supplemental files for 'development and evaluation of induced ...m...development and evaluation...
TRANSCRIPT
Development and Evaluation of Induced Partial Saturation (IPS), Delivery Method and Its Implementation in Large Laboratory
Specimens and in the Fieldby
Fritz Rudolph P. Nababan
Research part of NEESR Project
“Induced Partial Saturation (IPS) Through Transport and Reactivity for Liquefaction Mitigation”
CMMI/NEESRGrant Number: CMMI-1134940
PI: Prof. Mishac Yegian Co-PI: Prof. Akram Alshawabkeh
Seda Gokyer, Ph.D., Hadi Kazemiroodsari (Ph.D. Candidate)1
Scope of Presentation:
1 – Introduction to Liquefaction and IPS Technique
2 – Development of IPS Delivery System
3 – Testing of the Developed Delivery System
4 – Large Scale Laboratory Testin Laminar Box at NEES@UB
5 – Field Test at Wildlife Liquefaction Array (WLA) site NEES@UCSB
6 – Summary and Conclusions
2
Scope of Presentation:
1 – Introduction to Liquefaction and IPS Technique
2 – Development of IPS Delivery System
3 – Testing of the Developed Delivery System
4 – Large Scale Laboratory Testin Laminar Box at NEES@UB
5 – Field Test at Wildlife Liquefaction Array (WLA) site NEES@UCSB
6 – Summary and Conclusions
3
1. Introduction to Liquefaction and IPS Technique
Induced Partial Saturation (IPS)
Building Response on Fully Saturated Liquefied Sand
Building Response on IPS Treated Sand
Contact stresses between sand particles, Excess pore water pressure, ∆u
Excess pore water pressure ratio, ru = ∆u/
u = '0 or ru = u/'0 = 1Soil becomes like liquid (liquefaction) during the earthquake, when
What is liquefaction?
4
in water
in water
(at the end of reaction)
( ideal conditions - 100% efficiency)
+1 2-Na CO .1.5H O 2Na + CO + 1.5H O2 3 2 2 3 2 21.5H O 1.5H O + O2 2 2 2
0.75
Hydrogen peroxide H2O2 is oxygen bubble source
1. IPS Technique
Gas Source: Sodium Percarbonate
1. IPS - DELIVERY SYSTEM AND EVALUATION OFLIQUEFACTION MITIGATION
BY FRITZ NABABAN
6
DELIVERY SYSTEM ANDLIQUEFACTION MITIGATION
1. IPS – MONITORING OF PARTIAL SATURATION
BY HADI KAZEMIROODSARI
7
GAS BUBBLE GENERATIONAND SYSTEM FOR MONITORING
OF PARTIAL SATURATION
1. IPS – SIMULATION OF PARTIAL SATURATION
BY SEDA GOKYER, PH.D.
8
NUMERICAL SIMULATION TOOLFOR
IPS DESIGN ANDIMPLEMENTATION
Scope of Presentation:
1 – Introduction to Liquefaction and IPS Technique
2 – Development of IPS Delivery System
3 – Testing of the Developed Delivery System
4 – Large Scale Laboratory Testin Laminar Box at NEES@UB
5 – Field Test at Wildlife Liquefaction Array (WLA) site NEES@UCSB
6 – Summary and Conclusions
9
Strainer
Strainer
Pump
Pump
2-Solution Preparation
Water Source
Water Tanks
4- Solution Injection
1- Powder Delivery
3- Solution Pumping
2. Development of IPS Delivery System
10
4 Major Components
2. The developed IPS delivery system
Powder bottle (5 gals)
Acrylic powder box
Benchtop power supplyMiniature DC gear motorPVC shaft
Auger bit, ∅0.75"
Elbow pipe
Chemical powder
Cross section of controlled rate of powder dispenser
Miniature DCgear motor box
DC Power cord
