swaziland - manzini to mbadlane (mr3) highway project ... · iv project summary project overview 1....

33
AFRICAN DEVELOPMENT BANK SWAZILAND MANZINI TO MBADLANE (MR3) HIGHWAY PROJECT APPRAISAL REPORT OITC DEPARTMENT May 2014

Upload: others

Post on 22-Mar-2020

14 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Swaziland - Manzini to Mbadlane (MR3) Highway Project ... · iv PROJECT SUMMARY Project Overview 1. The Manzini-Mbadlane Highway Project in Swaziland entails the dualisation of an

AFRICAN DEVELOPMENT BANK

SWAZILAND

MANZINI TO MBADLANE (MR3) HIGHWAY PROJECT

APPRAISAL REPORT

OITC DEPARTMENT May 2014

Page 2: Swaziland - Manzini to Mbadlane (MR3) Highway Project ... · iv PROJECT SUMMARY Project Overview 1. The Manzini-Mbadlane Highway Project in Swaziland entails the dualisation of an

TABLE OF CONTENTS

1 STRATEGIC THRUST & RATIONALE .................................................................................................... 1

1.1 PROJECT LINKAGES WITH COUNTRIES STRATEGIES AND OBJECTIVES ................................... 1

1.2 RATIONALE FOR BANK’S INVOLVEMENT............................................................................... 1

1.3 DONORS COORDINATION ....................................................................................................... 2

2 PROJECT DESCRIPTION ........................................................................................................................... 3 2.1 PROJECT DEVELOPMENT OBJECTIVES ................................................................................... 3

2.2 PROJECT DESCRIPTION AND COMPONENTS ........................................................................... 3

2.3 TECHNICAL SOLUTION RETAINED AND OTHER ALTERNATIVES EXPLORED ........................... 4

2.4 PROJECT TYPE ........................................................................................................................ 5

2.5 PROJECT COST AND FINANCING ARRANGEMENTS ................................................................. 5

2.6 PROJECT’S TARGET AREA AND BENEFICIARIES ..................................................................... 7

2.7 PARTICIPATORY PROCESS FOR PROJECT DESIGN AND IMPLEMENTATION .............................. 8

2.8 BANK GROUP EXPERIENCE, LESSONS REFLECTED IN PROJECT DESIGN ................................. 8

KEY PERFORMANCE INDICATORS ....................................................................................................... 8

3 PROJECT FEASIBILITY ............................................................................................................................. 9 3.1 ECONOMIC AND FINANCIAL PERFORMANCE .......................................................................... 9

3.2 ENVIRONMENTAL AND SOCIAL IMPACTS............................................................................. 10

4 IMPLEMENTATION ................................................................................................................................. 13 4.1 IMPLEMENTATION ARRANGEMENTS ................................................................................... 13

4.2 MONITORING ....................................................................................................................... 15

4.3 GOVERNANCE ...................................................................................................................... 15

4.4 SUSTAINABILITY .................................................................................................................. 15

4.5 RISK MANAGEMENT ............................................................................................................. 17

4.6 KNOWLEDGE BUILDING ....................................................................................................... 18

5 LEGAL INSTRUMENTS AND AUTHORITY ......................................................................................... 18 5.1 LEGAL INSTRUMENT ............................................................................................................ 18

5.2 CONDITIONS ASSOCIATED WITH BANK’S INTERVENTION .................................................... 18

6 RECOMMENDATION .............................................................................................................................. 19 APPENDIX I: SWAZILAND COMPARATIVE SOCIO-ECONOMIC INDICATORS ......................................... I

APPENDIX II TABLE OF AFDB’S PORTFOLIO IN THE COUNTRY ......................................................... II

APPENDIX III RELATED PROJECTS FINANCED BY THE BANK AND OTHER DONORS, 2014 .............. III

APPENDIX IV: DETAILS OF PROJECT COST ....................................................................................... IV

APPENDIX V: PROJECT MAP .............................................................................................................. V

Page 3: Swaziland - Manzini to Mbadlane (MR3) Highway Project ... · iv PROJECT SUMMARY Project Overview 1. The Manzini-Mbadlane Highway Project in Swaziland entails the dualisation of an

i

Currency Equivalents As of February.2014

Swaziland 1 UA = 1.53 USD

1 USD = 11.28 Emalangeni (E)

Fiscal Year

Swaziland: 01 April – 31 March

Weights and Measures

1 metric ton = 2204 pounds (lbs)

1 kilometer (km) = 0.62 mile

1 hectare (ha) = 2.471 acres

Page 4: Swaziland - Manzini to Mbadlane (MR3) Highway Project ... · iv PROJECT SUMMARY Project Overview 1. The Manzini-Mbadlane Highway Project in Swaziland entails the dualisation of an

ii

LIST OF ABBREVIATIONS

ADB African Development Bank

ADF African Development Fund

ADDF Abu Dhabi Development Fund

ARAP Abbreviated Resettlement Action Plan

BADEA Arab Bank For Economic Development In Africa

CC Climate Change

ESIA Environmental and Social Impact Assessment

ESMP Environmental and Social Management Plan

EU The Commission of European Union

GBV Gender-Based Violence

GOKS Government of Swaziland

HGV Heavy Goods Vehicle

JAS Joint Assistance Strategy

MDG Millennium Development Goals

MIC Middle Income Country

MTP Medium Term Plan

MTS Medium Term Strategy

NERCHA The National Emergency Response Council on HIV and AIDS

NDS National Development Strategy

MPWT Ministry of Public Works and Transport

OFID OPEC Fund for International Development

OPRC Output-and Performance-based Road Contract

PAP Project Affected People

PCN Project Concept Note

PDR Preliminary Design Report

PRSP Poverty Reduction Strategic Paper

PRSAP Poverty Reduction Strategy and Action Programme

QCBS Quality and Cost Based Selection

RD Road Department

REC Regional Economic Community

RISP Regional Integration Strategy Paper

RMC Regional Member Country

SADC Southern African Development Community

SEA Swaziland Environmental Authority

STI Sexually Transmitted Infection

TA Technical Assistance

TAF Technical Assistance Fund

TOR Terms of Reference

UA Units of Account

UNCTAD United Nations Conference On Trade And Development

Page 5: Swaziland - Manzini to Mbadlane (MR3) Highway Project ... · iv PROJECT SUMMARY Project Overview 1. The Manzini-Mbadlane Highway Project in Swaziland entails the dualisation of an

iii

Loan Information

Client’s information

BORROWER: THE KINGDOM OF SWAZILAND

EXECUTING AGENCY(S): ROADS DEPARTMENT (MINISTRY OF PUBLIC WORKS

AND TRANSPORT)

Financing plan

SOURCE Amount (in millions)

Instrument Emalangeni (E) (USD) (UA)

Government 309.8 27.5 18.0 Counterpart contribution

AfDB (ADB) 517.7 45.9 30.0 Project Loan

AfDB (ADB MIC) 20.6 1.8 1.2 Technical Assistance Grant

BADEA 112.8 10.0 6.5 Project Loan

ADDF 203.0 18.0 11.8 Project Loan

KUWAIT FUND 157.9 14.0 9.1 Project Loan

OFID 169.2 15.0 9.8 Project Loan

TOTAL COST 1,491.0 132.2 86.40

Bank Group key financing information

FINANCING DETAILS LOAN MIC GRANT

LOAN CURRENCY United States Dollar (USD) UA

LOAN TYPE Enhanced Variable Spread Loan

LENDING RATE1 Base Rate + Funding Cost Margin + Lending Spread

BASE RATE2 Floating Base rate with free option to fix the Base rate.

LENDING SPREAD 60 basis points (0.60%) per annum N/A

REPAYMENT Semi-Annual N/A

TENOR Up to 20 years N/A

GRACE PERIOD3 Up to 5 years N/A

NPV (BASE CASE) USD54 million

EIRR (BASE CASE) 21.9% 1”Funding Cost Margin" means the six-month adjusted average of the difference between: (i) the refinancing rate of the Bank as to the

borrowings linked to 6-month LIBOR and allocated to all its floating interest loans denominated in USD; and (ii) 6-month LIBOR ending on

30 June and on 31 December. This spread shall apply to 6-month LIBOR which resets on 1 February and on 1 August. The Funding Cost

Margin shall be determined twice per year on 1 January for the semester ending on 31 December and on 1 July for the semester ending on

30 June; 2”Floating Base Rate" means the six (6)-month LIBOR denominated floating rate, set on each LIBOR Reset Date; Fixed Base Rate Date"

means any date, subsequent to the date on which the Minimum Interest Rate Fixing Amount is attained, on which the Bank – upon the request of the Borrower – calculates the Fixed Base Rate; 3"Grace Period" means the five (5) year period commencing from the Date of Signature of this Agreement during which only the interest

shall be payable except in the event of the acceleration of maturity of the Loan, at which time the principal together with interest shall be payable;

Timeframe - Main Milestones (expected)

Concept Note Approval 28 February 2014

Project Approval 28 May 2014

Effectiveness 31 December 2014

Last Disbursement 31 December 2019

Project Completion 30 June 2018

Last Repayment 31 December 2034

Page 6: Swaziland - Manzini to Mbadlane (MR3) Highway Project ... · iv PROJECT SUMMARY Project Overview 1. The Manzini-Mbadlane Highway Project in Swaziland entails the dualisation of an

iv

PROJECT SUMMARY Project Overview

1. The Manzini-Mbadlane Highway Project in Swaziland entails the dualisation of an

existing 30km single carriageway road between the city of Manzini and Mbadlane on the

MR3, a major road on the SADC regional network. The project is in two parts and financed

by loan and grant facility. The main part, which will be financed by the loan, is composed of

activities directly related to the delivery of the project road. The second part is Technical

Assistance services, to be financed by a grant facility.

2. The activities for the project road comprise: (i) carriageway upgrade of existing 30km

two-lane single paved carriageway to a two-lane dual carriageway and (ii) construction of a

new 32km two-lane single carriageway access and rural connecting roads and interchanges;

(iii) rural feeder road access to health services; (iv) implementation of environmental and

social measures, and; (v) implementation of institutional reform in the road subsector.

3. The estimated cost of the project is USD132.2 million (UA86.4 million; E1,491million)

funded through a co-financing arrangement between the Bank, Government of the Kingdom

of Swaziland (GOKS), Kuwait Fund, BADEA, Abu Dhabi Development Fund (ADDF) and

OFID. The Bank’s contribution comprises: (i) a loan of USD45.9 (UA30.0million), sourced

from sovereign ADB window, equivalent to 34.7% of the project cost, and; (ii) a grant of

UA1.2million (1.4%) from the MIC Technical Assistance Fund. The Government contributes

USD27.5 (20.8%) and the co-financiers in aggregate contribute USD 57.0million (43.1%) of

project cost.

4. The expected outcomes of this intervention include: (i) increased trade activities; (ii)

increased mobility of traffic; (iii) reduced transport and trade cost; (iv) job creation; (v)

improved access to health services, and; (vi) knowledge enhancement and capacity building.

The direct beneficiaries are the rural population (70% of the population) that depend on the

agro-based trade, the industrial and service sectors, the urban population and businesses of

the city of Manzini, and vulnerable rural communities with limited access to health facilities.

