strategic capacity management

36
Tata McGraw

Upload: rahul-khanna

Post on 05-May-2017

212 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Strategic Capacity Management

Tata McGraw

Page 2: Strategic Capacity Management

Chapter 5

Strategic Capacity Management

Page 3: Strategic Capacity Management

• Strategic Capacity Planning Defined• Capacity Utilization & Best Operating

Level• Economies & Diseconomies of Scale• The Experience Curve• Capacity Focus, Flexibility & Planning• Determining Capacity Requirements• Decision Trees• Capacity Utilization & Service Quality

OBJECTIVES

5-3

Page 4: Strategic Capacity Management

Strategic Capacity Planning

• Capacity can be defined as the ability to hold, receive, store, or accommodate

• Strategic capacity planning is an approach for determining the overall capacity level of capital intensive resources, including facilities, equipment, and overall labor force size

5-4

Page 5: Strategic Capacity Management

Capacity Utilization

• Where• Capacity used

– rate of output actually achieved • Best operating level

– capacity for which the process was designed

level operating BestusedCapacity rate nutilizatioCapacity

5-5

Page 6: Strategic Capacity Management

Best Operating Level

Example: Engineers design engines and assembly lines to operate at an ideal or “best operating level” to maximize output and minimize ware

Underutilization

Best OperatingLevel

Averageunit costof output

Volume

Overutilization

5-6

Page 7: Strategic Capacity Management

Example of Capacity Utilization

• During one week of production, a plant produced 83 units of a product. Its historic highest or best utilization recorded was 120 units per week. What is this plant’s capacity utilization rate?

Answer: Capacity utilization rate = Capacity used

Best operating level

= 83/120 =0.69 or 69%

5-7

Page 8: Strategic Capacity Management

Economies & Diseconomies of Scale

100-unitplant

200-unitplant 300-unit

plant

400-unitplant

Volume

Averageunit costof output

Economies of Scale and the Learning Curve working

Diseconomies of Scale start working

5-8

Page 9: Strategic Capacity Management

The Learning Curve

As plants produce more products, they gain experience in the best production methods and reduce their costs per unit

Total accumulated production of units

Cost orpriceper unit

Yesterday

TodayTomorrow

5-9

Page 10: Strategic Capacity Management

Capacity Focus

• The concept of the focused factory holds that production facilities work best when they focus on a fairly limited set of production objectives

• Plants Within Plants (PWP) – Extend focus concept to

operating level

5-10

Page 11: Strategic Capacity Management

Capacity Flexibility

• Flexible plants

• Flexible processes

• Flexible workers

5-11

Page 12: Strategic Capacity Management

Capacity Planning: Balance

Stage 1 Stage 2 Stage 3Unitsper

month6,000 7,000 5,000

Unbalanced stages of production

Stage 1 Stage 2 Stage 3Unitsper

month6,000 6,000 6,000

Balanced stages of production

Maintaining System Balance: Output of one stage is the exact input requirements for the next stage

5-12

Page 13: Strategic Capacity Management

Capacity Planning

• Frequency of Capacity Additions

• External Sources of Capacity

5-13

Page 14: Strategic Capacity Management

Determining Capacity Requirements

1. Forecast sales within each individual product line

2. Calculate equipment and labor requirements to meet the forecasts

3. Project equipment and labor availability over the planning horizon

5-14

Page 15: Strategic Capacity Management

Example of Capacity Requirements

A manufacturer produces two lines of mustard, FancyFine and Generic line. Each is sold in small and family-size plastic bottles.

The following table shows forecast demand for the next four years.

Year: 1 2 3 4FancyFineSmall (000s) 50 60 80 100Family (000s) 35 50 70 90GenericSmall (000s) 100 110 120 140Family (000s) 80 90 100 110

5-15

Page 16: Strategic Capacity Management

Example of Capacity Requirements (Continued): Product from a Capacity Viewpoint

• Question: Are we really producing two different types of mustards from the standpoint of capacity requirements?

• Answer: No, it’s the same product just packaged differently.

5-16

Page 17: Strategic Capacity Management

Example of Capacity Requirements (Continued) : Equipment and Labor Requirements

Year: 1 2 3 4Small (000s) 150 170 200 240Family (000s) 115 140 170 200

•Three 100,000 units-per-year machines are available for small-bottle production. Two operators required per machine.

•Two 120,000 units-per-year machines are available for family-sized-bottle production. Three operators required per machine.

5-17

Page 18: Strategic Capacity Management

Year: 1 2 3 4Small (000s) 150 170 200 240Family (000s) 115 140 170 200

Small Mach. Cap. 300,000 Labor 6Family-size Mach. Cap. 240,000 Labor 6

SmallPercent capacity used 50.00%Machine requirement 1.50Labor requirement 3.00Family-sizePercent capacity used 47.92%Machine requirement 0.96Labor requirement 2.88

Question: What are the Year 1 values for capacity, machine, and labor?

150,000/300,000=50%

At 2 operators for 100,000, it takes 3 operators for 150,000

At 1 machine for 100,000, it takes 1.5 machines for 150,000

©The McGraw-Hill Companies, Inc., 2004

5-18

Page 19: Strategic Capacity Management

Year: 1 2 3 4Small (000s) 150 170 200 240Family (000s) 115 140 170 200

Small Mach. Cap. 300,000 Labor 6Family-size Mach. Cap. 240,000 Labor 6

SmallPercent capacity used 50.00%Machine requirement 1.50Labor requirement 3.00Family-sizePercent capacity used 47.92%Machine requirement 0.96Labor requirement 2.88

Question: What are the values for columns 2, 3 and 4 in the table below?