PVC shaft
Auger bit, ∅0.75"
Aluminum angel
View of powder box seen from the back of auger
11
Component 1: Powder Delivery
2. The developed IPS delivery system
Chemical powder (controlled by float switch)
Mixer motor and blade(Continuous operation)
Mixing barrel
Limiting upper water level
(Switch off)
Float switch
Clean water supply pump (controlled by float switch)Limiting lower
water level(Switch on)
Clear acrylic platform
Heading for pumping system
Figure 2-15 Schematic of automation of solution preparation12
Component 2: Automated Solution Preparation
2. The developed IPS delivery system
Pressuregauges
Pneumatic expansion tank
Flow meter
Pressure gauge
Pressure controller
Constant pressure pump with manifold with four branches (capacity 40 GPM)
Constant pressure pump with manifold with six branches (capacity 70 GPM)
Manifold
13
Component 3: Solution Pumping
h
Pump pressure
Pumping system
Injection tube
H
Saturated loose sand
Injection tip
dw
2. The developed IPS delivery system
Schematic of Field Injection
14
Component 4: Solution Injection
2. The developed IPS delivery system
Open-ended (PVC tube, ∅1.25")
Closed-ended, Side perforation
(PVC pipe, ∅1.25")
Sharp edge Sharp
edge1.66"
1.36"
~2"
1.66"
PVC Cone
1.36"
Type of injection tips explored in the research
15
Component 4: Solution Injection
Clear PVC
tube
Pressure
coupler
Gas relief valve
Connection to pumping system
Scope of Presentation:
1 – Introduction to Liquefaction and IPS Technique
2 – Development of IPS Delivery System
3 – Testing of the Developed Delivery System
4 – Large Scale Laboratory Testin Laminar Box at NEES@UB
5 – Field Test at Wildlife Liquefaction Array (WLA) site NEES@UCSB
6 – Summary and Conclusions
16
3. Testing of the Developed Delivery System
Powder bottle
Powder box
Bench-top power supply
Electric digital scale
Plastic wrap
Set-up for calibrating the rate of powder dispenser
Miniature DCGear motor
468
1012141618202224
Req
uire
d vo
ltage
s (V
)
Intake pump15 GPM
Intake pump 10 GPM
4 6 8 10 12 14 16 18 20 22 24Required voltages (V)
0
100
200
300
400
500
600
700
800
0.0 0.2 0.4 0.6 0.8 1.0 1.2 1.4 1.6 1.8 2.0
Pow
der R
ate
requ
ired
(gr/m
in)
Targeted Concentration (% W)
Intake pump15 GPM
Intake pump 10 GPM
Relationship of voltage, powder delivery rate, and targeted concentration
Testing of Powder Delivery Rate
Observation: • The minimum voltage to run the motor at full load is 3.5Volt• The rate of powder delivery is constant for a particular voltage• The rate of powder delivery is proportional to the speed of the screw turning with the voltage• Maximum concentration is 1.8 (%W) for 10GPM supply water
17
Soil restrictions in the field was simulated by:1 - both the textile at the tip 2 - the number of valves opened in the manifold
0
5
10
15
20
25
30
0 5 10 15 20 25 30
Man
ifold
s' Pr
essu
re, P
SI
Actual Pressure (Pr. 62), PSI
Set up a d a o ds essu es e at o s p
InlineG3G2G1
1 Manifold
0
5
10
15
20
25
30
0 5 10 15 20 25 30Actual Pressure (Pr. 62), PSI
Set up a d a o ds essu es e at o s p
