Overview:
The data in the following plots came from output of modeling done for the City of Portsmouth in 2009. The various scenarios, baseline
conditions (which include future planned separation projects), and current conditions. Only data that was relevant to results needed were
generated; if a period is not shown it is because that output was not crucial to the planning process or all the values were 0.
Current Conditions 4
1. Modeled Flow from Mechanic St Pump Station during 2008 Calibration Period - Current Conditions 4
2. Modeled Flow from Deer St Pump Station during 2008 Calibration Period - Current Conditions 5
3. Modeled Flow from LaFayette St Pump Station during 2008 Calibration Period - Current Conditions 6
4. Modeled Flow from CSO 010A during 2008 Calibration Period - Current Conditions 7
5. Modeled Flow from CSO 010B during 2008 Calibration Period - Current Conditions 8
6. Modeled Flow from CSO 013 during 2008 Calibration Period - Current Conditions 9
7. Modeled Flow from Mechanic St Pump Station during 1968 Typical Year - Current Conditions 10
8. Modeled Flow from Mechanic St Pump Station during 1990, and 1993 Typical Years - Current Conditions 11
9. Modeled Flow from Deer St Pump Station during 1968 Typical Year - Current Conditions 12
10. Modeled Flow from Deer St Pump Station during 1990, and 1993 Typical Years - Current Conditions 13
11. Modeled Flow from LaFayette St Pump Station during 1968 Typical Year - Current Conditions 14
12. Modeled Flow from LaFayette St Pump Station during 1990, and 1993 Typical Years - Current Conditions 15
13. Modeled Flow from CSO 010A during 1968 Typical Year - Current Conditions 16
14. Modeled Flow from CSO 010A during 1990, and 1993 Typical Years - Current Conditions 17
15. Modeled Flow from CSO 010B during 1968 Typical Year - Current Conditions 18
16. Modeled Flow from CSO 010B during 1990, and 1993 Typical Years - Current Conditions 19
17. Modeled Flow from CSO 013 during 1968 Typical Year - Current Conditions 20
SWMM Modeling Output
City of Portsmouth
6/2/2010 Brown and Caldwell P a g e | 2
18. Modeled Flow from CSO 013 during 1990, and 1993 Typical Years - Current Conditions 21
Baseline Conditions 22
19. Modeled Flow from Mechanic St Pump Station during 1968 Typical Year - Baseline Conditions 22
20. Modeled Flow from Mechanic St Pump Station during 1988, 1989, 1990, and 1993 Typical Years - Baseline Conditions 23
21. Modeled Flow from Deer St Pump Station during 1968 Typical Year - Baseline Conditions 24
22. Modeled Flow from Deer St Pump Station during 1988, 1989, 1990, and 1993 Typical Years - Baseline Conditions 25
23. Modeled Flow from LaFayette St Pump Station during 1968 Typical Year - Baseline Conditions 26
24. Modeled Flow from LaFayette St Pump Station during 1988, 1989, 1990, and 1993 Typical Years - Baseline Conditions 27
25. Modeled Flow from CSO 010A during 1968 Typical Year - Baseline Conditions 28
26. Modeled Flow from CSO 010A during 1988, 1989, 1990, and 1993 Typical Years - Baseline Conditions 29
27. Modeled Flow from CSO 010B during 1968 Typical Year - Baseline Conditions 30
28. Modeled Flow from CSO 010B during 1988, 1989, 1990, and 1993 Typical Years - Baseline Conditions 31
29. Modeled Flow from CSO 013 during 1968 Typical Year - Baseline Conditions 32
30. Modeled Flow from CSO 013 during 1988, 1989, 1990, and 1993 Typical Years - Baseline Conditions 33
Model Scenario 1 34
