Signal Retiming Improvements in St. Johns County

Presented by:

In Association With:

April 23, 2013

APWA PRESENTATION

Page 2: T14 signal retiming results-manwell

US 1 Traffic Signal Locations

Wal-Mart Entrance

Shore Drive

Old Moultrie Road

Shores Blvd.

Wildwood Drive

Lewis Point Road

Watson Road

Page 3: T14 signal retiming results-manwell

US 1 Signal Retiming Results

Corridor Results:

Length of Corridor, 4.6 miles

Benefits

Weekday Delay Reduction per Year (Hours): 161,511 Weekday Cost Savings per Year (Time): $1,395,458 Weekend Delay Reduction per Year (Hours): 48,435 Weekend Cost Savings per Year (Time): $418,474 Weekday Fuel Reduction per Year (gal): 213,735 Weekday Cost Savings per Year (Cost of Fuel $3.70/gal): $790,821 Weekend Fuel Reduction per Year (gal): 41,915 Weekend Cost Savings per Year (Cost of Fuel $3.70/gal): $155,084

Cost Savings per Year (Reduced Emissions): $9,726 Reduced CO emissions, 17.6 Metric Tons per Year Reduced NOx emissions, 3.4 Metric Tons per Year Reduced VOC emissions, 4.1 Metric Tons per Year

Total Cost Savings per Year: $2,769,563

_______________________________________________________________

Costs

Retiming Cost per Intersection: $8,653

Cost of Retiming 7 Intersections: $60,571

_______________________________________________________________

Benefit-to-Cost Ratio, 46:1

Page 4: T14 signal retiming results-manwell

SR A1A Traffic Signal Locations

SR 312

Sea Grove Drive / A Street

CR A1A / Beach Boulevard

Ocean Trace Road

Pope Road

16th Street

Dondanville Road

Page 5: T14 signal retiming results-manwell

SR A1A Signal Retiming Results

Corridor Results:

Length of Corridor, 3.2 miles

Benefits

Weekday Delay Reduction per Year (Hours): 122,051 Weekday Cost Savings per Year (Time): $1,054,518 Weekend Delay Reduction per Year (Hours): 43,403 Weekend Cost Savings per Year (Time): $375,005 Weekday Fuel Reduction per Year (gal): 233,996 Weekday Cost Savings per Year (Cost of Fuel $3.70/gal): $865,786 Weekend Fuel Reduction per Year (gal): 40,468 Weekend Cost Savings per Year (Cost of Fuel $3.70/gal): $149,731

Cost Savings per Year (Reduced Emissions): $10,616 Reduced CO emissions, 19.2 Metric Tons per Year Reduced NOx emissions, 3.7 Metric Tons per Year Reduced VOC emissions, 4.5 Metric Tons per Year

Total Cost Savings per Year: $2,455,656

_______________________________________________________________

Costs

Retiming Cost per Intersection: $8,653

Cost of Retiming 7 Intersections: $60,571

_______________________________________________________________

Benefit-to-Cost Ratio, 41:1

Page 6: T14 signal retiming results-manwell

SR 13 Traffic Signal Locations

Fruit Cove Woods Drive / Edgewater Drive

Davis Pond Boulevard

Roberts Road

Race Track Road / Fruit Cove Road

Page 7: T14 signal retiming results-manwell

SR 13 Signal Retiming Results

Corridor Results:

Length of Corridor, 2.0 miles

Benefits

Weekday Delay Reduction per Year (Hours): 332,655 Weekday Cost Savings per Year (Time): $2,873,616 Weekend Delay Reduction per Year (Hours): 41,297 Weekend Cost Savings per Year (Time): $356,728 Weekday Fuel Reduction per Year (gal): 103,160 Weekday Cost Savings per Year (Cost of Fuel $3.70/gal): $381,693 Weekend Fuel Reduction per Year (gal): 48,693 Weekend Cost Savings per Year (Cost of Fuel $3.70/gal): $180,163 Cost Savings per Year (Reduced Emissions): $5,859 Reduced CO emissions, 10.6 Metric Tons per Year Reduced NOx emissions, 2.1 Metric Tons per Year Reduced VOC emissions, 2.5 Metric Tons per Year

Total Cost Savings per Year: $3,798,060

_______________________________________________________________

Costs

Retiming Cost per Intersection: $8,653

Cost of Retiming 4 Intersections: $34,612

_______________________________________________________________

Benefit-to-Cost Ratio, 110:1

Page 8: T14 signal retiming results-manwell

SR 207 Traffic Signal Locations

SR 312

Holmes Boulevard / Rolling Hills Drive

Lightsey Road

Wildwood Drive

Hilltop Road

Page 9: T14 signal retiming results-manwell

SR 207 Signal Retiming Results

Corridor Results:

Length of Corridor, 4.0 miles

Benefits

Weekday Delay Reduction per Year (Hours): 55,550 Weekday Cost Savings per Year (Time): $479,950 Weekend Delay Reduction per Year (Hours): 29,059 Weekend Cost Savings per Year (Time): $251,070 Weekday Fuel Reduction per Year (gal): 93,044 Weekday Cost Savings per Year (Cost of Fuel $3.70/gal): $344,263 Weekend Fuel Reduction per Year (gal): 30,437 Weekend Cost Savings per Year (Cost of Fuel $3.70/gal): $112,616

Cost Savings per Year (Reduced Emissions): $4,707 Reduced CO emissions, 8.6 Metric Tons per Year Reduced NOx emissions, 1.7 Metric Tons per Year Reduced VOC emissions, 2.0 Metric Tons per Year

Total Cost Savings per Year: $1,192,606

_______________________________________________________________

Costs

Retiming Cost per Intersection: $8,653

Cost of Retiming 5 Intersections: $43,265

_______________________________________________________________

Benefit-to-Cost Ratio, 28:1

Page 10: T14 signal retiming results-manwell

QUESTIONS?

Mark Manwell

England-Thims & Miller, Inc.

[email protected]

(904) 265-3203

Fred Kyle

Prosser Hallock, Inc.

[email protected]

(904) 739-3655

Signal Retiming Improvements in St. Johns County