support challenges and experinces on palabora … · 2009-10-15 · support challenges and...

14
SAIMM, SANIRE and ISRM The 6 th International Symposium on Ground Support in Mining and Civil Engineering Construction R C Jaggard Page 503 SUPPORT CHALLENGES AND EXPERINCES ON PALABORA BLOCK CAVE - INITIAL MINING THROUGH TO FULL PRODUCTION. R C Jaggard Rock Mechanics Superintendent, Palabora Mining Company Abstract Palabora Mining Company currently operates a large (32000 tpd) block cave, designed for a life of 20 years. The mine is mining the hardest rock to be caved over the highest height of draw (HOD). Some of the work done at the feasibility study was correct, but some assumed conditions were not experienced and were therefore incorrect. During the construction of the mine these recommendations, either correct or erroneous, were not followed! The paper deals with the original design of the support through to the support as installed. There are 314 drawpoints that will yield upwards of 500 000 tonnes of ore. Weekly monitoring of these drawpoints is done and steel brow sets are retro fitted (the feasibility decision was not to fully equip the footprint with brow sets). This retro fitting is not done elsewhere in the block cave community, and systems for working under operational drawpoints have been developed on mine to facilitate this. The sets were also not available ‘off the shelf’ and a design to suit had to be developed and then manufactured. During the mine’s construction, the undercut geometry designed as a diamond shape approached a seismically active dyke at an unfavourable angle which required management. Later the final mining of the undercut to the west proved to be a challenge - a large fault zone deep in the pit wall caused abutment stresses to load up the area between the fault and the undercut, requiring a call to be made in support strategy and mining rate. Modelling done prior to mining also failed to highlight the pit wall failure which has occurred. This caused 130 million tonnes of material to report to the pit bottom, which has affected the draw control strategy for the cave material. The author has been involved with the project, from 1999 when shaft sinking was still being completed and the first undercut blast taken, through all of the learnings to full production at over 32000 tonnes per day, hoisted out of a single shaft. Many papers discuss what has been designed and what is planned. This paper will attempt to discuss how support decisions made affect later mining, and to describe challenges to find the correct support type and the work done with local suppliers to find solutions. Many decisions made would be different next time. Nevertheless, Palabora Mining Company has operated over the past two years with no rock related injuries (fatal/reportable/lost time/medical treatment/first aid).

Upload: others

Post on 15-Aug-2020

4 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: SUPPORT CHALLENGES AND EXPERINCES ON PALABORA … · 2009-10-15 · SUPPORT CHALLENGES AND EXPERINCES ON PALABORA BLOCK CAVE - INITIAL MINING THROUGH TO FULL PRODUCTION. ... and the

SAIMM, SANIRE and ISRM

The 6th

International Symposium on Ground Support in Mining and Civil Engineering Construction

R C Jaggard

Page 503

SUPPORT CHALLENGES AND EXPERINCES ON PALABORA BLOCK

CAVE - INITIAL MINING THROUGH TO FULL PRODUCTION.

R C Jaggard

Rock Mechanics Superintendent, Palabora Mining Company

Abstract

Palabora Mining Company currently operates a large (32000 tpd) block cave, designed for a

life of 20 years. The mine is mining the hardest rock to be caved over the highest height of

draw (HOD). Some of the work done at the feasibility study was correct, but some assumed

conditions were not experienced and were therefore incorrect. During the construction of the

mine these recommendations, either correct or erroneous, were not followed!

The paper deals with the original design of the support through to the support as installed.

There are 314 drawpoints that will yield upwards of 500 000 tonnes of ore. Weekly

monitoring of these drawpoints is done and steel brow sets are retro fitted (the feasibility

decision was not to fully equip the footprint with brow sets). This retro fitting is not done

elsewhere in the block cave community, and systems for working under operational

drawpoints have been developed on mine to facilitate this. The sets were also not available

‘off the shelf’ and a design to suit had to be developed and then manufactured.

During the mine’s construction, the undercut geometry designed as a diamond shape

approached a seismically active dyke at an unfavourable angle which required management.

Later the final mining of the undercut to the west proved to be a challenge - a large fault zone

deep in the pit wall caused abutment stresses to load up the area between the fault and the

undercut, requiring a call to be made in support strategy and mining rate.

Modelling done prior to mining also failed to highlight the pit wall failure which has

occurred. This caused 130 million tonnes of material to report to the pit bottom, which has

affected the draw control strategy for the cave material.

