svsd 2015 bond program

6
1 SVSD 2015 Bond Program Mount Si High School Replacement Progress Status Report ________________________________________________________________________________ Date: August 15 th , 2017 To: Ryan Stokes Copy: Carolyn Malcolm, Joel Aune From: Clint Marsh Subject: August 15th Current Progress Status Weeks from July 15 th to August 15th, as follows: New: Phase One And Two General Contractor Phase One o Surveying For Building Layout Of AREAS F ‐ D And J (No Area I) Continues... AREA A AREA B AREA C AREA E ‐ AREA F ‐ AREA D: Footings And Foundations Have Been Dug Or Being Dug... Structural Steel Rebar And Steel Are Being Placed And Inspected... Concrete Has Been Or Is Being Poured In Footings And Foundations... Footings And Foundations Have Been Or Are Being Backfilled And Compacted... Underground Utilities Are Being Dug And Installed Where Applicable... Sewer ‐ Water ‐ Mechanical ‐ Electrical ‐ Telecommunications Structural Steel Erection and Steel Decking Continues: AREA A ‐ Complete AREA B ‐ Complete AREA C ‐ E ‐ F ‐ D ‐ Steel Fabrication In Process Concrete Floors Are Being Prepared With Steel Reinforcement Pending Concrete Steel Stud Roof Parapet Walls Are Being Constructed... o Multiple Material Deliveries Continue... o Staffing By Trade Continues To Be Increased As Required... Previous Relevant Status Items: Planning, Visioning, Education Specifications, Schematic Design, Design Development, Ten Development Permits (as listed in the September 16th Status Report), Five Health Department Permits, Labor & Industries Electrical Permit, Initial Demolition Projects, Relocation of the Twelve Classroom Portable Wing and TLC Portable, Installation of the Two Double‐Wide Temporary Portables, Silt Fence Installation, Surface Water Management Structures Installed, Temporary Perimeter Fencing Installed, Trucking Haul Roads Constructed, Crane/Probe Assemblies Completed, Temporary Parking Lot Constructed, Old Parking Lot Demolished, Construction Documents and Constructability Review Complete, GC Phase 1 & 2 Bid Process Complete, Temporary Retaining Wall, Temporary Sewer, Temporary Storm Lines, Permanent Water Line, Pad Sub‐Grade Established, Soil Haul Out, Rock Spall Import, Phase One Building Permits (5‐4‐2017), 3,519 Stone Column Installations, and Phase 1 & 2 General Contractor Mobilization Complete. Future Activities: Phase Two City Building Permit ‐ Permit Issue Pending Attachments: Spee West 8‐4‐2017 NE & 8‐11‐2017 NE Aerial Photos Spee West 8‐4‐2017 SE & 8‐11‐2017 SE Aerial Photos Progress Photos ‐ July 2017 & August 2017

Upload: others

Post on 24-Dec-2021

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: SVSD 2015 Bond Program

1  

SVSD 2015 Bond Program         Mount Si High School Replacement Progress Status Report ________________________________________________________________________________

Date:    August 15th, 2017 To:    Ryan Stokes 

Copy:    Carolyn Malcolm, Joel Aune From:    Clint Marsh  Subject:  August 15th Current Progress Status 

Weeks from July 15th to August 15th, as follows:  

New:  

Phase One And Two General Contractor 

Phase One o Surveying For Building Layout Of AREAS F ‐ D And J (No Area I) Continues... 

AREA A ‐ AREA B ‐ AREA C ‐ AREA E ‐ AREA F ‐ AREA D:  Footings And Foundations Have Been Dug Or Being Dug...  Structural Steel Rebar And Steel Are Being Placed And Inspected...  Concrete Has Been Or Is Being Poured In Footings And Foundations...  Footings And Foundations Have Been Or Are Being Backfilled And Compacted...  Underground Utilities Are Being Dug And Installed Where Applicable... 

Sewer ‐ Water ‐ Mechanical ‐ Electrical ‐ Telecommunications  Structural Steel Erection and Steel Decking Continues: 

AREA A ‐ Complete  AREA B ‐ Complete  AREA C ‐ E ‐ F ‐ D ‐ Steel Fabrication In Process 

Concrete Floors Are Being Prepared With Steel Reinforcement Pending Concrete  Steel Stud Roof Parapet Walls Are Being Constructed...  

o Multiple Material Deliveries Continue... o Staffing By Trade Continues To Be Increased As Required... 

 

Previous Relevant Status Items:  Planning,  Visioning,  Education  Specifications,  Schematic Design,  Design Development, Ten Development 

Permits  (as  listed  in  the  September  16th  Status  Report),  Five  Health  Department  Permits,  Labor  & Industries Electrical Permit,  Initial Demolition Projects, Relocation of the Twelve Classroom Portable Wing and TLC Portable, Installation of the Two Double‐Wide Temporary Portables, Silt Fence Installation, Surface Water  Management  Structures  Installed,  Temporary  Perimeter  Fencing  Installed,  Trucking  Haul  Roads Constructed,  Crane/Probe  Assemblies  Completed,  Temporary  Parking  Lot  Constructed,  Old  Parking  Lot Demolished, Construction Documents and Constructability Review Complete, GC Phase 1 & 2 Bid Process Complete, Temporary Retaining Wall, Temporary Sewer, Temporary Storm Lines, Permanent Water Line, Pad Sub‐Grade Established, Soil Haul Out, Rock Spall Import, Phase One Building Permits (5‐4‐2017), 3,519 Stone Column Installations, and Phase 1 & 2 General Contractor Mobilization Complete.  

Future Activities:  ‐ Phase Two City Building Permit ‐ Permit Issue Pending  

Attachments: Spee West 8‐4‐2017 NE & 8‐11‐2017 NE Aerial Photos Spee West 8‐4‐2017 SE & 8‐11‐2017 SE Aerial Photos Progress Photos ‐ July 2017 & August 2017 

Page 2: SVSD 2015 Bond Program

Mt Si High School8/4/2017

Page 3: SVSD 2015 Bond Program

Mt Si High School8/4/2017

Page 4: SVSD 2015 Bond Program

Mt Si High School8/11/2017

Page 5: SVSD 2015 Bond Program

Mt Si High School8/11/17

Page 6: SVSD 2015 Bond Program

SSnnooqquuaallmmiiee VVaalllleeyy SSDD -- PPiiccttuurreess TTaakkeenn:: JJuullyy//AAuugguusstt 22001177 --VVaarriioouuss TTiimmeess Mount Si High School Replacement Project - Phase 1 Progress Photographs

Page 1 of 1 Pages

Flying In And Setting Roof Beams-Area A Steel Floor Decking & Brace Frames-Area A Setting First Floor Beams-To Area B

Retaining Wall/Electrical Room-Area B Steel & Decking-Area B ...More Steel-Area B

Brace Frames & Steel Decking-Area A Steel Erection & Steel Decking-Area B/SE Steel Erection/Steel Frame-Area B/S

Steel Erection/Steel Decking -Area B/SW Steel Erection -Area B/NW Steel Erection-Area B-Area A/N