suffolk energy from waste facility 2018 annual … · 29/03/2019 [5 of 19] 1. plant description...
TRANSCRIPT
SUEZ Suffolk Annual Performance Report 2017
[1 of 19]
SUFFOLK
Energy from Waste Facility
2018 ANNUAL PERFORMANCE REPORT
29/03/2019 [2 of 19]
DOCUMENT
TITLE:
Suffolk – Energy from Waste Facility
2018 Annual Performance Report
ISSUE DATE: January 2019
(Resubmission March 2019)
PREPARED BY: NAME
EIR Manager Emma Woollen
APPROVED BY: NAME
Plant Manager Paul Newby
REPORT
DISTRIBUTION: NAME
No. of
Copies
SUEZ – EIR Manager
SUEZ – Plant Manager
Environment Agency Officer
1
1
1
29/03/2019 [3 of 19]
CONTENTS
1. Introduction 4 2. Plant description 5 3. Summary of plant operation 5 4. Permit variation 8 5. Summary of plant monitoring 8 6. Summary of plant compliance 12 7. Summary of plant improvements 13 8. Further information 14
APPENDIX 1. 2018 AIR EMISSIONS GRAPHS
29/03/2019 [4 of 19]
1. INTRODUCTION
Table 1: Plant details
Name of Company SUEZ Recycling and Recovery UK
Name of Plant SUEZ Suffolk – Energy from Waste Facility
Permit Number WP3438HZ
Address Lodge Lane
Great Blakenham
Ipswich
IP6 0JE
Phone 01473 839149
Contact Name/Position Paul Newby – EfW Plant Manager
Further information, description of waste types burned and origin
Municipal household waste
Commercial and Industrial waste
29/03/2019 [5 of 19]
1. PLANT DESCRIPTION
This non-hazardous waste incinerator operates 24/7 and can receive up to 269,000 tonnes of municipal waste and commercial/Industrial waste. The plant has two furnace lines with a processing capacity of 269,000 tonnes per annum. The heat produced by waste incineration is used to raise superheated steam which generates 177,000 MWh/annum of electricity.
Activities associated with the incineration are receipt and storage of municipal waste and commercial/industrial waste, production of steam and electricity, abatement of flue gas and handling of Incinerator Bottom Ash (IBA) and Air Pollution Control Residue (APCR).
Suffolk EfW commissioning finished on 1st December 2014, when the plant was handed over from the EPC contractor to SUEZ UK. Permit conditions apply since then. The data included in this report corresponds to the following period: 1st January 2018 to 31st December 2018.
2. SUMMARY OF PLANT OPERATION
Incoming waste is delivered to site by refuse collection trucks. It is then checked in, weighed and delivered into the reception hall.
RECEPTION HALL
A large reception hall allows for refuse collection trucks to manoeuvre and tip waste safely. Air needed for combustion is drawn into the furnace from here so that negative pressure is maintained in order to avoid odour and dust escaping the building.
BUNKER
Waste vehicles reverse to a wheel stop and tip their loads into a large concrete bunker. Mixing of waste occurs as the cranes driver sorts the waste looking for unsuitable material to be removed, and to improve the homogeneity of the incinerator feedstock.
CONTROL ROOM
The plant’s control room centralises the operation of all equipment, including the grab cranes used to mix and load waste into a hopper that feeds the furnace. All on-site functions are monitored automatically and manually. Its systems verify in real time that equipment is functioning properly, continuously monitor the combustion gas, and maximise the efficiency of the entire EfW process.
GRATE AND BOILER
Waste is lifted into the charging hoppers by the crane. From here it falls into the furnace-charging chute and then is introduced onto the grate system by hydraulic feeders for incineration. An auxiliary burner can be used to help keeping the temperature above 850°C if required. The thermal energy released from the burning is
used to convert water to super-heated steam along a boiler composed of 6 vertical passes. At high pressure, this steam drives a turbine to generate electricity.
ELECTRICITY GENERATION
Electricity is generated at 11kv, with an electric production of 170,461 MWh/annum and exporting 150,127 MWh/annum to the national grid.
29/03/2019 [6 of 19]
INCINERATOR BOTTOM ASH (IBA)
Ash left on the grate after incineration is carried by conveyor, after quenching, to the IBA processing facility. Up to 65,000 tonne of IBA is processed on site by the removal of ferrous and non-ferrous metal, stabilised and separated into fraction sizes of IBA prior to the export from site of the processed IBA and metals for re-use.
