substation equipment testing

Upload: krishna-das

Post on 02-Jun-2018

228 views

Category:

Documents


2 download

TRANSCRIPT

  • 8/11/2019 Substation Equipment Testing

    1/72

    2013 Doble Engineering Company. All Rights Reserved

    Substation Equipment Testing

    FECA Engineers ConferenceClearwater, Florida

    June 12, 2013

    Andre Lux

  • 8/11/2019 Substation Equipment Testing

    2/72

    2013 Doble Engineering Company. All Rights Reserved 2

    Confidential Notice

    Doble Engineering (Doble) hereby grants the recipient (you) the right to retain thispresentation and materials included within (the Presentation) for privatereference. No other rights, title, or interest, including, but not limited to, the rights tocopy, make use of, distribute, transmit, display or perform in public (or to thirdparties), edit, translate, or reformat any portion of the Presentation are hereby orotherwise granted and shall remain expressly reserved by Doble. Youacknowledge and agree that such limited license is expressly conditioned upon

    your acceptance of the terms herein. You further agree that, in the event of yourbreach, Doble will suffer irreparable damage and injury for which there is noadequate remedy at law. As such, Doble, in addition to any other rights andremedies available, shall be entitled to seek injunction by a tribunal of competent

    jurisdiction restricting you from committing or continuing any breach of these terms.

  • 8/11/2019 Substation Equipment Testing

    3/72

    2013 Doble Engineering Company. All Rights Reserved 3

    Tests are Performed to confirm the integrity of the equipmentor a part of it. These are performed:

    At various stages during the manufacturing process

    At final factory acceptance

    As on-site commissioning and acceptance

    As part of routine maintenance and diagnostics

    After system events

    As part of end-of-life determination and de-commissioning

    An important part of any equipments life cycle

    Test Significance

  • 8/11/2019 Substation Equipment Testing

    4/72

    2013 Doble Engineering Company. All Rights Reserved 4

    Average age (North America,typical utility) is 3540 years.

    On order of book life On order of anticipated

    design/expected life(whatever that means)

    Condition varies from utilityutility, and from one

    transformer to another, butmany are of marginalcondition and getting poorer.

    Replacement programs cantkeep up with escalating ageand degrading condition.

    Life extension programs aimto prolong life (age) evenfurther.

    Why all this focus on transformers?

    0

    25

    50

    75

    100

    125

    150

    175

    200

    225

    250

    275

    300

    325

    350

    375

    400

    0 -10 11 - 20 21 - 30 31 - 40 41 - 50 51 - 60 >60

    NumberofUnits

    Age Group

    Typical Transformer Population, Large

    North American IOU

    Number of TD Transformers

  • 8/11/2019 Substation Equipment Testing

    5/72

    2013 Doble Engineering Company. All Rights Reserved 5

    Potential Failure Impacts:

    Personnel safety Environmental impact

    Significant collateral

    damage

    Long outage times

    Degrading reliability

    Long lead times for

    replacement

    Significant monetary costs

    associated with unplanned

    outages.

    Why all this focus on transformers?

  • 8/11/2019 Substation Equipment Testing

    6/72

    2013 Doble Engineering Company. All Rights Reserved 6

    1. Overall (Transformer) Power Factor and Capacitance

    2. Bushing Power Factor and Capacitance

    3. Transformer Turns Ratio

    4. DC Winding Resistance

    5. Excitation Current6. Oil Quality

    7. Dissolved Gas Analysis

    8. Leakage Reactance

    9. Sweep Frequency Response Analysis10. Partial Discharge

    11. Visual Inspections

    Typical Transformer Tests

  • 8/11/2019 Substation Equipment Testing

    7/72

    2013 Doble Engineering Company. All Rights Reserved 7

    Each test targets a different area/component/accessory of the

    transformer: Core

    Winding

    Insulating fluid

    Solid insulation Tap Changer

    Bushings

    Controls

    Tank

    The main goal is to detect a developing condition (failure) andtake corrective action as appropriate.

    Each test targets a particular potential failuremode/aging/deterioration mechanism

    Test Significance

  • 8/11/2019 Substation Equipment Testing

    8/72

    2013 Doble Engineering Company. All Rights Reserved 8

    Large IOU Failure History, 19882008 (96 failures)

    What are the most common failure modes?

