t801 msc in manufacturing: management and technology. chain dossier/supply_chain... · t801 msc in...

128
Don Carmichael P5893614 T801 MSc in MANUFACTURING: MANAGEMENT AND TECHNOLOGY Name: Don Carmichael Personal Identifier: P5893614 Title of Dissertation: Supply chain planning systems in manufacturing. Date: September 1998

Upload: others

Post on 19-Oct-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

  • Don Carmichael P5893614

    T801 MSc in MANUFACTURING: MANAGEMENT AND TECHNOLOGY

    Name: Don Carmichael

    Personal Identifier: P5893614

    Title of Dissertation: Supply chain planning systems in

    manufacturing.

    Date: September 1998

  • Don Carmichael P5893614

    Project Title : Supply chain planning systems in manufacturing.

    A dissertation submitted in partial fulfillment of the requirement for the MSc in

    Manufacturing : Management and Technology.

    The complementary fulfillment of the requirements for the MSc being the following

    Diploma Courses :

    Course Title Reg. Result Points

    Year

    PT613 Manufacturing Management 1994 Pass 30

    PMT605 Project Management 1994 Merit 15

    T833 Implementation of New Technologies 1995 Merit 30

    PT611 Structure & Design of Manufacturing 1995 Merit 30

    Systems

    M866 Relational Database Design 1996 Pass 15

  • Don Carmichael Page i P5893614 List of Contents

    List of tables iii

    List of figures v

    Glossary of abbreviations vi

    Preface vii

    CHAPTER 1 Summary 1

    CHAPTER 2 Introduction to the project 3

    2.1 The aims and objectives of the project 3

    CHAPTER 3 Background and literature review 5

    3.1 Introduction to Supply Chain Planning (SCP) 5

    3.2 The manufacturing interface 15

    3.3 Finite Capacity Scheduling (FCS) 17

    3.4 The ‘leaner’ issues 25

    CHAPTER 4 SCP packages 33

    4.1 Introduction 33

    4.2 Survey of SCP packages 34

    4.3 Commonalities 35

    4.4 Analysis 39

    4.5 Future directions 39

    4.7 Conclusions 40

    CHAPTER 5 Survey 41

  • Don Carmichael Page ii P5893614

    5.1 Introduction to the survey 41

    5.2 The survey and the methodology 41

    5.3 Results of the survey 47

    5.3.1 Analysis of the results 56

    5.4 Conclusions 59

    CHAPTER 6 Discussion and conclusions 60

    6.1 Discussion 60

    6.2 What does industry want ? 69

    6.3 How are SCP packages helping ? 70

    6.4 Future directions 72

    6.5 Main Conclusions 72

    CHAPTER 7 Future work 74

    7.1 The broad SCP arena 74

    References 75

    Appendices 79

    Appendix A - The Questionnaire 79

    Appendix B - Questionnaire Response Analysis 82

    Appendix C - Supply Chain Planning package features 103

    Bibliography 112

    Fundamental Readings in Supply Chain Management 112

    Production Aspects of Supply-Chains 114

    Organisational Contexts 118

  • Don Carmichael Page iii P5893614

    List of tables

    The following are a list of the tables found in the main body text of this dissertation.

    Table Page

    Table 3.3 Areas of conflict in the supply chain [3] 21

    Table 5.3.0.1 Tabular summary of questionnaire results with

    respondent number versus question number with answers. (1

    of 5)

    51

    Table 5.3.0.2 Tabular summary of questionnaire results with

    respondent number versus question number with answers. (2

    of 5)

    52

    Table 5.3.0.3 Tabular summary of questionnaire results with

    respondent number versus question number with answers. (3

    of 5)

    53

    Table 5.3.0.4 Tabular summary of questionnaire results with

    respondent number versus question number with answers. (4

    of 5)

    54

    Table 5.3.0.5 Tabular summary of questionnaire results with

    respondent number versus question number with answers. (5

    of 5)

    55

    Table 5.3.1.1 Results of MCS/CA survey as reported in

    Manufacturing Computer Solutions January 1997 showing

    selected issues and the number of companies seeing this as

    a priority as a percentage.

    56

  • Don Carmichael Page iv P5893614

    Table 5.3.1.2 The results of table 5.3.1.1 with the

    corresponding project survey question number and

    percentage of respondents claiming each issue as a problem

    or serious business problem.

    57

  • Don Carmichael Page v P5893614

    List of figures

    The following is a list of figures found in the main body of this dissertation.

    Figure Page

    Figure 3.1.1 The scope of supply chain management. Supply

    chain management covers the flow of goods from supplier

    through manufacturing and distribution chains to the end

    user. (From[13]).

    7

    Figure 3.1.2 A more manufacturing related order driven

    supply chain. (From [3]).

    14

    Figure 3.1.3 The author’s own model of a single business

    internal supply chain

    15

    Figure 3.4.1 The overall aim of manufacturing business

    improvement

    25

    Figure 3.4.2 Suppliers organised into functional tiers 29

    Figure 6.1 Number of weeks stock by country from the

    European Logistics Comparative Survey 1998. [22]

    66

  • Don Carmichael Page vi P5893614 Glossary of abbreviations

    SCM Supply Chain Management

    SCP Supply Chain Planning

    MRP Materials Requirements Planning

    MRP II Manufacturing Resource Planning (an extension of MRP)

    ERP Enterprise Resource Planning (an extension of MRP II)

    CBP Constraint Based Planning

    JIT Just-In-Time; a method of production, developed by Toyota,

    whereby only the parts needed are produced and only delivered

    to the next operation when required. This cuts out wastes in

    inventory, storage and over-production.

    BPR Business Process Reengineering

    CPG Consumer Packaged Goods; an industry sector

    FCS Finite Capacity Scheduling is a process whereby a production

    plan consisting of a sequence of operations to fulfill orders is

    generated based on the real capacity of resources. These can

    be machines, operators, tooling or anything which is a constraint

    on the production process.

    ECR Efficient Consumer Response

    There are several companies mentioned and referenced throughout this dissertation.

    These companies are the market leading developers of two types of software system

    being :

  • Don Carmichael Page vii P5893614

    • Supply Chain Planning vendors; the two leaders being ‘i2’ Technologies with the

    Rhythm product and Manugistics. Other vendors, such as Numetrix and SynQuest

    are recognised as contenders for third place [16].

    • ERP vendors; the four market leaders are conveniently covered by the acronym

    ‘BOPS’ meaning BAAN (with the BAAN IV product), Oracle (with the Oracle

    Financials, Oracle Manufacturing, GEMMS and CPG package offerings),

    Peoplesoft (including it’s ‘Red Pepper’ supply chain optimisation system) and SAP

    (with the R/3 product). Other players and leaders in the American mid-market

    sector according to the authoritative industry analysts Gartner Group, are SSA

    (with the BPCS product) and QAD (with the MFG/PRO package).

    Preface

    Thanks are extended to the authors supervisor Dr. John Wright for his help and

    enthusiasm throughout the project.

  • Don Carmichael Page 1 P5893614

    CHAPTER 1 Summary

    ‘The best company cannot be competitive if it is part of a supply chain which is

    inefficient and ineffective’. [1]

    Dr. Canadine, of the Institute of Logistics, believes that leading edge companies are

    beginning to understand that competition and competitive advantage is not being

    played out between individual companies but by competing supply chains.

    In support of this a new breed of software vendors have developed supply chain

    planning (SCP) software packages which utilise concurrent optimisation algorithms

    to produce the optimum supply chain configuration and schedule. The optimum

    configuration and schedule may be based on lowest cost, material or capacity

    constraints, customer due date adherence or a user defined combination of optima.

    This dissertation describes the basic functionality to be found in supply chain

    planning systems and the often confusing coexistence of supply chain management

    systems.

    A survey by questionnaire across a random sample of manufacturing companies

    was undertaken and the dissertation analyses the data to come to a number of

    conclusions. Certainly, in the U.K, most manufacturers are still concerned with

    internal issues such as cost savings within manufacturing. There is little

    comprehension of the effects of each manufacturer’s (or supplier’s) place within the

  • Don Carmichael Page 2 P5893614 supply chain apart from specific industries such as the Automotive industry where

    lean manufacturing methods have led to strong partnerships between automotive

    companies and their tiers of suppliers.