AIR-COOLED CONDENSERS
After exiting the turbine, the steam is cooled and condensed back into water through air condensers. This recovered water is treated and reused in the boilers to produce more steam.
EMISSION CONTROL
The gases from the furnace are subject to a rigorous cleaning process involving urea as selective non-catalytic reduction (SNCR), lime and active carbon injections. This removes oxides of nitrogen, acidic gases, dioxins, and heavy metals from the gas stream.
AIR POLLUTION CONTROL RESIDUE (APCR)
The cleaned gas passes through fine-fabric bag filters to remove solid particles before it is emitted through the stack. The resultant APCR residue, or fly-ash, contains particles from the incineration process, lime used in the flue gas treatment, salts and carbon dust. It is stored in a sealed silo until it is tankered away for recycling.
EMISSIONS MONITORING
As they pass through the stack, the residual flue gases from the process are continuously monitored before release. This data is relayed automatically to the control room.
29/03/2019 [7 of 19]
Table 2: Plant key parameters
Plant size, including number of lines
269,000 t/yr
Two lines
Annual waste throughputs Mixed Municipal Waste
Commercial and Trade Waste
Not to exceed a combined total of 269,000t/yr
Total plant operational hours in the year
Operating hours:
Line 1 – 7834 h
Line 2 – 7956 h
Residues produced Bottom ash APCR Metals Other waste
Amount of each residue, including metals (where appropriate) recycled/land filled
62,881.86 t 6,508.28 t 9,752 t 0 t
Electricity Produced: 181,837.50 MWh
Exported: 161,189.18 MWh
Parasitic load: 20,648.32 MWh
Table 3: Annual waste throughput
Waste types EWC code Tonnes
Mixed Municipal Waste 20 03 01 231,780
Other 20 03 03
19 12 12
18 01 04
1,285
30,757
2,345
29/03/2019 [8 of 19]
3. PERMIT VARIATION
The current Permit WP3438HZ/V006 was issued in May 2017. No permit variation applications were made during 2018.
4. SUMMARY OF PLANT MONITORING
Table 4: Emission limits to air and monitoring during normal operation
A1 & A2
Particulate matter
30 mg/m3 (½-hr average) Continuous measurement
A1 & A2 10 mg/m3 (Daily average) Continuous measurement
A1 & A2
Total Organic Carbon (TOC)
20 mg/m3 (½-hr average) Continuous measurement
A1 & A2 10 mg/m3 (Daily average) Continuous measurement
A1 & A2
Hydrogen chloride
60 mg/m3 (½-hr average) Continuous measurement
A1 & A2 10 mg/m3 (Daily average) Continuous measurement
A1 & A2 Hydrogen fluoride 2 mg/m3 (Periodic over min 1-hr period) Bi-annual
A1 & A2
Carbon monoxide
150 mg/m3 (95% of 10-minute averages in any 24-hr period)
Continuous measurement
A1 & A2 50 mg/m3 (Daily average) Continuous measurement
A1 & A2
Sulphur dioxide
200 mg/m3 (½-hr average) Continuous measurement
A1 & A2 50 mg/m3 (Daily average) Continuous measurement
A1 & A2
Oxides of nitrogen (NO & NO2
expressed as NO2)
400 mg/m3 (½-hr average) Continuous measurement
A1 & A2 200 mg/m3 (Daily average) Continuous measurement
A1 & A2 Cadmium & thallium and their compounds (total) 0.05 mg/m3 (periodic over min 30
minute, max 8 hr period)
Bi-annual
A1 & A2 Mercury & its compounds Bi-annual
A1 & A2 Sb, As, Pb, Cr, Co, Cu, Mn, Ni and V & their compounds (total)
0.5 mg/m3 (periodic over min 30 minute, max 8 hr period)
Bi-annual
A1 & A2 Dioxins / furans (I-TEQ)
0.1 ng/m3 (periodic over min 6 hr, max 8 hr period)
Bi-annual
29/03/2019 [9 of 19]
Table 5: Annual mass emissions of monitored pollutants
Pollutant Reporting
Threshold
Line 1 Line 2 Notifiable releases
Carbon Dioxide CO2 10,000,000kg 263,990,370 kg Appendix 2
Ammonia NH3 10,000kg brt brt
Arsenic As 20kg brt brt
Cadmium Cd 10kg brt brt
Chromium Cr 100kg brt brt
Copper Cu 100kg brt brt
Lead Pb 200kg brt brt
Mercury Hg 10kg brt brt
Nickel Ni 50kg brt brt
Chlorine & inorganic chlorine compounds – as HCL 10,000kg brt brt
Dioxins & furans (PCDDs/PCDFs) as I-TEQ 0.0001 g brt brt
Dioxins & furans (PCDDs/PCDFs) as WHO-TEQ 0.0001kg brt brt
Fluorine & inorganic fluorine compounds – as HF 5,000kg brt brt
Nitrogen oxides (NO and NO2) as NO2 100,000kg brt brt
Nitrous oxide N2O 10,000kg brt brt
