streamlining solar pv projects to support the 5,000 mw ... · streamlining solar pv projects to...

18
Streamlining Solar PV Projects to Support the 5,000 MW Target in 2019 1a Markus Straslicka. Tetra Tech. Bali, Indonesia, 11 12 February 2016 BALI CLEAN ENERGY FORUM Nusa Dua, 11-12 February 2016

Upload: trandieu

Post on 17-Mar-2019

213 views

Category:

Documents


0 download

TRANSCRIPT

Streamlining Solar PV Projects to Support

the 5,000 MW Target in 2019

1aMarkus Straslicka. Tetra Tech.

Bali, Indonesia, 11 – 12 February 2016

BALI CLEAN ENERGY FORUM

Nusa Dua, 11-12 February 2016

Development Environment

2

Support Challenges

Ambitious Schedule, 5 GW 2019 • Diversity of Scenarios

Government Support • Complex Logistics

New Regulation • Grid Integration

Clean Market • Site Allocation

Utility Receptive • Market Development

Balanced Foundation for Development.

3

Achieve

5 GW

Target 2019

Regulatory & Permitting

Market

Size & Mechanisms

$ / kWh

& Payback Security

Balanced Foundation for Development.

4

Kick Start

Support

Competitive

Market

Target Support. Adaptive Policies

Balanced Foundation for Development.

5

Target Support. Adaptive Policies

Certainty: No discretionary decisions in the permitting chain.

Predictability: Every process must have a deadline and defined roadmap.

Structured: Who does what, under what criteria, in how much time.

Simplicity: Clean stepped process with no back loops.

Attractive: Market, participation mechanics and incentives.

Transparent: All processes must follow public known guidelines.

Sustainable: Predictable growth in market size and price.

Balanced Foundation for Development.

6

Target Support. Grid Integration & Support

Main Development Opportunities.

7

System Groups Platform Main Location Remarks

Rooftops Industrial

Commercial

Residential

Java-Bali Residential expected to be

small

Below 3 MW plants Ground Country Wide Expedite land permitting

Close to SubS, on 20 kV

Below 10 MW plants Ground Outside Java-Bali Within certain radius of

SubS, mainly on 20 kV

Above 10 MW plants Ground Outside Java-Bali PoC’s expected in 150 kV

Hybrid on Existing

Generation

Ground &

Rooftops

Outside Java-Bali &

Mainly over Dgen

High development

expected

Micro & Mini Grids

New Developments

Ground &

Rooftops

Outside Java-Bali New designs benefit from

higher efficiency

Streamlining Solar Projects. Development Diversity.

8

Same Basis, Specific Approach.

Mini & Micro

Grids

Hybrid Systems

Ground Systems

Rooftops

Streamlining Solar Projects. Developer Model.

9

Project Centric Approach vs Business Centric Approach

Project

Engineering

Business Model

Procurement

ConstructionBusiness

Model

Engineering

Procurement

Construction

Project

Streamlining Solar Projects. Developer Models.

10

Mid to Large Scale Projects

Subcontractors

Main Subcontractor A

Specialized Sub A1 … Ax

Main Subcontractor X

Specialized Sub X1 … Xy

EPC Contractor

Engineering

Procurement

Permitting

Construction

IPP Developer

Legal

Guarantees

Finance

Insurance

Streamlining Solar Projects. Integrated Developer

11

• Logistics

• Permitting

• Specialized Contractors

• Site Capacity

• Direct Construction Management

• Legal

• Financial

• Insurance

• Guarantees

• Design

• Permitting

• Engineering

• Procurement

EPC IPP

LocalSite

Small to Mid Scale Projects

Overview of Solar PV Technologies and Systems

Main components by cost share:

PV Modules 44.30 %

Inverter 7.49 %

Mounting/Racking 5.99 %

Balance of System 42.22 %

12

Overview of Solar PV Technologies and Systems

Balance of system. The Main Local Component.

• Design & Engineering.

• Topo & Geotech Study.

• ESIA.

• Permitting & Licenses.

• PoC Agreements.

• Installation Insurance.

• EPC Package:

• Site conditioning & logistics.

• Civil works, ground works, trenching

and backfilling.

• Passive security, fences, access.

• Cabling & ducting, DC, AC, HV, Comms

Install.

• Specialized labor (AC/LV electrical, DC

connections).

• Mechanical General Labor.

• Comms & SCADA Systems.

• AC/DC Testing.

• Step Up Transformers.

• HV Switchgear.

• HV Electrical Labor.

• HV Testing.

• Active Security.

• Interconnection works:

• HV line to off-site PoC.

• HV Grid Remote Disconnectors.

• HV SWG in Remote Substation.

• Testing, Commissioning & Hand Over.

13

Streamlining Solar Projects. Increasing Efficiency

14

• Minimize construction time with “building blocks” manageable with available resources

• Integrate your partners and suppliers in the opportunity evaluation and project design

• Create your own “flexible standards” to optimize procurement & capacity

• Minimize maintenance requirements & account for remoteness

• Select components that minimize the potential break points

• Develop a pipeline of projects to maximize your buying power

• Start the permitting for the next opportunities as they become available

• Select key equipment based on its capacity to support the particulars of the grid

Streamlining Solar Projects. Increasing Development

Efficiency

15

Main Areas in the Feasibility Study of Solar PV Projects

• From developer’ perspective:– Legal environment.

– Market size and participation options.

– Permitting process & technical regulations.

– Payback terms and guaranties.

– Grid capacity – Systems size.

– Viable interconnection options.

– Site options and conditions.

– Logistics & equipment available.

– Labor and specialized contractors.

– High level EPC & OM programs and costs.

– Financial model.16

• From PLN perspective:

– Analysis of proposed grid area for connection.

– Grid capacity vs Systems size,

• Existing generation.

• Existing loads.

• Feeders capacity & load.

• Planned increases in generation & load.

• Flow & load analysis (on developer).

– Viable interconnection options (near site tower, new derivation, new switchgear in

substation).

– Technical Specifications for interconnection.

17

Main Areas in the Feasibility Study of Solar PV Projects

For more information:

[email protected]

www.iced.or.id

18