    Through-Fault

    Winding

    Bushing

    Gassing

    Leads

    Lightning

    Tap Changer

    UnknownVandalism

    Leaking Valve

    Design Problem

    Overheating

    26 %

    20 %

    15%

    13%

    8%

    5%

    4%^4%

  • 8/11/2019 Substation Equipment Testing

    9/72

    2013 Doble Engineering Company. All Rights Reserved 9

    What is Power Factor?

    Power factor is a measurement of the efficiency of

    insulation system.

  • 8/11/2019 Substation Equipment Testing

    10/72

    2013 Doble Engineering Company. All Rights Reserved 10

    Basic Power Factor Circuit

  • 8/11/2019 Substation Equipment Testing

    11/72

    2013 Doble Engineering Company. All Rights Reserved 11

    The Term Power Factor Describes:

    The phase angle relationship between the applied voltage acrossand the total current through a specimen.

    The ratio of the real power to the apparent power.

    The relationship between the total and resistive current

    The efficiency of a power system in terms of real and reactive

    power flow

  • 8/11/2019 Substation Equipment Testing

    12/72

    2013 Doble Engineering Company. All Rights Reserved 12

    Insulation kV mA Watts % P.F.

    CH + CHL 10 28.5 1.45

    CH 10 7.05 0.38 0.39

    CHL (UST) 10 21.5 0.95 0.32

    CHL 21.45 1.07 0.36

    CL +CHL 2 39.5 5.5

    CL 2 17.65 2.85 1.18

    CHL (UST) 2 21.5 3.55 1.2

    CHL 21.85 2.65

    FPE, 3-, 2-winding , -Y transformer

    13.8/4.3 kV, 7 MVA

    High CL % P.F. & disagreement between HV & LV CHL %P.F.s

    Localized moisture/contamination in the L.V. winding

    Problem Revealed in LV Winding

  • 8/11/2019 Substation Equipment Testing

    13/72

    2013 Doble Engineering Company. All Rights Reserved 13

    Westinghouse, 3-Phase, 345/19 kV, 343 MVA Shell-Form Generator Step-up Transformer

    Test Date CH (%PF) CL (%PF) CHL (%PF)

    1972 0.50 0.59 0.47

    1975 1.60 0.57 1.44

    Routine Test Sister unit was tested & did not indicate a

    similar increase.Other tests performed:

    TTR, DC Winding Resistance, Exciting Current, TCG, DGA, Oil P.F. (No problems indicated)

    Transformer Defect Oil-Pump Problem

  • 8/11/2019 Substation Equipment Testing

    14/72

    2013 Doble Engineering Company. All Rights Reserved 14

    Transformer Defect Oil-Pump Problem

    Results of Internal Inspection:

    Oil pump No. 8 (located in the area of the - C H.V. bushing) wasseverely deteriorated. The outer bearing sleeve, the pump housing, &

    1/2 the width of the impeller blade were destroyed.

    After clean-up & repair, the unit was returned to service. It failed 4

    months later. It is believed that the fault resulted from the magnetic

    contamination introduced previously.

    1 other pump was found to have appreciable bearing wear & the

    remaining 7 pumps had varying, lesser degrees of bearing-wear.

  • 8/11/2019 Substation Equipment Testing

    15/72

    2013 Doble Engineering Company. All Rights Reserved 15

    Dielectric Capacitance

    C = CapacitanceA = area of electrodes = Dielectric constant

    d = Distance between electrodesAll of these variables are Physical Parameters

    AdC= Aed

  • 8/11/2019 Substation Equipment Testing

    16/72

    2013 Doble Engineering Company. All Rights Reserved 16

    Significance

    Indicate a physical change

    Bushings - shorting of capacitive layers

    Transformers - movement of core/coils

    Arresters - broken elements Suggested Limits

    + 5% - Investigate

    + 10% - Investigate/remove from service

    Changes in Current/Capacitance

  • 8/11/2019 Substation Equipment Testing

    17/72

    2013 Doble Engineering Company. All Rights Reserved 17

    Significance of Measured Capacitance

    Interwinding (CHT) capacitance of anautotransformer.