    The dissertation continues by exploring the reasons why the mainly American supply

    chain planning vendors have experienced such explosive growth in the USA. This

    growth is mainly to do with the immense potential for cost savings in the long lead

    times found in US supply chains, 105 days average replenishment times as

    compared to 38 days in the UK. This potential is further enhanced when

    consideration is given to the vast US geography and thus the large transportation

    costs. The US tends to be supply constrained, controlled by the manufacturer /

    supplier, rather than demand constrained, controlled by the retailer / customer, as is

    the situation in the UK. This means that manufacturers / suppliers in the US have the

    opportunity to optimise their own supply chains to their customers.

    The dissertation concludes by agreeing in part with some of the SCP vendors, such

    as Manugistics, who believe that their biggest task in the short term is education.

    The results of the author’s survey and other sources suggest that in the U.K, and

    perhaps in most of the EC, SCP vendors may find that there are neither the supply

    chain inefficiencies to justify the high SCP package costs nor the level of interest in

    SCP systems in America.

  • Don Carmichael Page 3 P5893614 CHAPTER 2 Introduction to the project

    2.1 The aims and objectives of the project

    It is now widely recognised that companies are no longer competing against other

    companies. Whole supply chains are now competing against each other.

    The pressures of modern business, the global community, customers expectations of

    personalisation and rapid delivery and the continuing need to reduce costs are all

    changing the way companies view themselves. The challenge now is to optimise and

    employ ‘lean’ principles across all a company’s relationship boundaries.

    The project concentrated itself on the rise of the supply chain planning software

    package, it’s roots in Finite Capacity Scheduling software products and the ‘softer’

    issues of the ‘lean’ enterprise.

    The aims of the project were to :

    1. gather together the current academic and recognised industry analyst knowledge

    to produce a picture of where supply chains are changing, and why. The focus of

    this was the effects on manufacturing with special emphasis on the ‘lean’

    manufacturing / enterprise revolution.

    2. match this against the experiences of real manufacturers coping with the

    demands placed on them by the great shift in supply chain complexity. The aim

    here was to find any conflicts in perceptions and views and compare these against

  • Don Carmichael Page 4 P5893614

    the book research results. This was achieved through the use of a survey by

    questionnaire and ultimately through comparison with the results of other similar

    surveys.

    3. generally describe Supply Chain Planning (SCP) package functionality and then to

    discuss how such a package addresses the supply chain pressures manufacturing

    and distribution companies are facing.

    4. detail further work required in this subject area and to surmise on the functionality

    requirements future SCP packages should include.

  • Don Carmichael Page 5 P5893614

    CHAPTER 3 Background and literature review

    3.1 Introduction to Supply Chain Planning (SCP)

    Supply chains are the supplier / manufacturer / distributor channels, networks and

    relationships [3] in manufacturing or services supply. A good short-hand describing

    some food supply chains would be the ‘plough to plate’ analogy, recently used in

    British food hygiene political discussions.

    The complexity and length of supply chains is increasing, as for example in the

    automotive industry. The Society of Motor Manufacturers and Traders (SMMT)

    ‘Passenger Car Logistics Survey’ [4] results show that by the year 2000 the average

    number of components or sub-assemblies car manufacturers believe a car will be

    assembled from is nine. This will have a massive impact along the automotive supply

    chain from Tier 1 (direct to car manufacturer) suppliers to Tier 3 (electrical sub

    components for dashboard assemblies, for example) and beyond. Design,

    manufacturing and assembly responsibility will be passed down automotive supply

    chains through closer and closer partnerships with suppliers. This, along with other

    ‘lean thinking’ ideas, was predicted in Womack et al’s ‘The Machine That Changed

    The World’ [5]; the lean production book.

    Manufacturing and supply planners are now having to consider a complex supply

    chain network as opposed to a single supplier / customer relationship [6]. The flow of

  • Don Carmichael Page 6 P5893614 information up and down supply chains is becoming more important than anything

    else.

    ‘The economy is changing structure. From being organised around the flow of things

    and the flow of money, it is becoming organised around the flow of information [7].’

    This statement by Peter Drucker is emphasised in the report on ‘ICL’s Logistics

    Strategy’ in the ‘International Journal of Logistics Management’ [3].

    ICL believe the most important feature of their supply chain is the flow of information.

    Excess inventory (stock) is seen as an undesirable result of imbalanced processes

    and the cost of that inventory is seen as being greater than the cost of managing the

    flow of information effectively. ICL’s predominant emphasis within their logistics

    strategy is to develop Information Technology (IT) applications that enhance logistics

    performance. Information must be substituted for inventory as the main trade-off for

    achieving customer service all along the supply chain.

    Figure 3.1.1 below is a good demonstration of a possible simplistic internal supply

    chain showing all of the potential inventory stocking points within one company and

    thus all of the points where excess inventory can be held. If this is multiplied by the

    network of different companies making up supply chains, one can see how big a

    potential problem excess inventory can be.

  • Don Carmichael Page 7 P5893614

    S u p p lie r s

    O rd e r s

    P r o c u r e m e n t M a n u fa c tu r in g F a c to r y D is tr ib u t io n C u s to m e r E n d u s e r s

    R a w m a te r ia l

    In -p ro c e s s

    D is tr ib u t io n S e ll in g p o in t

    Figure 3.1.1 The scope of supply chain management. Supply chain management

    covers the flow of goods from supplier through manufacturing and distribution chains

    to the end user. (From[13]).

    On top of all the above, business transactions are becoming faster and faster [8].

    Customer requirements have become more sophisticated. Product life cycles have

    reduced dramatically in most industries and competition has become global.

    In the past, focus on output value (local optima, as Goldratt puts it [9]), led to

    performance measures such as those based on standard hours, direct labour

    efficiency, factory output value and overhead recovery on direct labour. It was

    identified that the focuses on inventory and customer service were missing.

    This is highlighted when it is noted both that :

  • Don Carmichael Page 8 P5893614 1. ICL identify 80% of their costs as being material (other sources seem to average

    material costs across all manufacturing to about 58%) and that

    2. customer service features highly in modern supply chain techniques such as

    Efficient Consumer Response (ECR) [10].

    The major task for ICL is the management of material within an efficient international

    logistics chain.

    If companies such as ICL have identified the need for both an efficient logistics chain

    and IT applications to enhance the logistics performance, it is perhaps a surprise to

    learn that only 20% of U.S logistics professionals believe that IT systems are well

    integrated with the logistics processes in their company [11].

    This is not to say that U.S logistics professionals are against IT; most respondents of

    the KPMG survey [11] said that they thought IT was an ‘important tool’ and would

    ‘significantly improve logistics’. It can be seen that even in the U.S, who tend to be

    ahead of the UK in the take-up of IT systems, there is still a requirement and a

    market gap for IT systems to fully support supply chain logistics.

    At this point it is worth resolving the difficulties and confusion that may arise from

    using ‘supply chain’ terms and ‘logistics’ terms.

    During the literature review for this dissertation several sources defined the link

    between supply chain terminology and logistics thinking. ‘Supply chain’ terminology

  • Don Carmichael Page 9 P5893614 is a fairly recent invention as opposed to ‘Logistics’ terms and terminology, which is

    much older coming from the Napoleonic campaigns.

    Greenwood in the Institute of Logistics journal [12] believes that

    ‘if we analyse what the experts are calling supply chain management we find that

    they are really talking logistics but driven by the requirement of the decade’.

    Greenwood believes that supply chain management would be called ‘Demand Chain

    Management’ if the process were more fully understood. Further, Bowersox believes

    that the issues of logistics and supply chain management are practically

    synonymous [2]. The American magazines Distribution (January, 1996) and

    Purchasing both define Supply Chain Management (SCM) as interchanges or

    combinations of logistics processes.

    Many Manufacturing Resource Planning (MRP II) systems (especially those that

    have migrated into Enterprise Resource Management (ERP) systems to handle

    multiple currencies, multiple companies and multiple sites) are now calling their

    products Supply Chain Management (SCM) systems. As an example, the MRPII

    product the author used to work with, MFG/PRO by QAD, now calls itself a Global

    Supply Chain Management system.

    It is important to distinguish between two clearly definable IT systems solutions that

    address supply chain issues :

  • Don Carmichael Page 10 P5893614 1. the MRP II/ERP products, ‘relabeled’ as SCM products. For example, BAAN IV

    (Series), Oracle Manufacturing, SAP R/3 and SSA’s BPCS, are ‘transaction’

    systems; handling, for example, purchasing, sales and forecasting, shop floor

    production, quality and inventory transactions.

    2. true Supply Chain Planning (SCP) products, aimed at planning the supply chain

    as a whole. The system vendors here, such as Numetrix [13], Red Pepper,

    Manugistics and SynQuest believe that their products are the true supply chain

    management products.