InlineG3G2G1
2 Manifolds
0
5
10
15
20
25
30
0 5 10 15 20 25 30
Man
ifold
s' Pr
essu
re, P
SI
Actual Pressure (Pr. 62), PSI
InlineG3G2G1
3 Manifolds
0
5
10
15
20
25
30
0 5 10 15 20 25 30Actual Pressure (Pr. 62), PSI
InlineG3G2G1
4 Manifolds
Pres
sure
at t
he M
anifo
lds,
PSI
1 Valve open 2 Valves open
4 Valves open3 Valves open
(b)
(c)
(a)
Digital flowmeter
3. Testing of the Developed Delivery System
0
10
20
30
40
0 5 10 15 20 25 30 35
Dis
char
ge, G
PM
Set-up Pressure, PSI
Set-up Pressures vs. Pump Discharge
4 Manifolds
1 Manifold
2 Manifolds
3 Manifolds
4 Valves open
2 Valves open
3 Valves open
1 Valve open
Set-up Pressure vs. Pump DischargeTesting of the Constant Pressure Pump
18
Soil plug
Driving
Cleaning/ (washing)
InjectionDriven tube
Gardenhose
3. Testing of the Developed Delivery SystemTesting of Injection System
Driving Cleaning (washing)
Washed sample
Aligning Driving Cleaning (washing)
Driving open ended tube
Driving closed-ended tube with side perforation
19
Tube jetting
InjectionJetted tube
Annulus
Annular space created by water jetting
3. Testing of the Developed Delivery System
Aligning Jetting
Jetted tube
Jetting open ended tube
Jetting closed-ended tube with side perforation
20
Testing of Injection System
3. Testing of the Developed Delivery SystemTesting of Extraction of Injection Tubes
Extraction of driven injection tube Extraction of jetted injection tube
Come-along mounted on a wooden reaction frame
Pulling by bare-hand
21
Scope of Presentation:
1 – Introduction to Liquefaction and IPS Technique
2 – Development of IPS Delivery System
3 – Testing of the Developed Delivery System
4 – Large Scale Laboratory Testin Laminar Box at NEES@UB
5 – Field Test at Wildlife Liquefaction Array (WLA) site NEES@UCSB
6 – Summary and Conclusions
22
4. Large Scale Laboratory Test in Laminar Box
LVDT (Potentiometer)
Accelerometers
Overview of Laminar box of NEES@UB, Buffalo, NYNorth
EastWest
South
Scale, ft0 1 2 3 4 5
W ECL
9ft
16.5ft
20ft
Shaking direction
Laminar box details:• 20ft height, 9ft wide, 16.5ft long • 39 stacked laminates rest on shaking table, 6 inch height/laminate• Accelerometers and potentiometers (LVDT) on laminates
23
Two IPS tests were performed in Laminar Box at NEES@UB in 2014:
IPS Test 1: April 30 - May 20, 2014• Partly treatment of laminar box (only the top of 13.5ft)• Six pre-installed injection tubes (tip @10ft below the surface)
IPS Test 2: July 7 - July 21, 2014 • Treatment of the entire laminar box sand specimen• Jetted injection tubes
Pre-installed injection tube
Jetting of injection tube
24
4. Large Scale Laboratory Test in Laminar Box
IPS Test 1 Specimen IPS Test 2 Specimen
Piezometer
Wire Mesh
Conductivity Probes
Instrumentation placement: Piezometer and Conductivity probes were bundled in a wire mesh Wire meshes hung to instrumentation frame above the laminar box
Wire Meshes
Instrumentation frame Gantry cane
4. Large Scale Laboratory Test in Laminar Box
Placement of Instruments Within the Sand Specimen
25