56.67%1.703.40

58.33%1.173.50

66.67%2.004.00

70.83%1.424.25

80.00%2.404.80

83.33%1.675.00

5-19

Page 20: Strategic Capacity Management

Example of a Decision Tree Problem

A glass factory specializing in crystal is experiencing a substantial backlog, and the firm's management is considering three courses of action:

A) Arrange for subcontractingB) Construct new facilitiesC) Do nothing (no change)

The correct choice depends largely upon demand, which may be low, medium, or high. By consensus, management estimates the respective demand probabilities as 0.1, 0.5, and 0.4.

5-20

Page 21: Strategic Capacity Management

Example of a Decision Tree Problem (Continued): The Payoff Table

0.1 0.5 0.4Low Medium High

A 10 50 90B -120 25 200C 20 40 60

The management also estimates the profits when choosing from the three alternatives (A, B, and C) under the differing probable levels of demand. These profits, in thousands of dollars are presented in the table below:

5-21

Page 22: Strategic Capacity Management

Example of a Decision Tree Problem (Continued): Step 1. We start by drawing the three decisions

A

B

C

5-22

Page 23: Strategic Capacity Management

Example of Decision Tree Problem (Continued): Step 2. Add our possible states of nature, probabilities, and payoffs

AB

C

High demand (0.4)

Medium demand (0.5)

Low demand (0.1)

$90k$50k$10k

High demand (0.4)

Medium demand (0.5)

Low demand (0.1)

$200k$25k

-$120k

High demand (0.4)

Medium demand (0.5)

Low demand (0.1)

$60k$40k$20k

5-23

Page 24: Strategic Capacity Management

Example of Decision Tree Problem (Continued): Step 3. Determine the expected value of each decision

High demand (0.4)

Medium demand (0.5)

Low demand (0.1)

A

$90k$50k$10k

EVA=0.4(90)+0.5(50)+0.1(10)=$62k

$62k

5-24

Page 25: Strategic Capacity Management

Example of Decision Tree Problem (Continued): Step 4. Make decision

High demand (0.4)

Medium demand (0.5)

Low demand (0.1)

High demand (0.4)

Medium demand (0.5)

Low demand (0.1)

AB

CHigh demand (0.4)

Medium demand (0.5)

Low demand (0.1)

$90k$50k$10k

$200k$25k

-$120k

$60k$40k$20k

$62k

$80.5k

$46k

Alternative B generates the greatest expected profit, so our choice is B or to construct a new facility

5-25

Page 26: Strategic Capacity Management

Planning Service Capacity vs. Manufacturing Capacity

• Time: Goods can not be stored for later use and capacity must be available to provide a service when it is needed

• Location: Service goods must be at the customer demand point and capacity must be located near the customer

• Volatility of Demand: Much greater than in manufacturing

5-26

Page 27: Strategic Capacity Management

Service Utilization and Service Quality

5-27

Page 28: Strategic Capacity Management

Capacity Utilization & Service Quality

• Best operating point is near 70% of capacity

• From 70% to 100% of service capacity, what do you think happens to service quality?

5-28

Page 29: Strategic Capacity Management

Question Bowl

The objective of Strategic Capacity Planning is to provide an approach for determining the overall capacity level of which of the following?

a. Facilitiesb. Equipmentc. Labor force sized. All of the abovee. None of the above

Answer: d. All of the above

5-29

Page 30: Strategic Capacity Management

Question Bowl

To improve the Capacity Utilization Rate we can do which of the following?

a. Reduce “capacity used”b. Increase “capacity used”c. Increase “best operating level”d. All of the abovee. None of the above

Answer: b. Increase “capacity used” (This increases the numerator in the Capacity Utilization Rate ratio, which is desirable.)

5-30

Page 31: Strategic Capacity Management

Question Bowl

When we talk about Capacity Flexibility which of the following types of flexibility are included?

a. Plantsb. Processesc. Workersd. All of the abovee. None of the above

Answer: d. All of the above

5-31

Page 32: Strategic Capacity Management

Question Bowl

When adding capacity to existing operations which of the following are considerations that should be included in the planning effort?

a. Maintaining system balanceb. Frequency of additionsc. External sources d. All of the abovee. None of the above

Answer: d. All of the above

5-32

Page 33: Strategic Capacity Management

Question Bowl

Which of the following is a term used to describe the difference between projected capacity requirements and the actual capacity requirements?

a. Capacity cushionb. Capacity utilizationc. Capacity utilization rated. All of the abovee. None of the above

Answer: a. Capacity cushion

5-33

Page 34: Strategic Capacity Management

Question Bowl

In determining capacity requirements we must do which of the following?

a. Address the demands for individual product lines

b. Address the demands for individual plants

c. Allocate production throughout the plant network

d. All of the abovee. None of the above

Answer: d. All of the above

5-34

Page 35: Strategic Capacity Management

Question Bowl

In a Decision Tree problem used to evaluate capacity alternatives we need which of the following as prerequisite information?

a. Expect values of payoffsb. Payoff valuesc. A treed. All of the abovee. None of the above

Answer: b. Payoff values (Expected values are what is computed, not prerequisite to the analysis.)

5-35

Page 36: Strategic Capacity Management

1-36

End of Chapter 5

5-36