    The key to the real definition, for these SCP vendors, revolves around the system’s

    ability to understand, integrate and optimise the complete supply chain from

    supplier’s supplier to customer’s customer; to create the optimal sourcing, production

    and distribution plan. The aim of these SCP products is to react to the speed of

    change of business across the supply chain and create, for example,

    • the best splits across suppliers considering supplier capacity and availability.

    • the least ‘total acquisition’ cost distribution solution.

    • the best customer service level that can be achieved with the current demand plan

    and workforce resourcing rules.

    Keith Burgess, a consultant with KPMG’s Supply Chain Management Systems

    Group, [14] defines the goals of advanced supply chain planning systems as being:

  • Don Carmichael Page 11 P5893614

    • rapid optimisation of the total supply chain,

    • making available ‘what-if’ functionality – to test the effect of possible events on

    the total supply chain,

    • the ability to cope quickly with unforeseen problems,

    • flexible scheduling – allowing for more than the first-in-first-out (FIFO) approach

    adopted by most MRP systems, and

    • the ability to provide accurate and flexible information about the supply chain.

    These products logically sit above MRP II/ERP systems but require these transaction

    based systems to enact, record and feedback the optimised demand, supply and

    production plan.

    Most MRP II / ERP packages still rely on the Materials Requirement Planning (MRP)

    algorithms, invented in the 1960’s and defined by Orlicky [15], as the only constraint

    planning mechanism. However, the recognition of the importance of SCP products

    by the MRP II/ERP product vendors has arrived by a number of announcements

    reported over the last few months via the AMR Alert on Supply Chain Management

    Email series [23] being that :

  • Don Carmichael Page 12 P5893614 • Peoplesoft bought the SCP vendor Red Pepper to use a basis for a full ERP

    offering.

    • BAAN announced a constraint based planning (CBP) module, based on a product

    BAAN bought called MOOPI.

    • SAP announced a new module developed in-house within SAP called the

    Advanced Planner and Optimiser (APO) within SAP’s Supply Chain Optimisation,

    Planning and Execution (SCOPE) Initiative.

    • Both BAAN and SAP announced strategic alliances with the three top SCP

    product vendors ‘i2’ Technologies, Manugistics and Numetrix [16].

    Confusion still exists over the definition of supply chain management. Even

    Advanced Manufacturing Research (AMR), the leading industry analysts along with

    Gartner Group, still call SCP products SCM systems [16].

    For the rest of this dissertation the author will try to avoid any confusion by using the

    term ‘Supply Chain Planning (SCP)’ system to differentiate these supply chain

    optimisation products.

    White in Control [17] defines Supply Chain Planning (SCP) as

    ‘a constraint- based ‘decision support’ or planning tool that includes the following:

    Item Forecasting; Promotion and Event Planning; Item Inventory Planning;

  • Don Carmichael Page 13 P5893614 Replenishment Planning, incorporating Distribution Requirements Planning (DRP)

    and various Continuous Replenishment Strategies; Manufacturing Planning and

    Scheduling’.

    White sees Supply Chain Planning as the keystone to Supply Chain Management.

    The dissertation will investigate the effects that recently available Supply Chain

    Planning (SCP) software packages will have on manufacturing issues. This will be

    achieved by :

    • book research,

    • a survey by questionnaire,

    • and an investigation into the general functionality of a range of these packages

    As the dissertation confines itself to the effects of SCP on manufacturing, the scope

    of what is meant by manufacturing should be defined. Bowersox [2] defines

    manufacturing support within logistical integration as being

    ‘… managing work-in-process inventory as it flows between stages of

    manufacturing’.

    Figure 3.1.2 shows a more order related view of a supply chain and where in-

    process inventory sits within this environment.

  • Don Carmichael Page 14 P5893614

    The overall concern is not how production occurs but the what, when and where

    products are manufactured. Bowersox believes that whereas physical distribution

    must accommodate the uncertainty of consumer and industrial demand,

    manufacturing is under the control of the manufacturing enterprise.

    From Supplier Throughmanufacturing

    And distributionchain

    To the end user

    Supply chain

    Pro-curement

    order

    Rawmaterialinventory

    Shoporders

    In-processinventory

    MPS orders

    Finishedfactory

    inventory

    Factoryorders

    Distributioninventory

    Distri-butionorders

    Sellingfrom

    inventory

    Cust-omerorders

    Supplier Customer

    Figure 3.1.2 A more manufacturing related order driven supply chain. (From [3]).

    Figure 3.1.3, below, is a simplistic version of the supply chain diagrams used by the

    author to explain how information and inventory flow through a business.

    The company is the box split into information flow from right to left and material flow

    from left to right. To the right hand side of the box is the direct customer and to the

    left the supplier. The planning function is basically a balancing function to take the

    demand, in whatever form it is presented (sales orders, forecasts, planned inventory

    levels etc.), and convert the demand into

  • Don Carmichael Page 15 P5893614 1. What to make (produce, convert, pack, assemble etc.) and

    2. What to buy

    The box is used to demonstrate that a company is one unit and not a series of

    departments. Information generally flows from the front of the business to the back

    and materials the opposite direction.

    - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

    Planning

    What-to-buy

    What-to-make

    INFORMATION FLOW

    MATERIAL FLOW

    ValueAdded

    Purchasing

    Supply Dispatch and Distribution

    Demand

    Figure 3.1.3 The author’s own model of a single business internal supply chain.

    3.2 The manufacturing interface

    Dr. Canadine, the Director-General of the Institute of Logistics [1], calls

    manufacturing a ‘micro-logistics’ process, an individual section of a much larger

    supply chain. Micro-logistical thinking, says Canadine, has led to the development of

    Kanban, Just-in-Time, MRP and MRP II. Thinking of a manufacturing ‘interface’ is

  • Don Carmichael Page 16 P5893614 actually unhelpful as organisational boundaries are the enemy of the cross functional

    thinking that is required to optimise and understand supply chains.

    In Hill’s book ‘Manufacturing Strategy’ [28] there is much to convince the reader that

    business, marketing, manufacturing and thus all supply chain strategic issues all

    have to be considered at once. The traditional view is of business plans being split

    into sales / marketing plans and then handed to manufacturing to consider how the

    production targets can be met.

    There is a ‘macro-logistics’ strategic level where the design and control of the supply

    chain takes place and where issues such as :

    • the location of markets,

    • where to place manufacturing capacity,

    • which components to outsource and which to manufacture,

    • and how to resource service and maintenance

    are considered.

    So, in conclusion, manufacturing has to be considered as part of the whole supply

    chain and not spilt off as a separate entity as it is in ‘traditional’ logistics thinking

    within some companies.

  • Don Carmichael Page 17 P5893614

    3.3 Finite Capacity Scheduling (FCS)

    Production planners invariably claim to have picked the optimum production plan

    considering customer due date adherence, optimal throughput, mix and optimal cash

    usage. In manual production planning environments which require anything more

    than simplistic optimisation rules using ‘rules of thumb’ and experience, humans

    cannot, or rarely, actually achieve optimisation.

    A series of highly graphical software products have been developed to enable

    complex optimisation to be achieved. These are called finite capacity scheduling

    (FCS) products (or finite schedulers) with product names such as Preactor, CIM

    Leitstand, FI-2, and ‘i2’-Rhythm, SAP-APO for the supply chain variants .

    As of the middle of 1996 it was reported in an Aston Business School manufacturing

    technology survey [18] that about 19% of respondents used FCS products.

    One vendor of FCS products defines FCS as :

    ‘a process whereby a production plan consisting of a sequence of operations to fulfill

    orders is generated based on the real capacity of resources. These can be

    machines, operators, tooling or anything which is a constraint on the production

    process.’

    The reason FCS came into being was that most manufacturing planning systems

    assume sufficient resources are available when required, i.e. resources have infinite

  • Don Carmichael Page 18 P5893614 capacity. An MRP system typically takes the orders for products, breaks them down

    into component parts and calculates when to start making them based on the

    individual lead times. No account is taken of the current available capacity of

    resources.

    At the same time that the production order start times are calculated, the materials

    needed are ordered to arrive in time for the work to start. If there is a delay in

    production upstream of a particular operation then the materials will be ordered too

    early. With no concept of bottlenecks available to the planning system, resources

    become overloaded, queues of work get longer and work in progress increases.

    Because jobs must join the queues at each process step, orders take longer to make

    progress, expected lead times are too optimistic and deliveries are late.