The author has been involved with the project, from 1999 when shaft sinking was still being

completed and the first undercut blast taken, through all of the learnings to full production at

over 32000 tonnes per day, hoisted out of a single shaft. Many papers discuss what has been

designed and what is planned. This paper will attempt to discuss how support decisions made

affect later mining, and to describe challenges to find the correct support type and the work

done with local suppliers to find solutions.

Many decisions made would be different next time. Nevertheless, Palabora Mining Company

has operated over the past two years with no rock related injuries (fatal/reportable/lost

time/medical treatment/first aid).

Page 2: SUPPORT CHALLENGES AND EXPERINCES ON PALABORA … · 2009-10-15 · SUPPORT CHALLENGES AND EXPERINCES ON PALABORA BLOCK CAVE - INITIAL MINING THROUGH TO FULL PRODUCTION. ... and the

SAIMM, SANIRE and ISRM

The 6th

International Symposium on Ground Support in Mining and Civil Engineering Construction

R C Jaggard

Page 504

1. Mine location and description

Palabora Mining Company operates a copper block cave mine in the Limpopo province of

South Africa. The mine was developed in the late nineties with a target ore reserve of 240

million tons of Carbonatite at 0.70% copper. At 30000 tons per day the operation had a

planned life of mine of approximately 23 years.

The production level (extraction level) sits at a depth of about 1200m below surface and 14m

below the Undercut level used to initiate the caving. Column height ranges between around

400m directly below open-pit floor and 750m on the furthest columns in Western extent of

the footprint. This is currently the highest lift ever to be caved. Feasibility study results

indicated that production rate of 30000 tonnes per day will ensure financial viability for the

project. This has changed and current call is 32000 tpd with the call increasing again for

2008.

Figure 1: Layout and structure – Production level

The Palabora block cave is serviced by a service shaft, a ventilation shaft and a production

(rock handling) shaft with a herringbone production level layout consisting of 166 draw bells.

Tonnage is currently drawn from 314 drawpoints. Diesel LHD’s load ore from 19 cross cuts

and tip into four 750t/hr jaw crushers. The footprint covers approximately 100 000m2

.

2. Introduction

The challenge to a Rock Engineer is, (roughly quoting the original Chamber of Mines

coursework for the Certificate in Rock Mechanics), to adequately support the excavation for

the planned life of the excavation most economically to the mine.

Page 3: SUPPORT CHALLENGES AND EXPERINCES ON PALABORA … · 2009-10-15 · SUPPORT CHALLENGES AND EXPERINCES ON PALABORA BLOCK CAVE - INITIAL MINING THROUGH TO FULL PRODUCTION. ... and the

SAIMM, SANIRE and ISRM

The 6th

International Symposium on Ground Support in Mining and Civil Engineering Construction

R C Jaggard

Page 505

One of the challenges with a low grade block cave is to fulfil these functions. Once the initial

feasibility has been through to the financial Board and been rejected, the further versions of

this feasibility study then had a fair amount of “pencil sharpening” done, and some of the

required support capital fell away. This will be discussed in more detail, but much of the

shotcrete that has actually been placed was not planned for, in the belief that the ground was

‘good enough’. Certain support systems advocated for the undercut were changed in the

interests of safety and speed, and the installation of brow sets was limited to only the ‘worst’

drawpoints. The challenge for the Rock Engineer was then to decide when and where to

spend unbudgeted money and be able to validate decisions made.

Figure 2: Palabora open pit showing integrity of the benches.

Palabora open pit was a highly successful pit (Figure 2), with pit angles of 570

and beautiful

square benches standing stably from when the mine was begun in 1964. A lot of talk in the

industry at the time discussed the plan to block cave the extension of the ore body below the

mineable extent of the open pit. At that stage the Palabora Block Cave was planned to have

the highest HOD (Height of Draw) and would also be the hardest rock to be caved. Many

people in the industry believed that the rock was “too hard to cave” at 120 Mpa. Palabora sits

right on the unexplored side of the “caveability” graph (base graph after Hoek 1981).