4. Large Scale Laboratory Test in Laminar Box
N
EW
Mesh #1IP 1,IP 2, & IP 3
CP 1, CP 2, & CP 3
Mesh #2IP 7,IP 8, & IP 9
CP 7, CP 8, & CP 9
Mesh #5IP 10 & IP 11
CP 10 & CP 11
Mesh #4IP 12 & IP 13
CP 12 & CP 13
CP21CP20
CP19CP18
CP14 CP15 CP16 CP17
S
IT3
IT2
IT5 IT1 IT4
IT6
IT7
IT8
IT9 IT11
IT10
IT13
IT12
IT15
IT16IT17
IT18
IT19
IT20 IT21
IT22
IT23IT30
IT31
IT32
IT24
IT25
IT26 IT27
IT28
IT29
Laminar Box
IT14
Sand Specimen
CL
CL CL
CL
Scale, ft0 1 2 3 4 5 Mesh #3
IP 4,IP 5, & IP 6CP 4, CP 5, & CP 6
11
22
Note:Mesh indicates location of bundled Piezometers and Conductivity Probes
Instrumentation of IPS Test 2
26
4. Large Scale Laboratory Test in Laminar Box
Instrumentation - Section 1-1 Conductivity Probe
PiezometerPotentiometer (LVDT)Accelerometer
LEGEND:
HX
AEX
IP
CP
W ECL
Mesh #4 Mesh #1 Mesh #2 Mesh #5
Soil Surface
IP9CP9
IP11CP11
IP3CP3
IP2CP2
IP1CP1
IP10CP10
IP13CP13
IP12CP12
IP8CP8
IP7CP7
39
37
35
33
31
29
27
25
23
21
19
17
15
13
11
9
7
5
3
1
H31X
H29X
H27X
H25X
H23X
H21X
H19X
H17X
H15X
H13X
H11X
H9X
H7XH6XH5X
H3XH2XH1X
AE27X
AE35X
AE32X
AE30X
AE25X
AE23X
AE20X,Y
AE18X
AE15X
AE13X
AE10X,Y
AE5X,Y
AE2XAE1X
H0X
H4X
AE0X,Y
AE28X
AE3X
27
28
4. Large Scale Laboratory Test in Laminar BoxIPS Delivery Set-up
Pumping system
Two units automated mixing system joined
Hoses, ∅1"
29
Jetted Injection TubeAligning Injection Tube Jetting
Cone tip
Top and bottom injection tube
Injection tip Injection head
4. Large Scale Laboratory Test in Laminar BoxJetting of Injection Tube
30
4. Large Scale Laboratory Test in Laminar BoxIPS Treatment by Injection Tube
W ECL
Soil Surface
LEGEND:
Injection Tube (Bottom) (IT1-IT13)
N
EW
S
IT3
IT2
IT5 IT1 IT4
IT6
IT7
IT8
IT9 IT11
IT10
IT13
IT12
Laminar Box
Sand Specimen
Scale, ft0 1 2 3 4 5
Depth(ft)0.0
6.0
16.0
Untreated fully saturated Zone
Treated zone by bottom injections
IT1
Bottom injection
Bottom Injection Top Injection
W ECL
Soil Surface
LEGEND:
Injection Tube (Bottom) (IT1-IT13)Injection Tube (Top) (IT14 - IT32)
N
EW
S
IT3
IT2
IT5 IT1 IT4
IT6
IT7
IT8
IT9 IT11
IT10
IT13
IT12
IT15
IT16IT17
IT18
IT19
IT20 IT21
IT22
IT23IT30
IT31
IT32
IT24
IT25
IT26 IT27
IT28
IT29
Laminar Box
IT14
Sand Specimen
Scale, ft0 1 2 3 4 5
Depth(ft)0.0
6.0
16.0
Treated zone by bottom injections
Treated zone by surface injections
IT 14
Surface injection
(Bottom-up Injection)
31
• Total solution injected = 6,300 gallonsDepth (0ft – 15ft)
• Bottom injection = 4,500 gallons Depth (6ft – 15ft)
• Solution Concentration:- bottom injection = 0.9% - 1.4 % - during top injection = 1% - 2 %
4. Large Scale Laboratory Test in Laminar BoxSummary of All Injections
Cumm.Inflow IT Stage (gals)1 37:00 1.0-1.3 535.0 535.02 25:02 1.0 373.0 908.03 29:30 0.9-1.4 418.6 1326.64 0 0.9-1.1 414.4 1741.05 23:47 1.0 350.0 2091.06 21:30 0.8-1.0 361.0 2452.07 27:00 1.0 328.0 2780.08 24:37 0.9-1.1 431.0 3211.09 18:00 0.9-1.1 322.0 3533.010 25:10 0.9-1.1 372.0 3905.011 8:00 0.9-1.1 95.0 4000.012 28:30 0.9-1.1 342.0 4342.013 17:36 1.0-1.1 242.0 4584.014 17:40 0.9 0.0 4584.015 10:50 0.9 54.0 4638.016 14:56 1.1 87.0 4725.017 17:30 1.1 104.0 4829.018 16:25 1.0 72.0 4901.019 17:25 1.0 104.0 5005.020 14:36 1.0 80.0 5085.021 16:34 1.0 90.0 5175.022 13:50 1.0 80.0 5255.023 15:50 1.1 96.0 5351.024 13:23 1.0 30 5381.025 14:40 1.5-1.7 53 5434.026 41:13 1.5 208 5642.027 16:48 1.5 74 5716.028 6:12 1.5 21 5737.029 19:00 1.6 42 5779.030 39:00 1.7 191 5970.031 36:34 2.0 178 6148.032 39:30 2.0 97 6245.0
