SYDNEY LIGHT RAIL
WELCOME
Hon Patricia Forsythe, Executive Director,
Sydney Business Chamber
CONFIRMATION OF PURPOSE
AND INTRODUCTIONS
Abigail Goldberg, Chair
4
PROJECT UPDATE
Jeff Goodling, Project Director, Sydney Light Rail,
Transport for NSW
6
Project status
Planning conditions
Early Works
PPP tender process
Agenda
Project status
Feb 2013
Mobilise
integrated
project team
2013 Apr 2013
MOU with
key partners
Apr 2013
Finalisation
of inputs to
definition
design
Q3 2014
Definition
design
complete
Q4 2013
Business
case
Late 2013
Development
Agreements
with key
partners
Late 2013
Environmental
assessment
exhibition
Q2 2014
Planning
approval
granted
2014 Mid 2014
Award Early
Works
contract
Q3 2014
Commence
early works
construction
2015-2020 Construction
2015-2020
7
Q1 2014
Issue Early
Works
Request for
Proposals
End 2014
Award PPP
contract
Q1 2014
Issue PPP
Request for
Proposals
Q1 2014
Establish
Advisory
Board
Planning conditions Construction hours
6.00am to 10.00pm Monday to Friday
in CBD, 6.00am to 6.00pm other areas
8.00am to 5.00pm Saturdays
No work Sundays or public holidays
Works can occur at night through
out-of-hours applications, including
Moore Park Tunnel
8
Planning conditions Construction noise and vibration
9
Construction noise and vibration impact
statement prepared to include:
Proposed activities
Predicted noise and vibration levels
Review of alternative methods to
reduce noise and vibration
Mitigation treatments to reduce
impacts
10
Early Works
Olivia
Gardens
Inner West
platform
upgrades
Critical utility
relocations
Tramway
Oval
Robertson
Park
Tennis
Club
PPP tender process
13,000 data room
documents
3
Tenderers
114 Interactive
meetings
700 + Questions
to date
Short-listed consortia:
SydneyConnect
Including Serco Pty Ltd, John
Holland Pty Ltd and Plenary
Group Pty Ltd
iLinQ Sydney
Including Keolis Downer, Balfour
Beatty, McConnell Dowell,
Bombardier and Macquarie
Capital
Connecting Sydney Including
Transdev Sydney Pty Ltd,
Alstom Transport Australia Pty
Ltd, Acciona Infrastructure
Australia Pty Ltd and Capella
Capital.
11
FEEDBACK ON MATTERS
RAISED AT PREVIOUS MEETING
Jeff Goodling, Project Director, Sydney Light Rail, Transport for NSW
Business disruption
Working with utility companies
to ensure protection, relocation, or
upgrade of assets
George Street 3D utilities model
Confirming utility locations to ensure
minimal disruption
Consultation regarding disruption
13
Online communications
50,121 visits to the Sydney Light Rail
website since November 2013
Sydney Light Rail Facebook page
being developed
14
QUESTIONS AND ANSWERS
Workshop
What issues are likely to arise for business during the
construction period?
How can the project team best assist Business Forum
members during the light rail construction period?
What support could others provide? E.g. Council?
Members themselves?
16
Business objectives:
CLOSING REMARKS