Needs Assessment

5. The Kingdom of Swaziland has a population of about 1.2 million (2012 census) and a

lower middle income country with manufacturing, services, wholesale/retail trading,

agriculture and transport as the main GDP growth drivers. The agricultural sector is the main

source of income for more than 70 % of the population providing the raw materials for

dominant agro-based manufacturing industries. Swaziland is ranked third on intra-regional

trade within the SADC region and absorbs about 90% of its agro-based export. The agro-

industry is therefore its primary source of revenue through trade (export) and the road

subsector, particularly the MR3, is the vital link in the supply and value chain. The MR3 is

designated as a SADC regional road and the main east–west strategic link between the major

cities of Mbabane, Manzini, industrial areas of the country. In addition, the MR3 serves as

the major regional road link to Swaziland’s prime market of South Africa and to international

market through Mozambique via the port of Maputo.

Bank’s Added Value

6. Swaziland’s primary trunk road network is key for development and the Bank has

significant experience in developing the road infrastructure to support its key industries and

trade. To date, the Bank has financed significant part of this network, each intervention

strategically selected to maximize benefits. The project map (Appendix V) illustrates the

strategic interventions and the economic growth drivers. Complementing the interventions in

Page 7: Swaziland - Manzini to Mbadlane (MR3) Highway Project ... · iv PROJECT SUMMARY Project Overview 1. The Manzini-Mbadlane Highway Project in Swaziland entails the dualisation of an

v

the agro-business sector, the Bank’s added value arises from the interventions on trade routes

to improve regional connectivity with markets. The Bank has financed studies targeted at

instituting sector reforms and supported training programs and skills development to enhance

capacity. In addition to improving hard infrastructure, this intervention builds on the past

experiences by providing technical assistance to address the institutional challenges to

safeguard long term investments. The Bank also leverages its competency and relevance in

the sector to attract development financial institutions to collaborate on projects. Sharing

experiences gained by working with member states with established sectoral institutional

structures is an invaluable contribution by the Bank in assisting the country in implementing

sector reforms. Gender-based intervention has also been integrated to the project in an area

that contributes to reducing maternal mortality in Swaziland by improving access to local

clinics for a selective number of vulnerable communities.

Knowledge Management

7. The MR3 is critical to economic development and this project enhances its functionality.

This project utilises the knowledge to date to address softer challenges and also leverages

national and institutional knowledge on gender equity to design appropriate social

intervention. The project intervenes in the area of sector reforms, institutional strengthening

and capacity building evolving from the recommendations of bank-funded initiatives (e.g.

Transport Master Plan, 2014) and past projects.

Page 8: Swaziland - Manzini to Mbadlane (MR3) Highway Project ... · iv PROJECT SUMMARY Project Overview 1. The Manzini-Mbadlane Highway Project in Swaziland entails the dualisation of an

vi

MANZINI TO MBADLANE (MR3) HIGHWAY PROJECT: Results Based Logical Framework

Country and project name: The Kingdom of Swaziland: Manzini to Mbadlane Highway Project

Purpose of the project: To improve the standard/quality of the road linking Manzini and Mbadlane.

RESULTS CHAIN

PERFORMANCE INDICATORS MEANS OF

VERIFICATI

ON

RISKS / MITIGATION MEASURES Indicator (including CSI)

Baseline Target

IMP

AC

T

Increase in intra-regional trade (predominantly

sugar) within the SADC (SACU) region contributing to economic growth and poverty

reduction

Increase of trade volume (exports) to

the SADC (SACU) region.

143,000 Metric Tons

(2013, 0-6months)

160,000 Metric tons.

(2019/20; 0-6months)

Ministry of

Commerce, Industry & Trade;

SADC/ SACU data

, COMTRADE

Risks:

Lack of capacity and structure to implement sustainability

measures

Inadequate financial provisions for maintenance.

Non-implementation of effective sector reforms

Mitigation measure:

Medium to long term measures being implemented Project is facilitating implementation of sector reforms

covering institutional strengthening, road funding, capacity building, private sector participation.

OU

TC

OM

ES

Increased in trade traffic (HGV traffic) Av % of HGV to total traffic 15.2% (2013) >20% (2020) Traffic count & O/D survey reports;

Swaziland Road Safety Council

reports

Increased mobility to/from commercial/ economic centres and social facilities

AADT (Manzini-MR8 intersection )

12,500 (2013); 16,800 (2020)

Improved access of urban commuter traffic Average journey time for mini-buses 45mins; (2013) 32mins; (2020)

Contribute to the reduction in road accident rates on the Manzini to Mbadlane road.

No. of fatalities and serious injuries Fatalities: 22 (2013) Serious injuries: 58 (2013)

Fatalities: less than 10 Serious injuries:58 (2020)

OU

TP

UT

S

Dualing of 30km of the MR3 and access and

service road Km of road constructed 0km (2014) 75km (2018) Bank supervision

mission reports.

/Project quarterly

and completion reports/Ministry of

Health

Risks

Project start-up delays due to procurement and compensation related issues.

Inadequate skills and project management capacity of MWPT to effectively manage project.

Mitigating Measures

Close coordination between Bank and MPWT on procurement and project management support

Detailed collaboration amongst all project parties.

Training of MWPT staff on Project Management and TA provided on road management /contracting methodologies.

Construction of service and access roads Km of service and access roads 0km (2014) 32km (2018)

Rehabilitated feeder road access to health

services

No. of communities connected to local

health centres n/a

Minimum of two (2)

community sites

Road safety sensitisation No. road safety roadshows held 0 (2014) 2no. (2018)

Construction of roadside market facilities No of road side market. 0 2 Government/Donor

Reports

HIV/AIDS sensitisation and gender sensitization

No of GBV community sensitisation

sessions No of HIV/AIDS sensitisation sessions

0 (2014)

0 (2014)

>2no. sessions

>4no. sessions

Gender

Coordination Unit NERCHA,

PAPs Compensation and resettlement No. of PAPs compensated n/a 75 PAPs (2015) Approved ARAP

Training of MPWT staff on OPRC, PPP No. of persons trained (No of women) 0 25 staff trained (>10no women)

Swazi locals employed by the project No of jobs (% women/men) 0 500 min jobs (20/80)

A.

KE

Y A

CT

IVIT

IES

COMPONENTS INPUTS

A. Civil Works: All work activities in the construction of pavement, road and drainage structures and ancillaries; UA 65.88 million

B. Consulting Services: (i) Comprises pre-construction services (procurement support); construction supervision; technical and

financial audits; capacity building/training; Road safety audits; project management support

UA 3.31 million

C. Implementation of ESMP and sensitisation programmes on Gender, HIV/AIDs, Road Safety UA 0.17 million

D. Compensation and resettlement measures for PAPs UA 1.91 million

E. Weighbridge and axle load control measures UA 0.70 million

F. Rural community (feeder road) access to health services UA 0.58million

G. Technical Assistance (MIC grant) UA 1.02 million

UA 73.57 million (base cost) UA 86.4 million (incl. contingencies)

Page 9: Swaziland - Manzini to Mbadlane (MR3) Highway Project ... · iv PROJECT SUMMARY Project Overview 1. The Manzini-Mbadlane Highway Project in Swaziland entails the dualisation of an

vii

Indicative Project Time Frame

ID Task Name

1 Project Processing for Loan Approval

5 Loan Signature

6 Publication of GPN

7 RESSETTLEMENT AND COMPENSATION

9 Consultanct Services: Pre Contract Services & Construction Supervision

10 Procurement of Consultancy Services

28 Execution - Pre-Construction Services

29 Execution - Construction Supervision

30 Civil Works

31 Works Prequalification

39 Procurement

47 Execution of Works (excl DLP)

48 Technical Assistance: Project Management Support and Training

68 Technical Assistance Establishment of Road Authotity and Road Fund

28/05/14Project Processing for Loan Approval

26/06/14

05/06/14

RESSETTLEMENT AND COMPENSATION

Consultanct Services: Pre Contract Services & Construction Supervision

Procurement of Consultancy Services

Execution - Pre-Construction Services

Execution - Construction Supervision

Civil Works

Works Prequalification

Procurement

Execution of Works (excl DLP)

Technical Assistance: Project Management Support and Training

Technical Assistance Establishment of Road Authotity and Road Fund

Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 22014 2015 2016 2017 2018 2019

Page 10: Swaziland - Manzini to Mbadlane (MR3) Highway Project ... · iv PROJECT SUMMARY Project Overview 1. The Manzini-Mbadlane Highway Project in Swaziland entails the dualisation of an

1

REPORT AND RECOMMENDATION OF THE MANAGEMENT TO THE BOARD OF

DIRECTORS ON PROPOSED LOAN AND GRANT TO THE KINGDOM OF SWAZILAND

FOR THE MANZINI TO MBADLANE (MR3) HIGHWAY PROJECT

Management submits the following Report and Recommendation on a proposed loan for USD 132.2

million (UA 30.0 million) to the Kingdom of Swaziland to finance the Manzini-Mbadlane (MR3)

Highway Project and a proposed MIC Technical Assistance Fund Grant for UA1.2 million to finance

Technical Assistance services for capacity building and sector reform activities.

1 STRATEGIC THRUST & RATIONALE

Project linkages with countries strategies and objectives 1.1

The development strategies and objectives of the country are prescribed in two main 1.1.1

documents, namely: i) the National Development Strategy (NDS) (1999-2022); ii) the Poverty

Reduction Strategy and Action Programme (PRSAP) (2008-2022). Complementary to these

documents is the roadmap for fiscal structural reforms described in the Fiscal Adjustment Roadmap

(FAR). The linkages of the project with respective country priorities are described below.

By tackling the physical infrastructure and soft components, the project facilitates meeting 1.1.2

specific macro level objectives for development. These are: (i) improving the economic status of

human capital, (ii) enhancing the productivity of its mainly agro-based industries, and (iii) embarking

on real public sector reforms to improve efficiency.

The NDS defines development objectives at macro and sectoral levels. The former is linked 1.1.3

with industrialisation and agriculture development and the latter on, physical infrastructure, gender,

economic services (construction) and social welfare. While it recognises the need to attempt

diversification from dependency on agro-based industries, the agriculture sector will remain the

backbone of the economy. The project contributes to enhancing the competitive advantage of

agriculture sector by facilitating easy access to international and regional markets. It will also

positively impacts productivity of the industries and improves the livelihood of the significant rural

population. The project directly improves connectivity from the industrial hub of Matsapha to the port

of Maputo facilitating growth in international export vis-a-vis export to the SADC region. In addition

to infrastructure, the project provides opportunities for job creation, promotes and generate economic

services particularly in the urban area, and contributes to addressing some of the gender equality

aspects of the population. It also improves access to social welfare facilities such as hospitals and

schools within the project catchment area. The beneficiaries are detailed in Section 2.6

The sector reform intervention of the project aligns with some of the objectives of the 2011-1.1.4

2015 Fiscal Adjustment Roadmap (FAR) and the PRSAP. The FAR aims at medium term reforms in

expenditure control and revenue generation. It outlines the need for structural transformation of public

sector institutions to attract investment, improve efficiency and increase private participation.

Similarly, pillar 6 of the PRSAP iterates improving governance and strengthening institutions. The

alignment with FAR is translated to the sector in the context of effectively managing funding needs

for recurrent expenditure.

Rationale for Bank’s involvement 1.2

The main thrust of the Bank’s lending programme in Swaziland is to support the agenda of 1.2.1

Government to reduce poverty. The financing of this project offers good prospects for achieving this

objective through the development of a vital infrastructure system that supports economic drivers.

Investment rationale in the context of Bank strategies is described below.