Inflow (gals)
Bot
tom
Inje
ctio
n
6 -1
6
Injection Depth (ft)
Duration (min)
Conc. (%)
Surfa
ce In
ject
ion
0 - 6
Bubbles escaping
Bubbles escaping at mesh and jetted locations
Some of the dry zones observed during IPS injection32
4. Large Scale Laboratory Test in Laminar BoxCorrection on the Degree of Saturation due to Bubble Escape
After Injection day#2
After Injection day# 3
After Injection day# 5
HW = 12″ HW = 23″ HW = 8″
CP #Before Bubble
Escape(%)
Final degree of saturation
(%)CP1 67 85*
CP2 64 76*
CP3 85 95*
CP4 81 99**
CP5 71 89**
CP6 80 89*
CP7 79 97**
CP8 59 77**
CP9 77 84**
CP10 76 94**
CP11 77 87**
CP12 61 96*
CP13 84 100*
CP14 81 88**
CP15 74 100*
CP16 47 68*
CP17 80 90**
CP18 72 100*
CP19 CP data not reliableCP20 84 100**
CP21 CP data not reliable
Note: *): Based on CPs data interpretation**): Based on volume calculation
4. Large Scale Laboratory Test in Laminar BoxFinal Corrected Degree of Saturation due to Bubble Escape
33
4. Large Scale Laboratory Test in Laminar BoxSpatial Distribution of Final Corrected Degree of Saturation
Mesh #3
W ECL
Mesh #4 Mesh #1 Mesh #2 Mesh #5
Soil Surface
96%
100%
100%
88%
76%
95%
85%
100% 77%
84%
97%
94%
87%
99%
89%
89%
100%
68%
90%
34
Date Test No.
Input Motion
Amax (g) Cycle Duration
(s) Note
6/30/14 C0 -- CPT, VS7/16/14 T1 IM1 0.015g 5 2.5s Shaking7/16/14 T2 IM3 0.1g 15 7.5s Shaking7/16/14 T3 IM3 0.1g 15 7.5s Shaking7/17/14 C3 -- CPT, VS7/18/14 T4 IM1 0.015g 5 2.5s Shaking7/18/14 T5 IM3 0.1g 15 7.5s Shaking7/18/14 T6 IM3 0.1g 15 7.5s Shaking7/18/14 C6 -- CPT, VS7/21/14 T7 IM1 0.015g 5 2.5s Shaking7/21/14 T8 IM3 0.1g 15 7.5s Shaking7/21/14 T9 IM3 0.1g 15 7.5s Shaking7/21/14 C9 -- CPT, VS7/21/14 T10 IM1 0.015g 5 2.5s Shaking7/21/14 T11 IM5 0.2g 15 7.5s Shaking7/21/14 T12 IM5 0.2g 15 7.5s Shaking
4. Large Scale Laboratory Test in Laminar BoxShaking Tests of IPS Test 2 Specimen
35
Observation:• No free water on the surface of the specimen
• During and right after shaking, no water on the surface of the specimen
• One minute after the shaking water was over, water seeped out from the surface
• Observed settlement of the specimen was approximately 2“
36
4. Large Scale Laboratory Test in Laminar BoxVisual Observations (on top of the soil specimen)
1) Before shaking 2) During shaking
3) Right after shaking
Water table just under the surface of the sand
No water on the surface
About 2” of water on the surface, due
to settlementNo water on the surface
4) One minute after shaking
Observations:• Surface of the IPS Test 2 specimen after the surface was water drained
• There were no sand boils found on the surface of IPS Test 2 specimen
