Page 1: Stockton Infrared Thermographic Services, Inc. · PDF fileStockton Infrared Thermographic Services, Inc. presents ... at the facilities of. Stockton Infrared ... Infrared Thermography

Stockton Infrared Thermographic Services, Inc. presents

A Qualitative A Qualitative Infrared Thermographic Survey Infrared Thermographic Survey

Of Electrical SwitchgearOf Electrical Switchgearat the facilities ofat the facilities of

Page 2: Stockton Infrared Thermographic Services, Inc. · PDF fileStockton Infrared Thermographic Services, Inc. presents ... at the facilities of. Stockton Infrared ... Infrared Thermography

Stockton Infrared Thermographic Services, Inc.

8472 Adams Farm RoadRandleman, NC 27317-7331

(800) 248-7226

January 1, 2005

Mr. Kevin StephensonAcme Widget Company123 Main StreetAnytown, USA 12345(555) [email protected]

Dear Mr. Stephenson:

Thank you for your continued confidence in our services. Please find herein, the results of the qualitative infrared thermographic survey which was conducted at your facilities.

This report is respectfully submitted for your review.

SECTIONS CONTENTSSECTION 1 ………Cover letterSECTION 2 ………Summary & RecapSECTION 3 ………Data Log (complete list of equipment inspected)SECTION 4 ………Thermographic Reports (problem equipment found)SECTION 5 ………Repair Guide (list of problem equipment and severity rating)ENCLOSED ………CD-ROM (contains all files and software to open IR images)ENCLOSED ……...VHS Video tape (all equipment-not just problem equipment)

IMPORTANT NOTICE: Infrared Thermography is not a substitute for visual and/or other instrumental inspection techniques and should be a regular part of the overall P/PM (preventive/predictive maintenance) program at your facilities.

All work performed by Stockton Infrared is 100% satisfaction guaranteed. If you have a question or comment please let us know by calling (800) 248-7226. We are looking forward to working with you on your next scheduled survey.

Sincerely yours,

Certified Infrared Thermographer #3583GRS/vcs

RE: Infrared Survey of Electrical SwitchgearAcme Widget Company – Plant #2Anytown, USA

Visit us on the World Wide Web at:

www.stocktoninfrared.comwww.ElectriSCAN.com

Page 3: Stockton Infrared Thermographic Services, Inc. · PDF fileStockton Infrared Thermographic Services, Inc. presents ... at the facilities of. Stockton Infrared ... Infrared Thermography

SECTION 2A SUMMARY

Project InformationReport to : Kevin StephensonCompany : Acme Widget Company

Plant ID : Plant #2Plant Location : 123 Main StreetCity, Zip Code : Anytown, USA

E-SCAN Project : EGS40101GSThermographer : Greg Stockton, CIT #3583

Notes: Please read the Data log section of this report under "Remarks".• Some panel covers were not removed.• Some repairs were made by electrician during the survey.• Emmissivity settings = 1.0 unless otherwise noted.

SECTION 2B RECAP OF FINDINGS(NR) Not Rated = 2

(M) Minor = 12(A) Alert = 15

(S) Serious = 13(C) Critical = 10

TOTAL = 52

OV= Overview(s)NO=Not OperatingMCR=Motor Control RoomNS=Not SurveyedMCC= Motor Control CenterLO=Locked OutTO=Tagged Out

A=Amperage MTS=Manual Transfer Switch ATS=Automatic Transfer SwitchOH=OverheatingDNRC=Did not remove coverCNTR=ContactorCS=Combination Starter

(US) = Upstairs(DS) = Downstairs(F) = Front view(R) = Rear view(S) = Side view

KEY to Data Log Abbreviations

Page 4: Stockton Infrared Thermographic Services, Inc. · PDF fileStockton Infrared Thermographic Services, Inc. presents ... at the facilities of. Stockton Infrared ... Infrared Thermography