Page 11: Swaziland - Manzini to Mbadlane (MR3) Highway Project ... · iv PROJECT SUMMARY Project Overview 1. The Manzini-Mbadlane Highway Project in Swaziland entails the dualisation of an

2

The investment is in line with the Bank’s Ten Year Strategy (2013-22) in respect of 1.2.2

promoting: i) infrastructure development and regional economic integration by leveraging

Swaziland’s natural resources: ii) inclusive development with emphasis on gender mainstreaming and

employment opportunities; iii) institutional capacity enhancement, and; (iv) inherent climate change

mitigating gains from efficient transport operations.

By aligning with (i) and (iii) above, there is explicit consistency with the two pillars of the 1.2.3

Country Strategy Paper (CSP) (2014-2018), namely, Pillar I (Supporting Infrastructure Development

for Sustainable and Inclusive Growth) and Pillar II (Strengthening Governance and Institutional

Capacity), with project emphasis on institutional capacity. The project is listed in the CSP as a project

for the 2014 programme.

The project is well aligned with the two pillars of the Bank’s Southern Africa Regional 1.2.4

Integration Strategy Paper 2011-2015 (RISP), namely, regional infrastructure and capacity building in

support of infrastructure interventions. It is also aligned with the 2005-2019 SADC Regional

Integration Strategic Development Plan (RISDP) priority area of developing regional infrastructure.

Donors coordination 1.3

Donor coordination in Swaziland is typically at national and sectoral levels. At a national, 1.3.1

coordination is led by the Aid Coordination and Monitoring Section (ACMS) of the Ministry of

Economic Planning and Development. Set up in 2009, the ACMS mandate is to ensure aid

effectiveness across all sectors. At sector level, the intensity of the coordination varies by sector with

the dominating sectors being agriculture, health and social. The coordination platforms of health and

social sectors, either standalone or complementary, are the most active with the National Emergency

Response Council on HIV and AIDS (NERCHA) responsible for coordination of the implementation

of multi-sectoral responses to HIV and AIDS. The Swaziland Partnership (SwaP) Forum against

AIDS, a forum for all Development Partners (DP), provides strategic direction to DPs.

Donor portfolio is featured by transport, agriculture, social and health, capacity building and 1.3.2

education sectors with the Bank, the EU and recently the Kuwait Fund and BADEA, active in the

transport sector. The EU traditionally undertake feeder and rural road projects that are linked to their

agricultural projects. The EU, the United States and Global Fund concentrate on the agriculture and

health sectors. Similarly, the UN (UNDP, UNAIDS, UNICEF) focuses on the social and health sectors

as well as environment and climate change. Other participating donors include the World Bank, JICA,

China and Taiwan. At present, the EU is the only resident donor while USAID is expected to assume

residency by the end of 2014. Other donors including the Bank operate from South Africa. In addition,

common objectives of the Paris Declaration and Millennium Development Goals (MDG) bind donors

to the common cause through the OECD’s Development Assistance Committee although, in general,

donors are nominated or volunteer to lead in selected sectors in which they are most active. There is

no formal coordination platform for the transport sector and this intervention presents an opportunity

for transport to be featured in the coordination agenda. The implementation of this project will trigger

closer coordination between donors in which the Ministry of Public Works and Transport (MPWT),

through the ACMS, will play a key role. Some coordination is currently underway and had

contributed to the appraisal of this project. It is envisaged that the coordination platform will evolve

and take shape during implementation and project supervisions. As a signatory to the SADC protocol

on Transport Communication and Meteorology, MPWT is responsible for coordinating and

harmonizing regional projects with the mandate of SADC Secretariat.

Page 12: Swaziland - Manzini to Mbadlane (MR3) Highway Project ... · iv PROJECT SUMMARY Project Overview 1. The Manzini-Mbadlane Highway Project in Swaziland entails the dualisation of an

3

Table 1.1: Aid Coordination

Sector or subsector Size

GDP Exports Labor Force

Transport 7.5%*

Players - Public Annual Expenditure (average)**

Government Donors

[UA m] [UA m]

243 225 %

AfDB <1%

World Bank 7%

China and Taiwan 52%

EU 23%

UN (FAO, UNDP, UNFPA,

UNICEF)

US (PEPFAR) 10%

Japan 3%

BADEA

Global Fund

Kuwait Fund

Level of Donor Coordination

Existence of Thematic Working Groups Yes

Existence of SWAPs or Integrated Sector Approaches Yes

AfDB's Involvement in donor coordination*** Yes, M

* average of the last five years (2007 – 2011) for transport and storage (source: Africa Economic Outlook)

** Average of (2007 to 2011). *** L: leader, M: member but not leader, none: no involvement

2 PROJECT DESCRIPTION

2.1 Project Development Objectives

2.1.1 At sector level, the development objective is to improve regional interconnectivity thus

improve efficiency within the trade value-chain, particularly on exports, to increase trade flow and

generate revenue for the country and thus reduce poverty. Similarly, improved mobility to the urban

centre will enhance economic activities in the urban environment by boosting the productivity of the

service and retail sectors.

2.1.2 Project level development objectives will include reducing vehicle operating cost on the route

and improve mobility. The project will have a positive impact on: (i) road safety by mitigating

unacceptable road accidents on the MR3; (ii) improve trading activities of road side markets to

enhance income generation; (iii) gender-balanced job opportunities for skilled and unskilled labour for

Swazis; (iv) contribute towards reduction in maternal mortality by improve rural access to local health

services and; (v) through sensitisation, contribute to the efforts on mitigating HIV/AIDS prevalence

and Gender-Based Violence (GBV).

2.2 Project Description and Components

2.2.1 The Manzini-Mbadlane Highway Project is in two parts and financed by loan and grant

facility. The main part is associated with the delivery of the project road and associated infrastructure.

The second part is grant-funded Technical Assistance services on softer intervention that will facilitate

development of Bank pipeline and address sector-wide challenges. Detailed cost information appendix

IV.

Page 13: Swaziland - Manzini to Mbadlane (MR3) Highway Project ... · iv PROJECT SUMMARY Project Overview 1. The Manzini-Mbadlane Highway Project in Swaziland entails the dualisation of an

4

Table 2.1- Description Project Components

COMPONENT NAME USD

(m) UA (m)

COMPONENT DESCRIPTION

1 Civil works 100.80 65.88

Dualing of existing 30km main carriageway and construction of

32km service and access road, with associated infrastructure,

utilities and services including ICT ducting;

2 Consultancy services 5.06 3.31

Comprise: a) design review, pre-construction services,

construction supervision; b) financial audit services; c) technical

audits services; d) Project management support services to

project team. Services include short term procurement

consultant; project financial management expert; and project

management expert; e) independent road safety audits. The

safety audits will form part of the design review activity above.

3 Implementation of ESMP 0.27 0.17

This will be implemented as part of the responsibilities of the

civil works and comprise:

a) a minimum of two (2) community sensitisation sessions on

gender-based violence; b) a minimum of four (4) sensitisation

sessions on HIV/AIDS; c) two (2) road safety roadshows in the

city of the Manzini; d) all environmental and social measures as

stipulated in the ESMP

4 Resettlement and

Compensation. 2.93 1.91 Resettlement and compensations of 75 PAPs.

5 Community feeder road 0.89 0.58 Improvement of rural (feeder road) access to local health

services (see section 2.2.2)

6 Axle Load Control

(weighbridge) 1.06 0.70

Comprise: a) construction of weighbridge; b) Development and

deployment of axle load control operational measures and

procedures.

7

Technical Assistance

Services (MIC grant

funded)

1.56 1.02

To be funded by MIC grant, comprise implementation of the

following:

a) Sector Reforms: Establishment and institutionalisation of

the Roads Authority and the Road Fund (UA0.88million); b)

Training of MPWT personnel on OPRC methodologies and

Public-Private Partnerships (UA0.14million).

TOTAL BASE COST 112.57 73.57

2.2.2 The project includes a feeder road component (item 5 in table 2.1) aimed at improving selected

number of existing impassable gravel roads and tracks that link rural communities to their local rural

health clinics. This is to contribute towards addressing some of the transport-related and time-critical

vulnerabilities of expectant mothers in the rural areas. The intervention will target the zone of

influence project road within the Manzini and Lubombo districts. Further information is provided in

Gender section of Section 3.2 (Environmental and Social Impacts).

2.3 Technical solution retained and other alternatives explored

2.3.1 Two technical design solutions and a financing alternative were considered. The technical

solutions, which were based on lane configuration were: (i) the number of lanes for the main MR3

carriageway, and; (ii) dedicated alignment for urban and local/rural service road. The retention of the

existing asphalt concrete pavement type has been justified in the light of current traffic load.

2.3.2 Carriageway configuration: The dual carriageway option was chosen for the entire route as

opposed to dualing the urban section i.e. Manzini circle (0km) to MR8 intersection (km7) only, where

the traffic is heaviest and mostly urban. The choice to dual the entire road was based on road

geometry, heavy trucks, road safety and percentage growth of traffic. In addition, long term

expectations and generated traffic from the operations of the new Sikhuphe International Airport (not

Page 14: Swaziland - Manzini to Mbadlane (MR3) Highway Project ... · iv PROJECT SUMMARY Project Overview 1. The Manzini-Mbadlane Highway Project in Swaziland entails the dualisation of an

5

yet operational) had been considered.

2.3.3 Access road: The socio-economic environment of the project encompasses urban, residential,

commercial, social and agriculture development and facilities, each with its own access needs. To

ensure sustained functionality, safety and efficiency of the infrastructure, the project design segregates

local traffic from MR3 thoroughfare traffic. This reduces the adverse impact of mixed vehicular and

pedestrian traffic in urban area, improves the vehicle flow of thoroughfare and trade traffic,

complements urban development plans for Manzini city and improves the quality of living conditions

in the urban environment.

2.3.4 Financing options: As part of the efforts to reform the road subsector towards sustainability of

investment, procuring projects through public private partnership (PPP) financing has been one of the

approaches considered by government for future projects. Although the framework for such financing

is yet to be fully developed, the Manzini-Mbadlane Highway Project was a potential candidate. This

was considered in the spirit of widely adopting a user-pay principle for the MR3, given the high traffic

volume. However, project priority against the long development period for PPP structuring,

compounded by the lack of institutional capacity and an established framework, was the reason for

deferring this option. The government nonetheless remains committed to developing PPP project

financing specifically for the MR3 as part of its reform programme. The Manzini Bypass, currently

being designed, and the existing MR3 Mbabane Bypass and Mbabane-Ezulwini-Matsapha (both

previously Bank-funded projects), have been ear-marked as potential candidates for future tolling. The

proposed training on PPP and contracting methodologies helps government meet some of its

aspiration.

2.4 Project type

2.4.1 The project falls under the Bank’s investment programme on transport infrastructure

operations. It is a standalone project being financed by loan and grant facilities of the Bank and the

activities are well-defined works and implementation of economic and social measures. The grant will

finance Technical Assistance activities commensurate of the requirements of the Fund.

2.5 Project cost and financing arrangements

2.5.1 The estimated project cost (net of taxes/duties including contingencies) is USD132.2 million

(UA86.4 million) of which 76% is foreign exchange (Table 2.2). The project will be co-financed with

Government and with Kuwait Fund, BADEA, Abu Dhabi Development Fund and OFID, participating

collectively. Bank loan and grant component will be sourced from the sovereign ADB window and

Middle Income Country (MIC) Technical Assistance Fund, respectively.