Non-methane VOCs 100,000kg brt brt
Particulate matter 50,000kg brt brt
Polychlorinated biphenyls (PCBs) 0.0001kg brt brt
Sulphur oxides (SO2 and SO3) as SO2 150,000kg brt brt
Carbon monoxide CO 500,000Kg brt brt
Naphthalene 100Kg brt brt
Note: (Data was taken from Pollution Inventory reporting Form); *below reporting threshold
29/03/2019 [10 of 19]
5. SUMMARY OF PLANT COMPLIANCE
Summary of Breaches Reported During 2018
Date of Part A Line 1 or 2 Parameter(s) Date of Part B
01/01/2018 Line 2 TOC & SO2 08/01/2018
28/01/2018 Line 2 TOC 09/02/2018
26/03/2018 Line 2 TOC 28/03/2018
02/04/2018 Line 1 TOC 03/04/2018
09/04/2018 Line 1 TOC 21/05/2018
13/04/2018 Line 1 TOC 21/05/2018
30/04/2018 Line 1 Heavy metals -
08/05/2018 Line 2 NOx daily 17/05/2018
17/06/2018 Line 1 NOx 1/2 hour 05/07/2018
27/07/2018 Line 2 HCl 1/2 hour 28/09/2018*
21/10/2018 Line 2 2 x TOC 1/2 hour 18/01/2019
30/10/2018 Line 2 HCl 1/2 hour, SO2 1/2
hour, HCl daily 18/01/2019
Note: * Resubmitted 18/01/2018
29/03/2019 [11 of 19]
6. SUMMARY OF PLANT IMPROVEMENTS
Table 7: Plant improvements/Changes
Ref Improvement/change Status
PI1 Sootblower trial – an inspection of the final ECO was carried out during the September outage. Following a 6 month trial with no cleaning equipment in place, no hard build ups were found, most of the ash being soft and easy to remove. The shutdown cleaning method for the final ECO is still under discussion. The cleaning method used during Sep 17 (manual rodding) led to early fouling due to compacted residues and inspections in October revealed that a third of the flue gas path was blocked. A specific grit blasting method with a bespoke nozzle and different grit will be trialled during the planned shutdown in April 2018. This method has successfully been trialled at Wilton. A test with Shock Pulse Generators was initially considered in order to try different online cleaning methods to replace the current rake sootblowers. However, the brittle nature of the final ECO cast iron fins does not allow for this method. Clyde-Bergemann rake sootblowers were installed at Wilton and they are experiencing similar problems. There is no current intention to replace the Comeco rake sootblowers with another cleaning equipment. The current rake sootblowers will be removed during the April 2018 shut down.
Jan 2019 Update
Final Economiser – Comeco sootblowers removed due to unreliability and causing increasing corrosion of the final economiser. Final economiser inspected in Nov 18. Multiple leaks found. Leaks repaired and decision made to replace final economisers in May 2019.
Ongoing
PI2 Carbon change - We are looking at changing our carbon supplier from Cabot Norit GL50 to CPL Carbon Link Filtracarb FGT+. There is no discernible difference between the two products. The benefits to us from using CPL Carbon Link are the following:
- British supplier – reducing travel miles - Explosibility data has been provided which has been analysed and reduces our risk
through DSEAR and explosive atmospheres This is the same product that is used at our sister site at Wilton (Teesside) and they have the same flue gas treatment technology provider as ourselves and it is a recommended product by them.
Ongoing
PI3 Alternative fuel - an alternative fuel for the auxiliary burner was briefly trialled at Suffolk EfW during start-up following the September 2017 planned shutdown. This alternative fuel had previously been successfully trialled at other Suez EfW plants. Due to some problems with the fuel truck supply line first and with the start-up process later, the test was not fully completed. For this reason, a new trial has been scheduled for the next planned shutdown in April 2018. If successful, the permanent implementation of the new fuel will be assessed. This will lead to further modifications on the fuel delivery and storage systems. The modifications will be controlled via the company’s management of change procedure which will include the pertinent environment risk assessment. The EA will be notified in writing at least 14 days prior to the change being implemented.
