stop station terminal
TRANSCRIPT
-
8/2/2019 Stop Station Terminal
1/36
Stop, Station, andTerminal Capacity
May 4, 2004
Todays Topics
Station elements
Sizing station elements
Emergency evacuation considerations
-
8/2/2019 Stop Station Terminal
2/36
StationElements
GuidewayGuidewayPlatformPlatform
ShelterShelter
ElevatorElevator
StairsStairs
TicketTicket
MachineMachine
PedPedAccessAccess
BusBusAccessAccess
WalkwayWalkway
CustomerCustomer
InfoInfo
BenchBenchPhonePhone
Trash CanTrash Can
LightingLighting
LandscapingLandscaping
-
8/2/2019 Stop Station Terminal
3/36
Not Pictured
Faregates
Park-and-ride access
Bike storage
Artwork
Electronic displays
Station agents
Doorways
Moving walkways
Restrooms
Driver break areas
Vending
Escalators
Kiss-and-ride access
Types of Passenger Facilities
Bus stops
On-street
No to few amenities
Transit centers
Usually off-street
Few to many amenities
Transit stations
Off-street
Many amenities
-
8/2/2019 Stop Station Terminal
4/36
Types of Passenger Facilities
Design Issues
How many bus bays (loading areas) are needed?
Is there enough room for passengers to wait andcirculate?
Is there enough space & passenger demand forparticular amenities?
-
8/2/2019 Stop Station Terminal
5/36
Design Issues
Additional considerations for stations andterminals:
Are passenger processing elements (e.g., stairs and faregates) adequately sized?
What station element constrains capacity?
Emergency evacuation needs
Design Issues
Americans with Disabilities Act (ADA)
ADA requirements affect design
Addressed in TCQSM to the extent it impacts the sizing ofstation elements
TCQSM provides input into the design process, but isnt a
design manual
-
8/2/2019 Stop Station Terminal
6/36
Passenger Access
Location Walk/Bike Feeder Bus Kiss & Ride Park & Ride
Bus Stop transfer points
Transit Center sometimes
Bus/Rail Station
Intermodal Terminal
Bus Stop Elements
Limited passenger waiting area
Shelters and/or benches at higher boardingvolume stops
Trash receptacle
May have printed schedule information
Limited other amenities
-
8/2/2019 Stop Station Terminal
7/36
On-Street Bus Stop Capacity
Short dwell times (no layovers)
Use TCQSM bus capacity procedures
On-Street Bus Stop Capacity
Short dwell times (no layovers)
Use TCQSM bus capacity procedures
-
8/2/2019 Stop Station Terminal
8/36
Bus Transit Center Elements
Usually serve as transfer points
Multiple bus bays, usually off-street
Adjacent park & ride / kiss & ride possible
Site landscaping and lighting
Passenger plaza with shelters, benches, trashreceptacles, telephone, newspaper stand
Bus Transit Center Elements
Longer dwell times (> 3 min)
Buses terminating at transit center or station
Buses waiting for transfer connections
Typical practice is to provide a separate bus stopfor each route
More than one berth might be needed, dependingon route frequency and layover/recovery timeneeds
-
8/2/2019 Stop Station Terminal
9/36
PassengerWaitingAreas
Passenger Waiting Areas
Sizing passenger waiting areas based onmaintaining a desirable level of service
Concepts presented in Fruins Pedestrian Planning& Design
HCM has similar concepts, but intended forsidewalksTCQSMs levels of service are intended
for transit facilities
Level of service measure:average space per person
-
8/2/2019 Stop Station Terminal
10/36
Waiting Area LOS
LOS A
LOS B
LOS C
LOS D
LOS E
LOS F
>= 13 ft2 per person
10-13 ft2 per person
7-10 ft2 per person
3-7 ft2 per person
2-3 ft2 per person
< 2 f t2 per person
Sizing Passenger Waiting Areas
General process used for passenger waiting areasis applicable to most station elements, althoughspecifics (e.g., LOS thresholds) will differ
Presentation will only go through process once
1. Pick a design LOS
A function of how long people will be waiting: elevator vs.