• Piezometer results confirmed this visual observations in which the excess pore water pressure ratios were all less than 1 (no liquefaction)
No sand boils anywhere
37
4. Large Scale Laboratory Test in Laminar BoxVisual Observations on top of IPS Test 2 Specimen, After Shaking T2
38
Sand boils
Fully Saturated (Dr = 35%) IPS2 Specimen (Dr = 36%)
Measured average settlement = 2″
Sand boils observed on the surface
Measured average settlement = 4.5″
No sand boilson the surface
4. Large Scale Laboratory Test in Laminar BoxVisual Comparison of the Surface of Specimen of Fully Saturated and IPS Test 2 Specimens
39
Fully Saturated (Dr = 35%) IPS Test-2 Specimen (Dr = 36%)
VIDEO - 1 VIDEO - 2
4. Large Scale Laboratory Test in Laminar BoxVideo Comparison of the Surface of Specimen of Fully Saturated and IPS
Test 2 Specimens during and after the shaking
0.76
0.76
0.71
0.94
0.73
0.78
Max. Ru
0.75
0.73
0.61
0.80
Laminate
Top of Laminar Box
Otta
wa
Sand
Shaking Motion
0.0′
2.75′
4.75′
7.75′
10.75′
14.75′
5.75′
11.75′
12.75′
13.75′
6.75′
0.0
0.5
1.0
0.0
0.5
1.0
0.0
0.5
1.0
0.0
0.5
1.0
0.0
0.5
1.0
0.0
0.5
1.0
0.0
0.5
1.0
0.0
0.5
1.0
0.0
0.5
1.0
0.0
0.5
1.0
0 1 2 3 4 5 6 7 8 9 10Time, sec
Excess Pore Pressure Ratio Histories (T2-0.1g)
40
4. Large Scale Laboratory Test in Laminar Box
Excess Pore Pressure Comparison
41
Observation:• Excess pore pressure (∆U) build up in fully saturated specimen was instantaneous, in which it reached
its maximum excess pore pressure in about 2 sec. While in IPS Test 2 specimen was the build up was more gradual, in which it reached its maximum at the end of the shaking (7.5 sec).
• All piezometers in the fully saturated specimen except at the shallowest depth showed that thespecimen liquefied (∆ ), whereas piezometers in IPS Test 2 specimen showed that liquefactiondid not occur (∆ ) in the specimen (also confirmed by visual observation)
4. Large Scale Laboratory Test in Laminar Box
Fully-Saturated Specimen(DR = 35 %)
IPS Test 2 Specimen(DR = 36 %)
0
2
4
6
8
10
12
14
16
0 2 4 6 8
Dep
th, f
t
ΔU, psi
Δu=σvo'
0.25 sec
1.25 sec
2 sec
3.25 sec
4.5 sec
6 sec
7.5 sec
'(liquefaction)
0
2
4
6
8
10
12
14
16
0 2 4 6 8
Dep
th, f
t
ΔU, psi
Δu=σvo'
0.25 sec
1.25 sec
2 sec
3.25 sec
4.5 sec
6 sec
7.5 sec
'(liquefaction)
4. Large Scale Laboratory Test in Laminar BoxCumulative Settlement Comparison of Fully Saturated and IPS Test 2
due to only the Large Shakings
42
0 52
0
2
4
6
8
10
12
14
16
18
Test Number for Fully Saturated Specimen
Cum
ulat
ive
Settl
emen
t, in
Test Number for IPS Treated Specimen
0.1g0.1g
0.1g0.1g
0.1g0.1g
0.2g0.2g0.1g
0.1g0.1g
0.1g0.1g
0.1g0.1g
0.1g
T2 T3 T5 T6 T8 T9 T11 T12
T3 T10 T17 T24 T31 T38 T45 T52
IPS Test 2
Fully Saturated
Scope of Presentation:
1 – Introduction to Liquefaction and IPS Technique
2 – Development of IPS Delivery System
3 – Testing of the Developed Delivery System
4 – Large Scale Laboratory Testin Laminar Box at NEES@UB
5 – Field Test at Wildlife Liquefaction Array (WLA) site NEES@UCSB
6 – Summary and Conclusions