Page 4: SUPPORT CHALLENGES AND EXPERINCES ON PALABORA … · 2009-10-15 · SUPPORT CHALLENGES AND EXPERINCES ON PALABORA BLOCK CAVE - INITIAL MINING THROUGH TO FULL PRODUCTION. ... and the

SAIMM, SANIRE and ISRM

The 6th

International Symposium on Ground Support in Mining and Civil Engineering Construction

R C Jaggard

Page 506

Figure 3: Caveability chart

Rock Type RMR UCS

MPa

Density

(kg/m3

)

Tensile

Strength

MPa

Poisson’s

Ratio

Strength

Condition

Young’s

Modulus

E

Bulk

Mod

K

Shear

Mod

G

Coh’n

(MPa)

Frict'n

Angle

(deg)

Peak 14.1 9.4 5.7 3.8 46

Carbonatite 61 120 3100 1.0 0.25 Residual 7.1 4.7 2.8 2.2 33

Peak 13.3 8.9 5.3 5.6 54

Dolerite 601 320 3100 1.0 0.25 Residual 6.7 4.4 2.7 3.1 41

Peak 9.9 6.6 4.0 3.0 41

Foskorite 58 70 3500 1.0 0.25 Residual 5.0 3.3 2.0 1.7 27

Peak 8.4 5.6 3.4 2.9 41 Micaceous

pyroxenite 54 80 3100 1.0 0.25 Residual 4.2 2.8 1.7 1.6 25

3. Block cave support

In a conventional tabular mining layout the support utilized is finite and certainly in ‘follow

on’ footwall drives has an expected life of around 6 months. In block caving the whole

mining footprint and the ancillary chambers for pumps, crushers, workshops, etc are all

developed before the tonnes flow out of the shaft. This also means that the money spent on,

in Palabora’s case, 33km of development, is spent ahead of the generated income. Support

installation also needs to infringe as little as possible on the operational part of the cave.

Page 5: SUPPORT CHALLENGES AND EXPERINCES ON PALABORA … · 2009-10-15 · SUPPORT CHALLENGES AND EXPERINCES ON PALABORA BLOCK CAVE - INITIAL MINING THROUGH TO FULL PRODUCTION. ... and the

SAIMM, SANIRE and ISRM

The 6th

International Symposium on Ground Support in Mining and Civil Engineering Construction

R C Jaggard

Page 507

Palabora’s rock hoisting shaft currently does the highest tonnage of any single shaft in the

world.

• Best day – 42998 tons (May 2005)

• Best week – 36819 tpd (Week 24/2007)

• Best month –1 073 280 tons (35776 tpd April 2007)

To achieve this the cycle needs to run ideally with no interruptions - to take crosscuts down

for frequent rehabilitation and re-support is not conducive to this. Therefore the support has

to be:

• Correctly designed for the life of mine (at that time + 20 years).

• Economically practical as some of the funding was already reduced at feasibility.

• Allow for remote and therefore safe installation.

• Rapid in terms of both installation and re-entry.

4. Support challenges (Rock Bolt system)

Primary support on the mine has been done using 2.4m (length of the bolter boom) 20mm re-

bar with full column resin grouting. Using the Tamrock bolters at that stage the drill steel

was 25 AF, but had an actual diameter of 28mm. Using knock off bits the skirt on the bit was

prone to shearing if too small a diameter bit was used. A 32mm bit was the smallest that

could be used. The Australian handbook for hard rock mining advocates an annulus of resin

of around 2mm. The annulus found at Palabora was 6mm. Work with local suppliers came

up with a resin with a 70:30 mix ratio that could be used with an annulus of 6.5mm. The use

of a 25mm or 28mm bolt was not required from a support point of view so work was done on

the 20mm bar. Eventually a solution was found where a cold rolled thread was introduced on

a bar resulting in a 22mm x 20mm bar with two sets of half threads. Pull tests show this

combination to work exceptionally well.

5. Support challenges (Brow sets)

It was expected that only around 15% of the 314 brows on Palabora would need sets to be

installed. This was due to financial considerations and the belief that the rock, being so hard,

would not require solid support.

The first issue was to obtain sets other than the ‘Walter Bekker’ (T&H Mining) yielding

arches. The other companies that used to manufacture what was then (wrongly) referred to as

“Square sets” had concentrated on manufacturing yielding elongates for a huge market in

both the local Gold and Platinum mines, and locally manufactured sets were therefore

unavailable. Several of the yielding arches were installed, but although an excellent arch for

highly stressed ground, they were not designed for the use they were being put to. In a block

cave the set should not generally be subjected to high stresses, but is required to assist the

support system to hold the whole drawpoint area together. The set also provides a wear

platform for the rock that will pass through the bell and drawpoint, in Palabora’s case,

between 500 000 and 750 000 tonnes of material. In the dolerite dyke rich drawpoints, the

passing rock is highly abrasive having a UCS of over 300MPa. In the softer, but more blocky