Jan 2019 Update
Minor modifications required to fuel skid in May 2019 with the aspiration to accept alternative fuel in 2019.
Ongoing
29/03/2019 [12 of 19]
PI4 Bunker Repair - Consideration to carry out the bunker repair is now under discussion in alignment with the superheater replacement in April 2018. SUEZ are currently in discussion with Suffolk County Council and other waste management contractors on how to minimise any impact on the waste delivery partnership and traffic movements. Alternative solutions to waste treatment are currently being investigated.
Complete
PI5 Water Balance – Water balance on site had been an issue since plant handover. Project identified main water sources as passing valves and blocked pipework. A separate valve project focusing on upgrading isolation valves had a dramatic positive effect on the water balance. The blocked pipework was replaced in January 2019.
Complete
PI6 TOCs- A issue with frequent TOC exceedences was attributed to self-feeding of the waste onto the grate. Modification of the ‘shark fins’ designed to hold the waste resulted in stopping TOC issues related to self-feeding. Shark fins checked at every shutdown to prevent re-occurrence.
Complete
8. ENERGY EFFICENCY UPDATE
The SUEZ and Suffolk County Council Partnership continues to explore the potential for off takers of heat.
Following the start of the construction of the Sterling UK Greenhouse Project in 2017 the partnership has
been back in contact with Sterling UK to explore any opportunities. SUEZ and Suffolk County Council
partnership have also opened discussions with the property developer of St. James Business Park relating to
providing services of both heat and power.
9. FURTHER INFORMATION
Further information available at: http://www.suffolkefw.co.uk/
29/03/2019 [13 of 19]
APPENDIX 1. 2018 AIR EMISSIONS GRAPHS
Line 1 Particulate Matter
Line 1 Total Organic Carbon (TOC)
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
1/2 hourly ELV 30 30 30 30 30 30 30 30 30 30 30 30
Monthly 1/2 hourly mean 1.9 1.7 1.8 1.8 3.0 3.8 3.9 3.8 3.9 3.1 3.2 2.4
Monthly 1/2 hourly
maximum11.9 8.9 7.2 3.4 11.7 4.7 6.0 5.1 4.8 10.2 4.8 3.4
Daily ELV 10 10 10 10 10 10 10 10 10 10 10 10
Monthly daily mean 1.9 1.7 1.8 1.8 3.0 3.8 3.9 3.8 3.9 3.1 3.2 2.4
Monthly daily maximum 5.4 5.6 3.7 2.3 6 4.2 4.3 4.1 4.1 5.5 3.7 2.6
0
5
10
15
20
25
30
35
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
1/2 hourly ELV 20 20 20 20 20 20 20 20 20 20 20 20
Monthly 1/2 hourly mean 0.3 0.3 0.3 0.6 0.3 0.7 0.8 0.8 0.7 0.6 0.7 0.6
Monthly 1/2 hourly
maximum18.5 17.5 16 54.7 1.1 1.6 13.3 5.1 3.6 8 3.4 1.2
Daily ELV 10 10 10 10 10 10 10 10 10 10 10 10
Monthly daily mean 0.3 0.3 0.3 0.6 0.3 0.7 0.8 0.8 0.7 0.6 0.7 0.6
Monthly daily maximum 0.9 0.9 0.7 2.5 0.8 0.9 1.1 0.9 0.9 0.9 0.9 0.8
0
10
20
30
40
50
60
29/03/2019 [14 of 19]
Line 1 Hydrogen Chloride (HCl)
Line 1 Carbon Monoxide (CO)
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
