summary of the november 15, 1999, meeting regarding ... · nuclear regulatory commission...
TRANSCRIPT
tA UNITED STATES NUCLEAR REGULATORY COMMISSION
WASHINGTON, D.C. 20555-0001
December 2, 1999
LICENSEE: Baltimore Gas and Electric Company
FACILITY: Calvert Cliffs Nuclear Power Plant, Unit Nos. 1 and 2
SUBJECT: SUMMARY OF THE NOVEMBER 15, 1999, MEETING REGARDING CALVERT CLIFFS NUCLEAR POWER PLANT, UNIT NOS. 1 AND 2 RE: STEAM GENERATOR REPLACEMENT PROJECT (TAC NOS. MA6819 AND MA6820)
On November 15, 1999, the Nuclear Regulatory Commission (NRC), and Baltimore Gas and Electric Company (BGE/licensee) and their contractor, Steam Generator Team (SGT), held a meeting in One White Flint North, Rockville, Maryland to discuss the Calvert Cliffs Nuclear Power Plant, Unit Nos. 1 and 2 steam generator (SG) replacement project. Enclosure 1 is a list of attendees. Enclosure 2 is a copy of the viewgraphs distributed at the meeting.
The purpose of the meeting was for BGE to present the status of their Calvert Cliffs Nuclear Power Plant, Unit Nos. 1 and 2 SG replacement project.
BGE presented the fabrication status, safety analysis status and replacement activities. The staff inquired about the fabrication method and BGE and the NRC staff discussed the licensing issues and methodology relating to the safety analysis.
BGE stated that a new containment pressure/temperature calculation for the postulated main steam line break accident has been done to support SG replacement. The new analysis was done using the RELAP MOD 2 and CONTEMPT 23 computer codes. BGE stated that no unreviewed safety question was identified. The peak pressure and temperatures are below the design values. The loss-of-coolant accident analysis for containment pressure and temperature, which remains unchanged, is bounding.
The staff suggested that in the next meeting regarding SG replacement BGE make a brief presentation on the results of the licensee's evaluation of Chapter 15 safety analyses in a tabular format. This presentation should address each of the events which are either not effected by the replacement SG or they are slightly effected but reanalyses are not needed.
R, COP
December 2, 1999
-2
The replacement SGs are scheduled to be installed in Unit 1 and 2 in year 2002 and 2003, respectively. BGE plans to update the staff on its SG replacement in future meetings.
Original signed by:
Alexander W. Dromerick, Sr. Project Manager, Section 1 Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation
Docket Nos. 50-317 and 50-318
Enclosures: 1. List of Attendees 2. Meeting Handouts
cc w/encls: See next page
DISTRIBUTION:
HARD COPY (w/encls.) File Center PUBLIC PDI-1 R/F A. Dromerick OGC ACRS
E-MAIL (w/encl. 1). J. ZwolinskVS. Black E. Adensam S. Peterson S. Uttle A. Dromenck D. Jeng C. Beardslee M. Hartzman R. Lobel C. Liang
DOCUMENT NAME: G:XPDl-1\CC1-2XlVts111599.wpd
To receive a copy of this document. indicate in the box: "C" - Copy without attachment/enclosure "E" - Copy with attachment/enclosure "N" - No copy
OFFICE PD1 -l/Pm PDI-l/M PDI-1/SC(A) NAME QADrý2r'?& :Yc iSLtt1o - VNerses -I DATE 12/ /99 12/& /99 12I7I99. 2/ /99
OFFICIAL RECORD COPY
December 2, 1999
-2
The replacement SGs are scheduled to be installed in Unit 1 and 2 in year 2002 and 2003, respectively. BGE plans to update the staff on its SG replacement in future meetings.
Original signed by:
Alexander W. Dromerick, Sr. Project Manager, Section 1 Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation
Docket Nos. 50-317 and 50-318
Enclosures: 1. List of Attendees 2. Meeting Handouts
cc w/encls: See next page
DISTRIBUTION:
HARD COPY (w/encls.) File Center PUBLIC PDI-1 R/F A. Dromerick OGC ACRS
E-MAIL (w/encl. 1) J. Zwolinski/S. Black E. Adensam S. Peterson S. Little A. Dromerick D. Jeng C. Beardslee M. Hartzman R. Lobel C. Liang
DOCUMENT NAME: GA:\PDI-1\CC11-2VMts111 599.wpd
To receive a copy of this document, Indicate in the box: "C" - Copy without attachment/enclosure 'E" - Copy with
attachment/enclosure "N" - No copy
OFFICE POI-1!PM 4 PDI-1/Lr( I PDI-1/SC(A)7 NAME AD~r !'r k.'•c SLittl•l!" VNerses . , . oL
DATE 12/ •/99 12/-.1/99 12/ /99 ' ,...- 2/ /99
OFFICIAL RECORD COPY
-2
The replacement SGs are scheduled to be installed in Unit 1 and 2 in year 2002 and 2003, respectively. BGE plans to update the staff on its SG replacement in future meetings.