    FCS software tools are commonly integrated or interfaced into the MRP II business

    systems. An FCS tool requires information on resource and work centre capacity,

    shift calendars, the current usage of that capacity and the Master Production

    Schedule (MPS), or list of production orders. The FCS generally either

    • returns an optimised version of the MPS back to the MRP II system for execution

    or

    • takes control of the MPS where the execution system is linked directly to the

    FCS.

  • Don Carmichael Page 19 P5893614 Here, the execution system is the shopfloor control and feedback mechanism

    initiating and recording production actuals.

    Simpler FCS systems consider all constraints or bottlenecks in production as ‘hard’

    constraints. This means that if the right machine, operator and tooling have to be

    available at the same time to produce a particular production order then the FCS

    system has to determine a time when all three resources are free. It is worth pointing

    out that the more constraints defined for a FCS, the more complex the calculations

    become. Each constraint can be thought of as a dimension of calculation.

    More complex FCS systems and certainly those built into the Supply Chain Planning

    systems considered in this project have the concept of ‘soft’ constraints built in.

    In the author’s experience, if manufacturing planners are asked how they resolve a

    scheduling conflict if a rush order arrives and tools, for example, are not available,

    they tend to suggest buying in additional tooling. Thus tooling, in this case, can no

    longer be described as a constraint, merely a cashflow ‘penalty’ for having to

    purchase the tools.

    The machine or plant required to run the rush order was a ‘hard’ constraint but the

    tools were a ‘soft’ constraint. It can be seen then that the optimal plan across a

    series of resources may be a compromise that produces the least penalty.

  • Don Carmichael Page 20 P5893614 The penalty may be simply in cash terms say or if we now consider the FCS

    functionality (or ‘simultaneous constraint optimisation’ as the SCP vendor Red

    Pepper calls it) in SCP systems, the constraints and thus penalties could include :

    • Promise dates,

    • Request dates,

    • Inventory shortages,

    • Aggregate capacity,

    • Safety stocks,

    • Excess stocks and

    • Raw material shortages.

    On top of these ‘hard’ and ‘soft’ constraints there are other scheduling complexities

    that the better products have to consider such as sequencing environments, colour

    sequencing for example.

    This is where the optimal plan for producing a product made in different colours is

    usually to produce the lighter coloured products first and then the progressively

    darker colours thus minimising the cleaning time between colours.

    Other constraints can include

    • Shelf life,

    • Ramp up curves and

    • Scheduled maintenance.

  • Don Carmichael Page 21 P5893614

    Impact of objectives on …

    Functional objectives

    Inventory

    Customer

    service

    Total costs

    High customer service

    Low transportation costs

    Low warehousing costs

    Reduce inventories

    Fast deliveries

    Reduce labour costs

    Desired results

    Table 3.3 Areas of conflict in the supply chain [3]

    In the above table 3.3, the arrows point upwards for increases in inventory, customer

    service and total costs and downwards for resulting decreases in the set objectives.

    The darker arrow signifies the main desired impact of a functional objective, for

    example, the desired impact of a functional objective to reduce labour costs will

    reduce total costs but will also have the effect of increasing inventory and decreasing

    customer service.

    The table is trying to demonstrate the essential conflict of management objectives

    and measures across organisational boundaries across the supply chain.

  • Don Carmichael Page 22 P5893614

    Some SCP packages attack some of these conflicting objectives by presenting users

    with a mechanism to tell the SCP package the weighting the business places on

    particular management objectives. Thus, if the business objectives of customer

    service should be considered more important than excess stock then the SCP’s

    optimisation engine will determine that there is a higher ‘soft’ penalty for customer

    service and will therefore produce a stocking plan that may require more stock than

    absolutely necessary because there is a lower ‘soft’ penalty for excess stocks.

    Within the SCP product ‘Red Pepper’, there is a screen called the ‘ResponseAgent’

    Control Panel where the user moves a pointer up and down a meter representing 0

    to the left and 100 to the right to signify the weighting to be applied to :

    1. Request Dates,

    2. Promises Dates,

    3. Inventory Shortages,

    4. Aggregate Capacity,

    5. Safety Stocks,

    6. Excess Stocks and

    7. Raw Material Shortages.

    The ‘ResponseAgent’ tool uses all the meter readings to determine the relative

    penalties to be applied to each objective (or constraint as ‘Red Pepper’ call it) and

    then optimises all the constraints concurrently.

  • Don Carmichael Page 23 P5893614 Appendix C covers the detailed scheduling features of one SCP vendor’s package.

    The reason only one package is covered at the detail given is that the vendor,

    Numetrix, was the only company willing to detail the constraints covered.

    As a comparison, another SCP vendor, Logility, limits it’s description of the

    constraints covered to

    ‘equipment capabilities, intermediate storage limitations, shop calendars and

    production constraints such as synchronisation of multi-step operations, product

    sequencing, changeovers and inventory policies.’

    This comes back to a reoccurring theme with all SCP vendors in that they all

    complain that there is a broad lack of understanding of the SCP issues, benefits and

    product capabilities and yet hardly any of them will release information at a detailed

    enough level to examine the exact capabilities of each product.

    In the SCP vendors defence, they are competing in a extremely fast-moving and

    growing marketplace where functionality evolves almost weekly. Most SCP vendors

    seem to sell by :

    • fighting for the opportunity to develop a proof of concept pilot at the sales

    prospect’s plant,

    • using reference sites (current SCP customers) with proven demonstrable benefits

    realised through the SCP products.

  • Don Carmichael Page 24 P5893614 It may be that giving away too much information at the start of the sales cycle allows

    prospects the opportunity to perform direct functionality comparisons which the SCP

    vendors are unwilling to take part in.

  • Don Carmichael Page 25 P5893614

    3.4 The ‘leaner’ issues

    Through-put

    Produc-tivity

    Quality Morale

    Inventory WIP Operating Costs

    IMPR

    OVE

    RED

    UC

    E

    Figure 3.4.1 The overall aim of manufacturing business improvement

    The main objectives of a manufacturing business improvement exercise are shown

    in Figure 3.4.1.

    However, Figure 3.4.1 shows the utopian view of the business objectives. As we

    have seen, there are internal and external conflicts which may mean that a reduction

    in inventory, say, increases overall operating costs. One reason for this may be

    because the resulting reduction in customer service levels mean that more cost is

    required to replace the lost customers.

    So far this project has dealt with the ‘hard’ or more technical issues surrounding

    SCP. For supply chain planning to be effective, the ‘soft’ issues, i.e. relationships

  • Don Carmichael Page 26 P5893614 with the customer / consumer and the supplier, need to be developed. To achieve

    the utopian view in Figure 3.4.1, business improvement needs to address both the

    hard and soft issues simultaneously. This section deals with the ‘soft’ issues by

    examining the lean production revolution and the focus on relationship and value.

    In ‘The Machine That Changed The World’ [5], the lean production book, Womack et

    al. stress how important organisation, communication and relationships throughout

    the supply chain were to Eiji Toyoda and the production ‘genius’ Taiichi Ohno (the

    originators of the Toyota Production System which ultimately developed into lean

    production ideas).

    In considering an alternative to the mass-production method of car manufacture,

    Ohno and others at Toyota saw many problems with the traditional supply chain

    relationships :

    • component suppliers had little incentive to improve or optimise their parts as the

    design information on the rest of the vehicle was seen as proprietary.

    • ‘organising suppliers in vertical chains and then playing them against each other

    in search of the lowest short-term cost blocked the flow of information between

    suppliers.’ Suppliers were unable to share organisational and process /

    technological improvements.

  • Don Carmichael Page 27 P5893614

    The car assembler ‘might ensure that suppliers had low profit margins, but not

    that they steadily decreased the cost of production through improved organisation

    and process improvement’.

    • if the car assembler knew little of the component suppliers production techniques

    then it would be difficult to improve quality beyond specifying maximum levels of

    defects. It would be difficult to raise the quality level if most other suppliers

    achieved similar levels. Of course, quality of the components impacted the quality

    and perception of the finished good, in this case the car.

    • the coordination of day-to-day supplies from the supplier proved to be very

    difficult. Because of the inflexibility of suppliers’ tooling and the uneven demand

    from the car assembler, the suppliers built up large stocks into warehouses

    resulting in high inventory costs and the ‘routine production of thousands of parts

    that were later found to be defective’ when assembled into the cars.