FINISHING/FM #1 Panel PDP2-E/Overview 11:11:19FINISHING/FM #1FINISHING/FM #1 DC Drive Cabinet FM1-2/OV 11:16:10 Ch. Load/PhaseFINISHING/FM #1 B BreakerFINISHING/FM #1 Cntrl FM1-3/Predryer Oven 11:21:55FINISHING/FM #1 Cntrl FM1-3/Predryer Main 11:24:04 2FINISHING/FM #1 Cntrl Pnl FM1-3/Predryers 11:27:50 Check Fuse ClipFINISHING/FM #1 74K1/Phase AFINISHING/FM #1 Cntrl Pnl FM1-3/Tenters 11:30:02FINISHING/FM #1FINISHING/FM #1 Cntrl Pnl FM1-1/Main Brkr 11:32:39 Main PanelFINISHING/FM #1 Cntrl Pnl FM1-1/Wash Sctn 11:33:15 Door #1FINISHING/FM #1 Cntrl Pnl FM1-1/Wash Sctn 11:33:54 Door #2FINISHING/FM #1 Cntrl Pnl FM1-1/MS-0610 11:36:00 3 Door #2FINISHING/FM #1FINISHING/FM #1 Cntrl Pnl FM1-1/Wash Sctn 11:38:29 Door #3FINISHING/FM #1 Cntrl Pnl FM1-1/Brkr MS0610 11:44:38 4 Door #3FINISHING/FM #1FINISHING/FM #1 Cntrl Pnl FM1-1/Wash Sctn 11:47:33 Door #4FINISHING/FM #1 Cntrl Pnl FM1-1/Wash Sctn 11:47:59 Door #5FINISHING/FM #1FINISHING/FM #1 Motor MS 0610/Overview 11:50:04 Trend TempFINISHING/FM #1FINISHING/FM #1 Cntrl Pnl/Brusher Cabinet 11:53:29FINISHINGFINISHING/FM #2 Cntrl Pnl FM2-3/Brshr Cab. 11:56:04FINISHING/FM #2FINISHING/FM #2 Control Pnl/FM 2 Winder 11:57:00

PRINTING/BATTERY CHRGRS Panel LP-2/Overview 12:44:28PRINTING/BATTERY CHRGRS Panel LP-2/Circuits 14 & 16 12:48:54 5PRINTING/BATTERY CHRGRSPRINTING/BATTERY CHRGRS Panel RP-2/Overview 12:53:33

BOILER RM/115VAC PNL Panel/Overview 13:05:35 Rise On LoadBOILER RMBOILER RM/PNl PDP1-C-A Panel/Overview 13:09:09BOILER RMBOILER RM/AIR CMPRSSRS Starter Pnl/Sullair Cmprssr 13:10:54BOILER RM/AIR CMPRSSRSBOILER RM/AIR CMPRSSRS Strtr Pnl/Gard Dnvr Cmprssr 13:12:13BOILER RM/AIR CMPRSSRSBOILER RM/AIR CMPRSSRS Strtr Pnl/Ing. Rand Cmprssr 00:00:00 Locked Out

Example D

ata Log Page

Page 5: Stockton Infrared Thermographic Services, Inc. · PDF fileStockton Infrared Thermographic Services, Inc. presents ... at the facilities of. Stockton Infrared ... Infrared Thermography

BOILER RM/PNL PDP1-F Panel/Overview 13:14:19BOILER RMBOILER RM/FEED WATER Comb Strtr/Feed Water Pmp 1 00:00:00 Not OperatingBOILER RMBOILER RM/PNL PDP1-C Panel/Overview 13:16:27BOILER RMBOILER RM/FOG SYSTEM Disc/Filter Pump #1 00:00:00 Not OperatingBOILER RM/FOG SYSTEM Disc/Filter Pump #2 00:00:00 Not OperatingBOILER RM/FOG SYSTEM Disc/Filter Pump #3 13:19:36BOILER RMBOILER RM/AIR CMPRSSRS Strtr Pnl/Joy Air Cmprssr 00:00:00 Not OperatingBOILER RM/AIR CMPRSSRSBOILER RM/AIR CMPRSSRS Disc/Air Dryer 13:22:30 Rise/LoadBOILER RMBOILER RM/BOILER #1 Control Pnl/Blower 13:24:16