    Test Date 20C % PF Cap (pF)

    1965 0.20 2,650

    1968 0.29 2,756

    1974 0.29 3,710

    1982 0.32 5,100

  • 8/11/2019 Substation Equipment Testing

    18/72

    2013 Doble Engineering Company. All Rights Reserved 18

    Capacitance change can indicate movement and/or deformation of transformer windings.

    C=Ae

    d

    What other tests would

    confirm this?

    Leakage Reactance

    SFRA

    Significance of Measured Capacitance

  • 8/11/2019 Substation Equipment Testing

    19/72

    2013 Doble Engineering Company. All Rights Reserved 19

    Bushing Tests

  • 8/11/2019 Substation Equipment Testing

    20/72

    2013 Doble Engineering Company. All Rights Reserved 20

    Condenser Bushing Components

    Center Conductor

    Sight-Glass

    Liquid or Compound Filler

    Insulating Weather shed

    Main Insulating Core

    Tap Insulation

    Tap Electrode

    Mounting Flange

    Ground SleeveTapped Capacitance-Graded Layer

    Lower Insulator

  • 8/11/2019 Substation Equipment Testing

    21/72

    2013 Doble Engineering Company. All Rights Reserved 21

    Condenser Bushing Construction

    Voltage is stressed equally across each condenser layer of

    C1insulation

    Relationship between C1and C2 dependent upon desired

    voltage at the tap when in service

    Main Insulation C1

    CA = CB = CC = CD = CE = CF= CG = CH = CI = CJ

    V1 = V2 = V3 = V4 = V5 = V6 = V7 = V8 = V9= V10 Tap

    Electrode

    CKCenter

    Conductor

    Line-to-Ground Voltage for Type A and T

    Grounded

    Layer/Flange

  • 8/11/2019 Substation Equipment Testing

    22/72

    2013 Doble Engineering Company. All Rights Reserved 22

    Typical Condenser Bushing Construction

    Core Wind

    C2 Plate

    Foil

  • 8/11/2019 Substation Equipment Testing

    23/72

    2013 Doble Engineering Company. All Rights Reserved 23

    ABB O+C Construction

    C2 Plate

  • 8/11/2019 Substation Equipment Testing

    24/72

    2013 Doble Engineering Company. All Rights Reserved 24

    ABB O+C, 27 kV

    Conductors

  • 8/11/2019 Substation Equipment Testing

    25/72

    2013 Doble Engineering Company. All Rights Reserved 25

    Bushing Tests

    Ungrounded-Specimen Test

    Center Conductor to Tap, C1

    Tap Insulation Test

    Tap to Flange, C2

    Hot Collar TestExternally Applied Collar to Center Conductor

    Overall

    Center Conductor to Flange

  • 8/11/2019 Substation Equipment Testing

    26/72

    2013 Doble Engineering Company. All Rights Reserved 26

    Test kV I (mA) Watts 20C %PF

    10 1.313 -0.007 -0.053

    ABB Type O+C 230 kV bushing

    Staining of the Lower Insulator

    E it ti C t & L

  • 8/11/2019 Substation Equipment Testing

    27/72

    2013 Doble Engineering Company. All Rights Reserved 27

    Excitation Current & Loss

    Exciting Current and Loss Factory Tests at Rated Voltage.

    Field Tests at the Lesser of Rated Voltage or Highest

    Capability of the Test Set.

    Simple measurement of single-phase current on one side ofthe transformer, usually the HV side, with the other side left

    floating (with the exception of a grounded neutral).

    The tests should be performed at the highest possible test

    voltage without exceeding the voltage rating of the excitedwinding.

    Magnetic Circuit and Winding Tests

  • 8/11/2019 Substation Equipment Testing

    28/72

    2013 Doble Engineering Company. All Rights Reserved 28

    Excitation Current and Loss

    Excitation Current Tests Can Identify Problems in the Iron Core, Windings ,

    and Tap Changers

    Core

    Abnormal core assembly

    Windings

    Turn-to-turn shorts

    Turn-to-ground shorts (groundedwindings)

    High resistance turn-to turn or

    turn-to-ground shorts

    Tap Changers

    Mechanical failures

    Auxiliary transformer problems

    C &

  • 8/11/2019 Substation Equipment Testing

    29/72

    2013 Doble Engineering Company. All Rights Reserved 29

    Excitation Current & Loss

    What is Excitation Current?