Carbonatite, large oversize rocks reporting to the drawbell need to be blasted. Higher hang-

Page 6: SUPPORT CHALLENGES AND EXPERINCES ON PALABORA … · 2009-10-15 · SUPPORT CHALLENGES AND EXPERINCES ON PALABORA BLOCK CAVE - INITIAL MINING THROUGH TO FULL PRODUCTION. ... and the

SAIMM, SANIRE and ISRM

The 6th

International Symposium on Ground Support in Mining and Civil Engineering Construction

R C Jaggard

Page 508

ups are brought down using a ‘Medium reach rig’ where a 75mm hole is drilled in the rock

and blasted with HEF, an ammonium nitrate slurry explosive. Blasting is not to take place

immediately against the brow, but it is undertaken only metres away.

The yielding arches did not support the brow or provide an adequate wear platform.

Investigation was then done, looking at sets used worldwide. Designs from Henderson,

NorthParkes, Freeport and more locally Premier mines were all studied. A combined design

was generated and put together by engineers on Palabora Mining Company. This was sent

out to local steel works and the design has gone through three stages of design modifications

to the current one that is used.

Figure 4: Palabora design for “Stiff Brow” support

At a stage during the development it could be seen that the installation of brow sets was going

to be required, and from crosscuts 16 through to 20, all drawpoints were then equipped with

sets. The whole remainder of the footprint was in operation with now the challenge to get

30000 tonnes per day. The challenge was having to come back and retro-fit over 200 sets

with out introducing any constraints on the operational cycle.

Page 7: SUPPORT CHALLENGES AND EXPERINCES ON PALABORA … · 2009-10-15 · SUPPORT CHALLENGES AND EXPERINCES ON PALABORA BLOCK CAVE - INITIAL MINING THROUGH TO FULL PRODUCTION. ... and the

SAIMM, SANIRE and ISRM

The 6th

International Symposium on Ground Support in Mining and Civil Engineering Construction

R C Jaggard

Page 509

Figure 5: Detail showing buttress plate

On investigation it was found that mines world wide do not have a lot of experience in doing

this sort of retro-fit construction. Palabora had to come up with a system to install support in

operational drawpoints without putting persons at risk, and ensuring that the installed brow

support was in fact placed under the brow.

Draw

point

Draw

point

Draw

point

Shotcrete the top of the rill

and allow 24 hours for curing

Load out the lower portion of the

rill, shotcrete and cure again

Continue the process untill the mouth

of the drawpoint is stabilized and set

construction can continue

Drawpoint set - installed as per Survey layout

Figure 6: Drawpoint stabilization using FRS

Page 8: SUPPORT CHALLENGES AND EXPERINCES ON PALABORA … · 2009-10-15 · SUPPORT CHALLENGES AND EXPERINCES ON PALABORA BLOCK CAVE - INITIAL MINING THROUGH TO FULL PRODUCTION. ... and the

SAIMM, SANIRE and ISRM

The 6th

International Symposium on Ground Support in Mining and Civil Engineering Construction

R C Jaggard

Page 510

The drawpoint had to be in a free-flow condition as opposed to being hung up, since the

exposure to personnel should this hang up come down was unacceptable. As shown in Figure

6, the upper metre would be shotcreted with wet fibre reinforced shotcrete (FRS). Once this

had cured spiling was drilled in, often in the form of old drill steel. The lower portion of the

muck pile could now be lashed and another metre of shotcrete applied and new spiles

installed. In this manner the whole face could be safely shotcreted and supported and

effectively, completely shielding the construction crew from the open cave above them. A

vertical face is formed of shotcrete placed at a thickness of 300mm. The work on this

shotcrete design has allowed for the spiling to be dropped, and a system now exists for the

installation of a brow set in less that a week, from start to finish, and handed back to

operations. Around 54 sets per year are retro fitted.

6. Footprint support

All primary support was, as discussed, 20mm bolts, full column grouted with resin. All

breakaways were supported with 6m long, 18mm pre-stressed cable anchors and OSRO

straps with another two sets of anchors and OSRO straps at the brow position. Bolts and

OSRO straps replaced trusses on the ‘bullnoses’ and ‘camel backs’. The whole footprint has

been shotcreted with initially steel fibre (40kg/m3

) reinforced shotcrete and later with

polypropylene fibres (9kg/m3

).

