stop station terminal

Upload: richie-mathews

Post on 06-Apr-2018

219 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/2/2019 Stop Station Terminal

    1/36

    Stop, Station, andTerminal Capacity

    May 4, 2004

    Todays Topics

    Station elements

    Sizing station elements

    Emergency evacuation considerations

  • 8/2/2019 Stop Station Terminal

    2/36

    StationElements

    GuidewayGuidewayPlatformPlatform

    ShelterShelter

    ElevatorElevator

    StairsStairs

    TicketTicket

    MachineMachine

    PedPedAccessAccess

    BusBusAccessAccess

    WalkwayWalkway

    CustomerCustomer

    InfoInfo

    BenchBenchPhonePhone

    Trash CanTrash Can

    LightingLighting

    LandscapingLandscaping

  • 8/2/2019 Stop Station Terminal

    3/36

    Not Pictured

    Faregates

    Park-and-ride access

    Bike storage

    Artwork

    Electronic displays

    Station agents

    Doorways

    Moving walkways

    Restrooms

    Driver break areas

    Vending

    Escalators

    Kiss-and-ride access

    Types of Passenger Facilities

    Bus stops

    On-street

    No to few amenities

    Transit centers

    Usually off-street

    Few to many amenities

    Transit stations

    Off-street

    Many amenities

  • 8/2/2019 Stop Station Terminal

    4/36

    Types of Passenger Facilities

    Design Issues

    How many bus bays (loading areas) are needed?

    Is there enough room for passengers to wait andcirculate?

    Is there enough space & passenger demand forparticular amenities?

  • 8/2/2019 Stop Station Terminal

    5/36

    Design Issues

    Additional considerations for stations andterminals:

    Are passenger processing elements (e.g., stairs and faregates) adequately sized?

    What station element constrains capacity?

    Emergency evacuation needs

    Design Issues

    Americans with Disabilities Act (ADA)

    ADA requirements affect design

    Addressed in TCQSM to the extent it impacts the sizing ofstation elements

    TCQSM provides input into the design process, but isnt a

    design manual

  • 8/2/2019 Stop Station Terminal

    6/36

    Passenger Access

    Location Walk/Bike Feeder Bus Kiss & Ride Park & Ride

    Bus Stop transfer points

    Transit Center sometimes

    Bus/Rail Station

    Intermodal Terminal

    Bus Stop Elements

    Limited passenger waiting area

    Shelters and/or benches at higher boardingvolume stops

    Trash receptacle

    May have printed schedule information

    Limited other amenities

  • 8/2/2019 Stop Station Terminal

    7/36

    On-Street Bus Stop Capacity

    Short dwell times (no layovers)

    Use TCQSM bus capacity procedures

    On-Street Bus Stop Capacity

    Short dwell times (no layovers)

    Use TCQSM bus capacity procedures

  • 8/2/2019 Stop Station Terminal

    8/36

    Bus Transit Center Elements

    Usually serve as transfer points

    Multiple bus bays, usually off-street

    Adjacent park & ride / kiss & ride possible

    Site landscaping and lighting

    Passenger plaza with shelters, benches, trashreceptacles, telephone, newspaper stand

    Bus Transit Center Elements

    Longer dwell times (> 3 min)

    Buses terminating at transit center or station

    Buses waiting for transfer connections

    Typical practice is to provide a separate bus stopfor each route

    More than one berth might be needed, dependingon route frequency and layover/recovery timeneeds

  • 8/2/2019 Stop Station Terminal

    9/36

    PassengerWaitingAreas

    Passenger Waiting Areas

    Sizing passenger waiting areas based onmaintaining a desirable level of service

    Concepts presented in Fruins Pedestrian Planning& Design

    HCM has similar concepts, but intended forsidewalksTCQSMs levels of service are intended

    for transit facilities

    Level of service measure:average space per person

  • 8/2/2019 Stop Station Terminal

    10/36

    Waiting Area LOS

    LOS A

    LOS B

    LOS C

    LOS D

    LOS E

    LOS F

    >= 13 ft2 per person

    10-13 ft2 per person

    7-10 ft2 per person

    3-7 ft2 per person

    2-3 ft2 per person

    < 2 f t2 per person

    Sizing Passenger Waiting Areas

    General process used for passenger waiting areasis applicable to most station elements, althoughspecifics (e.g., LOS thresholds) will differ

    Presentation will only go through process once

    1. Pick a design LOS

    A function of how long people will be waiting: elevator vs.