15-minute wait on platform
LOS C a reasonable design level
LOS D a minimum design level
-
8/2/2019 Stop Station Terminal
11/36
Sizing Passenger Waiting Areas
2. Estimate maximum passenger demand
Also check effects of irregular operations to make suredangerous levels of crowding can be avoided or controlled
3. Calculate effective waiting area
(number of passengers) * (design space per passenger)
Sizing Passenger Waiting Areas
4. Include a buffer
Add a 1.5-ft buffer along platform edges and next to walls
Add a 1.0-ft buffer next to other obstructions, includinglow walls up to 3 feet high
-
8/2/2019 Stop Station Terminal
12/36
Sizing Passenger Waiting Areas
5. Allow space for passenger circulation
Use walkway procedures (shown later)
From stairs/escalators to platform
From trains to stairs/escalators
Transferring passengers traversing the platform
Sizing Passenger Waiting Areas
6. Allow for queue space at platform exits
Passengers may arrive at vertical circulation elements(stairs, escalators, elevators) faster than they can beprocessed
Provide 5 ft2 per person in queue at entrance to stair, etc.
Provide clear space at exit
-
8/2/2019 Stop Station Terminal
13/36
Sizing Passenger Waiting Areas
7. Account for space used by physical obstructions
Stairwells, escalators
Benches, pillars
Ad signs
8. Calculate total area needed
Sum areas from steps 3-7
Walkways
-
8/2/2019 Stop Station Terminal
14/36
Principles of Pedestrian Flow
Ped speed is related to density
The more pedestrians, the slower the average ped speed
Flow (how many pedestrians can pass by a givenpoint) is the product of speed and density:
V = S * D
Units: pedestrians per foot width per minute
Average space per pedestrian is related to speed
and flow
M = S / V, units: ft2/ped
Principles of Pedestrian Flow
Most design problems relate to solving for either:
Station element width (e.g., stairway width)
Station element area (e.g., platform area)
Result is a station element sized to accommodatea given number of persons per hour, at a designlevel of service
-
8/2/2019 Stop Station Terminal
15/36
Pedestrian Flow on Walkways
0
5
10
15
20
25
30
0 5 10 15 20 25 30 35 40 45 50
Pedestrian Space (ft2/p)
PedestrianFlow(
p/ft/min)
Commuter uni-directionalCommuter bi-directional
Shoppers multi-directional
Walkway LOS
LOS A
LOS B
LOS C
LOS D
LOS E
LOS F
>= 35 ft2/p, avg. speed 260 ft/min
25-35 ft2/p, avg. speed 250 ft/min
15-25 ft2/p, avg. speed 240 ft/min
10-15 ft2/p, avg. speed 225 ft/min
5-10 ft2/p, avg. speed 150 ft/min
< 5 f t2/p, avg. speed
-
8/2/2019 Stop Station Terminal
16/36
Walkway LOS
Walkways
Typical ped speed for design: 250 ft/min
Capacity occurs at LOS E/F threshold
Peds walk at a shuffle
-
8/2/2019 Stop Station Terminal
17/36
Walkway Design Process
1. Based on desired LOS, identify maximum flowrate per unit width
2. Estimate peak 15-minute demand
3. Allow for wheelchairs, users with large items
4. Compute design ped flow: (Step 2) / 15
5. Effective width = (Step 4 / Step 1)
6. Add buffer width: 1.5 feet on each side
Stairs&
Escalators
-
8/2/2019 Stop Station Terminal
18/36
Stairway LOS
Avg. Ped. Space Flow per Unit WidthLOS (ft2/p) (m2/p) (p/ft/min) (p/m/min) Description
A 20 1.9 5 16Sufficient area to freely select speed and topass slower-moving pedestrians. Reverseflows cause limited conflicts.
B 15-20 1.4-1.9 5-7 16-23
Sufficient area to freely select speed withsome difficulty in passing slower-movingpedestrians. Reverse flows cause minorconflicts.
C 10-15 0.9-1.4 7-10 23-33Speeds slightly restricted due to inability topass slower-moving pedestrians. Reverseflows cause some conflicts.
D 7-10 0.7-0.9 10-13 33-43Speeds restricted due to inability to passslower-moving pedestrians. Reverse flowscause significant conflicts.