    ~E1

    Iex

    1:1

    +

    -E2

    +

    -

    Excitation current is the current that flows when the winding of the

    transformer is energized under no-load conditions. It supplies the energy

    necessary to create the magnetic flux in the iron core.

    E i i C & L

  • 8/11/2019 Substation Equipment Testing

    30/72

    2013 Doble Engineering Company. All Rights Reserved 30

    Excitation Current & Loss

    When there is a Fault on the Secondary Winding

    1:11

    H1

    H0

    +E1

    -

    HV

    LV

    The primary current increases due to the current through the short-circuited turns.

    Excitation Current & Loss

  • 8/11/2019 Substation Equipment Testing

    31/72

    2013 Doble Engineering Company. All Rights Reserved 31

    Excitation Current & Loss

    Examine phase patterns

    Typical pattern is two high similar results on the outer

    phases and one lower result on the center phase

    however there are exceptions due to core design, etc.

    Residual magnetism can affect results DC tests can magnetize core

    Can be a result of being de-energized from the

    system

    Subsequent tests should be performed at same testvoltage and with same connections

  • 8/11/2019 Substation Equipment Testing

    32/72

    2013 Doble Engineering Company. All Rights Reserved 32

    Current (ma) Losses (watts)

    H3-H1 H1-H2 H2-H3 H3-H1 H1-H2 H2-H3

    Aug 7 2001 6.96 3.12 75.76 42.85 19.36 735.1April 10 2000 7.03 3.27 7.66 43.98 19.94 46.87

    Jan 19 1999 7.172 3.4 7.36 44.69 20.64 45.67

    May 5 1994 7.64 3.46 8.05 47.72 20.96 48.99

    A raccoon came into contact with the H3 bushing

    which took out the bushing and an associated

    voltage regulator. The bushing was replaced,

    regulator cleaned up and the equipment was putback into service after a series of tests. Shortly

    thereafter, the transformer was noted to be running

    hot.

    A DGA and TCG test was performed with very high

    results. %PF did not show any major changes but the

    Iex did.

    Winding Resistance

  • 8/11/2019 Substation Equipment Testing

    33/72

    2013 Doble Engineering Company. All Rights Reserved 33

    Winding Resistance

    Check for abnormalities due to loose connections, brokenstrands, and high-contact resistance in tap-changers.

    Interpretation of results is usually based on a comparisonof measurements made separately on each phase in the

    case of a wye-connected winding or between pairs ofterminals on a delta-connected winding.

    Comparison may also be made with original datameasured in the factory. Agreement to within 5% for any ofthe above comparisons is usually considered satisfactory.

    It may be necessary to convert the resistancemeasurements to values corresponding to the referencetemperature in the transformer test report

    Magnetic Circuit and Winding Tests

    Transformer Turns Ratio

  • 8/11/2019 Substation Equipment Testing

    34/72

    2013 Doble Engineering Company. All Rights Reserved 34

    Transformer Turns Ratio

    Ratio of the number of turns in a higher voltage winding

    to that in a lower voltage winding Factory and Field

    Low Voltage Method

    High Voltage Capacitance Reference Method

    Confirm nameplate ratios Detect short-circuited turn-to-turn insulation

    Find open-circuited windings

    Find problems with tap changer connections (DETC &

    LTC)

    Mechanical Integrity Diagnostics

  • 8/11/2019 Substation Equipment Testing

    35/72

    2013 Doble Engineering Company. All Rights Reserved 35

    Mechanical Integrity Diagnostics

    Frequency Response Analysis (FRA)

    Leakage Reactance

    Capacitance

    Excitation Current

    These independent diagnostic methods have their place inascertaining transformer condition

    Frequency Response Testing

  • 8/11/2019 Substation Equipment Testing

    36/72

    2013 Doble Engineering Company. All Rights Reserved 36

    Purpose

    Assess Mechanical Condition of Transformers (mechanical

    distortions)

    Detect Core and Winding Movement

    Due to large electromagnetic forces from fault currents Winding Shrinkage causing release of clamping

    pressure

    Transformer Relocations or Shipping

    Frequency Response Testing

  • 8/11/2019 Substation Equipment Testing

    37/72

    2013 Doble Engineering Company. All Rights Reserved 37

    Test Sequence

    Measures the response Voutfor a low voltage sign Vinthatvaries in frequency. For two winding three phase transformer 9 tests

    Open circuit test: one per winding, per phase (6 tests)

    Short circuit test: one per phase (3 tests)

    The analysis plots the ratio of the transmitted voltage Voutwaveform to the applied voltage waveform Vinin db.