    15-minute wait on platform

    LOS C a reasonable design level

    LOS D a minimum design level

  • 8/2/2019 Stop Station Terminal

    11/36

    Sizing Passenger Waiting Areas

    2. Estimate maximum passenger demand

    Also check effects of irregular operations to make suredangerous levels of crowding can be avoided or controlled

    3. Calculate effective waiting area

    (number of passengers) * (design space per passenger)

    Sizing Passenger Waiting Areas

    4. Include a buffer

    Add a 1.5-ft buffer along platform edges and next to walls

    Add a 1.0-ft buffer next to other obstructions, includinglow walls up to 3 feet high

  • 8/2/2019 Stop Station Terminal

    12/36

    Sizing Passenger Waiting Areas

    5. Allow space for passenger circulation

    Use walkway procedures (shown later)

    From stairs/escalators to platform

    From trains to stairs/escalators

    Transferring passengers traversing the platform

    Sizing Passenger Waiting Areas

    6. Allow for queue space at platform exits

    Passengers may arrive at vertical circulation elements(stairs, escalators, elevators) faster than they can beprocessed

    Provide 5 ft2 per person in queue at entrance to stair, etc.

    Provide clear space at exit

  • 8/2/2019 Stop Station Terminal

    13/36

    Sizing Passenger Waiting Areas

    7. Account for space used by physical obstructions

    Stairwells, escalators

    Benches, pillars

    Ad signs

    8. Calculate total area needed

    Sum areas from steps 3-7

    Walkways

  • 8/2/2019 Stop Station Terminal

    14/36

    Principles of Pedestrian Flow

    Ped speed is related to density

    The more pedestrians, the slower the average ped speed

    Flow (how many pedestrians can pass by a givenpoint) is the product of speed and density:

    V = S * D

    Units: pedestrians per foot width per minute

    Average space per pedestrian is related to speed

    and flow

    M = S / V, units: ft2/ped

    Principles of Pedestrian Flow

    Most design problems relate to solving for either:

    Station element width (e.g., stairway width)

    Station element area (e.g., platform area)

    Result is a station element sized to accommodatea given number of persons per hour, at a designlevel of service

  • 8/2/2019 Stop Station Terminal

    15/36

    Pedestrian Flow on Walkways

    0

    5

    10

    15

    20

    25

    30

    0 5 10 15 20 25 30 35 40 45 50

    Pedestrian Space (ft2/p)

    PedestrianFlow(

    p/ft/min)

    Commuter uni-directionalCommuter bi-directional

    Shoppers multi-directional

    Walkway LOS

    LOS A

    LOS B

    LOS C

    LOS D

    LOS E

    LOS F

    >= 35 ft2/p, avg. speed 260 ft/min

    25-35 ft2/p, avg. speed 250 ft/min

    15-25 ft2/p, avg. speed 240 ft/min

    10-15 ft2/p, avg. speed 225 ft/min

    5-10 ft2/p, avg. speed 150 ft/min

    < 5 f t2/p, avg. speed

  • 8/2/2019 Stop Station Terminal

    16/36

    Walkway LOS

    Walkways

    Typical ped speed for design: 250 ft/min

    Capacity occurs at LOS E/F threshold

    Peds walk at a shuffle

  • 8/2/2019 Stop Station Terminal

    17/36

    Walkway Design Process

    1. Based on desired LOS, identify maximum flowrate per unit width

    2. Estimate peak 15-minute demand

    3. Allow for wheelchairs, users with large items

    4. Compute design ped flow: (Step 2) / 15

    5. Effective width = (Step 4 / Step 1)

    6. Add buffer width: 1.5 feet on each side

    Stairs&

    Escalators

  • 8/2/2019 Stop Station Terminal

    18/36

    Stairway LOS

    Avg. Ped. Space Flow per Unit WidthLOS (ft2/p) (m2/p) (p/ft/min) (p/m/min) Description

    A 20 1.9 5 16Sufficient area to freely select speed and topass slower-moving pedestrians. Reverseflows cause limited conflicts.

    B 15-20 1.4-1.9 5-7 16-23

    Sufficient area to freely select speed withsome difficulty in passing slower-movingpedestrians. Reverse flows cause minorconflicts.

    C 10-15 0.9-1.4 7-10 23-33Speeds slightly restricted due to inability topass slower-moving pedestrians. Reverseflows cause some conflicts.