Alexander W. Dromerick, Sr. Project Manager, Section 1 Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation
Docket Nos. 50-317 and 50-318
Enclosures: 1. List of Attendees 2. Meeting Handouts
cc w/encls: See next page
Calvert Cliffs Nuclear Power Plant Unit Nos. 1 and 2
President Calvert County Board of
Commissioners 175 Main Street Prince Frederick, MD 20678
James P. Bennett, Esquire Counsel ' Baltimore Gas and Electric Company P.O. Box 1475 Baltimore, MD 21203
Jay E. Silberg, Esquire Shaw, Pittman, Potts, and Trowbridge 2300 N Street, NW Washington, DC 20037
Mr. Bruce S. Montgomery, Director NRM Calvert Cliffs Nuclear Power Plant 1650 Calvert Cliffs Parkway Lusby, MD 20657-4702
Resident Inspector U.S. Nuclear Regulatory Commission P.O. Box 287 St. Leonard, MD 20685
Mr. Richard I. McLean, Manager Nuclear Programs
Power Plant Research Program Maryland Dept. of Natural Resources Tawes State Office Building, B3 Annapolis, MD 21401
Regional Administrator, Region F U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406
Mr. Joseph H. Walter, Chief Engineer Public Service Commission of
Maryland Engineering Division 6 St. Paul Centre Baltimore, MD 21202-6806
Kristen A. Burger, Esquire Maryland People's Counsel 6 St. Paul Centre Suite 2102 Baltimore, MD 21202-1631
Patricia T. Birnie, Esquire Co-Director Maryland Safe Energy Coalition P.O. Box 33111 Baltimore, MD 21218
Mr. Loren F. Donatell NRC Technical Training Center 5700 Brainerd Road Chattanooga, TN 37411-4017
Mr. Charles H. Cruse Vice President, Nuclear Energy Baltimore Gas & Electric Company Calvert Cliffs Nuclear Power Plant 1650 Calvert Cliffs Parkway Lusby, MD 20657
LIST OF ATTENDEES
BALTIMORE GAS AND ELECTRIC COMPANY
CALVERT CLIFFS NUCLEAR POWER PLANT, UNIT NOS. 1 AND 2
NOVEMBER 15, 1999
NAME Alexander Dromerick Scott Stewart Getachero Tesfaye Kenneth Romney Alan Thornton Tom Kenerth Kevin Connell Mary Beth Baker Mark Ceraldi Sheri Peterson David C. Jeng Cheryl Beardslee Mark Hartzman Richard Lobel Chu-yu Liang Christine Cave
ORGANIZATION NRR/DLPM Region I BGE BGE BGE BGE SGT FTI SGT NRR/DLPM NRR/EMEB NRR/EMCB NRR/EMCB NRR/SPLB NRR/SRXB McGrew-Hill
Enclosure 1
CAL VERT CLIFFS NUCLEAR POWER PLANT UNITS 1 & 2 STEAM GENERATOR REPLACEMENT
REPLACEMENT STEAM GENERA TOR SAFETY EVALUATION REVIEW AND
PROJECT STATUS
PRESENTA TION TO THE NRC
NOVEMBER 15, 1999
Baltimore Gas and Electric Company
Fnr1nr iirn
Calvedt Cliffs Nuclear Power Plant Steam Generator Replacement Project
Baltimore Gas and Electric Company Attendees
Name A. R. Thornton K. M. Romney G. Tesfaye ---E. S. Broczkows K. J. Connell ---M. D. Ceraldi -M. B. Baker -----