MAINT. OFFICES/PNLS Panel PP-8-C/Overview 13:28:45MAINT. OFFICES/PNLSMAINT. OFFICES/PNLS Panel RP-15/Overview 13:31:16MAINT. OFFICES/PNLS Panel RP-15/Circuit #21 13:32:37 6

FINISHING/PNL LP-8 Panel/Overview 13:45:35FINISHING/PNL LP-8 Panel/Circuit #9 13:47:27 7FINISHINGFINISHING/PNL RP-7 Panel/Overview 13:50:11 Rise On LoadFINISHINGFINISHING/PNL PP-8-B Panel/Overview 13:58:18 Load Imbalance

Breaker 7

PRINTING/PNL PDP2-G Panel/Overview 14:05:59PRINTING/PNL PDP2-G Panel/Breaker #1 14:07:21 8

FAN ROOM/FAN #1 Comb Strtr/Fan #1 14:15:00 9FAN ROOM/FAN #1FAN ROOM/FAN #1 Soft Start/Fan #1 14:19:37FAN ROOMFAN ROOM/FAN #2 Comb Strtr/Fan #2 14:20:38 10FAN ROOM/FAN #2FAN ROOM/FAN #2 Soft Start/Fan #2 14:25:04

Example D

ata Log Page

Page 6: Stockton Infrared Thermographic Services, Inc. · PDF fileStockton Infrared Thermographic Services, Inc. presents ... at the facilities of. Stockton Infrared ... Infrared Thermography

THERMOGRAPHIC REPORTReport No. 14BF Goodrich Textile Performance Chemicals Division

AREAWASTEWATER

LOCATIONComb Starter/Aerator #6-South

Date 11/10/98Time 09:09:08

Ambient temp. 68.1

Reference temp. 75.9

High temp. 97.4

Temp. rise 21.5

RISE ABOVE IN DEGREES F Ambient*** Reference*** Adjacent phase*** Direct measurement

AMPERAGESA: 22B: 22C: 22

DESCRIPTIONMAIN DISCONNECT-KNIFE CONNECTION/Phase B, Line Side

RECOMMENDATIONCheck Knife Connection.TEMP. RATING TEMP. RISE (in F degrees) CLASSIFICATION

Minor 1-18 Routine. Repair during regular maintenance, little chance of physical damage

*** Alert 19-36 Repair within 30 days, watch load and inspect for physical damage.

Serious 37-54 Repair/Replace ASAP. Inspect surrounding components for physical damage.

CRITICAL >55 IMMEDIATE REPAIR/REPLACE. DANGER EXISTS!

Knife Connection

*>89.6°F

*<25.6°F

30.035.040.045.050.055.060.065.070.075.080.085.0

Plant ID

T-Report #

Plant Area

Plant Location

Temp. Data

Time/Date

How Measured

High Temp.

Amperage

Description

Recommendation

Classification

Plant #2

Key to Thermographic Reports

Page 1

Page 7: Stockton Infrared Thermographic Services, Inc. · PDF fileStockton Infrared Thermographic Services, Inc. presents ... at the facilities of. Stockton Infrared ... Infrared Thermography

Spot 1 97.4

*>84.6°F

*<28.6°F

30.0

35.0

40.0

45.0

50.0

55.0

60.0

65.0

70.0

75.0

80.0

Spot 1 97.4

*>84.6°F

*<28.6°F

30.0

35.0

40.0

45.0

50.0

55.0

60.0

65.0

70.0

75.0

80.0

Spot 2 68.1

Spot 3 75.9

Spot 4 97.4

*>90.4°F

*<46.9°F

50.0

55.0

60.0

65.0

70.0

75.0

80.0

85.0

90.0

*>89.6°F

*<25.6°F

30.035.040.045.050.055.060.065.070.075.080.085.0

Quantitative Data

Close-Up

Wide-Angle Shot of the Entire Panel

Key to Thermographic Reports

Page 2

Page 8: Stockton Infrared Thermographic Services, Inc. · PDF fileStockton Infrared Thermographic Services, Inc. presents ... at the facilities of. Stockton Infrared ... Infrared Thermography