Figure 7: Support layout for the Production Cross Cuts and Drawpoint entrance

Page 9: SUPPORT CHALLENGES AND EXPERINCES ON PALABORA … · 2009-10-15 · SUPPORT CHALLENGES AND EXPERINCES ON PALABORA BLOCK CAVE - INITIAL MINING THROUGH TO FULL PRODUCTION. ... and the

SAIMM, SANIRE and ISRM

The 6th

International Symposium on Ground Support in Mining and Civil Engineering Construction

R C Jaggard

Page 511

Figure 8: Support layout for Drawpoint and Bell area

7. Support monitoring

Monitoring in the footprint is done around the clock. Geotechnical observers work on all

three shifts taking readings. Brow measurements are taken in every drawpoint on a weekly

basis and data for these is available from when the drawpoint was first mined up until present,

and can be cross referenced against tonnes drawn, and geology.

Brow monitoring relative to the crosscut’s breakaway position is picked up using a remote

laser instrument (Distomat).

Brow position

Figure 9: Brow wear monitoring

Page 10: SUPPORT CHALLENGES AND EXPERINCES ON PALABORA … · 2009-10-15 · SUPPORT CHALLENGES AND EXPERINCES ON PALABORA BLOCK CAVE - INITIAL MINING THROUGH TO FULL PRODUCTION. ... and the

SAIMM, SANIRE and ISRM

The 6th

International Symposium on Ground Support in Mining and Civil Engineering Construction

R C Jaggard

Page 512

Readings are plotted against tonnes to obtain wear rates, and drawpoints are prioritized for set

installation. All drawpoint lengths below 9m are noted, drawpoints with lengths below 8m

become short listed for rehabilitation, with the sub 7m drawpoints getting retro-fit sets

installed.

Brow Wear (monthly)

6.0

7.0

8.0

9.0

10.0

11.0

12.0

13.0

27-Jan-04

15-Apr-04

08-Jul-04

30-Sep-04

W

eek51

W

eek15\05

W

eek26\05

W

eek36\05

W

eek46\05

W

eek06\06

W

eek16\06

W

eek27\06

W

eek38\06

W

eek50\06

W

eek09\07

W

ee20/07

W

eek30/07

W

eek41/07

DP

L

en

gth

1W8 1W7 1W6 1W5 1W4 1W3 1W2 1W1

Graph 1: Brow wear measured in crosscut 1

The wear on the brows is shown in Graph 1. Here relatively rapid wear is seen in the first

part of draw and certain drawpoints can be seen to be wearing faster than the others. Where

the plot stops is the point where a retro-fit set has been installed.

Tonnes (monthly)

0

2000

4000

6000

8000

10000

12000

14000

Jan-04

M

ar-04

M

ay-04

Jul-04

Sep-04

Nov-04

Jan-05

M

ar-05

M

ay-05

Jul-05

Sep-05

Nov-05

Jan-06

M

ar-06

M

ay-06

Jul-06

Sep-06

Nov-06

Jan-07

M

ar-07

M

ay-07

Jul-07

Sep-07

Nov-07

Tonnes

L01W01 L01W02 L01W03 L01W04 L01W05 L01W06 L01W07 L01W08

Graph 2: Tonnes drawn crosscut 1

Tonnes drawn for the drawpoints are shown in Graph 2. Over time a gradual increase in the

monthly draw can be seen. This relates mostly to the fragmentation size reducing over time

Page 11: SUPPORT CHALLENGES AND EXPERINCES ON PALABORA … · 2009-10-15 · SUPPORT CHALLENGES AND EXPERINCES ON PALABORA BLOCK CAVE - INITIAL MINING THROUGH TO FULL PRODUCTION. ... and the

SAIMM, SANIRE and ISRM

The 6th

International Symposium on Ground Support in Mining and Civil Engineering Construction

R C Jaggard

Page 513

with an increasing HOD. What is of most interest is that the wear in the drawpoints is very

heavily affected by the local geology and blast related fractures, which leads to high initial

wear and a very shallow residual tail to the graph. Features that run parallel to the brow do

not affect the brow much. The damaging geological structures are the ones that run

perpendicular to the brow. Mapping of all structures during the development stage before

shotcrete is applied is vitally important.

8. Convergence monitoring

Convergence readings are taken on a twice weekly basis from all of the stations. These are

taken from sets of 3 point stations throughout the mine. The readings are also cross

referenced against the tonnes drawn from the drawpoints, and in this way the influence of

overdrawn or underdrawn drawpoints is observed and monitored.