Page 15: Swaziland - Manzini to Mbadlane (MR3) Highway Project ... · iv PROJECT SUMMARY Project Overview 1. The Manzini-Mbadlane Highway Project in Swaziland entails the dualisation of an

6

Table 2.2 – Total Project Cost Estimates by Component (Net of Taxes)

FE= 3%; LC: 6%

2.5.2 The co-financing arrangement with the development partners will be on parallel financing

basis. It entails: (i) the Bank and GOKS jointly co-financing km0 to km13, designated as Lot 1; and

(ii) GOKS and other Development Partners (described above) jointly co-financing km13-km30,

designated as Lot 2. Detailed cost breakdown by component, lot and funding source is provided in

Appendix IV.

2.5.3 The contribution of the project by funding source is illustrated in Table 2.3 The Bank’s loan

contribution is USD45.9 million (UA30.0million), equivalent to 34.7% of project cost, and a

UA1.2million grant. The Government counterpart contribution is 20.8% and the grouped funding of

Kuwait Fund, BADEA, ADDF and OFID constitutes 43.1% of project cost.

Table 2. 3 - Sources of Financing

SOURCE Contribution (in millions) % Total

USD (UA)

Government 27.5 18.0 20.8%

AfDB (ADB) 45.9 30.0 34.7%

AfDB (ADB MIC) 1.8 1.2 1.4%

Sub total 47.7 31.2 36.1%

*BADEA 10.0 6.5 7.6%

*ADDF 18.0 11.8 13.6%

*KUWAIT FUND 14.0 9.1 10.6%

*OFID 15.0 9.8 11.3%

Subtotal 57.0 37.2 43.1%

TOTAL 132.2 86.4 100% * co-financiers group funding

2.5.4 The project cost by procurement category and expenditure schedule are shown in Tables 2.4

and 2.5.

UA millions USD (million)

Components

Foreign

Exchange

Local

Currency Total Costs

Foreign

Exchange

Local

Currency Total Costs %Foreign

Civil Works 53.17 12.71 65.88 81.35 19.45 100.80 80%

Consultancy Services 2.60 0.71 3.31 3.97 1.09 5.06 79%

Implementation of ESMP 0.00 0.17 0.17 0.00 0.27 0.27 0%

Resettlement & Compensation 0.00 1.91 1.91 0.00 2.93 2.93 0%

Weighbridge 0.35 0.35 0.70 0.53 0.53 1.06 50%

Feeder Road 0.00 0.58 0.58 0.00 0.89 0.89 0%

Technical Assistance Services 0.82 0.20 1.02 1.25 0.31 1.56 80%

Base Cost 56.94 16.63 73.57 87.1 25.47 112.57 77%

Physical 5.69 1.66 7.35 8.71 2.55 11.26

Subtotal 62.63 18.29 80.92 95.81 28.02 123.83

Price contingency 2.92 2.56 5.48 4.49 3.88 8.37

TOTAL 65.55 20.85 86.40 100.3 31.9 132.2 76%

Page 16: Swaziland - Manzini to Mbadlane (MR3) Highway Project ... · iv PROJECT SUMMARY Project Overview 1. The Manzini-Mbadlane Highway Project in Swaziland entails the dualisation of an

7

Table 2.4 – Project Total Cost by category of expenditures (UA Million)

Category

Foreign

Exchange

Local

Currency Total Costs %Foreign

Works 53.52 13.64 67.16 80%

Services 3.42 0.91 4.33 79%

Miscellaneous 0.00 2.08 2.08 50%

Base Cost 56.94 16.63 73.57 77%

Physical 5.69 1.66 7.35

Subtotal 62.63 18.29 80.92

Price contingency 2.92 2.56 5.48

TOTAL 65.55 20.85 86.40 76%

Table 2.5 – Total Expenditure schedule by component (UA Million)

Components 2014/15 2015/16 2016/17 2017/18 2018/19 Total

Civil Works 0.00 9.82 23.09 26.41 6.56 65.88

Consultancy Services 0.17 0.66 0.99 0.99 0.50 3.31

Implementation of ESMP 0.00 0.09 0.03 0.03 0.02 0.17

Resettlement & Compensation 0.95 0.96 0.00 0.00 0.00 1.91

Weighbridge 0.00 0.11 0.24 0.28 0.07 0.70

Feeder Road 0.00 0.15 0.17 0.17 0.09 0.58

Technical Assistance 0.10 0.42 0.20 0.20 0.10 1.02

Base Cost 1.22 12.21 24.72 28.08 7.34 73.57

Physical 0.12 1.22 2.47 2.81 0.73 7.35

Subtotal 1.34 13.43 27.19 30.89 8.07 80.92

Price contingency 0.00 2.28 1.87 1.10 0.23 5.48

TOTAL 1.34 15.71 29.06 31.99 8.30 86.40

2.6 Project’s Target area and Beneficiaries

2.6.1 The Manzini-Mbadlane Road Project serves the Manzini city, the commercial hub of

Swaziland. The city provides employment to more than 250,000 Swazis who would directly benefit

from the project in terms of economic activities and travel cost and time. The road also connects to the

main tourist and social infrastructure situated in Manzini municipality and directly linked to South

Africa, its largest trading partner and socially-integrated neighbour. The project provides easy access

to the new international airport serving the entire population. The road facilitates easy access

workplace by taxis, cars, and other public transport. There are other small scale commercial and

agriculture activities along the project road. The new road will help in the delivery of supplies and

inputs as well as provide accessibility to potential buyers.

2.6.2 Matsapha is the industrial heartland of the Kingdom with broad manufacturing base for

textiles, metal works, food processing, paper mills, engineering works, beverage processing, building

and construction, and others. It provides employment to more than 30,000 Swazis across the

employment spectrum including market trading. The project road will enhance current access for the

trading industries and will benefit the population of Matsapha. The sources of raw material for these

industries are the farming communities along the corridor will therefore benefit from the increased

activities within the supply chain.

2.6.3 Beyond the project geographic boundaries, the sugar development projects by government and

donors (currently the EU) east of the country in the Lubombo region (see project map), trucks to the

industrial and commercial centres will benefit from quicker access and reduced transport cost. Transit

traffic between Mozambique and South Africa will similarly benefit. The port of Maputo would

experience increased activities at its port as a result of potential growth in exports to international

markets.

Page 17: Swaziland - Manzini to Mbadlane (MR3) Highway Project ... · iv PROJECT SUMMARY Project Overview 1. The Manzini-Mbadlane Highway Project in Swaziland entails the dualisation of an

8

2.7 Participatory process for project design and implementation

2.7.1 The Swaziland Environmental Authority (SEA) directive requires public consultation to be

carried out as part of the ESIA scoping exercise and these were held and minuted on 19th

and 26th

March and 4th June 2010. Subsequent meetings were held during the ESIA preparation exercise. The

make-up of the stakeholders engaged were government institutions, Members of Parliament, local

residents, businesses, Manzini City Council and the traditional authorities of Mafutseni and Malindza.

The local and traditional authorities directly affected by the project were the focus areas of public

engagement. The methodology of engagement was field visits, workshops and meetings. Some of the

issues or concerns expressed at community meetings which have informed the project design,

included (i) employment opportunities, (ii) land expropriation and compensation, (iii) traffic and

personal safety and accesses points (schools, residences, farms, bus/taxi ranks etc.); (iv) loss of

business; (v) project extent, timeframe and impact on planned commercial developments; (vi)

transparency and community awareness of the project activities. A detailed survey and consultation

was carried out for all properties affected by the project and the vetting and valuation process is in line

with the Acquisition of Property Act. The Bank consulted with the local council and donors in the

course of preparing this project.

2.8 Bank Group experience, lessons reflected in project design

2.8.1 The Bank’s total commitments in the transport sector in Swaziland aggregates to UA 127.79

million, covering ten operations (seven projects and three studies), all of which have been completed.

The most recent is the Transport Master Plan, which completed in February 2014. Project Completion

Reports (PCR) on investment are up to date.

2.8.2 The main lessons on past performance of Bank-funded transport sector operations in

Swaziland are: (i) changes in designs during project implementation which led to cost overruns; and

(ii) counterpart contributions towards project costs were higher than envisaged at appraisal as a result

of scope changes. Both lessons are jointly mitigated through design review, a recommendation of

recent PCRs.

2.8.3 Unlike previous projects, the physical environment and terrain at project location is very gentle

hence unchallenging and follows existing alignment with wider road reserve. It is envisaged that the

rationale and concept in providing easy access for local traffic at the onset will eliminate design

changes in the implementation stage, which was a factor in previous projects. Though severe

procurement challenges were not experienced in the past, the Bank’s regional office (SARC) will

organize seminars/workshops to familiarize GOKS with Bank’s procurement procedures on need

basis in order to minimize delays. Support for financial management has been identified as an area

that merits attention and has been addressed by the project.

2.8.4 MPWT, through the RD, has the responsibility for the planning, construction and maintenance

of the road system. Planning, co-ordination and management of road transport investments are

reasonably good, taking into account the human resource constraints. To augment the institutional

capacity of the RD, the project will provide Technical Assistance (TA) to support the project. This

assistance will, among others, strengthen the management, planning and supervisory skills of RD to

manage the project effectively.

Key performance indicators

2.8.5 The project’s performance indicators are provided in the Results Based Logical Framework

(RBLF) including baseline and targets. The indicators include: (i) travel time; (ii) gender equity

sensitizations, (iii) HIV/AIDS sensitization; (iv) indicators of the ESMP; (v) vehicle per day or ADT;

(vi) road accidents; (vii) jobs created; (viii) no of persons trained; (ix) cross border export trade (tons)

and trade traffic (% of total traffic), and; (x) no of sites of feeder roads improved. Other baseline data

will be collected by the supervision consultant and the Executing Agency. Data associated with the

Page 18: Swaziland - Manzini to Mbadlane (MR3) Highway Project ... · iv PROJECT SUMMARY Project Overview 1. The Manzini-Mbadlane Highway Project in Swaziland entails the dualisation of an

9

ESMP will be coordinated between the project and SEA. Data on HIV/AIDS incidences will be

collected by the project by a service provider and coordinated with the Executing Agency and

NERCHA. The data collected will be on knowledge, attitudes and practices, from which to base the

awareness and prevention activities related to the road’s zone of influence, before and after the

project. In identifying the locations for the feeder road intervention, the Executing Agency, in

collaboration with the Ministry of Health, will collect data on maternal-related incidences to support

each intervention.

3 PROJECT FEASIBILITY

3.1 Economic and Financial performance

3.1.1 Traffic analysis carried for this project was necessary to justify the economic benefits of the

investment accrued during the serviceability life of the infrastructure utilizing established design and

maintenance parameters. The primary beneficiaries are the road users, through whom economic

benefits to the country are realized and the objective of the traffic analysis, is to identify all categories

of road-user traffic on the project road in order to quantify benefits.

3.1.2 Classified traffic counts were undertaken at major junctions on the project road and historic

traffic data were reviewed and analyzed. Classified 12 hour traffic counts on the project road were

conducted in November 2009 at twelve (12) locations and updated in August 2013. For the purpose of

the analysis, the project road was divided into four main sections based on traffic characteristics,

starting from the Manzini city circle (section 1), with the heaviest traffic, travelling eastwards to

Mbadlane (section 4). The Annual Average Daily Traffic (AADT) derived and used for the analysis

were 7,779 and 10,440 for the entire road and Lot 1 respectively.