THERMOGRAPHIC REPORTReport No. 1

Acme Widget CompanyPlant #2

AREAAIR COMP RM/PANEL CPAL 3

LOCATIONBreaker/Circuits #40-42

Date 6/4/2002Time 10:02:57

Ambient temp. 85.6

Reference temp. 101.2

High temp. 123.4

Temp. rise 22.2

RISE ABOVE IN DEGREES F Ambient*** Reference*** Adjacent phase*** Direct measurement

AMPERAGES#40: 27.9#42: 27.6

DESCRIPTIONBreaker (30Amp) is overheating. Breaker load exceedes 80%. There is apparent internal damage.

RECOMMENDATIONReplace breaker, check ratings.

TEMP. RATING TEMP. RISE CLASSIFICATIONF degrees

Minor 1-18 Routine. Repair during regular maintenance, little chance of physical damage.

*** Alert 19-36 Repair within 30 days, watch load and inspect for physical damage.

Serious 37-54 Repair/Replace ASAP. Inspect surrounding components for physical damage.

CRITICAL >55 IMMEDIATE REPAIR/REPLACE. DANGER EXISTS!

QUESTIONS ABOUT THIS REPORT? Call 1-800-248-SCAN

Page 9: Stockton Infrared Thermographic Services, Inc. · PDF fileStockton Infrared Thermographic Services, Inc. presents ... at the facilities of. Stockton Infrared ... Infrared Thermography

THERMOGRAPHIC REPORT Report No. 1 (CON'T)

Area: AIR COMP RM/PANEL CPAL 3 Acme Widget CompanyLoc: Breaker/Circuits #40-42 Plant #2

123.4

Reference101.2

*>126.4°F

*<75 6°F

76.0

78.0

80.0

82.0

84.0

86.0

88.0

90.0

92.0

94.0

96.0

98.0

100.0

102.0

104.0

106.0

108.0

110.0

112.0

114.0

116.0

118.0

120.0

122.0

124.0

126.0

Page 10: Stockton Infrared Thermographic Services, Inc. · PDF fileStockton Infrared Thermographic Services, Inc. presents ... at the facilities of. Stockton Infrared ... Infrared Thermography

THERMOGRAPHIC REPORTReport No. 2

Acme Widget CompanyPlant #2

AREASS1/480V MAIN #1/DIST PANEL

LOCATIONBreaker 45 (NE Lights)

Date 6/4/2002Time 10:02:57

Ambient temp. 82.0

Reference temp. 89.9

High temp. 111.2

Temp. rise 21.3

RISE ABOVE IN DEGREES F Ambient*** Reference*** Adjacent phase*** Direct measurement

AMPERAGESPhase A: 89Phase B: 113Phase C: 143

DESCRIPTIONCircuit imbalanced.

RECOMMENDATIONBalance loads.

TEMP. RATING TEMP. RISE CLASSIFICATIONF degrees

Minor 1-18 Routine. Repair during regular maintenance, little chance of physical damage.

*** Alert 19-36 Repair within 30 days, watch load and inspect for physical damage.

Serious 37-54 Repair/Replace ASAP. Inspect surrounding components for physical damage.

CRITICAL >55 IMMEDIATE REPAIR/REPLACE. DANGER EXISTS!

QUESTIONS ABOUT THIS REPORT? Call 1-800-248-SCAN

Min Max 89.9 111.2Min Max 89.9 111.2

Page 11: Stockton Infrared Thermographic Services, Inc. · PDF fileStockton Infrared Thermographic Services, Inc. presents ... at the facilities of. Stockton Infrared ... Infrared Thermography

THERMOGRAPHIC REPORT Report No. 2 (CON'T)

Area: SS1/480V MAIN #1/DIST PANEL Acme Widget CompanyLoc: Breaker 45 (NE Lights) Plant #2

Front view

Page 12: Stockton Infrared Thermographic Services, Inc. · PDF fileStockton Infrared Thermographic Services, Inc. presents ... at the facilities of. Stockton Infrared ... Infrared Thermography

THERMOGRAPHIC REPORTReport No. 3

Acme Widget CompanyPlant #2

AREAAIR COMP SHED/A.C. #1

LOCATIONDisc/Air Compressor #1

Date 6/4/2002Time 10:02:57

Ambient temp. 80.8

Reference temp. 138.0

High temp. 265.0

Temp. rise 127.0

RISE ABOVE IN DEGREES F Ambient*** Reference*** Adjacent phase*** Direct measurement

AMPERAGESPhase A: 45Phase B: 46Phase C: 45

DESCRIPTIONSWITCH (blade connector), phase A overheating.