E 4-7 0.4-0.7 13-17 43-56Speeds of all pedestrians reduced.Intermittent stoppages likely to occur.Reverse flows cause serious conflicts.
F 4 0.4 Variable Variable Complete breakdown in pedestrian flow withmany stoppages. Forward progressdependent on slowest moving pedestrians.
Pedestrian Flow on Stairs
0
5
10
15
20
25
30
0 5 10 15 20 25 30 35 40 45 50
Pedestrian Space (ft2/p)
PedestrianFlow(
p/ft/min)
-
8/2/2019 Stop Station Terminal
19/36
Pedestrian Ascent Speed on Stairs
0
25
50
75
100
125
150
175
200
0 5 10 15 20 25 30 35 40 45 50Pedestrian Space (ft2/p)
SlopeSpeed(ft/min)
Stairway Capacity Factors
Even minor reverse flows may reduce stairwaycapacity by as much as one-half
Although sizing procedures may suggest acontinuum of stairway widths, capacity is reallyadded in one-person-width increments(roughly 30 inches)
-
8/2/2019 Stop Station Terminal
20/36
Stairway Design Factors
Most new construction will use escalators as theprimary vertical circulation element
Can design to LOS E in this case
Where stairs will be the primary verticalcirculation element, design to LOS C to D
Emergency evacuation needs may require betterLOS (discussed later)
Stairway Design Process
1. Based on desired LOS, identify maximum flowrate per unit width
2. Estimate peak 15-minute demand
3. Compute design ped flow: (Step 2) / 15
4. Required width = (Step 3 / Step 1)
5. If minor, reverse-flow use occurs, add width ofone lane (30 inches)
-
8/2/2019 Stop Station Terminal
21/36
Escalator Capacity Factors
Angle of incline
Stair width
Operating speed
Escalator Capacity Factors
Manufacturers often state capacity based on amaximum theoretical capacitytwo people onevery stepwhich is never obtained
Capacity reduction factors
Intermittent ped arrivals
Ped inability to board quickly
Peds carrying baggage or packages Ped desire for a more comfortable space
-
8/2/2019 Stop Station Terminal
22/36
Escalator Capacity
Nominal capacity values based on oneperson every other step (single-width), orone person every step (double-width)
Elevators
-
8/2/2019 Stop Station Terminal
23/36
Elevator Usage
Vertical circulation within station
Deep station access
New York: 168th, 181st, 191st
Washington, DC: Forest Glen
Portland, OR: Washington Park
When not working, impacts station access for
mobility impaired
Elevator Capacity
Calculated similarly to transit vehicles
Car capacity is combination of loading standard (area perpassenger) and elevator floor area
Time to make round-trip, including loading and unloadingpassengers
Station access elevators often have doors on bothsides for simultaneous loading/unloading
-
8/2/2019 Stop Station Terminal
24/36
MovingWalkways
Moving Walkways
Typical speed 100 ft/min, some up to 160 ft/min
Less than typical walking speed
Capacity limited at entrance
Speed not a factor unless it causes persons to hesitate whenentering
Similar capacity as escalators
Double-width: about 90 p/min
-
8/2/2019 Stop Station Terminal
25/36
Doorways
Doorway Capacity
-
8/2/2019 Stop Station Terminal
26/36
FareControl
Fare Control Capacity
-
8/2/2019 Stop Station Terminal
27/36
TicketMachines
Ticket Machine Capacity
Time per passenger varies widely depending onmachine design and complexity of fare system
Least standardized element of transit design
Infrequent passengers require more time
Consider impacts of out-of-service machines
-
8/2/2019 Stop Station Terminal
28/36
Ticket Machine Examples
EmergencyEvacuation
-
8/2/2019 Stop Station Terminal
29/36
Emergency Evacuation Design
Must address evacuation requirements(person flow determined from the maximumperson accumulation and the maximum time toevacuate station)
Ability to remove passengers from platform areabefore next vehicle arrives
Overall passenger flow through station is animportant consideration (bottlenecks!)