    Toyota’s answer to the inflexibility of their own and their supplier’s tooling

    changeovers developed ultimately into the SMED (Single Minute Exchange of Dies)

    techniques which allowed rapid changeovers from production of one type of part on

    a press, say, to another. This technique was certainly critical to the whole ‘Just-In-

    Time’ or kanban system of which so much has been written.

    The kanban technique is a ‘pull’ system whereby a customer buys a product and

    only a minimum quantity of the product or components (the aim being a single

    instance of a product) is made at each stage to replenish the product pulled from the

  • Don Carmichael Page 28 P5893614 stage in front. The mechanism to control this was the product container carrying the

    parts to the next stage. As this technique was to be used across the whole supply

    chain, almost all inventories were eliminated at Toyota’s and Toyota’s suppliers

    plants and warehouses and the full fragility of the ‘JIT’ supply chain was exposed.

    Because there was no or minimal buffer stock between each supplier and process,

    as soon as a single process failed the whole system came to a stop. The idea was

    that any quality or process failure should have been anticipated.

    Certainly, Womack’s book [5] reports that lean manufacturers using these

    techniques rapidly focus on process and component quality and generally achieve

    quality figures 3 times better than traditional mass production plants.

    Toyota’s answers to the ‘softer’ issues being supplier organisation, communication

    and relationship problems, resulted in the development of a new lean-production

    approach to component supply.

    This new approach meant that suppliers would now be intimately involved in

    Toyota’s product development, have interlocking equity with Toyota group members,

    rely on Toyota for outside financing of capital investment projects and accept Toyota

    people as their own personnel.

    The suppliers were organised into functional tiers, whatever the legal or formal

    relationship. First tier suppliers became an integral part of the product development

    team and were given overall performance and cost specifications for major sub-

    assemblies. The supplier was given free reign on the engineering decisions and was

  • Don Carmichael Page 29 P5893614 expected to interrelate with the other tier 1 suppliers. Tier 1 suppliers were expected

    to form tier 2 supplier organisations or associations which would concentrate on the

    fabrication of the individual components making up the major sub-assembly.

    Automotive Supplier 1

    Tier 1 Supplier

    Tier 1 Supplier

    Tier 2 Supplier

    Tier 2 Supplier

    Tier 2 Supplier

    Automotive Supplier 2

    Figure 3.4.2 Suppliers organised into functional tiers

    In Figure 3.4.2 above the Automotive suppliers are seen at the top of the supply

    chain and their suppliers organised into :

    • Tier 1 suppliers who supply major sub-assemblies direct to the automotive

    supplier;

    • Tier 2 suppliers, usually specialist manufacturers, who supply the Tier 1

    suppliers.

    • Tier n suppliers exist beneath this structure (not featured in the Figure 3.4.2

    above); ultimately, down to the raw material extractors, rubber plant for tyres, ore

    for metals etc.

  • Don Carmichael Page 30 P5893614 A point to note about Figure 3.4.2 is that Tier 1 suppliers will often be supplying

    multiple car assemblers. In Toyota’s case, Tier 1 suppliers, which may be part

    owned by Toyota or have previously been Toyota in-house assembly operations, are

    encouraged to perform work for other industries or assemblers. This would generally

    be seen as producing higher profit margins.

    Womack’s ‘lean manufacturing’ book [5] reports that Nippondenso, a $7 billion

    company, is the largest manufacturer of electrical and electronic systems and engine

    computers. Toyota holds 22 % of its equity and Nippondenso does 60% of its

    business with Toyota. Another 30% of the equity is held by the Toyota supplier group

    of companies, and 6% by Robert Bosch, the giant German components firm.

    The cross ownership that proliferates within Toyota’s supply chain has some

    parallels outside Toyota such as Ford’s purchase, or part ownership, of the Eastern

    European Autopal headlamp manufacturing plants.

    Toyota also shares personnel with it’s suppliers and helps out with workload surges.

    In summary, it can be seen that Toyota, as the original lean manufacturing company,

    has developed very high levels of communication, resource and fiscal interaction

    with it’s suppliers. Toyota’s suppliers can be seen as sharing Toyota’s destiny.

    Of course, it must be remembered that although automobile manufacturing is an

    important business activity it cannot be seen as representative of all industries, types

    of production or manufacturers place within the supply chain. Toyota, in common

  • Don Carmichael Page 31 P5893614 with other car manufacturers, lives at the top of the supply ‘food chain’ and therefore

    has the opportunity and power to change their suppliers and supply chains. Without

    the help of the ultimate car assembler, it can sometimes be difficult for Tier 2

    suppliers to develop the levels of communication and relationships required to

    achieve a lean supply chain with their own suppliers.

    The Odette ‘Passenger Car Logistics Survey’ [4] showed that Tier 2 or 3 suppliers

    can often be larger than the direct, Tier 1, suppliers. An example here could be a

    dedicated dashboard assembly supplier to two or three automobile assemblers with

    a company like Lucas, say, supplying the instrumentation to the dashboard

    assembler.

    It is interesting to note the similarities between Lean Manufacturing principles (as

    derived from the Toyota Production System), Value Engineering and business

    process re-engineering.

    A definition of business process re-engineering (BPR) from Thomas Gunn’s real-time

    enterprise book [8] is:

    ‘The improvement of business processes by a cross-functional team that first seeks

    to understand and document the entire process, then simplifies and removes the

    waste from it, then applies information systems to improve the speed and quality of

    the process as well as improve it’s flexibility and the productivity of the people

    associated with it.’

  • Don Carmichael Page 32 P5893614 It seems a core principle in Value Engineering, Lean Manufacturing and BPR is the

    reduction of waste and the concentration on the value added functions.

  • Don Carmichael Page 33 P5893614

    CHAPTER 4 SCP packages

    4.1 Introduction

    Investigating the functionality of Supply Chain Planning (SCP) packages proved very

    difficult. Most SCP suppliers are willing to provide high level glossy brochures and

    impeccable references but have no detailed system or functionality descriptions. The

    reasons for this appears to be that the SCP sales environment is highly competitive

    and functionality is rapidly expanding, especially with the two market leaders

    Manugistics and ‘i2’.

    A SCP sales cycle involves the use of reference sites and paid proof of concept

    projects. These projects are short-term, limited implementations of the product within

    the customers own site. The SCP software package will be configured to represent a

    limited version of the customer’s supply chain and manufacturing environment and

    then loaded with a sub-set of the customer’s business data so that the concept,

    feasibility, justification and potential cost savings can be demonstrated. The

    customer can then decide whether to commit to the whole project.

    As a result of the above, SCP vendors feel they do not have to provide highly

    detailed system descriptions.

  • Don Carmichael Page 34 P5893614 4.2 Survey of SCP packages

    As of late 1997 the main SCP suppliers competing in Europe were:

    • ‘i2’ -Rhythm – primarily focused on the Electronics sector

    • Manugistics – focused on the Consumer Packaged Goods (CPG) sector

    • Numetrix – focused on the Process sector

    • ‘Red Pepper’ / Peoplesoft

    • SynQuest

    • American Software

    Materials gathered and analysed include the sales literature from Manugistics,

    Numetrix with it’s ‘Supply Chain Visibility / Integrator’ and ‘i2’ with the ‘Rhythm’

    product (the big three according to AMR [16]) with the addition of SynQuest

    materials.

    It was initially thought that there could have been difficulty in getting even access to

    SCP system vendors high level glossy brochures. However, the author’s employer is

    an MRP II systems house, and thus a potential partner for SCP vendors. The author

    has been able to use this influence to source a set of product literature for each of

    the major SCP packages.

  • Don Carmichael Page 35 P5893614 4.3 Commonalities

    All SCP packages extend finite capacity scheduling (FCS) concepts into supply

    chain and distribution concepts, for example by being able to consider a single

    machine capacity bottleneck and it’s impact across a whole supply chain. All the

    packages are capable of simultaneous optimisation against a range of factors

    including set business goals; particular service level commitments, inventory value

    limits, supply limitations and overtime constraints. Some packages talk about using

    ‘life’ type random algorithms to produce the best optimisation across all constraints.

    The better packages have extended their functionality into Transportation

    Management, Demand Management and specific ‘improvement’ algorithms for

    particular industry sectors. This may mean specific sequence dependant

    optimisation algorithms for paint mixing plants say, where if a darker colour follows a

    lighter coloured paint less cleaning time is needed than when a lighter colour follows

    a darker where a complete clean-down is required.

    The more sophisticated packages cope with ‘soft’ penalty optimisation where the

    ‘best’ plan may be the one where the least amount of overtime payments are made.