RECOMMENDATIONCheck switch connections.

TEMP. RATING TEMP. RISE CLASSIFICATIONF degrees

Minor 1-18 Routine. Repair during regular maintenance, little chance of physical damage.

Alert 19-36 Repair within 30 days, watch load and inspect for physical damage.

Serious 37-54 Repair/Replace ASAP. Inspect surrounding components for physical damage.

*** CRITICAL >55 IMMEDIATE REPAIR/REPLACE. DANGER EXISTS!

QUESTIONS ABOUT THIS REPORT? Call 1-800-248-SCAN

Page 13: Stockton Infrared Thermographic Services, Inc. · PDF fileStockton Infrared Thermographic Services, Inc. presents ... at the facilities of. Stockton Infrared ... Infrared Thermography

THERMOGRAPHIC REPORT Report No. 3 (CON'T)

Area: AIR COMP SHED/A.C. #1 Acme Widget CompanyLoc: Disc/Air Compressor #1 Plant #2

Page 14: Stockton Infrared Thermographic Services, Inc. · PDF fileStockton Infrared Thermographic Services, Inc. presents ... at the facilities of. Stockton Infrared ... Infrared Thermography

THERMOGRAPHIC REPORTReport No. 4

Acme Widget CompanyPlant #2

AREACHILLER PAD/CHILLER CH-2

LOCATIONStarter Pnl/Contactor #2

Date 6/4/2002Time 10:02:57

Ambient temp. 95.2

Reference temp. 108.0

High temp. 138.0

Temp. rise 30.0

RISE ABOVE IN DEGREES F Ambient*** Reference*** Adjacent phase*** Direct measurement

AMPERAGESPhase A: 99Phase B: 96Phase C: 99

DESCRIPTIONContactor connector overheating.

RECOMMENDATIONReinstall wire, check connection.

TEMP. RATING TEMP. RISE CLASSIFICATIONF degrees

Minor 1-18 Routine. Repair during regular maintenance, little chance of physical damage.

*** Alert 19-36 Repair within 30 days, watch load and inspect for physical damage.

Serious 37-54 Repair/Replace ASAP. Inspect surrounding components for physical damage.

CRITICAL >55 IMMEDIATE REPAIR/REPLACE. DANGER EXISTS!

QUESTIONS ABOUT THIS REPORT? Call 1-800-248-SCAN

Page 15: Stockton Infrared Thermographic Services, Inc. · PDF fileStockton Infrared Thermographic Services, Inc. presents ... at the facilities of. Stockton Infrared ... Infrared Thermography

THERMOGRAPHIC REPORT Report No. 4 (CON'T)

Area: CHILLER PAD/CHILLER CH-2 Acme Widget CompanyLoc: Starter Pnl/Contactor #2 Plant #2

*>149.0°F

*<95.8°F

100.0

105.0

110.0

115.0

120.0

125.0

130.0

135.0

140.0

145.0

Page 16: Stockton Infrared Thermographic Services, Inc. · PDF fileStockton Infrared Thermographic Services, Inc. presents ... at the facilities of. Stockton Infrared ... Infrared Thermography

THERMOGRAPHIC REPORTReport No. 5

Acme Widget CompanyPlant #2

AREAVACUUM FAN ROOM/MCC-A

LOCATIONCubicle A1/Vacuum Fan #1

Date 6/4/2002Time 10:02:57

Ambient temp. 77.7

Reference temp. 104.0

High temp. 156.0

Temp. rise 52.0

RISE ABOVE IN DEGREES F Ambient*** Reference*** Adjacent phase*** Direct measurement

AMPERAGESPhase A: 170Phase B: 170Phase C: 170

DESCRIPTIONBreaker lug/phase A, line side.