31. Modeled Flow from CSO 010A during 1968 Typical Year - Scenario 1 34
32. Modeled Flow from CSO 010A during 1988, 1989, 1990, and 1993 Typical Years - Scenario 1 35
33. Modeled Flow from CSO 010B during 1968 Typical Year - Scenario 1 36
34. Modeled Flow from CSO 010B during 1988, 1989, 1990, and 1993 Typical Years - Scenario 1 37
35. Modeled Flow from CSO 013 during 1988, 1989, 1990, and 1993 Typical Years - Scenario 1 38
Model Scenario 3 39
36. Modeled Flow from CSO 010A during 1968 Typical Year - Scenario 3 39
37. Modeled Flow from CSO 010A during 1988, 1989, and 1990 Typical Years - Scenario 3 40
SWMM Modeling Output
City of Portsmouth
6/2/2010 Brown and Caldwell P a g e | 3
38. Modeled Flow from CSO 010B during 1968 Typical Year - Scenario 3 41
39. Modeled Flow from CSO 010B during 1988, 1989, and 1990 Typical Years - Scenario 3 42
Model Scenario 4 43
40. Modeled Flow from CSO 010A during 1968 Typical Year - Scenario 4 43
41. Modeled Flow from CSO 010A during 1988, 1989, 1990, and 1993 Typical Years - Scenario 4 44
42. Modeled Flow from CSO 010B during 1968 Typical Year - Scenario 4 45
43. Modeled Flow from CSO 010B during 1988, 1989, 1990, and 1993 Typical Years - Scenario 4 46
Model Scenario 4 (Optimized Storage from Pipeline Replacement) 47
Model Scenario 5 48
44. Modeled Flow from CSO 010A during 1968 Typical Year - Scenario 5 48
45. Modeled Flow from CSO 010A during 1988, 1989, and 1990 Typical Years - Scenario 5 49
46. Modeled Flow from CSO 010B during 1968 Typical Year - Scenario 5 50
47. Modeled Flow from CSO 010B during 1988, 1989, and 1990 Typical Years - Scenario 5 51
48. Modeled Flow from CSO 013 during 1968 Typical Year - Scenario 5 52
49. Modeled Flow from CSO 013 during 1988, 1989, and 1990 Typical Years - Scenario 5 53
SWMM Modeling Output
City of Portsmouth
6/2/2010 Brown and Caldwell P a g e | 4
Current Conditions
1. Modeled Flow from Mechanic St Pump Station during 2008 Calibration Period - Current Conditions
SWMM Modeling Output
City of Portsmouth
6/2/2010 Brown and Caldwell P a g e | 5
2. Modeled Flow from Deer St Pump Station during 2008 Calibration Period - Current Conditions
SWMM Modeling Output
City of Portsmouth
6/2/2010 Brown and Caldwell P a g e | 6
3. Modeled Flow from LaFayette St Pump Station during 2008 Calibration Period - Current Conditions
SWMM Modeling Output
City of Portsmouth
6/2/2010 Brown and Caldwell P a g e | 7
4. Modeled Flow from CSO 010A during 2008 Calibration Period - Current Conditions
SWMM Modeling Output
City of Portsmouth
6/2/2010 Brown and Caldwell P a g e | 8
5. Modeled Flow from CSO 010B during 2008 Calibration Period - Current Conditions
SWMM Modeling Output
City of Portsmouth
6/2/2010 Brown and Caldwell P a g e | 9
6. Modeled Flow from CSO 013 during 2008 Calibration Period - Current Conditions
SWMM Modeling Output
City of Portsmouth
6/2/2010 Brown and Caldwell P a g e | 10
7. Modeled Flow from Mechanic St Pump Station during 1968 Typical Year - Current Conditions
SWMM Modeling Output
City of Portsmouth
6/2/2010 Brown and Caldwell P a g e | 11
8. Modeled Flow from Mechanic St Pump Station during 1990, and 1993 Typical Years - Current Conditions
SWMM Modeling Output
City of Portsmouth
6/2/2010 Brown and Caldwell P a g e | 12
9. Modeled Flow from Deer St Pump Station during 1968 Typical Year - Current Conditions
SWMM Modeling Output
City of Portsmouth
6/2/2010 Brown and Caldwell P a g e | 13
