SHRP2 Safety Overall goal: Make a significant improvement in highway safety by greatly increasing our knowledge of driver behavior –How the driver interacts with and adapts to the roadway, traffic environment, traffic controls, weather, etc. –Differences in crash risk associated with these interactions –Proposed countermeasures based on the findings

TRANSCRIPT

Page 1: Strategic Highway Research Program 2 – Safety Component (SHRP2 Safety) 2012 Update Forrest Council

Strategic Highway Research Program 2 – Safety Component (SHRP2 Safety)

2012 Update

Forrest Council

Page 2: Strategic Highway Research Program 2 – Safety Component (SHRP2 Safety) 2012 Update Forrest Council

• Congressional-mandated (and AASHTO supported) research

• Four areas, 2007-14– Renewal (get in, get out, stay out)– Reliability (of travel times)– Capacity (increasing with systems

approach)– Safety (driver behavior)

Overall SHRP2

Page 3: Strategic Highway Research Program 2 – Safety Component (SHRP2 Safety) 2012 Update Forrest Council

SHRP2 Safety• Overall goal: Make a significant

improvement in highway safety by greatly increasing our knowledge of driver behavior – How the driver interacts with and adapts to the

roadway, traffic environment, traffic controls, weather, etc.

– Differences in crash risk associated with these interactions

– Proposed countermeasures based on the findings

Page 4: Strategic Highway Research Program 2 – Safety Component (SHRP2 Safety) 2012 Update Forrest Council

SHRP2 Safety (cont.)• Proposed safety research program

originally had two “tracks”– Naturalistic Driving Study

• Instrument 2K private vehicles and observe and record driver behavior, roadway, surrounding traffic, environment, etc.

• Collect roadway inventory data for sample of roads driven and merge with instrumented vehicle data

– Site-based Risk Study (Feasibility Study)• Instrument series of locations (e.g., intersections,

curves) and observe and record vehicle interactions under different roadway, traffic, and traffic control/warning conditions

• Feasibility study completed – no more effort

Page 5: Strategic Highway Research Program 2 – Safety Component (SHRP2 Safety) 2012 Update Forrest Council

Naturalistic Driving• Use new technology to continually

record– Driver behavior – Vehicle behavior– Roadway environment– Weather– Surrounding traffic

• 1,950 data collection system used for two years -- 3,700 vehicle years

• Six locations across nation• Supplemented by Roadway Inventory

Data– 12,500 centerline miles of data

collection– Collection at each of six sites

• Emphasis on ROR and Intersection crashes

Page 6: Strategic Highway Research Program 2 – Safety Component (SHRP2 Safety) 2012 Update Forrest Council

NDS Data Being Collected • Pre-driving

– Vision and Visual-cognitive – Cognitive and psychomotor (e.g., memory, reaction time)– Physical (e.g., upper and lower body strength/flexibility)– Health-related (e.g., sleep quality, medical conditions)– Psychological (e.g., risk-taking behavior, attention deficit)– Driver knowledge and driver history

• While driving– Multiple cameras/video– Accelerometer data – GPS– Forward radar– Passive alcohol sensor– Turn signals– Vehicle network data (accelerator, brake, ABS, airbag

deployment, seat belt use, etc.)– Cell phone use records (begin/end, no content)

Page 7: Strategic Highway Research Program 2 – Safety Component (SHRP2 Safety) 2012 Update Forrest Council

Data Collection Sites

Site DAS unitsBloomington, IN 150Central PA 150Tampa Bay, FL 450Erie County, NY 450Raleigh-Durham, NC 300Seattle, WA 450

1,950

Page 8: Strategic Highway Research Program 2 – Safety Component (SHRP2 Safety) 2012 Update Forrest Council

Current Status – Naturalistic Driving Study

• Data Collection– To be completed by November, 2013– 2,000 vehicles now in field, 1/3 of total data– 450,000+ trip files in database; 2.5M+ miles of

driving• Analysis contracts: working with initial data

sets– Four contractors in phase I proof of concept

effort• Road departure on rural 2-lane curves • Offset left-turn bays • Driver inattention • Rear-end crashes on congested freeways

Page 9: Strategic Highway Research Program 2 – Safety Component (SHRP2 Safety) 2012 Update Forrest Council

Roadway Inventory Data (RID)• Spatial-based inventory data on sample of

roads in each site to link with vehicle position data– Sample determined in part by NDS vehicle use

• Two sources of RID data – Collect spatial data from existing mapping and

inventory sources in each site – Collect additional data on-site with mobile data

collection • Fugro-Roadware vehicle• 12,500 centerline miles (both directions)

Page 10: Strategic Highway Research Program 2 – Safety Component (SHRP2 Safety) 2012 Update Forrest Council

RID Mobile Data Items• Horizontal Curvature: Radius, Length, PC, PT, Direction

– Had to change required specification • Grade• Cross Slope/Superelevation• Lane in terms of the number, width, and type ( turn, passing,

acceleration, car pool, etc…) • Shoulder type/curb; paved width if exists• Intersection location, number of approaches, and control