    Most packages appear to have sophisticated graphics that can visually show the

    effect of different ‘what-if’ distribution plans and their effect on cash-flow and

    machine capacity. Certainly, most packages allow users to graphically describe

    machines, interdependencies and geographical locations of plants and warehouses.

    This capability was ably demonstrated by SynQuest at the CIM 97 show at the

    Birmingham NEC.

  • Don Carmichael Page 36 P5893614 Most SCP packages were originally built on UNIX computer operating system

    platforms. The reason for this is that SCP packages achieve their characteristically

    rapid and near ‘real-time’ scheduling responses by utilising fast stand-alone

    computers with huge amounts of Random Access Memory (RAM) memory. In the

    early days of SCP developments, UNIX was ideally suited for this. Additionally,

    UNIX, in most of it’s versions and variants, had a graphical user interface that can be

    used on UNIX workstations.

    Most SCP products are ‘client server’ products. This means that there is a powerful

    central ‘server’ computer (or computers) performing the intensive calculations and

    data transactions for the multiple graphical ‘client’ workstations (or more usually

    Personal Computers). This can be imagined as a star configuration with many

    ‘clients’ connected to the central ‘server’ computer. As the client computers are,

    themselves, moderately powerful, some of the computing load is offloaded from the

    server onto the client. This is especially the case for intensive graphical tasks.

    The reason for the large computer memory requirement is that SCP products place

    as much of the business data (sales orders, stock values and transportation

    networks etc ) as possible into memory so that the disk drives (which are mechanical

    and thus slower than electronic computer memory) are used as little as possible. The

    idea is that all of the SCP calculations are performed in memory.

    Nowadays, almost all SCP vendors have a Microsoft NT platform offering (although

    vendors such as Numetrix have struggled to develop an NT offering). Because

    Microsoft NT is usually supplied on high powered PC (personal computer) hardware,

  • Don Carmichael Page 37 P5893614 and is therefore a mass produced commodity item, there is a cost advantage in

    buying ‘NT based software packages for potential SCP customers.

    One SCP supplier, American Software (with their product Logility), did have an

    AS/400 offering that only seemed to be available in the U.S. American Software also

    have a Windows 95 version of their product but this can only be used in specific

    scenarios where there are a limited number of transactions.

    In SAP’s case, with it’s SCOPE (Supply Chain Optimisation, Planning And

    Execution) initiative, the SCP product was designed and developed for NT and is

    intended to run on it’s own networked server NT box. The actual SCP product within

    the SCOPE initiative is called the APO (Advanced Planner and Optimiser) module.

    SAP have developed a memory based environment for the APO module called

    ‘liveCache’ which manages the large amount of NT memory required.

    None of the SCP vendors would quote typical prices for their solutions, reasoning

    that the price depended on a series of factors including the number of users, the

    scope, the level of integration with an ERP package and who was asking. However,

    on further inquiry a common consensus was that SCP vendors generally target

    companies with a turnover greater that £200 million. Their argument being that

    companies with a turnover less than this figure would find the costs of buying,

    implementing and integrating a SCP product excessive.

  • Don Carmichael Page 38 P5893614 Companies with a turnover higher than £200 million would possibly be outside the

    definition of SMEs (Small to Medium size Enterprises) used by ERP vendors. It is

    probably fair to say that, at the present, SCP vendors are only targeting large

    companies.

  • Don Carmichael Page 39 P5893614

    4.4 Analysis

    The claim for all the SCP packages is that they can and are reducing millions of

    pounds from supply chain costs including warehousing, transportation and lost

    business. This is achieved by optimising the supply chain in almost real-time by

    reacting to major events as they occur, e.g. by re-routing stock or re-planning

    transportation routes to meet the company’s defined service levels.

    A key issue is the comparison of supply chain optimisation with improvement

    methodologies such as those based on ‘lean’ principles. SCP products cannot

    reorganise the factory layout, investigate set-up reduction techniques or improve

    supplier relationships. SCP products are as helpless as MRP products in that they

    are software based and therefore can only work with the information they are given.

    SCP systems cannot compete with ‘lean’ solutions and, on occasions, can actually

    stop companies from taking the steps towards a ‘lean’ enterprise in instances when

    they are seen as a ‘panacea’. An ideal solution would be one where SCP systems

    could co-exist with ‘lean’ solutions.

    4.5 Future directions

    Already, leaders in the ERP / MRP II marketplace have seen the potential of SCP

    and are at least partnering with the SCP vendors and, in the case of SAP, writing

    their own SCP product to sit on top of their ERP business systems.

  • Don Carmichael Page 40 P5893614

    PeopleSoft, who didn’t have an ERP product based on MRP principles previously, is

    now trying to change the paradigm by publicising their belief that Enterprise

    Resource Planning (ERP) systems are dead, to be replaced by Enterprise Resource

    Optimisation (ERO) systems based on SCP technology (in PeopleSoft’s case Red

    Pepper).

    In the short term, SCP systems will really only appeal to larger companies with big

    budgets and lots of resources. In the longer term though, medium sized companies

    may feel the pressure to purchase SCP systems in order that their customers, the

    larger companies, can include them in their supply chain optimisation calculations.

    4.7 Conclusions

    SCP systems are expanding everyone’s view as to the potential for cost savings and

    control over the speed and uncertainty of modern business.

    One conclusion from the analysis could be that supply chain planning systems are

    providing a ‘crutch’ for companies who cannot face or do not believe in going down

    the ‘lean enterprise’ route.

  • Don Carmichael Page 41 P5893614

    CHAPTER 5 Survey

    5.1 Introduction to the survey

    Originally, the research part of the dissertation was to have been a series of

    interviews with logistics and manufacturing professionals currently dealing with

    supply chain issues. Thus the research would have been qualitative rather than

    quantitative. However, the literature review turned up a number of surveys examining

    supply chain issues in the manufacturing context and the focus of the research part

    of the project changed to a questionnaire based approach.

    The first of these was a survey by Benchmark Research for Computer Associates

    [19], the second a survey by Warwick Business School [20] and the third a 1995

    survey by AT Kearney, UMIST and the Institute of Logistics [21]. As these surveys

    had already explored similar areas, it was felt that constructing the author’s own

    questionnaire would allow the author the opportunity to both compare and contrast

    the results obtained in the other surveys and build upon and focus upon the

    manufacturing related supply chain issues.

    5.2 The survey and the methodology

    Before building the survey questionnaire, the author investigated the possibility of

    using his (then) employer, Largotim’s resources to provide the logistics and funding

    for the 1000 questionnaires that were felt to be required to gain an adequate

    response level to the survey. The Sales Director at Largotim agreed but decided that

  • Don Carmichael Page 42 P5893614 it should be a joint questionnaire; the employer would add certain questions of

    interest to the MRP II business onto the supply chain questionnaire. Some of these

    questions were to investigate the requirement for third party software additions to the

    MFG/PRO business system package. MFG/PRO, from the U.S company QAD, was

    Largotim’s MRP II offering.

    These questions can be clearly seen in the second part of ‘Appendix 2 - The Supply

    Chain Questionnaire’. Questions about desktop integration have only an indirect

    relationship with the supply chain systems issues. The questions relating to project

    timescales (‘How soon will this be addressed’, 1-5) were related to the employer’s

    wish to see if any new business could be developed with the questionnaire

    respondent.

    This issue of the dual purpose of the questionnaire should be emphasised as it may

    have made the questionnaire too complex and unfocused and thus resulted in a

    lower quality and quantity of response.

    As the author was trying to compare and contrast some previous research by

    Robertson, Swan and Newell from the University of Warwick [20], some of the style

    of questions were based on the same problem scale as that research, from 1, not a

    problem, to 5, a very serious business problem. These can be seen in the second

    part of the questionnaire in ‘Appendix 2 - The Supply Chain Questionnaire’.

    In building the questionnaire, the author received help from one of the Largotim

    marketing team to ensure the questions were unambiguous and without the author’s

  • Don Carmichael Page 43 P5893614 bias as to the desired answers. The format of the questionnaire was based on an

    insurance questionnaire from Barclays Bank which had been extensively market

    researched while being developed.

    Since the Initial Report the main complication affecting the project plan had been the

    extended negotiations and efforts required to get the questionnaire through the

    employer’s marketing department. One of the reasons why it seemed difficult to gain

    agreement on the format and logistics of the survey became evident only at the

    beginning of May, when it was announced that the author’s employer had been

    bought out by a large American corporation. This had been distracting the attentions

    of the senior management at Largotim.