10. Modeled Flow from Deer St Pump Station during 1990, and 1993 Typical Years - Current Conditions
SWMM Modeling Output
City of Portsmouth
6/2/2010 Brown and Caldwell P a g e | 14
11. Modeled Flow from LaFayette St Pump Station during 1968 Typical Year - Current Conditions
SWMM Modeling Output
City of Portsmouth
6/2/2010 Brown and Caldwell P a g e | 15
12. Modeled Flow from LaFayette St Pump Station during 1990, and 1993 Typical Years - Current Conditions
SWMM Modeling Output
City of Portsmouth
6/2/2010 Brown and Caldwell P a g e | 16
13. Modeled Flow from CSO 010A during 1968 Typical Year - Current Conditions
SWMM Modeling Output
City of Portsmouth
6/2/2010 Brown and Caldwell P a g e | 17
14. Modeled Flow from CSO 010A during 1990, and 1993 Typical Years - Current Conditions
SWMM Modeling Output
City of Portsmouth
6/2/2010 Brown and Caldwell P a g e | 18
15. Modeled Flow from CSO 010B during 1968 Typical Year - Current Conditions
SWMM Modeling Output
City of Portsmouth
6/2/2010 Brown and Caldwell P a g e | 19
16. Modeled Flow from CSO 010B during 1990, and 1993 Typical Years - Current Conditions
SWMM Modeling Output
City of Portsmouth
6/2/2010 Brown and Caldwell P a g e | 20
17. Modeled Flow from CSO 013 during 1968 Typical Year - Current Conditions
SWMM Modeling Output
City of Portsmouth
6/2/2010 Brown and Caldwell P a g e | 21
18. Modeled Flow from CSO 013 during 1990, and 1993 Typical Years - Current Conditions
SWMM Modeling Output
City of Portsmouth
6/2/2010 Brown and Caldwell P a g e | 22
Baseline Conditions
19. Modeled Flow from Mechanic St Pump Station during 1968 Typical Year - Baseline Conditions
SWMM Modeling Output
City of Portsmouth
6/2/2010 Brown and Caldwell P a g e | 23
20. Modeled Flow from Mechanic St Pump Station during 1988, 1989, 1990, and 1993 Typical Years -
Baseline Conditions
SWMM Modeling Output
City of Portsmouth
6/2/2010 Brown and Caldwell P a g e | 24
21. Modeled Flow from Deer St Pump Station during 1968 Typical Year - Baseline Conditions
SWMM Modeling Output
City of Portsmouth
6/2/2010 Brown and Caldwell P a g e | 25
22. Modeled Flow from Deer St Pump Station during 1988, 1989, 1990, and 1993 Typical Years - Baseline
Conditions
SWMM Modeling Output
City of Portsmouth
6/2/2010 Brown and Caldwell P a g e | 26
23. Modeled Flow from LaFayette St Pump Station during 1968 Typical Year - Baseline Conditions
SWMM Modeling Output
City of Portsmouth
6/2/2010 Brown and Caldwell P a g e | 27
24. Modeled Flow from LaFayette St Pump Station during 1988, 1989, 1990, and 1993 Typical Years -
Baseline Conditions
SWMM Modeling Output
City of Portsmouth
6/2/2010 Brown and Caldwell P a g e | 28
25. Modeled Flow from CSO 010A during 1968 Typical Year - Baseline Conditions
SWMM Modeling Output
City of Portsmouth
6/2/2010 Brown and Caldwell P a g e | 29
26. Modeled Flow from CSO 010A during 1988, 1989, 1990, and 1993 Typical Years - Baseline Conditions
SWMM Modeling Output
City of Portsmouth
6/2/2010 Brown and Caldwell P a g e | 30
27. Modeled Flow from CSO 010B during 1968 Typical Year - Baseline Conditions
SWMM Modeling Output
City of Portsmouth
6/2/2010 Brown and Caldwell P a g e | 31
28. Modeled Flow from CSO 010B during 1988, 1989, 1990, and 1993 Typical Years - Baseline Conditions
SWMM Modeling Output
City of Portsmouth
6/2/2010 Brown and Caldwell P a g e | 32
29. Modeled Flow from CSO 013 during 1968 Typical Year - Baseline Conditions
SWMM Modeling Output
City of Portsmouth