RECOMMENDATIONCheck breaker lug and connections.

TEMP. RATING TEMP. RISE CLASSIFICATIONF degrees

Minor 1-18 Routine. Repair during regular maintenance, little chance of physical damage.

Alert 19-36 Repair within 30 days, watch load and inspect for physical damage.

*** Serious 37-54 Repair/Replace ASAP. Inspect surrounding components for physical damage.

CRITICAL >55 IMMEDIATE REPAIR/REPLACE. DANGER EXISTS!

QUESTIONS ABOUT THIS REPORT? Call 1-800-248-SCAN

Page 17: Stockton Infrared Thermographic Services, Inc. · PDF fileStockton Infrared Thermographic Services, Inc. presents ... at the facilities of. Stockton Infrared ... Infrared Thermography

THERMOGRAPHIC REPORT Report No. 5 (CON'T)

Area: VACUUM FAN ROOM/MCC-A Acme Widget CompanyLoc: Cubicle A1/Vacuum Fan #1 Plant #2

*>150.7°F

*<57.2°F

60.0

80.0

100.0

120.0

140.0

Page 18: Stockton Infrared Thermographic Services, Inc. · PDF fileStockton Infrared Thermographic Services, Inc. presents ... at the facilities of. Stockton Infrared ... Infrared Thermography

THERMOGRAPHIC REPORTReport No. 6

Acme Widget CompanyPlant #2

AREAMAINMCR #3MCC #3-2

LOCATIONCubicle D2/Pump 3B

Date 6/4/2002Time 10:02:57

Ambient temp. 86.0

Reference temp. 104.8

High temp. 224.2

Temp. rise 119.4

RISE ABOVE IN DEGREES F Ambient*** Reference*** Adjacent phase*** Direct measurement

AMPERAGESPhase A: 30Phase B: 28Phase C: 29

DESCRIPTIONFuse and fuse clip/phase A, load side.

RECOMMENDATIONReplace fuse and fuse clip.

TEMP. RATING TEMP. RISE CLASSIFICATIONF degrees

Minor 1-18 Routine. Repair during regular maintenance, little chance of physical damage.

Alert 19-36 Repair within 30 days, watch load and inspect for physical damage.

Serious 37-54 Repair/Replace ASAP. Inspect surrounding components for physical damage.

*** CRITICAL >55 IMMEDIATE REPAIR/REPLACE. DANGER EXISTS!

QUESTIONS ABOUT THIS REPORT? Call 1-800-248-SCAN

Page 19: Stockton Infrared Thermographic Services, Inc. · PDF fileStockton Infrared Thermographic Services, Inc. presents ... at the facilities of. Stockton Infrared ... Infrared Thermography

THERMOGRAPHIC REPORT Report No. 6 (CON'T)

Area: MAINMCR #3MCC #3-2 Acme Widget CompanyLoc: Cubicle D2/Pump 3B Plant #2

*>134.9°F

*<70.9°F

75.0

80.0

85.0

90.0

95.0

100.0

105.0

110.0

115.0

120.0

125.0

130.0

*>130.6°F

*<71.8°F

75.0

80.0

85.0

90.0

95.0

100.0

105.0

110.0

115.0

120.0

125.0

130.0

*>146.6°F

*<85.0°F

85.0

90.0

95.0

100.0

105.0

110.0

115.0

120.0

125.0

130.0

135.0

140.0

145.0

High TempMax 224.2

High TempMax 224.2

Reference104.8

*>221.7°F

*<57.8°F

60.0

70.0

80.0

90.0

100.0

110.0

120.0

130.0

140.0

150.0

160.0

170.0

180.0

190.0

200.0

210.0

220.0

Page 20: Stockton Infrared Thermographic Services, Inc. · PDF fileStockton Infrared Thermographic Services, Inc. presents ... at the facilities of. Stockton Infrared ... Infrared Thermography