    Low voltage Signal 20hz to 2Mhz

    in

    out

    V

    VdB

    10log20

  • 8/11/2019 Substation Equipment Testing

    38/72

    2013 Doble Engineering Company. All Rights Reserved 38

    SFRA - Sweep Frequency Response Analysis

    Core Tap windings

    Main windingClamping structures

    Tap leads

    < 2 kHz

    2 kHz20 kHz 20 kHz100 kHz

    100 kHz400 kHz

    400 kHz2 MHz

    Case Study: Close in Fault

  • 8/11/2019 Substation Equipment Testing

    39/72

    2013 Doble Engineering Company. All Rights Reserved 39

    Case Study: Close-in Fault

    Capacity: 25/33/41 MVA

    Voltage: 112/14.4 kV BIL 450KV

    Entered service 1996 (10 years old)

    Transformer saw a number of close in

    faults, while attempting to isolate a cable

    problem

    The bus attached to the low side caught fire No surge arresters on low side

    Can the transformer be placed back

    into service?

    Overall Capacitance and Power Factor

  • 8/11/2019 Substation Equipment Testing

    40/72

    2013 Doble Engineering Company. All Rights Reserved 40

    Overall Capacitance and Power Factor

    PF Results are acceptable

    CapacitanceUnknown because no precious overallresults.

  • 8/11/2019 Substation Equipment Testing

    41/72

    2013 Doble Engineering Company. All Rights Reserved 41

    Exciting Current Results

  • 8/11/2019 Substation Equipment Testing

    42/72

    2013 Doble Engineering Company. All Rights Reserved 42

    Per Phase Leakage Reactance

  • 8/11/2019 Substation Equipment Testing

    43/72

    2013 Doble Engineering Company. All Rights Reserved 43

    3Ph Equivalent LR

    O Ci i Hi h Sid

  • 8/11/2019 Substation Equipment Testing

    44/72

    2013 Doble Engineering Company. All Rights Reserved 44

    Open Circuit High Side

    O Ci it L Sid

  • 8/11/2019 Substation Equipment Testing

    45/72

    2013 Doble Engineering Company. All Rights Reserved 45

    Open Circuit Low Side

    Sh t Ci it

  • 8/11/2019 Substation Equipment Testing

    46/72

    2013 Doble Engineering Company. All Rights Reserved 46

    Short Circuit

    C St d L k R t

  • 8/11/2019 Substation Equipment Testing

    47/72

    2013 Doble Engineering Company. All Rights Reserved 47

    Case Study Leakage Reactance

    0.2 dB delta is significant here!

    T Y L t

  • 8/11/2019 Substation Equipment Testing

    48/72

    2013 Doble Engineering Company. All Rights Reserved 48

    Two Years Later

    Fl id T t

  • 8/11/2019 Substation Equipment Testing

    49/72

    2013 Doble Engineering Company. All Rights Reserved 49

    Fluid Tests

    Why Measure Gases in Oil?

  • 8/11/2019 Substation Equipment Testing

    50/72

    2013 Doble Engineering Company. All Rights Reserved 50

    Excellent indicators of incipient fault condition - Most

    important diagnostic in the industry

    Can help determine the materials involved

    Severity of the condition - abnormal amounts

    Detect of wide variety of conditions - most important test

    Gas-in-oil analysis complex - not easily simplified for easyanalysis in all cases

    Why Measure Gases in Oil?

    K G A l i

  • 8/11/2019 Substation Equipment Testing

    51/72

    2013 Doble Engineering Company. All Rights Reserved 51

    Key Gas Analysis

    Condition

    Key Gas

    Arcing High concentration of hydrogen and acetylene, with

    minor quantities of methane and ethylene.

    Key gas - Acetylene

    Corona Low-energy electrical discharge creates hydrogen and

    methane, with lesser quantities of ethane and ethylene.