Cave convergence stations.

Rim convergence stations.

Crusher extensometers.

RAW water doors convergence station

Figure 10: Convergence stations, Strain gauges and Extensometers

Resultant movementConvergence bolts

Measurements

A B

C

Figure 11: Convergence station setup

Page 12: SUPPORT CHALLENGES AND EXPERINCES ON PALABORA … · 2009-10-15 · SUPPORT CHALLENGES AND EXPERINCES ON PALABORA BLOCK CAVE - INITIAL MINING THROUGH TO FULL PRODUCTION. ... and the

SAIMM, SANIRE and ISRM

The 6th

International Symposium on Ground Support in Mining and Civil Engineering Construction

R C Jaggard

Page 514

Movements seen have very interestingly shown that the Carbonatite does behave elastically.

With a monthly production rate of over 1 million tonnes small changes in the rockmass can

be related to the evenness of draw and also the local geology. Over 4000 individual

convergence setups are done on a month by month basis. With the rock behaving in an

elastic manner it is important that the choice of support has an elasticity to it. Tendons should

have the ability to deform to the small increments that occur in the footprint.

Figure 12: Tonnes pulled from the cave week 45

Higher tonnage was drawn on the southern side of the footprint during week 45 as shown in

Figure 12. This shows reasonably even draw elsewhere in the cave apart from crosscut 11

which was closed, and crosscut 8 which was on rehabilitation.

Figure 13 shows the plotted movements within the cave for the same period. Although very

small, the movements show that the area where the higher draw relative to its sister

drawpoints took place underwent a slight “rebound”.

0 tonnes

100 tonnes

500 tonnes

1,500 tonnes

3,000 tonnes

4,500 tonnes

Production - Week 45

24

6

810

1214

161820

13

57

9

11

13

15

17

19

Page 13: SUPPORT CHALLENGES AND EXPERINCES ON PALABORA … · 2009-10-15 · SUPPORT CHALLENGES AND EXPERINCES ON PALABORA BLOCK CAVE - INITIAL MINING THROUGH TO FULL PRODUCTION. ... and the

SAIMM, SANIRE and ISRM

The 6th

International Symposium on Ground Support in Mining and Civil Engineering Construction

R C Jaggard

Page 515

Figure 13: Convergence measured in the footprint

9. Conclusions

In conclusion, a number of points can be made:

• The most important factor is the support planning at the feasibility stage. If mistakes

are made and short cuts taken at this point, the long-term effect can be huge.

• Monitoring systems are vitally important to check the modelling results and to be

able to accurately gauge what rock movements the support units are being subjected

to.

• When purchasing equipment such as extensometers, if the code of practice (ground

control document) requires many readings (4000 per month at Palabora), be careful

what unit is purchased. Many units are not capable of this type of usage and will give

poor data.

• When designing the support system, time is important since it may be necessary to

develop support components, in conjunction with support suppliers, that currently

may not exist.

• Support units must be able to accommodate the ground movements that the mining

system is going to generate.

• Modern mines cannot be expected to allocate production time to retro-fitting of

support. Do not allow the idea “we will come back later and catch that back up” to

even be thought, let alone voiced.

-3.2 mm

-3 mm

-2.6 mm

-2 mm

-1.6 mm

-0.8 mm

-0.6 mm

0 mm

0.8 mm

Convergence - Week 45

24

6

810

1214

161820

13

57

9

11

13

15

17

19

Page 14: SUPPORT CHALLENGES AND EXPERINCES ON PALABORA … · 2009-10-15 · SUPPORT CHALLENGES AND EXPERINCES ON PALABORA BLOCK CAVE - INITIAL MINING THROUGH TO FULL PRODUCTION. ... and the

SAIMM, SANIRE and ISRM

The 6th

International Symposium on Ground Support in Mining and Civil Engineering Construction

R C Jaggard

Page 516

• Mining at an average of 34000 tpd can be done with the correct support design and

installation. Zero rock related injuries have occurred in the last two years at Palabora.

The last injury recorded occurred when a contracts manager barred a piece of rock

onto his foot in 2004.

0

1

2

3

4

5

6

1997

1998

1999

2000

2001

2002

2003

2004

2005

2006

2007

Rock related Injuries

Rate per 1000 per annum

Fatal

Reportable

Lost time

Minor

• Finally, as intimated earlier, the support should be designed for the mine’s life, to

perform as required and to be practical, and still, very importantly, at the best cost.