3.1.3 The traffic growth for normal and generated traffic were analysed. Diverted traffic was not

taken into account as there are no viable or competitive alternative routes to the project road. Traffic

growth rates were obtained from the road feasibility study of the project road and past records of

previously funded projects. In the last decade, economic growth has been around 2-3% whereas traffic

growth rates recorded have averaged 5% for cars and light vehicles, about 4% for buses and trucks.

Based on the above forecast, the Average Traffic Growth Rates used for the 20 years post-

construction period were derived. A ramp up of traffic following construction is estimated as 7%p.a

from 3%p.a growth during the construction period and returning to the normal growth of 4%p.a for

each of the consecutive five year periods. In addition to growth in normal traffic, traffic generated by

operations of the new Sikhuphe International Airport had also been considered.

3.1.4 The methodology for the economic analysis was based on the comparison of 'with project' and

'without project' scenarios over a 20 year service life of the road each with a corresponding

maintenance regime. The maintenance interventions for the ‘without project’ approach is annual

routine maintenance, patching and resealing every 5 years. The maintenance interventions for the

‘with’ project road includes routine maintenance, patching and overlay every 8years.

3.1.5 The economic analysis was carried out using the Highway Development and Management

(HDM - IV) model and the viability of the road assessed using the criteria of Economic Internal Rate

of Return (EIRR) and Net Present Value (NPV). The economic costs included construction costs,

routine and periodic maintenance costs, consultancy services and the physical contingency. A

conversion factor of 0.8 was used to derive the economic costs from financial cost. The salvage value

at the end of the 20-year life span was calculated on the basis of the estimated residual value of the

aggregated components of the infrastructure to be 20% of the construction costs. The analysis was

modelled in USD based on a prevailing rate of exchange. Details on the cost is provided in Technical

Annex B7

Page 19: Swaziland - Manzini to Mbadlane (MR3) Highway Project ... · iv PROJECT SUMMARY Project Overview 1. The Manzini-Mbadlane Highway Project in Swaziland entails the dualisation of an

10

3.1.6 The economic return on the total investment based on the quantifiable project economic

benefits and costs, discounted at 12%, during the design life of 20 years is EIRR of 21.9%, with a

NPV of USD52million. The corresponding EIRR and NPV values for the Bank-funded section are

24.8% and US$36million, respectively. The net benefit is USD107million and USD61million for

whole project and Lot 1, respectively. The EIRR in both cases are above the cut-off rate of return of

12% opportunity cost of capital in Swaziland and thus confirms the viability of the intervention in the

project. Detailed information on the analysis is provided in Technical Annex B7.

Table 3.1: Key Economic Results Summary

Scenarios EIRR (Lot 1 and 2)) EIRR (Lot 1)

Base case 21.9% 24.8%

Construction cost (+10%) 20.3% 23.2%

Benefits (-)10% 20.4% 23.7%

Construction cost (+10%) & Benefits (-10%) 18.8% 22.0%

3.1.7 The VOC on the existing project road is estimated at US$ 0.41/km for cars and USD 1.68-

USD 3.01/km for light buses through to trucks and the equivalent weighted average is US$ 1.2/veh-

km, which is reduced to USD 1.07/veh-km when the project opens. The average travel time over the

30km section of the MR3 is reduced by 28% from 45mins hours to 32minutes.

3.1.8 The sensitivity analysis was carried out on three scenarios and are summarised in Table 3.1

with significant margin within the EIRR threshold on each of the variables. The switch values of the

variables, beyond which the project loses its economic viability, i.e. EIRR less than 12% or NPV

being zero or negative, were checked. On cost, the viability of the whole project and Lot 1 could be

threatened if cost is increased by 95%. On benefits, 30% and 45% reduction on the whole project and

Lot 1 respectively could threaten economic viability.

3.2 Environmental and Social impacts

Environment

3.2.1 The project has been validated as category 2 by ORQR on 29 July 2013. The ESMP, prepared

in 2013, was summarized and posted on AfDB’s website on 25 April 2014.

3.2.2 The environmental impacts of project activities would include some of the following:

vegetation clearance; noise and dust pollution; disturbances to the biodiversity and fauna migration;

potential encroachment of archaeological and cultural sites; waste generation from construction,

operation activities and camp activities possibly leading to pollution of soil and ground water; creation

of borrow pits. Construction traffic and use of heavy machinery will give rise to increased risk of

injuries to employees and the public. There is expectation of labour influx and generated vehicular

traffic to the project area which would increase pressure on social and infrastructure services, increase

health risks (STI/HIV/AIDS) and impact on bio-diversity, natural resources such as trees and wildlife.

The country is well served by watercourses and biodiversity, particularly in the rural setting, which

the ESIA makes adequate provisions to preserve or minimize impact.

3.2.3 In general, the contractor will comply with the requirement of the ESMP in mitigating

environmental risks. In addition, the contractor will compile a comprehensive waste management plan

covering all incidences and activities. Some of the mitigation measures to be deployed include

construction of temporary and compliant waste and pollutants (fuel, oils, hazardous substance etc.)

storage and disposal facilities. Enabling works such as vegetation clearance of sites will be planned

and executed by controlled sectioning of sites to ensure rehabilitation or recovery of vegetation post

construction. This will also minimize soil erosion and contamination of watercourse. Storage of

stockpiles of spoil will be controlled so as to minimize washout of spoil, dust pollution and

Page 20: Swaziland - Manzini to Mbadlane (MR3) Highway Project ... · iv PROJECT SUMMARY Project Overview 1. The Manzini-Mbadlane Highway Project in Swaziland entails the dualisation of an

11

sedimentation in water courses. Unprotected roads, particularly temporary diversions and tracks in the

proximity of urban or built up areas, will be watered and speed limits imposed to minimise dust

pollution and assure road safety. The contractor will collaborate with the road safety department of

MPWT in deploying road safety measures that impact the public. Construction noise will be

minimised through the use of well-serviced and efficient plants and equipment. Individual and mature

trees of conservation importance will be marked and avoided, wherever possible. Watercourse will be

monitored for contamination. The contractor will raise awareness among staff and public on fauna and

flora protection. Use of existing borrow-pits and spoil sites will take precedence over new sites which

will undergo environmental assessment (ESIA) prior to use. The overseeing authority, SEA, will

collaborate with the project to ensure compliance with the project’s environmental licence. Further

mitigation measures such as health risks and road safety are addressed in subsequent sections.

Climate change

3.2.4 Swaziland has one of the lowest CO2 emissions among its middle income counterparts at

0.9mt per capita (1.6mt for middle income countries) and marginally above the average of Sub Sahara

Africa of 0.8mt per capita. The major emitters are the industrial and mining sectors with

disproportionate emissions by the transport sector from vehicle-km travelled. The project’s mitigation

and adaptation features are as follows.

3.2.5 Mitigation: Improving vehicle usage and better traffic management which improve vehicle

operational efficiency is an intrinsic feature of the engineering design and will inherently mitigate and

contribute to the reduction in emission. Construction methodology will be scrutinised through control

measures (project specification) to minimise adverse impact. The project will ensure efficient

machinery are used and embark on fuel efficiency awareness campaigns. Waste reduction efforts

during construction will ensure that methane production from waste associated with the project is

reduced, if not avoided. Practical adaptation possibilities of the design, over and above the standard

design practices will be further reviewed during the design review phase against the Bank’s Climate

Change requirements to enhance environmental sustainability.

3.2.6 Adaptation: Climatic conditions used for the design of road infrastructure are generally to

accommodate temperature fluctuations and rainfall patterns which affect the configuration and

structural behaviours of bridges, pavement types and profiles, sizing of drainage structures and

preserving natural habitat. In addition, safety factors are built in the design to accommodate excess

loading conditions. There is no country specific data supporting irregular patterns on each of the

above. However, the engineering design adopted for the project complies with the standards

commensurate with the environment thus has inherent adaptation features. The asphaltic pavement

structure is sound, the bridge configuration and thermal movement are adequately accommodated, the

drainage structures are well designed and provisions made for the migration of animals. Although the

design has taken into account maintainability, a principle for all good designs, the risk to the resilience

of the infrastructure lies in the quality of the maintenance regime planned for the infrastructure.

Therefore appropriate road maintenance is part of the adaptation strategies that this intervention will

facilitate.

Gender

3.2.7 Gender equity and relations are embedded in Swaziland’s constitution and receive significant

attention from development partners. To ensure aid effectiveness, the project design, in lieu of

designing own intervention, is anchored on existing gender programmes that have direct linkage with

the project activities. The project will contribute to addressing employment inequality for women by

earmarking not less than 20% of an expected 500 skilled and unskilled labour force for women and

with preference given to Swazi nationals and locals of both genders. A mechanism for the recruitment

process may be through job fairs in and around the key project area and towns such as Manzini,

Hhelehele, Mafutsemi and Mbadlane. The job and pay distribution will respect the national legislation

Page 21: Swaziland - Manzini to Mbadlane (MR3) Highway Project ... · iv PROJECT SUMMARY Project Overview 1. The Manzini-Mbadlane Highway Project in Swaziland entails the dualisation of an

12

of employment and compensations. Secondly, the project will conduct sensitization programme that

will encompass Sexual and Gender Based Violence (SGBV), instituting codes of conduct on all

project sites and providing adequate welfare facilities. The sessions will be executed by a service

provider recruited by Executing Agency and will follow format and structure of established

programme (see Technical Annex B8 for details).

3.2.8 Consultation on gender issues, particularly on maternal health, suggested project to consider

intervening in minor rural roads to local health facilities/clinics that are within the zone of influence of

the project road. The Swaziland MDG 2012 Progress Report cites accessibility difficulties

experienced by expecting mother as one of the critical contributors of child and maternal mortalities in

the rural areas of the country. An intervention that significantly reduce the travel time to clinics will

save lives and contributes to reduction in avoidable mortalities. To be included as part of the civil

works, the project makes provision to repair or rehabilitate a number of existing impassable rural

feeder roads at selected inaccessible sites linking vulnerable communities to the local clinic. The

project sites shall be selected by the Roads Department and shall be in the district of Manzini and

Lubombo, which are within project zone of influence. Potential rural communities may include:

Mkhiweni (to Dvokolwako clinic); Mhlabeni (to Matsanjeni Good Sherpered clinic) and others. A

provisional sum of E10million (US$890,000) sourced from ADB loan has been allocated for this

intervention and the Bank will closely monitor this activity.

Social

3.2.9 The road project will have both negative and positive social impacts during implementation

and operation. Among the immediate benefits will be creation of wealth among the 500 who will

obtain jobs at construction sites. Majority of the jobs will be for unskilled and semi-skilled local

people. In addition, suppliers of construction materials to site, and services such as site security

services, cleaning services and meal services to workers. During operation, the project road will yield

economic benefits to road users and facilitate economic growth in the areas served. In addition, the

project will construct road side markets for use by communities. These will serve several purposes

including providing space for traders and venders to operate from; improving the environment and

hygiene through provision of toilet facilities, waste pits and clean water; and improve road safety. The

road design accommodates service roads which will facilitate use of the roads by local communities in

a secure and safe way.