    Key gas - Hydrogen

    Overheated Oil Includes ethylene and methane, and lesser quantities

    of hydrogen and ethane.

    Key gas - Ethylene

    Overheated Cellulose Carbon dioxide and carbon monoxide are evolvedfrom over-heated cellulose. Hydrocarbon gasses will

    be formed if the fault involves an oil-impregnated

    structure.

    Key gas - Carbon Monoxide

    Gases Produced during Overheating

  • 8/11/2019 Substation Equipment Testing

    52/72

    2013 Doble Engineering Company. All Rights Reserved52

    Gases Produced during Overheating

    Temperature of Overheating Gas Chemical Symbol

    Low Temperature (~120o ) Methane CH4

    Ethane C2H6

    Ethylene C2H4

    High Temperature (>350oC) Acetylene C2H2

    Combustible Gases Westinghouse 24 years old

  • 8/11/2019 Substation Equipment Testing

    53/72

    2013 Doble Engineering Company. All Rights Reserved 53

    Combustible Gases Westinghouse 24 years old

    Rating 115 kV, 40 MVA

    0

    250

    500

    750

    1000

    1250

    1500

    1750

    2000

    2250

    2500

    1/1/89 9/28/91 6/24/94 3/20/97 12/15/99 9/10/02 6/6/05

    Date

    Concentration,p

    pm

    .

    Hydrogen (H2)

    Methane (CH4)Carbon Monox. (CO)

    Ethane (C2H6)

    Ethylene (C2H4)

    Comb Gas

    Acetylene (C2H2)

    Overheating of Support Structure

  • 8/11/2019 Substation Equipment Testing

    54/72

    2013 Doble Engineering Company. All Rights Reserved 54

    Overheating of Support Structure

    Main Clamping Top Beam

    Water Content

  • 8/11/2019 Substation Equipment Testing

    55/72

    2013 Doble Engineering Company. All Rights Reserved 55

    Water content of oil and paper are related and can be described

    using equilibrium curves

    Dielectric breakdown voltage of the insulation system

    Ability to overload

    Temperature water vapor bubbles evolve from solid insulation afunction of its water content, with 2% water in paper can go up to

    140C without risk of bubbles

    Aging of the solid insulation directly proportional

    Susceptibility to high relative saturation of water in oil and

    formation of free water

    Water Content

  • 8/11/2019 Substation Equipment Testing

    56/72

    2013 Doble Engineering Company. All Rights Reserved 56

    Power Factor - Measure of dielectric losses, dielectric

    heating, indicator soluble polar, ionic or colloidalcontaminants or aging byproducts

    Color - Rapid change indicator of accelerated aging of the

    insulation system

    Interfacial Tension - Detects deterioration of oil in the early

    stages of aging, affected by the polar contaminants

    Acidity - Aging byproducts, accelerates aging of paper andcorrodes metal

    Physical Properties and Inhibitor Content

  • 8/11/2019 Substation Equipment Testing

    57/72

    2013 Doble Engineering Company. All Rights Reserved 57

    Viscosity

    Should not change with aging

    Important characteristic for cooling

    Takes gross contamination, aging, or over processing to change

    significantly Relative density

    Should not change with aging

    Simple periodic measure

    Takes gross contamination, aging, or over processing to changesignificantly

    Inhibitor Content - replenish when handling the oil

    Physical Properties and Inhibitor Content

    Partial Discharge

  • 8/11/2019 Substation Equipment Testing

    58/72

    2013 Doble Engineering Company. All Rights Reserved 58

    PD diagnostics can be used to trend changes in the level

    and severity of insulation degradation Once presentit dominates as its own inherent stress

    degradation mechanism

    Its an early warning signal and precursor to completeinsulation failure and breakdown

    Early detection of PD is critical in the prevention of in

    catastrophic failures

    Partial Discharge

    Types of PD

  • 8/11/2019 Substation Equipment Testing

    59/72

    2013 Doble Engineering Company. All Rights Reserved 59

    Types of PD

    Void/Protrusions in solidinsulation, cavity in liquids.