    D 7-10 0.7-0.9 10-13 33-43Speeds restricted due to inability to passslower-moving pedestrians. Reverse flowscause significant conflicts.

    E 4-7 0.4-0.7 13-17 43-56Speeds of all pedestrians reduced.Intermittent stoppages likely to occur.Reverse flows cause serious conflicts.

    F 4 0.4 Variable Variable Complete breakdown in pedestrian flow withmany stoppages. Forward progressdependent on slowest moving pedestrians.

    Pedestrian Flow on Stairs

    0

    5

    10

    15

    20

    25

    30

    0 5 10 15 20 25 30 35 40 45 50

    Pedestrian Space (ft2/p)

    PedestrianFlow(

    p/ft/min)

  • 8/2/2019 Stop Station Terminal

    19/36

    Pedestrian Ascent Speed on Stairs

    0

    25

    50

    75

    100

    125

    150

    175

    200

    0 5 10 15 20 25 30 35 40 45 50Pedestrian Space (ft2/p)

    SlopeSpeed(ft/min)

    Stairway Capacity Factors

    Even minor reverse flows may reduce stairwaycapacity by as much as one-half

    Although sizing procedures may suggest acontinuum of stairway widths, capacity is reallyadded in one-person-width increments(roughly 30 inches)

  • 8/2/2019 Stop Station Terminal

    20/36

    Stairway Design Factors

    Most new construction will use escalators as theprimary vertical circulation element

    Can design to LOS E in this case

    Where stairs will be the primary verticalcirculation element, design to LOS C to D

    Emergency evacuation needs may require betterLOS (discussed later)

    Stairway Design Process

    1. Based on desired LOS, identify maximum flowrate per unit width

    2. Estimate peak 15-minute demand

    3. Compute design ped flow: (Step 2) / 15

    4. Required width = (Step 3 / Step 1)

    5. If minor, reverse-flow use occurs, add width ofone lane (30 inches)

  • 8/2/2019 Stop Station Terminal

    21/36

    Escalator Capacity Factors

    Angle of incline

    Stair width

    Operating speed

    Escalator Capacity Factors

    Manufacturers often state capacity based on amaximum theoretical capacitytwo people onevery stepwhich is never obtained

    Capacity reduction factors

    Intermittent ped arrivals

    Ped inability to board quickly

    Peds carrying baggage or packages Ped desire for a more comfortable space

  • 8/2/2019 Stop Station Terminal

    22/36

    Escalator Capacity

    Nominal capacity values based on oneperson every other step (single-width), orone person every step (double-width)

    Elevators

  • 8/2/2019 Stop Station Terminal

    23/36

    Elevator Usage

    Vertical circulation within station

    Deep station access

    New York: 168th, 181st, 191st

    Washington, DC: Forest Glen

    Portland, OR: Washington Park

    When not working, impacts station access for

    mobility impaired

    Elevator Capacity

    Calculated similarly to transit vehicles

    Car capacity is combination of loading standard (area perpassenger) and elevator floor area

    Time to make round-trip, including loading and unloadingpassengers

    Station access elevators often have doors on bothsides for simultaneous loading/unloading

  • 8/2/2019 Stop Station Terminal

    24/36

    MovingWalkways

    Moving Walkways

    Typical speed 100 ft/min, some up to 160 ft/min

    Less than typical walking speed

    Capacity limited at entrance

    Speed not a factor unless it causes persons to hesitate whenentering

    Similar capacity as escalators

    Double-width: about 90 p/min

  • 8/2/2019 Stop Station Terminal

    25/36

    Doorways

    Doorway Capacity

  • 8/2/2019 Stop Station Terminal

    26/36

    FareControl

    Fare Control Capacity

  • 8/2/2019 Stop Station Terminal

    27/36

    TicketMachines

    Ticket Machine Capacity

    Time per passenger varies widely depending onmachine design and complexity of fare system

    Least standardized element of transit design

    Infrequent passengers require more time

    Consider impacts of out-of-service machines

  • 8/2/2019 Stop Station Terminal

    28/36

    Ticket Machine Examples

    EmergencyEvacuation

  • 8/2/2019 Stop Station Terminal

    29/36

    Emergency Evacuation Design

    Must address evacuation requirements(person flow determined from the maximumperson accumulation and the maximum time toevacuate station)

    Ability to remove passengers from platform areabefore next vehicle arrives

    Overall passenger flow through station is animportant consideration (bottlenecks!)