T. L. Konerth----.
ki ----------mmm
ki ----------......-------
NRC Presentation November 15, 1999, Slide 2
kI. P
Title BGE Project Manager BGE Project Engineer BGE Senior Licensing Engineer BGE Senior Mechanical Engineer SGT RSG Engineering Manager SGT Lead Licensing Engineer FTI Senior Licensing Engineer BGE Senior Engineer
Calvert Cliffs Nuclear Power Plant Steam Generator Replacement Project
-. 0'
NHU P-resentation November 15, 1999, ~Slide 3
I-
Meeting Objectives
*** Present to the NRC staff an Overview of Replacement SG Safety Evaluation
S:-Update SG Fabrication Status
. °•A A-
Calvert Cliffs Nuclear Power Plant Steam Generator Replacement Project
N Agenda is •-en
** Introduction o** RSG Safety Evaluation o** NRC Submittals
oe* Fabrication Status
*.*Open Discussion *+*Closing Remarks
A. R. Thornton
K. J. Connell
G. Tesfaye
K. M. Romney
All Attendees
A. R. Thornton
NRC Presentation November 15, 1999, Slide 4
a
Calvert Cliffs Nuclear Power Plant Steam Generator Replacement Project
N,!p Functional Relationships
NRC Presentation November 15, 1999, Slide. 5
Calved Cliffs Nuclear Power Plant Steam Generator Replacement Project
"RSG Safety Evaluation Overview
"• Draft Licensing Report (complete)
"* Final Licensing Report
*. *RSG 50.59
**. Updated Licensing Report (Unit 1)
*. Updated Licensing Report (Unit 2)
NRC Presentation November 15, 1999, Slide 6
July 1999
May 2000
Jan 2001
April 2002
April 2003
'I'A
AP AN
Calvert Cliffs Nuclear Power Plant Steam Generator Replacement Project
IOCFR50.59 Scope
NRC Presentation November 15, 1999, Slide 7
b ra
Calvert Cliffs Nuclear Power Plant Steam Generator Replacement Project
Review Process
o. Review each accident and identify: > the acceptance criteria
> the critical parameters that affect the approach to the acceptance criteria
o:o Compare the OSG and RSG characteristics
o* Could use of the RSG adversely affect the approach to an acceptance criterion?
> No.. .UFSAR remains bounding > Yes.. .Additional evaluation required
*o Are all acceptance criteria met? > Yes.. .Document evaluation in UFSAR
> No...USQ ** All documents reviewed I approved by SGT & BGE
NRC Presentation November 15, 1999, Slide 8
N
b ,e
Calvert Cliffs Nuclear Power Plant Steam Generator Replacement Project
Steam Generator Comparison y Original Vs Replacement
o*. RSG Design >Tubing will be Alloy 690 with reduced wall
thickness
>UA within 4% of current SG >RCS volume decrease of 26 ft3 (0.25%) >Secondary-side inventory within 2% at
normal operating level
>Small weight and center of gravity changes
NRC Presentation November 15, 1999, Slide 9
b • ,fl •m
Calvert Cliffs Nuclear Power Plant Steam Generator Replacement Project
N?,,..,Steam Generator Comparison •/ Original Vs. Replacement
•o RSG Design >RCS operating temperatures unchanged >RSG has 1.9 ft2 integral flow restrictor >RCS flow resistance will decrease slightly Alncrease secondary side design pressure
to be equal to the steam piping
HGENRC Presentation November 15, 1999, Slide 10NRC
Presentation
November
15, 1999, Slide
10
i *l ,, im
Calvert Cliffs Nuclear Power Plant Steam Generator Replacement Project
Comparisons of SGRPs
* Millstone - 2
l3 St. Lucie
E D. C. Cook- 2
l D. C. Cook- 1i
a Salem
D Ginna o '-oGuire/Catawba
I Byron/Braidwood
* Calvert Cliffs
-20.0% -10.0% 0.0% 10.0% 20.0% 30.0% 40.0%
% Change From Original
NRC Presentation November 15, 1999, Slide 11AMPAP:CAw
k ,e
Calvert Cliffs Nuclear Power Plant Steam Generator Replacement Project
Replacement Steam Generator Safety Analysis
**.Impact of RSG on Safety Analysis >Overall, RSG is very similar to current SG
>No significant impact on safety analysis
NRC Presentation November 15, 1999, Slide 12
Calvert Cliffs Nuclear Power Plant Steam Generator Replacement Project
",••Replacement Steam Generator New Analysis
**oMSLB Containment Response )Reanalyzed MSLB containment Response
>Current licensing basis is DEG break with 20% moisture carry-over
>New analysis incorporates integral flow restrictor (1.9ft2)
>No credit taken for moisture carry-over
NRC Presentation November 15, 1999, Slide 13
Calvert Cliffs Nuclear Power Plant Steam Generator Replacement Project
"Replacement Steam Generator New Analysis
**oMSLB Containment Response (cont.) >Methodologies have been approved for
PWR use
>Peak Pressures & Temperatures Below Design
>No USQ identified
NRC Presentation November 15, 1999, Slide 14
Calvert Cliffs Nuclear Power Plant Steam Generator Replacement Project
••Replacement Steam Generator New Analysis
*.** Loss of Electric Load
>Reanalyzed LOEL for peak secondary pressure response
AIncrease to the SG design pressure from 1000 psia to 1015 psia
>Secondary pressure upset limit is 110% of design pressure
>Peak secondary side pressure is below upset limit
>Not USQ
NRC Presentation November 15, 1999, Slide 15
9
Calvert Cliffs Nuclear Power Plant Steam Generator Replacement Project
- Activities Requiring NRC Review and Approval
:.*Technical Specification Revisions
o*oASME Code Relief Requests
**.No USQs are Anticipated
-**All Submittals will be made at least I year prior to replacement outage
NRC Presentation November 15, 1999, Slide 16
S9
Calvert Cliffs Nuclear Power Plant Steam Generator Replacement Project
Technical Specification Revision
o**SG Level References > Current SG levels are referenced with respect to
the feed ring elevation
> SG level set points are not expected to change relative to % span
>Since feed ring elevation is lower, editorial change is needed
o* SG Repair Options.