43
5. Field Test in WLA site at NEES@UCSBSatellite Photos
44
Salton Sea, Southern California
Wildlife Array, WLA
Map of 14 CPT locations around the USGS old site (Holzer et al., 1989 and Holzer and Youd, 2007)
5. Field Test in WLA site at NEES@UCSB
Observed sand ejecta near to the IPS site after the Superstition Hills Earthquake M6.6, 1987 (source: USGS)
Challenge: Heterogeneity of the site
45
7Cg WSW 4Cg ENE 1Cg3CgWest EastESE
5. Field Test in WLA site at NEES@UCSB
Cross Section (with factors of safety, FS), liquefaction susceptible analysis WLA using the Superstition Hills Earthquake, 1987 (Holzer and Youd)
Heterogeneity of the Site
46
Exploratory Test Site (First trip)
Exploratory Test Site (Second trip)
Final Test Site (Third trip)
5. Field Test in WLA site at NEES@UCSBExploratory tests and final IPS site Locations at WLA
Trip 1: January 23rd to February 4th, 2014 (exploratory test 1)
Trip 2: March 3rd to March 18th, 2014 (exploratory test 2)
Trip 3: May 20th to June 25th, 2014 (pilot test and full scale production) 47
(1) Split spoon sampling
(2) Washing boring with casing
Independent soil investigations
5. Field Test in WLA site at NEES@UCSBExploratory Test Findings: Soil Stratigraphy
Depth (ft)0
2
4
6
8
10
12
14
16
Silt
Clay
Silty Sand/ Sand
Findings:
1- Groundwater level was about 5ft below the ground surface2- The top soil is a medium to high plasticity Clay layer.3- The Sand deposit is found at about 10ft below the ground surface4- A thin silt interlayer separates the clay on top and sand below
48
Casing of PVC∅1.25"
Inner/extraction tube Extraction Pump
River water & Extracted ground water tested in the lab
Alamo River Water
Groundwater
5. Field Test in WLA site at NEES@UCSBExploratory Test Findings: Water Supply
49
One of the Challenge in field Implementation at WLA site
50
5. Field Test in WLA site at NEES@UCSBExploratory Test Findings: Injection and Extraction Tubes Installation
Aligning Driving Cleaning (Washing)
51
Injection tube
Extraction tube
IPS delivery system
Relief valve
Field monitoring by CPs
Findings:1 – Injection by gravity driven flow works well
2 – Treatment using simultaneous injection and extraction tubes gave better results
3 – Conductivity Probes in three level depths to better capture the solution flow and estimate the degree of saturation
5. Field Test in WLA site at NEES@UCSBExploratory Test Findings: IPS Field Delivery
52
5. Field Test in WLA site at NEES@UCSB
24"
Driven Injection Tube(Directional Perforation)
Driven Extraction Tube(3600 Perforation)
Cone tip
Clay
Silty Sand/ Sand
Collapsed sand
Landscape fabric wrapped
Inner tube, PVC ∅3/4"
PVC ∅1.25"
PVC ∅1.25"
Landscape fabric wrapped
24"-Perforation
Cone tip
Exploratory Test Findings: Injection and Extraction Tubes
53
Pilot test site
IPS treated site Untreated site
5. Field Test in WLA site at NEES@UCSBDetails of the final IPS test site
54
5. Field Test in WLA site at NEES@UCSBIPS Test: Pattern of IPS injections and extraction tubes
IPS treated
site
1.2
m2.
