thesteel option is 4.18m, which includes a

    700mm zone or services distribution throu

    the beams with 400mm diameter holes

    a owe a mm cen res.

    The overall oor-to-oor height or the

    concrete option is 4.375m, which includes a

    475mm clear zone below the concrete band

    beams or services distribution.

    o op ons a s o nc u e a owances

    within the oor-to-oor heights or a 150mm

    ceiling and lighting zone and a 200mm

    raised oor zone.

  • 7/29/2019 Steel Insight 3

    6/9

    h Apr 2012

    08 | Building 2 Cost comparison

    09 | Bu ng 2 Programme

    compar son

    Mace also undertook te programming

    analysis or Building 2, analysing bot

    te rame and te wole building

    construction durations (see Figures 3

    an ).

    e substructure works commence

    wit te CFA piling, ollowed by

    excavation or te pile caps and

    lit pits. For te steel option, te

    structura rame s erecte on a

    foor by foor basis wit te steel

    decking installation, stud welding and

    concrete foor toppings ollowing on

    progressively.

    or t e concrete opt on,

    te columns and walls progress as

    soon as te ground foor slab is cast,

    and eac foor slab is constructed in

    two pours, wit te concrete sear

    wa s comp ete progress ve y w t

    eac foor.

    e durations or construction o

    te ground foor slab (our weeks

    t ree ays), externa aca e

    wee s) an nterna wor s to a

    A nis (21 weeks per foor) were

    assumed to be te same or eac

    option. e internal t out is assumed

    to commence on t e groun oor

    an progress up t e u ng w t

    a lag o two weeks between te

    commencement o te next foor,

    giving an overall duration o 39 weeks

    or eac opt on.

    e t e su structure an groun

    slab construction ave te same

    programme period (20 weeks) or

    eac option, te steel rame as

    a s gn cant y s orter rame an

    foor construction period (16 weeks

    compared wit 28 weeks or teconcrete option), wic enables te

    internal t out works to start earlier.

    s resu ts n t e ce u ar stee

    option providing a signicantly

    sorter period o bot rame

    construction and overall programme

    or Building 2 compared wit te post

    tensone concrete opt on, w t a

    saving o 12 weeks demonstrated or

    te rame and eigt weeks across te

    overall programme.

    eel Cellular Composite Post ensioned Concrete

    B nd Beam and lab

    s rc re 56 m2 60 m2

    ame and l 194 m2 210 m2

    otal Bilding 1,861 m G ,922 m G

    G re 2: STS G 2 AS G SS r (G )

    tnsiond conct band bam otion. n a

    total bilding basis, th stl otion bnfts

    om ow s s c cos s o

    light am wight and a low oo cost

    d to th cost o th stl dck comad

    with th ost tnsiond slab.

    Th stl otion has a low oo-to-

    oo g . m coma w . m

    which slts in abot a 5% low xtnal

    nvlo cost d to th small aa o

    cladding and also has low liminais

    costs d to its shot ogamm, which

    con s o s ows ova cos .

    all, th am and oo cost o thstl otion is ov 8% low than th

    conct otion and ov 3% low on a

    whol bilding basis.

    Th Bilding 2 cost stdy also considd

    whol bilding cost alongsid am and

    oo cos s, w s s c , oo a n

    xtnal nvlo viwd in dtail, howv

    basmnt costs hav bn xcldd om

    th stdy. As th am matial choic also

    mac s on ogamm, s s o

    ac ogamm an ogs cs ana yss

    w also incldd whn dtmining

    liminais costs.

    All costs a at Q1 2012 ics and a

    as on cons c on n y o n on.

    Th ky costs o Bilding 2 xssd as a

    cos m A a shown blow.As shown, th cllla stl comosit

    otion has both a low am and oo cost

    and low total bilding cost than th ost

  • 7/29/2019 Steel Insight 3

    7/9

    | A 2012

    10 | Building 2 ogistics and buildability

    he assumed logistics for both the

    cellular steel and post tensioned concrete

    options are similar, with the substructure

    works progressing from the main core

    pile caps working out in two directions

    for both options.

    Both frames would also utilise a lufng

    jib tower crane (about 50m radius)

    situated outside of the building footprint,

    used for distribution of the steel frame

    and oor decking for the steel option

    and for reinforcement and formwork

    distribution for the concrete option.

    he lufng jib also helps to overcome

    oversailing issues common in city

    centres.

    he superstructure works for the

    concrete option were assumed to

    progress in two phases with two or

    three pours required for the oor slabs.

    Pumps would be used for the placing

    of the oor slab concrete for the post

    tensioned option and for the lightweight

    concrete topping for the steel option and

    both options utilise an external hoist for

    t out material vertical distribution.

    11 | Building 2 mbodied carbo

    comparison

    While cost and programme are key criteria

    assessing design options for many projects

    the comparative environmental credentials

    are also important. BA therefore carried

    ot an embodied carbon assessment for

    both frame options for Bilding 2.

    mbodied carbon is considered to be

    the cradle to grave carbon dioxide (2)

    emissions occrring over the whole life

    cycle of the bilding, inclding end of life

    considerations bt exclding the operation

    carbon occrring dring the bilding se.