NRC Presentation November 15, 1999, Slide 17
Calvert Cliffs Nuclear Power Plant Steam Generator Replacement Project
,ASME Code Relief Requests
* :.Code Case N-20-4 ** *Code Case 2142-1
• **Code Case 2143-1*:*Other Code Cases as Required
NRC Presentation November 15, 1999, Slide 18
P
Calvert Cliffs Nuclear Power Plant Steam Generator Replacement Project
Fabrication Status
:**Steam Generators ,oTubing *.*Audits and Assessments
NRC Presentation November 15, 1999, Slide 19
Calvert Cliffs Nuclear Power Plant Steam Generator Replacement Project
RSG Fabrication Schedule
'qN3GE - Calvert Cliffs Replacement Steam Generators - FarticatOn Schedule Sumrbmary
Bgabcock & Wilcox Canada201•
82 0
y - 9 A
72 I
I,
NRC Presentation November 15, 1999, Slide 20
a
*
p
.. p P.4�a
I732
Calvert Cliffs Nuclear Power Plant Steam Generator Replacement Project
achining Divider Plate for RSG 3
NRC Presentation November 15, 1999, Slide 21
, ',
jr 4 JAMP &-
Calvert Cliffs Nuclear Power Plant Steam Generator Replacement Project
--Divider Plate Welded into RSG 2
NRC Presentation November 15, 1999, Slide 22
I D • *l
Calvert Cliffs Nuclear Power Plant Steam Generator Replacement Project
Machining of Cone Handholes and Inspection "Ports in RSG I
NRC Presentation November 15, 1999, Slide 23
, , . •
Calvert Cliffs Nuclear Power Plant Steam Generator Replacement Project
achining of Cone Handhole in RSG 1
NRC Presentation November 15, 1999, Slide 24
a0
a AP
p :4JI AP :CA,10
Calvert Cliffs Nuclear Power Plant Steam Generator Replacement Project
\.team Generator Base Support Pieces
NRC Presentation November 15, 1999, Slide 25
a p
Calvert Cliffs Nuclear Power Plant Steam Generator Replacement Project
"Lifting Lugs inside Secondary Cone
!I*1
NRC Presentation November 15, 1999, Slide 26
II *LJ
Calved Cliffs Nuclear Power Plant Steam Generator Replacement Project
4 Primary Head Loading in Seattle
NRC Presentation November 15, 1999, Slide 27
SI b
Calved Cliffs Nuclear Power Plant Steam Generator Replacement Project
mitomo Tube Manufacturing Process
L�J
.4
L NOT WRIOG- I
COLD ROLLIG TUES
NRC Presentation November 15, 1999, Slide 28
I e.�
I ,,,,EA ,,,• TRAMN I ,,, .USTL CODOWN, MYRSAI TEST" I="' FINAL '''brL'PI
AP
JAND -&
Calvert Cliffs Nuclear Power Plant Steam Generator Replacement Project
Audits and Assessments
o*. Non-Conformance Control - August 1999 > No findings, five recommendations, one observation
**ooNUPIC - QA Program - September 1999 (draft) > Two Findings
+** Procurement Control - November 1999 4.°2000 Preliminary Audit Plan:
> Vendor Control
> Process Control, Clean Room Activities, Foreign Material Control
> Detrimental Materials Control
NRC Presentation November 15, 1999, Slide 29
I U
Calvert Cliffs Nuclear Power Plant Steam Generator Replacement Project
ATBGE-NRC Meeting Schedule
*.*Project overview meeting (July 29,1998) o* SG Fabrication QA/QC review and project
status meeting (April 28, 1999) .** Replacement SG safety evaluation review
.meeting (November 15, 1999) o*o Pre-installation meeting Unit I (Spring 2002) *.*Post installation meeting Unit 1(Fall 2002) **oPre-installation meeting Unit 2 (Spring 2003) +. Post Installation meeting Unit 2 (Fall 2003) ***Other meetings as needed
NRC Presentation November 15, 1999, Slide 30
, y. , '