4 m
1.2m2.4m
1 58
3 67
12 4 2 10
9 1316
11 1415
Injection Tube Location
LEGEND:
Extraction Tube Location
Injection onlyInjection and extraction
55
5. Field Test in WLA site at NEES@UCSBIPS Test: During the Treatment
IPS treated
site
Injection and extraction Monitoring using Conductivity Probes
56
IPS treated
site
5. Field Test in WLA site at NEES@UCSBIPS Test: Delivery System after Treatment
Extraction tube
Relief valve
Powder delivery and mixing
system
2.4 m
2.4 m
Dissolved solids & conductivity probes
Injection tubes
57
5. Field Test in WLA site at NEES@UCSBSite Instrumentation
Dep
th (f
t)
Dep
th (m
)
0
1
2
3
4
0
2
4
6
8
10
12
5
14
16
P1
P4
P5
Sand
Clay
P2P3
Silty Sand
1.2m
2.4m P1
P3P4
P2P5
1.2m2.4m
G1 G2 G3 G4
G7G6G5
Piezometer
GeophoneG8
IPS treated
site
Untreated site
Dep
th (f
t)
1.2m
2.4m P1
P2
P3P4
P5
1.2m2.4m
Dep
th (m
)
0
1
2
3
4
0
2
4
6
8
10
12
5
14
16
P1
P4P5 Sand
Clay
P2P3
G1 G2 G3G4
G7G6G5
Injection Tube
Extraction Tube
Piezometer
Silty Sand
Geophone
IPS Treated SiteUntreated Site
58
Treated zone
Presumed treated
(IPS Site is permanently Instrumented)
5. Field Test in WLA site at NEES@UCSBSite Characterization: CPTs
IPS treated
site
Untreated site
Silty sand interface
0
5
10
15
20
25
0 100 200 300 400
Dep
th (f
t)
qc (ksf)
CPT 1
CPT 1a
0
5
10
15
20
25
0 5 10 15 20Rf (%)
CPT 1
CPT 1a
Silty sand interface
0
5
10
15
20
25
0 100 200 300 400
Dep
th (f
t)
qc (ksf)
CPT 5
CPT 4
0
5
10
15
20
25
0 5 10 15 20Rf (%)
CPT 5 CPT 4
IPS Treated SiteUntreated Site
59
5. Field Test in WLA site at NEES@UCSBSite Characterization: Wave velocity measurement
(a) (b)
0
5
10
15
20
0 1500 3000 4500 6000 7500
Dep
th (f
t)
VP (fps)
Untreated
Treated Site
0
5
10
15
20
0 250 500 750
Dep
th (f
t)
VS (fps)
UntreatedTreated Site
Vs Profiles Vp Profiles
IPS treated
site
Untreated site
60
5. Field Test in WLA site at NEES@UCSBShaking Tests
IPS treated
site
Untreated site
61
5. Field Test in WLA site at NEES@UCSBShaking Results – Untreated Site vs. IPS Treated Site
IPS treated
site
Untreated site
62
End of shakingEnd of shaking
IPS Treated SiteUntreated Site
Challenges Faced at WLA:• Silty medium dense sands, (not easy to liquefy)• Contaminated silty river and ground water, (accelerated reaction, and reduced permeability)• High temperatures, (accelerated reaction and shortened injection time)• 10 feet of clay over sand, (difficult to penetrate to silty sand and difficult to shake silty
sand) • Small area of shaking, (spatial variability of density became important)• Silty sand at treated site was looser than untreated site• Shaking energy at depth of silty sand was small, (excess pore pressure ratios were less than
0.2)Because of above, test results were inconclusive.
Future field tests should be performed at favorable sites (New Zealand per NSF)
63
5. Field Test in WLA site at NEES@UCSB
IPS treated
site
Untreated site
Scope of Presentation:
1 – Introduction to Liquefaction and IPS Technique
2 – Development of IPS Delivery System
3 – Testing of the Developed Delivery System
4 – Large Scale Laboratory Testin Laminar Box at NEES@UB
5 – Field Test at Wildlife Liquefaction Array (WLA) site NEES@UCSB
6 – Summary and Conclusions
64
6. Summary and Conclusions
65
Automated IPS Delivery System has been designed and manufactured
The IPS Delivery System was tested in the laboratory and in the field. The system is
capable of inducing partial saturation efficiently and reliably.
IPS implemented in the laminar box and then shaken demonstrated its effectiveness as
a liquefaction mitigation measure.
The field IPS implementation identified important fundamental knowledge gaps that
need to be further investigated, including effect of: spatial variability in soil density and
permeability, temperature, natural sand gradation, contaminated water with ions,
interaction between injection holes, and large energy needed to liquefy sand in the field.
The field IPS tests indicated need for further field research.
Acknowledgement
Prof. M. K. YegianProf. Akram AlshawabkehProf. Thomas C. SheahanProf. Luca Caracoglia
Prof. S. ThevanayagamProf. Kenneth StokoeProf. T.L. YoudDr. Jamieson Steidl
Seda Gokyer, Ph.D.Hadi Kazemiroodsari (Ph.D. Candidate)Ata Firat Karamanle (Master Student)
Michael McNeilKurt BraunDavid WhelpheyArmando & Jesse
The Fulbright Program, IIE, US Department of State
66