    Other reasons for the delay centered around the legalities of running the prize

    competition being used to leverage a higher rate of returns. Largotim’s marketing

    department believed that 4% was a good response rate to this type of questionnaire

    and that the addition of the prize could boost the response up to 10% giving about

    100 responses from a mailshot of 1000. As Largotim provided manufacturing and

    business systems to one of the bigger Formula 1 racing teams, Williams Grand Prix

    Racing, the prize offered was two tickets to a test session at Silverstone as a guest

    of Williams and Largotim.

    This was the first time the employer had actually run a competition open to external

    scrutiny and there was some hesitancy as to how prize competitions should be run.

  • Don Carmichael Page 44 P5893614 The database used by the author’s employer was a ‘random’ one bought from Dun &

    Bradstreet two years ago. The age of the database was a concern as names,

    addresses and job titles of the questionnaire’s target audience would not be

    particularly accurate. The targeted audience was Managing Directors, Operations

    Directors and Senior Production Managers. The ‘randomness’ of the database

    contacts could not be validated as the marketing department could only be certain

    that the database held at least five thousand manufacturing companies which they

    believed were represented across all business sectors and across all regions of the

    UK in equal proportions. This could not be tested and so should be taken into

    account in the analysis of the results.

    The questionnaire was tested by two of the author’s best customer contacts. The

    contacts, one being an IT Manager in a Tier 1 automotive supplier and the other a

    Business Analyst in a large communications company, were initially informed of the

    intended purpose of the questionnaire analysis and were then given the chance to

    comment on the both the format and the questions within the questionnaire.

    Initial responses from the two ‘testers’ revolved around issues on the complexity of

    the questionnaire and specific questions which were felt to be missing. One of the

    ‘testers’ felt that question 2 on the questionnaire, regarding the use of third party

    warehousing, needed to split into three questions looking at the proportion of third

    party warehousing being used. In retrospect, of course, this type of feedback only

    added to the complexity of the questionnaire.

  • Don Carmichael Page 45 P5893614 The complexity issue was again raised with the Largotim Sales Management but

    there was a lack of interest. The Marketing Manager was keen to progress with the

    mailing of the existing questionnaire, more as a method of completing the task which

    she was beginning to regret she had agreed to.

    Following an update to the questionnaire based on the two customer responses, the

    contacts were then asked to fill in the questionnaire. The results were then analysed

    to see if any further improvements could be made to the questionnaire. Their

    responses were mapped onto a single spreadsheet designed by the author to allow

    ease and accuracy of results recording and then later ease of analysis.

    After some experimentation a template version of the questionnaire was built. The

    template version included more and clearer numbering to improve the accuracy of

    the recording of the returned questionnaires onto the spreadsheet.

    Finally, once a covering letter had been designed, a Freepost address set-up and

    the mail merge addresses loaded out of the marketing database, the mail shot

    began. This happened on Wednesday 14th May.

    Because of the prolonged design and planning period for the questionnaire, it was

    decided that a window of only one and a half weeks should be allowed for

    responses. This was managed by emphasizing a closing date for the prize

    competition as the 23rd May. It was felt by members of the marketing department that

    if the respondent did not fill in the questionnaire either the day of receipt or the day

    after the likelihood was that the questionnaire would probably be binned or put to the

  • Don Carmichael Page 46 P5893614 bottom of an in-tray. As a reply paid (Freepost) envelope was included with the

    questionnaire there was minimal effort required from the respondent after the

    questionnaire was filled in, i.e. folding into the envelope and posting into a mail tray.

  • Don Carmichael Page 47 P5893614

    5.3 Results of the survey

    Unfortunately, there was a very low response rate to the survey. There were 21

    responses from the 1000 questionnaires posted. There were various reasons

    hypothesized as to the reasons for this but they could be summarised as the :

    • complexity of the survey

    • length of the survey

    • negativity of the questions

    • short response time

    • lack of profile of the company sending the questionnaire

    • age and inaccuracy of the mailing list

    • requirement for the respondent to give their name and address

    • lack of telephone follow-up

    A major psychological factor was the questionnaire’s requirement for respondents to

    rate the severity of particular business problems. From the respondent’s viewpoint

    this could have been seen as a reflection on the individual or possibly a criticism of

    the respondents company. This would give weight to the argument that the questions

    should have been phrased in a more positive manner.

    In addition to the above, some companies have a policy of not filling in

    questionnaires. On investigation, most of these companies believe that time

    consumed by individuals interpreting then researching, investigating and finally filling

  • Don Carmichael Page 48 P5893614 in the questionnaire does not warrant the effort or any expected research gains.

    There was also the suspicion that these particular companies trusted neither the

    promises of anonymity given in the questionnaire nor the authority or standing of the

    company requesting the information.

    This may have been different if the questionnaire had been compiled by say one of

    the ‘Big 5’ consultancies and the research perhaps destined for a focused

    benchmarking tome.

    The randomness and suitability of the mailing list has been questioned elsewhere in

    this project but it is worth noting here that the best surveys, analysed by the author,

    used mailing lists from two sources:

    • either the Institute of Operations Management’s membership list;

    • or a Management Consultancies client list.

    The competition part of the survey produced a number of negative affects being that

    some of the potential respondents were sceptical about a questionnaire purporting to

    be anonymous and yet seeming to trick the respondent into giving their name,

    address, title, company and telephone number.

    Also, some respondents did not believe the legitimacy of the Williams Grand Prix /

    Silverstone prize draw. Largotim, being a mid-range MRP II vendor and thus not

  • Don Carmichael Page 49 P5893614 having a vast marketing budget or market presence, was probably not associated

    with Williams Grand Prix.

    On reflection, the author’s experience is that many sales ‘pitches’ start with a

    telephone caller asking if the respondent would mind taking part in some

    independent research questionnaire. These generally turn into sales ‘pitches’ once a

    few qualifying questions have been answered and the respondent either realises

    they are speaking to, or the telephone caller reveals themselves as, a telesales

    person

    The likely motive of the Sales Management who influenced the format and agreed

    the logistics of the questionnaire was to use the contact list generated and a brief

    analysis of a few qualifying questionnaire responses to drive a telesales campaign.

    The reader can rightly assume from this that the Marketing department reported

    directly into the Sales Management and thus there was never any intention of

    guiding the questionnaire to simply produce some focused yet anonymous research

    that might be fed into the MRP II research and development program.

  • Don Carmichael Page 51 P5893614

    Question Nmbr I II III IV V VI VII VIII

    Response Format Nmbr Nmbr Nmbr Nmbr Nmbr Option £ Option

    Respondents

    1 2400 700 10 15 30 Globally 220M Industrial/Electronics2 1400 700 8 8 8 Globally 80M Automotive3 550 3 9 0 0 Internat. 72M Process4 5250 2100 3 2 5 Globally 640M Industrial/Electronics5 400 150 2 2 2 Globally 50M Medical6 135 135 10 17 17 Inernat. 150M Industrial/Electronics7 1700 1200 4 4 9 Globally 150M Industrial/Electronics8 2250 1400 9 3 4 Internat. Food & Beverage 9 1814 290 17 17 Globally 291M Industrial/Electronics

    10 180 180 1 1 Internat. 7.5M Automotive11 800 200 4 Internat. 100M Consumer Packaged Goods 12 1100 125 1 1 47 Nationally 39M Food & Beverage 13 1000 650 4 2 3 Nationally 120M Consumer Packaged Goods14 312 304 3 3 3 Internat. 57M Industrial/Electronics15 430 400 1 3 2 Internat 230M Food & Beverage

    16 140 135 1 1 1 Globally 10M Industrial/Electronics

    17 750 420 4 4 4 Nationally 280M Food & Beverage

    18 2500 200 16 16 Nationally 1500M Medical

    19 500 220 1 2 Globally 200M Medical

    20 275 190 1 2 1 Globally 20M Industrial/Electronics

    21 410 390 3 0 1 Nationally 40M Automotive

    Table 5.3.0.1 Tabular summary of questionnaire results with respondent number versus question number with answers. (1 of 5)

  • Don Carmichael Page 52 P5893614

    Question Nmbr 1a b 2a B c 3 4 5 6 7 8 9a 9b 10 11 12a 12b 13

    Response Format Mfg % Dist % Y/N Nmbr % Y/N Y/N Y/N Y/N Y/N Y/N Y/N Y/N Y/N Y/N Y/N Y/N Option