1/2 hourly ELV 60 60 60 60 60 60 60 60 60 60 60 60
Monthly 1/2 hourly mean 5.2 4.1 4.5 5.2 4.3 5.4 4.7 7.2 7.5 3.4 4.8 6.0
Montly 1/2 hourly maximum 27.1 10.7 31.2 19 28.5 18.4 33.7 33.7 26.4 22.2 10.5 29.1
Daily ELV 10 10 10 10 10 10 10 10 10 10 10 10
Monthly daily mean 5.2 4.1 4.5 5.2 4.3 5.4 4.7 7.2 7.5 3.4 4.8 6.0
Monthly daily maximum 7.7 6.0 7.4 7.3 7.3 8.3 8.8 8.5 8.6 6.9 6.1 9.2
0
10
20
30
40
50
60
70
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
10 minute ELV 150 150 150 150 150 150 150 150 150 150 150 150
Monthly 10 minute mean 3.9 4.1 3.6 12.2 3.3 2.7 2.8 2.0 2.2 1.9 2.5 1.6
Monthly 10 minute
maximum398.5 544.6 774.3 1461 143.4 397.1 421 317 386.5 348.5 309 244.8
Daily ELV 50 50 50 50 50 50 50 50 50 50 50 50
Monthly daily mean 3.9 4.1 3.6 12.2 3.3 2.7 2.8 2.0 2.2 1.9 2.5 1.6
Monthly daily maximum 12.2 8.5 9.5 47.1 9.9 6.4 7.9 4.4 4.0 6.2 5.5 3.5
0
200
400
600
800
1000
1200
1400
1600
29/03/2019 [15 of 19]
Line 1 Sulphur Dioxide (SO2)
Line 1 Oxides of Nitrogen (NOx)
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
1/2 hourly ELV 200 200 200 200 200 200 200 200 200 200 200 200
Monthly 1/2 hourly mean 37.6 40.9 32.3 32.9 16.8 35.4 40.6 38.6 40.0 29.5 39.0 20.8
Montly 1/2 hourly maximum 148 129.8 139.1 128.4 100.5 169.5 152 129.6 144.2 145 117.9 141.5
Daily ELV 50 50 50 50 50 50 50 50 50 50 50 50
Monthly daily mean 37.6 40.9 32.3 32.9 16.8 35.4 40.6 38.6 40.0 29.5 39.0 20.8
Monthly daily maximum 46.7 45.6 45.4 44.2 32.5 47.4 47.4 46.4 46.5 45.8 47.4 40.0
0
50
100
150
200
250
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
1/2 hourly ELV 400 400 400 400 400 400 400 400 400 400 400 400
Monthly 1/2 hourly mean 179.9 179.8 180.4 178.7 183.3 183.2 184.2 183.2 175.6 141.8 183 181.8
Montly 1/2 hourly maximum 202.6 282 345.3 297.8 345.5 406.4 391.7 357.8 374.5 365.2 328.4 304.5
Daily ELV 200 200 200 200 200 200 200 200 200 200 200 200
Monthly daily mean 179.9 179.8 180.4 178.7 183.3 183.2 184.2 183.2 175.6 141.8 183 181.8
Monthly daily maximum 189.1 180.9 193.7 182.0 193.9 193.5 194.7 210.0 189.7 189.3 189.1 195.3
0
50
100
150
200
250
300
350
400
450
29/03/2019 [16 of 19]
Line 2 Particulate Matter
Line 2 Total Organic Carbon (TOC)
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
1/2 hourly ELV 30 30 30 30 30 30 30 30 30 30 30 30
Monthly 1/2 hourly mean 2.0 1.8 1.9 0.8 2.0 1.1 0.2 0.2 0.2 0.2 0.3 0.2
Montly 1/2 hourly maximum 5.3 2.4 2.4 2.5 3.2 2.6 0.3 0.4 0.3 0.4 0.4 0.3
Daily ELV 10 10 10 10 10 10 10 10 10 10 10 10
Monthly daily mean 2.0 1.8 1.9 0.8 2.0 1.1 0.2 0.2 0.2 0.2 0.3 0.2
Monthly daily maximum 3.8 2.0 2.0 2.1 2.5 2.3 0.3 0.3 0.3 0.3 0.3 0.3
0
5
10
15
20
25
30
35
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
1/2 hourly ELV 20 20 20 20 20 20 20 20 20 20 20 20
Monthly 1/2 hourly mean 0.5 0.4 0.4 0.2 0.4 0.3 0.3 0.3 0.3 0.4 0.3 0.3
Montly 1/2 hourly maximum 29.1 17.9 34.3 14.6 6.2 1.3 4.7 10.1 1.6 69.5 3.6 17.9
Daily ELV 10 10 10 10 10 10 10 10 10 10 10 10
Monthly daily mean 0.5 0.4 0.4 0.2 0.4 0.3 0.3 0.3 0.3 0.4 0.3 0.3