3.2.10 A potential negative outcome of the project would be the risk of spread of HIV/AIDS/STI and

TB in the communities in the project area. The project design therefore includes activities on

sensitization and awareness campaigns for project workers and public communities. In section 1.3, the

level of donor coordination in the social and health sectors were described as active and to ensure aid

effectiveness, the Bank consulted with Government and some donors (EU, UNDP) on existing

programmes to avoid or minimize duplication. The Bank identified on-going programmes of the

United States PEPFAR (President's Emergency Plan for AIDS Relief), NERCHA (the National

Emergency Response Council on HIV and AIDS) through its affiliates namely SWABCHA

(Swaziland Business Collation of HIV and AIDS), as collectively the most effective way of

maximizing impact. Other programme are organized by Community Based Organizations and NGOs

through the CANGO (Coordinating Assembly for NGOs). A minimum of four (4) sensitization

sessions will be conducted during implementation period with the expectation of reaching no less than

2000 people within the zone of influence of the road. The RD will be responsible for the session

executed through a service provide and in collaboration with NERCHA, SWABCHA and CANGO. A

provisional sum of the E600,000 (US$54,000) has been set aside as part of the ESMP implementation.

Road Safety

3.2.11 Increase in road accidents is a potential outcome of the project thus risking project objective.

During implementation, potential causes of road accidents could stem from temporary traffic

Page 22: Swaziland - Manzini to Mbadlane (MR3) Highway Project ... · iv PROJECT SUMMARY Project Overview 1. The Manzini-Mbadlane Highway Project in Swaziland entails the dualisation of an

13

management measures such as access blockages and diversions. During normal use of the project

road, increased vehicular traffic and driving speeds could result in increased accidents. An estimated

220 fatalities per year are the result of road accidents in Swaziland, and the MR3 has one of the

highest number of incidents being the main thoroughfare for local and cross-border traffic. In 2013,

163 major accidents were recorded. The project design has included measures for mitigation which

include ensuring compliance by contractor of proper and adequate signage and demarcations. The

project will conduct awareness and educational programs (roadshow) for motorists and pedestrians

during implementation and operational phases. A provisional sum of E550,000 (US$50,000) has been

set aside for this purpose. Above all, the road design shall undergo a technical safety audit to ensure

compliance with safety measures.

Involuntary Resettlement

3.2.12 The project works will directly impact seventy five (75) properties in a form of land,

structures, formal and informal businesses, crops and trees. Among the affected are eight (8)

properties that belong to government or are in national trust tenure. An abbreviated resettlement plan

has been prepared in line with the Bank’s ESAP. A provisional budget of E33.0 million (excluding

contingencies) has been set aside for compensation and resettlement support. After completion of the

road, some of the informal businesses will resume in the roadside markets that will be constructed

under the project.

4. IMPLEMENTATION

4.1 Implementation Arrangements

4.1.1 The Roads Department (RD) of MPWT will be the Executing Agency (EA) for the project.

The Chief Roads Engineer (CRE) of the RD will nominate a Project Coordinator (PC) for each Lot

(described in section 2.5), who will be responsible for the day-to-day management of respective road

section. The CRE will have overall responsibility for the delivery of the project road. The local

authority will work with RD to oversee the resettlement and compensation activities and the

implementation of social measures. Similarly, SEA and Ministry of Tourism and Environment will

collaborate with the RD to oversee the environmental compliance. Supporting the PC will be a project

team of engineers, procurement, environmentalist and financial management experts. The PC shall

have a minimum of BSc. Degree in Civil Engineering and a minimum of 10 years experience in

capital projects in roads infrastructure.

4.1.2 The TA for the establishment of the Road Authority and Road Fund, which is funded by the

MIC grant, will be managed by the MPWT in collaboration with the Ministry of Finance. The TA for

the training and project management support will be managed by the RD and the Secretary of the

MPWT will have oversight responsibility. The coordination structure for overseeing the establishment

of the Road Authority and the Road Fund will comprise the Permanent Secretaries of all the relevant

ministries, including the Ministry of Finance and Economic Planning and MPWT with an oversight

responsibility at ministerial level.

4.1.3 To assist the CRE in overseeing the management of the two contracts or Lots, a Technical

Assistance support in the form of an individual consultant specialised in contract and project

management will be appointed by the project, and funded through the loan facility. The CRE shall be

responsible for designating task to the consultant in a manner that ensures effective management of

the project.

Page 23: Swaziland - Manzini to Mbadlane (MR3) Highway Project ... · iv PROJECT SUMMARY Project Overview 1. The Manzini-Mbadlane Highway Project in Swaziland entails the dualisation of an

14

Procurement

4.1.4 The project road will be implemented as two main lots (Lots 1 and 2), as described earlier, and

procured under separate procurement rules. The AfDB rules will be used for Lot 1 components and

the rules of other co-financiers for Lot 2.

4.1.5 The Bank-funded main civil works contract, which comprises: (i) construction and upgrade of

new and existing carriageway and all associated infrastructure, utilities and services; (ii)

implementation of environmental and social measures; (iii) construction of weighbridge and

implementation of axle load control measures, will be procured on the basis of International

Competitive Bidding (ICB) with prequalification in accordance with the Bank’s “Rules and

Procedures for Procurement of Goods and Works”. The civil works contract for feeder road access

will be procured through National Competitive Bidding (NCB) using the Bank Standard Bidding

Documents. The Bank’s Standard Bidding Documents will be used with Bank’s prior review of the

documents at each stage of the procurement phase.

4.1.6 The Bank funded consultancy services, including technical assistance services will be procured

by short-listing of qualified consulting firms in accordance with the Bank’s “Rules and Procedures for

Use of Consultants”. The method of selection would be Quality and Cost Based Selection (QCBS).

Technical, financial, and road safety audit services will be procured through national shortlist using

Least Cost Selection (LCS) method.

4.1.7 The Executing Agency will be responsible for the procurement of goods, works, consulting

services, training services and an assessment of the capacity to implement procurement actions for the

project has been carried out by the Bank. Based on the assessment, it has been proposed to strengthen

this capacity with the appointment of one Senior Procurement Specialist(s) in MPWT. Further details

of procurement arrangement are discussed in detail under Section B5 of the Technical Annex.

Financial Management and Disbursement Arrangements

4.1.8 The MPWT will be responsible for all aspects of Project Financial Management. The Finance

Department of MPWT was assessed for its capacity to handle the Project Financial management

responsibilities and in broad terms, the staff, systems and procedures in place were fund to be

adequate, subject to a few mitigation measures proposed. Whilst the department is manned by staff

with sufficient experience in public sector accounting and prior experience in Bank funded operations

of a similar nature the staff are on secondment from the Accountant General’s Department and hence

subjected to planned periodic rotation across other Government Ministries and Departments. While

broader experience is beneficial to staff, the lack of continuity potentially disrupts the execution of

project tasks and this is reflected in the delayed auditing of existing Bank portfolio. The Bank

therefore finds it necessary to recommend a Financial Management Officer/consultant recruited to

assume overall operational responsibility over the financial management of the project. Due to the

inability of the existing cash-based Treasury Accounting System (TAS) to comprehensively meet the

Bank’s record keeping and financial reporting requirements (particularly with respect to capital and

accruals accounting), a basic accounting system (including procedures) will be put in place to

complement the TAS.

4.1.9 All disbursements from the Bank’s resources will follow the procedures and requirements

outlined in AfDB’s Disbursement Handbook, as applicable. Disbursement will be principally through

the Direct Payment Method, but a Special Account will be opened (in USD) with the Central Bank for

the purposes of paying expenses of a smaller nature to service providers, including those under (i)

road safety, gender and HIV/AIDS awareness campaign component and; (ii) project management

support (Section 2.2, Table 2.1). Periodic and Annual Financial reporting will be carried out in

accordance with Bank rules. The Office of the Auditor General will be responsible for the annual

external audit as per its constitutional mandate, although such services may be outsourced at the

Page 24: Swaziland - Manzini to Mbadlane (MR3) Highway Project ... · iv PROJECT SUMMARY Project Overview 1. The Manzini-Mbadlane Highway Project in Swaziland entails the dualisation of an

15

Auditor General’s discretion. It will be desirable for the RD/MPWT to engage the Auditor General in

good time to confirm what audit arrangements will be put in place. The procurement of the

consultancy services for the audits will be in line with Bank’s procedures and the cost financed from

the proceeds of the ADB Loan.

4.2 Monitoring

4.2.1 Project monitoring will cover: environment, social, quality of works, general management

activities of the project and compliance with various institutional agreements and protocols (e.g. local

employment laws). The Bank will monitor adherence to key milestones, quality of deliverables and

outputs through periodic supervisions, mid-term reviews, implementation support and quarterly

reporting. The ESMP identifies project impact, the control measures and implementation

responsibilities. The monitoring regime, which will reflect impact and mitigation measures described

in Section 3.2 above, will cover all phases of the project. Given the variability of the bio-physical

environment, the ESMP will be a live document, subject to periodic reviews and updates, to ensure its

effectiveness as a working tool. The Bank will monitor closely the activities on the resettlement and

compensation of PAPs ensuring compliance with the agreed ARAP to ensure project schedule is not

unduly compromised. The Bank’s regional office (SARC) will be on hand to monitor the project. The

project implementation and monitoring schedule is provided below in Table 4.2.

Table 4.2 – Implementation Monitoring Timeframe

Timeframe Milestone Monitoring process Feedback loop

Q4-2014 Project Launching Field Mission Progress Reporting

Q1-2015 Pre-contract services start Field Supervision Progress reporting

Q3- 2015 Procurement of Civil works Supervision Progress Reporting

Q3 -2016 Construction Start + 6 months Field Mission/Midterm

Review Progress Reporting

Q2 -2018 Substantial completion (3 months prior to

construction End date ) of civil works

Field Mission/Project

Completion Report

Project Completion

Report

Q2-2019 Defects Liability Period & First year of

Operations Project Evaluation

Standard supervision program : Q1-2016; Q2-2017; Q4-2017;

4.3 Governance

4.3.1 The Mo Ibrahim Index of African Governance ranks Swaziland poorly in participation and

human rights, as well as sustainable economic opportunity. In 2012, Swaziland was ranked 27 out of

52 countries, with a score of 49 (well below the regional average score of 59). Performance in public

management, a sub-category of governance, has dropped by 8.4 points over the last six years to a

score of 53.1. In addition, the Bank’s Country Policy and Institutional Assessment (CPIA) shows a

weakening governance environment, with the country’s score declining from 3.5 in 2010 to 3 in 2011.

In 2012, the governance score improved to 3.3 but the country’s ranking slipped to 47 from 44 in

2011. There are major weaknesses on the expenditure side due to inefficient resource allocations.

Strengthening the budgetary process to enhance resource allocation and capacitating oversight bodies

to ensure effective delivery of their core mandate and to foster transparency in procurement and

accountability will be important. The Fiscal Adjustment Roadmap (described in section 1.1.4), jointly

sponsored by donors, has been structured, developed and under implementation to help address some

of the institutional challenges faced by the government.

4.4 Sustainability

Recurrent Costs

4.4.1 Throughout the construction and Defects Liability Period for the road, the contractor will be

responsible for road maintenance. One year after commissioning, the maintenance expenditure will be

taken over by the RD and will be charged to the road maintenance budget. The maintenance activities

comply with the current maintenance policy mostly comprising routine maintenance of the roadside,

Page 25: Swaziland - Manzini to Mbadlane (MR3) Highway Project ... · iv PROJECT SUMMARY Project Overview 1. The Manzini-Mbadlane Highway Project in Swaziland entails the dualisation of an

16

ancillary works including pothole patching. This is estimated at E8.3 million per year for the project

road. Also periodic maintenance, comprising of resealing of the surface after every eight years of

traffic use would be undertaken to refresh and prolong the life of the road. It is estimated that about

E15.0 million would be needed for periodic maintenance. The above maintenance expenditure would

be met by the GOKS through allocations to the RD from the national budgets.