    Surface discharge

    Corona

    PD Insulation Model

  • 8/11/2019 Substation Equipment Testing

    60/72

    2013 Doble Engineering Company. All Rights Reserved 60

    The voids

    capacitance CCis

    part of the overalldielectrics capacitance

    which includes the

    remaining series

    capacitance CBandshunt capacitance CA

    The void has a

    breakdown voltage VS

    that once reached

    across the void Ccwill

    spark over (PD)

    VS

    CC

    CA

    CB

    CACC

    CB

    =

    Partial Discharge

  • 8/11/2019 Substation Equipment Testing

    61/72

    2013 Doble Engineering Company. All Rights Reserved 61

    Causes of PD in insulation system:

    Voids in epoxy resins, polymers, paper Bubbles in liquids/oils

    Metal deposits, irregularities such as protrusions,contaminants

    Electrodes and insulation surfaces and interfaces

    Can arise through:

    Poor design and manufacture

    Damage of equipment e.g. Transport damage Poor installation processespoor workmanship

    General ageing or deterioration of materials

    g

    PD Measurement on Transformers

  • 8/11/2019 Substation Equipment Testing

    62/72

    2013 Doble Engineering Company. All Rights Reserved 62

    ValveConnector

    Tank

    Sensor Application Measuring Impedance

  • 8/11/2019 Substation Equipment Testing

    63/72

    2013 Doble Engineering Company. All Rights Reserved 63

    Se so pp cat o easu g peda ce

    PD Measuring Impedance for Bushing Tap Installation

    Acoustics

  • 8/11/2019 Substation Equipment Testing

    64/72

    2013 Doble Engineering Company. All Rights Reserved 64

    Acoustics are a valid technique for locatingPD but its thewrong approach for detecting PD due to low sensitivity of

    the AE method and the fact that PD imbedded in thewinding will not produce acoustic pressure wavesdetectable on the tank wall. So no Acoustic Signal does notmean no PD and detection via HF-CT on the star point endwill only work for strong PD.

  • 8/11/2019 Substation Equipment Testing

    65/72

    Why Monitor Bushings?

  • 8/11/2019 Substation Equipment Testing

    66/72

    2013 Doble Engineering Company. All Rights Reserved 66

    Why Monitor Bushings?

    Bushing MonitoringGradual Increase

  • 8/11/2019 Substation Equipment Testing

    67/72

    2013 Doble Engineering Company. All Rights Reserved 67

    Gradual deterioration over several month span.

    g g

    Bushing MonitoringSudden Increase

  • 8/11/2019 Substation Equipment Testing

    68/72

    2013 Doble Engineering Company. All Rights Reserved 68

    The bushing was one of a type which had several failures around the world

    recently.

    A sudden variation in leakage current raised an alarm. Operations took the bushing off line and replaced ita tear down indicated they

    had just hoursbefore catastrophic failure

    g g

    Transformer Test Summary

  • 8/11/2019 Substation Equipment Testing

    69/72

    2013 Doble Engineering Company. All Rights Reserved 69

    Each test is sensitive to certain types of issues.

    Motivation for testing should always be determinedbefore arbitrarily performing a variety of tests

    Routine testing should provide owner with a high levelof comfort with transformer condition

    Investigative testing needs to be more focused andthorough

    Test results should always be scrutinized and takenseriously

    Transformer Test Summary

  • 8/11/2019 Substation Equipment Testing

    70/72

    2013 Doble Engineering Company. All Rights Reserved 70

    Planning discussions for contingencies are important in

    making good decisions There are cases where some tests will fail to identify a

    problem.

  • 8/11/2019 Substation Equipment Testing

    71/72

    Confidential Notice

  • 8/11/2019 Substation Equipment Testing

    72/72

    Confidential Notice

    Doble Engineering (Doble) hereby grants the recipient (you) the right to retain this

    presentation and materials included within (the Presentation) for privatereference. No other rights, title, or interest, including, but not limited to, the rights tocopy, make use of, distribute, transmit, display or perform in public (or to thirdparties), edit, translate, or reformat any portion of the Presentation are hereby orotherwise granted and shall remain expressly reserved by Doble. Youacknowledge and agree that such limited license is expressly conditioned uponyour acceptance of the terms herein. You further agree that, in the event of your

    breach, Doble will suffer irreparable damage and injury for which there is noadequate remedy at law. As such, Doble, in addition to any other rights andremedies available, shall be entitled to seek injunction by a tribunal of competent

    jurisdiction restricting you from committing or continuing any breach of these terms.