Monthly daily maximum 1.9 0.9 1.9 0.8 1.4 0.5 0.4 0.5 0.4 2.5 0.4 0.8
0
10
20
30
40
50
60
70
80
29/03/2019 [17 of 19]
Line 2 Hydrogen Chloride (HCl)
Line 2 Carbon Monoxide (CO)
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
1/2 hourly ELV 60 60 60 60 60 60 60 60 60 60 60 60
Monthly 1/2 hourly mean 4.3 3.2 4.3 2.7 4.5 6.9 7.4 6.5 6.5 4.2 7.7 7.1
Montly 1/2 hourly maximum 10.6 9.3 21.6 17.4 17.5 26.1 70.3 21.9 48.1 178.5 30.0 35.1
Daily ELV 10 10 10 10 10 10 10 10 10 10 10 10
Monthly daily mean 4.3 3.2 4.3 2.7 4.5 6.9 7.4 6.5 6.5 4.2 7.7 7.1
Monthly daily maximum 6.3 5.2 7.6 8.2 7.8 8.9 8.9 9.2 9.4 10.7 9.0 9.0
0
20
40
60
80
100
120
140
160
180
200
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
10 minute ELV 150 150 150 150 150 150 150 150 150 150 150 150
Monthly 10 minute mean 4.2 4.2 4.1 2.0 4.2 0.7 1.3 0.6 0.6 0.5 0.9 0.3
Monthly 10 minute
maximum542.7 364.8 389.3 516.7 990.6 323 324.2 390.2 344.2 357 312.9 226.2
Daily ELV 50 50 50 50 50 50 50 50 50 50 50 50
Monthly daily mean 4.2 4.2 4.1 2 4.2 0.7 1.3 0.6 0.6 0.5 0.9 0.3
Monthly daily maximum 3.6 9.6 7.9 9.7 32.0 4.3 4.3 4.3 3.7 4.8 4.7 2.9
0
200
400
600
800
1000
1200
29/03/2019 [18 of 19]
Line 2 Sulphur Dioxide (SO2)
Line 2 Oxides of Nitrogen (NOx)
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
1/2 hourly ELV 200 200 200 200 200 200 200 200 200 200 200 200
Monthly 1/2 hourly mean 43.2 42.5 40.5 15 18.8 12.4 13.1 5.7 7.4 5.9 17.9 13.8
Montly 1/2 hourly maximum 255 177.5 176.4 96.8 144.7 92.5 106.5 62.5 103.2 210 117 134.1
Daily ELV 50 50 50 50 50 50 50 50 50 50 50 50
Monthly daily mean 43.2 42.5 40.5 15 18.8 12.4 13.1 5.7 7.4 5.9 17.9 13.8
Monthly daily maximum 47.8 46.8 45.5 45.4 45.4 18.5 19.0 13.1 16.0 13.7 28.8 25.3
0
50
100
150
200
250
300
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
1/2 hourly ELV 400 400 400 400 400 400 400 400 400 400 400 400
Monthly 1/2 hourly mean 180.3 174.1 182.6 78.3 164.5 180.6 180.8 181.1 174.4 139.1 179.7 180.7
Montly 1/2 hourly maximum 334 360.6 348.5 229.8 363.5 288 309.7 305.2 281.5 313.8 313.6 340.5
Daily ELV 200 200 200 200 200 200 200 200 200 200 200 200
Monthly daily mean 180.3 174.1 182.6 78.3 164.5 180.6 180.8 181.1 174.4 139.1 179.7 180.7
Monthly daily maximum 187.0 188.6 194.2 187.1 212.8 185.1 185.5 192.5 185.0 186.5 182.3 193.9
0
50
100
150
200
250
300
350
400
450
Permit Reference Number : WP3438HZ Operator : SUEZ Recycling and Recovery UK Facility : SUEZ Suffolk Energy from Waste Facility Form Number : E1 / 01/09/11 Reporting of Energy Usage/Export for the year 2018 Energy Source
Energy Usage Unit
Contained Energy (MWh)
Electricity produced
181,837.50 MWh 181,837.50
Electricity imported 731.01 MWh 731.01
Electricity Exported 161,189.18 MWh 161,189.18 Natural Gas 0 tonnes 0 Gas Oil 412 tonnes - Recovered Fuel Oil 0 tonnes 0 Steam/hot water exported
0 MWh 0
Operator’s comments : This report includes data from 1st January 2018 to 31st December 2018, the period under permit conditions.