    Respondents

    1 90 10 Y 5 20 N N Y Y Y Y N Y AS4002 95 5 N N Y Y Y Y Y Y AS400 3 100 0 N Y N Y N Y N Y N N N N N Mainframe4 70 30 N N Y Y Y N Y N Y UNIX5 75 25 N N N Y Y N N N UNIX 6 85 15 N N N Y N N N N UNIX 7 100 0 N N N Y Y Y Y Y UNIX/NOVELL 8 95 5 Y 4 25 Y Y Y N Y Y Y N N N N N Windows NT9 100 0 N N Y Y N N N N N Mainframe

    10 100 0 N N N Y Y N N N Windows NT 11 100 0 Y 2 10 N Y Y Y Y Y Y AS/400 12 50 50 N Y Y Y N Y N Y Y N Y Y Windows NT 13 8 20 N N N Y N N Y N N AS/40014 100 0 N N Y Y Y N N N Y AS/40015 84 16 Y 4 5 N Y Y N Y Y N Y UNIX

    16 40 5 N N Y Y Y N Y N N AS400

    17 80 20 N Y - - - - N Y N N N Y N UNIX

    18 0 100 N N Y Y N N N N N UNIX/Windows NT

    19 0 20 Y 1 100 Y N Y N Y Y Y Y N N N Y Windows NT

    20 10 90 N N N Y Y Y N Y Windows NT

    21 95 5 Y 1 5 N Y Y N N Y UNIX

    Table 5.3.0.2 Tabular summary of questionnaire results with respondent number versus question number with answers. (2 of 5)

  • Don Carmichael Page 53 P5893614

    Question Nmbr 14a b 15a b 16a b 17a b 18a b 19a b 20a b 21a b 22a b 23a b

    Response Format 1-6 1-5 1-6 1-5 1-6 1-5 1-6 1-5 1-6 1-5 1-6 1-5 1-6 1-5 1-6 1-5 1-6 1-5 1-6 1-5

    Respondents

    1 3 2 2 5 3 2 4 4 4 3 2 4 2 4 4 4 2 4 2 52 5 1 5 1 2 2 2 1 4 1 4 1 5 1 4 1 4 1 4 13 1 1 1 1 1 1 6 1 6 1 1 1 1 1 1 1 6 1 1 14 1 1 1 1 2 2 1 1 1 1 3 3 2 2 3 4 1 2 1 15 3 4 1 1 1 1 2 1 2 5 1 5 2 5 6 5 1 1 2 16 2 5 2 2 1 2 2 2 2 5 2 5 2 5 1 5 1 1 2 57 3 2 1 6 1 6 3 2 1 3 2 3 2 3 38 3 3 3 4 1 1 2 2 1 1 1 1 2 2 6 5 1 1 2 59 3 4 3 4 2 5 1 5 1 5 1 5 1 5 1 5 2 5 1 5

    10 3 4 4 4 3 4 3 4 4 4 3 4 3 4 3 4 3 4 4 411 1 1 4 2 1 1 1 1 1 1 6 1 3 3 1 1 2 2 1 112 1 1 1 1 1 2 1 1 2 3 2 1 3 3 2 2 1 1 1 213 2 3 1 1 1 1 3 4 1 1 1 1 1 1 1 1 2 3 3 414 3 4 2 2 3 1 2 4 1 1 3 4 1 1 3 4 3 2 1 115 4 2 3 2 1 1 3 4 3 2 4 2 2 4 4 2 2 2 4 2

    16 4 2 3 2 1 1 1 1 2 2 1 0 1 0 6 0 3 4 3 3

    17 4 4 4 4 2 5 4 5 4 3 3 5 2 5 3 5 3 3 3 5

    18 6 5 3 4 2 2 3 2 3 2 3 2 6 5 6 5 3 2 3 4

    19 3 4 2 3 1 5 2 2 2 1 6 6 6 2 2 2 3

    20 2 2 1 1 1 2 1 1 2 2 1 1 1 1 1 1 6 6 3 2

    21 1 1 2 4 2 4 1 1 1 1 1 5 6 5 6 5 3 2 2 5

    Table 5.3.0.3 Tabular summary of questionnaire results with respondent number versus question number with answers. (3 of 5)

  • Don Carmichael Page 54 P5893614

    Question Nmbr 24a b 25a b 26a b 27a b 28a b 29a b 30a b 31a b 32a b 33a b

    Response Format 1-6 1-5 1-6 1-5 1-6 1-5 1-6 1-5 1-6 1-5 1-6 1-5 1-6 1-5 1-6 1-5 1-6 1-5 1-6 1-5

    Respondents

    1 3 3 1 5 1 5 3 4 3 4 1 5 1 5 1 5 4 2 3 32 1 1 2 2 6 5 4 1 4 1 4 1 4 1 4 2 4 2 4 13 1 1 6 1 6 1 1 1 1 1 1 1 1 1 1 1 1 1 1 14 1 1 1 1 1 2 1 1 1 1 1 1 1 1 1 1 1 1 1 15 1 1 2 1 6 5 1 1 2 2 3 1 1 5 2 5 2 5 6 56 1 1 2 2 1 5 2 5 2 2 2 5 1 5 1 5 2 5 2 57 6 2 2 1 2 2 3 2 2 2 6 1 3 2 6 8 1 1 1 1 6 5 1 5 1 1 1 1 6 5 6 5 6 5 6 59 6 5 2 4 6 5 1 5 1 5 2 2 1 1 1 1 1 5 1 5

    10 3 4 3 4 6 5 2 2 3 2 3 2 1 5 3 2 3 2 4 211 1 1 6 6 6 1 1 1 1 1 1 1 1 1 1 6 12 1 2 2 2 1 1 1 1 2 3 1 2 2 2 1 1 1 1 1 213 1 1 1 1 1 1 1 1 1 1 1 1 1 1 3 4 1 1 1 114 3 4 2 2 1 1 1 1 2 2 2 2 3 4 1 1 3 4 1 115 5 2 1 1 3 2 3 2 3 1 3 1 1 5 1 2 1 2 1 2

    16 2 2 1 0 1 0 3 2 3 2 4 2 1 0 3 3 3 3 3 3

    17 3 2 2 2 1 1 1 1 3 2 3 2 1 1 3 4 4 2 2 5

    18 4 2 3 2 2 5 3 2 3 2 3 4 6 5 2 2 1 1 2 5

    19 2 2 6 2 2 6 3 4 6 6 6 6 6

    20 1 1 1 1 2 3 3 2 3 2 1 1 2 1 2 2 3 2 2 2

    21 2 5 1 1 6 5 6 5 2 2 2 2 2 2 2 1 2 2 22

    Table 5.3.0.4 Tabular summary of questionnaire results with respondent number versus question number with answers. (4 of 5)

  • Don Carmichael Page 55 P5893614

    Question Nmbr 34a b 35a b 36a b 37a b 38a b 39a b 40a b

    Response Format 1-6 1-5 1-6 1-5 1-6 1-5 1-6 1-5 1-6 1-5 1-6 1-5 1-6 1-5

    Respondents

    1 4 4 4 4 4 4 3 3 3 4 4 3 4 22 4 1 4 2 4 1 4 2 5 1 4 1 5 13 1 1 1 1 1 1 1 1 1 1 1 1 1 14 2 5 2 2 1 1 1 1 1 2 2 2 1 15 6 5 2 5 4 2 1 5 2 5 6 5 2 56 1 5 2 2 2 2 3 3 2 5 2 5 2 57 6 3 2 4 2 6 2 3 6 2 38 1 1 1 1 3 2 3 2 1 1 1 1 6 59 1 1 1 1 1 2 6 5 1 2 1 1 1 1

    10 2 1 3 4 4 2 3 4 3 4 6 5 3 211 6 6 3 4 1 1 4 4 1 1 2 512 1 1 1 1 1 1 1 1 2 2 2 2 1 113 1 1 1 1 3 4 1 1 1 1 1 1 1 114 1 1 3 4 3 2 3 2 3 2 2 2 3 315 5 3 3 2 3 2 3 2 4 2 3 2 4 2

    16 1 0 2 4 3 2 4 2 4 3 2 2 3 2

    17 1 1 1 1 4 4 2 5 3 2 3 5 4 2

    18 6 5 2 2 6 5 6 5 3 2 6 5 6 5

    19 2 1 3 3 3 5 1 5 3 4 2 3 1 5

    20 6 6 3 2 2 2 2 2 3 2 2 2 3 2

    21 6 5 2 2 2 2 1 1 1 1 6 5 2 2

    Table 5.3.0.5 Tabular summary of questionnaire results with respondent number versus question n