    Emergency Evacuation Design

    General considerations

    Sufficient exit capacity to evacuate station occupants(including those on trains) from platforms in 4.0 minutesor less, and to reach point of safety in 6.0 minutes or less

    Sufficient exit capacity to get from most remote point onplatform to point of safety in 6.0 minutes or less

    Second egess route remote from major

    egress route from each platform

  • 8/2/2019 Stop Station Terminal

    30/36

    Emergency Evacuation Design

    Number of people to design for:

    Loads of one train on each track during peak 15 minutes

    Assume each train one headway late (i.e., is carrying twice itsnormal load, but no more than a maximum schedule load)

    Passengers on platform during peak 15 minutes, assumingtrains are one headway late

    Emergency Evacuation Design

    Changes to normal design procedure:

    NFPA 130 specifies passenger flow rates for specificstation elements

    NFPA 130 specifies minimum widths for egress routes

    Assume one escalator out of service; escalators cannotprovide more than half of exit capacity

    Elevators cannot be used for exit capacity

  • 8/2/2019 Stop Station Terminal

    31/36

    Emergency Evacuation Design

    Maximum capacity required for normal operationsor emergency evacuation will govern

    Because emergency evacuation routes may bedifferent than routes taken by passengers duringnormal operations, you cant assume thatevacuation needs will govern in all cases

    PlatformSizing

    Example

  • 8/2/2019 Stop Station Terminal

    32/36

    Platform Sizing Example

    New underground light rail station

    Design year conditions:

    A.M. exiting volume: 3,200 p/h

    A.M. entering volume: 500 p/h

    P.M. exiting volume: 500 p/h

    P.M. entering volume: 2,900 p/h

    Current peak hour factor (PHF) on completedportion of system is 0.714

    Platform Sizing Example

    Convert hourly volumes to peak 15-min volumes

    Highest entering volume occurs during p.m. peak:

    )(4 PHF

    PP

    h

    15=

    p015,1)714.0(4

    900,2 ==15

    P

  • 8/2/2019 Stop Station Terminal

    33/36

    Platform Sizing Example

    Two 4-car (300-ft) trains arrive in each directionin each 15-minute period

    Under normal operating conditions, half of thepeak 15-minute demand could be on the platform

    just before trains arrived

    507 passengers

    At a design LOS C (7 ft2/p), 507 * 7,

    or 3,549 ft2

    is required to store passengers

    Platform Sizing Example

    During the peak 15 minutes, approximately 175passengers will arrive on four trains

    Forecast that highest-volume (outbound) trains wouldbring 61 passengers each

    Designer estimates that 3/4 of passengers would be onplatform at any given time, given proposed locations ofstation exits

    From walkway procedure, design LOS C is 15 ft2/p

    Required space = 61 * 15 * 0.75 = 686 ft2

  • 8/2/2019 Stop Station Terminal

    34/36

    Platform Sizing Example

    Look at queue storage needs at exit points

    Two escalators proposed to be provided

    Escalator procedure gives capacity of 68 p/min at a typicalincline speed of 90 ft/min

    Escalator capacity of 136 p/min is greater than passengerdemand of 61 exiting passengers per outbound trainnoqueue would develop

    Platform Sizing Example

    Consider unused platform space

    Elevator shafts, stairways, escalators

    Benches, information displays, advertising displays

    Pillars

    Designer determines 550 ft2 required based onproposed station elements

  • 8/2/2019 Stop Station Terminal

    35/36

    Platform Sizing Example

    Calculate buffer area required

    Platform is 300 feet long to accommodate 4-car trains

    Provide 1.5-ft buffer next to platform edges

    Two edges on a center (island) platform

    300 * 2 *1.5 = 900 ft2 required

    Also consider any other walls designed into platform

    Example assumes buffer space associated with elevators,stairs, escalators was built into the unused-space calculation

    Platform Sizing Example

    Calculate total area required

    Passenger waiting area: 3,549 ft2

    Walking area: 686 ft2

    Queue storage: 0 ft2

    Unused platform space: 550 ft2

    Buffer space: 900 ft2

    Total area required under normal operations andLOS C conditions: 5,685 ft2

  • 8/2/2019 Stop Station Terminal

    36/36

    Platform Sizing Example

    Also check:

    Emergency evacuation needs and impacts on stationelement sizing

    Irregular train operations resulting in more passengerswaiting on platform

    How long a disruption could occur before platform crowdingreached uncomfortable or dangerous levels?

    See TCQSM Part 7, Example Problem 3