(uncontrolled, all-way stop, two-way stop, yield, signalized, roundabout). Ramp termini are considered intersections

• Posted speed limit sign and location • Median presence (Y/N), type (depressed, raised, flush,

barrier) • Rumble Strip presence (Y/N), location (centerline, edgeline,

shoulder) • Lighting presence( Y/N)

Page 11: Strategic Highway Research Program 2 – Safety Component (SHRP2 Safety) 2012 Update Forrest Council

RID Supplemental Data• Supplemental data on things affecting safety

and operations– Historic crash data– AADT– Short duration traffic counts– Seat belt laws– Winter road conditions– Weather– Work zones– Safety treatments (maybe!)– etc.

Page 12: Strategic Highway Research Program 2 – Safety Component (SHRP2 Safety) 2012 Update Forrest Council

RID Current Status• Existing RID being collected from DOTs• Initial mobile data collection

– Completed by end of 2012 for FL, NC, NY– Completed early in 2013 for WA, IN– Completed end of 2013 for PA

• Additional 6,300 miles to be distributed among sites and collected in 2013

• Supplemental data collection just initiated. Completed in 2013.

Page 13: Strategic Highway Research Program 2 – Safety Component (SHRP2 Safety) 2012 Update Forrest Council

2012 - 2013 Implementation Plans for Safety• Preparing for wider data use

– Decisions on and preparation of user-friendly files (no personal identifiers)

– Possible web-based tutorial, training• Planning for implementation and long-

term stewardship– Volpe Center study to identify long-term

stewardship/ownership options for NDS and RID.

Page 14: Strategic Highway Research Program 2 – Safety Component (SHRP2 Safety) 2012 Update Forrest Council

2012 – 2014 Implementation for Other SHRP2 Areas• Other three SHRP2 areas

– Renewal (get in, get out, stay out)– Reliability (of travel times)– Capacity (increasing with systems approach)

• Funding for implementation came from continuing resolutions (and some MAP-21)

• FHWA and AASHTO developed a joint 3-year implementation plan (Approximately $81M)

Page 15: Strategic Highway Research Program 2 – Safety Component (SHRP2 Safety) 2012 Update Forrest Council

2012 Starts

• Project Management Tools $0.5M– R09 Managing Risk in Rapid Renewal Contracts– R10 Managing Complex Projects

• R04 Bridge Designs for Rapid Renewal (2011) $4.0M

• R26 Preservation on High Volume Roadways (2011) $3.0M

• L12 Training for Traffic Incident Responders (2011) $4.5M

• Organizing for Reliability $6.5M– L31 CEO Workshop on Operations (2011)– L17 Knowledge Transfer System (2011)– L06 Organizing Agencies for Systems Operations and Mgt.– L01 Business Processes for Reliability

• C06 Integrating Ecosystem & Highway Planning $1.5M

$20.0M

15

Page 16: Strategic Highway Research Program 2 – Safety Component (SHRP2 Safety) 2012 Update Forrest Council

2013 Starts – Estimated

• TCAPP $6 – 7M– C01 TCAPP– C02 Performance Measures– C19 Expedited Project Delivery

• R07 Performance Specs for Rapid Renewal $0.2 –.05M• R15B Integrating Utility/Transportation (2011) $2 –

3M• R16 Railroad Agreements (2011) $1 – 2M• R23 Long-Life Pavements (2011) $1 – 2M• R06 Web Tool for Non-destructive Testing $1 –

2MEstimated costs ~ $14M

16

Page 17: Strategic Highway Research Program 2 – Safety Component (SHRP2 Safety) 2012 Update Forrest Council

2014 Starts - Estimated• Economic Impact Tools $1 –

2M– C03 Economic Impact Case Studies– C11 Economic Impact Analysis Tools

• C10 Travel Demand and Network Models $3 – 4M

• C15 Freight Planning Guide $1 – 2M

• Reliability Analysis Tools $3 – 4M– L02 Monitoring Programs for Reliability– L05 Planning/Programming for Reliability– L08 Reliability in the Highway Capacity Manual

• L36 Regional Operations Forum $0.5 – 1M• R19A Bridges Beyond 100 Years $1 – 2M• Pavement Technologies

– R05 Modular Pavement Solutions– R21 Composite Pavement Systems TBD

Estimated costs ~ $11M

17

Page 18: Strategic Highway Research Program 2 – Safety Component (SHRP2 Safety) 2012 Update Forrest Council

Additional Implementation Funding• Additional funding for continued implementation

of SHRP2 projects in FY 2013 and FY 2014 recently approved by AASHTO vote– 4 percent of each state's State Planning and

Research (SP&R) funding– Two-thirds of funding for product demonstration– Remaining one-third for educational outreach,

communications, IT support, evaluating the demonstrations, and administration of the program.

• So the future planning will now have to be modified.

18