Emergency Evacuation Design
General considerations
Sufficient exit capacity to evacuate station occupants(including those on trains) from platforms in 4.0 minutesor less, and to reach point of safety in 6.0 minutes or less
Sufficient exit capacity to get from most remote point onplatform to point of safety in 6.0 minutes or less
Second egess route remote from major
egress route from each platform
-
8/2/2019 Stop Station Terminal
30/36
Emergency Evacuation Design
Number of people to design for:
Loads of one train on each track during peak 15 minutes
Assume each train one headway late (i.e., is carrying twice itsnormal load, but no more than a maximum schedule load)
Passengers on platform during peak 15 minutes, assumingtrains are one headway late
Emergency Evacuation Design
Changes to normal design procedure:
NFPA 130 specifies passenger flow rates for specificstation elements
NFPA 130 specifies minimum widths for egress routes
Assume one escalator out of service; escalators cannotprovide more than half of exit capacity
Elevators cannot be used for exit capacity
-
8/2/2019 Stop Station Terminal
31/36
Emergency Evacuation Design
Maximum capacity required for normal operationsor emergency evacuation will govern
Because emergency evacuation routes may bedifferent than routes taken by passengers duringnormal operations, you cant assume thatevacuation needs will govern in all cases
PlatformSizing
Example
-
8/2/2019 Stop Station Terminal
32/36
Platform Sizing Example
New underground light rail station
Design year conditions:
A.M. exiting volume: 3,200 p/h
A.M. entering volume: 500 p/h
P.M. exiting volume: 500 p/h
P.M. entering volume: 2,900 p/h
Current peak hour factor (PHF) on completedportion of system is 0.714
Platform Sizing Example
Convert hourly volumes to peak 15-min volumes
Highest entering volume occurs during p.m. peak:
)(4 PHF
PP
h
15=
p015,1)714.0(4
900,2 ==15
P
-
8/2/2019 Stop Station Terminal
33/36
Platform Sizing Example
Two 4-car (300-ft) trains arrive in each directionin each 15-minute period
Under normal operating conditions, half of thepeak 15-minute demand could be on the platform
just before trains arrived
507 passengers
At a design LOS C (7 ft2/p), 507 * 7,
or 3,549 ft2
is required to store passengers
Platform Sizing Example
During the peak 15 minutes, approximately 175passengers will arrive on four trains
Forecast that highest-volume (outbound) trains wouldbring 61 passengers each
Designer estimates that 3/4 of passengers would be onplatform at any given time, given proposed locations ofstation exits
From walkway procedure, design LOS C is 15 ft2/p
Required space = 61 * 15 * 0.75 = 686 ft2
-
8/2/2019 Stop Station Terminal
34/36
Platform Sizing Example
Look at queue storage needs at exit points
Two escalators proposed to be provided
Escalator procedure gives capacity of 68 p/min at a typicalincline speed of 90 ft/min
Escalator capacity of 136 p/min is greater than passengerdemand of 61 exiting passengers per outbound trainnoqueue would develop
Platform Sizing Example
Consider unused platform space
Elevator shafts, stairways, escalators
Benches, information displays, advertising displays
Pillars
Designer determines 550 ft2 required based onproposed station elements
-
8/2/2019 Stop Station Terminal
35/36
Platform Sizing Example
Calculate buffer area required
Platform is 300 feet long to accommodate 4-car trains
Provide 1.5-ft buffer next to platform edges
Two edges on a center (island) platform
300 * 2 *1.5 = 900 ft2 required
Also consider any other walls designed into platform
Example assumes buffer space associated with elevators,stairs, escalators was built into the unused-space calculation
Platform Sizing Example
Calculate total area required
Passenger waiting area: 3,549 ft2
Walking area: 686 ft2
Queue storage: 0 ft2
Unused platform space: 550 ft2
Buffer space: 900 ft2
Total area required under normal operations andLOS C conditions: 5,685 ft2
-
8/2/2019 Stop Station Terminal
36/36
Platform Sizing Example
Also check:
Emergency evacuation needs and impacts on stationelement sizing
Irregular train operations resulting in more passengerswaiting on platform
How long a disruption could occur before platform crowdingreached uncomfortable or dangerous levels?
See TCQSM Part 7, Example Problem 3