step 3. creation of very simple pipe (eng)

6

Click here to load reader

Upload: ravindra-vishe

Post on 04-Apr-2015

32 views

Category:

Documents


4 download

TRANSCRIPT

Page 1: Step 3. Creation of Very Simple Pipe (Eng)

PDMS tutorial from Said: Step 3. Creation of very simple pipe

This tutorial created by Said Babanli (Azerbaijan). (Created on 28.10.08) Please send comments or additional info to mail: [email protected]

Step 3. Creation of very simple pipe First of all, enter to piping mode Design Pipework. From menu select Create Pipe. Type pipe name in field Name. If required change Specification and Attributes.

Click OK. Now program requires entering branch name. By default it is b1.

Set Explicit in list Head/Tail settings and click OK.

Page 2: Step 3. Creation of Very Simple Pipe (Eng)

PDMS tutorial from Said: Step 3. Creation of very simple pipe

This tutorial created by Said Babanli (Azerbaijan). (Created on 28.10.08) Please send comments or additional info to mail: [email protected]

Select Head and enter all coordinates. Enter Nominal bore and Direction (direction is way from head along nearest element of current branch. Currently this id East. If take into account that both ends is flanged and we don’t know defined connection to other piping elements (nozzle, tee ….) and we know only coordinates we will select 150# RF flange in Connection. Then click Apply.

Now select Tail. Fill all info about coordinates, connection type, and nominal bore. In case Direction that is defining same way but from tail along close section of branch. In this case is W. and Apply and you will see next picture.

Page 3: Step 3. Creation of Very Simple Pipe (Eng)

PDMS tutorial from Said: Step 3. Creation of very simple pipe

This tutorial created by Said Babanli (Azerbaijan). (Created on 28.10.08) Please send comments or additional info to mail: [email protected]

We can see now pipe. But if your pipe straight and have different direction you will see only dash line. Now required to install components (flanges, valves, tees). We need install 2 flange and gaskets at the both ends of pipe. From main menu Create Components..

There a lot of components. We need to select Assembly (flange and gasket). If you want to start installation of components from head to tail (normally have to be so), select option Forwards. If from tail to head – Backwards. Select Auto conn to automatically connection to previous components or head and tail of pipe. Direction in list (Direct N) is not applicable to Assembly. It has a meaning for elbows to show correct direction of end and where to connect – Thro head. And click Create.

Page 4: Step 3. Creation of Very Simple Pipe (Eng)

PDMS tutorial from Said: Step 3. Creation of very simple pipe

This tutorial created by Said Babanli (Azerbaijan). (Created on 28.10.08) Please send comments or additional info to mail: [email protected]

Select Gasket flange to head and Apply.

Select type of flange. This option can be different because of local database installed by Admin.

Page 5: Step 3. Creation of Very Simple Pipe (Eng)

PDMS tutorial from Said: Step 3. Creation of very simple pipe

This tutorial created by Said Babanli (Azerbaijan). (Created on 28.10.08) Please send comments or additional info to mail: [email protected]

A you can see flange is already installed. Lets install to tail.

Apply

Ok

Page 6: Step 3. Creation of Very Simple Pipe (Eng)

PDMS tutorial from Said: Step 3. Creation of very simple pipe

This tutorial created by Said Babanli (Azerbaijan). (Created on 28.10.08) Please send comments or additional info to mail: [email protected]

So very simple pipe is done.