    The stdy adopts a similar approach to

    the cost stdy by considering the whole

    bilding rather than jst the strctral fram

    for each option; however it focses on the

    emissions from the strctral elements as

    they represent the main differences in term

    of carbon between the options.

    To ensre a balanced approach, readily

    available indstry data on materials

    emissions from Target Zero pblications fo

    steel and from oncrete entre pblication

    for concrete have been adopted. on-

    strctral embodied carbon emissions hav

    been based on benchmark information and

    are consistent across both frame options.

    Transport emissions are based on the

    epartment for Transport statistics for the

    average length of hal per commodity and

    on oncrete entre data on the average

    delivery distance of ready-mixed concrete

    constrction sites.

    n assessing the emissions from the

    constrction and demolition activities on

    site, uK nvironment Agency data, the Mac

    constrction programming information and

    an estimated period for demolition have

    been considered.

    n considering cradle to grave emissions

    for each option, end of life scenarios have

    been selected to reect crrent practice,where 99% of the strctral steel and 82%

    of the concrete reinforcement are recycled

    and 100% of the concrete is down-cycled t

    provide granlar ll material.

    The reslts of the stdy are shown in

    Figre 5 overleaf.

    BA rstly assessed the bildings in

    line with the cost stdy and sing only

    ortland ement for the concrete mix, whi

    demonstrated that the embodied carbon

    was signicantly lower for the steel frame

    than that for the concrete frame; with the

    FGu 3: BuG 2 uA ST MST FAM GAMM

    Grondworks and Slab

    Steel Frame and ecks

    Slab ors

    oof Works

    xternal Facade

    nternal Works

    elllar Steel omposite

    0 10 20 30 40 50 60 70 80

    72.4

    20.4

    16.4

    16

    39.2

    12

    5

    FGu 4: BuG 2 ST TS BA BAM FAM GAMM

    Grondworks and Slab

    oncrete Frame and Slabs

    oof Works

    xternal Facade

    nternal Works

    T oncrete Band Beam

    0 10 20 30 40 50 60 70 80 90

    80.3

    20.4

    16

    39.3

    28.3

    5

  • 7/29/2019 Steel Insight 3

    8/9

    | A 2012

    12 | ummary and conclusion

    he study illustrates that or both

    typical ofce building types, on

    a like or like basis steel ramed

    solutions are highly competitive,

    with the rame and upper oor costs

    or the steel ramed options being

    potentially up to 9% lower than

    or concrete.

    he study has also highlighted

    the importance o considering total

    building cost not just structural rame

    cost, as the choice o the structural

    rame material and confguration

    will have associated impacts on

    many other elements, including

    the substructure, roo and external

    cladding. he total building cost

    or the steel options are on average

    around 5% lower than the concrete

    options as a result o the rame and

    upper oor costs noted above and

    smaller oundations, lightweight

    roos, lower storey heights reducing

    cladding costs and reduced

    preliminaries costs.

    Furthermore, the construction

    durations o the steel ramed

    solutions are also shorter than the

    concrete ramed buildings (up to 13%

    or Building 1 and 11% or Building 2).

    he study also considers embodied

    carbon, which is projected to become

    an increasingly important criterion

    or design options moving orward.

    he study shows that in this area as

    well, steel ramed solutions have

    a noticeably reduced embodied

    carbon compared with the concrete

    solutions, with an 18-30% lower

    embodied carbon total or the

    cellular steel option than the post

    tensioned band beam option orBuilding 2.

    Over three key assessment

    criteria, the study has illustrated

    that steel ramed solutions in current

    construction practice can outperorm

    concrete options and provide

    lower cost, shorter programmes

    and lower embodied carbon.

    More detail on the study can be

    ound at www.steelconstruction.org

    steel option having over 23% less embodied

    carbon than the concrete option.

    However, refecting the common practice

    o sing cement replacement to redce

    sstainability impacts, the embodied

    carbon was also assessed sing 30% cement

    replacement with fy ash and grond

    granlated blast rnace slag. This level

    o cement replacement is considered to

    be a reasonable replacement withot

    having a signicantly adverse impact on

    constrction programme de to increased

    cring time.

    n this case, the embodied carbon redced

    to 184kg2/m2 or the steel option and

    to 204kg2/m2 or the post tensioned

    concrete option. Thogh the dierence

    between the steel and concrete options

    was redced, it was still signicant with

    the steel rame having arond 11% less

    embodied carbon than the post tensioned

    concrete rame.

    Finally, the impact o sing steel bearing

    piles on the embodied carbon or both

    rame options was also assessed based on

    alternative sbstrctre soltions developed

    by BA and Tata Steel which tilised 356 x

    368 x 152 uKB in lie o FA piles.

    The se o steel bearing piles reslts in

    an increased nmber and length o piles or

    both rame options, rom 147nr (2,490m) to

    190nr (3,984m) or the steel rame and rom

    150nr (3,225m) to 241nr (5,400m) or the

    concrete option; however, there are osets

    in terms o a signicant redction in the size

    o pile caps and associated redctions to

    excavation and disposal or both options.