Project Sustainability

4.4.2 The total length of road network in Swaziland is approximately 4,800 km, of which 1,200 km

is paved. Forty eight percent (48%) of the road network is classified as Main Roads (MR) with

District Roads (DR) making up the remaining 52 percent. Of the paved network, conditions vary: 33%

as very good condition; 45% good; 18% fair; and; 4% poor. Swaziland has a relatively well developed

road network which links the various parts of the country. The government has been investing in roads

construction, upgrading and rehabilitation and the total proclaimed road network grew by 20 percent

between 1997 and 2012. Most of the roads radiate from Mbabane and connect to the MR3, linking

regions in addition to being part of the country’s major import-export corridors. The responsibility for

the formulation of road development plans and sustainability of quality road networks through

adequate maintenance falls under the Roads Department. Municipalities of the cities and towns have

own departments responsible for the administration of their road networks although RD assumes the

role for most of the road network and funding is through national budget.

4.4.3 Based on the maintenance report, needs for maintenance and rehabilitation of the existing

roads is E120 million annually though to sustain the condition of the paved roads, it is estimated that

minimum annual budget allocation of E180million is required. The sustainability of the road

infrastructure is critical for sustainable economic growth given the role it plays to the country. The

consequence of increased trade traffic is compromising the design life and serviceability of the

infrastructure.

4.4.4 At macro level, the Bank’s CSP cites a number of risks to investment, some of which have

direct impact on the sustainability of investment. The pertinent factors include: (i) the lack of

governance structures; (ii) skills shortages and limited institutional capacity; (iii) inadequate public

financial management systems. Translating this to the sector, the risks are: i) inadequate capacity of

the sector agencies in managing assets; (ii) lack of financial governance and management systems to

better allocate budget and manage recurrent expenditure; and (iii) the lack of reforms to safeguard

investment such as absence of axle load control measures. These risks are reflected in Section 4.5 as

sustainability risks to be mitigated by the project.

4.4.5 The government recognises the above as issues to be addressed and conducted a study to

develop the principles, legislative process and the framework for the implementation of the reforms in

2005 (Swaziland Road Sector Reform: Framework for the Road Sector Reform Principles and

Processes - December, 2005). It also brings it in line with the aspirations of the National Transport

Policy and the SADC Protocol, which addresses interoperability and harmonization on a regional

perspective. One of the objectives of the sector reform is structural transformation of the sector in the

form of organizational restructuring of the agencies. The intended output is the transformation of the

current Roads Department, from a department under the MPWT, to an autonomous Road Agency or

Authority headed by a CEO with powers to determine funding needs for recurrent expenditure. The

funds for the Agency will consist of moneys from road user charges (RUC) through the RUC account

or Road Fund. The source for the RUC will be from fuel levy, license fee, cross-border charges and

other charges.

4.4.6 The Funds entity, i.e. the Road Fund, will be an autonomous entity responsible for road

funding function including funding allocation approvals. In general, these reforms are consistent with

the standard structures region-wide to ensure funds are ‘ring-fenced’ for recurrent expenditure and

investment of road infrastructure, as opposed to being absorbed into national budgets. While some

Page 26: Swaziland - Manzini to Mbadlane (MR3) Highway Project ... · iv PROJECT SUMMARY Project Overview 1. The Manzini-Mbadlane Highway Project in Swaziland entails the dualisation of an

17

progress has been made, the process has been slow and intermittent. The Legislative process is in the

final stages of parliamentary enactment. Given the level of investment in the country, the Bank

considers it relevant to facilitate the implementation of the reform to safeguard its investment and

ensure sustainability of trade-led growth.

4.4.7 The Bank has reviewed some of the available information on the sector reform programme and

consider it a necessary intervention to support the government. The project has therefore included

three components as a contribution to the reform. The project will finance training programmes on

two selected themes (OPRC methodologies and PPP) for key MPWT staff as part of the institutional

capacity building. The institutionalization and establishment of the Road Agency and the Road Fund,

which is a key part of reforms programme will be implemented as per the existing implementation

framework and legislative process. There is currently no operational axle load measures in the country

and by encouraging trade, there is real risk to the investment in terms of uncontrolled loading on the

infrastructure. The project will finance the construction of a weighbridge and the formulation of

operational procedures for axle load control as to complement the sector reform programme.

4.5 Risk management

4.5.1 This project is characterized by two risk profiles. They are risks associated with

implementation and risks to sustainability of the investment. Other project-specific risks relate to

features that are considered unique to the project. A source of information to better evaluate country

specific risks, in addition to generic risks typical of such project, is past appraisal reports and PCRs.

4.5.2 Implementation risks: These comprise pre-construction, primarily procurement-related risks,

and construction risk, both of which may lead to cost overruns and schedule delays. Potential

contributing factors include: (i) longer procurement period; (ii) capacity constraint of MPWT to

manage two concurrent contracts; (iii) design scope changes; (iv) compensation and resettlement

complications; (v) technical and environmental risks. Of these risk factors, the most probable is the

lack of capacity of MPWT, though a common feature of past project was cost overrun caused by

design scope change. The project has made the following provisions to mitigate the implementation

risks:

a) Improving the capacity of the Executing Agency in the form of TA to assist in the

management of two contracts: Notwithstanding the TA support, RD has significant experience

in managing donor-funded capital projects including the Bank’s. The added TA support is to

mitigate potential risks in managing concurrent contracts procured by differing procurement

rules.

b) Risk of procurement delays is mitigated by providing short term, procurement support on

Bank procurement rules to RD.

c) The likelihood of design creep and consequently cost increase are considered low. Project cost

has been reviewed (January 2014) to accommodate price changes and adequate contingencies

have been incorporated to reflect a recent project in the country. Secondly, and unlike previous

projects, the project allows for a design review to be undertaken in order to ensure it fully

meets the needs of government and follows a recommendation of Bank PCRs.

d) Resettlement and compensation comprise mainly property compensations and modest

resettlement. The risk is less and the process of compensation has already began with

budgetary allocations ‘gazetted’ (February 2014).

4.5.3 Sustainability risks: As addressed in section 4.4, the risks to sustainability are: i) inadequate

sector reforms and the failure to implement; (ii) inadequate capacity of sector agency; (iii) inadequate

provisions for recurrent expenditure for maintenance. The proposed mitigation measure has medium

to long term dimensions in the form of institutional and transformational reform of the sector and the

Page 27: Swaziland - Manzini to Mbadlane (MR3) Highway Project ... · iv PROJECT SUMMARY Project Overview 1. The Manzini-Mbadlane Highway Project in Swaziland entails the dualisation of an

18

project addresses some of the challenges through three interventions described under project

sustainability.

4.6 Knowledge Building

4.6.1 This project provides the opportunity for new skills to be developed within the sector. It

enables the Bank to intervene in building the knowledge capacity of the sector in a manner that

empowers the sector agencies to better manage road assets. The intervention institutes structured

reforms, which (i) assigns clear responsibilities for managing roads; (ii) creates ownership of roads to

encourage cost effective service delivery; (iii) stabilises road finance through reliable source of funds,

and; (iv) strengthens management of roads by introducing sound business practices. This is a

transformational process for the sector and the Bank will leverage experience gained in working with

established parastatals in member countries to positively influence and enhance the operations of the

new setup. The Bank has proposed semi-annual reporting on the implementation of the reforms in

order share and build on its experiences.

5 LEGAL INSTRUMENTS AND AUTHORITY

5.1 Legal instrument

5.1.1 The Bank instruments to finance this project are:

i) A loan agreement between the Kingdom of Swaziland and the Bank for a loan of USD

45.9 million, and

ii) A letter of agreement between the Kingdom of Swaziland and the Bank for a grant of

UA1.2 million from the MIC Technical Assistance Fund Grant.

5.2 Conditions associated with Bank’s intervention

Conditions Precedent to the Entry into Force of the ADB Loan Agreement

5.2.1 The entry into force of the Loan Agreement shall be subject to the fulfilment by the Borrower

of the provisions of Section 12.01 of the General Conditions Applicable to the African Development

Bank Loan Agreements and Guarantee Agreements.

Conditions Precedent to the Entry into Force of the MIC Grant Letter of Agreement:

5.2.2 The Letter of Agreement shall enter into force upon signature by the parties thereto.

Conditions Precedent to First Disbursement of the ADB Loan:

5.2.3 The obligation of the Bank to make the first disbursement of the Loan shall be conditional

upon entry into force of the Loan Agreement in accordance with Section 5.2.1 above and the

fulfilment by the Borrower of the following conditions:

i) the opening of a special account denominated in USD in a bank acceptable to the Bank for

receipt of certain proceeds of the Loan (See Section 4.1.8);

ii) appointment of an Engineer whose terms of reference, qualification and experience are

acceptable to the Bank, to serve as the Project Coordinator;

Conditions Precedent to First Disbursement of the MIC Grant:

5.2.4 The obligation of the Bank to make the first disbursement of the MIC Grant shall be

conditional upon:

i) entry into force of the Letter of Agreement in accordance with Section 5.2.2 above:

ii) a United States Dollar special account (the “Special Account”) has been opened in a bank

acceptable to the Bank for receipt of the proceeds of the Grant;

Page 28: Swaziland - Manzini to Mbadlane (MR3) Highway Project ... · iv PROJECT SUMMARY Project Overview 1. The Manzini-Mbadlane Highway Project in Swaziland entails the dualisation of an

19

Other Conditions of the Loan

5.2.5 The Borrower will provide evidence in form and substance acceptable to the Bank of the

following:

i) prior to the commencement of civil works on any civil works, having fully compensated and/or

resettled all Project Affected Persons affected by such works in accordance with the ARAP.

ii) within nine (9) months of the Date of Signature, provide evidence, in form and substance

satisfactory to the Bank, of having secured the co-financing for Lot 2 of the Project.

iii) within six (6) months of the Date of Signature, provide evidence, in form and substance

satisfactory to the Bank, of the recruitment of a financial management officer for the Project,

with terms of reference, qualifications and experience acceptable to the Bank.

Undertakings

5.2.6 The Borrower hereby undertakes the following:

i) To implement and report to the Bank on a quarterly basis in a form acceptable to the Bank on

the implementation of the ESIA, the ESMP and the ARAP;

ii) Borrower shall report to the Bank on a semi-annual basis on the progress of the

implementation of the Road Sector Reforms components, namely (a) the establishment and

institutionalization of the Roads Authority and the Road Fund; and (b) capacity building

program on the training of MPWT personnel.

6 RECOMMENDATION

6.1.1 The project design is consistent with pillars of Bank and Country development strategies for

poverty reduction by supporting trade-led and socially inclusive growth. The cross-cutting issues have

been considered in the design and close monitoring will be instituted to ensure positive project impact.

The institutional capacity deficiencies have been addressed. The hard infrastructure is complemented

by soft components to ensure that an efficient and sustainable infrastructure system evolves as the

output. The project risks are manageable and practical mitigation measures have been built into the

design.

6.1.2 Management recommends that the Board of Directors approve, subject to the conditions

stipulated in this report:

i) The proposed ADB loan of USD45.9 million (UA30.0million) to the Government of the

Kingdom of Swaziland for the purpose of co-financing the implementation of the Manzini to

Mbadlane Highway Project

ii) The proposed MIC Technical Assistance Fund Grant for UA1.20 million to the Government of

the Kingdom of Swaziland to finance Technical Assistance services for capacity building and

sector reform activities.