REPAIR GUIDE- Equipment needing repairsAcme Widget CompanyPlant #2Anytown, USA

T# PLANT AREA AREA LOCATION CLASS

1 FLOCKING AREA FLOCK LINE #2 CNTRL RM Control Pnl FL2-J/Main Brkr S2 FINISHING AREA FINISHING/FM #1 Cntrl FM1-3/Predryer Main A3 FINISHING AREA FINISHING/FM #1 Cntrl Pnl FM1-1/MS-0610 C4 FINISHING AREA FINISHING/FM #1 Cntrl Pnl FM1-1/Brkr MS0610 A5 PRINTING AREA PRINTING/BATTERY CHRGRS Panel LP-2/Circuits 14 & 16 M6 MAINTENANCE OFFICES MAINT. OFFICES/PNLS Panel RP-15/Circuit #21 A7 FINISHING AREA FINISHING/PNL LP-8 Panel/Circuit #9 A8 PRINTING AREA PRINTING/PNL PDP2-G Panel/Breaker #1 C9 FAN ROOM FAN ROOM/FAN #1 Comb Strtr/Fan #1 C

10 FAN ROOM FAN ROOM/FAN #2 Comb Strtr/Fan #2 A11 SUBSTATION #2 SUBSTN #2/PNL LP-7 Panel/Circuit #13 A12 PRINTING AREA PRINTING/PM #4/CNTRLS Main Control Pnl/Main Brkr C13 SUBSTATION #1 SUBSTN #1/13.2V Main 13.2V Switch/Overview S14 CUTTING AREA CUTTING/CNTRLS Control Pnl CT3-2/Main Disc A15 EMBOSSER EMBOSSER/HOT OIL Control Pnl/Relay-Heaters A16 WASTEWATER AREA WASTEWATER/PUMPS Pump Control Pnl/FU 36 & 38 S17 3803 WAREHOUSE 3803 WRHSE/PNL PP-4B Panel/Overview S18 3803 WAREHOUSE 3803 WRHSE/PNL PP3-B Panel/Overview A19 PRINTING AREA PRINTING/PM #3/PDP2-D Panel/Breaker-PM-3 Cntrls A20 DYE HOUSE DYE HSE/JETS 1-4 Control Pnl/1-4-Main Brkr S21 DYE HOUSE DYE HSE/OVEN TENTER Main Breaker/Overview M22 DYE HOUSE DYE HSE/AIR CMPRSSR #1 Starter Pnl/Overview S23 DYE HOUSE DYE HSE/BOILER Control Pnl/Blr Blwr Fuses C24 PRINTING AREA PRINTING/PM #3/CNTRLS Control Pnl 3-5/Main Switch A25 FLOCKING AREA FLOCK #1 CNTRL RM Cntrl Pnl-Ex. Fans/Fan M17E C26 FLOCKING AREA FLOCK RANGE #1/DISCS Main Disc #52/Overview S

(NR) Not Rated = 2 (M) Minor = 12

(A) Alert = 15 (S) Serious = 13 (C) Critical = 10

TOTAL = 52

Page 21: Stockton Infrared Thermographic Services, Inc. · PDF fileStockton Infrared Thermographic Services, Inc. presents ... at the facilities of. Stockton Infrared ... Infrared Thermography

See many more examples on our web

site at:www.ElectriSCAN.com

Page 22: Stockton Infrared Thermographic Services, Inc. · PDF fileStockton Infrared Thermographic Services, Inc. presents ... at the facilities of. Stockton Infrared ... Infrared Thermography

Aerial Electrical Infrared on Transmission LinesLoose Bushing

Temperature profileMin. Mean Max. 246.4 251.0 258.3

258.3 258.3

251.0 251.0

246.4 246.4

Mechanical Equipment IR P/PM

Electrical Equipment IR P/PM

Industrial Process MonitoringStructural Analysis

800800--248248--SCANSCAN

Bond Beam Incomplete

Environmental Impact Surveys

Building Heat Loss SurveysAerial Infrared Roof Moisture Surveys

Typical R&D test set-up

www.www.stocktonstocktoninfraredinfrared.com.com

State-of-the-Art