    The steel bearing piles can also be

    extracted at end o lie and recycled or

    re-sed elsewhere.

    While the se o steel bearing piles

    does have a cost implication, with the

    sbstrctre costs or the steel option

    increasing rom 56/m2 to 71/m2 and rom

    60/m2 to 90/m2 GFA or the concrete

    option, some o this will be oset throgh

    programme benets and they can also

    deliver embodied carbon benets. n a

    sbstrctre only basis, the embodied

    carbon redces by 15% or the steel ramed

    option and by 5% or the concrete option

    and across the whole bilding, the

    embodied carbon redces to 195kg2/m2

    or the steel option and to 250kg/2/m2

    or the post tensioned concrete option in

    the base case scenario. This demonstrates

    that where sstainability is a key driver,

    signicant benets cold be realised by

    the consideration o a steel bearing pile

    sbstrctre soltion.

    elllar Steel omposite ost Tensioned Band Beam oncrete

    FGu 5: BuG 2 A T GA MB AB MAS

    300

    250

    200

    150

    100

    50

    0

    k

    gco

    2/m2

    253

    205

    184

    204195

    250

    ost Stdy 30% ementeplacement

    Steel Bearing iles

  • 7/29/2019 Steel Insight 3

    9/9

    g | A 2012

    his article was produced by Rachel

    Oldham (associate) and Alastair

    Wolstenholme (partner) of gardiner &

    heobald. t is the third in a series that

    provides uidance on the realistic costin

    of structural steelwork. he next teel

    nsiht will appear on 27 July 2012. f you

    are considerin usin structural steelwor

    for your buildin, bride or structure,

    we recommend an early dialoue witha specialist steelwork contractor. hey

    can offer a rane of support and advice,

    includin budet estimates and value

    enineerin. teelwork contractors can

    be sourced accordin to project size and

    technical competency. his searchable

    function is available at

    TH ST SGHT SS

    WWW.CORUCO.ORg

    13 | ost update

    The results of the comparison study are

    reected in the latest structural steelwork

    cost table ranges in Figure 6.

    The cost range for the low rise, short span

    building (Building 1) has remained constant

    across Q1 2012, which reects the continuing

    difcult market conditions throughout the

    construction industry generally.

    Following the production of typical designs

    for the two building types, the description

    and rate range for the high rise, long span

    frame noted in the table has been updated

    to align with Building 2. However, it should

    be noted that for high rise or long span

    structures with more complex elements or an

    irregular grid the rate range would need to

    be adjusted accordingly, and could be 15-20%

    higher than those noted for Building 2. To

    address this, a further frame type has been

    included within Figure 6.

    Similarly, the ranges for oor costs and

    re protection have been adjusted to align

    with the results of the cost study and market

    testing, with the oor costs for both the

    metal deck and precast options reducing by

    around 15%.

    The continual forecasts of difcult

    economic conditions across 2012 continues

    to suggest that structural steelwork tender

    returns will remain stable well into 2012,

    ocation BC ndex ocation BC ndex

    ity of odo 114 eeds 100

    nottigham 97 newcastle 94

    Birmigham 99 lasgow 102

    achester 94 Belfast 61

    iverpool 90 ardiff 94

    FG 7: BS AT FATS, AS AT 23 MAH 2012

    FG 6: AT ST AGS BAS GSS TA F AA

    P

    Frame - low rise, short spans, repetitive

    rid / sections, easy access (Buildin 1)

    Frame - hih rise, lon spans, easy access,

    repetitive rid (Buildin 2)

    Frame - hih rise, lon spans, complex

    access, irreular rid, complex elements

    Floor - metal deckin and lihtweiht

    concrete toppin

    Floor precast concrete composite oor

    and toppin

    Fire protection (60 min resistance)

    Portal frames low eaves (6-8m)

    Portal frames hih eaves (10-13m)

    gFA Rate ()

    City of ondon

    90 - 120/m2

    140 - 170/m2

    165 - 190/m2

    45 - 65/m2

    50 - 70/m2

    8 - 16/m2

    55 - 75/m2

    65 - 90/m2

    gFA Rate ()

    BC ndex 100

    75 - 100/m2

    125 - 150/m2

    145 - 170/m2

    40 - 58/m2

    45 - 60/m2

    7 - 14/m2

    45 - 65/m2

    55 - 75/m2

    and the rates in Figure 6 can be considered

    suitable for the cost planning of projects

    where the structural works will commence i

    Q2 and Q3 2012.

    To use the table a) identify which frame

    type most closely relates to the project und

    consideration b) select and add the oor

    type under consideration c) add re

    protection if required.

    As highlighted in previous Steel nsights,

    before using such standard ranges it is

    important to conrm the anticipated frame

    weight and variables such as the oor-to-o

    heights with the design team to determine

    whether they are above or below the averag

    and to adjust the rate used accordingly.

    Similarly, all of the other key cost drivers o

    complexity, site conditions, location, functio

    logistics, programme and procurement

    strategy should be considered in turn.