6/2/2010 Brown and Caldwell P a g e | 33
30. Modeled Flow from CSO 013 during 1988, 1989, 1990, and 1993 Typical Years - Baseline Conditions
SWMM Modeling Output
City of Portsmouth
6/2/2010 Brown and Caldwell P a g e | 34
Model Scenario 1
31. Modeled Flow from CSO 010A during 1968 Typical Year - Scenario 1
SWMM Modeling Output
City of Portsmouth
6/2/2010 Brown and Caldwell P a g e | 35
32. Modeled Flow from CSO 010A during 1988, 1989, 1990, and 1993 Typical Years - Scenario 1
SWMM Modeling Output
City of Portsmouth
6/2/2010 Brown and Caldwell P a g e | 36
33. Modeled Flow from CSO 010B during 1968 Typical Year - Scenario 1
SWMM Modeling Output
City of Portsmouth
6/2/2010 Brown and Caldwell P a g e | 37
34. Modeled Flow from CSO 010B during 1988, 1989, 1990, and 1993 Typical Years - Scenario 1
SWMM Modeling Output
City of Portsmouth
6/2/2010 Brown and Caldwell P a g e | 38
35. Modeled Flow from CSO 013 during 1988, 1989, 1990, and 1993 Typical Years - Scenario 1
SWMM Modeling Output
City of Portsmouth
6/2/2010 Brown and Caldwell P a g e | 39
Model Scenario 3
36. Modeled Flow from CSO 010A during 1968 Typical Year - Scenario 3
SWMM Modeling Output
City of Portsmouth
6/2/2010 Brown and Caldwell P a g e | 40
37. Modeled Flow from CSO 010A during 1988, 1989, and 1990 Typical Years - Scenario 3
SWMM Modeling Output
City of Portsmouth
6/2/2010 Brown and Caldwell P a g e | 41
38. Modeled Flow from CSO 010B during 1968 Typical Year - Scenario 3
SWMM Modeling Output
City of Portsmouth
6/2/2010 Brown and Caldwell P a g e | 42
39. Modeled Flow from CSO 010B during 1988, 1989, and 1990 Typical Years - Scenario 3
SWMM Modeling Output
City of Portsmouth
6/2/2010 Brown and Caldwell P a g e | 43
Model Scenario 4
40. Modeled Flow from CSO 010A during 1968 Typical Year - Scenario 4
SWMM Modeling Output
City of Portsmouth
6/2/2010 Brown and Caldwell P a g e | 44
41. Modeled Flow from CSO 010A during 1988, 1989, 1990, and 1993 Typical Years - Scenario 4
SWMM Modeling Output
City of Portsmouth
6/2/2010 Brown and Caldwell P a g e | 45
42. Modeled Flow from CSO 010B during 1968 Typical Year - Scenario 4
SWMM Modeling Output
City of Portsmouth
6/2/2010 Brown and Caldwell P a g e | 46
43. Modeled Flow from CSO 010B during 1988, 1989, 1990, and 1993 Typical Years - Scenario 4
SWMM Modeling Output
City of Portsmouth
6/2/2010 Brown and Caldwell P a g e | 47
Model Scenario 4 (Optimized Storage from Pipeline Replacement)
No Flow from CSOs
SWMM Modeling Output
City of Portsmouth
6/2/2010 Brown and Caldwell P a g e | 48
Model Scenario 5
44. Modeled Flow from CSO 010A during 1968 Typical Year - Scenario 5
SWMM Modeling Output
City of Portsmouth
6/2/2010 Brown and Caldwell P a g e | 49
45. Modeled Flow from CSO 010A during 1988, 1989, and 1990 Typical Years - Scenario 5
SWMM Modeling Output
City of Portsmouth
6/2/2010 Brown and Caldwell P a g e | 50
46. Modeled Flow from CSO 010B during 1968 Typical Year - Scenario 5
SWMM Modeling Output
City of Portsmouth
6/2/2010 Brown and Caldwell P a g e | 51
47. Modeled Flow from CSO 010B during 1988, 1989, and 1990 Typical Years - Scenario 5
SWMM Modeling Output
City of Portsmouth
6/2/2010 Brown and Caldwell P a g e | 52
48. Modeled Flow from CSO 013 during 1968 Typical Year - Scenario 5
SWMM Modeling Output
City of Portsmouth
6/2/2010 Brown and Caldwell P a g e | 53
49. Modeled Flow from CSO 013 during 1988, 1989, and 1990 Typical Years - Scenario 5