Page 29: Swaziland - Manzini to Mbadlane (MR3) Highway Project ... · iv PROJECT SUMMARY Project Overview 1. The Manzini-Mbadlane Highway Project in Swaziland entails the dualisation of an

I

Appendix I: Swaziland Comparative Socio-Economic Indicators

Indicator Year Swaziland Africa Developing Countries

Developed Countries

Charts

Basic Indicators

Area ('000 Km²) 17.4 30,046.

4 80,976.0 54,658.4

Total Population (millions) 2013 1.2 1,109.0 5,628.5 1,068.7

Urban Population (% of Total) 2013 21.2 40.2 44.8 77.7

Population Density (per Km²) 2013 67.8 35.4 66.6 23.1

GNI per Capita (US $) 2011 3,300.0 1,594.2 2,780.3 39,688.1

Labor Force Participation - Total (%) 2013 34.6 37.4 0.0 0.0

Labor Force Participation - Female (%) 2013 39.4 42.5 39.8 43.3

Gender -Related Development Index Value 2007 0.6 0.5 .. 0.9

Human Develop. Index (Rank among 169 countries) 2012 141.0 .. .. ..

Popul. Living Below $ 1 a Day (% of Population) 2010 40.6 .. 25.0 ..

Demographic Indicators

Population Growth Rate - Total (%) 2013 1.5 2.5 1.4 0.7

Population Growth Rate - Urban (%) 2013 1.3 3.4 2.4 1.0

Population < 15 years (%) 2013 37.8 40.9 29.2 17.7

Population >= 65 years (%) 2013 3.5 3.5 6.0 15.3

Dependency Ratio (%) 2013 68.5 77.3 52.8 ..

Sex Ratio (per 100 female) 2013 97.4 100.0 934.9 948.3

Female Population 15-49 years (% of total population) 2013 25.9 24.0 53.3 47.2

Life Expectancy at Birth - Total (years) 2013 49.0 59.2 65.7 79.8

Life Expectancy at Birth - Female (years) 2013 48.3 60.3 68.9 82.7

Crude Birth Rate (per 1,000) 2013 29.9 35.3 21.5 12.0

Crude Death Rate (per 1,000) 2013 14.3 10.4 8.2 8.3

Infant Mortality Rate (per 1,000) 2013 64.0 61.9 53.1 5.8

Child Mortality Rate (per 1,000) 2013 91.1 97.4 51.4 6.3

Total Fertility Rate (per woman) 2013 3.3 4.6 2.7 1.8

Maternal Mortality Rate (per 100,000) 2010 320.0 415.3 440.0 10.0

Women Using Contraception (%) 2013 64.1 31.7 61.0 75.0

Health & Nutrition Indicators

Physicians (per 100,000 people) 2004 16.0 52.6 77.0 287.0

Nurses (per 100,000 people)* 2004 320.4 .. 98.0 782.0

Births attended by Trained Health Personnel (%) 2010 82.0 .. 39.0 99.3

Access to Safe Water (% of Population) 2011 72.2 67.8 84.0 99.6

Access to Health Services (% of Population) 2000 55.0 65.2 80.0 100.0

Access to Sanitation (% of Population) 2011 57.0 40.5 54.6 99.8

Percent. of Adults (aged 15-49) Living with HIV/AIDS 2011 26.0 4.7 161.9 14.1

Incidence of Tuberculosis (per 100,000) 2011 1,317.0 235.8 .. ..

Child Immunization Against Tuberculosis (%) 2011 98.0 81.2 89.0 99.0

Child Immunization Against Measles (%) 2011 98.0 76.3 76.0 92.6

Underweight Children (% of children under 5 years) 2008 7.3 .. 27.0 0.1

Daily Calorie Supply per Capita 2009 2,249.0 2,564.7 2,675.2 3,284.7

Public Expenditure on Health (as % of GDP) 2011 5.6 5.9 4.0 6.9

Education Indicators

Gross Enrolment Ratio (%) .. .. .. ..

Primary School - Total 2011 115.1 101.8 106.0 101.5

Primary School - Female 2011 108.9 97.8 104.6 101.2

Secondary School - Total 2011 60.0 45.4 62.3 100.3

Secondary School - Female 2011 59.1 41.9 60.7 100.0

Primary School Female Teaching Staff (% of Total) 2011 70.8 43.7 .. ..

Adult Literacy Rate - Total (%) 2011 87.8 .. 19.0 ..

Adult Literacy Rate - Male (%) 2011 87.3 .. .. ..

Adult Literacy Rate - Female (%) 2011 88.4 .. .. ..

Percentage of GDP Spent on Education 2011 8.2 5.3 .. 5.4

Environmental Indicators

Land Use (Arable Land as % of Total Land Area) 2011 10.2 8.4 9.9 11.6

Annual Rate of Deforestation (%) 2000 -1.2 0.6 0.4 -0.2

Annual Rate of Reforestation (%) .. .. .. ..

Per Capita CO2 Emissions (metric tons) 2011 0.9 1.1 .. ..

Sources : ADB Statistics Department Databases; World Bank: World Development Indicators Last update: March 2014 UNAIDS; UNSD; WHO, UNICEF, WRI, UNDP; Country Reports. Note n.a.: Not Applicable : Data Not Available.

Page 30: Swaziland - Manzini to Mbadlane (MR3) Highway Project ... · iv PROJECT SUMMARY Project Overview 1. The Manzini-Mbadlane Highway Project in Swaziland entails the dualisation of an

II

Appendix II Table of AfDB’s portfolio in the Country

Division Long name Sector Name Amount App. Amount

Dis. Dis. Ratio

Windo

w

OSGE2 TA FOR PUBLIC FINC

MGMT REFORMS Multi-Sector 478,452.0 163,749.5 34.2 [ ADB ]

ESTA2 SCB - II Multi-Sector 490,600.0 0.0 0.0 [ ADB ]

Total Multi-Sector 969,052.0 163,749.5

Page 31: Swaziland - Manzini to Mbadlane (MR3) Highway Project ... · iv PROJECT SUMMARY Project Overview 1. The Manzini-Mbadlane Highway Project in Swaziland entails the dualisation of an

III

Appendix III Related Projects Financed by the Bank and Other Donors, 2014

Project Name Donor Type of

Works/Sector Amount

(million)

Fiscal Adjustment Roadmap (FAR)

AfDB, EU, IMF,

UNDP and the

World Bank

Governance and

financial

Management

UA 10.22

Lower Usuthu Smallholder Irrigation Project (LUSIP I) AfDB

Agriculture

Lower Usuthu Irrigation Project (LUSIP) EU Agriculture &

Infrastructure EUR 11

National Water and sanitation project (Lumbobo and

Shiselweni regions)

EU Water and

Sanitation EUR 19

Support to Education and Training (SET), Education for

All (EFA), Human Resources Development

EU Education EUR 23

Swaziland Health, HIV/AIDS and TB Project

EU

Health

EUR 14.5

World Bank US$20

UN (UNFPA,

UNAIDS

Maternal Child Health Care World Bank Health US$ 2.57

PEPFAR United States Health US$ 35.6

Mbadlane to Sikhuphe International Airport (D42) road

construction

BADEA

Kuwait Fund Transport

Swaziland/China Bilateral cooperation agreement. Republic of China

(Taiwan) Multi-sector: US$ 180m

Improvement of Secondary School Education Japan Education ¥1, 143

billion

Page 32: Swaziland - Manzini to Mbadlane (MR3) Highway Project ... · iv PROJECT SUMMARY Project Overview 1. The Manzini-Mbadlane Highway Project in Swaziland entails the dualisation of an

IV

Appendix IV: Details of Project Cost

Table 1- Project Cost Breakdown by Component and Source (UA million)

PROJECT COMPONENT FUNDING SOURCE

AfDB Co-

financier Grant

GOKS

(lot 1)

GOKS

(lot 2) TOTAL

Civil works

Civil Works 23.06 31.29 - 9.88 1.65 65.88

Weighbridge 0.35 0.00 - 0.35 0.00 0.70

Feeder Road 0.55 0.00 - 0.03 0.58

Subtotal 23.96 31.29 - 10.26 1.65 67.16

Consultancy Services

Design Reviews & Construction

Supervision 1.23 0.49

- 0.31 1.05 3.08

Project Management Support 0.17 - - - - 0.17

Project Financial Audits Services 0.03 - - - - 0.03

Project Technical Audits Services 0.03 - - - - 0.03

Subtotal 1.46 0.49 - 0.31 1.05 3.31

Technical Assistance

Training Programme - - 0.14 - - 0.14

Establishment of Roads Authority/Road

Fund - - 0.88

- - 0.88

Subtotal 0.00 0.00 1.02 0.00 0.00 1.02

Complementary Components

- -

-

Implementation of ESMP 0.17 - -

- 0.17

Resettlement & Compensation - - - 1.91 - 1.91

Subtotal 0.17 0.00

1.91 2.08

BASE COST 25.59 31.78 1.02 11.52 3.66 73.57

contingencies(physical) 2.56 3.17 0.10 1.15 0.37 7.35

Subtotal 28.15 34.95 1.12 12.67 4.03 80.92

contingencies (price) 1.85 2.30 0.08 0.92 0.33 5.48

TOTAL COST 30.00 37.25 1.20 13.59 4.36 86.40

Table 2 – Total Cost Estimate by Component and Lot

Components ADB & GOKS GOKS& Co-Financiers

TOTAL LOT 1 (0km - km13) LOT 2 (km13-km30)

USD UA m USD UA m USD UA m

Civil Works 50.40 32.94 50.40 32.94 100.80 65.88

Consultancy Services 2.70 1.77 2.36 1.54 5.06 3.31

Implementation of ESMP 0.27 0.17 0.00 0.00 0.27 0.17

Resettlement &

Compensation 1.47 0.96 1.46 0.95 2.93 1.91

Weighbridge 1.06 0.70 0.00 0.00 1.06 0.70

Feeder Road 0.89 0.58 0.00 0.00 0.89 0.58

Technical Assistance

Services 1.56 1.02 0.00 0.00 1.56 1.02

Base Cost 58.35 38.14 54.22 35.43 112.57 73.57

Physical 5.84 3.81 5.42 3.54 11.26 7.35

Subtotal 64.19 41.95 59.64 38.97 123.83 80.92

Price contingency 4.35 2.84 4.02 2.64 8.37 5.48

TOTAL 68.54 44.79 63.66 41.61 132.20 86.40

Page 33: Swaziland - Manzini to Mbadlane (MR3) Highway Project ... · iv PROJECT SUMMARY Project Overview 1. The Manzini-Mbadlane Highway Project in Swaziland entails the dualisation of an

V

Appendix V: Project Map

1994, 1999, Two

International road

project (MR4)

1989, Main Roads

Rehabilitation (MR24) 40km.

1987, Mbabane-

Mbalambanyasti Road

(MR19)

2003: Mbabane Bypass (MR3)

1992: Mbabane-Matsapha (MR3)

1989 Main Roads

Rehabilitation (MR8), 66km

1981, Lonhlupheko-

Lomahasha (MR3) 50km.

1978, 1984: Mhokodo River -

Mahamba. Road (MR9)

Project Map (including past Bank funded project)

PROJECT

Urban City

Agriculture

centres

(Sugar)

Industrial

Centre