Signed …………… …………………………………. Date…28/01/18…………………….. (authorised to sign as representative of SUEZ Recycling and Recovery UK)
Permit Number: WP3438HZ Operator: SUEZ Recycling and Recovery UK Facility: SUEZ Suffolk Energy from Waste Facility Form Number: R1 / 01/09/11 Reporting of Waste Disposal and Recovery for the year 2018 Waste Description
Disposal Recovery Route Tonnes Tonnes
1) Hazardous Wastes APC Residues Landfill
Reprocessing 6508.28 0.00
IBA which is classified as hazardous waste
N/A 0.00
Total hazardous waste 6508.28 0.00 2) Non-Hazardous Wastes
IBA Reprocessing 62881.86 0.00 Other non-hazardous wastes Metals Recycling 9752 0.00 Total non-hazardous waste 72663.86 0.00 TOTAL WASTE - 79142.14 0.00
Operator’s comments : This report includes data from 1st January 2018 to 31st December 2018, the period under permit conditions.
Signed …………Emma Woollen…………………………………………………. Date……25/01/18………………….. (authorised to sign as representative of SUEZ Recycling and Recovery UK)
Permit Number : WP3438HZ Operator : SUEZ Recycling and Recovery UK Facility : SUEZ Suffolk Energy from Waste Facility Form Number : WU/RM1 / 01/09/11
Reporting of Water and Other Raw Material Usage for the year 2018 Raw Material Usage Unit Specific Usage Unit Mains water 96,192 m3 0.36 m3/t
Site borehole N/A m3 N/A m3/t River abstraction N/A m3 N/A m3/t Total water usage 96,192 m3 0.36 m3/t Ammonia (or Urea) 548.58 Tonnes 2.08 kg/t Activated carbon (or coke) 81.26 Tonnes 0.31 kg/t
Lime/hydrated lime or sodium bicarbonate
2,389.80 Tonnes 9.05 kg/t
Operator’s comments : This report includes data from 1st January 2018 to 31st December 2018, the period under permit conditions.
Signed …………… ………………………………. Date………28/01/19…….. (authorised to sign as representative of SUEZ Recycling and Recovery UK)
Permit Reference Number: WP3438HZ Operator: SUEZ Recycling and Recovery UK Facility: SUEZ Suffolk Energy from Waste Facility
Schedule 4 – Reporting of performance data Data required to be recorded and reported by Condition 4.2.2. The data should be assessed as the frequency given and reported annually to the Agency. Permit conditions – 1st January 2018 to 31st December 2018 Table S4.2: Annual Production/Treatment Total Municipal Waste Incinerated – tonnes
263990.37 Total Commercial and Industrial Waste Incinerated – tonnes
Electrical energy produced – MWhrs 181837.50
Thermal energy produced e.g. steam - KWhrs N/A
Electrical energy exported – KWhrs 161189.18
Electrical energy used on installation – KWhrs 20648.32
Waste heat utilised by the installation - KWhrs N/A
Performance Parameters assessed quarterly 1st January 2018 to 31st December 2018 Table S4.3: Performance parameters
Parameter Frequency of assessment
Result Performance Indicator
Electrical energy exported Quarterly
607.90 KWhrs/tonne of waste incinerated (dry basis)
Electrical energy imported Quarterly
2.77 KWhrs/tonne of waste incinerated (dry basis)
Electrical energy used at the installation
Quarterly 78.22
KWhrs/tonne of waste incinerated (dry basis)
Fuel oil consumption Quarterly 1.31 Kgs/tonne of waste incinerated (dry basis)
Mass of Bottom Ash produced Quarterly 238.20 Kgs/tonne of waste incinerated (dry basis)
Mass of APC residues produced Quarterly 24.65 Kgs/tonne of waste incinerated (dry basis)
Urea Consumption Quarterly 2.08 Kgs/tonne of waste incinerated (dry basis)
Activated Carbon consumption Quarterly 0.31 Kgs/tonne of waste incinerated (dry basis)
Lime consumption Quarterly 9.05 Kgs/tonne of waste incinerated (dry basis)
Water consumption Quarterly 364.38 Kgs/tonne of waste incinerated (dry basis)
Periods of WID abnormal operation Quarterly
Line 1: 0 Line 2: 2 occasions (1.5 hours total)
No. of occasions and cumulative hours for current calendar year for each line.
Signed ……… …………………………. Date………28/03/18………….. (authorised to sign as representative of Operator)